You are on page 1of 3

ID:BC200414926

Assignment Solution
Consider the scenario of a software project having two main phases.

Each phase consists of three main tasks:


Requirements, Design, and Development.

These steps must be performed sequentially. Requirements for phase two can begin
immediately on the completion of the requirements task for phase one, but the
design for phase two must await satisfactory development of the phase one design
task. Requirements task is expected to take 4 weeks for phase one, and 2 weeks for
phase two, while the design is expected to take 3 weeks for phase one and 2 weeks
for phase two. Development is expected to take 2 weeks for both phases.
Question No 1:
5 Marks

You are required to create an online account (with your student ID) using the
following link:

Login (clickup.com)

You have to submit a screenshot of the home page of the software (after Signup/
login) . The screenshot must include your Student ID as your Name.
Paste your screenshot here:

Question No 2:
10 Marks
You are required to develop a Gantt Chart based on the above-mentioned scenario.
You have to submit a screenshot of the drawn Gantt chart. The screenshot must
include your Student ID as your name.
The screenshot should also contain your PC’s current date and time.

You need to open the given link (clickup.com) in any browser on your PC, and
create the required Gantt chart free of cost.

Paste your screenshot here: