You are on page 1of 451

DAFTAR SEWA P E R A L A T AN

SUMBER DATA : PASARAN BEBAS


D A E R A H : KABUPATEN KEBUMEN
EDISI 2023

HARGA
NO. PERALATAN SATUAN MINIMUM MAKSIMUM KET.
(Rp) (Rp)

1 Dump Truck 3 ton Jam 115,000 120,000


2 Dump Truck 9 ton Jam 160,000 170,000
3 Truk Bak Terbuka Engkel Jam 130,000 140,000
4 Truk Tanki Air Jam 290,000 300,000
5 Bulldozer 100 - 150 hp Jam 650,000 700,000
6 Motor Grader Jam 600,000 640,000
7 Wheel Loader Jam 250,000 280,000
8 Excavator Jam 610,000 660,000
9 Crane 35 ton Jam 435,000 450,000
10 Flat Bed Truck jam 400,000 440,000
11 Baby Roller / Pedestrian Jam 110,000 120,000
12 P.Tire Roller 8 - 10 ton Jam 530,000 550,000
13 Baby Roller jam 50,000 60,000
14 Vibrator Roller self 7 ton Jam 500,000 510,000
15 Pile Driver / Hammer jam 150,000 160,000
16 Water Pump Jam 35,000 40,000
17 Asphalt Sprayer Jam 135,000 140,000
18 Pick Up single cabin Jam 55,000 64,000
19 A M P Jam 5,500,000 5,600,000
20 Asphalt Finisher Jam 330,000 350,000
21 Concrete Vibrator Jam 55,000 60,000
22 Compressor Jam 300,000 320,000
23 Concrete Mixer 0,125m3 Jam 75,000 80,000
24 Concrete Cutter jam 35,000 40,000
25 Stamper Jam 35,000 40,000
26 Genset 5-25kva+bbm Jam 180,000 185,000
27 Alat Pengecat Marka Jam 300,000 320,000
28 Mesin Las jam 180,000 200,000
29 Stone Crusher jam 850,000 900,000
30 Truck Trailler trip 7,250,000 7,400,000
skafolding blan 350000 400000
HARGA YANG
NO. MATERIAL SATUAN MERK KET.
DISEPAKATI (Rp)

I BAHAN DASAR
1 BATU KALI Bulat Utuh m3 Survey Levelansir 281,000
Bulat Belah m3 Survey Levelansir 281,000
Pecah 10/15 m3 Survey Levelansir 301,000
Pecah 5/7 m3 Survey Levelansir 312,500
Pecah 3/5 m3 Survey Levelansir 337,000
2 KERIKIL Timbun / Sirtu m3 Survey Levelansir 225,000
Sawur / Koral m3 Survey Levelansir 236,000
Beton 0,5/1 m3 Survey Levelansir 352,000
Beton 1/2 m3 Survey Levelansir 362,000
Beton 2/3 m3 Survey Levelansir 372,000
Biasa m3 Survey Levelansir 263,500
Tras Giling m3 Survey Levelansir 213,000
3 BATU BATA ex lokal bh 900

4 PASIR Urug m3 Survey Levelansir 190,000


Pasang m3 Survey Levelansir 313,000
Beton m3 Survey Levelansir 376,000
5 TANAH Cadas m3 Survey Levelansir 143,000
Liat m3 Survey Levelansir 147,500
Merah m3 Survey Levelansir 250,000
6 KAPUR Padam m3 Survey Levelansir 283,000
Pasang m3 Survey Levelansir 363,000
Semen Merah m3 Survey Levelansir 158,500
7 PORTLAND CEMENT
Merk I 40 kg zak Tiga Roda 60,000
Merk I 50 kg zak Tiga Roda 71,000
Merk II 40 kg zak Holcim 55,000
Merk II 50 kg zak Holcim 65,000
Semen Putih 40 kg zak Tiga Roda 116,000
Semen Putih 50 kg zak - 151,000
Semen warna kg AM 15,250

II BAHAN PENUTUP ATAP

1 SIRAP (100 lbr) pak 612,000

2 GENTENG BETON Genteng Beton Warna standard bh 6,000


Genteng Beton Warna Special bh 7,500
Genteng Beton Warna Khusus bh 7,250
Kerpus Beton Warna Standard bh 7,500
Kerpus Beton Warna Special bh 12,500
Kerpus Beton Warna Khusus bh 13,750
3 GENTENG TANAH LIAT
Plentong bh 22,250
Kodok bh 2,500
Kodok Glasur bh 5,700
Nok kerpus Kodok bh 4,900
Nok kerpus Kodok Glasur bh 6,250
Plentong super besar 18 bh/m2 bh 3,500
Nok kerpus plentong super bh 4,500
Genteng Magase bh 3,200
Genteng Magaze glazur bh 7,000
Genteng Morando biasa bh 3,800
Genteng Morando glazur bh 8,000
4 GENTENG KACA
Vlaam tebal 2 mm bh 13,500
Vlaam tebal 3 mm bh 17,150
Kodok tebal 2 mm bh 16,300
Kodok tebal 3 mm bh 19,500
5 GENTENG ASPAL
Nok Genteng Aspal bh 66,500
6 GENTENG METAL
Nok Genteng Metal M2 48,000
7 ASBES GELOMBANG BESAR
. 250 cm X 92 cm X 5 mm bh 104,500
. 225 cm X 92 cm X 5 mm bh 90,500
. 180 cm X 92 cm X 5 mm bh 79,000
. 200 cm X 102 cm X 5 mm bh 90,500
. 225 cm X 102 cm X 5 mm bh 100,500
. 250 cm X 102 cm X 5 mm bh 112,000
. 200 cm X 102 cm X 6 mm bh 98,500
. 225 cm X 102 cm X 6 mm bh 90,000
. 250 cm X 102 cm X 6 mm bh 106,000
Asbes Gelombang Kecil
. 150 cm X 105 cm X 4 mm bh 44,700
. 180 cm X 105 cm X 4 mm bh 51,200
. 210 cm X 105 cm X 4 mm bh 52,600
. 240 cm X 105 cm X 4 mm bh 59,000
. 270 cm X 105 cm X 4 mm bh 84,000
. 300 cm X 105 cm X 4 mm bh 90,500
. 300 cm X 108 cm X 6 mm bh 104,000
. 270 cm X 108 cm X 6 mm bh 94,500
. 240 cm X 108 cm X 6 mm bh 75,000
. 210 cm X 108 cm X 6 mm bh 65,000
. 180 cm X 108 cm X 6 mm bh 55,500

ONDULINE : 95 cm x 200cm x 0.3mm lbr 200,000


ONDUVILLA : 40cm x 106 cm x 0,3mm lbr 101,000
NOK Jabes nok 36,000
. Kerpus Genteng bh 33,000
. Stel Besar bh 35,000
. Paten Besar bh 52,000
Nokstel gelombang harflex
. Stel Besar bh 54,000
. Patent Besar bh 57,000
. Plat besar bh 64,500
NOK UNT ONDULINE & ONDUVILLA
Ukuran 50cm x 50 cm x 0,3mm lbr 100,000
8 ASBES PLAT
. 100cm X 100 cm X 3 mm bh 18,000
. 100cm X 100 cm X 4 mm bh 19,500
. 50 cm X 200 cm X 3 mm bh 16,400
. 40 cm X 200 cm X 3 mm bh 15,200
FIBER PLAT uk. 100cm x 100cm x 4mm lbr 31,000
unt Plafond uk. 120cm x 240cm x 4mm lbr 61,500
uk. 122cm x 244cm x 4mm lbr 68,000
GRC BOARD uk.122cm x 244cm x 5mm lbr 69,500
uk.122cm x 244cm x 6mm lbr 104,500
uk.122cm x 244cm x 8mm lbr 128,000
uk.122cm x 244cm x 10mm lbr 166,500
9 FIBRE GLASS (JABES)
180 X 92 cm bh 55,000
200 X 92 cm bh 64,700
250 X 92 cm bh 75,500
180 X 105 cm bh 84,000
210 X 105 cm bh 100,000
250 X 105 cm bh 112,000
10 SENG PLAT
BJLS 0,18 lebar 55 cm m' 23,700
BJLS 0,20 lebar 55 cm m' 25,200
BJLS 0,28 lebar 55 cm m' 33,700
BJLS 0,30 lebar 55 cm m' 36,200
11 SENG GELOMBANG
BJLS 0,18 panjang 180 cm lbr 62,200
BJLS 0,20 panjang 180 cm lbr FUMIRA 65,200
BJLS 0,30 panjang 180 cm lbr 101,500
BJLS 0,40 panjang 180 cm lbr 112,000
III . B A H A N K A Y U
1 JATI Papan m3 20,183,200
Balok/pesagen m3 19,863,000
2 KAMPER Papan m3 14,096,500
Balok/pesagen m3 12,174,000
3 KRUING Papan m3 12,196,200
Balok/pesagen m3 9,887,500
4 MERANTI Papan m3 6,979,000
Balok/pesagen m3 7,162,000
5 TAHUN Kelas I Papan m3 Laban , Akasia 3,176,200
Balok/pesagen m3 3,008,200
TAHUN Kelas II Papan m3 Albasiah , Mahoni 3,135,000
Balok/pesagen m3 Glugu 2,887,000
6 BENGKIRAI Papan m3 15,132,700
Balok/pesagen m3 12,764,500
7 DOLKEN Sedang 8 x 10 x 400 cm bt 34,700
Kecil 6 x 7 x 400 cm bt 12,400
Besar 10 x 12 x 400 cm bt 16,000
Kayu Galam φ (8-10) cm, panjang 4 m bt 14,000
Kayu cetakan m3 3,124,000
Kayu bakar m3 214,200
Bambu bt 17,500
Kayu Glugu Tua Utuh ( > 6 m) bt 495,000
IV . BAHAN PENUTUP DINDING / LANTAI
1 UBIN (TEGEL BIASA)
PC polos 30 X 30 cm m2 68,000
20 X 20 cm m2 77,000
PC warna 30 X 30 cm m2 79,500
20 X 20 cm m2 80,500
Teraso 30 X 30 cm m2 89,500
2 TEGEL PLINT
PC warna 10 X 20 cm bh 1,700
PC abu-abu 15 x 20 bh 1,500

3 POLIS UBIN Lantai/badan m' 3,300


Plint m' 3,100
Trap m' 3,400

4 UBIN PORSELIN
Lokal 11 X 11 putih dos 83,200
11 X 11 warna dos 89,500
Lokal 15 X 15 putih dos 89,500
15 X 15 warna dos 93,700
5 MOZAIK PORSELIN
10 X 20 cm m2 95,700
15 X 15 cm m2 91,200
20 X 20 cm m2 106,000
20 X 25 cm m2 108,000

6 Keramik 30 X 30 cm m2 57,500
20 X 20 cm m2 64,500
33 x 33 cm m2 71,000
40 x 40 cm m2 70,000
50 x 50 cm m2 78,000
60 x 60 cm m2 128,000
25 x 25 cm m2 74,000
15 x 20 cm m2 88,700
20 x 40 cm m2
25 x 40 cm m2
30 x 60 cm m2

7 Parquet Jati m2 320,500


8 Batu Paros m2 134,200
9 Batu Tempel Hitam m2 159,700
10 GRANITO 40 x 40 cm m2 173,700
30 x 30 cm m2 166,000
60 x 60 cm m2 311,000
11 Bata Ringan Tebal 7,5 cm Buah 8,200
12 Bata Ringan Tebal 10 cm Buah 10,100
13 Marmer m2 907,700
V.BAHAN CETAK
1 BUIS BETON Ø 10 cm - 100 cm bh 97,000
Ø 20 cm - 100 cm bh 102,000
Ø 30 cm - 100 cm bh 112,500
Ø 50 cm - 100 cm bh 166,500
Ø 60 cm - 100 cm bh 234,000
Ø 70 cm - 100 cm bh 296,500
Ø 80 cm - 100 cm bh 402,500
Ø 100 cm - 100 cm bh 575,000
U 10 cm - 100 cm bh 60,200
U 20 cm - 100 cm bh 83,500
U 30 cm - 100 cm bh 101,500
U 50 cm - 100 cm bh 122,700
U 60 cm - 100 cm bh 169,700
Gorong-Gorong bertulang
Ø 20 cm - 100 cm bh 60,000
Ø 30 cm - 100 cm bh 75,000
Ø 50 cm - 100 cm bh
Ø 60 cm - 100 cm bh
Ø 70 cm - 100 cm bh
Ø 80 cm - 100 cm bh
Ø 100 cm - 100 cm bh
2 LUBANG ANGIN (ROSTER) PC + PASIR
10 X 20 cm PC + PASIR box 10,000
20 X 20 cm PC + PASIR box 23,000
25 X 25 cm PC + PASIR box 30,000
30 X 30 cm PC + PASIR box 50,000
15 X 25 cm PC + PASIR box 11,000
15 X 30 cm PC + PASIR box 13,700
3 U DITCH DAN BOX CULVERT
● BETON K 250
uditch uk. 30 x 30 x 120 tbl 5 cm unit 358,000
Uditch uk. 30 x 40 x 120 tbl 5 cm unit 388,000
uditch uk. 30 x 50 x 120 tbl 5 cm unit 504,000
uditch uk. 40 x 40 x 120 tbl 5 cm unit -
uditch uk. 40 x 50 x 120 tbl 5 cm unit -
Uditch uk. 40 x 60 x 120 tbl 5 cm unit 523,000
uditch Uk. 50 x 50 x 120 tbl 7 cm unit 616,000
Uditch uk. 50 x 60 x 120 tbl 7 cm unit 691,000
uditch Uk. 50 x 70 x 120 tbl 7 cm unit -
uditch uk. 60 x 60 x 120 tbl 7 cm unit -
uditch uk. 60 x 70 x 120 tbl 7 cm unit 704,000
uditch uk. 60 x 80 x 120 tbl 7 cm unit 775,000
uditch uk. 60 x 100 x 120 tbl 7 cm unit 966,200
uditch uk. 80 x 80 x 120 tbl 8 cm unit -
uditch uk. 80 x 80 x 120 tbl 7 cm unit -
uditch uk. 80 x 100 x 120 tbl 7 cm unit 911,000
uditch uk. 30 x 40 x 120 tbl 8 cm unit 1,006,000
uditch uk. 40 x 50 x 120 tbl 8 cm unit 1,146,000
uditch uk. 40 x 60 x 120 tbl 8 cm unit -
uditch uk. 60 x 70 x 120 tbl 8 cm unit -
uditch uk. 40 x 60 x 120 tbl 10 cm unit -
uditch uk. 60 x 60 x 120 tbl 10 cm unit -
uditch uk. 60 x 70 x 120 tbl 10 cm unit -
uditch uk. 80 x 100 x 120 tbl 10 cm unit -
uditch uk. 100 x 100 x 120 tbl 10 cm unit 1,338,000
uditch uk. 120 x120 x 120 tbl 10 cm unit 1,637,000
uditch uk. 120 x 140 x 120 tbl 10 cm unit -
Uditch uk. 60 x 80 x 120 tbl 15 cm unit -
Uditch uk. 80 x 100 x 120 tbl 15 cm unit -
Cover LC uk. 40 x 120 tbl 10 cm unit -
Cover HD uk. 40 x 120 tbl 15 cm unit -
Cover LC uk. 50 x 120 tbl 10 cm unit -
Cover HD uk. 50 x 120 tbl 15 cm unit -
Cover LC uk. 64 x 120 tbl 10 cm unit -
Cover HD uk. 64 x 120 tbl 15 cm unit -
Cover LC uk. 74 x 120 tbl 10 cm unit -
Cover HD uk. 74 x 120 tbl 15 cm unit -
Cover LC uk. 96x 120 tbl 10 cm unit -
Cover HD uk. 96 x 120 tbl 15 cm unit -
Cover uk. 54 x 120 tbl 10 cm unit -
Cover uk. 54 x 120 tbl 20 cm unit -
Cover uk. 77 x 120 tbl 10 cm unit -
Cover uk. 77 x 120 tbl 20 cm unit -
Cover uk. 90 x 120 tbl 20 cm unit -
Cover LC uk. 94x 120 tbl 10 cm unit -
Cover HD uk. 94 x 120 tbl 15 cm unit -
Cover LC uk. 100x 120 tbl 10 cm unit -
Cover HD uk. 100 x 120 tbl 15 cm unit 1,993,000
Cover LC uk. 110x 120 tbl 10 cm unit -
Cover HD uk. 110 x 120 tbl 15 cm unit -
Cover LC uk. 120x 120 tbl 12 cm unit 3,102,000
Cover HD uk. 120 x 120 tbl 15 cm unit 3,514,000
Cover LC uk. 140x 120 tbl 12 cm unit -
Cover HD uk. 140 x 120 tbl 15 cm unit -
Uditch uk. 200 x 200 x 120 tbl 17 cm unit 7,452,000
Uditch uk. 200 x 200 x 120 tbl 20 cm unit -
Box Culvert 40 x 40 x 120 tbl 8 cm unit -
Box Culvert 50 x 50 x 120 tbl 8 cm unit -
Box Culvert 50 x 50 x 120 tbl 16 cm unit -
Box Culvert 60 x 60 x 120 tbl 8,5 cm unit -
Box Culvert 60 x 60 x 120 tbl 16 cm unit -
Box Culvert 60 x 80 x 120 tbl 12 cm unit -
Box Culvert 80 x 80 x 120 tbl 10 cm unit -
Box Culvert 80 x 80 x 120 tbl 12 cm unit -
Box Culvert 80 x 100 x 120 tbl 12 cm unit -
Box Culvert 80 x 80 x 120 tbl 15 cm unit -
Box Culvert 80 x 80 x 120 tbl 20 cm unit -
Box Culvert 100 x 100 x120 tbl 12 cm unit -
Box Culvert 100 x 100 x 120 tbl 15 cm unit -
Box Culvert 120 x 120 x 120 tbl 15 cm unit -
Box Culvert 120 x 120 x 120 tbl 14 cm unit -
Box Culvert 150 x 150 x 120 tbl 17 cm unit -
Box Culvert 200 x 200 x 120 tbl 20 cm unit -

● BETON K 350
uditch uk. 30 x 30 x 120 tbl 5 cm unit 400,700
Uditch uk. 30 x 40 x 120 tbl 5 cm unit 477,500
uditch uk. 30 x 50 x 120 tbl 5 cm unit 553,200
uditch uk. 40 x 40 x 120 tbl 5 cm unit 599,000
uditch uk. 40 x 50 x 120 tbl 5 cm unit 675,000
Uditch uk. 40 x 60 x 120 tbl 5 cm unit 623,500
uditch Uk. 50 x 50 x 120 tbl 7 cm unit 762,000
Uditch uk. 50 x 60 x 120 tbl 7 cm unit 899,700
uditch Uk. 50 x 70 x 120 tbl 7 cm unit 935,000
uditch uk. 60 x 60 x 120 tbl 7 cm unit 1,074,000
uditch uk. 60 x 70 x 120 tbl 7 cm unit 823,000
uditch uk. 60 x 80 x 120 tbl 7 cm unit 910,700
uditch uk. 60 x 100 x 120 tbl 7 cm unit 962,700
uditch uk. 80 x 80 x 120 tbl 8 cm unit 1,678,000
uditch uk. 80 x 80 x 120 tbl 7 cm unit 1,598,000
uditch uk. 80 x 100 x 120 tbl 7 cm unit 1,784,000
uditch uk. 30 x 40 x 120 tbl 8 cm unit 333,000
uditch uk. 40 x 50 x 120 tbl 8 cm unit 484,000
uditch uk. 40 x 60 x 120 tbl 8 cm unit 509,000
uditch uk. 60 x 70 x 120 tbl 8 cm unit 872,000
uditch uk. 40 x 60 x 120 tbl 10 cm unit 509,000
uditch uk. 60 x 60 x 120 tbl 10 cm unit 847,000
uditch uk. 60 x 70 x 120 tbl 10 cm unit 908,000
uditch uk. 80 x 100 x 120 tbl 10 cm unit 2,396,000
uditch uk. 100 x 100 x 120 tbl 10 cm unit 1,251,000
uditch uk. 120 x120 x 120 tbl 10 cm unit 605,000
uditch uk. 120 x 140 x 120 tbl 10 cm unit 1,503,000
Uditch uk. 60 x 80 x 120 tbl 15 cm unit 1,210,000
Uditch uk. 80 x 100 x 120 tbl 15 cm unit 3,261,000
Cover LC uk. 40 x 120 tbl 10 cm unit 656,000
Cover HD uk. 40 x 120 tbl 15 cm unit 420,000
Cover LC uk. 50 x 120 tbl 10 cm unit 678,000
Cover HD uk. 50 x 120 tbl 15 cm unit 750,000
Cover LC uk. 64 x 120 tbl 10 cm unit 1,100,000
Cover HD uk. 64 x 120 tbl 15 cm unit 220,000
Cover LC uk. 74 x 120 tbl 10 cm unit 330,000
Cover HD uk. 74 x 120 tbl 15 cm unit 330,000
Cover LC uk. 96x 120 tbl 10 cm unit 440,000
Cover HD uk. 96 x 120 tbl 15 cm unit 495,000
Cover uk. 54 x 120 tbl 10 cm unit 440,000
Cover uk. 54 x 120 tbl 20 cm unit 495,000
Cover uk. 77 x 120 tbl 10 cm unit 550,000
Cover uk. 77 x 120 tbl 20 cm unit 660,000
Cover uk. 90 x 120 tbl 20 cm unit 687,000
Cover LC uk. 94x 120 tbl 10 cm unit 626,000
Cover HD uk. 94 x 120 tbl 15 cm unit 919,000
Cover LC uk. 100x 120 tbl 10 cm unit 733,000
Cover HD uk. 100 x 120 tbl 15 cm unit 1,052,000
Cover LC uk. 110x 120 tbl 10 cm unit 772,000
Cover HD uk. 110 x 120 tbl 15 cm unit 1,158,000
Cover LC uk. 120x 120 tbl 12 cm unit 932,000
Cover HD uk. 120 x 120 tbl 15 cm unit 1,158,000
Cover LC uk. 140x 120 tbl 12 cm unit 1,077,000
Cover HD uk. 140 x 120 tbl 15 cm unit 1,331,000
Uditch uk. 200 x 200 x 120 tbl 17 cm unit 7,692,500
Uditch uk. 200 x 200 x 120 tbl 20 cm unit 9,196,000
Box Culvert 40 x 40 x 120 tbl 8 cm unit 1,265,000
Box Culvert 50 x 50 x 120 tbl 8 cm unit 1,598,000
Box Culvert 50 x 50 x 120 tbl 16 cm unit 3,155,000
Box Culvert 60 x 60 x 120 tbl 8,5 cm unit 1,797,000
Box Culvert 60 x 60 x 120 tbl 16 cm unit 3,528,000
Box Culvert 60 x 80 x 120 tbl 12 cm unit 3,022,000
Box Culvert 80 x 80 x 120 tbl 10 cm unit 3,328,000
Box Culvert 80 x 80 x 120 tbl 12 cm unit 2,486,500
Box Culvert 80 x 100 x 120 tbl 12 cm unit 2,420,000
Box Culvert 80 x 80 x 120 tbl 15 cm unit 4,459,000
Box Culvert 80 x 80 x 120 tbl 20 cm unit 5,857,000
Box Culvert 100 x 100 x120 tbl 12 cm unit 3,025,000
Box Culvert 100 x 100 x 120 tbl 15 cm unit 3,025,000
Box Culvert 120 x 120 x 120 tbl 15 cm unit 3,850,000
Box Culvert 120 x 120 x 120 tbl 14 cm unit 6,323,000
Box Culvert 150 x 150 x 120 tbl 17 cm unit 8,452,000
Box Culvert 200 x 200 x 120 tbl 20 cm unit 13,603,000
VI . B A H A N B E S I
1 BESI BETON besi beton polos kg 17,000
besi beton prestress kg 17,000
besi beton ulir kg 18,000
besi IWF kg 20,200
Besi scuare tube m 17,500
Besi lis kaca (1 x 1) cm m 17,000
2 BESI PLAT Besi Strip kg 19,000
Kawat Seling 1/2'' m' 52,000
Kawat Seling 1'' m' 172,000

3 BESI PROFIL Besi Profil kg 17,000


a BAJA RINGAN
GALVALUME lebar : 7,5cm tebal : 1mm btg pnj : 6 m 143,500
type CT 75 lebar : 7,5cm tebal : 0.75mm btg pnj : 6 m 111,000
lebar : 7,5cm tebal : 0,65mm btg pnj : 6 m 104,000
b type RT 12 tinggi : 3,5 cm, tebal : 0,45mm btg pnj : 6 m 54,000
type RT 10 tinggi : 3,0 cm, tebal : 0,45mm btg pnj : 6 m 49,000
c HOLLOW GALVANIS LIPAT
tinggi 2 cm; tebal : 0,3 mm btg pnj : 4 m 27,000
tinggi 4 cm; tebal : 0,3 mm btg pnj : 4 m 30,500
4 JARING - JARING BAJA
Diameter 4 - 15 kg 17,000
Diameter 6 - 15 kg 17,000
Kawat bronjong Ø 3 mm kg 28,000
Kawat bronjong Ø 4 mm kg 28,000
5 BESI SIKU L 40 X 40 X 4 btg 138,000
L 50 X 50 X 5 btg 141,000
L 60 X 60 X 6 btg 325,000

6 KAWAT - Ikat beton/bendrat kg 28,000


- Harmonika 12 X 45 mm m2 3,500
- Harmonika 12 X 24 mm m2 37,000
- Harmonika 14 X 30 mm m 38,000
- Harmonika 14 X 35 mm m2 42,000
- Kawat Nyamuk Nylon m2 25,000
- Kawat Kasa m2 28,000
- Saringan pasir m2 19,500
- Kawat loket m2 38,000
- Kawat duri rol 100,000
- Kawat bronjong kg 28,000
- Wiremesh m 6 2,1 m x 5,2 m Lembar 550,000
- Wiremesh m 8 2,1 m x 5,2 m Lembar 816,000
- Wiremesh m 10 2,1 m x 5,2 m Lembar 1,149,000

VII . B A H A N P I P A
1 Pipa PVC SII SCJ , S - 12,5 (10 bar)
Pipa PVC DN 20 ( ½" ) AW JIS btg RUCIKA pnj : 4 m 27,500
Pipa PVC DN 25 ( ¾" ) AW JIS btg RUCIKA pnj : 4 m 35,200
Pipa PVC DN 32 ( 1" ) AW JIS btg RUCIKA pnj : 4 m 55,500
Pipa PVC diameter 1,25" btg RUCIKA pnj : 4 m 56,000
Pipa PVC diameter 1,5" btg RUCIKA pnj : 4 m 78,000
Pipa PVC diameter 2" btg RUCIKA pnj : 4 m 101,000
Pipa PVC diameter 2,5" btg RUCIKA pnj : 4 m 150,000
Pipa PVC diameter 3" btg RUCIKA pnj : 4 m 198,000
Pipa PVC diameter 4" btg RUCIKA pnj : 4 m 292,000
Pipa PVC diameter 1,5" btg pnj : 6 m 138,500
Pipa PVC diameter 2" btg pnj : 6 m 203,000
Pipa PVC diameter 2,5" btg pnj : 6 m 290,000
Pipa PVC diameter 3" btg pnj : 6 m 419,000
Pipa PVC diameter 4" btg pnj : 6 m 614,000

2 Pipa Medium B Galvanis - SII


Pipa Medium B Galvanis DN ½" btg pnj : 6 m 113,000
Pipa Medium B Galvanis DN 25 ( ¾" ) btg pnj : 6 m 136,000
Pipa Medium B Galvanis DN 32 ( 1" ) btg pnj : 6 m 190,000
Pipa Medium B Galvanis DN 50 ( 1½" ) btg pnj : 6 m 275,000
Pipa Medium B Galvanis DN 63 ( 2" ) btg pnj : 6 m 355,000
Pipa Medium B Galvanis DN 2½" btg pnj : 6 m 436,000
Pipa Medium B Galvanis DN 90 ( 3" ) btg pnj : 6 m 651,000
Pipa Medium B Galvanis DN 110 ( 4" ) btg pnj : 6 m 1,106,000
Pipa Medium B Galvanis DN 160 ( 6" ) btg pnj : 6 m 2,492,000
Pipa Medium B Galvanis DN 200 ( 8" ) btg pnj : 6 m 5,305,000
Pipa Medium B Galvanis DN 250 ( 10") btg pnj : 6 m

3 Pipa PVC AW
Pipa PVC dia 1/2" btg WAVIN pnj : 4 m 26,000
Pipa PVC dia 3/4" btg WAVIN pnj : 4 m 36,500
Pipa PVC dia 1" btg WAVIN pnj : 4 m 47,500
Pipa PVC DN 40 ( 1½" ) btg WAVIN pnj : 4 m 88,000
Pipa PVC DN 63 ( 2" ) btg WAVIN pnj : 4 m 137,000
Pipa PVC DN 67 ( 2,5" ) btg WAVIN pnj : 4 m 158,000
Pipa PVC DN 90 ( 3" ) btg WAVIN pnj : 4 m 183,000
Pipa PVC DN 110 ( 4" ) btg WAVIN pnj : 4 m 332,000
Pipa PVC DN 160 ( 6" ) btg WAVIN pnj : 4 m 705,000
Pipa PVC DN 200 ( 8" ) btg WAVIN pnj : 4 m 1,173,000
Pipa PVC DN 250 ( 10" ) btg WAVIN pnj : 4 m 1,832,000
Pipa PVC DN 315 ( 12" ) btg WAVIN pnj : 4 m 2,635,000

4 Pipa HDPE
pipa HDPE Ø 63 mm m' 50,000
pipa HDPE Ø 100 mm m' 102,500
pipa HDPE Ø 125 mm m' 167,500
pipa HDPE Ø 150 mm m' 320,200
pipa HDPE Ø 200 mm m' 499,700
pipa HDPE Ø 250 mm m' 788,500
pipa HDPE Ø 300 mm m' 1,255,500
pipa HDPE Ø 400 mm m' 1,922,000
pipa HDPE Ø 450 mm m' 2,563,000
pipa HDPE Ø 500 mm m' 3,139,500
pipa HDPE Ø 600 mm m' 4,933,700
pipa HDPE Ø 800 mm m' 7,880,700

5 Pipa GIP
pipa GIP Ø 63 mm (Medium SII) btg pnj : 6 m 1,217,700
pipa GIP Ø 100 mm (Medium SII) btg pnj : 6 m 2,243,000
pipa GIP Ø 125 mm (Medium SII) btg pnj : 6 m 3,011,700
pipa GIP Ø 150 mm (Medium SII) btg pnj : 6 m 3,652,200
pipa GIP Ø 200 mm (Medium SII) btg pnj : 6 m 5,254,000
6 Pipa Baja
pipa baja Ø 63 mm batang pnj : 6 m 833,000
pipa baja Ø 100 mm batang pnj : 6 m 1,601,700
pipa baja Ø 125 mm batang pnj : 6 m 3,011,000
pipa baja Ø 150 mm batang pnj : 6 m 3,107,500
pipa baja Ø 200 mm batang pnj : 6 m 4,677,500
pipa baja Ø 250 mm batang pnj : 6 m 7,317,000
pipa baja Ø 300 mm batang pnj : 6 m 9,611,000
pipa baja Ø 400 mm batang pnj : 6 m 14,801,000
pipa baja Ø 450 mm batang pnj : 6 m 18,581,500
pipa baja Ø 500 mm batang pnj : 6 m 22,746,200
pipa baja Ø 600 mm batang pnj : 6 m 32,357,700

7 Pipa Spiral
Pipa Spiral diameter 1,25" m' 24,900
Pipa Spiral diameter 1,5" m' 25,900
Pipa Spiral diameter 2" m' 35,000
Pipa Spiral diameter 3" m' 60,000
Pipa Spiral diameter 4" m' 139,900
Pipa Spiral diameter 6" m' 319,900

8 Aksesoris Pipa
Pipa Fitting PVC – ELBOW (D-DL) 1 1/4″ Buah 4,000
Pipa Fitting PVC – ELBOW (D-DL) 1 1/2″ Buah RUCIKA AW 8,400
Pipa Fitting PVC – ELBOW (D-DL) 2″ Buah 13,000
Pipa Fitting PVC – ELBOW (D-DL) 2 1/2″ Buah 14,200
Pipa Fitting PVC – ELBOW (D-DL) 3″ Buah 21,000
Pipa Fitting PVC – ELBOW (D-DL) 4″ Buah 36,500
Pipa Fitting PVC – ELBOW (D-DL) 5″ Buah 86,500
Pipa Fitting PVC – ELBOW (D-DL) 6″ Buah 91,000
Pipa Fitting PVC – ELBOW (D-DL) 8″ Buah 229,000
Pipa Fitting PVC – ELBOW (D-DL) 10″ Buah 441,500
Pipa Fitting PVC – ELBOW (D-DL) 12″ Buah 602,000
Pipa Fitting PVC – SOCKET (D-DS) 1 1/4″ Buah 6,000
Pipa Fitting PVC – SOCKET (D-DS) 1 1/2″ Buah 8,000
Pipa Fitting PVC – SOCKET (D-DS) 2″ Buah 10,600
Pipa Fitting PVC – SOCKET (D-DS) 2 1/2″ Buah 5,000
Pipa Fitting PVC – SOCKET (D-DS) 3″ Buah 19,500
Pipa Fitting PVC – SOCKET (D-DS) 4″ Buah 33,000
Pipa Fitting PVC – SOCKET (D-DS) 5″ Buah 45,000
Pipa Fitting PVC – SOCKET (D-DS) 6″ Buah 51,000
Pipa Fitting PVC – SOCKET (D-DS) 8″ Buah 112,000
Pipa Fitting PVC – SOCKET (D-DS) 10″ Buah 171,000
Pipa Fitting PVC – TEE (D-DT) 1 1/4″ Buah 5,000
Pipa Fitting PVC – TEE (D-DT) 1 1/2″ Buah 13,700
Pipa Fitting PVC – TEE (D-DT) 2″ Buah 18,500
Pipa Fitting PVC – TEE (D-DT) 2 1/2″ Buah 20,000
Pipa Fitting PVC – TEE (D-DT) 3″ x 1 1/2″ Buah 11,000
Pipa Fitting PVC – TEE (D-DT) 3″ x 2″ Buah 31,000
Pipa Fitting PVC – TEE (D-DT) 3″ x 2 1/2″ Buah 14,000
Pipa Fitting PVC – TEE (D-DT) 3″ Buah 40,000
Pipa Fitting PVC – TEE (D-DT) 4″ x 2″ Buah 20,500
Pipa Fitting PVC – TEE (D-DT) 4″ x 3″ Buah 25,000
Pipa Fitting PVC – TEE (D-DT) 4″ Buah 69,500
Pipa Fitting PVC – TEE (D-DT) 5″ x 4″ Buah 40,000
Pipa Fitting PVC – TEE (D-DT) 5″ Buah 44,000
Pipa Fitting PVC – TEE (D-DT) 6″ x 4″ Buah 58,000
Pipa Fitting PVC – TEE (D-DT) 6″ Buah 195,000
Pipa Fitting PVC – TEE (D-DT) 8″ x 4″ Buah 79,000
Pipa Fitting PVC – TEE (D-DT) 8″ Buah 267,000
Pipa Fitting PVC – INCREASER (D-IN) 1 1/2″ x 1 1/4″ (Rucika) Buah 4,000
Pipa Fitting PVC – INCREASER (D-IN) 2″ x 1 1/4″ Buah 6,000
Pipa Fitting PVC – INCREASER (D-IN) 2″ x 1 1/2″ Buah 7,000
Pipa Fitting PVC – INCREASER (D-IN) 2 1/2″ x 1 1/2″ Buah 8,000
Pipa Fitting PVC – INCREASER (D-IN) 2 1/2″ x 2″ Buah 9,000
Pipa Fitting PVC – INCREASER (D-IN) 3″ x 1 1/2″ Buah 10,000
Pipa Fitting PVC – INCREASER (D-IN) 3″ x 2″ Buah RUCIKA 12,000
Pipa Fitting PVC – INCREASER (D-IN) 3″ x 2 1/2″ Buah 17,800
Pipa Fitting PVC – INCREASER (D-IN) 4″ x 2″ Buah 24,400
Pipa Fitting PVC – INCREASER (D-IN) 4″ x 2 1/2″ Buah 22,000
Pipa Fitting PVC – INCREASER (D-IN) 4″ x 3″ Buah 24,000
Pipa Fitting PVC – INCREASER (D-IN) 5″ x 4″ Buah 47,000
Pipa Fitting PVC – INCREASER (D-IN) 6″ x 3″ Buah 64,000
Pipa Fitting PVC – INCREASER (D-IN) 6″ x 4″ Buah 80,000
Pipa Fitting PVC – INCREASER (D-IN) 6″ x 5″ Buah 77,000
Pipa Fitting PVC – INCREASER (D-IN) 8″ x 4″ Buah 114,500
Pipa Fitting PVC – INCREASER (D-IN) 8″ x 6″ Buah 127,700
Pipa Fitting PVC – CAP (D) 1 1/4″ Buah 4,000
Pipa Fitting PVC – CAP (D) 1 1/2″ Buah 8,000
Pipa Fitting PVC – CAP (D) 2″ Buah 9,000
Pipa Fitting PVC – CAP (D) 3″ Buah 13,700
Pipa Fitting PVC – CAP (D) 4″ Buah 25,000
Fitting PVC – SOCKET (AW) 1/2″ Buah 3,500
Fitting PVC – SOCKET (AW) 3/4″ Buah 4,200
Fitting PVC – SOCKET (AW) 1″ Buah 5,800
Fitting PVC – SOCKET (AW) 1 1/4″ Buah 7,200
Fitting PVC – SOCKET (AW) 1 1/2″ Buah 9,000
Fitting PVC – SOCKET (AW) 2″ Buah 9,000
Fitting PVC – SOCKET (AW) 2 1/2″ Buah 22,000
Fitting PVC – SOCKET (AW) 3″ Buah 43,000
Fitting PVC – SOCKET (AW) 4″ Buah 69,500
Fitting PVC – SOCKET (AW) 6″ Buah 117,000
Fitting PVC – SOCKET (AW) 8″ Buah 249,000
Fitting PVC – SOCKET (AW) 10″ Buah 359,000
Fitting PVC – VALVE SOCKET (AW) 1/2″ Buah 3,000
Fitting PVC – VALVE SOCKET (AW) 1/2″ x 3/4″ Buah 3,000
Fitting PVC – VALVE SOCKET (AW) 3/4″ Buah 4,000
Fitting PVC – VALVE SOCKET (AW) 1″ x 1/2″ Buah 4,000
Fitting PVC – VALVE SOCKET (AW) 1″ x 3/4″ Buah 5,000
Fitting PVC – VALVE SOCKET (AW) 1″ Buah 6,000
Fitting PVC – VALVE SOCKET (AW) 1 1/4″ Buah 4,200
Fitting PVC – VALVE SOCKET (AW) 1 1/2″ Buah 10,500
Fitting PVC – VALVE SOCKET (AW) 2″ Buah 13,000
Fitting PVC – VALVE SOCKET (AW) 3 '' Buah 38,000
Fitting PVC – VALVE SOCKET (AW) 4″ Buah 50,200
Fitting PVC – FAUCET SOCKET (AW) 1/2″ Buah 4,000
Fitting PVC – FAUCET SOCKET (AW) 1/2″ x 3/4″ Buah 4,000
Fitting PVC – FAUCET SOCKET (AW) 3/4″ Buah 4,000
Fitting PVC – FAUCET SOCKET (AW) 1″ x 1/2″ Buah 6,000
Fitting PVC – FAUCET SOCKET (AW) 1″ x 3/4″ Buah 6,500
Fitting PVC – FAUCET SOCKET (AW) 1″ Buah 6,500
Fitting PVC – FAUCET SOCKET (AW) 1 1/4″ Buah 8,000
Fitting PVC – FAUCET SOCKET (AW) 1 1/2″ Buah 4,000
Fitting PVC – FAUCET SOCKET (AW) 2″ Buah 11,000
Fitting PVC – TEE (AW) 1/2″ Buah 5,000
Fitting PVC – TEE (AW) 3/4″ x 1/2″ Buah 5,000
Fitting PVC – TEE (AW) 3/4″ Buah 5,000
Fitting PVC – TEE (AW) 1″ x 1/2″ Buah 6,800
Fitting PVC – TEE (AW) 1″ x 3/4″ Buah 7,600
Fitting PVC – TEE (AW) 1″ Buah 8,200
Fitting PVC – TEE (AW) 1 1/4″ x 1/2″ Buah 10,400
Fitting PVC – TEE (AW) 1 1/4″ x 3/4″ Buah 11,000
Fitting PVC – TEE (AW) 1 1/4″ x 1″ Buah 12,000
Fitting PVC – TEE (AW) 1 1/4″ Buah 12,600
Fitting PVC – TEE (AW) 1 1/2″ x 1/2″ Buah 14,000
Fitting PVC – TEE (AW) 1 1/2″ x 3/4″ Buah 14,000
Fitting PVC – TEE (AW) 1 1/2″ x 1″ Buah 14,000
Fitting PVC – TEE (AW) 1 1/2″ x 1 1/4″ Buah 17,000
Fitting PVC – TEE (AW) 1 1/2″ Buah 16,000
Fitting PVC – TEE (AW) 2″ x 1/2″ Buah 17,500
Fitting PVC – TEE (AW) 2″ x 3/4″ Buah 17,000
Fitting PVC – TEE (AW) 2″ x 1″ Buah 17,000
Fitting PVC – TEE (AW) 2″ x 1 1/4″ Buah 27,000
Fitting PVC – TEE (AW) 2″ x 1 1/2″ Buah 22,000
Fitting PVC – TEE (AW) 2″ Buah 22,000
Fitting PVC – TEE (AW) 2 1/2″ Buah 36,000
Fitting PVC – TEE (AW) 3″ x 2″ Buah 42,000
Fitting PVC – TEE (AW) 3″ Buah 53,000
Fitting PVC – TEE (AW) 4″ Buah 98,000
Fitting PVC – TEE (AW) 6″ Buah 259,000
Fitting PVC – TEE (AW) 8″ Buah 515,000

9 Lain - Lain
Clam Sadle CI 1" X 1/2" buah 34,000
Clam Sadle CI 1" X 3/4" buah 34,000
Clam Sadle CI 1,25" X 1/2" buah 39,000
Clam Sadle CI 1,25" X 3/4" buah 39,000
Clam Sadle CI 1,5" X 1/2" buah 40,000
Clam Sadle CI 1,5" X 3/4" buah 40,000
Clam Sadle CI 2" X 1/2" buah 43,000
Clam Sadle CI 2" X 3/4" buah 43,000
Clam Sadle CI 2" X 1" buah 43,000
Clam Sadle CI 3" X 1/2" buah 56,000
Clam Sadle CI 3" X 3/4" buah 56,000
Clam Sadle CI 3" X 1" buah 56,000
Doble Niple GI 1/2" buah ONDA 9,000
Doble Niple GI 3/4" buah ONDA 13,000
Doble Niple GI 1" buah ONDA 18,000
Doble Niple GI 1¼" buah ONDA 28,000
Doble Niple GI 1½" buah ONDA 33,000
Doble Niple GI 2" buah ONDA 52,000
Flange steel 1,5" buah 84,000
Flange steel GI 2" buah 89,000
Flange steel GI 3" buah 159,000
Flange steel GI 4" buah 192,000
Gate Valve CI 1,5" buah ONDA 382,000
Gate Valve CI 2" buah ONDA 509,000
Gate Valve CI 2,5" buah ONDA 1,206,000
Gate Valve CI 3" buah ONDA 1,801,200
Gate Valve CI 6" buah 5,018,000
Gate Valve CI 8" buah 8,785,000
Giboult Joint CI 2" buah 127,000
Giboult Joint CI 3" buah 192,000
Giboult Joint CI 4" buah 236,000
Giboult Joint CI 6" buah 446,000
Giboult Joint CI 8" buah 636,000
Stop Valve brass (katup) KITSU 3/4" buah 57,000
Stop Valve brass (katup) KITSU 1" buah 84,000
Stop Valve brass (katup) KITSU 1¼" buah 126,000
Stop Valve brass (katup) KITSU 1½" buah 182,000
Stop Valve brass (katup) KITSU 2" buah 299,000
Stop Valve brass (katup) KITSU 2,5" buah 509,000
Stop Valve brass (katup) KITSU 3" buah 604,000
Water Moor GI ¾" buah 40,000
Water Moor GI 1" buah 43,000
Water Moor GI 1¼" buah 60,000
Water Moor GI 1½" buah 78,000
Water Moor GI 2" buah 113,000
Clam Saddle PVC 1" X ½" buah 89,000
Clam Saddle PVC 1" X ¾" buah 89,000
Clam Saddle PVC 1,5" X ½" buah 34,000
Clam Saddle PVC 1,5" X ¾" buah 34,000
Clam Saddle PVC 2" X ½" buah 37,000
Clam Saddle PVC 2" X ¾" buah 38,000
Clam Saddle PVC 2" X 1" buah 38,000
Clam Saddle PVC 3" X ½" buah 51,000
Clam Saddle PVC 3" X ¾" buah 51,000
Clam Saddle PVC 3" X 1" buah 51,000
Flange Socket RR PVC 1,5" buah 51,000
Flange Socket RR PVC 2" buah 96,000
Flange Socket RR PVC 3" buah 127,000
Flange Socket RR PVC 4" buah 158,000
Water Level Control unit 300,000
Tutup Meteran Fiber buah 71,000
Air Vent CI DN 2" (Kuningan) buah 71,000
Air Vent CI DN 1,5" (Kuningan) buah 350,000
Meter Air Ø 15 mm kuningan lengkap (coupling dengan segel pengaman ) ONDA buah 599,000
Meter Air Ø 15 mm kuningan lengkap (coupling dengan segel pengaman ) AMIKO buah 599,000
Meter Air Ø 15 mm kuningan lengkap (coupling dengan segel pengaman ) FA buah 599,000
Stop Kran (searah) Ø 15 mm (Kuningan) buah 64,000
Katup Searah Ø 15 mm (kuningan) buah 64,000
Double nepeel Ø 15 mm (kuningan) buah 12,000
Plug kran GI Ø 15 mm (kuningan) buah 59,000
Generator set kubota 14 pk buah 43,440,000
Kubota double stater 8,5 pk buah 22,385,000
Kubota 8,5 pk buah 51,734,000
Kubota double stater 11 pk buah 82,346,000
Pompa Air Sanchin model SCN 120 buah 6,820,000
Pompa Air Sanchin model SCN 45 buah 2,970,000
Check valve dia 1,5" (kuningan) buah 446,000
Check valve dia 2" (kuningan) buah 666,000
Stop Valve Brass Kitsu Dn 2" (kuningan) buah 229,000
Stop Valve Brass Kitsu Dn 4" (kuningan) buah 2,850,000
Valve Socket PVC 2" buah 666,000
Double nepeel dn 2x1,5 mm buah 700,000
Fot clep + screen dia 2" buah 446,000
Fot clep + screen dia 1,5" buah 285,000
Fleksibel joint dia 2" buah 1,017,000
Fleksibel joint dia 1,5" buah 826,000
Pompa Jet Pump 2" buah 1,837,000
Groundfosh Sp 5A - 52/5,5 kw/380 V/1,5" (210 m) buah 119,790,000
Groundfosh Sp 9A - 36/7,5 kw/380 V/2" (200 m) buah 113,100,000
Groundfosh Sp 9A - 56/11 kw/380 V/2" (300 m) buah 252,890,000
Groundfosh Sp 9A - 75/15 kw/380 V/2" (400 m) buah 319,440,000
Groundfosh N5 4 - 23 M/1"/175 watt/dlm sumur 8m/daya dorong 13,9 m/kapasitas buah 3,461,000
L/detik = 100 head 11/80 head 15,5/60 head 18/40 head 20
Groundfosh N5 13 - 18 M/1,5"/400 watt/dlm sumur 8m/daya dorong 12,5 m/kapasitas buah 4,659,000
L/detik = 300 head 6,5/250 head 10/150 head 16/100 head 18
Maxon Pump Sp 5A - 33/3 kw/380V/1,5" (200 m) buah
Maxon Pump Sp 3 - 52/4 kw/380V/1,25" (300 m) buah
Maxon Pump Sp 8 - 25/4 kw/380V/2" (150 m) buah
Maxon Pump Sp 2 - 65/3 kw/380V/1,25" (400 m) buah
Franklin + CND Sj 3 - 43/3 kw/380V/1,25" (200 m) buah
Franklin + CND Sj 3 - 43/4 kw/380V/1,5" (150 m) buah
Franklin + CND Sj 8 - 50/7,5 kw/380V/1,25" (200 m) buah
VIII . B A H A N L A N G I T - L A N G I T
1 AKUSTIK-uk : 30 X 30 lbr 7,000
30 X 60 lbr 19,000
60 X 120 lbr 57,000
List Kayu Profil m' 18,500
2 SOFT BOARD-uk: 4'X 8'
Gypsum tebal 9 mm lbr A+ 69,000
3 HARD BOARD-uk: 4'X 8' lbr 66,000
GYPROC uk.120cmx240cmx9mm lbr GRC 71,500
4 POLY WOOD
Teak wood
90 X 210 X 3 mm lbr 92,000
. 120 X 240 X 3 mm lbr 102,500
. 90 X 210 X 4 mm lbr 106,200
. 90 X 210 X 9 mm lbr 142,000
. 90 X 210 X 12 mm lbr 176,700
. 90 X 210 X 15 mm lbr 221,500
. 90 X 210 X 18 mm lbr 291,000
Tripleks
. 120 X 240 X 3 mm lbr 57,200
. 120 X 240 X 4 mm lbr 76,000
. 120 X 240 X 6 mm lbr 85,500
Multipleks
. 120 X 240 X 9 mm lbr 129,500
. 120 X 240 X 12 mm lbr 172,500
. 120 X 240 X 15 mm lbr 217,000
. 120 X 240 X 18 mm lbr 269,700
Formika ukuran pintu lbr 126,000

IX . B A H A N F I N I S H I N G
1 KAYU
Menie kg TIGER 14,000
Dempul plamur kg TIGER 38,000
Ambril/amplas lbr BLACK PUMA 4,000
Batu Apung kg 32,700
Cat dasar kg ALTEK 51,000
. Emco kg 67,000
. Yunior 66 (nippon paint) kg 46,200
- Kuas bh 3" 13,000
. Deculux kg 48,500
. Siralax ons 14,000
. Spiritus ltr TIGER 15,500
. Plitur jadi ltr INDAN HEAD 67,000

2 TEMBOK
Kalkarium kg 7,300
Kapur sirih kg 3,600
Plamur kg TIGER 38,000
Cat Tembok kg DECOLIT 50,000
Sintex 5 kg VERSATEX 38,000
Danabride 5 kg 26,000
Catylac 5 kg 147,000
Mowilex 2,50 kg 118,000
3 BESI
Menie kg TIGER 40,200
Cat mengkilat kg ALTEX 69,500
Cat kg 32,500
Thinner A ltr IMPALA 28,500
Minyak cat ltr 28,200
Thinner Super ltr 33,500
Residu (teer/aspal) ltr 18,500
Fibre glass (tanki air)
kapasitas 550 liter. bh 1,191,500
kapasitas 1100 liter. bh 1,968,200
Lem Aica Aibon kg 27,500

X.BAHAN KACA
1 POLOS 3 mm m2 89,000
5 mm m2 118,000
2 ES KABUR 3 mm m2 94,500
5 mm m2 113,700
3 RAY BAND 3 mm m2 89,000
5 mm m2 121,000

XI . BAHAN INSTALASI LISTRIK

1 KABEL LISTRIK
NYA : . 1 X 1 1/2 mm2 rol 200,000
SPLN LMK 1 X 2 1/2 mm2 rol 300,000
. 1X4 mm2 m' 6,000
1X6 mm2 m' 10,000
NYY :. mm2 m' 8,500
PRIMA 2 X 1 1/2
2 X 2 1/2
2X4
3 X 1 1/2
3 X 2 1/2
3X4
3X6
SUPREME 2 X 2 1/2 mm2 m' 18,000
. 2X4 mm2 m' 35,000
2X6 mm2 m' 45,000
3 X 1 1/2 mm2 m' 17,500
3 X 2 1/2 mm2 m' 27,000
3X4 mm2 m' 45,000
3X6 mm2 m' 65,000
NYM :. 2 X 1 1/2 mm2 m' 10,500
SUPREME 2 X 2 1/2 mm2 m' 18,000
. 2X4 mm2 m' 28,500
3 X 1 1/2 mm2 m' 20,000
3 X 2 1/2 mm2 m' 27,500
3X4 mm2 m' 38,000
3X6 mm2 m' 60,000

2 SKAKELAR
Out bauw . Seri bh broco 18,500
. Engkel bh broco 16,000
In bauw . Seri bh 16,000
. Engkel bh 16,000

3 FUSE BOX (SEKERING KASA)


1 group bh 51,000
2 group bh 59,000
3 group bh 59,500

4 STEKER - Biasa bh 8,500


Arde bh 10,000
T Biasa bh 22,000
T dengan Arde bh 27,200
5 FITING Flaon bh 13,000
Gantung bh 9,000
Kap bh 14,500
Kombinasi bh 16,500

6 STOP KONTAK - Arde Outbow putih bh 17,700


Arde Outbow hitam bh 11,500
Arde IB bh 17,500
Arde Putar bh 18,500

XII . ALAT - ALAT PENGUNCI & PENGGANTUNG


1 KUNCI TANAM Union : 1 X slag bh GRT 71,000
2 X slag bh 127,000
Yale : 1 X slag bh 120,200
2 X slag bh 144,700
Kuda : 1 X slag bh 71,000
2 X slag bh 82,200

2 ENGSEL DAN GERENDEL


Engsel Angin bh 19,200
Kupu-kupu biasa bh 17,000
Nylon kupu-kupu bh 9,500
Espagnoled - dalam negeri bh 34,500
Grendel Tanam luar negeri bh 94,000
Grendel biasa bh 121,700
Kait Angin bh 16,000
Door Stop bh 78,200
Door Closer bh 702,200
XIII . BAHAN SANITAIR
1 KLOSET DUDUK bh TOTO 1,505,500
2 KLOSET JONGKOK bh TOTO 187,000
3 WASTAFEL PEDESTAL bh 150,000
4 WASTAFEL MEJA OVAL bh 803,000
5 WASTAFEL GANTUNG BULAT bh 440,500
6 WASTAFEL GANTUNG SUDUT bh 409,200
7 WASTAFEL GANTUNG SUDUT KECIL bh 275,700
8 WASTAFEL BAK CUCI bh 196,200
9 TEMPAT SABUN GANTUNG bh 42,500
10 TEMPAT SABUN TANAM bh 40,000

11 SEPTIC TANK (ETERNIT GRESIK)


5 Pemakai 500 liter unit 1,857,500
10 Pemakai 1.000 liter unit 2,603,000
12 LAIN - LAIN
Kran Air bh 31,000
Seal tape bh 8,700
Floor drain bh 40,000
Urinoir bh 102,500
Batchuip bh 916,200
Bak Fibreglass bh 334,000
Bak Cuci Piring bh 208,200
XIV . ALAT PENGIKAT KAYU
1 PAKU - ukuran 1" s/d 4" kg 20,000
2 PAKU - payung kg 42,700
3 PAKU - sekrup kg PCS 51,200
4 PAKU - beton kg DUS 97,200
5 MUR BAUT (kuda-kuda) kg 28,700
6 ANGKUR BAUT bh 23,700
7 LEM KAYU bh 20,000
8 Tali Ijuk kg 8,500
9 Paku skrup 1 cm – 2,5 cm Buah 1,200
10 Paku Sekrup 3,5" kg 37,700
11 Skrup fixer buah 1,400
12 Paku pancing kg 17,500
XV . POMPA AIR.
1 POMPA AIR TANGAN
Dragon buatan Indonesia bh 600,000
2 POMPA AIR LISTRIK
Sanyo 100 watt bh 524,000
Fuji 250 watt bh 832,000
Shimizu . 100 watt bh 483,000
. 90 watt bh 475,000
Dab . 125 watt bh 399,000
. 175 watt bh 537,000

X VI . PAVING BLOCK
1 SQUARE Abu-abu m2 76,200
Merah/hitam m2 87,200
2 HOLLAND Abu-abu m2 87,200
Merah/hitam m2 90,200
3 UNIDECOR Abu-abu m2 89,500
Merah/hitam m2 102,500
4 UNI Abu-abu m2 89,500
Merah/hitam m2 102,500
5 TRIHEX Abu-abu m2 89,500
Merah/hitam m2 102,500
6 OLYMPIA HEXA Abu-abu m2 89,500
7 HEXAGONAL Abu-abu m2 89,700
Merah/hitam m2 102,700
8 CASTLE Abu-abu m2 102,500
9 TRAPEZ Abu-abu m2 89,500
10 TRAPEZ GRASS BLOCK
Abu-abu m2 89,500
11 STANDARD GRASS BLOCK ABU-ABU BH 10,000
12 BATACO BH 6,000
13 KANSTEEN m' BJ 77,000

XVII. L A I N - L A I N
1 KREI 25 MM m2 55,200
2 Sliding Pintu J4 bh 247,000
3 Jendela nako (rangka + kaca 5 mm) bh 218,000
4 Rolling door Besi m2 440,000
Rolling door Almunium m2 450,000
5 Awning Almunium m2 256,500
6 Kusen Almunium 4" Putih m' 102,500
7 WIDE FLANGE BEAM
150 X 75 X 5 X 7 X 12 btg 1,345,500
8 ACP m2 240,000
9 Atap Galvalume m2 55,000
Nok Galvalume m1
10 Atap PVC (Alderon) m2 135,000
Nok PVC (Alderon) m1
11 Talang PVC m2 144,000
12 Talang Fiber m2 180,000
12 Plafon PVC m2 161,000
8 ASPAL.
Aspal Ex Pertamina isi Net 160 kg drum 1,632,000

Hotmix Tebal = 4 Cm m2 180,000


Hotmix Tebal = 5 Cm m2 190,000
Hotmix Tebal = 6 Cm m2 190,000
Hotmix Tebal = 7 Cm m2 210,000
Binder Course ton 950,000
Wearing Course ton 1,000,000
Hot Roller Sheet ton
Sand Sheet ton 1,150,000
Sand Sheet Emulsi liter 11,000
Cold Mix ton -
Prime / Tack Coard RC liter 11,000
Prime Coat MC liter
Prime / Tack Coat Emulsi liter

9 KACA
Cermin tebal 5 mm m2 175,000

10 PAGAR BRC. Pagar BRC 90 A2 /lb 370,500


Pagar BRC 120 A2 /lb 453,200
11 LAIN-LAIN
Minyak Beton & bekisting ltr 25,700
Pintu Lipat Besi m2 440,000
Sunscreen Allumunim m2 115,500
Allumunium Foil m2 rol 16,000
Soda api kg 25,000
Sabun kg 36,700
Air m3 5,000
Solar (Industri) ltr 11,700
Premium (Industri) ltr 12,700
Pelumas ltr 36,000
Karpet m2 46,200
Wallpaper Kelas I roll 420,000
Wallpaper Kelas II roll 231,500
Formite/penjaga bekisting/spacer Buah 7,700
kawat las kg 55,000
Sewa Alat Las Listrik Jam 12,500
Sealant Tube 40,200
Alluminium strip m’ 10,000
Profil kaca m 34,000
Venetions blinds dan vertical blinds (tirai) m2 183,000
Batu granit kg 7,000
Batu teraso kg 7,630
Profil Alluminium "T" m’ 11,500
Kawat diameter 4 mm kg 24,200
Ramset Buah 11,500
Rooflight 90 x 180 Lbr 152,000
Plastic Aerotor Buah 8,000
Bambu buah 40,000
Bilik bambu m2 56,500
tutup beton U ditch 1000x1000 mm type B (untuk beban ringan) m 500,000
tutup beton U ditch 800x800 mm type B (untuk beban ringan) m 500,000
U ditch beton bertulang 1000x1000 mm, tebal 9,0 cm m
U ditch beton bertulang 800x800 mm, tebal 7,0 cm m 799,000
Box Culvert (gorong - gorong persegi) precast 1500x1500 cm m' 4,226,000
Box Culvert type DUB 200X200 m' 6,801,500
Vynil 30x30 cm bh 9,000
Geotextile non Woven m2 16,000
Geomembran HDPE HDS 1,5 mm terpasang m2 115,000
Klem Besi Galvanis bh 174,000
Alat Ukur V Notch bh 605,000
Mistar Ukur P = 0,5 m bh 285,000
Mistar Ukur P = 4 m bh 2,299,000
Papan Nama Embung unit 1,725,000
Papan Peringatan Embung unit 575,000
Tangga Tali unit 230,000
Pelampung + Tali bh 345,000
Gebalan Rumput m2 108,900
Pintu Angkat Baja b = 0.20, h = 0.20 Bh 3,993,000
Pintu Angkat Baja b = 0.25, h = 0.25 Bh 4,393,000
Pintu Angkat Baja b = 0.30, h = 0.30 Bh 4,659,000
Pintu Angkat Baja b = 0.35, h = 0.35 Bh 4,930,500
Pintu Angkat Baja b = 0.40, h = 0.40 Bh 5,990,000
Pintu Angkat Baja b = 0.45, h = 0.45 Bh 6,655,000
Pintu Angkat Baja b = 0.50, h = 0.50 Bh 7,321,000
Pintu Sorong/Geser Baja b = 0.30 h = 0.30 Bh 9,120,300
Pintu Sorong/Geser Baja b = 0.35 h = 0.35 Bh 10,640,000
Pintu Sorong/Geser Baja b = 0.40 h = 0.40 Bh 13,680,200
Pintu Sorong/Geser Baja b = 0.40 h = 0.50 Bh 12,645,000
Pintu Sorong/Geser Baja b = 0.50 h = 0.50 Bh 15,200,600
Pintu Sorong/Geser Baja b = 0.55 h = 0.55 Bh 16,266,100
Pintu Sorong/Geser Baja b = 0.60 h = 0.60 Bh 17,479,600
Pintu Sorong/Geser Baja b = 0.65 h = 0.65 Bh 19,762,700
Pintu Sorong/Geser Baja b = 0.70 h = 0.70 Bh 22,583,800
Pintu Sorong/Geser Baja b = 0.75 h = 0.75 Bh 24,321,000
Pintu Sorong/Geser Baja b = 0.80 h = 0.70 Bh 22,627,000
Pintu Sorong/Geser Baja b = 0.90 h = 1.00 Bh 23,958,000
Pintu Sorong/Geser Baja b = 1.00 h = 1.00 Bh 30,401,200
Pintu Sorong/Geser Baja b = 1.00 h = 1.20 Bh 33,441,300
Pintu Sorong/Geser Baja b = 1.20 h = 1.20 Bh 36,481,500
Pintu Sorong/Geser Kayu b = 1.30 h = 1.10 Bh 39,521,600
Pintu Sorong/Geser Kayu b = 1.30 h = 1.35 Bh 40,577,600
Pintu Sorong/Geser Kayu b = 1.50 h = 1.50 Bh 43,696,100
Pintu Sorong/Geser Kayu b = 1.60 h = 1.60 Bh
Pintu Sorong/Geser Kayu b = 1.70 h = 1.70 Bh
Pintu Sorong/Geser Kayu b = 1.80 h = 1.80 Bh
Pintu Sorong/Geser Kayu b = 1.85 h = 1.85 Bh
Pintu Sorong/Geser Kayu b = 2.00 h = 2.00 Bh
Pintu Sorong/Geser Kayu b = 2.25 h = 2.25 Bh
Pintu Sorong/Geser Kayu b = 2.50 h = 2.50 Bh
Pintu Sorong/Geser Kayu b = 2.75 h = 2.75 Bh
Pintu Sorong/Geser Kayu b = 3.00 h = 3.00 Bh
Pintu Sorong/Geser Kayu b = 3.25 h = 3.00 Bh
Pintu Katrol b =2.50 h =2.00 Bh 96,800,000
Pintu Katrol b =2.50 h =2.25 Bh 102,850,000
Pintu Katrol b =2.50 h =2.50 Bh 114,950,000
Pintu Katrol b =2.50 h =2.75 Bh 114,950,000
Pintu Katrol b =3.75 h =2.00 Bh 114,950,000
Pintu Katrol b =3.75 h =2.25 Bh
Pintu Katrol b =3.75 h =2.50 Bh
Pintu Katrol b =3.75 h =2.75 Bh
Pintu Katrol b =3.75 h =3.00 Bh
Pintu Katrol b =4.00 h =2.00 Bh
Pintu Katrol b =4.00 h =2.25 Bh
Pintu Katrol b =4.00 h =2.50 Bh
Pintu Katrol b =4.00 h =2.75 Bh
Pintu Katrol b =4.00 h =3.00 Bh
Gembolo Kuningan Bh 9,075,000
Pintu Klep Fiber Resin(1.00 x1.00) m Bh 25,237,000
Katrol 3 Ton Bh 3,449,000
Katrol 4 Ton Bh 3,993,000
Katrol 5 Ton Bh 5,143,000
Katrol 10 Ton Bh 9,680,000
Kawat Las kg 39,000
Kawat Bronjong Pabrikasi dia,2.7 mm Uk. ( 2.00 x 1.00x 0.50 )m Unit 424,000
Kawat Bronjong Pabrikasi dia,3,0 mm Uk. ( 3.00 x 1.00x 0.50 )m Unit 669,200
Cangkul Bh 102,500
Sabit Bh 42,000
Cakar (tanpa gagang) Bh 106,000
Karung plastik Lbr 8,000
Mesin Potong Rumput Gendong (Honda ) Bh 5,060,000

Aspal Kemas KG Drum Harga Mengikuti 12,000

Aspal Curah Liter Harga Mengikuti 11,000

Kerosen / Minyak Tanah LITER 16,000

Cat Marka (Non Thermoplas) Kg 42,000

Cat Marka (Thermoplastic) Kg 43,000

Bensin LITER
Solar LITER -

Minyak Pelumas / Olie LITER 39,000

Plastik Filter M2 18,000

Glass Bead Kg 71,000

Pelat Rambu (Eng. Grade) BH 349,000

Pelat Rambu (High I. Grade) BH 447,000

Rel Pengaman M' 662,000


Guide Post 15x15x120 buah 499,000
Set Pile buah 790,000
Mini Pile 25x25 buah 170,000
Tiangpancang Persegi buah 2,350,000

Beton K-225 Redimix M3 1,100,000

Pemantul Cahaya (Reflector) Bh. 109,000

Arbocell Kg. 51,000


Tiang Pancang Baja m'
Tiang Pancang Beton Pratekan m3
PCI Girder L=17 m buah 61,408,000
PCI Girder L=21 m buah 80,465,000
PCI Girder L=26 m buah 131,890,000
PCI Girder L=32 m buah 204,490,000
PCI Girder L=36 m buah 250,470,000
PCI Girder L=41 m buah 302,500,000
Cerucuk m 6,000
Bahan Pengawet kreosot liter 6,000
Mata Kucing buah 154,000
Anchorage Buah 1,989,000
Anti strpping agent Kg 46,000
Ducting (Kabel prestress) m'
Ducting (Strand prestress) m'
Elastomer jenis 1 (35 x 30 x 3,6 cm) buah
Elastomer jenis 2 (40 x 35 x 3,9 cm) buah
Elastomer jenis 3 (45 x 40 x 4,5 cm) buah
Expansion Tipe Joint Asphaltic Plug m
Expansion Joint Tipe Rubber m
Expansion Joint Baja Siku m
Kerb Pracetak Type 2 (penghalang/Barrier) buah
Mini Timber Pile buah
Expansion Joint Tipe Toma m'
Strip Bearing buah
Joint Socket Pile 35 x 35 set
Joint Socket Pile 16 x 16 x 16 set
Mikro Pile 16 x 16 x 16 m'
Matras Concrete buah
Assetilline botol 326,000
Oksigen (isi 6 m3) botol 42,500
Batu Bara kg 2,000
Joint Sealent kg 54,000
Cat Anti Karat kg 54,000
Expansion Cap kg 27,000
Polytene 125 mikron kg 98,500
Curing Compound liter 24,000
Kayu Acuan m3 2,904,000
Additive LITER 62,000
Casing m
Tiang Pancang Beton Ø 400 (K600 Kelas A2) m
Tiang Pancang Beton Ø 500 (K600 Kelas A2) m
Tiang Pancang Beton Ø 600 (K600 Kelas A2) buah
Bak Fiber HU 1 m3 buah 4,598,000
Bak Fiber HU 2 m4 buah 6,341,000
Bak Fiber HU 3 m5 buah 9,438,000
BAHAN BAJA
Besi Tempa m2 319,000
Rangka Atap Baja Ringan m2 Smart Truss;Prima Truss 143,000
BAHAN ALMUNIUM
Rangka Jendela Almunium m' Alexindo 4 INC 122,000
Rangka Pintu Almunium m' Alexindo 122,000
Kusen & Pintu PVC Toilet unit Maspion 605,000
Handle Pintu bh Ex. Cisa Type 75.01 82,000
Selinder bh Ex. Cisa Type. 08510 55,000
Slot Tanam bh 242,000
BAHAN LANTAI DAN DINDING KERAMIK
Plint Keramik 10/30 cm bh Ex. Roman 11,000
Plint Granitetile 10/40 cm bh Ex. Granito 22,000
BAHAN PENUTUP ATAP
Genteng Keramik bh Ex. Jatiwangi 25 bh/m2 3,500
Genteng Keramik Glazur bh Ex. KANMURI 15 bh/m2 7,400
Nok Genteng Keramik bh Ex. Jatiwangi 4 bh/m 16,500
Nok Genteng Keramik Glazur bh Ex. KANMURI 4 bh/m 20,300
BAHAN KACA
Kaca Polos 8 mm m2 275,000
BAHAN FINISHING
Plamir Kayu kg FOX 33,000
Wood Filler kg Impra 38,700
BAHAN SANITARI
Shower Spray unit Ex. Toto Type. THT 20 NBPIV 435,000
Shower Set unit Ex. Toto Type. TX 423 SZ 1,511,000
Kran Zink bh Ex. Toto T 30 AR13NV7N 775,000
Kran Dinding bh Ex. Toto Type. T 23 B13v7N 502,000
BAHAN PARTISI DINDING/PLAFON
List Profil 5 cm Gypsum m' 16,000
Rangka Plafon Metal Furing m2 Termasuk Paku Ripet 137,000
BAHAN SALURAN AIR
Bak Kontrol Ø 60 Unit Tinggi 92 cm 737,500
Bak Kontrol Ø 40 Unit Tinggi 70 cm 443,700
Bak Kontrol Ø 30 Unit Tinggi 52 cm 298,700
Bak Penangkap Lemak Ø 30 Unit Tinggi 52 cm 686,200
Bak Penangkap Lemak Ø 60 Unit Tinggi 10 cm 418,000
Bak Penangkap Lemak Ø 40 Unit Tinggi 10 cm 220,000
Tutup Beton Ø 30 Unit Tinggi 5 cm 75,000
Bak Kontrol Precast Ø 30 cm bh 230,000
Bak Kontrol Precast Ø 40 cm bh 350,000
Bak Kontrol Precast Ø 60 cm bh 550,000
Bak Kontrol Precast Ø 32 cm (penangkap lemak/gestrep) bh 230,000
Leher Angsa bh 80,000
Pipa Air Limbah Ø 4" m' setara rucika 563,300
Pipa Air Limbah Ø 6" m' setara rucika 1,092,500
Pipa Air Limbah Ø 8" m' setara rucika 1,669,500
Stop Kran dia 1" bh Ex. Onda 165,000
Tangki Air 1000 Liter bh EXEL 1,705,000
Tangki Air 500 Liter bh EXEL 1,045,000
Tandon Air Fiberglas vol 650 liter bh setara pinguin 850,000
Tandon Air Fiberglas vol 1050 liter bh setara pinguin 1,300,000
Tandon Air Fiberglas vol 1200 liter bh setara pinguin 1,800,000
Tandon Air Fiberglas vol 1550 liter bh setara pinguin 2,500,000
Tandon Air Fiberglas vol 2000 liter bh setara pinguin 3,100,000
Pelampung Otomatis bh 80,000
Roof Drain Metal bh 88,000
Mesin Jet Pump Kap.250 Watt unit Groundfos 4,372,000
Mesin Pompa Tekan kap. 150 Watt unit Groundfos 3,036,000
PERALATAN ELEKTRIK
Pemasangan Meteran Baru 1300 Watt Unit 1,300,000
Pemasangan Meteran Baru 2200 Watt Unit 2,082,000
Pemasangan Meteran Baru 3200 Watt Unit 3,941,000
Tambah Daya KWH 1,352
Kabel LVTC m' 12,000
Box Panel PVC Isi 4 MCB bh Legram 46,000
MCB 6 A bh Legram 71,000
MCB 4 A bh Legram 52,000
Kabel NYM 2x2,5 mm m' 10,000
Kabel NYM 3x2,5 mm m' 13,000
Kabel Telephone 4 x 0,5 mm m' 11,000
Isolasi bh 9,000
Outlet TV bh Broco 46,000
Outlet Telephone bh Broco 46,000
Down Light/ PLC 13 Watt bh 132,000
Fitting Plafond +Lampu SL bh Panasonic 68,000
Lammpu TL 2x18 Watt Grille bh Panasonic 275,000
Lammpu TL 2x36 Watt Grille bh Panasonic 352,000
PERALATAN AIR BERSIH
DAFTAR UPAH PEKERJA

SUMBER DATA : PASARAN BEBAS


D A E R A H : KABUPATEN KEBUMEN
EDISI 2023

HARGA
NO. URAIAN PEKERJA SATUAN KET.
(Rp)
1 Pekerja Hr 82,000

2 Mandor Hr 95,000

3 Tukang listrik Hr 90,000

4 Tukang kayu Hr 90,000

5 Kep. tk. kayu Hr 95,000

6 Tukang batu Hr 90,000

7 Kep. tk. batu Hr 95,000

8 Tukang besi Hr 90,000

9 Kep. tk. besi Hr 95,000

10 T u k a n g c a t Hr 90,000

11 K e p . t k . c a t Hr 95,000

12 T u k a n g p l i t u r Hr 90,000

13 T u k a n g j a l a n Hr 90,000

14 T u k a n g g a l i Hr 90,000

15 Tukang masak aspal Hr 90,000

16 T k . l e i d e n g Hr 90,000

17 M a s i n i s Hr 90,000

18 P e m b . M a s i n i s Hr 82,000

19 P e n j a g a a p i Hr 82,000

20 P e n j a g a m a l a m Hr 82,000

21 S o p i r Hr 90,000

22 P e m b a n t u S o p i r Hr 82,000

23 Tukang Vibrator Hr 90,000

24 Tukang Ereksi Hr 90,000

25 Operator Crane Hr 120,000

26 Pembantu Operator Crane Hr 88,000

720096400.xlsx 451 utk


DAFTAR HARGA SATUAN PEKERJAAN
BERDASAR PERMEN PU NO.1 2022

SUMBER DATA : PASARAN BEBAS EDISI 2023


DAERAH : KABUPATEN KEBUMEN

HARGA SATUAN
NO. KODE URAIAN PEKERJAAN SAT PEKERJAAN
Rp
DIVISI 1 A. 1.1.1 HARGA SATUAN PEKERJAAN PERSIAPAN
1 A.1.1.1.1 Pembuatan 1 m2 pagar sementara dari kayu tinggi 2 meter m2 886,548.30

2 A.1.1.1.2 Pembuatan 1 m' pagar sementara dari seng gelombang m' 981,662.55

3 A.1.1.1.3 Pembuatan 1 m2 pagar sementara dari kawat duri tinggi 1.8 meter m2 1,131,548.00

4 A.1.1.1.4 Pengukuran dan Pemasangan 1 m' Bouwplank m' 245,353.24


5 A.1.1.1.5 Pembuatan 1 m2 kantor sementara m2 2,866,468.00
6 A.1.1.1.6 Pembuatan 1 m2 gudang m2 2,388,705.00
7 A.1.1.1.7 Pembuatan 1 m2 rumah jaga m2 2,482,526.75
8 A.1.1.1.8 Pembersihan 1 m2 dan Perataan lapangan m2 14,245.00
9 A.1.1.1.9 Pembuatan 1m2 Bedeng Pekerja m2 2,687,993.00
10 A.1.1.1.10 Pembuatan 1 m2 bak adukan m2 279,497.24

11 A.1.1.1.11 Pembuatan1 m2 Steger/Perancah dari Bambu sd Tinggi 6 meter m2 340,126.60

12 A.1.1.1.14 Pembongkaran 1 m3 Beton Bertulang m3 1,272,323.80


13 A.1.1.1.15 Pemasangan 1m2 Pagar BRC Galvanis m2 75,672.17
14 A.1.1.1.16 Pemasangan 1 m2 Panel Beton Pracetak 50x50x240cm untuk Pagar m2 631,185.92
15 A.1.1.1.17 Pebuatan 1 m2 jalan sementara m2 175,846.00
16 A.1.1.1.18 Pembongkaran 1 m3 dinding tembok bata m3 601,363.40
17 A.1.1.1.19 Pembongkaran 1 m3 keramik exiting m3 30,036.60

DIVISI 1 A.1.5.1 HARGA SATUAN PEKERJAAN TANAH


1 A.1.5.1.1 Penggalian Tanah Biasa Sedalam s.d 1 m m2 70,262.50
2 A.1.5.1.2 Penggalian Tanah Biasa Sedalam > 1 s.d 2 m m2 85,882.50
3 A.1.5.1.3 Penggalian Tanah Biasa Sedalam > 2 s.d 3 m m2 101,711.50
4 A.1.5.1.4 Penggalian Tanah Keras Sedalam s.d 1 m m2 93,544.00
5 A.1.5.1.5 Penggalian Tanah Cadas Sedalam s.d 1 m m2 141,570.00
6 A.1.5.1.6 Penggalian Tanah Lumpur Sedalam s.d 1 m m2 112,942.50
7 A.1.5.1.7 Pengerjaan Striping Tebing Setinggi s.d 1 m m2 5,032.50
8 A.1.5.1.8 Pembuangan Tanah sejauh s.d 30 m m3 30,811.00
9 A.1.5.1.9 Pemadatan Tanah per 20 cm m3 50,325.00
10 A.1.5.1.10 Pengurugan dengan Pasir Urug m3 278,905.00
11 A.1.5.1.11 Pemasangan Lapisan Pudel Cmp. 1Kp : 3Ps : 7TL m3 449,113.50

12 A.1.5.1.13 Pemasangan Lapisan Ijuk tebal 10 cm untuk Bidang Resapan Tangki Septik m2 71,197.50

13 A.1.5.1.14 Pengurugan dengan Sirtu Padat m3 322,162.50


14 A.1.5.1.15 Pengurugan kembali 1 m3 galian tanah m3 50,325.00
15 A.1.5.1.16 Pemasangan Trucuk bambu Ø10 cm panjang 4 m titik 118,185.79

720096400.xlsx 451/50 hspk


HARGA SATUAN
NO. KODE URAIAN PEKERJAAN SAT PEKERJAAN
Rp
DIVISI 3 A.3.2.1. HARGA SATUAN PEKERJAAN PONDASI
1 A.3.2.1.1 Pemasangan Pondasi Batu Belah 1SP : 3 PP m3 1,127,274.50
2 A.3.2.1.2 Pemasangan Pondasi Batu Belah 1SP : 4 PP m3 1,074,117.00
3 A.3.2.1.3 Pemasangan Pondasi Batu Belah 1SP : 5 PP m3 1,037,236.20
4 A.3.2.1.4 Pemasangan Pondasi Batu Belah 1SP : 6 PP m3 1,011,321.30
5 A.3.2.1.5 Pemasangan Pondasi Batu Belah 1SP : 8 PP m3 975,768.20
6 A.3.2.1.6 Pemasangan Pondasi Batu Belah 1KP : 1SM : 2PP m3 837,127.50

7 A.3.2.1.7 Pemasangan Pondasi Batu Belah, 1 PC : 3 KP : 10 PP m3 952,629.70

8 A.3.2.1.8 Pemasangan Pondasi Batu Belah, ¼ PC : 1KP : 4 PP m3 923,474.20

9 A.3.2.1.9 Pemasang Batu Kosong (Anstamping) untuk pondasi gedung m3 604,725.00

10 A.3.2.1.10 Pemasangan Pondasi Siklop 60% Beton m3 3,575,016.50

11 A.3.2.1.11 Pemasangan Pondasi Sumuran Ø 100 cm m3 1,054,531.50


12 A.3.2.1.12 Pasang Pondasi Rolag Trashram Bata Merah 1 Pc : 3 Ps m3 1,485,907.50
13 A.3.2.1.13 Pasang suling - suling m' 18,580.10

DIVISI 4 A.4.1.1 HARGA SATUAN PEKERJAAN BETON

1 A.4.1.1.1 Pembuatan 1 m3 beton mutu fc 7,4 Mpa (K100) m3 1,161,356.43

2 A.4.1.1.2 Pembuatan 1 m3 beton mutu fc 9,8 Mpa (K125) m3 1,201,672.30

3 A.4.1.1.3 Pembuatan 1 m3 beton mutu fc 12,2 Mpa (K150) m3 1,233,076.43

4 A.4.1.1.4 Pembuatan 1 m3 lantai kerja beton mutu fc 7,4 Mpa m3 1,091,529.83

5 A.4.1.1.5 Pembuatan 1 m3 beton mutu fc 14,5 Mpa (KI75) m3 1,270,336.05

6 A.4.1.1.6 Pembuatan 1 m3 beton mutu fc 16,9 Mpa (K200) m3 1,305,846.84

7 A.4.1.1.7 Pembuatan 1 m3 beton mutu fc 19,3 Mpa (K225) m3 1,332,715.48

8 A.4.1.1.8 Pembuatan 1 m3 beton mutu fc 21,7 Mpa (K250) m3 1,350,254.02

9 A.4.1.1.9 Pembuatan 1 m3 beton mutu fc 24,0 Mpa (K275) m3 1,380,734.14

10 A.4.1.1.10 Pembuatan 1 m3 beton mutu fc 26,4 Mpa (K300) m3 1,390,036.30

11 A.4.1.1.11 Pembuatan 1m3 Beton mutu f'c=28,8 MPa (K325) m3 1,476,757.42

12 A.4.1.1.12 Pembuatan 1m3 Beton mutu f'c=31,2 MPa (K350) m3 1,489,100.47

13 A.4.1.1.13 Pembuatan 1 m3 Beton Kedap Air dengan Aditif Kedap Air m3 985,626.79

14 A.4.1.1.15 Pembesian 10 kg dengan Besi Polos atau Ulir Kg 215,363.50


15 A.4.1.1.16 Pemasangan 10 kg kabel prategang (Prestressed) Polos/strands Kg 209,726.00
16 A.4.1.1.17 Pemasangan 1 kg Jaring Anyaman Tulangan Tunggal (Wiremesh) M6- M8 Kg 32,314.70
Pemasangan 1 m2 Bekisting untuk Pondasi Telapak Beton Bangunan
17 A.4.1.1.18 m2 219,865.80
Gedung
18 A.4.1.1.19 Pemasangan 1 m2 Bekisting untuk Sloof Beton Bangunan Gedung m2 236,410.90
19 A.4.1.1.20 Pemasangan 1 m2 Bekisting untuk Kolom Beton Bangunan Gedung m2 489,715.05
20 A.4.1.1.21 Pemasangan 1 m2 Bekisting untuk Balok Bangunan Gedung m2 522,343.80
21 A.4.1.1.22 Pemasangan 1 m2 Bekisting untuk Plat lantai Beton Bangunan Gedung m2 551,315.05
22 A.4.1.1.23 Pemasangan 1 m2 Bekisting untuk Dinding Sheerwall m2 561,606.10
23 A.4.1.1.25 Pemasangan 1 m2 Bekisting untuk Tangga Beton Bangunan Gedung m2 455,211.35
24 A.4.1.1.26 Pembuatan 1 m' kolom praktis beton bertulang (11 x 11) cm m' 113,417.04
25 A.4.1.1.27 Pembuatan 1 m' Ring Balok Beton Bertulang (10 x 15) cm m' 137,463.26
26 A.4.1.1.28 Pemasangan bekisting 1 m2 Jembatan untuk Pengecoran Beton m2 128,096.63

720096400.xlsx 451/51 hspk


HARGA SATUAN
NO. KODE URAIAN PEKERJAAN SAT PEKERJAAN
Rp

DIVISI 4 A.4.1.2 HARGA SATUAN PEKERJAAN BETON PRACETAK


1 A.4.1.2.1 Pembuatan 1 m2 lahan produksi tebal 8 cm beton fc 14,5 Mpa, slump (120±20) m m2 101,544.82
2 A.4.1.2.2 Pembuatan 1 m2 lahan produksi tebal 10 cm beton fc 14,5 Mpa, slump (120±20) m2 126,954.40
3 A.4.1.2.3 Pembuatan 1 m2 lahan produksi tebal 12 cm beton fc 14,5 Mpa, slump (120±20) m2 152,264.99
4 A.4.1.2.4 Pembuatan 1 m2 lahan produksi tebal 15 cm beton fc 14,5 Mpa, slump (120±20) m2 190,429.96

Pembuatan 1 m2 Bekisting untuk Pelat Beton Pracetak Komponen Modular


5 A.4.1.2.5. m2 64,883.50
Bangunan Gedung (5 kali pakai)

6 A.4.1.2.6. Pembuatan 1 m2 Bekisting untuk Balok Beton Pracetak (10-12 kali pakai) m2 50,702.30
7 A.4.1.2.7. Pembuatan 1 m2 Bekisting untuk Kolom Beton Pracetak (10-12 Kali Pakai) m2 42,824.10
8 A.4.1.2.8. Pemasangan dan Membuka Cetakan 1 Buah Komponen Pelat Beton Pracetak buah 7,085.10
9 A.4.1.2.9. Pemasangan dan Membuka Cetakan 1 Buah Komponen Balok Beton Pracetak buah 11,520.30
10 A.4.1.2.10. Pemasangan dan Membuka Cetakan 1 Buah Komponen Kolom Beton Pracetak buah 9,302.70
11 A.4.1.2.11. Penuangan/Menebar Beton 1 m3 untuk Pelat Beton Pracetak m3 53,782.30
12 A.4.1.2.12. Penuangan/Menebar Beton 1 m3 untuk Balok Beton Pracetak m3 55,338.80
13 A.4.1.2.13. Penuangan/Menebar Beton 1 m3 untuk Kolom Beton Pracetak m3 49,744.20
Pemasangan 1 buah Komponen untuk Pelat Beton Pracetak Beserta
14 A.4.1.2.14. buah 55,275.00
Indeks Kenaikan Lantai Ereksi Pelat Hingga 24 Lantai
Pemasangan 1 buah Komponen Balok Pracetak Beserta Indeks Kenaikan Lantai
15 A.4.1.2.15. buah 50,325.00
Ereksi Balok Hingga 24 Lantai
Pemasangan 1 buah Komponen Kolom Pracetak Beserta Indeks Kenaikan Lantai
16 A.4.1.2.16 buah 148,280.00
Ereksi Balok Hingga 24 Lantai
17 A.4.1.2.17. Pemindahan 1 buah Komponen untuk Pelat Pracetak (± 20 m) buah 5,475.80
18 A.4.1.2.18. Pemindahan 1 buah Komponen untuk Balok Pracetak ( ± 20 m) buah 5,475.80
19 A.4.1.2.19. Pemindahan 1 buah Komponen untuk Kolom Pracetak ( ± 20 m) buah 5,475.80
20 A.4.1.2.20. Bahan 1 m3 Grout campuran m3 14,743.58
21 A.4.1.2.21. Bahan 1 m3 Grout (tidak campuran) m3 13,553.10
22 A.4.1.2.22. Upah 1 titik Pekerjaan Grout pada Joint Beton Pracetak titik 47,932.50
23 A.4.1.2.23. Pemasangan 1 titik Bekisting Joint Pracetak titik 160,956.40
24 A.4.1.2.24. Upah 1 titik Joint dengan Sling titik 44,951.50

DIVISI 4 A.4.2.1 HARGA SATUAN PEKERJAAN BESI DAN ALLUMUNIUM

1 A.4.2.1.1 Pembuatan 1 kg Baja Profil kg 33,797.50


2 A.4.2.1.2 Pemasangan Rangka Kuda-kuda Baja IWF kg 37,845.50
3 A.4.2.1.3 Pengerjaan Perakitan Baja kg 4,781.70

4 A.4.2.1.4 Pembuatan Pintu Pelat Baja tebal 2 mm rangkap m2 1,184,111.50

5 A.4.2.1.5 Pengerjaan Pengelasan dengan Las Listrik cm 11,401.50


6 A.4.2.1.6 Pembuatan Rangka Jendela Squaretube m2 250,353.40
7 A.4.2.1.7 Pemasangan 1 m2 Pintu Rolling Door Besi m2 724,207.00
8 A.4.2.1.8 Pemasangan Pintu Folding door Bahan Plastik/PVC m2 574,145.00
9 A.4.2.1.9 Pemasangan 1 m2 Sunscreen Aluminium m2 222,244.00
10 A.4.2.1.10 Pemasangan Rolling Door Allumunium m2 699,875.00
11 A.4.2.1.15 Pemasangan 1 m2 Teralis Besi strip (20 x 3) mm m2 505,151.09
12 A.4.2.1.16 Pemasangan 1 m2 Kawat Nyamuk m2 100,535.67
13 A.4.2.1.17 Pemasangan 1 m2 Jendela Nako dan Tralis m2 357,054.50

14 A.4.2.1.18 Pemasangan 1 m’ Talang Datar/Jurai Seng bjls 28 Lebar 90cm m' 234,862.10

15 A.4.2.1.19 Pemasangan 1 m Talang ½ Lingkaran D-15cm. Seng Pelat bjls 30 m' 78,078.00

720096400.xlsx 451/52 hspk


HARGA SATUAN
NO. KODE URAIAN PEKERJAAN SAT PEKERJAAN
Rp
Pemasangan 1 m2 Rangka Besi Hollow Galvanis 40.40 mm. Modul 60x120cm.
16 A.4.2.1.20 m2 269,437.67
untuk Partisi
Pemasangan 1 m2 Rangka Besi Hollow Galvanis 40.40 mm. Modul 60x60cm.
17 A.4.2.1.21 m2 321,091.83
untuk Plafond
Pemasangan 1 m2 Atap Pelana Rangka Atap Baja Ringan (Canai Dingin) Profil
18 A.4.2.1.22 m2 288,939.09
C75
Pemasangan 1 m2 Atap Jurai/Limasan Rangka Atap Baja Ringan (Canai Dingin)
19 A.4.2.1.23 m2 294,351.97
Profil C75
20 A.4.2.1.24 Pemasangan 1 m Kusen Aluminium m' 162,157.60
21 A.4.2.1.25 Pemasangan 1 m2 Pintu Aluminium Strip Lebar 8 cm m2 816,669.15
22 A.4.2.1.26 Pemasangan Pintu Kaca Rangka Allumunium m2 788,264.40
23 A.4.2.1.27 Pemasangan 1 m2 Venetions Blinds dan Vertical Blinds m2 273,058.50
24 A.4.2.1.28 Pemasangan 1 m2 Aluminium Composit Panel (ACP) rangka besi hollow 40.40.1, m2 690,096.00

DIVISI 4 A.4.4.1 HARGA SATUAN PEKERJAAN PASANGAN DINDING

Pemasangan 1m2 Dinding Bata Merah (5x11x22) cm Tebal 1 Batu


1 A.4.4.1.1 m2 318,021.00
dengan Mortar tipe M.fc’ 17. 2 Mpa ( Setara Campuran 1SP : 2PP).
Pemasangan 1m2 Dinding Bata Merah (5x11x22) cm Tebal 1 Batu
2 A.4.4.1.2 m2 304,168.70
dengan Mortar tipe S.fc’ 12. 5 Mpa ( Setara Campuran 1SP : 3PP)
Pemasangan 1m2 Dinding Bata Merah (5x11x22) cm tebal 1 Batu dengan
3 A.4.4.1.3 m2 294,156.50
Mortar tipe N.fc’ 5.2 Mpa ( Setara Campuran 1SP : 4PP)
Pemasangan 1m2 Dinding Bata Merah (5x11x22) cm tebal 1 Batu dengan
4 A.4.4.1.4 m2 289,982.00
Mortar tipe O. fc’ 2.4 Mpa ( Setara Campuran 1SP : 5PP)
Pemasangan 1m2 Dinding Bata Merah (5x11x22) cm tebal 1 batu
5 A.4.4.1.5 m2 290,681.60
Campuran 1SP : 6PP
Pemasangan Dinding Bata Merah Ukuran (5x11x22) cm Tebal 1 Bata Camp.
6 A.4.4.1.6 m2 277,427.26
1SP : 3 KP :10PP
Pemasangan 1m2 Dinding Bata Merah (5x11x22) cm Tebal ½ Batu dengan
7 A.4.4.1.7 m2 153,640.30
Mortar tipe M.fc’ 17. 7 Mpa ( Setara Campuran 1SP : 2PP).
Pemasangan 1m2 Dinding Bata Merah (5x11x22) cm tebal ½ Batu dengan
8 A.4.4.1.8 m2 146,671.14
Mortar tipe S. fc’ 12. 5 Mpa ( Setara Campuran 1SP : 3PP).
Pemasangan 1m2 Dinding Bata Merah (5x11x22) cm Tebal ½ Batu dengan
9 A.4.4.1.9 m2 142,905.40
Mortar tipe N.fc’ 5.2 Mpa ( Setara Campuran 1SP : 4PP)
Pemasangan 1m2 Dinding Bata Merah (5x11x22)cm Tebal ½ Batu dengan
10 A.4.4.1.10 m2 140,550.96
Mortar tipe O. fc’ 2.4 Mpa ( Setara Campuran 1SP : 5PP)
Pemasangan 1m2 Dinding Bata Merah (5x11x22)cm tebal ½ Batu
11 A.4.4.1.11 m2 139,654.24
Campuran 1SP : 6PP

12 A.4.4.1.12 Pemasangan Dinding Bata Merah 1/2 Batu 1SP : 8PP m2 136,955.50

13 A.4.4.1.13 Pemasangan Dinding Bata Merah 1/2 Batu 1SP : 3KP : 10PP m2 138,281.00

14 A.4.4.1.14 Pemasangan Dinding Bata Merah 1/2 Batu Camp. 1SP : 1KP : 1PP m2 123,811.60

15 A.4.4.1.15 Pemasangan Dinding Bata Merah 1/2 Batu 1SM : 1KP : 2PP m2 125,312.00

Pemasangan 1m2 Dinding Conblock HB20 dengan Mortar Tipe S.fc’ 12.
16 A.4.4.1.16 m2 438,949.94
5 Mpa ( Setara Campuran 1SP : 3PP)
Pemasangan 1m2 Dinding Conblock HB20 Campuran1SP :4PP dengan
17 A.4.4.1.17 m2 443,966.82
Mortar Tipe N.fc’ 5.2 Mpa ( Setara Campuran 1SP : 4PP)
Pemasangan 1m2 Dinding Conblock HB15 dengan Mortar Tipe S. fc’ 12.
18 A.4.4.1.18 m2 358,792.28
5 Mpa ( Setara Campuran 1SP : 3PP)
Pemasangan 1 m2 Dinding Conblock HB15 dengan Mortar Tipe N. fc’
19 A.4.4.1.19 m2 362,219.00
5.2 Mpa ( Setara Campuran 1SP : 4PP)
Pemasangan 1 m2 Dinding Conblock HB10 dengan Mortar Tipe S. fc’ 12.
20 A.4.4.1.20 m2 277,981.22
5 Mpa (Setara Campuran 1SP : 3PP)
Pemasangan 1 m2 Dinding Conblock HB10 dengan Mortar Tipe N. fc’
21 A.4.4.1.21 m2 281,178.26
5.2 Mpa (Setara Campuran 1SP : 4PP)
Pemasangan 1 m2 Dinding Terawang (rooster) 12x11x24 dengan
22 A.4.4.1.22 m2 323,015.00
Mortar Tipe S.fc’ 12. 5 Mpa ( Setara Campuran 1SP : 3PP)
Pemasangan 1 m2 Dinding Terawang (rooster) 12x11x24 dengan Mortar
23 A.4.4.1.23 m2 323,015.00
Tipe N.fc’ 5.2 Mpa ( Setara Campuran 1SP : 4PP)
Pemasangan 1 m2 Dinding bata Berongga Ekspose 12x11x24 dengan
24 A.4.4.1.24 m2 381,998.10
Mortar Tipe S.fc’ 12. 5 Mpa ( Setara Campuran 1SP : 3PP)

25 A.4.4.1.25 Pemasangan 1 m2 Dinding Bata Ringan Tebal 7.5cm dengan Mortar Siap Pakai m2 280,426.44

26 A.4.4.1.26 Pemasangan 1m2 Dinding Bata Ringan Tebal 10cm dengan Mortar Siap Pakai m2 284,436.76

720096400.xlsx 451/53 hspk


HARGA SATUAN
NO. KODE URAIAN PEKERJAAN SAT PEKERJAAN
Rp

DIVISI 4 A.4.4.2 HARGA SATUAN PEKERJAAN PLESTERAN


1 A.4.4.2.1 Pemasangan Plesteran 1 Pc : 1 Pp Tebal 15 mm m2 76,476.49
2 A.4.4.2.2 Pemasangan Plesteran 1 Pc : 2 Pp Tebal 15 mm m2 69,025.53
3 A.4.4.2.3 Pemasangan Plesteran 1 Pc : 3 Pp Tebal 15 mm m2 65,965.37
4 A.4.4.2.4 Pemasangan Plesteran 1 Pc : 4 Pp Tebal 15 mm m2 63,741.48
5 A.4.4.2.5 Pemasangan Plesteran 1 Pc : 5 Pp Tebal 15 mm m2 62,664.45
6 A.4.4.2.6 Pemasangan Plesteran 1 Pc : 6 Pp Tebal 15 mm m2 61,724.65
7 A.4.4.2.7 Pemasangan Plesteran 1 Pc : 7 Pp Tebal 15 mm m2 61,266.39
8 A.4.4.2.8 Pemasangan Plesteran 1 Pc : 8 Pp Tebal 15 mm m2 60,808.13

9 A.4.4.2.9 Pemasangan Plesteran 1 Pc :1/2 Kp:3 Pp Tebal 15 mm m2 62,791.52

10 A.4.4.2.10 Pemasangan Plesteran 1 Pc : 2 Kp : 8 Pp Tebal 15 mm m2 60,945.50

11 A.4.4.2.11 Pemasangan Plesteran 1 SM : 1 Kp : 1 Pp Tebal 15 mm m2 54,956.55

12 A.4.4.2.12 Pemasangan Plesteran 1 SM : 1 Kp : 2 Pp Tebal 15 mm m2 56,051.05

13 A.4.4.2.13 Pemasangan Plesteran 1 Pc : 2 Pp Tebal 20 mm m2 92,357.80


14 A.4.4.2.14 Pemasangan Plesteran 1Pc : 3Pp Tebal 20 mm m2 67,917.36
15 A.4.4.2.15 Pemasangan Plesteran 1 Pc : 4 Pp Tebal 20 mm m2 85,197.64
16 A.4.4.2.16 Pemasangan Plesteran 1Pc : 5Pp Tebal 20 mm m2 83,876.36
17 A.4.4.2.17 Pemasangan Plesteran 1Pc : 6Pp Tebal 20 mm m2 82,508.54

18 A.4.4.2.18 Pemasangan Plesteran 1 SM : 2 Kp : 2 Pp Tebal 20 mm m2 76,634.25

19 A.4.4.2.19 Pemasangan 1 m2 Berapen 1SP : 5PP Tebal 15 mm m2 40,246.45

20 A.4.4.2.20 Pemasangan Plesteran Skoning 1 Pc : 2Pp, lebar 10 mm m2 56,725.90

21 A.4.4.2.21 Pemasangan Plesteran Granit 1Pc : 2 Granit , Tebal 10 mm m2 199,892.00

22 A.4.4.2.22 Pemasangan Plesteran Traso 1Pc : 2Traso, lebar 10 mm m2 210,287.00

23 A.4.4.2.23 Pemasangan Plesteran Ciprat (kamprotan) 1Pc : 2 Pp m2 48,861.34

24 A.4.4.2.24 Pemasangan Finishing 1 m2 Dinding Siar Pasangan Bata Merah m2 27,823.58

25 A.4.4.2.25 Pemasangan Finishing 1m2 Dinding Siar Pasangan Conblock Ekspose m2 13,290.20

26 A.4.4.2.26 Pemasangan 1m2 Finishing Siar Pasangan Batu Kali. Campuran 1SP : 2PP m2 59,777.08

27 A.4.4.2.27 Pemasangan Acian m2 35,464.00

28 A.4.4.2.28 Pemasangan Plesteran dg Mortar Siap Pakai (MSP) m2 51,823.75

29 A.4.4.2.29 Pemasangan Acian dg Mortar Siap Pakai (MSP) m2 41,201.88

DIVISI 4 A.4.4.3 HARGA SATUAN PEKERJAAN PENUTUP LANTAI dan DINDING

1 A.4.4.3.1 Pemasangan 1 m2 lantai Ubin PC Abu-abu 40 x 40 cm m2 69,521.10

2 A.4.4.3.2 Pemasangan 1 m2 lantai Ubin PC Abu-abu 30 x 30 cm m2 150,571.50

3 A.4.4.3.3 Pemasangan 1 m2 lantai Ubin PC Abu-abu 20 x 20 cm m2 163,309.30

4 A.4.4.3.5 Pemasangan 1m2 Lantai ubin Warna Ukuran 30cm x 30cm m2 192,019.00
5 A.4.4.3.6 Pemasangan 1m2 Lantai ubin Warna Ukuran 20cm x 20cm m2 195,902.30
6 A.4.4.3.7 Pemasangan 1m2 Lantai Ubin Teraso Ukuran 40cm x 40cm m2 92,401.10
7 A.4.4.3.8 Pemasangan 1m2 Lantai Ubin Teraso Ukuran 30cm x 30cm m2 203,889.00
8 A.4.4.3.9 Pemasangan 1m2 Lantai Ubin Granit Ukuran 40cm x 40cm m2 303,533.45

720096400.xlsx 451/54 hspk


HARGA SATUAN
NO. KODE URAIAN PEKERJAAN SAT PEKERJAAN
Rp
9 A.4.4.3.10 Pemasangan 1m2 Lantai Ubin Granit Ukuran 30cm x 30cm m2 294,694.50
10 A.4.4.3.11 Pemasangan 1m2 Lantai Ubin Granit Ukuran 60cm x 60cm m2 425,036.33
11 A.4.4.3.12 Pemasangan 1m' plint Ubin Ukuran 10cm x 40cm m' 71,724.73
12 A.4.4.3.13 Pemasangan 1m' plint Ubin Ukuran 10cm x 30cm m' 87,841.93
13 A.4.4.3.16 Pemasangan 1 m’ Plint Ubin PC Abu-abu Ukuran 20 s.d. <30 cm m2 31,372.00
14 A.4.4.3.19 Pemasangan 1 m’ Plint Ubin Warna Ukuran 20 s.d. <30cm m2 33,100.98
15 A.4.4.3.20 Pemasangan 1 m2 lantai keramik 60x60 cm m2 237,894.43
16 A.4.4.3.21 Pemasangan 1 m2 lantai keramik 40x40 cm m2 248,803.50
17 A.4.4.3.32 Pemasangan Lantai Keramik 10x 20 cm m2 294,278.38

18 A.4.4.3.33 Pemasangan lantai Keramik Uk. 10 x 10 cm / 5 x 20 cm m2 302,198.38

19 A.4.4.3.34 Pemasangan Lantai Keramik 33 x 33 cm m2 249,581.96


20 A.4.4.3.35 Pemasangan Lantai Keramik 30 x 30 cm m2 231,971.00
21 A.4.4.3.36 Pemasangan Lantai Keramik 20 x 20 cm m2 241,706.30

22 A.4.4.3.37 Pemasangan Lantai Keramik uk.10 x 33 cm, untuk variasi / border m2 373,572.10

23 A.4.4.3.39 Pemasangan Plint Keramik Ukuran 10x20 cm m' 74,339.98


24 A.4.4.3.40 Pemasangan Plint Keramik Ukuran 10x10 cm m' 80,609.98
25 A.4.4.3.41 Pemasangan Plint Keramik Ukuran 5x20 cm m' 86,439.98
26 A.4.4.3.43 Pemasangan Lantai Marmer Ukuran 1.00x1.00 cm m2 1,204,110.38
27 A.4.4.3.44 Pemasangan Lantai Karpet m2 120,543.50
28 A.4.4.3.45 Pemasangan 1 m2 underlayer (pelapis bawah karpet) m2 57,326.50
29 A.4.4.3.46 Pemasangan Lantai Parquet Jati m2 493,086.00
30 A.4.4.3.48 Pemasangan Dinding Porselen 11 x 11 cm m2 316,281.39
31 A.4.4.3.49 Pemasangan Dinding Porselen 10x20 cm, m2 316,868.20
32 A.4.4.3.50 Pemasangan Dinding Porselen 20x20 cm, m2 312,290.00
33 A.4.4.3.53 Pemasangan Dinding Keramik 10x20 cm, m2 316,868.20
34 A.4.4.3.54 Pemasangan Dinding Keramik 20x20 cm, m2 314,622.00
35 A.4.4.3.55 Pemasangan Dinding Marmer Ukuran 1.00x1.00 cm m2 1,297,723.68
36 A.4.4.3.56 Pemasangan Dinding Keramik uk 20 x 25 cm m2 316,954.00
37 A.4.4.3.57 Pemasangan Dinding Keramik uk 30 x 60 cm m2 385,363.00

38 A.4.4.3.58 Pemasangan Dinding Batu Paros / Batu Tempel Hitam m2 299,183.50

39 A.4.4.3.59 Pemasangan Lantai Vynil uk.30 x 30 cm m2 189,013.00


40 A.4.4.3.60 Pemasangan Wallpaper Lebar 50 Cm m2 156,920.50
42 A.4.4.3.62 Pemasangan 1 m' plint vynil 15cm x 30cm m' 31,394.00
43 A.4.4.3.63 Pemasangan Plint Kayu Klas II Ukuran 2x10 cm m2 67,648.46
44 A.4.4.3.64 Pemasangan Paving Block Natural Tebal 6 Cm m2 193,282.87
45 A.4.4.3.65 Pemasangan Paving Block Natural Tebal 8 Cm m2 238,375.17
46 A.4.4.3.66 Pemasangan Paving Block Berwarna Tebal 6 Cm m2 206,725.97
47 A.4.4.3.67 Pemasangan Paving Block Berwarna Tebal 8 Cm m2 242,041.47
48 A.4.4.3.68 Pemasangan Saluran U-20 cm m' 465,332.64
49 A.4.4.3.69 Pemasangan Saluran U-30 cm m' 478,037.64
50 A.4.4.3.70 Pembongkaran 1 m2 penutup lantai/penutup dinding lama m2 50,898.10

720096400.xlsx 451/55 hspk


HARGA SATUAN
NO. KODE URAIAN PEKERJAAN SAT PEKERJAAN
Rp

DIVISI 4 A.4.5.1 HARGA SATUAN PEKERJAAN LANGIT-LANGIT (PLAFON)

1 A.4.5.1.1 Pemasangan Langit-langit Asbes (1,00x1,00) m, tebal 4 mm, 5 mm & 6 mm m2 34,600.50

2 A.4.5.1.2 Pemasangan 1 m2 Langit-langit Akustik Ukuran 30 x 30 cm m2 118,085.00

3 A.4.5.1.3 Pemasangan 1 m2 Langit-langit Akustik Ukuran 30 x 60 cm m2 142,807.50

4 A.4.5.1.4 Pemasangan 1 m2 Langit-langit Akustik Ukuran 60 x 120 cm m2 115,637.50

5 A.4.5.1.5 Pemasangan 1 m2 Langit-langit Kayu Lapis. Tebal 3 mm. 4 mm dan 6 m2 52,497.50

6 A.4.5.1.6 Memasang Langit-langit Lambriziring Kayu Jati, tebal 6 mm m2 497,142.80

7 A.4.5.1.7 Memasang Langit-langit Gypsu Board, Ukuran (120x240) tebal 9 mm m2 48,837.80

8 A.4.5.1.8 Memasang Langit-langit Kalsiboard, Ukuran (120x240) tebal 3.5 mm m2 46,099.06

9 A.4.5.1.9 Memasang Langit-langit Akustik Uk (60x120) cm & Berikut Rangka Allumunium m2 267,602.50

10 A.4.5.1.10 List Langit-langit Kayu Profil m1 31,883.50


11 A.4.5.1.11 List Langit-langit Gypsum Profil m1 32,076.00
12 A.4.5.1.12 Pembongkaran 1 m2 langit - langit (plafon) m2 25,162.50
13 A.4.5.1.13 Memasang Langit-langit Tripleks, Ukuran (120x240) tebal 4 mm m2 52,497.50

DIVISI 4 A.4.5.2 HARGA SATUAN PEKERJAAN PENUTUP ATAP

1 A.4.5.2.1 Pemasangan Atap Genteng Plentong Kecil m2 83,762.25


2 A.4.5.2.2 Pemasangan Atap Genteng Kodok / Glazuur m2 179,377.00
3 A.4.5.2.3 Pemasangan1 m2 Atap Genteng Palentong Besar/Morando m2 72,787.00
4 A.4.5.2.4 Pemasangan 1 m’ Bubung Genteng Palentong Kecil m' 107,322.60
5 A.4.5.2.5 Pemasangan 1 m’ Bubung Genteng Kodok Glazuur m' 109,522.60
6 A.4.5.2.6 Pemasangan 1 m’ Bubung Genteng Palentong Besar m' 102,372.60
7 A.4.5.2.7 Pemasangan 1 m2 Roof Light Fibreglass 90cm x180cm m2 137,324.00

8 A.4.5.2.8 Pemasangan 1 m2 Atap Serat Semen Gelombang 92cm x 250cm x 5mm m2 84,836.40

9 A.4.5.2.9 Pemasangan 1 m2 Atap Serat Semen Gelombang 92cm x 225cm x 5mm m2 86,387.40

10 A.4.5.2.10 Pemasangan1 m2 Atap Serat Semen Gelombang 92cm x 200cm x 5mm m2 86,057.40

11 A.4.5.2.11 Pemasangan1 m2 Atap Serat Semen Gelombang 92cm x 180cm x 5mm m2 91,832.40

12 A.4.5.2.12 Pemasangan1 m2 Atap Serat Semen Gelombang 105cm x 300cm x 5 mm m2 61,499.90

13 A.4.5.2.13 Pemasangan1 m2 Atap Serat Semen Gelombang 105cm x 270cm x 4 mm m2 65,465.40

14 A.4.5.2.14 Pemasangan1 m2 Atap Serat Semen Gelombang 105cm x 240cm x 4 mm m2 55,213.40

15 A.4.5.2.15 Pemasangan 1 m2 Atap Serat Semen Gelombang 105cm x 240cm x 5mm m2 56,166.00

16 A.4.5.2.16 Pemasangan 1 m2 Atap Serat Semen Gelombang 105cm x 105cm x 4mm m2 65,993.40

17 A.4.5.2.17 Pemasangan 1 m2 Atap Serat Semen Gelombang 105cm x 210cm x 5mm m2 56,166.00

18 A.4.5.2.18 Pemasangan 1 m2 Atap Serat Semen Gelombang 105cm x 150cm x 5mm m2 65,993.40

19 A.4.5.2.19 Pemasangan 1 m2 Atap Serat Semen Gelombang 108cm x 300cm x 6mm m2 70,613.40

20 A.4.5.2.20 Pemasangan 1 m2 Atap Serat Semen Gelombang 108cm x 270cm x 6mm m2 66,785.40

21 A.4.5.2.21 Pemasangan 1 m2 Atap Serat Semen Gelombang 108cm x 240cm x 6mm m2 65,113.40

720096400.xlsx 451/56 hspk


HARGA SATUAN
NO. KODE URAIAN PEKERJAAN SAT PEKERJAAN
Rp
22 A.4.5.2.22 Pemasangan 1 m2 Atap Galvalum berpasir 0.5mm m2 276,072.50

26 A.4.5.2.32 Pemasangan 1 m2 Atap Genteng Beton m2 103,290.00


27 A.4.5.2.33 Pemasangan 1 m2 Atap Genteng Aspal 80x100 cm m2 216,766.00
28 A.4.5.2.34 Pemasangan 1 m2 Atap Genteng Metal m2 109,604.00
29 A.4.5.2.35 Pemasangan 1 m2 Atap Sirap Kayu m2 249,531.70
30 A.4.5.2.36 Pemasangan 1 m’ Nok/Bubung Genteng Beton m' 120,357.60
31 A.4.5.2.37 Pemasangan 1 m’ Nok/Bubung Genteng Aspal m' 224,731.38
32 A.4.5.2.38 Pemasangan 1 m’ Nok/Bubung Genteng Metal m' 99,506.00
33 A.4.5.2.39 Pemasangan 1 m’ Nok/Bubung Atap Sirap m' 56,512.50
34 A.4.5.2.40 Pemasangan 1 m2 Atap Seng Gelombang 105cm x180cm m2 44,407.00
35 A.4.5.2.41 Pemasangan 1 m’ Nok/Bubung Atap Seng m' 33,819.50
36 A.4.5.2.44 Pemasangan 1 m2 Lapisan Aluminium Foil m2 38,318.50
37 A.4.5.2.45 Pemasangan 1 m' nok atap asbes m' 22,698.50
40 A.4.5.2.48 Pembongkaran 1 m2 penutup atap termasuk kuda-kuda m2 60,390.00

DIVISI 4 A.4.6.1 HARGA SATUAN PEKERJAAN KAYU


Pembuatan dan Pemasangan 1 m3 Kusen Pintu dan Kusen Jendela. Kayu Kelas
1 A.4.6.1.1 m3 27,050,155.00
I
Pembuatan dan Pemasangan 1 m3 Kusen Pintu dan Kusen Jendela Kayu Kelas
2 A.4.6.1.2 m3 18,661,830.00
II atau III

3 A.4.6.1.3 Pembuatan dan Pemasangan 1 m2 Pintu Klamp Standar Kayu Kelas II m2 769,719.50

4 A.4.6.1.4 Pembuatan dan Pemasangan 1 m2 Pintu Klamp Sederhana Kayu Kelas III m2 769,719.50

5 A.4.6.1.5 Pembuatan 1 m2 Daun Pintu Panel. Kayu Kelas I atau II m2 1,045,121.00

6 A.4.6.1.6 Pembuatan 1 m2 Pintu dan Jendela Kaca. Kayu Kelas I atau II m2 717,767.60

7 A.4.6.1.7 Pembuatan 1 m2 Pintu dan Jendela Jalusi Kayu Kelas I atau II m2 1,833,130.20

Pembuatan 1 m2 Daun pintu Plywood Rangkap. Rangka Kayu Kelas II Tertutup


8 A.4.6.1.8 m2 812,776.25
(Lebar Sampai 90cm)

9 A.4.6.1.9 Pembuatan 1m2 Pintu Plywood Rangkap. Rangka Expose Kayu Kelas I atau II m2 864,457.44

10 A.4.6.1.10 Pembuatan dan Pemasangan 1 m2 Jalusi Kusen Kayu Kelas I atau II m2 1,628,599.50

11 A.4.6.1.11 Pembuatan 1 m2 Teakwood Rangkap. Rangka Expose Kayu Kelas I m2 1,009,332.50

Pembuatan 1 m2 Teakwood Rangkap Lapis Formika. Rangka Expose Kayu


12 A.4.6.1.12 m2 936,454.75
Kelas II

Pemasangan 1 m3 Konstruksi Kuda-kuda Konvensional. Kayu Kelas I.


13 A.4.6.1.13 m3 16,862,340.00
II dan III Bentang Sampai Dengan 6 Meter

14 A.4.6.1.14 Pemasangan 1 m3 Konstruksi Kuda-kuda Expose. Kayu Kelas I m3 29,495,152.50

15 A.4.6.1.15 Pemasangan 1 m3 Konstruksi Gordeng. Kayu kelas II m3 18,453,325.00

16 A.4.6.1.16 Pemasangan 1 m2 Rangka Atap Genteng Keramik. Kayu kelas II m2 261,676.14

17 A.4.6.1.17 Pemasangan 1 m2 Rangka Atap Genteng Beton Kayu Kelas II m2 309,885.18

18 A.4.6.1.18 Pemasangan 1 m2 Rangka Atap Sirap. Kayu Kelas II m2 216,464.60

19 A.4.6.1.19 Pemasangan 1 m2 Rangka Langit-Langit 50x100cm. Kayu kelas II atau III m2 264,830.06

20 A.4.6.1.20 Pemasangan 1 m2 Rangka Langit-Langit 60x60cm. Kayu Kelas II atau III m2 275,699.82

21 A.4.6.1.21 Pemasangan 1 m’ Lisplank Ukuran 3x20cm. Kayu Kelas I atau Kelas II m' 269,604.94

22 A.4.6.1.22 Pemasangan 1 m’ Lisplank Ukuran 3x30cm. Kayu Kelas I atau Kelas II m' 203,100.15

720096400.xlsx 451/57 hspk


HARGA SATUAN
NO. KODE URAIAN PEKERJAAN SAT PEKERJAAN
Rp
23 A.4.6.1.23 Pemasangan 1 m2 Rangka Dinding Pemisah 60x120cm Kayu kelas II atau III m2 441,877.70

24 A.4.6.1.24 Pemasangan 1 m2 Dinding Pemisah Teakwood Rangkap Rangka Kayu Klas II m2 526,093.70

25 A.4.6.1.25 Pemasangan 1 m2 Dinding Pemisah Plywood Rangkap Rangka Kayu Kelas II m2 530,994.20

26 A.4.6.1.26 Pemasangan 1 m2 Dinding Lambrisering dari Papan Kayu Kelas I m2 417,858.10

Pemasangan 1 m2 Dinding Lambrisering dari Plywood (Kayu Lapis) Ukuran


27 A.4.6.1.27 m2 45,160.50
120x240cm

28 A.4.6.1.28 Pemasangan 1 m2 Dinding Bilik. Rangka Kayu Kelas III atau IV m2 216,041.65

29 A.4.6.1.29 Pasang Kasau & Reng Kayu Bengkirai m2 192,278.90

30 A.4.6.1.30 Pasang Kasau & Reng Kayu Kruing m2 154,302.50

31 A.4.6.1.31 Pasang Papan Sirip m' 88,666.60

DIVISI 4 A.4.6.2 HARGA SATUAN PEKERJAAN KUNCI dan KACA

1 A.4.6.2.1 Pemasangan 1 Buah Kunci Tanam Antik bh 258,395.50


2 A.4.6.2.2 Pemasangan 1 Buah Kunci Tanam Biasa bh 211,139.50
3 A.4.6.2.3 Pemasangan 1 Buah Kunci Tanam Kamar Mandi bh 182,954.75
4 A.4.6.2.4 Pemasangan 1 Buah Kunci Tanam Silinder bh 209,904.75
5 A.4.6.2.5 Pemasangan 1 Buah Engsel Pintu bh 29,004.25
6 A.4.6.2.6 Pemasangan 1 Buah Engsel Jendela Kupu-Kupu bh 31,069.50
7 A.4.6.2.7 Pemasangan 1 Buah Engsel Angin bh 52,082.25
8 A.4.6.3.8 Pemasangan 1 Buah Spring Knip bh 85,761.50
9 A.4.6.2.9 Pemasangan 1 Buah Kait Angin bh 36,206.50
10 A.4.6.2.10 Pemasangan 1 Buah Doorcloser bh 831,916.25
11 A.4.6.2.11 Pemasangan 1 Buah Kunci Slot (Grendel) untuk Jendela bh 157,668.50
12 A.4.6.2.12 Pemasangan 1 Buah Door Holder bh 90,806.10
13 A.4.6.2.13 Pemasangan 1 Buah Doorstop bh 97,919.25
14 A.4.6.2.14 Pemasangan 1 Buah Rel Pintu Dorong bh 343,095.50
15 A.4.6.2.15 Pemasangan 1 Buah Kunci Lemari bh 44,053.35
16 A.4.6.2.16 Pemasangan 1 m2 Kaca Polos Tebal 3 mm m2 125,538.88
17 A.4.6.2.17 Pemasangan 1 m2 Kaca Polos Tebal 5 mm m2 160,628.88
18 A.4.6.2.18 Pemasangan 1 m2 Kaca Polos Tebal 8 mm m2 356,008.95
19 A.4.6.2.19 Pemasangan 1 m2 Kaca Buram Tebal 12 mm m2 459,563.50
20 A.4.6.2.20 Pemasangan 1 m2 Kaca Cermin Tebal 5mm m2 229,598.88

DIVISI 4 A.4.7.1 HARGA SATUAN PEKERJAAN PENGECATAN

1 A.4.7.1.1 Pengikisan / pengerokan 1 m2 Permukaan Cat Tembok Lama m2 15,218.50

2 A.4.7.1.2 Pencucian 1 m2 Bidang Permukaan Tembok yang Pernah dicat m2 15,862.00

3 A.4.7.1.3 Pengerokan 1 m2 Karat Cat Lama permukaan Baja dg cara manual m2 16,384.50

4 A.4.7.1.4 Pengecatan Bidang Kayu Baru (1 lp Plamuur, 1 lp Cat dasar, 2 Lp Cat Penutup) m2 45,224.30

5 A.4.7.1.5 Pengecatan Bidang Kayu Baru (1 lp Plamuur, 1 lp Cat dasar, 3 Lp Cat Penutup) m2 59,093.10

6 A.4.7.1.6 Pelaburan Bidang Kayu dg Teak Oil m2 35,354.00


7 A.4.7.1.7 Pelaburan 1 m2 Bidang Kayu dg Politur m2 88,504.90

720096400.xlsx 451/58 hspk


HARGA SATUAN
NO. KODE URAIAN PEKERJAAN SAT PEKERJAAN
Rp
8 A.4.7.1.8 Pelaburan 1 m2 Bidang Kayu dg Cat Residu & Ter m2 10,003.13
9 A.4.7.1.9 Pelaburan 1 m2 Bidang Kayu dg Vernis m2 49,472.50
Pengecat 1 m2 Tembok Baru (1lap.Plamir, 1lap Cat Dasar 2 Lap.Cat Penutup)
10 A.4.7.1.10 m2 28,263.16
Interior

11 A.4.7.1.11 Pengecat 1 m2 Tembok Baru (1lap Cat Dasar 2 Lap.Cat Penutup) - exterior m2 30,495.85

12 A.4.7.1.12 Pengecatan 1 m2 Tembok Lama (1lap. Cat dasar, 2lap Cat Penutup) interior m2 20,717.44

13 A.4.7.1.13 Pengecatan 1 m2 Tembok Lama (1lap.cat dasar, 2lap Cat Penutup) - exterior m2 25,157.00

14 A.4.7.1.14 Pelaburan 1 m2 Tembok dengan Kalkarium m2 8,239.00


15 A.4.7.1.15 Pelaburan 1 m2 Tembok dengan Kapur Sirih m2 17,244.70

16 A.4.7.1.16 Pelaburan 1 m2 Tembok lama dengan Kapur m2 10,279.50

17 A.4.7.1.17 Pemasangan Wallpaper m2 140,885.25

18 A.4.7.1.18 Pengecatan 1 m2 Permukaan Baja dg Meni Besi & Perancah m2 56,951.29

19 A.4.7.1.17 Pengecatan 1 m2 dengan cat kedap air (2 kali lapis) m2 137,659.50

Pengecatan 1 m2 Permukaan Baja Galvanis Secara Semprot Sistem 3 Lapis Cat


20 A.4.7.1.22 m2 116,875.00
Terakhir

DIVISI 5 A.5.1.1 HARGA SATUAN PEKERJAAN SANITASI DALAM GEDUNG

1 A.5.1.1.1 Pemasangan 1 Buah Closet Duduk/MoNoblock unit 2,178,797.50


2 A.5.1.1.2 Pemasangan 1 Buah Closet Jongkok Porselen unit 631,345.00
3 A.5.1.1.4 Pemasangan 1 Buah Urinoir unit 370,150.00
4 A.5.1.1.5 Pemasangan 1 Buah Wastafel unit 792,110.00
5 A.5.1.1.6 Pemasangan 1 Buah Bak Mandi Teraso Volume 0.30 m3 unit 1,298,550.00
6 A.5.1.1.7 Pemasangan 1 Buah Bak Fibreglass Volume 0.3 m3 unit 1,226,863.00
7 A.5.1.1.8 Pemasangan 1buah Bak Mandi Pasangan Bata Volume 0.30 m3 unit 1,832,510.12
8 A.5.1.1.11 Pemasangan Bak Beton Bertulang Vol. 1 m3 unit 7,784,604.05
9 A.5.1.1.12 Pemasangan Bak Cuci Piring Stainless stell bh 328,828.50
10 A.5.1.1.14 Pemasangan Floor Drain bh 56,369.50
Pemasangan 1 buah Bak Kontrol Pasangan Bata 30x30cm Tinggi 35cm dengan
11 A.5.1.1.16 bh 487,080.00
Tutup Beton
Pemasangan 1 buah Bak Kontrol Pasangan Bata 45cm x 45cm tinggi 50cm
12 A.5.1.1.17 bh 721,055.50
dengan Tutup Beton
Pemasangan 1 buah Bak Kontrol Pasangan Bata 60cm x 60cm Tinggi 65cm
13 A.5.1.1.18 bh 921,367.70
dengan Tutup Beton
14 A.5.1.1.19 Pemasangan 1 m’ Pipa Galvanis Diameter ½” m' 49,653.63
15 A.5.1.1.20 Pemasangan 1 m’ Pipa Galvanis Diameter ¾ ” bh 79,328.43
16 A.5.1.1.20.a Pemasangan Pipa Galvanis Ø ¾" m' 56,189.47
17 A.5.1.1.21 Pemasangan 1 m’ Pipa Galvanis Diameter 1” m' 71,534.47
18 A.5.1.1.22 Pemasangan 1 m’ Pipa Galvanis Diameter 1 ½” m' 108,110.93
19 A.5.1.1.23 Pemasangan 1 m’ Pipa Galvanis Diameter 3” m' 222,579.50
20 A.5.1.1.24 Pemasangan 1 m’ Pipa Galvanis Diameter 4” m' 351,875.33
21 A.5.1.1.25 Pemasangan 1 m’ Pipa PVC tipe AW Diameter ½” m' 21,745.08
22 A.5.1.1.26 Pemasangan 1 m’ Pipa PVC tipe AW Diameter ¾ ” m' 25,027.20
23 A.5.1.1.27 Pemasangan 1 m’ Pipa PVC tipe AW Diameter 1” m' 33,680.08
24 A.5.1.1.28 Pemasangan 1 m’ Pipa PVC tipe AW Diameter 1½” m' 48,282.30
25 A.5.1.1.29 Pemasangan 1 m’ Pipa PVC tipe AW Diameter 2” m' 58,086.05
26 A.5.1.1.30 Pemasangan 1 m’ Pipa PVC tipe AW Diameter 2½” m' 86,437.45
27 A.5.1.1.31 Pemasangan 1 m’ Pipa PVC tipe AW Diameter 3” m' 106,897.45

720096400.xlsx 451/59 hspk


HARGA SATUAN
NO. KODE URAIAN PEKERJAAN SAT PEKERJAAN
Rp
28 A.5.1.1.32 Pemasangan 1 m’ Pipa PVC tipe AW Diameter 4” m' 134,488.20
29 A.5.1.1.33 Pemasangan 1 m’ Pipa PVC tipe D Diameter 2” m' 44,842.46
30 A.5.1.1.34 Pemasangan 1 m’ Pipa PVC tipe D Diameter 2 ½” m' 63,189.78
31 A.5.1.1.35 Pemasangan 1 m’ Pipa PVC tipe D Diameter 3” m' 76,201.06
32 A.5.1.1.36 Pemasangan 1 m’ Pipa PVC tipe D Diameter 4” m' 106,718.43

33 A.5.1.1.37 Pemasangan 1 m’ Pipa Air Limbah Jenis Pipa Tanah Ǿ 20 cm m' 437,142.20

34 A.5.1.1.38 Pemasangan 1 m’ Pipa Air Limbah Jenis Pipa Tanah diameter 15 cm m' 203,153.50

35 A.5.1.1.39 Pemasangan 1 m’ Pipa Beton Diameter 15 – 20 cm m' 195,339.54


36 A.5.1.1.40 Pemasangan 1 m’ Pipa Beton Diameter 30 – 100 cm m' 639,780.90
37 A.5.1.1.41 Pemasangan 1 m’ Pipa PVC type D diameter 5" m' 152,612.76
38 A.5.1.1.42 Pemasangan 1 m’ Pipa PVC type D diameter 6" m' 195,195.14
39 A.5.1.1.43 Pemasangan 1 m’ Pipa PVC type D diameter 8" m' 322,942.26
40 A.5.1.1.44 Pemasangan 1 m’ Pipa PVC type D diameter 10" m' 519,294.33
41 A.5.1.1.45 Pemasangan 1 m’ Pipa PVC type D diameter 12" m' 718,012.08
42 A.5.1.1.46 Pemasangan 1 buah kran diameter ½" atau ¾" buah 79,543.75
43 A.5.1.1.47 Pemasangan 1 m' pipa galvanis diameter 2½" m' 153,861.77
44 A.5.1.1.48 Pemasangan 1 buah tandon air fiberglass vol 650 liter buah 1,623,177.60
45 A.5.1.1.49 Pemasangan 1 buah tandon air fiberglass vol 1050 liter buah 2,279,587.20
47 A.5.1.1.51 Pemasangan 1 buah tandon air fiberglass vol 1500 liter buah 3,298,389.60
48 A.5.1.1.52 Pemasangan 1 buah tandon air fiberglass vol 2000 liter buah 4,809,499.20

HARGA SATUAN PEKERJAAN SISTEM DISTRIBUSI JARINGAN


DIVISI 6 A.6.1.1
LISTRIK
1 A.6.1.1.1 Pemasangan 1 buah MCCB Buah 462,000.00
2 A.6.1.1.2 Pemasangan 1 buah Stopkontak Buah 316,470.00
3 A.6.1.1.3 Pemasangan 1 buah led monitor 55", smart tv Buah 9,495,447.50
4 A.6.1.1.4 Pemasangan 1 titik instalasi cctv Titik 533,049.00
5 A.6.1.1.5 Pemasangan 1 buah NVR 16 chanel Buah 26,744,547.50
6 A.6.1.1.6 Pemasangan 1 buah Indoor Dome Camera With Varifocal Lens 3-10mm, infared, 10 Buah 14,923,507.50
7 A.6.1.1.7 Pemasangan 1 buah Bullet 2MP HDR 3.2-10mm ip66 ik10 ir Buah 19,736,007.50
8 A.6.1.1.8 Pemasangan 1 buah hub 8 port Buah 3,571,188.50
9 A.6.1.1.9 Pemasangan 1 buah 19" Wallmount 6U-45mm Buah 5,001,188.50
10 A.6.1.1.10 Pemasangan 1 buah amunicator Buah 12,164,267.50

DIVISI 6 A.6.2.1 HARGA SATUAN PEKERJAAN SISTEM PENCAHAYAAN

1 A.6.2.1.1 Pemasangan 1 Buah Titik Lampu Buah 510,950.00


2 A.6.2.1.2 Pemasangan 1 buah lampu RD 150 E27 LEDBULB 6W Buah 77,643.50
3 A.6.2.1.3 Pemasangan 1 buah lampu RD 150 E27 LEDBULB 10W Buah 93,043.50
4 A.6.2.1.4 Pemasangan 1 buah lampu RD 150 E27 LEDBULB 12W Buah 108,443.50
5 A.6.2.1.5 Pemasangan 1 buah lampu THEME 150 E27 LEDBULB 10W Buah 310,843.50
6 A.6.2.1.6 Pemasangan 1 buah lampu THEME 150 E27 LEDBULB 10+BATERAI Buah 1,425,143.50
7 A.6.2.1.7 Pemasangan 1 buah lampu THEME 150 E27 LEDBULB 14,5W Buah 357,043.50
8 A.6.2.1.8 Pemasangan 1 buah lampu THEME 150 E27 LEDBULB 14,5+BATERAI Buah 1,471,343.50
9 A.6.2.1.9 Pemasangan 1 buah BL CG TL LED 1X14,5 W Buah 483,543.50
10 A.6.2.1.10 Pemasangan 1 buah BL CG TL LED 1X14,5 W + BATERAI Buah 1,447,143.50

720096400.xlsx 451/60 hspk


HARGA SATUAN
NO. KODE URAIAN PEKERJAAN SAT PEKERJAAN
Rp
11 A.6.2.1.11 Pemasangan 1 buah BL CG TL LED 2X14,5 W Buah 798,143.50
12 A.6.2.1.12 Pemasangan 1 buah RM M4 2XTL LED MASTER 18 W Buah 744,243.50
14 A.6.2.1.14 Pemasangan 1 buah EXIT LED Buah 296,543.50
23 A.6.2.1.23 Pemasangan 1 buah stop kontak 16A, 1ph, umum(wall type) Buah 23,417.90
24 A.6.2.1.24 Pemasangan 1 buah stop kontak 16A, 1ph, tipe lantai Buah 949,617.90
26 A.6.2.1.26 Pemasangan 1 m' tray cable uk 200mm x 100mm m' 117,606.50
27 A.6.2.1.27 Pemasangan 1 m' tray cable uk 300mm x 100mm m' 123,106.50
28 A.6.2.1.28 Pemasangan 1 m' tray cable uk 400mm x 100mm m' 129,838.50
29 A.6.2.1.29 Pemasangan 1 m' cable ladder uk 400mm x 100mm m' 126,318.50
30 A.6.2.1.30 Pemasangan 1 m' cable ladder uk 200mm x 100mm m' 122,446.50
31 A.6.2.1.31 Pemasangan 1 m' cable ladder uk 300mm x 100mm m' 122,666.50
32 A.6.2.1.32 Pemasangan 1 titik instalasi exhaust fan titik 368,984.00
33 A.6.2.1.33 Pemasangan 1 titik stopkontak lantai titik 408,914.00
34 A.6.2.1.34 Pemasangan 1 titik stopkontak AC titik 738,474.00
35 A.6.2.1.35 Pemasangan 1 m' kabel NYY 3 X 16 mm m' 76,569.90
36 A.6.2.1.36 Pemasangan 1 m' kabel NYY 4 X 4 mm m' 76,569.90
37 A.6.2.1.37 Pemasangan 1 m' kabel NYY 4 X 6 mm m' 76,569.90
38 A.6.2.1.38 Pemasangan 1 m' kabel NYY 4 X 10 mm m' 57,334.75
39 A.6.2.1.39 Pemasangan 1 m' kabel NYY 4 X 16 mm m' 57,334.75
40 A.6.2.1.40 Pemasangan 1 m' kabel NYY 4 X 25 mm m' 57,334.75
41 A.6.2.1.41 Pemasangan 1 m' kabel NYY 4 X 35 mm m' 57,334.75
42 A.6.2.1.42 Pemasangan 1 m' kabel NYY 4 X 50 mm m' 57,334.75
43 A.6.2.1.43 Pemasangan 1 m' kabel NYY 4 X 70 mm m' 76,389.50
44 A.6.2.1.44 Pemasangan 1 m' kabel NYY 4 X 95 mm m' 76,389.50
45 A.6.2.1.45 Pemasangan 1 m' kabel NYY 4 X 120 mm m' 76,389.50
46 A.6.2.1.46 Pemasangan 1 m' kabel NYY 4 X 150 mm m' 76,389.50
47 A.6.2.1.47 Pemasangan 1 m' kabel NYY 4 X 185 mm m' 76,389.50
48 A.6.2.1.48 Pemasangan 1 m' kabel NYY 1c X 120 mm m' 61,897.00
49 A.6.2.1.49 Pemasangan 1 m' kabel NYY 1c X 150 mm m' 61,897.00
50 A.6.2.1.50 Pemasangan 1 m' kabel NYY 1c X 185 mm m' 61,897.00
51 A.6.2.1.51 Pemasangan 1 m' kabel NYY 1c X 240 mm m' 61,897.00
52 A.6.2.1.52 Pemasangan 1 m' kabel NYY 1c X 300 mm m' 61,897.00
53 A.6.2.1.53 Pemasangan 1 buah penangkal petir elektro statis radius 135 meter Buah 7,501,417.00

DIVISI 7 A.7.1.1 HARGA SATUAN PEKERJAAN SANITASI DI LUAR GEDUNG


1 A.7.1.1.1 Pemasangan 1 m' pipa HDPE Ø63 mm m' 60,153.50
2 A.7.1.1.2 Pemasangan 1 m’ pipa HDPE Ø100 mm m' 118,462.30
3 A.7.1.1.3 Pemasangan 1 m’ pipa HDPE Ø 125 mm m' 191,108.50
4 A.7.1.1.4 Pemasangan 1 m' pipa HDPE Ø 150 mm m' 361,508.40
5 A.7.1.1.5 Pemasangan 1 m’ pipa HDPE Ø 200 mm m' 564,964.40
6 A.7.1.1.6 Pemasangan 1 m’ pipa HDPE Ø 250 mm m' 887,338.10
7 A.7.1.1.7 Pemasangan 1 m’ pipa HDPE Ø 300 mm m' 1,406,575.50
8 A.7.1.1.8 Pemasangan 1 m’ pipa HDPE Ø 400 mm m' 2,157,743.50
9 A.7.1.1.9 Pemasangan 1 m’ pipa HDPE Ø 450 mm m' 2,907,121.80
10 A.7.1.1.10 Pemasangan 1 m’ pipa HDPE Ø 500 mm m' 3,518,384.10
11 A.7.1.1.11 Pemasangan 1 m’ pipa HDPE Ø 600 mm m' 5,503,925.90

720096400.xlsx 451/61 hspk


HARGA SATUAN
NO. KODE URAIAN PEKERJAAN SAT PEKERJAAN
Rp
12 A.7.1.1.12 Pemasangan 1 m’ pipa HDPE Ø 800 mm m' 8,802,773.10
13 A.7.1.1.13 Pemasangan 1 m’ pipa HDPE Ø 900 mm m' 10,137,271.10
14 A.7.1.1.14 Pemasangan 1 m’ pipa HDPE Ø 1000 mm m' 11,385,558.80
15 A.7.1.1.15 Pemasangan 1 m’ pipa HDPE Ø 1100 mm m' 12,886,693.60
16 A.7.1.1.16 Pemasangan 1 m’ pipa HDPE Ø 1200 mm m' 14,468,855.50
17 A.7.1.1.17 Pemasangan 1 m' pipa air limbah Ø4" m' 198,767.25
18 A.7.1.1.18 Pemasangan 1 m' pipa air limbah Ø6" m' 365,690.16
19 A.7.1.1.19 Pemasangan 1 m' pipa air limbah Ø8" m' 547,692.09
20 A.7.1.1.20 Pemasangan bak kontrol Precast Ø 30 cm bh 402,297.50
21 A.7.1.1.21 Pemasangan bak kontrol Precast Ø 40 cm bh 598,317.50
22 A.7.1.1.22 Pemasangan bak kontrol Precast Ø 60 cm bh 925,017.50
23 A.7.1.1.23 Pemasangan bak kontrol Precast Ø 32 cm (penangkap lemak/greascetrap) bh 402,297.50
24 A.7.1.1.24 Pemasangan Leher Angsa Precast bh 204,792.50

DIVISI 7 A.7.1.2 HARGA SATUAN PEKERJAAN ASESORIS PIPA


1 A.7.1.2.1 Pemasangan 1 buah Pipa Fiting PVC - ELBOW (D-DL) 1 1/4" bh 9,229.00
2 A.7.1.2.2 Pemasangan 1 buah Pipa Fiting PVC - ELBOW (D-DL) 1 1/2" bh 14,069.00
3 A.7.1.2.3 Pemasangan 1 buah Pipa Fiting PVC - ELBOW (D-DL) 2" bh 19,129.00
4 A.7.1.2.4 Pemasangan 1 buah Pipa Fiting PVC - ELBOW (D-DL) 2 1/2" bh 20,449.00
5 A.7.1.2.5 Pemasangan 1 buah Pipa Fiting PVC - ELBOW (D-DL) 3" bh 27,929.00
6 A.7.1.2.6 Pemasangan 1 buah Pipa Fiting PVC - ELBOW (D-DL) 4" bh 44,979.00
7 A.7.1.2.7 Pemasangan 1 buah Pipa Fiting PVC - ELBOW (D-DL) 5" bh 99,979.00
8 A.7.1.2.8 Pemasangan 1 buah Pipa Fiting PVC - ELBOW (D-DL) 6" bh 104,929.00
9 A.7.1.2.9 Pemasangan 1 buah Pipa Fiting PVC - ELBOW (D-DL) 8" bh 256,729.00
10 A.7.1.2.10 Pemasangan 1 buah Pipa Fiting PVC - ELBOW (D-DL) 10" bh 490,479.00
11 A.7.1.2.11 Pemasangan 1 buah Pipa Fiting PVC - ELBOW (D-DL) 12" bh 667,029.00
12 A.7.1.2.12 Pemasangan 1 buah Pipa Fiting PVC - SOCKET (D-DS) 1 1/4" bh 11,429.00
13 A.7.1.2.13 Pemasangan 1 buah Pipa Fiting PVC - SOCKET (D-DS) 1 1/2" bh 13,629.00
14 A.7.1.2.14 Pemasangan 1 buah Pipa Fiting PVC - SOCKET (D-DS) 2" bh 16,489.00
15 A.7.1.2.15 Pemasangan 1 buah Pipa Fiting PVC - SOCKET (D-DS) 2 1/2" bh 10,329.00
16 A.7.1.2.16 Pemasangan 1 buah Pipa Fiting PVC - SOCKET (D-DS) 3" bh 26,279.00
17 A.7.1.2.17 Pemasangan 1 buah Pipa Fiting PVC - SOCKET (D-DS) 4" bh 41,129.00
18 A.7.1.2.18 Pemasangan 1 buah Pipa Fiting PVC - SOCKET (D-DS) 5" bh 54,329.00
19 A.7.1.2.19 Pemasangan 1 buah Pipa Fiting PVC - SOCKET (D-DS) 6" bh 60,929.00
20 A.7.1.2.20 Pemasangan 1 buah Pipa Fiting PVC - SOCKET (D-DS) 8" bh 128,029.00
21 A.7.1.2.21 Pemasangan 1 buah Pipa Fiting PVC - SOCKET (D-DS) 10" bh 192,929.00
22 A.7.1.2.22 Pemasangan 1 buah Pipa Fiting PVC - TEE (D-DT) 1 1/4" bh 10,329.00
23 A.7.1.2.23 Pemasangan 1 buah Pipa Fiting PVC - TEE (D-DT) 1 1/2" bh 19,899.00
24 A.7.1.2.24 Pemasangan 1 buah Pipa Fiting PVC - TEE (D-DT) 2" bh 25,179.00
25 A.7.1.2.25 Pemasangan 1 buah Pipa Fiting PVC - TEE (D-DT) 2 1/2" bh 26,829.00
26 A.7.1.2.26 Pemasangan 1 buah Pipa Fiting PVC - TEE (D-DT) 3" x 1 1/2" bh 16,929.00
27 A.7.1.2.27 Pemasangan 1 buah Pipa Fiting PVC - TEE (D-DT) 3" x 2" bh 38,929.00
28 A.7.1.2.28 Pemasangan 1 buah Pipa Fiting PVC - TEE (D-DT) 3" 2 1/2" bh 20,229.00
29 A.7.1.2.29 Pemasangan 1 buah Pipa Fiting PVC - TEE (D-DT) 3" bh 48,829.00
30 A.7.1.2.30 Pemasangan 1 buah Pipa Fiting PVC - TEE (D-DT) 4" x 2" bh 27,379.00
31 A.7.1.2.31 Pemasangan 1 buah Pipa Fiting PVC - TEE (D-DT) 4" x 3" bh 32,329.00
32 A.7.1.2.32 Pemasangan 1 buah Pipa Fiting PVC - TEE (D-DT) 4" bh 81,279.00

720096400.xlsx 451/62 hspk


HARGA SATUAN
NO. KODE URAIAN PEKERJAAN SAT PEKERJAAN
Rp
33 A.7.1.2.33 Pemasangan 1 buah Pipa Fiting PVC - TEE (D-DT) 5" x 4" bh 48,829.00
34 A.7.1.2.34 Pemasangan 1 buah Pipa Fiting PVC - TEE (D-DT) 5" bh 53,229.00
35 A.7.1.2.35 Pemasangan 1 buah Pipa Fiting PVC - TEE (D-DT) 6" x 4" bh 68,629.00
36 A.7.1.2.36 Pemasangan 1 buah Pipa Fiting PVC - TEE (D-DT) 6" bh 219,329.00
37 A.7.1.2.37 Pemasangan 1 buah Pipa Fiting PVC - TEE (D-DT) 8" x 4" bh 91,729.00
38 A.7.1.2.38 Pemasangan 1 buah Pipa Fiting PVC - TEE (D-DT) 8" bh 298,529.00
39 A.7.1.2.39 Pemasangan 1 buah Pipa Fiting PVC - INCREASER (D-IN) 1 1/2" X 1 1/4" bh 9,229.00
40 A.7.1.2.40 Pemasangan 1 buah Pipa Fiting PVC - INCREASER (D-IN) 2" X 1 1/4" bh 11,429.00
41 A.7.1.2.41 Pemasangan 1 buah Pipa Fiting PVC - INCREASER (D-IN) 2" X 1 1/2" bh 12,529.00
42 A.7.1.2.42 Pemasangan 1 buah Pipa Fiting PVC - INCREASER (D-IN) 2 1/2" X 1 1/2" bh 13,629.00
43 A.7.1.2.43 Pemasangan 1 buah Pipa Fiting PVC - INCREASER (D-IN) 2 1/2" X 2" bh 14,729.00
44 A.7.1.2.44 Pemasangan 1 buah Pipa Fiting PVC - INCREASER (D-IN) 3" X 1 1/2" bh 15,829.00
45 A.7.1.2.45 Pemasangan 1 buah Pipa Fiting PVC - INCREASER (D-IN) 3" X 2" bh 18,029.00
46 A.7.1.2.46 Pemasangan 1 buah Pipa Fiting PVC - INCREASER (D-IN) 3" X 2 1/2" bh 24,409.00
47 A.7.1.2.47 Pemasangan 1 buah Pipa Fiting PVC - INCREASER (D-IN) 4" X 2" bh 31,669.00
48 A.7.1.2.48 Pemasangan 1 buah Pipa Fiting PVC - INCREASER (D-IN) 4" X 2 1/2" bh 29,029.00
49 A.7.1.2.49 Pemasangan 1 buah Pipa Fiting PVC - INCREASER (D-IN) 4" X 3" bh 31,229.00
50 A.7.1.2.50 Pemasangan 1 buah Pipa Fiting PVC - INCREASER (D-IN) 5" X 4" bh 56,529.00
51 A.7.1.2.51 Pemasangan 1 buah Pipa Fiting PVC - INCREASER (D-IN) 6" X 3" bh 75,229.00
52 A.7.1.2.52 Pemasangan 1 buah Pipa Fiting PVC - INCREASER (D-IN) 6" X 4" bh 92,829.00
53 A.7.1.2.53 Pemasangan 1 buah Pipa Fiting PVC - INCREASER (D-IN) 6" X 5" bh 89,529.00
54 A.7.1.2.54 Pemasangan 1 buah Pipa Fiting PVC - INCREASER (D-IN) 8" X 4" bh 130,779.00
55 A.7.1.2.55 Pemasangan 1 buah Pipa Fiting PVC - INCREASER (D-IN) 8" X 6" bh 145,299.00
56 A.7.1.2.56 Pemasangan 1 buah Pipa Fiting PVC - CAP (D) 1 1/4" bh 9,229.00
57 A.7.1.2.57 Pemasangan 1 buah Pipa Fiting PVC - CAP (D) 1 1/2" bh 13,629.00
58 A.7.1.2.58 Pemasangan 1 buah Pipa Fiting PVC - CAP (D) 2" bh 14,729.00
59 A.7.1.2.59 Pemasangan 1 buah Pipa Fiting PVC - CAP (D) 3" bh 19,899.00
60 A.7.1.2.60 Pemasangan 1 buah Pipa Fiting PVC - CAP (D) 4" bh 32,329.00
61 A.7.1.2.61 Pemasangan 1 buah Fiting PVC - SOCKET (AW) 1/2" bh 8,679.00
62 A.7.1.2.62 Pemasangan 1 buah Fiting PVC - SOCKET (AW) 3/4" bh 9,449.00
63 A.7.1.2.63 Pemasangan 1 buah Fiting PVC - SOCKET (AW) 1" bh 11,209.00
64 A.7.1.2.64 Pemasangan 1 buah Fiting PVC - SOCKET (AW) 1 1/4" bh 12,749.00
65 A.7.1.2.65 Pemasangan 1 buah Fiting PVC - SOCKET (AW) 1 1/2" bh 14,729.00
66 A.7.1.2.66 Pemasangan 1 buah Fiting PVC - SOCKET (AW) 2" bh 14,729.00
67 A.7.1.2.67 Pemasangan 1 buah Fiting PVC - SOCKET (AW) 2 1/2" bh 29,029.00
68 A.7.1.2.68 Pemasangan 1 buah Fiting PVC - SOCKET (AW) 3" bh 52,129.00
69 A.7.1.2.69 Pemasangan 1 buah Fiting PVC - SOCKET (AW) 4" bh 81,279.00
70 A.7.1.2.70 Pemasangan 1 buah Fiting PVC - SOCKET (AW) 6" bh 133,529.00
71 A.7.1.2.71 Pemasangan 1 buah Fiting PVC - SOCKET (AW) 8" bh 278,729.00
72 A.7.1.2.72 Pemasangan 1 buah Fiting PVC - SOCKET (AW) 10" bh 399,729.00
73 A.7.1.2.73 Pemasangan 1 buah Fiting PVC - VALVE SOCKET (AW) 1/2" bh 8,129.00
74 A.7.1.2.74 Pemasangan 1 buah Fiting PVC - VALVE SOCKET (AW) 1/2" X 3/4" bh 8,129.00
75 A.7.1.2.75 Pemasangan 1 buah Fiting PVC - VALVE SOCKET (AW) 3/4" bh 9,229.00
76 A.7.1.2.76 Pemasangan 1 buah Fiting PVC - VALVE SOCKET (AW) 1" x 1/2" bh 9,229.00
77 A.7.1.2.77 Pemasangan 1 buah Fiting PVC - VALVE SOCKET (AW) 1" x 3/4" bh 10,329.00
78 A.7.1.2.78 Pemasangan 1 buah Fiting PVC - VALVE SOCKET (AW) 1" bh 11,429.00
79 A.7.1.2.79 Pemasangan 1 buah Fiting PVC - VALVE SOCKET (AW) 1 1/4" bh 9,449.00
80 A.7.1.2.80 Pemasangan 1 buah Fiting PVC - VALVE SOCKET (AW) 1 1/2" bh 16,379.00

720096400.xlsx 451/63 hspk


HARGA SATUAN
NO. KODE URAIAN PEKERJAAN SAT PEKERJAAN
Rp
81 A.7.1.2.81 Pemasangan 1 buah Fiting PVC - VALVE SOCKET (AW) 2" bh 19,129.00
82 A.7.1.2.82 Pemasangan 1 buah Fiting PVC - VALVE SOCKET (AW) 3" bh 46,629.00
83 A.7.1.2.83 Pemasangan 1 buah Fiting PVC - VALVE SOCKET (AW) 4" bh 60,049.00
84 A.7.1.2.84 Pemasangan 1 buah Fiting PVC - FAUCET SOCKET (AW) 1/2" bh 9,229.00
85 A.7.1.2.85 Pemasangan 1 buah Fiting PVC - FAUCET SOCKET (AW) 1/2" x 3/4" bh 9,229.00
86 A.7.1.2.86 Pemasangan 1 buah Fiting PVC - FAUCET SOCKET (AW) 3/4" bh 9,229.00
87 A.7.1.2.87 Pemasangan 1 buah Fiting PVC - FAUCET SOCKET (AW) 1" x 1/2" bh 11,429.00
88 A.7.1.2.88 Pemasangan 1 buah Fiting PVC - FAUCET SOCKET (AW) 1" x 3/4" bh 11,979.00
89 A.7.1.2.89 Pemasangan 1 buah Fiting PVC - FAUCET SOCKET (AW) 1" bh 11,979.00
90 A.7.1.2.90 Pemasangan 1 buah Fiting PVC - FAUCET SOCKET (AW) 1 1/4" bh 13,629.00
91 A.7.1.2.91 Pemasangan 1 buah Fiting PVC - FAUCET SOCKET (AW) 1 1/2" bh 9,229.00
92 A.7.1.2.92 Pemasangan 1 buah Fiting PVC - FAUCET SOCKET (AW) 2" bh 16,929.00
93 A.7.1.2.93 Pemasangan 1 buah Fiting PVC - TEE (AW) 1/2" bh 10,329.00
94 A.7.1.2.94 Pemasangan 1 buah Fiting PVC - TEE (AW) 3/4" x 1/2" bh 10,329.00
95 A.7.1.2.95 Pemasangan 1 buah Fiting PVC - TEE (AW) 3/4" bh 10,329.00
96 A.7.1.2.96 Pemasangan 1 buah Fiting PVC - TEE (AW) 1" x 1/2" bh 12,309.00
97 A.7.1.2.97 Pemasangan 1 buah Fiting PVC - TEE (AW) 1" x 3/4" bh 13,189.00
98 A.7.1.2.98 Pemasangan 1 buah Fiting PVC - TEE (AW) 1" bh 13,849.00
99 A.7.1.2.99 Pemasangan 1 buah Fiting PVC - TEE (AW) 1 1/4" x 1/2" bh 16,269.00
100 A.7.1.2.100 Pemasangan 1 buah Fiting PVC - TEE (AW) 1 1/4" x 3/4" bh 16,929.00
101 A.7.1.2.101 Pemasangan 1 buah Fiting PVC - TEE (AW) 1 1/4" x 1" bh 18,029.00
102 A.7.1.2.102 Pemasangan 1 buah Fiting PVC - TEE (AW) 1 1/4" bh 18,689.00
103 A.7.1.2.103 Pemasangan 1 buah Fiting PVC - TEE (AW) 1 1/2" x 1/2" bh 20,229.00
104 A.7.1.2.104 Pemasangan 1 buah Fiting PVC - TEE (AW) 1 1/2" x 3/4" bh 20,229.00
105 A.7.1.2.105 Pemasangan 1 buah Fiting PVC - TEE (AW) 1 1/2" x 1" bh 20,229.00
106 A.7.1.2.106 Pemasangan 1 buah Fiting PVC - TEE (AW) 1 1/2" x 1 1/4" bh 23,529.00
107 A.7.1.2.107 Pemasangan 1 buah Fiting PVC - TEE (AW) 1 1/2" bh 22,429.00
108 A.7.1.2.108 Pemasangan 1 buah Fiting PVC - TEE (AW) 2" x 1/2" bh 24,079.00
109 A.7.1.2.109 Pemasangan 1 buah Fiting PVC - TEE (AW) 2" x 3/4" bh 23,529.00
110 A.7.1.2.110 Pemasangan 1 buah Fiting PVC - TEE (AW) 2" x 1" bh 23,529.00
111 A.7.1.2.111 Pemasangan 1 buah Fiting PVC - TEE (AW) 2" x 1 1/4" bh 34,529.00
112 A.7.1.2.112 Pemasangan 1 buah Fiting PVC - TEE (AW) 2" x 1 1/2" bh 29,029.00
113 A.7.1.2.113 Pemasangan 1 buah Fiting PVC - TEE (AW) 2" bh 29,029.00
114 A.7.1.2.114 Pemasangan 1 buah Fiting PVC - TEE (AW) 2 1/2" bh 44,429.00
115 A.7.1.2.115 Pemasangan 1 buah Fiting PVC - TEE (AW) 3" x 2" bh 51,029.00
116 A.7.1.2.116 Pemasangan 1 buah Fiting PVC - TEE (AW) 3" bh 63,129.00
117 A.7.1.2.117 Pemasangan 1 buah Fiting PVC - TEE (AW) 4" bh 112,629.00
118 A.7.1.2.118 Pemasangan 1 buah Fiting PVC - TEE (AW) 6" bh 289,729.00
119 A.7.1.2.119 Pemasangan 1 buah Fiting PVC - TEE (AW) 8" bh 571,329.00

720096400.xlsx 451/64 hspk


HARGA SATUAN
NO. KODE URAIAN PEKERJAAN SAT PEKERJAAN
Rp
DIVISI 8 A.8.1.1 HARGA SATUAN PEKERJAAN LAIN - LAIN
1 A.8.1.1.1 Pemasangan 1 m' Pagar Kawat Duri Tinngi m m' 49,237.38
2 A.8.1.1.2 Pemasangan 1 m' Pagar beton Pracetak (240x40x5) cm K.225 m' 514,337.73
3 A.8.1.1.3 Pemasangan 1 m2 Roster R1 m2 901,692.00
4 A.8.1.1.4 Pemasangan 1 buah pompa Jet Pump buah 2,056,312.50
5 A.8.1.1.5 Pemasangan 1 buah pompa Submersible Grounfosh SP 5A-17 buah 27,535,612.50
6 A.8.1.1.6 Pemasangan 1 buah pompa Submersible Grounfosh SP 5A-25 buah 44,035,612.50
7 A.8.1.1.7 Pemasangan 1 buah pompa Grounfosh Sp 5A-52/5,5 kw/380 V/1,5" (210m) buah 131,804,612.50
8 A.8.1.1.8 Pemasangan 1 buah pompa Grounfosh Sp 9A - 36/7,5 kw/380 V/2" (200 m) buah 124,445,612.50
9 A.8.1.1.9 Pemasangan 1 buah pompa Grounfosh Sp 9A - 56/11 kw/380 V/2" (300 m) buah 278,214,612.50
10 A.8.1.1.10 Pemasangan 1 buah pompa Grounfosh Sp 9A - 75/15 kw/380 V/2" (400 m) buah 351,419,612.50
11 A.8.1.1.11 Pemasangan 1 buah pompa Grounfosh N5 4 - 23 M/1"/175 watt buah 3,842,712.50
12 A.8.1.1.12 Pemasangan 1 buah pompa Grounfosh N5 13 - 18 M/1,5"/400 watt buah 5,160,512.50

720096400.xlsx 451/65 hspk


REKAPITULASI BQ

KEGIATAN : PEMBANGUNAN
PEKERJAAN : RUMAH TINGGAL 2 LANTAI
LOKASI : KEBUMEN
KABUPATEN : KEBUMEN
TAHUN ANGGARAN : 2023

NO JENIS PEKERJAAN JUMLAH TOTAL (Rp.)

I PEKERJAAN PERSIAPAN Rp 15,295,005.62


II PEKERJAAN TANAH Rp 6,642,325.80
III PEKERJAAN PONDASI Rp 41,524,211.32
IV PEKERJAAN BETON Rp 326,380,080.80
V PEKERJAAN DINDING DAN PLESTERAN Rp 116,646,722.70
VI PEKERJAAN KUSEN PINTU DAN JENDELA Rp 27,670,339.99
VII PEKERJAAN ATAP Rp 70,684,032.22
VIII PEKERJAAN PLAFOND Rp 28,862,030.51
IX PEKERJAAN KERAMIK Rp 68,184,139.89
X PEKERJAAN PENGECATAN Rp 13,593,420.21
XI PEKERJAAN LISTRIK Rp 71,368,489.50
XII PEKERJAAN SANTITASI 14,633,729.00
XIII PEKERJAAN LAIN - LAIN Rp 16,644,737.75
JUMLAH KONSTRUKSI Rp 818,129,265.29
JUMLAH Rp 818,129,265.29
PPN 10% Rp 81,812,926.53
JUMLAH TOTAL Rp 899,942,191.82
Dibuklatkan Rp 899,942,000.00
RINCIAN PERHITUNGAN VOLUME PEKERJAAN
Sub Pekerjaan :
Item Pekerjaan :
Satuan :
SKET GAMBAR URAIAN PERHITUNGAN

Pembersihan Lokasi Pekerjaan


= 10.00 m x 20.00 m = 200.00 m2

B B Pengukuran & Pemasangan Bouwplank


1 2 3 4 1 2 3 4 = 10.00 m + 20.00 m + 10.00 m + 20.00 m
850 850
150 400 300 150 400 300

T.JEMUR
Pembuatan 1 buah kotak adukan ukuran 40cm x50cm x25cm (Koefisien usuk sesuai analisa SNI - A.6.10)
300

300

300

300
TAMAN -0.15
-0.15

A
100

A
= 0.40 m x 0.50 m x 2.00 m 0.40 m2
TERAS T.SHOLAT BALKON
250

250

250
-0.05 +0.15 +3.48

B K.TIDUR B
350

NAIK +3.50

DAPUR
R.SANTAI
300

300

325
R.MAKAN ±0.00
+3.50
±0.00

A A A A
1800

1800

1800

1800
KM/WC
150

150

-0.05
KM/WC KM/WC

225
R.KELUARGA C +3.48 +3.48 C
550

±0.00

K.TIDUR TURUN
300

300

±0.00

D K.TIDUR UTAMA
D
400

R.TAMU +3.50
±0.00
200

200

200

CARPORT E E
-0.15
300

300

300

300

150 400 300 150 300 400


850 850

B B

DENAH LANTAI 1 DENAH LANTAI 2


SKALA 1 : 100 SKALA 1 : 100

RINCIAN PERHITUNGAN VOLUME PEKERJAAN


Sub Pekerjaan :
Item Pekerjaan :
Satuan :
SKET GAMBAR URAIAN PERHITUNGAN

1 2 3 4 1.00
850
150 400 300

Galian Pondasi Batu Kali


Panjang
300

300

Kolom 15x15 cm
Sloof 15x35 cm
Sloof 15x25 cm
A A
250

250

III

B B
110

III 110
300

300

90
II II 70
1800

1800

35
150

150
1 2 3 4
850
150 400 300

300

300
Kolom 15x15 cm
Sloof 15x35 cm
Sloof 15x25 cm
vertical = 20.00 m + 2.00 m + 2.00 m
A A
20.00 m + m + = 44.00

250

250
III

B B horizontal = 10.00 m + 10.00 m + 10.00

110
III 110 10.00 m + 2.00 m + - = 42.00

300

300
= 86.00
90
II II 70

1800

1800
35

150

150
C C
volume = 0.90 x 0.80 x 86.00
I I

300

300
D D 2.00
Sloof 15x35 cm
200

200
Footplat 110x110 cm
Kolom 15x35 cm
E E Galian Pondasi Footplat
Sloof 15x25 cm Volume = - m x 1.10 m x 2.00 m x 12.00 ttk
300

300
Sloof 15x25 cm

150 400 300


850 3.00
1 2 3 4

DENAH PONDASI FOOTPLAT Vol Galian Pondasi Batu Kali + Volume GalianFootplat = 61.92 + -
SKALA 1 : 100
dikurangi
Volume Pondasi Batu + Vol Footplat =
15

HOLLOW 5X10 CM
KUSEN ALUMINIUM Ø10-150 MM 15
SLOOF 15X35 CM URUGAN TANAH Ø12-150 MM
URUGAN TANAH URUGAN PASIR
URUGAN PASIR SPESI 1PC:2KP:3PS
SPESI 1PC:2KP:3PS KERAMIK 50X50 CM Ø10-150 MM

4.00
KERAMIK 50X50 CM SLOOF 15X25 CM 15 Ø12-150 MM
LANTAI KERJA 5 CM
±0.00 Ø10-150 MM
110

±0.00

Bawah Pondasi Batu = 86.00 m x 0.10 m x 0.70 m


-0.05
-0.05 Ø12-150 MM
-0.15 -0.10

55 20 10
Bawah Pondasi Footp = - m x 1.10 m x 12.00 ttk x 0.10
-0.45

110 47.5 15 47.5

Bawah Lantai
PONDASI BATU KALI
URUGAN TANAH 110
AANSTAMPING
URUGAN PASIR
-1.25

-1.40
-1.50
DETAIL FOOTPLAT 2
SKALA 1 : 25
R. Tamu' = - m x 2.77 x 0.10
10
35
70 10
15 Kamar Tidur = - m x 3.85 x 0.10
DETAIL PONDASI III - III
SKALA 1 : 25 SLOOF 15X35 CM
URUGAN TANAH
Km/wc = - m x 1.45 x 0.10
R. makan/dapur = - m x 4.25 x 0.10
URUGAN PASIR
TRASRAM 1PC:3PS
SPESI 1PC:2KP:3PS +0.40
BATU BATA
KERAMIK 50X50 CM
PLESTERAN 1PC:2KP:3PS
Ø10-150 MM
Ø12-150 MM
15
±0.00 ±0.00
-0.05
-0.10
teras = - m x 4.00 x 0.10
15
Ø10-150 MM
Ø12-150 MM
-0.45
t sholat = - m x 3.00 x 0.10
LANTAI KERJA 5 CM
Ø10-150 MM
110

Ø12-150 MM PONDASI BATU KALI


URUGAN TANAH
55 20 10

AANSTAMPING
URUGAN PASIR
-1.25
110 47.5 15 47.5 -1.40
110 -1.50

35
10 70 10

DETAIL FOOTPLAT 1 DETAIL PONDASI I - I


SKALA 1 : 25 SKALA 1 : 25

RINCIAN PERHITUNGAN VOLUME PEKERJAAN


Sub Pekerjaan :
Item Pekerjaan :
Satuan :
SKET GAMBAR URAIAN PERHITUNGAN

1 2 3 4
850 1.00
150 400 300
Panjang
vertical = 20.00 m + 2.00 m + 2.00 m
20.00 m + m + = 44.00
300

300

Kolom 15x15 cm
Sloof 15x35 cm
Sloof 15x25 cm
A A
horizontal = 10.00 m + 10.00 m + 10.00
250

250

III
10.00 m + 2.00 m + - = 42.00
B B = 86.00
110

III 110
300

300

90
Volume = 0.35 m + 0.70 m x 0.80 m x 86.00 m
II II 70
2.00
1800

1800

35
150

150

C C
2.00
I I
300

300

D D Volume = 0.15 m x 0.90 m x 86.00 m


Sloof 15x35 cm
200

200

Footplat 110x110 cm
Kolom 15x35 cm
E E

Sloof 15x25 cm
300

300

Sloof 15x25 cm

150 400 300


850
1 2 3 4
III 110

300

300
90
II II 70

1800

1800
35

150

150
C C

I I

300

300
D D
Sloof 15x35 cm

200

200
Footplat 110x110 cm
Kolom 15x35 cm
E E

Sloof 15x25 cm

300

300
Sloof 15x25 cm

150 400 300


850
1 2 3 4

DENAH PONDASI FOOTPLAT


SKALA 1 : 100
15

HOLLOW 5X10 CM
KUSEN ALUMINIUM Ø10-150 MM 15
SLOOF 15X35 CM URUGAN TANAH Ø12-150 MM
URUGAN TANAH URUGAN PASIR
URUGAN PASIR SPESI 1PC:2KP:3PS
SPESI 1PC:2KP:3PS KERAMIK 50X50 CM Ø10-150 MM
KERAMIK 50X50 CM SLOOF 15X25 CM 15 Ø12-150 MM
LANTAI KERJA 5 CM
±0.00 Ø10-150 MM

110
-0.05 ±0.00
-0.05 Ø12-150 MM
-0.15 -0.10

55 20 10
-0.45

110 47.5 15 47.5


PONDASI BATU KALI
URUGAN TANAH 110
AANSTAMPING
URUGAN PASIR
-1.25

-1.40
DETAIL FOOTPLAT 2
-1.50 SKALA 1 : 25
35
15
10 70 10

DETAIL PONDASI III - III


SKALA 1 : 25 SLOOF 15X35 CM
URUGAN TANAH
URUGAN PASIR
TRASRAM 1PC:3PS
SPESI 1PC:2KP:3PS +0.40
BATU BATA
KERAMIK 50X50 CM
PLESTERAN 1PC:2KP:3PS
Ø10-150 MM 15
Ø12-150 MM ±0.00 ±0.00
-0.05
-0.10

Ø10-150 MM
15 Ø12-150 MM
-0.45
LANTAI KERJA 5 CM
Ø10-150 MM
110

Ø12-150 MM PONDASI BATU KALI


URUGAN TANAH
55 20 10

AANSTAMPING
URUGAN PASIR
-1.25
110 47.5 15 47.5 -1.40
110 -1.50

35
10 70 10

DETAIL FOOTPLAT 1 DETAIL PONDASI I - I


SKALA 1 : 25 SKALA 1 : 25

RINCIAN PERHITUNGAN VOLUME PEKERJAAN


Sub Pekerjaan :
Item Pekerjaan :
Satuan :
SKET GAMBAR URAIAN PERHITUNGAN

1.00

= 1.10 m x 1.10 m x 0.05 m x 12.00 ttk


35

30

25

GAMBAR
2.00
15

-
15 15 15 15
tapak = 1.10 m x 1.10 m x 12.00 ttk x 0.25
TYPE SL B1 (Tumpuan) B2 (Tumpuan) KP
DIMENSI 150 mm x 350 mm 150 mm x 300 mm 150 mm x 250 mm 150 mm x 150 mm pedestal = 0.15 m x 0.35 m x 12.00 ttk x 1.60 m
TULANGAN ATAS 2P Ø12 mm 2P Ø12 mm 2P Ø12 mm 2P Ø10 mm
TULANGAN TENGAH 4P Ø10 mm 2P Ø10 mm 2P Ø10 mm
TULANGAN BAWAH 2P Ø12 mm 2P Ø12 mm 2P Ø12 mm 2P Ø10 mm -
SEKANG 2P Ø10 mm - 150 mm 2P Ø10 mm - 100 mm 2P Ø10 mm - 100 mm 2P Ø8 mm - 150 mm
tapak
Ø12 = 7.20 m x 8.33 bh x 0.89 x 86.00 ttk
Ø10 = 7.20 m x 8.33 bh x 0.62 x 86.00 ttk
35

30

pedestal
25

GAMBAR
15

Ø12 = 2.35 m x 8.00 bh x 0.89 x - ttk


Ø10 = 0.88 m x 13.33 bh x 0.62 x - ttk
15 15 15 15
TYPE KS B1 (Lapangan) B2 (Lapangan) B3
DIMENSI
TULANGAN ATAS
150 mm x 350 mm
2P Ø12 mm
150 mm x 300 mm
2P Ø12 mm
150 mm x 250 mm
2P Ø12 mm
150 mm x 150 mm
2P Ø10 mm
-
TULANGAN TENGAH
TULANGAN BAWAH
4P Ø10 mm
2P Ø12 mm
2P Ø10 mm
2P Ø12 mm
2P Ø10 mm
2P Ø12 mm 2P Ø10 mm
tapak = 2.70 m x 12.00 ttk
SEKANG 2P Ø10 mm - 150 mm 2P Ø10 mm - 200 mm 2P Ø10 mm - 200 mm 2P Ø8 mm - 150 mm pedestal = 1.00 m x 1.60 m x - ttk

3.00
-
Lantai 1 = 0.15 m x 0.35 m x 3.50 m x - ttk
Lantai 2 = 0.15 m x 0.35 m x 3.50 m x - ttk
-
Lantai 1

Ø12 = 3.50 m x 8.00 bh x 0.89 x - ttk


Ø10 = 0.88 m x 23.33 bh x 0.62 x - ttk

Lantai 2

Ø12 = 3.50 m x 8.00 bh x 0.89 x - ttk


Ø10 = 0.88 m x 23.33 bh x 0.62 x - ttk

RINCIAN PERHITUNGAN VOLUME PEKERJAAN


Sub Pekerjaan :
Item Pekerjaan :
Satuan :
SKET GAMBAR URAIAN PERHITUNGAN

-
Lantai 1 = 1.00 m x 3.50 m x - ttk
Lantai 2 = 1.00 m x 3.50 m x - ttk
35

30

25

GAMBAR 15
4.00
15 15 15 15 -
Lantai 1 = 0.15 m x 0.15 m x 3.50 m x - ttk
TYPE SL B1 (Tumpuan) B2 (Tumpuan) KP
DIMENSI 150 mm x 350 mm 150 mm x 300 mm 150 mm x 250 mm 150 mm x 150 mm Lantai 2 = 0.15 m x 0.15 m x 3.50 m x - ttk
TULANGAN ATAS 2P Ø12 mm 2P Ø12 mm 2P Ø12 mm 2P Ø10 mm
TULANGAN TENGAH 4P Ø10 mm 2P Ø10 mm 2P Ø10 mm
TULANGAN BAWAH 2P Ø12 mm 2P Ø12 mm 2P Ø12 mm 2P Ø10 mm
SEKANG 2P Ø10 mm - 150 mm 2P Ø10 mm - 100 mm 2P Ø10 mm - 100 mm 2P Ø8 mm - 150 mm
-
Lantai 1
Ø10 = 4.00 bh x 3.50 m x 0.62 x - ttk
35

30

Ø8 = 0.48 bh x 3.50 m x 0.40 x - ttk


25

GAMBAR
15

Lantai 2
15 15 15 15 Ø10 = 4.00 bh x 3.50 m x 0.62 x - ttk
TYPE KS B1 (Lapangan) B2 (Lapangan) B3 Ø8 = 0.48 bh x 3.50 m x 0.40 x - ttk
DIMENSI 150 mm x 350 mm 150 mm x 300 mm 150 mm x 250 mm 150 mm x 150 mm
TULANGAN ATAS 2P Ø12 mm 2P Ø12 mm 2P Ø12 mm 2P Ø10 mm
TULANGAN TENGAH 4P Ø10 mm 2P Ø10 mm 2P Ø10 mm
TULANGAN BAWAH 2P Ø12 mm 2P Ø12 mm 2P Ø12 mm 2P Ø10 mm
SEKANG 2P Ø10 mm - 150 mm 2P Ø10 mm - 200 mm 2P Ø10 mm - 200 mm 2P Ø8 mm - 150 mm -
Lantai 1 = 0.60 m x 3.50 m x 13.00 ttk
Lantai 2 = 0.60 m x 3.50 m x 13.00 ttk

5.00
-
panjang
vertical = 20.00 m + 2.00 m + 2.00 m
20.00 m + m + = 44.00
horizontal =
10.00 m + 10.00 m + 10.00
10.00 m + 2.00 m + - = 42.00
= 86.00
volume = 0.15 m x 0.35 m x 74.00
RINCIAN PERHITUNGAN VOLUME PEKERJAAN
Sub Pekerjaan :
Item Pekerjaan :
Satuan :
SKET GAMBAR URAIAN PERHITUNGAN

-
Ø12 = 4.00 bh x 74.00 m x 0.89
Ø10 = 4.00 bh x 74.00 m x 0.62
Ø10 = 0.88 m x 493.33 bh x 0.62
35

30

25
GAMBAR

15
15 15 15 15 -
= 0.15 m x 0.35 m x 74.00
TYPE SL B1 (Tumpuan) B2 (Tumpuan) KP
DIMENSI 150 mm x 350 mm 150 mm x 300 mm 150 mm x 250 mm 150 mm x 150 mm
TULANGAN ATAS 2P Ø12 mm 2P Ø12 mm 2P Ø12 mm 2P Ø10 mm
TULANGAN TENGAH 4P Ø10 mm 2P Ø10 mm 2P Ø10 mm
TULANGAN BAWAH 2P Ø12 mm 2P Ø12 mm 2P Ø12 mm 2P Ø10 mm 6.00
SEKANG 2P Ø10 mm - 150 mm 2P Ø10 mm - 100 mm 2P Ø10 mm - 100 mm 2P Ø8 mm - 150 mm
Membuat Beton mutu f'c=19,3 MPa (K225), slum (12±2)cm, w/c = 0,58
panjang
vertical = 5.00 + 3.00 + 2.50
35

30

25

GAMBAR

15
horizontal = 4.00 + 4.50 + 8.50

15 15 15 15
TYPE KS B1 (Lapangan) B2 (Lapangan) B3
volume = 0.15 m x 0.25 m x 27.50
DIMENSI 150 mm x 350 mm 150 mm x 300 mm 150 mm x 250 mm 150 mm x 150 mm
TULANGAN ATAS 2P Ø12 mm 2P Ø12 mm 2P Ø12 mm 2P Ø10 mm
TULANGAN TENGAH 4P Ø10 mm 2P Ø10 mm 2P Ø10 mm
TULANGAN BAWAH 2P Ø12 mm 2P Ø12 mm 2P Ø12 mm 2P Ø10 mm
SEKANG 2P Ø10 mm - 150 mm 2P Ø10 mm - 200 mm 2P Ø10 mm - 200 mm 2P Ø8 mm - 150 mm

-
Ø12 = 4.00 bh x 27.50 m x 0.89
Ø10 = 2.00 bh x 27.50 m x 0.62
Ø10 = 0.88 m x 183.33 bh x 0.62

-
= 0.15 m x 0.25 m x 27.50

RINCIAN PERHITUNGAN VOLUME PEKERJAAN


Sub Pekerjaan :
Item Pekerjaan :
Satuan :
SKET GAMBAR URAIAN PERHITUNGAN

7.00
-
35

30

25

GAMBAR
15

15 15 15 15
TYPE SL B1 (Tumpuan) B2 (Tumpuan) KP
DIMENSI 150 mm x 350 mm 150 mm x 300 mm 150 mm x 250 mm 150 mm x 150 mm
TULANGAN ATAS 2P Ø12 mm 2P Ø12 mm 2P Ø12 mm 2P Ø10 mm
panjang = 7.00 7.00 7.00 3.00
3.00 4.00

35

30

25
GAMBAR

15
volume = 0.15 m x 0.30 m x 31.00 m
15 15 15 15
TYPE SL B1 (Tumpuan) B2 (Tumpuan) KP
DIMENSI 150 mm x 350 mm 150 mm x 300 mm 150 mm x 250 mm 150 mm x 150 mm -
TULANGAN ATAS
TULANGAN TENGAH
2P Ø12 mm
4P Ø10 mm
2P Ø12 mm
2P Ø10 mm
2P Ø12 mm
2P Ø10 mm
2P Ø10 mm
Ø12 = 4.00 bh x 31.00 m x 0.89
TULANGAN BAWAH 2P Ø12 mm 2P Ø12 mm 2P Ø12 mm 2P Ø10 mm Ø10 = 2.00 bh x 31.00 m x 0.62
SEKANG 2P Ø10 mm - 150 mm 2P Ø10 mm - 100 mm 2P Ø10 mm - 100 mm 2P Ø8 mm - 150 mm
Ø10 = 0.78 m x 206.67 bh x 0.62
35

30
-

25
GAMBAR

15
= 0.75 m x 31.00 m
8.00
15 15 15 15
-
TYPE KS B1 (Lapangan) B2 (Lapangan) B3 panjang = 11.00 11.00 7.50 2.50
DIMENSI 150 mm x 350 mm 150 mm x 300 mm 150 mm x 250 mm 150 mm x 150 mm
TULANGAN ATAS 2P Ø12 mm 2P Ø12 mm 2P Ø12 mm 2P Ø10 mm
TULANGAN TENGAH 4P Ø10 mm 2P Ø10 mm 2P Ø10 mm
TULANGAN BAWAH 2P Ø12 mm 2P Ø12 mm 2P Ø12 mm 2P Ø10 mm
SEKANG 2P Ø10 mm - 150 mm 2P Ø10 mm - 200 mm 2P Ø10 mm - 200 mm 2P Ø8 mm - 150 mm volume = 0.15 m x 0.25 m x 32.00 m

-
Ø12 = 4.00 bh x 32.00 m x 0.89
Ø10 = 2.00 bh x 32.00 m x 0.62
Ø10 = 0.68 m x 213.33 bh x 0.62

-
= 0.65 m x 32.00 m

RINCIAN PERHITUNGAN VOLUME PEKERJAAN


Sub Pekerjaan :
Item Pekerjaan :
Satuan :
SKET GAMBAR URAIAN PERHITUNGAN

8.00
-
panjang = 6.50 6.50 5.00
5.00 5.00 = 28.00 m'
35

30

25

GAMBAR
15

volume = 0.15 x 0.15 x 28.00


15 15 15 15
-
TYPE SL B1 (Tumpuan) B2 (Tumpuan) KP
DIMENSI 150 mm x 350 mm 150 mm x 300 mm 150 mm x 250 mm 150 mm x 150 mm
TULANGAN ATAS
TULANGAN TENGAH
2P Ø12 mm
4P Ø10 mm
2P Ø12 mm
2P Ø10 mm
2P Ø12 mm
2P Ø10 mm
2P Ø10 mm
Ø10 = 4.00 bh x 28.00 m x 0.62
TULANGAN BAWAH 2P Ø12 mm 2P Ø12 mm 2P Ø12 mm 2P Ø10 mm Ø10 = 0.48 m x 186.67 bh x 0.62
SEKANG 2P Ø10 mm - 150 mm 2P Ø10 mm - 100 mm 2P Ø10 mm - 100 mm 2P Ø8 mm - 150 mm

-
35

30

25

GAMBAR
15

15 15 15 15
TYPE KS B1 (Lapangan) B2 (Lapangan) B3
DIMENSI 150 mm x 350 mm 150 mm x 300 mm 150 mm x 250 mm 150 mm x 150 mm
TULANGAN ATAS 2P Ø12 mm 2P Ø12 mm 2P Ø12 mm 2P Ø10 mm
TULANGAN TENGAH 4P Ø10 mm 2P Ø10 mm 2P Ø10 mm
TULANGAN BAWAH 2P Ø12 mm 2P Ø12 mm 2P Ø12 mm 2P Ø10 mm
TYPE SL B1 (Tumpuan) B2 (Tumpuan) KP
DIMENSI 150 mm x 350 mm 150 mm x 300 mm 150 mm x 250 mm 150 mm x 150 mm
TULANGAN ATAS 2P Ø12 mm 2P Ø12 mm 2P Ø12 mm 2P Ø10 mm
TULANGAN TENGAH 4P Ø10 mm 2P Ø10 mm 2P Ø10 mm
TULANGAN BAWAH 2P Ø12 mm 2P Ø12 mm 2P Ø12 mm 2P Ø10 mm
SEKANG 2P Ø10 mm - 150 mm 2P Ø10 mm - 100 mm 2P Ø10 mm - 100 mm 2P Ø8 mm - 150 mm

35

30
= 0.45 m x 28.00

25
GAMBAR

15
15 15 15 15
TYPE KS B1 (Lapangan) B2 (Lapangan) B3 9.00
-
DIMENSI 150 mm x 350 mm 150 mm x 300 mm 150 mm x 250 mm 150 mm x 150 mm
TULANGAN ATAS 2P Ø12 mm 2P Ø12 mm 2P Ø12 mm 2P Ø10 mm
TULANGAN TENGAH
TULANGAN BAWAH
4P Ø10 mm
2P Ø12 mm
2P Ø10 mm
2P Ø12 mm
2P Ø10 mm
2P Ø12 mm 2P Ø10 mm
= 3.00 x 12.00 x 0.12 = 4.32 m3
SEKANG 2P Ø10 mm - 150 mm 2P Ø10 mm - 200 mm 2P Ø10 mm - 200 mm 2P Ø8 mm - 150 mm = 1.00 x 11.00 x 0.12 = 1.32 m3
= 3.00 x 10.00 x 0.12 = 3.60 m3
= 9.24 m3

-
horizontal = 7.00 x 66.67 x 0.62 = 287.93 kg
= 4.00 X 13.33 x 0.62 = 32.91 kg
vertical = 10.00 x 46.67 x 0.62 = 287.93 kg
= 2.00 x 26.67 x 0.62 = 32.91 kg
= 641.68 kg

= 1,283.36

-
= 3.00 x 12.00 = 36.00 m2
= 1.00 x 11.00 = 11.00 m2
= 3.00 x 10.00 = 30.00 m2
= 77.00 m2

RINCIAN PERHITUNGAN VOLUME PEKERJAAN


Sub Pekerjaan :
Item Pekerjaan :
Satuan :
SKET GAMBAR URAIAN PERHITUNGAN

1.00
panjang lantai 1
B B horizontal = 8.50 3.00 7.00 1.50
1 2 3 4 1 2 3 4 4.00 4.00 3.00
vertical = 18.00 18.00 7.50 1.50
850 850
150 400 300 150 400 300

3.00 2.50 5.00


T.JEMUR
300

300

300

300

TAMAN -0.15
-0.15

A A
volume = 86.50 x 3.50
100

TERAS T.SHOLAT BALKON


250

250

250

-0.05 +0.15 +3.48

B B
K.TIDUR
pengurang
350

NAIK +3.50

DAPUR
R.SANTAI PU = 1.00 x 2.15 = 2.15 M2
300

300

325

R.MAKAN ±0.00
+3.50
P1 = 0.90 x 2.15 = 1.94 M2
±0.00

A A A A
PK = 0.80 x 2.15 = 1.72 M2
1800

1800

1800

1800

KM/WC
150

150

-0.05
KM/WC KM/WC
PJ = 2.37 x 2.15 = 5.10 M2
225

R.KELUARGA C +3.48 +3.48 C


550

±0.00

K.TIDUR TURUN J1 = 8.50 x 2.65 = 22.53 M2


300

300

±0.00

PL = 3.10 x 2.15 = 6.67 M2


D K.TIDUR UTAMA
D
400

R.TAMU
±0.00
+3.50
J5 = 1.55 x 2.25 = 3.49 M2
200

200

200

E E
J6 = 2.20 x 2.65 = 5.83 M2
CARPORT
-0.15
J4 = 1.55 x 2.25 = 3.49 M2
J3 = 2.00 x 2.50 = 5.00 M2
300

300

300

300

J2 = 1.75 x 2.50 = 4.38 M2


= 62.27 M2
150 400 300 150 300 400
850 850

B B

DENAH LANTAI 1 DENAH LANTAI 2


SKALA 1 : 100 SKALA 1 : 100
D K.TIDUR UTAMA
D

400
R.TAMU +3.50
±0.00

200

200

200
CARPORT E E
-0.15

300

300

300

300
150 400 300 150 300 400
850 850

B B

DENAH LANTAI 1 DENAH LANTAI 2


SKALA 1 : 100 SKALA 1 : 100
VOLUME TOTAL = 302.75 - 62.27 = 240.48 M2

3.00
= 240.48 x 2.00 = 480.96 M2

4.00 = 480.96

RINCIAN PERHITUNGAN VOLUME PEKERJAAN


Sub Pekerjaan :
Item Pekerjaan :
Satuan :
SKET GAMBAR URAIAN PERHITUNGAN

1.00
PU = 2.15 + 2.15 + 1.00
850 850
150 400 300 150 400 300 P1 = 2.15 + 2.15 + 0.80
PM = 1.95 + 2.15 + 0.90
PK = 2.15 + 2.15 + 0.80
PJ = 2.15 + 2.15 + 0.80
300

300

300

300

= 1.53 + 1.53 + 6.00


J1 = 2.60 + 2.65 + 0.85
100

KS

PL = 2.15 x 6.00 + 3.10 x 2.00


250

250

250

J3
J5 = 2.15 x 3.00
= 1.55 x 2.00
350

PL PJ
NAIK
= 0.95
300

300

325

P1
J6 = 2.65 x 4.00 + 2.20 x 2.00
J4 = 2.25 x 3.00 + 1.55 x 2.00
J6
J3 = 2.50 x 4.00 + 2.00 x 2.00
1800

1800
1800

1800

PK
150

150

VK
PM
P1
J2 = 2.50 x 3.00 + 1.75 x 2.00
225
550

TURUN P1 PK
300

300

J5 J1
400

2.00
PU
J4 = 1.99 x 2.00 + 0.55 x 2.00
200

200

200

J4 J2
J3 = 2.24 x 6.00 + 0.60 x 6.00
J2 = 2.24 x 4.00 + 0.64 x 4.00
300

300

300

300

150 400 300 150 300 400


Luas = 33.64 x 0.10
850 850

3.00
PM = 1.59 + 2.15 + 2.10
DENAH KOSEN LANTAI 1 DENAH KOSEN LANTAI 2
PK = 2.15 x 2.00 + 0.70 x 3.00
PL = 2.15 x 10.00 + 0.44 x 10.00

Luas = 38.14 x 0.10


RINCIAN PERHITUNGAN VOLUME PEKERJAAN
Sub Pekerjaan :
Item Pekerjaan :
Satuan :
SKET GAMBAR URAIAN PERHITUNGAN

4.00
850 850
150 400 300 150 400 300 PU = 9.00 x 0.10
PM = 0.50 x 0.80
PK = 1.09 x 0.50
PJ = 0.69 x 1.90 x 2.00
300

300

300

300
1.85 x 0.60
100

KS
250

250

250
J3
J1 = 0.85 + 2.65
PL = 1.94 x 0.44 x 5.00
350

PL PJ
NAIK
J5 = 0.95 x 1.05 x 2.00
300

300

P1 325

J6
J6 = 2.55 x 0.66 x 3.00
1800

1800
1800

1800

PK
150

150

VK
PM
P1
225
550

J4 = 0.65 x 2.15 x 1.00


PK
TURUN P1
= 0.45 x 2.15 x 1.00
300

300

J5 J1 J3 = 0.40 x 2.24 x 3.00


400

J2 = 0.64 x 2.24 x 2.00


PU
200

200

200

J4 J2
300

300

300

300

150 400 300 150 300 400


850 850

DENAH KOSEN LANTAI 1 DENAH KOSEN LANTAI 2

RINCIAN PERHITUNGAN VOLUME PEKERJAAN


Sub Pekerjaan :
Item Pekerjaan : ; scoor 8/12
Satuan :
SKET GAMBAR URAIAN PERHITUNGAN

VII
D 1.00
Kuda kuda full
C bin balk 8/14 = 0.08 x 0.14 x 5.32
kaki kuda2 8/12 = 0.08 x 0.12 x 2.37
balok mander 8/12 = 0.08 x 0.12 x 1.38 x 2.00
Balok Mander 8/12
Balok Nok 8/12
Balok Suri" 2/20
scoor 8/12 = 0.08 x 0.12 x 1.10 x 2.00
Genteng Bubungan
B Plat Lebar 4 cm
Baut Ø3 cm
balok kunci 8/14 = 0.08 x 0.14 x 1.00
A Kaki Kuda - Kuda 8/12
Usuk 5/7
Genteng Keramik
balok nok 8/12 = 0.08 x 0.12 x 1.40
GAMBAR KUDA - KUDA Reng 2/3
murplat 8/12 = 0.08 x 0.12 x 24.00
SKALA 1 : 50

Scoor 8/12
Kaki Kuda" 8/12
Gording 8/12 1/2 Kuda Kuda
Penahan Gording
bin balk 8/14 = 0.08 x 0.14 x 2.66
Bin Balk 8/14
Murplat 8/12 Usuk 5/7
Ring Balk 15x25 Genteng Keramik

kaki kuda2 8/12 = 0.08 x 0.12 x 1.19


Reng 2/3 Reng 2/3
Usuk 5/7
Genteng Keramik DETAIL KUDA - KUDA "D"
SKALA 1 : 25
balok mander 8/12 = 0.08 x 0.12 x 0.69
Bin Balk 8/14 scoor 8/12 = 0.08 x 0.12 x 0.55
Plat Lebar 4 cm
Baut Ø3 cm
Balok Mander 8/12
balok kunci 8/14 = 0.08 x 0.14 x 0.50
balok nok 8/12 = 0.08 x 0.12 x 0.70
Baut Ø3 cm
Scoor 8/12
Balok Kunci 8/14
murplat 8/12 = 0.08 x 0.12 x 24.00
Pas.Dinding 1/2 Bata
DETAIL KUDA - KUDA "C"
Plesteran SKALA 1 : 25
Plafond +7.63
Lisplank 2/20

DETAIL KUDA - KUDA "A"


SKALA 1 : 25 Kuda kuda full = 2.00 bh x 0.38 m3 = 0.77 m3
1/2 Kuda Kuda = 4.00 bh x 0.30 m3 = 1.18 m3
DETAIL KUDA - KUDA "B" = 1.95 m3
SKALA 1 : 25

2.00
= 0.08 x 0.12 x 12.80

3.00

= 1.32 + 8.21 x 4.00 x 2.00 sisi


2.00

= 6.90 : 2.00 x 4.00 x 2.00 sisi

5.00 = =

RINCIAN PERHITUNGAN VOLUME PEKERJAAN


Sub Pekerjaan :
Item Pekerjaan : ; Km/wc
Satuan :
SKET GAMBAR URAIAN PERHITUNGAN

1.00
850 850
150 400 300 150 400 300
Lantai 1
R. Tamu' = 5.00 m x 2.77
Kamar Tidur = 2.85 m x 3.85
Km/wc = 1.35 m x 1.45
300

300

300

300
100
250

250

250
350
300

300

325
850 850
150 400 300 150 400 300

300

300

300

300
R. makan/dapur = 5.27 m x 4.25
teras = 2.50 m x 4.00

100
250
t sholat = 2.50 m x 3.00

250

250
350
Lantai 2
Kamar Utama = 4.00 m x 4.00
300

300

325
r tngga = 3.00 m x 5.50
Km/wc = 2.25 m x 1.50 x 2.00
1800

1800

1800

1800
150

150
r. sanati = 3.25 m x 3.00

225
K. tidur = 3.50 m x 4.00

550
balkon = 2.50 m x 3.00
300

300

400
200

200

200
2.00
Lantai 1
R. Tamu' = 5.00 m + 2.77 x 2.00
300

300

300

300
Kamar Tidur = 2.85 m + 3.85 x 2.00
Km/wc = 1.35 m + 1.45 x 2.00
150 400 300 150 300 400 R. makan/dapur = 5.27 m + 4.25 x 2.00
850 850 teras = 2.50 m + 4.00 x 2.00
t sholat = 2.50 m + 3.00 x 2.00
DENAH PLAFOND LANTAI 1 DENAH PLAFOND LANTAI 2
SKALA 1 : 100 SKALA 1 : 100 Lantai 2
Kamar Utama = 4.00 m x 4.00 x 2.00
r tngga = 3.00 m x 5.50 x 2.00
Km/wc = 2.25 m x 1.50 x 2.00
r. sanati = 3.25 m x 3.00 x 2.00
K. tidur = 3.50 m x 4.00 x 2.00
balkon = 2.50 m x 3.00 x 2.00

RINCIAN PERHITUNGAN VOLUME PEKERJAAN


Sub Pekerjaan :
Item Pekerjaan :
Satuan :
SKET GAMBAR URAIAN PERHITUNGAN

850 850
1.00
150 400 300 150 400 300 Lantai 1
R. Tamu' = 5.00 m x 2.77
Kamar Tidur = 2.85 m x 3.85
300

300

300

300

R. makan/dapur = 5.27 m x 4.25


teras = 2.50 m x 4.00
100

t sholat = 2.50 m x 3.00


250

250

250

Lantai 2
350

Kamar Utama = 4.00 m x 4.00


300

300

325

r tngga = 3.00 m x 5.50


1800

1800

1800

1800

r. sanati = 3.25 m x 3.00


150

150

K. tidur = 3.50 m x 4.00


225
550
300

300

400
200

200

200
00

00

00

00
350
300

300

325
1800

1800

1800

1800
150

150

225
550
balkon = 2.50 m x 3.00

300

300

400
-
200

200

200
Lantai 1
Km/wc = 1.35 m x 1.45
300

300

300

300
Lantai 2
Km/wc = 2.25 m x 1.50 x 2.00
150 400 300 150 300 400
850 850

Lantai 1
DENAH KERAMIK LANTAI 1 DENAH KERAMIK LANTAI 2 Km/wc = 1.35 m + 1.45 x 2.00 x 1.50
SKALA 1 : 100 SKALA 1 : 100

Lantai 2
Km/wc = 2.25 m + 1.50 x 4.00 x 1.50
= 60.00 m
= 61.92 m3

= - m3

= 61.92 m3

= 6.02 m3
= - m3

= - m3
= - m3
= - m3
= - m3
= - m3
= - m3
= 6.02 m3

= 36.12 m3

= 11.61 m3
= 0.73

= 3.63 m3
= 1.01 m3
= 4.64 m3

= ### kg
= ### kg

= - kg
= - kg
= ### kg

= 32.40 m2
= - m2
= 32.40 m2

= - m3
= - m3
= - m3

= - kg
= - kg

= - m2
= - m2
= - m2

= - m2
= - m2
= - m2

= - m3
= - m3
= - m3

= - kg
= - kg

= - kg
= - kg
= - kg

= 27.30 m2
= 27.30 m2
= 54.60 m2

= 44.00 m'

= 30.00 m'
= 74.00 m'

= 3.89 m3
= 262.85 kg
= 182.63 kg
= 267.86 kg
= 713.34 kg

= 3.89 m2

= 10.50 m2

= 17.00 m2
= 27.50 m2

= 1.03 m3

= 97.68 kg
= 33.94 kg
= 99.54 kg
= 231.16 kg

= 1.03 m2
= 31.00 m'

= 1.40 m3

= 110.11 kg
= 38.25 kg
= 99.46 kg
= 247.83 kg

= 23.25 m2

= 32.00 m'

= 1.20 m3

= 113.66 kg
= 39.49 kg
= 89.51 kg
= 242.66 kg

= 20.80 m2

= 0.63 m2

= 69.10 kg
= 55.28 kg
= 124.39 kg
= 12.60 m2

x 2.00

= 31.00

= 55.50
= 86.50 m'

= 302.75
= 5.30 m'
= 5.10 m'
= 5.00 m'
= 5.10 m'
= 5.10 m'
= 9.05 m'
= 6.10 m'
= 19.10 m'
= 6.45 m'
= 3.10 m'
= 0.95 m'
= 15.00 m'
= 9.85 m'
= 14.00 m'
= 11.00 m'
= 120.20 m'

= 5.08 m'
= 17.04 m'
= 11.52 m'
= 33.64 m'

= 3.36 m2

= 5.84 m'
= 6.40 m'
= 25.90 m'
= 38.14 m'

= 3.81 m2
= 0.90 m2
= 0.40 m2
= 0.55 m2
= 2.61 m2
= 1.11 m2

= 2.25 m2
= 4.27 m2
= 1.99 m2

= 5.05 m2

= 1.40 m2
= 0.97 m2
= 2.69 m2
= 2.87 m2
= 27.05 m2
= 0.06 m3
= 0.02 m3
= 0.03 m3
= 0.02 m3
= 0.01 m3
= 0.01 m3
= 0.23 m3

= 0.38 m3

= 0.03 m2
= 0.01 m3
= 0.01 m3
= 0.01 m3
= 0.01 m3
= 0.01 m3
= 0.23 m3

= 0.30 m3

= 0.12 m3

= 38.12 m2

= 27.60 m2
= 65.72 m2

= 13.85 m2
= 10.97 m2
= 1.96 m2
= 22.40 m2
= 10.00 m2
= 7.50 m2

= 16.00 m2
= 16.50 m2
= 6.75 m2
= 9.75 m2
= 14.00 m2
= 7.50 m2
= 137.18 m2

= 27.70 m'
= 21.95 m'
= 3.92 m'
= 44.79 m'
= 20.00 m'
= 15.00 m'

= 32.00 m'
= 33.00 m'
= 6.75 m'
= 19.50 m'
= 28.00 m'
= 15.00 m'
= 267.61 m'

= 13.85 m2
= 10.97 m2

= 22.40 m2
= 10.00 m2
= 7.50 m2

= 16.00 m2
= 16.50 m2

= 9.75 m2
= 14.00 m2
= 7.50 m2
= 128.47 m2

= 1.96 m2

= 6.75 m2
= 8.71 m2

= 8.40 m2

= 22.50 m2
= 30.90 m2
DAFTR KUANTITAS DAN HARGA
KEGIATAN : PEMBANGUNAN
PEKERJAAN : RUMAH TINGGAL 2 LANTAI
LOKASI : KEBUMEN
KABUPATEN : KEBUMEN
TAHUN ANGGARAN : 2023

NO JENIS PEKERJAAN ANALISA KUANTITAS


I PEKERJAAN PERSIAPAN
1 Pengukuran dan Pemasangan 1 m' Bouwplank A.1.1.1.4 53.00 M'
2 Pembersihan 1 m2 dan Perataan lapangan A.1.1.1.8 153.00 m2
3 Pembuatan 1 m2 bak adukan A.1.1.1.10 0.40 M2
JUMLAH PEKERJAAN PERSIAPAN

II PEKERJAAN TANAH
1 Menggali Tanah Biasa Sedalam 1 m A.1.5.1.1 59.04 M3
2 Penggalian Tanah Biasa Sedalam > 1 s.d 2 m A.1.5.1.2 29.04 M3
3 Pengurugan kembali 1 m3 galian tanah A.1.5.1.15 M3
4 Pengurugan dengan Pasir Urug A.1.5.1.10 13.86 M3
JUMLAH PEKERJAAN TANAH

III PEKERJAAN PONDASI


1 Pemasangan Pondasi Batu Belah 1SP : 6 PP A.3.2.1.4 34.44 M3
2 Pemasang Batu Kosong (Anstamping) untuk pondasi ged A.3.2.1.9 11.07 M3
JUMLAH PEKERJAAN PONDASI

IV PEKERJAAN BETON
1 Pembuatan 1 m3 beton mutu fc 7,4 Mpa (K100) A.4.1.1.1 0.73 M3
2 FOOTPLAT
Pembuatan 1 m3 beton mutu fc 19,3 Mpa (K225) A.4.1.1.7 4.64 m3
Pembesian 10 kg dengan Besi Polos atau Ulir A.4.1.1.15 137.08 kg
Pemasangan 1 m2 Bekisting untuk Pondasi Telapak BetonA.4.1.1.18
Bangunan 51.60 m2
Gedung
3 KOLOM 15/35
Pembuatan 1 m3 beton mutu fc 19,3 Mpa (K225) A.4.1.1.7 4.41 m3
Pembesian 10 kg dengan Besi Polos atau Ulir A.4.1.1.15 90.08 kg
Pemasangan 1 m2 Bekisting untuk Kolom Beton Banguna A.4.1.1.20 84.00 m2
4 KOLOM 15/15
Pembuatan 1 m3 beton mutu fc 19,3 Mpa (K225) A.4.1.1.7 2.05 m3
Pembesian 10 kg dengan Besi Polos atau Ulir A.4.1.1.15 23.25 kg
Pemasangan 1 m2 Bekisting untuk Kolom Beton Banguna A.4.1.1.20 54.60 m2
5 SLOOF 15/35
Pembuatan 1 m3 beton mutu fc 19,3 Mpa (K225) A.4.1.1.7 4.46 m3
Pembesian 10 kg dengan Besi Polos atau Ulir A.4.1.1.15 81.94 kg
Pemasangan 1 m2 Bekisting untuk Sloof Beton Bangunan A.4.1.1.19 4.46 m2
6 SLOOF 15/25
Pembuatan 1 m3 beton mutu fc 19,3 Mpa (K225) A.4.1.1.7 1.03 m3
Pembesian 10 kg dengan Besi Polos atau Ulir A.4.1.1.15 23.12 kg
Pemasangan 1 m2 Bekisting untuk Dinding Sheerwall A.4.1.1.23 1.03 m2
7 BALOK B1 15/30
Pembuatan 1 m3 beton mutu fc 19,3 Mpa (K225) A.4.1.1.7 1.40 m3
Pembesian 10 kg dengan Besi Polos atau Ulir A.4.1.1.15 24.78 kg
Pemasangan 1 m2 Bekisting untuk Balok Bangunan Gedu A.4.1.1.21 23.25 m2
8 BALOK B2 15/25
Pembuatan 1 m3 beton mutu fc 19,3 Mpa (K225) A.4.1.1.7 1.20 m3
Pembesian 10 kg dengan Besi Polos atau Ulir A.4.1.1.15 24.27 kg
Pemasangan 1 m2 Bekisting untuk Balok Bangunan Gedu A.4.1.1.21 20.80 m2
8 BALOK B2 15/15
Pembuatan 1 m3 beton mutu fc 19,3 Mpa (K225) A.4.1.1.7 0.63 m3
Pembesian 10 kg dengan Besi Polos atau Ulir A.4.1.1.15 12.44 kg
Pemasangan 1 m2 Bekisting untuk Balok Bangunan Gedu A.4.1.1.21 12.60 m2
9 BETON PLAT LANTAI 2 tb 12 cm
Pembuatan 1 m3 beton mutu fc 19,3 Mpa (K225) A.4.1.1.7 9.24 m3
Pembesian 10 kg dengan Besi Polos atau Ulir A.4.1.1.15 128.34 kg
Pemasangan 1 m2 Bekisting untuk Plat lantai Beton Ban A.4.1.1.22 77.00 m2
11 TANGGA
Pembuatan 1 m3 beton mutu fc 19,3 Mpa (K225) A.4.1.1.7 2.54 m3
Pembesian 10 kg dengan Besi Polos atau Ulir A.4.1.1.15 35.46 kg
Pemasangan 1 m2 Bekisting untuk Tangga Beton Bangun A.4.1.1.25 12.00 m2
JUMLAH PEKERJAAN BETON

V PEKERJAAN 1m2
Pemasangan DINDING DAN
Dinding PLESTERAN
Bata Merah (5x11x22) cm
1 tebal 1 batu A.4.4.1.5 240.48 M2
3 Campuran
Pemasangan 1SP : 6PP 1 Pc : 6 Pp Tebal 15 mm
Plesteran A.4.4.2.6 480.96 M2
4 Pemasangan Acian A.4.4.2.27 480.96 M2
JUMLAH PEKERJAAN PLESTERAN

VI PEKERJAAN KUSEN PINTU DAN JENDELA


1 Pemasangan Profil alluminium sek. EDICO Coklat 4" A.4.2.1.11. C 120.20 m'
tbl=1
Pasangmm
Daun Jendela Alumunium Sek. Edico Coklat
2 Ls.22 3.36 m2
accesories
Pasang Daunlengkap
Pintu aluminium Sek. ALEXINDO Coklat
3 Ls.24 3.81 m2
accesories lengkap
4 Pemasangan Kaca Bening 5mm DP 27.05 m2
JUMLAH PEKERJAAN KUSEN JENDELA

VII PEKERJAAN ATAP


1 Pemasangan 1 m3 Konstruksi Kuda-kuda Konvensional. Kayu Kelas I.
A.4.6.1.13 1.95 M3
II dan III Bentang Sampai Dengan 6 Meter
2 Pemasangan 1 m3 Konstruksi Gordeng. Kayu kelas II A.4.6.1.15 0.12 M3
3 Pemasangan 1 m2 Rangka Atap Genteng Beton Kayu A.4.6.1.17 65.72 M2
Kelas II
4 Pemasangan 1 m2 Atap Genteng Beton A.4.5.2.32 65.72 M2
5 Pemasangan 1 m’ Nok/Bubung Genteng Beton A.4.5.2.36 1.32 M'
6 Pemasangan 1 m’ Lisplank Ukuran 3x20cm. Kayu Kelas I atA.4.6.1.21 30.30 M'
JUMLAH PEKERJAAN ATAP

VIII PEKERJAAN PLAFOND


Pasang plafond Gypsumboard 9mm rangka hollow LS &
1 galvanis 35.35.3 dan 20.40.2(uk.60x80) finish cat sek. A.4.5.1.7.A 137.18 M2
Decolith
2 List Langit-langit Gypsum Profil A.4.5.1.11 267.61 M'
JUMLAH PEKERJAAN PLAFOND

IX PEKERJAAN KERAMIK
1 Pemasangan 1m2 Lantai Ubin Granit Ukuran 60cm x 60c A.4.4.3.11 128.47 M2
Pemasangan 1m2 Lantai ubin Warna Ukuran 30cm x 30c A.4.4.3.5 8.71 M2
2 Pemasangan Dinding Keramik uk 30 x 60 cm A.4.4.3.57 30.90 M2
JUMLAH PEKERJAAN KERAMIK

X PEKERJAAN PENGECATAN
1 Pengecat 1 m2 Tembok Baru (1lap.Plamir, 1lap Cat Dasar A.4.7.1.10 480.96 M2
2 Pengecatan Plafond A.4.7.1.10 M2
JUMLAH PEKERJAAN PENGECATAN

XI PEKERJAAN LISTRIK
1 Pemasangan 1 Buah Titik Lampu A.6.2.1.1 119.00 TITIK
2 Pemasangan 1 buah Stopkontak A.6.1.1.2 7.00 TITIK
3 Pemasangan 1 buah lampu RD 150 E27 LEDBULB 12W A.6.2.1.4 77.00 Titik
4 Pemasangan 1 titik stopkontak AC A.6.2.1.34 3.00 Titik
5 Pekerjaan Saklar Tunggal DIHIT 3.00 Titik
6 Pekerjaan Saklar Ganda DIHIT 13.00 Titik
7 Pemasangan baru daya listrik PLN 1800 watt DIHIT 1.00 Ls
8 Pemasangan 1 buah MCCB A.6.1.1.1 1.00 Ls
JUMLAH PEKERJAAN LISTRIK

XII PEKERJAAN SANTITASI


1 Pemasangan 1 buah closet duduk/ monoblock A.5.1.1.1 2.00 Bh
2 Pemasangan 1 buah wastafel A.5.1.1.5 1.00 Bh
3 Pemasangan 1 buah Bak cuci piring stainlessteel sek. A.5.1.1.12 1.00 Bh
Wasser
4 Pemasangan 1 buah floor drain A.5.1.1.14 2.00 Bh
5 Pemasangan 1 buah kran diameter ½” atau 3/4” A.5.1.1.46 5.00 Bh
6 Pemasangan 1 m' pipa PVC tipe AW diameter 1/2" A.5.1.1.25 30.00 M2
7 Pemasangan 1 m’ pipa PVC tipe AW diameter 3/4” A.5.1.1.26 30.00 M2
8 Pemasangan 1 m’ pipa PVC tipe AW diameter 3” A.5.1.1.31 30.00 M2
9 Pemasangan 1 m’ pipa PVC tipe AW diameter 4” A.5.1.1.32 30.00 M2
JUMLAH PEKERJAAN SANITASI

XIII PEKERJAAN LAIN - LAIN


1 Pekerjaan oemasangan tralis besi hollow 4x4 cm Ls 1.00 unit
2 Pekerjaan Pemasangan railling tangga Ls 1.00 unit
JUMLAH PEKERJAAN LAIN LAIN

JUMLAH KONSTRUKSI :
PPN 10% :
JUMLAH :
DIBULATAN :
Terbilang :
# Delapan ratus Sembilan puluh Sembilan juta Sembilan ratus Empat puluh dua rib
S DAN HARGA

HARGA JUMLAH HARGA


JUMLAH TOTAL (Rp)
SATUAN (Rp) (Rp)

245,353.24 13,003,721.72
14,245.00 2,179,485.00
279,497.24 111,798.90
15,295,005.616

70,262.50 4,148,298.00
85,882.50 2,494,027.80
13,566.67 -
278,905.00 3,865,553.57
6,642,325.800

1,011,321.30 34,829,905.57
604,725.00 6,694,305.75
41,524,211.322

1,161,356.43 843,144.77

1,332,715.48 6,181,134.38
215,363.50 29,522,166.41
219,865.80 11,345,075.28

1,332,715.48 5,877,275.25
215,363.50 19,399,806.25
489,715.05 41,136,064.20

1,332,715.48 2,728,734.94
215,363.50 5,008,062.83
489,715.05 26,738,441.73

1,332,715.48 5,947,242.81
215,363.50 17,646,397.03
236,410.90 1,054,983.64

1,332,715.48 1,374,362.83
215,363.50 4,978,292.41
561,606.10 579,156.29
-
1,332,715.48 1,859,138.09
215,363.50 5,337,276.09
522,343.80 12,144,493.35

1,332,715.48 1,599,258.57
215,363.50 5,225,970.49
522,343.80 10,864,751.04

1,332,715.48 839,610.75
215,363.50 2,678,846.27
522,343.80 6,581,531.88

1,332,715.48 12,314,291.00
215,363.50 27,638,890.14
551,315.05 42,451,258.85

1,332,715.48 3,385,097.31
215,363.50 7,636,789.71
455,211.35 5,462,536.20
326,380,080.799

290,681.60 69,902,965.83
61,724.65 29,687,026.90
35,464.00 17,056,729.98
116,646,722.704

160,000.00 19,232,000.00
890,292.75 2,994,944.81
363,284.00 1,385,565.18
150,000.00 4,057,830.00
27,670,339.987

16,862,340.00 32,934,713.10
18,453,325.00 2,267,544.58
309,885.18 20,365,654.03
103,290.00 6,788,218.80
120,357.60 158,872.03
269,604.94 8,169,029.68
70,684,032.215

147,825.50 20,278,332.53

32,076.00 8,583,697.98
28,862,030.506
425,036.33 54,604,417.74
192,019.00 1,672,005.44
385,363.00 11,907,716.70
68,184,139.886

28,263.16 13,593,420.21
28,263.16 -
13,593,420.209

510,950.00 60,803,050.00
316,470.00 2,215,290.00
108,443.50 8,350,149.50
738,474.00 2,215,422.00
53,735.00 161,205.00
54,285.00 705,705.00
4,000,000.00 4,000,000.00
462,000.00 462,000.00
71,368,489.500

2,178,797.50 4,357,595.00
792,110.00 792,110.00
328,828.50 328,828.50
56,369.50 112,739.00
79,543.75 397,718.75
21,745.08 652,352.25
25,027.20 750,816.00
106,897.45 3,206,923.50
134,488.20 4,034,646.00
14,633,729.000

3,000,000.00 3,000,000.00
5,000,000.00 5,000,000.00
16,644,737.750

RP. 818,129,265.294
Rp. 81,812,926.529
Rp. 899,942,191.824
Rp. 899,942,000.000

bilan ratus Empat puluh dua ribu rupiah #


DAFTAR HARGA SATUAN BAHAN BANGUNAN

SUMBER DATA : PASARAN BEBAS


D A E R A H : KABUPATEN KEBUMEN
EDISI 2023

NO. J E N I S B A H A N SAT HARGA (Rp) KET

I BAHAN DASAR
1 BATU KALI Bulat Utuh m3 281,000
Bulat Belah m3 281,000
Pecah 10/15 m3 301,000
Pecah 5/7 m3 312,500
Pecah 3/5 m3 337,000
2 KERIKIL Timbun/sirtu m3 225,000
Sawur / Koral m3 236,000
Beton 0,5/1 m3 352,000
Beton ,1/2 m3 362,000
Beton ,2/3 m3 372,000
Biasa m3 263,500
Tras Giling m3 213,000
3 BATU BATA ex lokal bh 900

4 PASIR Urug m3 190,000


Pasang m3 313,000
Beton m3 376,000
Batu Granit kg 7,000
Batu Traso kg 7,630

5 TANAH Padas m3 143,000


Liat m3 147,500
Merah m3 250,000
6 KAPUR Pasang m3 363,000
Padam m3 283,000
Semen Merah m3 158,500
7 PORTLAND CEMENT
Merk I 40 kg zak 65,000
Merk I 50 kg zak 76,000
Merk II 40 kg zak 60,000
Merk II 50 kg zak 68,000
Semen Putih 40 kg zak 119,000
Semen Putih 50 kg zak 151,000
Semen warna kg 16,000
Mortar Siap Pakai 40 kg zak 125,000
Semen Gout 20 kg zak 133,200 sika grout
Sacreing 166,500

file:///conversion/tmp/activity_task_scratch/720096400.xlsx 97/451 hdb


NO. J E N I S B A H A N SAT HARGA (Rp) KET

II BAHAN PENUTUP ATAP

1 SIRAP (100 lbr) pak 612,000

2 GENTENG BETON Genteng Beton Warna standard bh 6,000


Genteng Beton Warna Special bh 7,500
Genteng Beton Warna Khusus bh 7,250
Kerpus Beton Warna Standard bh 7,500
Kerpus Beton Warna Special bh 12,500
Kerpus Beton Warna Khusus bh 13,750
Nok Genteng Beton Warna standard bh 25,000
3 GENTENG TANAH LIAT
Vlaam/Plentong bh 2,225
Kodok bh 2,500
Kodok Glasur bh 5,700
Nok kerpus Kodok bh 4,900
Nok kerpus Kodok Glasur bh 6,250
Plentong super besar 18 bh/m2 bh 3,500
Nok kerpus plentong super bh 4,500
Genteng Magase bh 3,200
Genteng Magaze glazur bh 7,000
Genteng Morando biasa bh 3,800
Genteng Morando glazur bh 8,000
4 GENTENG KACA
Vlaam tebal 2 mm bh 13,500
Vlaam tebal 3 mm bh 17,150
Kodok tebal 2 mm bh 16,300
Kodok tebal 3 mm bh 19,500
5 GENTENG ASPAL
30 cm X 50 cm bh 16,000
Nok Genteng Aspal bh 66,500
6 GENTENG METAL
T 0,3 mm m2 67,000
Nok Genteng Metal bh 48,000
7 ASBES GELOMBANG BESAR
. 180 cm X 92 cm X 5 mm bh 79,000
. 200 cm X 92 cm X 5 mm bh 90,000
. 225 cm X 92 cm X 5 mm bh 90,500
. 250 cm X 92 cm X 5 mm bh 104,500
. 200 cm X 102 cm X 5 mm bh 90,250
. 225 cm X 102 cm X 5 mm bh 100,500
. 250 cm X 102 cm X 5 mm bh 112,000
. 200 cm X 102 cm X 6 mm bh 98,500
. 225 cm X 102 cm X 6 mm bh 90,000
. 250 cm X 102 cm X 6 mm bh 106,000
. 180 cm X 108 cm X 6 mm bh 62,500

file:///conversion/tmp/activity_task_scratch/720096400.xlsx 98/451 hdb


NO. J E N I S B A H A N SAT HARGA (Rp) KET

. 210 cm X 108 cm X 6 mm bh 65,000


. 240 cm X 108 cm X 6 mm bh 76,000
. 270 cm X 108 cm X 6 mm bh 96,000
. 300 cm X 108 cm X 6 mm bh 108,000
Asbes Gelombang Kecil
. 150 cm X 105 cm X 4 mm bh 44,700
. 180 cm X 105 cm X 4 mm bh 51,200
. 210 cm X 105 cm X 4 mm bh 52,600
. 240 cm X 105 cm X 4 mm bh 59,000
. 270 cm X 105 cm X 4 mm bh 84,000
. 300 cm X 105 cm X 4 mm bh 90,500
. 300 cm X 108 cm X 6 mm bh 104,000
. 270 cm X 108 cm X 6 mm bh 94,500
. 240 cm X 108 cm X 6 mm bh 75,000
. 210 cm X 108 cm X 6 mm bh 65,000
. 180 cm X 108 cm X 6 mm bh 55,500

ONDULINE : 95 cm x 200cm x 0.3mm lbr 200,000


ONDUVILLA : 40cm x 106 cm x 0,3mm lbr 101,000
NOK Jabes nok bh 36,000
. Kerpus Genteng bh 33,000
. Stel Besar bh 35,000
. Paten Besar bh 52,000
Nokstel gelombang harflex
. Stel Besar bh 54,000
. Patent Besar bh 57,000
. Plat besar bh 64,500
NOK UNT ONDULINE & ONDUVILLA
Ukuran 50cm x 50 cm x 0,3mm lbr 100,000
galvalum berpasir 0.5 mm m2 213,120
8 ASBES PLAT
. 100cm X 100 cm X 3 mm bh 18,000
. 100cm X 100 cm X 4 mm bh 19,500
. 50 cm X 200 cm X 3 mm bh 16,400
. 40 cm X 200 cm X 3 mm bh 15,200
FIBER PLAT uk. 100cm x 100cm x 4mm lbr 31,000
unt Plafond uk. 120cm x 240cm x 4mm lbr 61,500
uk. 122cm x 244cm x 4mm lbr 68,000
GRC BOARD uk.122cm x 244cm x 5mm lbr 69,500
uk.122cm x 244cm x 6mm lbr 104,500
uk.122cm x 244cm x 8mm lbr 128,000
uk.122cm x 244cm x 10mm lbr 166,500

file:///conversion/tmp/activity_task_scratch/720096400.xlsx 99/451 hdb


NO. J E N I S B A H A N SAT HARGA (Rp) KET

9 FIBRE GLASS (JABES)


180 X 92 cm bh 55,000
200 X 92 cm bh 64,700
250 X 92 cm bh 75,500
180 X 105 cm bh 84,000
210 X 105 cm bh 100,000
250 X 105 cm bh 112,000
10 SENG PLAT
BJLS 0,18 lebar 55 cm m' 23,700
BJLS 0,20 lebar 55 cm m' 25,200
BJLS 0,28 lebar 55 cm m' 33,700
BJLS 0,30 lebar 55 cm m' 36,200
11 SENG GELOMBANG
BJLS 0,18 panjang 180 cm lbr 62,200
BJLS 0,20 panjang 180 cm lbr 65,200
BJLS 0,30 panjang 180 cm lbr 101,500
BJLS 0,40 panjang 180 cm lbr 112,000
Rooflight 90 x 180 lbr 175,000

III . B A H A N K A Y U
1 JATI Papan m3 20,183,200
Balok/pesagen m3 19,863,000
2 KAMPER Papan m3 14,096,500
Balok/pesagen m3 12,174,000
3 KRUING Papan m3 12,196,200
Balok/pesagen m3 9,887,500
4 MERANTI Papan m3 6,979,000
Balok/pesagen m3 7,162,000
5 TAHUN KELAS I Papan m3 3,176,200
Balok/pesagen m3 3,008,200
TAHUN KELAS II Papan m3 3,135,000
Balok/pesagen m3 2,887,000
6 BENGKIRAI Papan m3 15,132,700
Balok/pesagen m3 12,764,500
7 DOLKEN Sedang 8 x 10 x 400 cm bt 34,700
Kecil 6 x 7 x 400 cm bt 12,400
Besar 10 x 12 x 400 cm bt 16,000
Kayu cetakan m3 3,124,000
Kayu bakar m3 214,200
Bambu bt 17,500
Kayu Galam φ (8-10) cm, panjang 4 m bt 14,000
Kayu Glugu Tua Utuh ( > 6 m) bt 495,000

IV . BAHAN PENUTUP DINDING / LANTAI


1 UBIN (TEGEL BIASA)
PC polos 30 X 30 cm m2 68,000
20 X 20 cm m2 77,000
PC warna 30 X 30 cm m2 79,500

file:///conversion/tmp/activity_task_scratch/720096400.xlsx 100/451 hdb


NO. J E N I S B A H A N SAT HARGA (Rp) KET

20 X 20 cm m2 80,500
Teraso 30 X 30 cm m2 89,500
2 TEGEL PLINT
PC warna 10 X 20 cm bh 1,700
PC abu-abu 15 x 20 bh 1,500

3 POLIS UBIN Lantai/badan m' 3,300


Plint m' 3,100
Trap m' 3,400

4 UBIN PORSELIN
Lokal 11 X 11 putih dos 83,200
11 X 11 warna dos 89,500
Lokal 15 X 15 putih dos 89,500
15 X 15 warna dos 93,700
5 MOZAIK PORSELIN
10 X 20 cm m2 95,700
15 X 15 cm m2 91,200
20 X 20 cm m2 106,000
20 X 25 cm m2 108,000
30 x 60 cm m2 180,000

6 Keramik 30 X 30 cm m2 57,500
20 X 20 cm m2 64,500
33 x 33 cm m2 71,000
25 x 25 cm m2 74,000
15 x 20 cm m2 88,700
40 x 40 cm m2 70,000
50 x 50 cm m2 78,000
60 x 60 cm m2 128,000
20 x 40 cm m2 111,000
25 x 40 cm m2 88,800
30 x 60 cm m2 138,750
Border Kramik 10 x 33 m2 90,000
Plin Kramik 10 x 10 bh 5,000
Plin Kramik 10 x 20 bh 9,000
Plin Kramik 5 x 20 bh 5,500

7 Parquet Jati m2 320,200


8 Batu Paros m2 134,200
9 Batu Tempel Hitam m2 159,700
10 GRANITO 40 x 40 cm m2 173,700
30 x 30 cm m2 166,000
60 x 60 cm m2 311,000
plint biasa motif 10 x 40 cm buah 16,650
10 x 30 cm buah 16,650
plint granit 10 x 60 cm buah 15,540
11 Marmer m2 907,700

12 Wallpaper Dinding 0,5 m x 10 m m' 42,000

file:///conversion/tmp/activity_task_scratch/720096400.xlsx 101/451 hdb


NO. J E N I S B A H A N SAT HARGA (Rp) KET

V.BAHAN CETAK
1 BUIS BETON Ø 10 cm - 100 cm bh 97,000
Ø 20 cm - 100 cm bh 102,000
Ø 30 cm - 100 cm bh 112,500
Ø 50 cm - 100 cm bh 166,500
Ø 60 cm - 100 cm bh 234,000
Ø 70 cm - 100 cm bh 296,500
Ø 80 cm - 100 cm bh 402,500
Ø 100 cm - 100 cm bh 575,000
U 10 cm - 100 cm bh 60,200
U 15 cm - 100 cm bh 83,500
U 20 cm - 100 cm bh 83,500
U 30 cm - 100 cm bh 101,500
U 50 cm - 100 cm bh 122,700
U 60 cm - 100 cm bh 169,700
Gorong-Gorong bertulang 60,000
Ø 20 cm - 100 cm 75,000
Ø 30 cm - 100 cm
Ø 50 cm - 100 cm
Ø 60 cm - 100 cm
Ø 70 cm - 100 cm
Ø 80 cm - 100 cm
Ø 100 cm - 100 cm
2 LUBANG ANGIN (ROSTER) PC + PASIR
10 X 20 cm box 10,000
20 X 20 cm box 23,000
25 X 25 cm box 30,000
30 X 30 cm box 50,000
15 X 25 cm box 11,000
15 X 30 cm box 13,700
3 Bata Roster (5 X 11 X 22) cm bh 4,000
Roster R1 bh 25,000
4 Bata Ringan ( Herbel t : 7,5 cm) bh 8,200
Bata Ringan ( Herbel t : 10 cm) bh 10,100
5 Panel Beton Pracetak lbr 162,062
Kolom Beton Pracetak btg 416,250

VI . B A H A N B E S I
1 BESI BETON besi beton polos kg 17,000
besi beton prestress kg 17,000
besi beton ulir kg 18,000
besi IWF kg 20,200
Besi scuare tube m 17,500
Besi lis kaca (1 x 1) cm m 17,000
2 BESI PLAT Besi Strip kg 19,000
Besi Strip m' 6,000
Kawat Seling 1/2'' m' 52,000
Kawat Seling 1'' m' 172,000
3 BESI PROFIL Besi Profil kg 17,000
Besi Scuare tube m' 10,000
Besi List kaca 1 x 1 cm m' 8,000
Alumunium Strip m' 122,000
a BAJA RINGAN

file:///conversion/tmp/activity_task_scratch/720096400.xlsx 102/451 hdb


NO. J E N I S B A H A N SAT HARGA (Rp) KET

GALVALUME lebar : 7,5cm tebal : 1mm btg 143,500 panj : 6 m


type CT 75 lebar : 7,5cm tebal : 0.75mm btg 111,000 panj : 6 m
lebar : 7,5cm tebal : 0,65mm btg 104,000 panj : 6 m
lebar : 7,5cm kg 16,800

file:///conversion/tmp/activity_task_scratch/720096400.xlsx 103/451 hdb


NO. J E N I S B A H A N SAT HARGA (Rp) KET

b type RT 12 tinggi : 3,5 cm, tebal : 0,45mm btg 54,000 panj : 6 m


type RT 10 tinggi : 3,0 cm, tebal : 0,45mm btg 49,000 panj : 6 m
c HOLLOW GALVANIS LIPAT
tinggi 2 cm; tebal : 0,3 mm btg 27,000 panj : 4 m
tinggi 4 cm; tebal : 0,3 mm btg 30,500 panj : 4 m
Besi Hollow 4 cm x 4 cm x 0,2 cm btg 170,000 panj : 6 m

4 JARING - JARING BAJA


Diameter 4 - 15 kg 17,000
Diameter 6 - 15 kg 17,000
Kawat Bronjong kg 28,000
5 BESI SIKU L 40 X 40 X 4 btg 138,000
L 50 X 50 X 5 btg 141,000
L 60 X 60 X 6 btg 325,000

6 KAWAT - Ikat beton/bendrat kg 28,000


- Harmonika 12 X 45 mm m2 3,500
- Harmonika 12 X 24 mm m2 37,000
- Harmonika 14 X 30 mm m2 38,000
- Harmonika 14 X 35 mm m2 42,000
- Kawat Nyamuk Nylon m2 25,000
- Kawat Kasa m2 28,000
- Saringan pasir m2 19,500
- Kawat loket m2 38,000
- Kawat duri rol 83,250
- Kawat bronjong kg 28,000
- Kawat las kg 55,000
- Wiremesh m 6 2,1 m x 5,2 m lembar 550,000 15,823
- Wiremesh m 8 2,1 m x 5,2 m lembar 816,000 13,206
- Wiremesh m 10 2,1 m x 5,2 m lembar 1,149,000

VII . B A H A N P I P A
1 Pipa PVC SII SCJ , S - 12,5 (10 bar)
Pipa PVC DN 20 ( ½" ) AW JIS btg 27,500 panjang 4 m
Pipa PVC DN 25 ( ¾" ) AW JIS btg 35,200 panjang 4 m
Pipa PVC DN 32 ( 1" ) AW JIS btg 55,500 panjang 4 m
Pipa PVC diameter 1,25" 56,000 panjang 4 m
Pipa PVC DN 40 ( 1½" ) btg 78,000 panjang 4 m
Pipa PVC DN 63 ( 2" ) btg 101,000 panjang 4 m
Pipa PVC diameter 2,5" btg 150,000 panjang 4 m
Pipa PVC DN 90 ( 3" ) btg 198,000 panjang 4 m
Pipa PVC DN 110 ( 4" ) btg 292,000 panjang 4 m
Pipa PVC DN 160 ( 6" ) btg 682,500 panjang 4 m
Pipa PVC DN 200 ( 8" ) btg 1,129,200 panjang 4 m
Pipa PVC DN 250 ( 10" ) btg 1,775,000 panjang 4 m
Pipa PVC DN 315 ( 12" ) btg 2,496,700 panjang 4 m
Pipa PVC diameter 1,5" btg 138,500 panjang 6 m
Pipa PVC diameter 2" btg 203,000 panjang 6 m
Pipa PVC diameter 2,5" btg 290,000 panjang 6 m
Pipa PVC diameter 3" btg 419,000 panjang 6 m
Pipa PVC diameter 4" btg 614,000 panjang 6 m

file:///conversion/tmp/activity_task_scratch/720096400.xlsx 104/451 hdb


NO. J E N I S B A H A N SAT HARGA (Rp) KET

Pipa Tanah Jenis Pipa Limbah DN 15 cm btg 400,000 panjang 4 m

2 Pipa Medium B Galvanis - SII


Pipa Medium B Galvanis DN ½" btg 113,000 panjang 6 m
Pipa Medium B Galvanis DN 25 ( ¾" ) btg 136,000 panjang 6 m
Pipa Medium B Galvanis DN 32 ( 1" ) btg 190,000 panjang 6 m
Pipa Medium B Galvanis DN 50 ( 1½" ) btg 275,000 panjang 6 m
Pipa Medium B Galvanis DN 63 ( 2" ) btg 355,000 panjang 6 m
Pipa Medium B Galvanis DN 2½" btg 436,000 panjang 6 m
Pipa Medium B Galvanis DN 90 ( 3" ) btg 651,000 panjang 6 m
Pipa Medium B Galvanis DN 110 ( 4" ) btg 1,106,000 panjang 6 m
Pipa Medium B Galvanis DN 160 ( 6" ) btg 2,492,000 panjang 6 m
Pipa Medium B Galvanis DN 200 ( 8" ) btg 5,305,000 panjang 6 m
Pipa Medium B Galvanis DN 250 ( 10") btg panjang 6 m

3 Pipa PVC AW
Pipa PVC dia 1/2" btg 26,000 pnj : 4 m
Pipa PVC dia 3/4" btg 36,500 pnj : 4 m
Pipa PVC dia 1" btg 47,500 pnj : 4 m
Pipa PVC DN 40 ( 1½" ) btg 88,000 pnj : 4 m
Pipa PVC DN 63 ( 2" ) btg 137,000 pnj : 4 m
Pipa PVC DN 67 ( 2,5" ) btg 158,000 pnj : 4 m
Pipa PVC DN 90 ( 3" ) btg 183,000 pnj : 4 m
Pipa PVC DN 110 ( 4" ) btg 332,000 pnj : 4 m
Pipa PVC DN 160 ( 6" ) btg 705,000 pnj : 4 m
Pipa PVC DN 200 ( 8" ) btg 1,173,000 pnj : 4 m
Pipa PVC DN 250 ( 10" ) btg 1,832,000 pnj : 4 m
Pipa PVC DN 315 ( 12" ) btg 2,635,000 pnj : 4 m
Pipa PVC D 2" btg 69,930 pnj : 4 m
Pipa PVC D 2.5" btg 95,460 pnj : 4 m
Pipa PVC D 3" btg 125,985 pnj : 4 m
Pipa PVC D 4" btg 197,580 pnj : 4 m
Pipa PVC D 5" btg 305,250 pnj : 4 m
Pipa PVC D 6" btg 405,150 pnj : 4 m
Pipa PVC D 8" btg 704,850 pnj : 4 m
Pipa PVC D 10" btg 1,165,500 pnj : 4 m
Pipa PVC D 12" btg 1,631,700 pnj : 4 m

4 Pipa HDPE
pipa HDPE Ø 20 mm m' 25,000
pipa HDPE Ø 32 mm m' 32,500
pipa HDPE Ø 40 mm m' 40,000
pipa HDPE Ø 63 mm m' 50,000
pipa HDPE Ø 100 mm m' 102,500
pipa HDPE Ø 125 mm m' 167,500
pipa HDPE Ø 150 mm m' 320,200
pipa HDPE Ø 200 mm m' 499,700
pipa HDPE Ø 250 mm m' 788,500
pipa HDPE Ø 300 mm m' 1,255,500
pipa HDPE Ø 400 mm m' 1,922,000
pipa HDPE Ø 450 mm m' 2,563,000
pipa HDPE Ø 500 mm m' 3,139,500

file:///conversion/tmp/activity_task_scratch/720096400.xlsx 105/451 hdb


NO. J E N I S B A H A N SAT HARGA (Rp) KET

pipa HDPE Ø 600 mm m' 4,933,700


pipa HDPE Ø 800 mm m' 7,880,700
pipa HDPE Ø 900 mm m' 9,031,000
pipa HDPE Ø 1000 mm m' 10,124,000
pipa HDPE Ø 1100 mm m' 11,467,000
pipa HDPE Ø 1200 mm m' 12,830,000

5 Pipa GIP
pipa GIP Ø 63 mm (Medium SII) btg 1,217,700 pnj : 6 m
pipa GIP Ø 100 mm (Medium SII) btg 2,243,000 pnj : 6 m
pipa GIP Ø 125 mm (Medium SII) btg 3,011,700 pnj : 6 m
pipa GIP Ø 150 mm (Medium SII) btg 3,652,200 pnj : 6 m
pipa GIP Ø 200 mm (Medium SII) btg 5,254,000 pnj : 6 m

6 Pipa Baja
pipa baja Ø 63 mm batang 833,000 pnj : 6 m
pipa baja Ø 100 mm batang 1,601,700 pnj : 6 m
pipa baja Ø 125 mm batang 3,011,000 pnj : 6 m
pipa baja Ø 150 mm batang 3,107,500 pnj : 6 m
pipa baja Ø 200 mm batang 4,677,500 pnj : 6 m
pipa baja Ø 250 mm batang 7,317,000 pnj : 6 m
pipa baja Ø 300 mm batang 9,611,000 pnj : 6 m
pipa baja Ø 400 mm batang 14,801,000 pnj : 6 m
pipa baja Ø 450 mm batang 18,581,500 pnj : 6 m
pipa baja Ø 500 mm batang 22,746,200 pnj : 6 m
pipa baja Ø 600 mm batang 32,357,700 pnj : 6 m

7 Pipa Spiral
Pipa Spiral diameter 1,25" m' 24,900
Pipa Spiral diameter 1,5" m' 25,900
Pipa Spiral diameter 2" m' 35,000
Pipa Spiral diameter 3" m' 60,000
Pipa Spiral diameter 4" m' 139,900
Pipa Spiral diameter 6" m' 319,900

8 Aksesoris Pipa
Pipa Fitting PVC – ELBOW (D-DL) 1 1/4″ buah 4,000
Pipa Fitting PVC – ELBOW (D-DL) 1 1/2″ buah 8,400
Pipa Fitting PVC – ELBOW (D-DL) 2″ buah 13,000
Pipa Fitting PVC – ELBOW (D-DL) 2 1/2″ buah 14,200
Pipa Fitting PVC – ELBOW (D-DL) 3″ buah 21,000
Pipa Fitting PVC – ELBOW (D-DL) 4″ buah 36,500
Pipa Fitting PVC – ELBOW (D-DL) 5″ buah 86,500
Pipa Fitting PVC – ELBOW (D-DL) 6″ buah 91,000
Pipa Fitting PVC – ELBOW (D-DL) 8″ buah 229,000
Pipa Fitting PVC – ELBOW (D-DL) 10″ buah 441,500
Pipa Fitting PVC – ELBOW (D-DL) 12″ buah 602,000
Pipa Fitting PVC – SOCKET (D-DS) 1 1/4″ buah 6,000
Pipa Fitting PVC – SOCKET (D-DS) 1 1/2″ buah 8,000
Pipa Fitting PVC – SOCKET (D-DS) 2″ buah 10,600
Pipa Fitting PVC – SOCKET (D-DS) 2 1/2″ buah 5,000
Pipa Fitting PVC – SOCKET (D-DS) 3″ buah 19,500

file:///conversion/tmp/activity_task_scratch/720096400.xlsx 106/451 hdb


NO. J E N I S B A H A N SAT HARGA (Rp) KET

Pipa Fitting PVC – SOCKET (D-DS) 4″ buah 33,000


Pipa Fitting PVC – SOCKET (D-DS) 5″ buah 45,000
Pipa Fitting PVC – SOCKET (D-DS) 6″ buah 51,000
Pipa Fitting PVC – SOCKET (D-DS) 8″ buah 112,000
Pipa Fitting PVC – SOCKET (D-DS) 10″ buah 171,000
Pipa Fitting PVC – TEE (D-DT) 1 1/4″ buah 5,000
Pipa Fitting PVC – TEE (D-DT) 1 1/2″ buah 13,700
Pipa Fitting PVC – TEE (D-DT) 2″ buah 18,500
Pipa Fitting PVC – TEE (D-DT) 2 1/2″ buah 20,000
Pipa Fitting PVC – TEE (D-DT) 3″ x 1 1/2″ buah 11,000
Pipa Fitting PVC – TEE (D-DT) 3″ x 2″ buah 31,000
Pipa Fitting PVC – TEE (D-DT) 3″ x 2 1/2″ buah 14,000
Pipa Fitting PVC – TEE (D-DT) 3″ buah 40,000
Pipa Fitting PVC – TEE (D-DT) 4″ x 2″ buah 20,500
Pipa Fitting PVC – TEE (D-DT) 4″ x 3″ buah 25,000
Pipa Fitting PVC – TEE (D-DT) 4″ buah 69,500
Pipa Fitting PVC – TEE (D-DT) 5″ x 4″ buah 40,000
Pipa Fitting PVC – TEE (D-DT) 5″ buah 44,000
Pipa Fitting PVC – TEE (D-DT) 6″ x 4″ buah 58,000
Pipa Fitting PVC – TEE (D-DT) 6″ buah 195,000
Pipa Fitting PVC – TEE (D-DT) 8″ x 4″ buah 79,000
Pipa Fitting PVC – TEE (D-DT) 8″ buah 267,000
Pipa Fitting PVC – INCREASER (D-IN) 1 1/2″ x 1 1/4″ (Rucika) buah 4,000
Pipa Fitting PVC – INCREASER (D-IN) 2″ x 1 1/4″ buah 6,000
Pipa Fitting PVC – INCREASER (D-IN) 2″ x 1 1/2″ buah 7,000
Pipa Fitting PVC – INCREASER (D-IN) 2 1/2″ x 1 1/2″ buah 8,000
Pipa Fitting PVC – INCREASER (D-IN) 2 1/2″ x 2″ buah 9,000
Pipa Fitting PVC – INCREASER (D-IN) 3″ x 1 1/2″ buah 10,000
Pipa Fitting PVC – INCREASER (D-IN) 3″ x 2″ buah 12,000
Pipa Fitting PVC – INCREASER (D-IN) 3″ x 2 1/2″ buah 17,800
Pipa Fitting PVC – INCREASER (D-IN) 4″ x 2″ buah 24,400
Pipa Fitting PVC – INCREASER (D-IN) 4″ x 2 1/2″ buah 22,000
Pipa Fitting PVC – INCREASER (D-IN) 4″ x 3″ buah 24,000
Pipa Fitting PVC – INCREASER (D-IN) 5″ x 4″ buah 47,000
Pipa Fitting PVC – INCREASER (D-IN) 6″ x 3″ buah 64,000
Pipa Fitting PVC – INCREASER (D-IN) 6″ x 4″ buah 80,000
Pipa Fitting PVC – INCREASER (D-IN) 6″ x 5″ buah 77,000
Pipa Fitting PVC – INCREASER (D-IN) 8″ x 4″ buah 114,500
Pipa Fitting PVC – INCREASER (D-IN) 8″ x 6″ buah 127,700
Pipa Fitting PVC – CAP (D) 1 1/4″ buah 4,000
Pipa Fitting PVC – CAP (D) 1 1/2″ buah 8,000
Pipa Fitting PVC – CAP (D) 2″ buah 9,000
Pipa Fitting PVC – CAP (D) 3″ buah 13,700
Pipa Fitting PVC – CAP (D) 4″ buah 25,000
Fitting PVC – SOCKET (AW) 1/2″ buah 3,500
Fitting PVC – SOCKET (AW) 3/4″ buah 4,200
Fitting PVC – SOCKET (AW) 1″ buah 5,800
Fitting PVC – SOCKET (AW) 1 1/4″ buah 7,200
Fitting PVC – SOCKET (AW) 1 1/2″ buah 9,000
Fitting PVC – SOCKET (AW) 2″ buah 9,000
Fitting PVC – SOCKET (AW) 2 1/2″ buah 22,000
Fitting PVC – SOCKET (AW) 3″ buah 43,000
Fitting PVC – SOCKET (AW) 4″ buah 69,500

file:///conversion/tmp/activity_task_scratch/720096400.xlsx 107/451 hdb


NO. J E N I S B A H A N SAT HARGA (Rp) KET

Fitting PVC – SOCKET (AW) 6″ buah 117,000


Fitting PVC – SOCKET (AW) 8″ buah 249,000
Fitting PVC – SOCKET (AW) 10″ buah 359,000
Fitting PVC – VALVE SOCKET (AW) 1/2″ buah 3,000
Fitting PVC – VALVE SOCKET (AW) 1/2″ x 3/4″ buah 3,000
Fitting PVC – VALVE SOCKET (AW) 3/4″ buah 4,000
Fitting PVC – VALVE SOCKET (AW) 1″ x 1/2″ buah 4,000
Fitting PVC – VALVE SOCKET (AW) 1″ x 3/4″ buah 5,000
Fitting PVC – VALVE SOCKET (AW) 1″ buah 6,000
Fitting PVC – VALVE SOCKET (AW) 1 1/4″ buah 4,200
Fitting PVC – VALVE SOCKET (AW) 1 1/2″ buah 10,500
Fitting PVC – VALVE SOCKET (AW) 2″ buah 13,000
Fitting PVC – VALVE SOCKET (AW) 3 '' buah 38,000
Fitting PVC – VALVE SOCKET (AW) 4″ buah 50,200
Fitting PVC – FAUCET SOCKET (AW) 1/2″ buah 4,000
Fitting PVC – FAUCET SOCKET (AW) 1/2″ x 3/4″ buah 4,000
Fitting PVC – FAUCET SOCKET (AW) 3/4″ buah 4,000
Fitting PVC – FAUCET SOCKET (AW) 1″ x 1/2″ buah 6,000
Fitting PVC – FAUCET SOCKET (AW) 1″ x 3/4″ buah 6,500
Fitting PVC – FAUCET SOCKET (AW) 1″ buah 6,500
Fitting PVC – FAUCET SOCKET (AW) 1 1/4″ buah 8,000
Fitting PVC – FAUCET SOCKET (AW) 1 1/2″ buah 4,000
Fitting PVC – FAUCET SOCKET (AW) 2″ buah 11,000
Fitting PVC – TEE (AW) 1/2″ buah 5,000
Fitting PVC – TEE (AW) 3/4″ x 1/2″ buah 5,000
Fitting PVC – TEE (AW) 3/4″ buah 5,000
Fitting PVC – TEE (AW) 1″ x 1/2″ buah 6,800
Fitting PVC – TEE (AW) 1″ x 3/4″ buah 7,600
Fitting PVC – TEE (AW) 1″ buah 8,200
Fitting PVC – TEE (AW) 1 1/4″ x 1/2″ buah 10,400
Fitting PVC – TEE (AW) 1 1/4″ x 3/4″ buah 11,000
Fitting PVC – TEE (AW) 1 1/4″ x 1″ buah 12,000
Fitting PVC – TEE (AW) 1 1/4″ buah 12,600
Fitting PVC – TEE (AW) 1 1/2″ x 1/2″ buah 14,000
Fitting PVC – TEE (AW) 1 1/2″ x 3/4″ buah 14,000
Fitting PVC – TEE (AW) 1 1/2″ x 1″ buah 14,000
Fitting PVC – TEE (AW) 1 1/2″ x 1 1/4″ buah 17,000
Fitting PVC – TEE (AW) 1 1/2″ buah 16,000
Fitting PVC – TEE (AW) 2″ x 1/2″ buah 17,500
Fitting PVC – TEE (AW) 2″ x 3/4″ buah 17,000
Fitting PVC – TEE (AW) 2″ x 1″ buah 17,000
Fitting PVC – TEE (AW) 2″ x 1 1/4″ buah 27,000
Fitting PVC – TEE (AW) 2″ x 1 1/2″ buah 22,000
Fitting PVC – TEE (AW) 2″ buah 22,000
Fitting PVC – TEE (AW) 2 1/2″ buah 36,000
Fitting PVC – TEE (AW) 3″ x 2″ buah 42,000
Fitting PVC – TEE (AW) 3″ buah 53,000
Fitting PVC – TEE (AW) 4″ buah 98,000
Fitting PVC – TEE (AW) 6″ buah 259,000
Fitting PVC – TEE (AW) 8″ buah 515,000

9 Lain - Lain
Clam Sadle CI 1" X 1/2" buah 34,000

file:///conversion/tmp/activity_task_scratch/720096400.xlsx 108/451 hdb


NO. J E N I S B A H A N SAT HARGA (Rp) KET

Clam Sadle CI 1" X 3/4" buah 34,000


Clam Sadle CI 1,25" X 1/2" buah 39,000
Clam Sadle CI 1,25" X 3/4" buah 39,000
Clam Sadle CI 1,5" X 1/2" buah 40,000
Clam Sadle CI 1,5" X 3/4" buah 40,000
Clam Sadle CI 2" X 1/2" buah 43,000
Clam Sadle CI 2" X 3/4" buah 43,000
Clam Sadle CI 2" X 1" buah 43,000
Clam Sadle CI 3" X 1/2" buah 56,000
Clam Sadle CI 3" X 3/4" buah 56,000
Clam Sadle CI 3" X 1" buah 56,000
Doble Niple GI 1/2" buah 9,000
Doble Niple GI 3/4" buah 13,000
Doble Niple GI 1" buah 18,000
Doble Niple GI 1¼" buah 28,000
Doble Niple GI 1½" buah 33,000
Doble Niple GI 2" buah 52,000
Flange steel 1,5" buah 84,000
Flange steel GI 2" buah 89,000
Flange steel GI 3" buah 159,000
Flange steel GI 4" buah 192,000
Gate Valve CI 1,5" buah 382,000
Gate Valve CI 2" buah 509,000
Gate Valve CI 2,5" buah 1,206,000
Gate Valve CI 3" buah 1,801,200
Gate Valve CI 6" buah 5,018,000
Gate Valve CI 8" buah 8,785,000
Giboult Joint CI 2" buah 127,000
Giboult Joint CI 3" buah 192,000
Giboult Joint CI 4" buah 236,000
Giboult Joint CI 6" buah 446,000
Giboult Joint CI 8" buah 636,000
Stop Valve brass (katup) KITSU 3/4" buah 57,000
Stop Valve brass (katup) KITSU 1" buah 84,000
Stop Valve brass (katup) KITSU 1¼" buah 126,000
Stop Valve brass (katup) KITSU 1½" buah 182,000
Stop Valve brass (katup) KITSU 2" buah 299,000
Stop Valve brass (katup) KITSU 2,5" buah 509,000
Stop Valve brass (katup) KITSU 3" buah 604,000
Water Moor GI ¾" buah 40,000
Water Moor GI 1" buah 43,000
Water Moor GI 1¼" buah 60,000
Water Moor GI 1½" buah 78,000
Water Moor GI 2" buah 113,000
Clam Saddle PVC 1" X ½" buah 89,000
Clam Saddle PVC 1" X ¾" buah 89,000
Clam Saddle PVC 1,5" X ½" buah 34,000
Clam Saddle PVC 1,5" X ¾" buah 34,000
Clam Saddle PVC 2" X ½" buah 37,000
Clam Saddle PVC 2" X ¾" buah 38,000
Clam Saddle PVC 2" X 1" buah 38,000
Clam Saddle PVC 3" X ½" buah 51,000
Clam Saddle PVC 3" X ¾" buah 51,000

file:///conversion/tmp/activity_task_scratch/720096400.xlsx 109/451 hdb


NO. J E N I S B A H A N SAT HARGA (Rp) KET

Clam Saddle PVC 3" X 1" buah 51,000


Flange Socket RR PVC 1,5" buah 51,000
Flange Socket RR PVC 2" buah 96,000
Flange Socket RR PVC 3" buah 127,000
Flange Socket RR PVC 4" buah 158,000
Water Level Control buah 300,000
Tutup Meteran Fiber buah 71,000
Air Vent CI DN 2" (Kuningan) buah 71,000
Air Vent CI DN 1,5" (Kuningan) buah 350,000
Meter Air Ø 15 mm kuningan lengkap (coupling dengan segel pengaman ) ONDA buah 599,000
Meter Air Ø 15 mm kuningan lengkap (coupling dengan segel pengaman ) AMIKO buah 599,000
Meter Air Ø 15 mm kuningan lengkap (coupling dengan segel pengaman ) FA buah 599,000
Stop Kran (searah) Ø 15 mm (Kuningan) buah 64,000
Katup Searah Ø 15 mm (kuningan) buah 64,000
Double nepeel Ø 15 mm (kuningan) buah 12,000
Double nepeel ø 15 mm ( PVC RUCIKA WAVIN ) buah
Elbow socket 90 Gl ø 15 mm (Rucika Wavin) buah
Plug kran GI Ø 15 mm (kuningan) buah 59,000
Generator set kubota 14 pk buah 43,440,000
Kubota double stater 8,5 pk buah 22,385,000
Kubota 8,5 pk buah 51,734,000
Kubota double stater 11 pk buah 82,346,000
Pompa Air Sanchin model SCN 120 buah 6,820,000
Pompa Air Sanchin model SCN 45 buah 2,970,000
Check valve dia 1,5" (kuningan) buah 446,000
Check valve dia 2" (kuningan) buah 666,000
Stop Valve Brass Kitsu Dn 2" (kuningan) buah 229,000
Stop Valve Brass Kitsu Dn 4" (kuningan) buah 2,850,000
Valve Socket PVC 2" buah 666,000
Double nepeel dn 2x1,5 mm buah 700,000
Fot clep + screen dia 2" buah 446,000
Fot clep + screen dia 1,5" buah 285,000
Fleksibel joint dia 2" buah 1,017,000
Fleksibel joint dia 1,5" buah 826,000
Pompa Jet Pump 2" buah 1,837,000
Pompa Submersible Grounfosh SP 5A-17 buah 25,000,000
Pompa Submersible Grounfosh SP 5A-25 buah 40,000,000
Groundfosh Sp 5A - 52/5,5 kw/380 V/1,5" (210 m) buah 119,790,000
Groundfosh Sp 9A - 36/7,5 kw/380 V/2" (200 m) buah 113,100,000
Groundfosh Sp 9A - 56/11 kw/380 V/2" (300 m) buah 252,890,000
Groundfosh Sp 9A - 75/15 kw/380 V/2" (400 m) buah 319,440,000
Groundfosh N5 4 - 23 M/1"/175 watt/dlm sumur 8m/daya dorong 13,9 m/kapasitas buah 3,461,000
L/detik = 100 head 11/80 head 15,5/60 head 18/40 head 20 buah
Groundfosh N5 13 - 18 M/1,5"/400 watt/dlm sumur 8m/daya dorong 12,5 m/kapasitas buah 4,659,000
L/detik = 300 head 6,5/250 head 10/150 head 16/100 head 18 buah
Maxon Pump Sp 5A - 33/3 kw/380V/1,5" (200 m) buah
Maxon Pump Sp 3 - 52/4 kw/380V/1,25" (300 m) buah
Maxon Pump Sp 8 - 25/4 kw/380V/2" (150 m) buah
Maxon Pump Sp 2 - 65/3 kw/380V/1,25" (400 m) buah
Franklin + CND Sj 3 - 43/3 kw/380V/1,25" (200 m) buah
Franklin + CND Sj 3 - 43/4 kw/380V/1,5" (150 m) buah
Franklin + CND Sj 8 - 50/7,5 kw/380V/1,25" (200 m) buah

file:///conversion/tmp/activity_task_scratch/720096400.xlsx 110/451 hdb


NO. J E N I S B A H A N SAT HARGA (Rp) KET

VIII . B A H A N L A N G I T - L A N G I T
1 AKUSTIK-uk : 30 X 30 lbr 7,000
30 X 60 lbr 19,000
60 X 120 lbr 57,000
List Kayu Profil m' 18,500
List Gypsum profil buah 15,000
2 SOFT BOARD-uk: 4'X 8'
Gypsum tebal 9 mm lbr 69,000
kalsiboard tebal 3.5 mm lbr 62,160
3 HARD BOARD-uk: 4'X 8' lbr 66,000
GYPROC uk.120cmx240cmx9mm lbr 71500
4 PLY WOOD
Teak wood
90 X 210 X 3 mm lbr 92,000
. 120 X 240 X 3 mm lbr 102,500
. 90 X 210 X 4 mm lbr 106,200
. 90 X 210 X 9 mm lbr 142,000
. 90 X 210 X 12 mm lbr 176,700
. 90 X 210 X 15 mm lbr 221,500
. 90 X 210 X 18 mm lbr 291,000

file:///conversion/tmp/activity_task_scratch/720096400.xlsx 111/451 hdb


NO. J E N I S B A H A N SAT HARGA (Rp) KET

Tripleks
. 120 X 240 X 3 mm lbr 57,200
. 120 X 240 X 4 mm lbr 76,000
. 120 X 240 X 6 mm lbr 85,500
Multipleks
. 120 X 240 X 9 mm lbr 129,500
. 120 X 240 X 12 mm lbr 172,500
. 120 X 240 X 15 mm lbr 217,000
. 120 X 240 X 18 mm lbr 269,700
Formika ukuran pintu lbr 126,000

IX . B A H A N F I N I S H I N G
1 KAYU
Menie kg 14,000
Dempul plamur kg 38,000
Ambril/amplas m 17,500
Batu Apung kg 32,700
Cat dasar kg 51,000
. Emco kg 67,000
. Yunior 66 (nippon paint) kg 46,200
- Koas bh 18,000
. Deculux kg 48,500
. Siralax ons 14,000
. Spiritus ltr 15,500
. Plitur jadi ltr 67,000

2 TEMBOK
Kalkarium kg 7,300
Kapur sirih kg 3,600
Plamur kg 38,000
Cat Tembok Interior kg 33,078 setara catylac
Cat Tembox exterior kg 55,500 setara catylac
Sintex 5 kg 38,000
Danabride 5 kg 26,000
Catylac 5 kg 147,000
Mowilex 2,50 kg 118,000

file:///conversion/tmp/activity_task_scratch/720096400.xlsx 112/451 hdb


NO. J E N I S B A H A N SAT HARGA (Rp) KET

3 BESI
Menie kg 40,200
Cat mengkilat kg 69,500
Cat kg 32,500
Thinner A ltr 28,500
Minyak cat ltr 28,200
Thinner Super ltr 33,500
Residu (teer/aspal) ltr 18,500
Fibre glass (tanki air)
kapasitas 550 liter. bh 1,191,500
kapasitas 1100 liter. bh 1,968,200
Lem Aica Aibon kg 27,500
Cat Kedap Air kg 105,450

X.BAHAN KACA
1 POLOS 3 mm m2 89,000
5 mm m2 118,000
8 mm m2 277,500
2 ES KABUR 3 mm m2 94,500
5 mm m2 113,700
3 RAY BAND 3 mm m2 89,000
5 mm m2 121,000
12 mm m2 344,100

XI . BAHAN INSTALASI LISTRIK

1 KABEL LISTRIK
NYA : . 1 X 1 1/2 mm2 rol 200,000
SPLN LMK 1 X 2 1/2 mm2 rol 300,000
. 1X4 mm2 m' 6,000
1X6 mm2 m' 10,000
NYY :. 2 X 1 1/2 mm2 m' 8,500
SUPREME 2 X 2 1/2 mm2 m' 18,000
. 2X4 mm2 m' 35,000
2X6 mm2 m' 45,000
3 X 1 1/2 mm2 m' 17,500
3 X 2 1/2 mm2 m' 27,000
3X4 mm2 m' 45,000
3X6 mm2 m' 65,000

file:///conversion/tmp/activity_task_scratch/720096400.xlsx 113/451 hdb


NO. J E N I S B A H A N SAT HARGA (Rp) KET

NYM :. 2 X 1 1/2 mm2 m' 10,500


SUPREME 2 X 2 1/2 mm2 m' 18,000
. 2X4 mm2 m' 28,500
3 X 1 1/2 mm2 m' 20,000
3 X 2 1/2 mm2 m' 27,500
3X4 mm2 m' 38,000
3X6 mm2 m' 60,000

2 SKAKELAR
Out bauw . Seri bh 18,500
. Engkel bh 16,000
In bauw . Seri bh 16,000
. Engkel bh 16,000

3 FUSE BOX (SEKERING KASA)


1 group bh 51,000
2 group bh 59,000
3 group bh 59,500

4 STEKER - Biasa bh 8,500


Arde bh 10,000
T Biasa bh 22,000
T dengan Arde bh 27,200

5 FITING Flaon bh 13,000


Gantung bh 9,000
Kap bh 14,500
Kombinasi bh 16,500

6 STOP KONTAK - Arde Outbow putih bh 17,700


Arde Outbow hitam bh 11,500
Arde IB bh 17,500
Arde Putar bh 18,500

file:///conversion/tmp/activity_task_scratch/720096400.xlsx 114/451 hdb


NO. J E N I S B A H A N SAT HARGA (Rp) KET

XII . ALAT - ALAT PENGUNCI & PENGGANTUNG


1 KUNCI TANAM Union : 1 X slag bh 71,000
2 X slag bh 127,000
Yale : 1 X slag bh 120,200
2 X slag bh 144,700
Kuda : 1 X slag bh 71,000
2 X slag bh 82,200
Kunci Tanam Antik bh 170,000

2 ENGSEL DAN GERENDEL


Engsel Angin bh 19,200
Kupu-kupu biasa bh 17,000
Nylon kupu-kupu bh 9,500
Espagnoled - dalam negeri bh 34,500
Grendel Tanam luar negeri bh 94,500
Grendel biasa bh 121,700
Kunci Lemari bh 13,000
Kait Angin bh 16,000
Door Closer bh 702,200
Door Stop bh 78,200
Door holder bh 28,416
Spring Knip bh 61,050

XIII . BAHAN SANITAIR


1 KLOSET DUDUK bh 1,505,500
2 KLOSET JONGKOK bh 187,000
3 WASTAFEL PEDESTAL bh 150,000
4 WASTAFEL MEJA OVAL bh 803,000
5 WASTAFEL GANTUNG BULAT bh 440,500
6 WASTAFEL GANTUNG SUDUT bh 409,200
7 WASTAFEL GANTUNG SUDUT KECIL bh 275,700
8 WASTAFEL BAK CUCI bh 196,200
9 TEMPAT SABUN GANTUNG bh 42,500
10 TEMPAT SABUN TANAM bh 40,000
11 URINOIR bh 102,500
12 BATCHUIP bh 916,200
13 BAK FIBREGLAS bh 334,000
14 BAK CUCI PIRING bh 208,200

file:///conversion/tmp/activity_task_scratch/720096400.xlsx 115/451 hdb


NO. J E N I S B A H A N SAT HARGA (Rp) KET

15 SEPTIC TANK (ETERNIT GRESIK)


5 Pemakai 500 liter unit 1,857,500
10 Pemakai 1.000 liter unit 2,603,000
16 LAIN - LAIN
Kran Air bh 31,000
Seal tape bh 8,700
Floor drain bh 40,000
Water drain bh 57,000

XIV . ALAT PENGIKAT KAYU


1 PAKU - ukuran 1" s/d 4" kg 20,000
2 PAKU - payung kg 42,700
3 PAKU - sekrup kg 51,200 80 pcs
4 PAKU - beton kg 97,200
5 MUR BAUT (kuda-kuda) kg 28,700
6 ANGKUR BAUT bh 23,700
7 LEM KAYU bh 20,000
8 Tali Ijuk kg 8,500
Paku skrup 1 cm – 2,5 cm Buah 1,200
Paku Sekrup 3,5" kg 37,700
Skrup fixer buah 1,400
Paku pancing kg 17,500
XV . POMPA AIR.
1 POMPA AIR TANGAN
Dragon buatan Indonesia bh 600,000
2 POMPA AIR LISTRIK
Sanyo 100 watt bh 524,000
Fuji 250 watt bh 832,000
Shimizu . 100 watt bh 483,000
. 90 watt bh 475,000
Dab . 125 watt bh 399,000
. 175 watt bh 537,000

file:///conversion/tmp/activity_task_scratch/720096400.xlsx 116/451 hdb


NO. J E N I S B A H A N SAT HARGA (Rp) KET

X VI . PAVING BLOCK
1 SQUARE Abu-abu m2 76,200
Merah/hitam m2 87,200
2 HOLLAND Abu-abu m2 87,200
Merah/hitam m2 90,200
3 UNIDECOR Abu-abu m2 89,500
Merah/hitam m2 102,500
4 UNI Abu-abu m2 89,500
Merah/hitam m2 102,500
5 TRIHEX Abu-abu m2 89,500
Merah/hitam m2 102,500
6 OLYMPIA HEXA Abu-abu m2 89,500
7 HEXAGONAL Abu-abu m2 89,700
Merah/hitam m2 102,700
8 CASTLE Abu-abu m2 102,500
9 TRAPEZ Abu-abu m2 89,500
10 TRAPEZ GRASS BLOCK
Abu-abu m2 89,500
11 STANDARD GRASS BLOCK ABU-ABU BH 10,000
12 BATACO BH 6,000
13 KANSTEEN m' 77,000
XVII. L A I N - L A I N
1 KREI 25 MM m2 55,200
2 Sliding Pintu J4 bh 247,000
3 Naco per Daun bh 218,000
4 Rolling door Besi m2 440,000
Rolling door Almunium m2 450,000
5 Awning Almunium m2 256,500
6 Kusen Almunium 4" Putih m' 102,500
7 WIDE FLANGE BEAM
150 X 75 X 5 X 7 X 12 btg 1,345,500
8 ACP m2 240,000
9 Atap Galvalume m2 55,000
Nok Galvalume m1
10 Atap PVC (Alderon) m2 195,000
Nok PVC (Alderon) m1
11 Talang PVC m2 144,000
12 Talang Fiber m2 180,000
13 Plafon PVC m2 161,000
Kusen UPVC
Pintu UPVC
Jendela UPVC
8 ASPAL.
Aspal Ex Pertamina isi Net 160 kg drum 1,632,000

Hotmix Tebal = 4 Cm m2 180,000


Hotmix Tebal = 5 Cm m2 190,000
Hotmix Tebal = 6 Cm m2 190,000
Hotmix Tebal = 7 Cm m2 210,000
Binder Course ton 950,000
Wearing Course ton 1,000,000
Hot Roller Sheet ton

file:///conversion/tmp/activity_task_scratch/720096400.xlsx 117/451 hdb


NO. J E N I S B A H A N SAT HARGA (Rp) KET

Sand Sheet ton 1,150,000


Sand Sheet Emulsi ton 11,000
Cold Mix ton
Prime / Tack Coard RC liter 11,000
Prime Coat MC liter
Prime / Tack Coat Emulsi liter
9 KACA
Cermin tebal 5 mm m2 175,000
Profil Kaca m' 34,000

10 PAGAR BRC. Pagar BRC 90 A2 /lb 370,500


Pagar BRC 120 A2 /lb 453,200
11 LAIN-LAIN
Minyak Beton & bekisting ltr 25,700
Pintu Lipat Besi m2 440,000
Sunscreen Allumunim m2 115,500
Allumunium Foil m2 16,000
skrup fixer bh 700
Venetions Blinds atau Vertical Blinds (tirai) m2 183,000
Soda api kg 25,000
Bilik Bambu m2 56,500
Sabun kg 36,700
Air m3 5,000
Koas Alang-alang ikat 3,000
Solar (Industri) ltr 11,700
Premium (Industri) ltr 12,700
Pelumas ltr 36,000
Teak Oil ltr 47,000
Sealant Tube 40,200
Vernis ltr 80,000
Plastic Aerotor bh 23,000
Vynil 30x30 cm bh 10,000
Karpet m2 46,200
Wallpaper Kelas I roll 420,000
Wallpaper Kelas II roll 231,500
Formite/penjaga bekisting/spacer Buah 7,700
kawat las kg 55,000
Sewa Alat Las Listrik Jam 12,500
Alluminium strip m’ 10,000
Profil kaca m 34,000
Rooflight 90 x 180 Lbr 152,000
Strorox – 100 liter 58,000 damdex

DAFTAR HARGA SATUAN UNTUK HSBGN 2021 YANG BELUM ADA DI DATA SURVEY 2020

BAHAN BAJA
Besi Tempa m2 319,000
Rangka Atap Baja Ringan m2 Smart Truss;Prima Truss
BAHAN ALMUNIUM 143,000
Rangka Jendela Almunium m' 122,000 Alexindo
Rangka Pintu Almunium m' 122,000 Alexindo
Kusen & Pintu PVC Toilet unit 605,000 Maspion
Handle Pintu bh 82,000 Ex. Cisa

file:///conversion/tmp/activity_task_scratch/720096400.xlsx 118/451 hdb


NO. J E N I S B A H A N SAT HARGA (Rp) KET

Selinder bh 55,000 Ex. Cisa


Slot Tanam bh 242,000
BAHAN LANTAI DAN DINDING KERAMIK
Plint Keramik 10/30 cm bh 11,000 Ex. Roman
Plint Granitetile 10/40 cm bh 22,000 Ex. Granito
BAHAN PENUTUP ATAP
Genteng Keramik bh 35,000 Ex. Jatiwangi
Genteng Keramik Glazur bh 7,400 Ex. KANMURI
Nok Genteng Keramik bh 16,500 Ex. Jatiwangi
Nok Genteng Keramik Glazur bh 20,300 Ex. KANMURI
BAHAN KACA
Kaca Polos 8 mm m2 275,000
BAHAN FINISHING
Plamir Kayu kg 33,000
Wood Filler kg 38,700 Impra
BAHAN SANITARI
Shower Spray unit 435,000 Ex. Toto
Shower Set unit 1,511,000 Ex. Toto
Kran Zink bh 775,000 Ex. Toto
Kran Dinding bh 502,000 Ex. Toto
BAHAN PARTISI DINDING/PLAFON
List Profil 5 cm Gypsum m' 16,000
Rangka Plafon Metal Furing m2 137,000
BAHAN SALURAN AIR
Bak Kontrol Ø 60 Unit 737,500
Bak Kontrol Ø 40 Unit 443,700
Bak Kontrol Ø 30 Unit 298,700
Bak Penangkap Lemak Ø 30 Unit 686,200
Bak Penangkap Lemak Ø 60 Unit 418,000
Bak Penangkap Lemak Ø 40 Unit 220,000
Tutup Beton Ø 30 Unit 75,000
Stop Kran dia 1" bh 165,000 Ex. Onda
Tangki Air 1000 Liter bh 1,705,000 EXEL
Toren Fiberglas vol 300 liter bh 732,600
Toren Fiberglas vol 520 liter bh 1,098,900
Toren Fiberglas vol 650 liter bh 1,254,300
Toren Fiberglas vol 1050 liter bh 1,787,100
Toren Fiberglas vol 1500 liter bh 2,614,050
Toren Fiberglas vol 2000 liter bh 3,840,600
Toren Fiberglas vol 5000 liter bh 8,502,600
Tangki Air 500 Liter bh 1,045,000 EXEL
Pelampung Otomatis bh 80,000
Roof Drain Metal bh 88,000
Mesin Jet Pump Kap.250 Watt unit 4,372,000 Groundfos
Mesin Pompa Tekan kap. 150 Watt unit 3,036,000 Groundfos
PERALATAN ELEKTRIK
Pemasangan Meteran Baru 1300 Watt Unit 1,300,000
Pemasangan Meteran Baru 2200 Watt Unit 2,082,000
Pemasangan Meteran Baru 3200 Watt Unit 3,941,000
Pemasangan Meteran Baru 3500 Watt Unit
Pemasangan Meteran Baru 4500 Watt Unit
Tambah Daya KWH 1,352
Kabel LVTC m' 12,000

file:///conversion/tmp/activity_task_scratch/720096400.xlsx 119/451 hdb


NO. J E N I S B A H A N SAT HARGA (Rp) KET

Box Panel PVC Isi 4 MCB bh 46,000 Legram


MCB 6 A bh 71,000 Legram
MCB 4 A bh 52,000 Legram
Kabel NYM 2x2,5 mm m' 10,000
Kabel NYM 3x2,5 mm m' 13,000
Kabel Telephone 4 x 0,5 mm m' 11,000
Kabel UTP cat 6 m' 11,902
Pipa Conduit btg 17,600
Soket pipa bh 3,300
Tee doos bh 13,200
Klem pipa bh 3,800
fhiser bh 1,500
Isolasi bh 9,000
Lass Doop bh 15,000
Outlet TV bh 46,000 Broco
Outlet Telephone bh 46,000 Broco
Down Light/ PLC 13 Watt bh 132,000
Fitting Plafond +Lampu SL bh 68,000 Panasonic
Lammpu TL 2x18 Watt Grille bh 275,000 Panasonic
Lammpu TL 2x36 Watt Grille bh 352,000 Panasonic
Led Monitor 55" smart tv bh 8,500,000
Lampu rd 150 e27 ledbull 6w bh 54,000
Lampu rd 150 e27 ledbull 10w bh 68,000
Lampu rd 150 e27 ledbull 12w bh 82,000
Lampu RM M4 2xtl led master 18 w bh 660,000
Exit led bh 253,000
Stop kontak 16A ph umum bh 16,000
Stop kontak 16A ph lantai bh 858,000
Tray Cable uk 200x100 mm rol 605,000
Tray Cable uk 00x100 mm rol 730,000
Tray Cable uk 400x100 mm rol 883,000
Cable Ladder uk 200x100 mm rol 440,000
Cable Ladder uk 300x100 mm rol 495,000
Cable Ladder uk 400x100 mm rol 528,000
Kabel NYY 4x4 mm m'
Kabel NYY 4x6 mm m'
Kabel NYY 4x10 mm m'
Kabel NYY 4x16 mm m'
Kabel NYY 4x25 mm m' 410,000
Kabel NYY 4x35 mm m' 572,000
Kabel NYY 4x50 mm m' 759,000
Kabel NYY 4x70 mm m' 1,072,000
Kabel NYY 4x95 mm m' 1,479,000
Penangkal Petir Radius 135 meter bh 6,710,000
Bak Kontrol Precast Ø 30 cm bh 253,000
Bak Kontrol Precast Ø 40 cm bh 385,000
Bak Kontrol Precast Ø 60 cm bh 605,000
Bak Kontrol Precast Ø 32 cm (penangkap lemak/gestrep) bh 253,000
Leher Angsa bh 120,000
Pipa Air Limbah Ø 4" m' setara rucika 104,210
Pipa Air Limbah Ø 6" m' setara rucika 202,112
Pipa Air Limbah Ø 8" m' setara rucika 308,858
Pipa Air Limbah Ø 10" m' setara rucika 492,932

file:///conversion/tmp/activity_task_scratch/720096400.xlsx 120/451 hdb


NO. J E N I S B A H A N SAT HARGA (Rp) KET

Pipa Air Limbah Ø 12" m' setara rucika 768,176


Pipa Air Limbah Ø 16" m' setara rucika 1,248,214

Pipa air limbah SDR - 41 ø 8'' (Rucika Lite) batang 1,223,400 pnjng 6 meter
Formite/Penjaga jarak / Spacer (alat bantu) buah 8,000
Sewa Alat (las listrik) jam 13,000
karpet m2 65,000
underlayer m2 19,000
plint vinyl buah 6,500
Paku 12 cm buah 1,000
Ramset buah 13,000
Profil Allumunium "T" m' 13,000
Bambu btg 80,000

file:///conversion/tmp/activity_task_scratch/720096400.xlsx 121/451 hdb


DAFTAR HARGA SATUAN PEKERJAAN (AHSP) NO.28/PRT/M/2016
BIDANG CIPTA KARYA
SUMBER DATA : PASARAN BEBAS
D A E R A H : KABUPATEN KEBUMEN
EDISI 2023

HARGA
JUMLAH
BAHAN/UPAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN
Rp Rp
DIVISI I A. 1.1.1 K.3 HARGA SATUAN PEKERJAAN PERSIAPAN
Pembuatan 1 m2 pagar sementara dari kayu tinggi 2
A.1.1.1.1 1 m2 886,548.30
1 meter
A TENAGA 54,600.00
L.01 0.4 OH Pekerja 82,000.00 32,800.00
L.02 0.2 OH Tukang Kayu 90,000.00 18,000.00
L.03 0.02 OH Kepala Tukang 95,000.00 1,900.00
L.04 0.02 OH Mandor 95,000.00 1,900.00
B BAHAN 751,353.00
1.25 Btg Kayu Dolken diameter 8 - 10 / 400 cm 14,000.00 17,500.00
5.0 Kg Portalnd Semen 1,625.00 8,125.00
0.005 m3 Pasir Beton 376,000.00 1,880.00
0.009 m3 Koral Beton 372,000.00 3,348.00
0.072 m3 Kayu 5/7 9,887,500.00 711,900.00
0.06 Kg Paku Biasa 2" - 5" 20,000.00 1,200.00
0.40 liter Residu 18,500.00 7,400.00
C PERALATAN
D Jumlah A + B + C 805,953.00
E Overhead & Profit (contah 10%) 10% 80,595.30
F Harga Satuan Pekerjaan (D+E) 886,548.30

Pembuatan 1 m' pagar sementara dari seng


A.1.1.1.2 1 m' 981,662.55
1 gelombang
A TENAGA 56,200.00
L.01 0.2 OH Pekerja 82,000.00 16,400.00
L.02 0.4 OH Tukang Kayu 90,000.00 36,000.00
L.03 0.02 OH Kepala Tukang 95,000.00 1,900.00
L.04 0.02 OH Mandor 95,000.00 1,900.00
B BAHAN 836,220.50
1.25 Btg Kayu Dolken diameter 8 - 10 / 400 cm 14,000.00 17,500.00
2.5 Kg Portalnd Semen 1,625.00 4,062.50
1.2 Lbr Seng Gelombang 3" - 5" 65,200.00 78,240.00
0.005 m3 Pasir Beton 376,000.00 1,880.00
0.009 m3 Koral Beton 372,000.00 3,348.00
0.072 m3 Kayu 5/7X4m Kayu Kruing 9,887,500.00 711,900.00
0.06 Kg Paku Biasa 2" - 5" 20,000.00 1,200.00
0.45 Kg Meni Besi 40,200.00 18,090.00
C PERALATAN
D Jumlah A + B + C 892,420.50
E Overhead & Profit (contah 10%) 10% 89,242.05
F Harga Satuan Pekerjaan (D+E) 981,662.55

Pembuatan 1 m2 pagar sementara dari kawat duri


A.1.1.1.3 1 m2 1,131,548.00
1 tinggi 1.8 meter
A TENAGA 47,200.00
L.01 0.2 OH Pekerja 82,000.00 16,400.00
L.02 0.3 OH Tukang Kayu 90,000.00 27,000.00
L.03 0.02 OH Kepala Tukang 95,000.00 1,900.00
L.04 0.02 OH Mandor 95,000.00 1,900.00
B BAHAN 981,480.00
1.00 Btg Kayu Dolken diameter 8 - 10 / 400 cm 89,500.00 89,500.00
2.0 Kg Portalnd Semen 0.00 -
25.0 m' Kawat Duri 34,700.00 867,500.00
0.005 m3 Pasir Beton 0.00 -
0.009 m3 Koral Beton 60,000.00 540.00
0.06 Kg Paku Biasa 2" - 5" 399,000.00 23,940.00
C PERALATAN
D Jumlah A + B + C 1,028,680.00
E Overhead & Profit (contah 10%) 10% 102,868.00
F Harga Satuan Pekerjaan (D+E) 1,131,548.00

2 A.1.1.1.4 1 m' Pengukuran dan Pemasangan 1 m' Bouwplank 245,353.24


A Tenaga 18,625.00
L.01 0.1 OH Pekerja 82,000.00 8,200.00
L.02 0.1 OH Tukang Kayu 90,000.00 9,000.00
L.03 0.01 OH Kepala Tukang 95,000.00 950.00
L.04 0.005 OH Mandor 95,000.00 475.00
B Bahan 204,423.40
0.012 m3 Kayu 5/7x 4m Kayu Kruing 9,887,500.00 118,650.00
0.02 Kg Paku Biasa 2" - 5" 20,000.00 400.00
0.007 m3 Kayu Papan 3/20 Kruing 12,196,200.00 85,373.40
C PERALATAN
D Jumlah A + B + C 223,048.40
E Overhead & Profit (contah 10%) 10% 22,304.84
F Harga Satuan Pekerjaan (D+E) 245,353.24
3 A.1.1.1.5 K.3 1 m2 Pembuatan 1 m2 kantor sementara 2,866,468.00

A Tenaga 467,250.00
L.01 2 OH Pekerja 82,000.00 164,000.00
L.02 2 OH Tukang Kayu 90,000.00 180,000.00
L.02 1 OH Tukang Batu 90,000.00 90,000.00
L.03 0.3 OH Kepala Tukang 95,000.00 28,500.00
L.04 0.05 OH Mandor 95,000.00 4,750.00
B Bahan 2,138,630.00
1.25 Btg Kayu Dolken Ø 8 - 10 / 4 m 14,000.00 17,500.00
0.18 m3 Kayu (kruing) 9,887,500.00 1,779,750.00
0.80 Kg Paku Biasa 2" - 5" 20,000.00 16,000.00
1.1 Kg Besi Strip 19,000.00 20,900.00
35 Kg Portland Sement 1,625.00 56,875.00
0.15 m3 Pasir pasang 313,000.00 46,950.00
0.1 m3 Pasir Beton 376,000.00 37,600.00
0.15 m3 Koral Beton 372,000.00 55,800.00
30 buah Batu bata Merah 900.00 27,000.00
0.25 Lbr Seng Plat 23,700.00 5,925.00
0.20 buah Jendela Naco 218,000.00 43,600.00
0.08 m2 Kaca Polos 89,000.00 7,120.00
0.15 buah Kunci Tanam 127,000.00 19,050.00
0.06 Lbr Plywood 4 mm 76,000.00 4,560.00

C PERALATAN
D Jumlah A + B + C 2,605,880.00
E Overhead & Profit (contah 10%) 10% 260,588.00
F Harga Satuan Pekerjaan (D+E) 2,866,468.00

4 A.1.1.1.6 K.3 1 m2 Pembuatan 1 m2 gudang 2,388,705.00


A Tenaga 236,000.00
L.01 1 OH Pekerja 82,000.00 82,000.00
L.02 1.50 OH Tukang Kayu 90,000.00 135,000.00
L.03 0.15 OH Kepala Tukang 95,000.00 14,250.00
L.04 0.05 OH Mandor 95,000.00 4,750.00
B Bahan 1,935,550.00
3.00 Btg Kayu Dolken Ø 8 - 10 / 4 m 14,000.00 42,000.00
0.18 m3 Kayu (kruing) 9,887,500.00 1,779,750.00
0.80 Kg Paku Biasa 2" - 5" 20,000.00 16,000.00
1.50 Lbr Seng Gelombang 65,200.00 97,800.00
C PERALATAN
D Jumlah A + B + C 2,171,550.00
E Overhead & Profit (contah 10%) 10% 217,155.00
F Harga Satuan Pekerjaan (D+E) 2,388,705.00
5. A.1.1.1.7 K.3 1 m2 Pembuatan 1 m2 rumah jaga 2,482,526.75
A Tenaga 285,750.00
L.01 1 OH Pekerja 82,000.00 82,000.00
L.02 2 OH Tukang Kayu 90,000.00 180,000.00
L.03 0.2 OH Kepala Tukang 95,000.00 19,000.00
L.04 0.05 OH Mandor 95,000.00 4,750.00
B Bahan 2,250,917.50
1.7 Btg Kayu Dolken diameter 8 - 10 / 400 cm 14,000.00 23,800.00
0.21 m3 Kayu (kruing) 9,887,500.00 2,076,375.00
0.3 Kg Paku Biasa 2" - 5" 20,000.00 6,000.00
10.5 Kg Portland Semen 1,625.00 17,062.50
0.03 m3 Pasir Beton 376,000.00 11,280.00
0.05 m3 Koral Beton 372,000.00 18,600.00
1.5 Lbr Seng Gelombang 65,200.00 97,800.00
0.25 Lbr Seng Plat 23,700.00 5,925.00
C PERALATAN
D Jumlah A + B + C 2,256,842.50
E Overhead & Profit (contah 10%) 10% 225,684.25
F Harga Satuan Pekerjaan (D+E) 2,482,526.75

6. A.1.1.1.8 K.3 1 m2 Pembersihan 1 m2 dan Perataan lapangan 14,245.00


A Tenaga 12,950.00
L.01 0.1 OH Pekerja 82,000.00 8,200.00
L.04 0.05 OH Mandor 95,000.00 4,750.00
B Bahan
C PERALATAN
D Jumlah A + B + C 12,950.00
E Overhead & Profit (contah 10%) 10% 1,295.00
F Harga Satuan Pekerjaan (D+E) 14,245.00

7. A.1.1.1.9 K.3 1 m2 Pembuatan 1m2 Bedeng Pekerja 2,687,993.00


A Tenaga 285,750.00
L.01 1 OH Pekerja 82,000.00 82,000.00
L.02 2 OH Tukang Kayu 90,000.00 180,000.00
L.03 0.2 OH Kepala Tukang 95,000.00 19,000.00
L.04 0.05 OH Mandor 95,000.00 4,750.00
B Bahan 2,157,880.00
1.25 Btg Kayu Dolken diameter 8 - 10 / 400 cm 14,000.00 17,500.00
0.186 m3 Kayu (kruing) 9,887,500.00 1,839,075.00
0.30 Kg Paku Biasa 2" - 5" 20,000.00 6,000.00
18.00 Kg Portland Semen 1,625.00 29,250.00
0.03 m3 Pasir Beton 376,000.00 11,280.00
0.05 m3 Koral Beton 372,000.00 18,600.00
1.50 Lbr Seng Gelombang 65,200.00 97,800.00
1.35 Lbr Plywood 102,500.00 138,375.00
C PERALATAN
D Jumlah A + B + C 2,443,630.00
E Overhead & Profit (contah 10%) 10% 244,363.00
F Harga Satuan Pekerjaan (D+E) 2,687,993.00

8 A.1.1.1.10 1 m2 Pembuatan 1 m2 bak adukan 279,497.24

A Tenaga 29,850.00
L.02 0.30 OH Tukang Kayu 90,000.00 27,000.00
L.03 0.03 OH Kepala Tukang 95,000.00 2,850.00
B Bahan 224,238.40
0.036 m3 Kayu Papan Kelas III (tahun) 3,176,200.00 114,343.20
0.036 m3 Kayu Balok Kelas III 3,008,200.00 108,295.20
0.080 kg Paku Biasa 20,000.00 1,600.00
C PERALATAN
D Jumlah A + B + C 254,088.40
E Overhead & Profit (contah 10%) 10% 25,408.84
F Harga Satuan Pekerjaan (D+E) 279,497.24
9 A.1.1.1.11 K.3 1 m2 Pembuatan1 m2 Steger/Perancah dari Bambu sd Tinggi 6 meter 340,126.60
A Tenaga 285,750.00
L.01 1.00 OH Pekerja 82,000.00 82,000.00
L.02 2.00 OH Tukang Kayu 90,000.00 180,000.00
L.03 0.20 OH Kepala Tukang 95,000.00 19,000.00
L.04 0.05 OH Mandor 95,000.00 4,750.00
B Bahan 23,456.00
1.250 Btg Bambu diameter 6 - 8 / 600 cm 17,500.00 21,875.00
0.186 Kg Tali Ijuk 8,500.00 1,581.00
C PERALATAN
D Jumlah A + B + C 309,206.00
E Overhead & Profit (contah 10%) 10% 30,920.60
F Harga Satuan Pekerjaan (D+E) 340,126.60

10 A.1.1.1.14 1 m3 Pembongkaran 1 m3 Beton Bertulang 1,272,323.80


A Tenaga 1,156,658.00
L.02 13.334 OH Pekerja 82,000.00 1,093,388.00
L.04 0.666 OH Mandor 95,000.00 63,270.00
B Bahan
C PERALATAN
D Jumlah A + B + C 1,156,658.00
E Overhead & Profit (contah 10%) 10% 115,665.80
F Harga Satuan Pekerjaan (D+E) 1,272,323.80

11 A.1.1.1.15 1 m2 Pemasangan 1m2 Pagar BRC Galvanis 75,672.17


B Tenaga 3,804.00
L.01 0.042 OH Pekerja 82,000.00 3,444.00
L.02 0.004 OH Tukang 90,000.00 360.00
L.03 0.002 OH Kepala Tukang 95,000.00 190.00
L.04 0.042 OH Mandor 95,000.00 3,990.00
B Bahan
0.1434 Lbr Kawat Jaring (BRC) 453,200.00 64,988.88
C PERALATAN
D Jumlah A + B + C 68,792.88
E Overhead & Profit (contah 10%) 10% 6,879.29
F Harga Satuan Pekerjaan (D+E) 75,672.17

12 A.1.1.1.16 1 m2 Pemasangan 1 m2 Panel Beton Pracetak 50x50x240cm untuk Pagar 631,185.92


B Tenaga 44,945.00
L.01 0.375 OH Pekerja 82,000.00 30,750.00
L.02 0.125 OH Tukang 90,000.00 11,250.00
L.03 0.012 OH Kepala Tukang 95,000.00 1,140.00
L.04 0.019 OH Mandor 95,000.00 1,805.00

B Bahan 528,860.38
0.986 Lbr Panel Beton Pracetak 162,062.00 159,793.13
0.525 Batang Kolom Beton Pracetak 416,250.00 218,531.25
45 Kg Semen Portland 1,520.00 68,400.00
0.074 m3 Pasir Beton 376,000.00 27,824.00
0.146 m3 Kerikil 372,000.00 54,312.00
C PERALATAN
D Jumlah A + B + C 573,805.38
E Overhead & Profit (contah 10%) 10% 57,380.54
F Harga Satuan Pekerjaan (D+E) 631,185.92

13 A.1.1.1.17 1 m2 Pebuatan 1 m2 jalan sementara 175,846.00


B Tenaga 82,000.00
L.01 1 OH Pekerja 82,000.00 82,000.00
HARGA
JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN BAHAN/UPAH
Rp Rp
DIVISI II A.1.5.1 HARGA SATUAN PEKERJAAN TANAH

1 A.1.5.1.1 1 m3 Penggalian Tanah Biasa Sedalam s.d 1 m 70,262.50


A TENAGA 63,875.00
L.01 0.75 OH Pekerja 82,000.00 61,500.00
L.04 0.025 OH Mandor 95,000.00 2,375.00
B BAHAN
C PERALATAN
D Jumlah A + B + C 63,875.00
E Overhead & Profit (contah 10%) 10% 6,387.50
F Harga Satuan Pekerjaan (D+E) 70,262.50

2 A.1.5.1.2 1 m3 Penggalian Tanah Biasa Sedalam > 1 s.d 2 m 85,882.50


A TENAGA 78,075.00
L.01 0.90 OH Pekerja 82,000.00 73,800.00
L.04 0.045 OH Mandor 95,000.00 4,275.00
B BAHAN
C PERALATAN
D Jumlah A + B + C 78,075.00
E Overhead & Profit (contah 10%) 10% 7,807.50
F Harga Satuan Pekerjaan (D+E) 85,882.50

3 A.1.5.1.3 1 m3 Penggalian Tanah Biasa Sedalam > 2 s.d 3 m 101,711.50


A TENAGA 92,465.00
L.01 1.05 OH Pekerja 82,000.00 86,100.00
L.04 0.067 OH Mandor 95,000.00 6,365.00
B BAHAN
C PERALATAN
D Jumlah A + B + C 92,465.00
E Overhead & Profit (contah 10%) 10% 9,246.50
F Harga Satuan Pekerjaan (D+E) 101,711.50

4 A.1.5.1.4 1 m3 Penggalian Tanah Keras Sedalam s.d 1 m 93,544.00


TENAGA 85,040.00
L.01 1.000 OH Pekerja 82,000.00 82,000.00
L.04 0.032 OH Mandor 95,000.00 3,040.00
B BAHAN
C PERALATAN
D Jumlah A + B + C 85,040.00
E Overhead & Profit (contah 10%) 10% 8,504.00
F Harga Satuan Pekerjaan (D+E) 93,544.00

5 A.1.5.1.5 1 m3 Penggalian Tanah Cadas Sedalam s.d 1 m 141,570.00


A TENAGA 128,700.00
L.01 1.50 OH Pekerja 82,000.00 123,000.00
L.04 0.060 OH Mandor 95,000.00 5,700.00
B BAHAN
C PERALATAN
D Jumlah A + B + C 128,700.00
E Overhead & Profit (contah 10%) 10% 12,870.00
F Harga Satuan Pekerjaan (D+E) 141,570.00
6 A.1.5.1.6 1 m3 Penggalian Tanah Lumpur Sedalam s.d 1 m 112,942.50
A TENAGA 102,675.00
L.01 1.200 OH Pekerja 82,000.00 98,400.00
L.04 0.045 OH Mandor 95,000.00 4,275.00
B BAHAN
C PERALATAN
D Jumlah A + B + C 102,675.00
E Overhead & Profit (contah 10%) 10% 10,267.50
F Harga Satuan Pekerjaan (D+E) 112,942.50

7 A.1.5.1.7 1 m2 Pengerjaan Striping Tebing Setinggi s.d 1 m 5,032.50


A TENAGA 4,575.00
L.01 0.05 OH Pekerja 82,000.00 4,100.00
L.04 0.005 OH Mandor 95,000.00 475.00
B BAHAN
C PERALATAN
D Jumlah A + B + C 4,575.00
E Overhead & Profit (contah 10%) 10% 457.50
F Harga Satuan Pekerjaan (D+E) 5,032.50

8 A.1.5.1.8 1 m3 Pembuangan Tanah sejauh s.d 30 m 30,811.00


A TENAGA 28,010.00
L.01 0.330 OH Pekerja 82,000.00 27,060.00
L.04 0.010 OH Mandor 95,000.00 950.00
B BAHAN
C PERALATAN
D Jumlah A + B + C 28,010.00
E Overhead & Profit (contah 10%) 10% 2,801.00
F Harga Satuan Pekerjaan (D+E) 30,811.00

9 A.1.5.1.9 1 m3 Pemadatan Tanah per 20 cm 50,325.00


A TENAGA 45,750.00
L.01 0.5 OH Pekerja 82,000.00 41,000.00
L.04 0.05 OH Mandor 95,000.00 4,750.00
B BAHAN
C PERALATAN
D Jumlah A + B + C 45,750.00
E Overhead & Profit (contah 10%) 10% 4,575.00
F Harga Satuan Pekerjaan (D+E) 50,325.00
10 A.1.5.1.10 1 m3 Pengurugan dengan Pasir Urug 278,905.00
A TENAGA 25,550.00
L.01 0.30 OH Pekerja 82,000.00 24,600.00
L.04 0.01 OH Mandor 95,000.00 950.00
B BAHAN 228,000.00
1.2 m3 Pasir Urug 190,000.00 228,000.00
C PERALATAN
D Jumlah A + B + C 253,550.00
E Overhead & Profit (contah 10%) 10% 25,355.00
F Harga Satuan Pekerjaan (D+E) 278,905.00

11 A.1.5.1.11 1 m3 Pemasangan Lapisan Pudel Cmp. 1Kp : 3Ps : 7TL 449,113.50


A TENAGA 113,000.00
L.01 0.800 OH Pekerja 82,000.00 65,600.00
L.02 0.400 OH Tukang Batu 90,000.00 36,000.00
L.03 0.04 OH Kepala Tukang 95,000.00 3,800.00
L.04 0.080 OH Mandor 95,000.00 7,600.00
B BAHAN 295,285.00
0.135 m3 Pasir Pasang 313,000.00 42,255.00
0.400 m3 Kapur Padam 283,000.00 113,200.00
0.948 m3 Tanah Liat 147,500.00 139,830.00
C PERALATAN
D Jumlah A + B + C 408,285.00
E Overhead & Profit (contah 10%) 10% 40,828.50
F Harga Satuan Pekerjaan (D+E) 449,113.50

Pemasangan Lapisan Ijuk tebal 10 cm untuk Bidang


12 A.1.5.1.13 1 m2 71,197.50
Resapan Tangki Septik

A TENAGA 13,725.00
0.15 OH Pekerja 82,000.00 12,300.00
0.015 OH Mandor 95,000.00 1,425.00
B BAHAN 51,000.00
6.00 kg Ijuk 8,500.00 51,000.00
C PERALATAN
D Jumlah A + B + C 64,725.00
E Overhead & Profit (contah 10%) 10% 6,472.50
F Harga Satuan Pekerjaan (D+E) 71,197.50

13 A.1.5.1.14 1 m3 Pengurugan dengan Sirtu Padat 322,162.50


A TENAGA 22,875.00
0.25 OH Pekerja 82,000.00 20,500.00
0.025 OH Mandor 95,000.00 2,375.00
B BAHAN 270,000.00
1.2 m3 Sirtu 225,000.00 270,000.00
C PERALATAN
D Jumlah A + B + C 292,875.00
E Overhead & Profit (contah 10%) 10% 29,287.50
F Harga Satuan Pekerjaan (D+E) 322,162.50
HARGA
JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN BAHAN/UPAH
Rp Rp
DIVISI III A.3.2.1. HARGA SATUAN PEKERJAAN PONDASI
1 A.3.2.1.1 1 m3 Pemasangan Pondasi Batu Belah 1SP : 3 PP 1,127,274.50
A TENAGA 204,750.00
L.01 1.5 OH Pekerja 82,000.00 123,000.00
L.02 0.750 OH Tukang Batu 90,000.00 67,500.00
L.03 0.075 OH Kepala Tukang 95,000.00 7,125.00
L.04 0.075 OH Mandor 95,000.00 7,125.00
B BAHAN 820,045.00
1.2 m3 Batu Belah 15/20 301,000.00 361,200.00
202 Kg Portland Sement 1,520.00 307,040.00
0.485 m3 Pasir Pasang 313,000.00 151,805.00
C PERALATAN
D Jumlah A + B + C 1,024,795.00
E Overhead & Profit (contah 10%) 10% 102,479.50
F Harga Satuan Pekerjaan (D+E) 1,127,274.50

2 A.3.2.1.2 1 m3 Pemasangan Pondasi Batu Belah 1SP : 4 PP 1,074,117.00


A TENAGA 204,750.00
L.01 1.5 OH Pekerja 82,000.00 123,000.00
L.02 0.750 OH Tukang Batu 90,000.00 67,500.00
L.03 0.075 OH Kepala Tukang 95,000.00 7,125.00
L.04 0.075 OH Mandor 95,000.00 7,125.00
B BAHAN 771,720.00
1.2 m3 Batu Belah 15/20 301,000.00 361,200.00
163 Kg Portland Sement 1,520.00 247,760.00
0.52 m3 Pasir Pasang 313,000.00 162,760.00
C PERALATAN
D Jumlah A + B + C 976,470.00
E Overhead & Profit (contah 10%) 10% 97,647.00
F Harga Satuan Pekerjaan (D+E) 1,074,117.00

3 A.3.2.1.3 1 m3 Pemasangan Pondasi Batu Belah 1SP : 5 PP 1,037,236.20


A TENAGA 204,750.00
L.01 1.5 OH Pekerja 82,000.00 123,000.00
L.02 0.750 OH Tukang Batu 90,000.00 67,500.00
L.03 0.075 OH Kepala Tukang 95,000.00 7,125.00
L.04 0.075 OH Mandor 95,000.00 7,125.00
B BAHAN 738,192.00
1.2 m3 Batu Belah 15/20 301,000.00 361,200.00
136 Kg Portland Sement 1,520.00 206,720.00
0.544 m3 Pasir Pasang 313,000.00 170,272.00
C PERALATAN
D Jumlah A + B + C 942,942.00
E Overhead & Profit (contah 10%) 10% 94,294.20
F Harga Satuan Pekerjaan (D+E) 1,037,236.20
4 A.3.2.1.4 1 m3 Pemasangan Pondasi Batu Belah 1SP : 6 PP 1,011,321.30
A TENAGA 204,750.00
L.01 1.5 OH Pekerja 82,000.00 123,000.00
L.02 0.750 OH Tukang Batu 90,000.00 67,500.00
L.03 0.075 OH Kepala Tukang 95,000.00 7,125.00
L.04 0.075 OH Mandor 95,000.00 7,125.00
B BAHAN 714,633.00
1.2 m3 Batu Belah 15/20 301,000.00 361,200.00
117 Kg Portland Sement 1,520.00 177,840.00
0.561 m3 Pasir Pasang 313,000.00 175,593.00
C PERALATAN
D Jumlah A + B + C 919,383.00
E Overhead & Profit (contah 10%) 10% 91,938.30
F Harga Satuan Pekerjaan (D+E) 1,011,321.30

5 A.3.2.1.5 1 m3 Pemasangan Pondasi Batu Belah 1SP : 8 PP 975,768.20


A Tenaga 204,750.00
L.01 1.5 OH Pekerja 82,000.00 123,000.00
L.02 0.750 OH Tukang Batu 90,000.00 67,500.00
L.03 0.075 OH Kepala Tukang 95,000.00 7,125.00
L.04 0.075 OH Mandor 95,000.00 7,125.00
B Bahan 682,312.00
1.2 m3 Batu Belah 15/20 301,000.00 361,200.00
91 Kg Portland Sement 1,520.00 138,320.00
0.584 m3 Pasir Pasang 313,000.00 182,792.00
C PERALATAN
D Jumlah A + B + C 887,062.00
E Overhead & Profit (contah 10%) 10% 88,706.20
F Harga Satuan Pekerjaan (D+E) 975,768.20

6 A.3.2.1.6 1 m3 Pemasangan Pondasi Batu Belah 1KP : 1SM : 2PP 837,127.50


A Tenaga 204,750.00
L.01 1.5 OH Pekerja 82,000.00 123,000.00
L.02 0.750 OH Tukang Batu 90,000.00 67,500.00
L.03 0.075 OH Kepala Tukang 95,000.00 7,125.00
L.04 0.075 OH Mandor 95,000.00 7,125.00
B Bahan 556,275.00
1.2 m3 Batu Belah 15/20 301,000.00 361,200.00
0.17 m3 Kapur Pasang (KP) 363,000.00 61,710.00
0.17 Kg Semen Merah (SM) 158,500.00 26,945.00
0.340 m3 Pasir Pasang 313,000.00 106,420.00
C PERALATAN
D Jumlah A + B + C 761,025.00
E Overhead & Profit (contah 10%) 10% 76,102.50
F Harga Satuan Pekerjaan (D+E) 837,127.50
7 A.3.2.1.7 1 m3 Pemasangan Pondasi Batu Belah, 1 PC : 3 KP : 10 PP 952,629.70
A Tenaga 204,750.00
L.01 1.5 OH Pekerja 82,000.00 123,000.00
L.02 0.750 OH Tukang Batu 90,000.00 67,500.00
L.03 0.075 OH Kepala Tukang 95,000.00 7,125.00
L.04 0.075 OH Mandor 95,000.00 7,125.00
B Bahan 661,277.00
1.2 m3 Batu Belah 15/20 301,000.00 361,200.00
61 kg Portland Sement 1,520.00 92,720.00
0.147 m3 Kapur Pasang 363,000.00 53,361.00
0.492 m3 Pasir Pasang 313,000.00 153,996.00
C PERALATAN
D Jumlah A + B + C 866,027.00
E Overhead & Profit (contah 10%) 10% 86,602.70
F Harga Satuan Pekerjaan (D+E) 952,629.70

8 A.3.2.1.8 1 m3 Pemasangan Pondasi Batu Belah, ¼ PC : 1KP : 4 PP 923,474.20


A Tenaga 204,750.00
L.01 1.5 OH Pekerja 82,000.00 123,000.00
L.02 0.750 OH Tukang Batu 90,000.00 67,500.00
L.03 0.075 OH Kepala Tukang 95,000.00 7,125.00
L.04 0.075 OH Mandor 95,000.00 7,125.00
B Bahan 634,772.00
1.2 m3 Batu Belah 15/20 301,000.00 361,200.00
41 kg Portland Sement 1,520.00 62,320.00
0.131 m3 Kapur Pasang 363,000.00 47,553.00
0.523 m3 Pasir 313,000.00 163,699.00
C PERALATAN
D Jumlah A + B + C 839,522.00
E Overhead & Profit (contah 10%) 10% 83,952.20
F Harga Satuan Pekerjaan (D+E) 923,474.20

9 A.3.2.1.9 1 m3 Pemasang Batu Kosong (Anstamping) untuk pondasi gedung 604,725.00


A Tenaga 106,470.00
L.01 0.78 OH Pekerja 82,000.00 63,960.00
L.02 0.39 OH Tukang Batu 90,000.00 35,100.00
L.03 0.039 OH Kepala Tukang 95,000.00 3,705.00
L.04 0.039 OH Mandor 95,000.00 3,705.00
B Bahan 443,280.00
1.2 m3 Batu Belah 15/20 301,000.00 361,200.00
0.432 m3 Pasir Urug 190,000.00 82,080.00
C PERALATAN
D Jumlah A + B + C 549,750.00
E Overhead & Profit (contah 10%) 10% 54,975.00
F Harga Satuan Pekerjaan (D+E) 604,725.00
10 A.3.2.1.10 1 m3 Pemasangan Pondasi Siklop 60% Beton 3,575,016.50

A Tenaga 377,625.00
L.01 3.4 OH Pekerja 82,000.00 278,800.00
L.02 0.85 OH Tukang Batu 90,000.00 76,500.00
L.03 0.085 OH Kepala Tukang 95,000.00 8,075.00
L.04 0.15 OH Mandor 95,000.00 14,250.00
B Bahan 2,872,390.00
0.480 m3 Batu Belah 15/20 cm 301,000.00 144,480.00
126 Kg Besi Beton 17,000.00 2,142,000.00
194 Kg Portland Semen 1,520.00 294,880.00
0.312 m3 Pasir Beton 376,000.00 117,312.00
0.468 m3 Koral Beton 263,500.00 123,318.00
1.8 Kg Kawat Beton 28,000.00 50,400.00
C PERALATAN
D Jumlah A + B + C 3,250,015.00
E Overhead & Profit (contah 10%) 10% 325,001.50
F Harga Satuan Pekerjaan (D+E) 3,575,016.50

11 A.3.2.1.11 1 m3 Pemasangan Pondasi Sumuran Ø 100 cm 1,054,531.50


A Tenaga 287,705.00
L.01 2.40 OH Pekerja 82,000.00 196,800.00
L.02 0.8 OH Tukang Batu 90,000.00 72,000.00
L.03 0.08 OH Kepala Tukang 95,000.00 7,600.00
L.04 0.119 OH Mandor 95,000.00 11,305.00
B Bahan 670,960.00
0.45 m3 Batu Belah 15/20 cm 301,000.00 135,450.00
194 Kg Portland Semen 1,520.00 294,880.00
0.312 m3 Pasir Beton 376,000.00 117,312.00
0.468 m3 Koral Beton 263,500.00 123,318.00
C PERALATAN
D Jumlah A + B + C 958,665.00
E Overhead & Profit (contah 10%) 10% 95,866.50
F Harga Satuan Pekerjaan (D+E) 1,054,531.50
HARGA
JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN BAHAN/UPAH
Rp Rp
DIVISI IV A.4.1.1 HARGA SATUAN PEKERJAAN BETON

1 A.4.1.1.1 1 m3 Pembuatan 1 m3 beton mutu fc 7,4 Mpa (K100) 1,161,356.43

A Tenaga 170,595.00
L.01 1.65 OH Pekerja 82,000.00 135,300.00
L.02 0.275 OH Tukang Batu 90,000.00 24,750.00
L.03 0.028 OH Kepala Tukang 95,000.00 2,660.00
L.04 0.083 OH Mandor 95,000.00 7,885.00
B Bahan 885,183.57
247 Kg Portland Semen 1,520.00 375,440.00
869 Kg Pasir Beton 268.57 233,388.57
999 Kg Kerikil (maksimum 30 mm) 275.56 275,280.00
215 ltr Air 5.00 1,075.00
C PERALATAN
D Jumlah A + B + C 1,055,778.57
E Overhead & Profit (contoh 10%) 10% 105,577.86
F Harga Satuan Pekerjaan (D+E) 1,161,356.43
10%

2 A.4.1.1.2 1 m3 Pembuatan 1 m3 beton mutu fc 9,8 Mpa (K125) 1,201,672.30

A Tenaga 170,595.00
L.01 1.650 OH Pekerja 82,000.00 135,300.00
L.02 0.275 OH Tukang Batu 90,000.00 24,750.00
L.03 0.028 OH Kepala Tukang 95,000.00 2,660.00
L.04 0.083 OH Mandor 95,000.00 7,885.00
B Bahan 921,834.37
276 Kg Portland Semen 1,520.00 419,520.00
828 kg Pasir Beton 268.57 222,377.14
1,012 kg Kerikil (maksimum 30 mm) 275.56 278,862.22
215 ltr Air 5.00 1,075.00
C PERALATAN
D Jumlah A + B + C 1,092,429.37
E Overhead & Profit (contoh 10%) 10% 109,242.94
F Harga Satuan Pekerjaan (D+E) 1,201,672.30

3 A.4.1.1.3 1 m3 Pembuatan 1 m3 beton mutu fc 12,2 Mpa (K150) 1,233,076.43

A Tenaga 170,595.00
L.01 1.650 OH Pekerja 82,000.00 135,300.00
L.02 0.275 OH Tukang Batu 90,000.00 24,750.00
L.03 0.028 OH Kepala Tukang 95,000.00 2,660.00
L.04 0.083 OH Mandor 95,000.00 7,885.00
B Bahan 950,383.57
299 Kg Portland Semen 1,520.00 454,480.00
799 kg Pasir Beton 268.57 214,588.57
1,017 kg Kerikil (maksimum 30 mm) 275.56 280,240.00
215 ltr Air 5.00 1,075.00
C PERALATAN
D Jumlah A + B + C 1,120,978.57
E Overhead & Profit (contoh 10%) 10% 112,097.86
F Harga Satuan Pekerjaan (D+E) 1,233,076.43
4 A.4.1.1.4 1.00 m3 Pembuatan 1 m3 lantai kerja beton mutu fc 7,4 Mpa 1,091,529.83

A Tenaga 118,870.00
L.01 1.200 OH Pekerja 82,000.00 98,400.00
L.02 0.200 OH Tukang Batu 90,000.00 18,000.00
L.03 0.020 OH Kepala Tukang 95,000.00 1,900.00
L.04 0.006 OH Mandor 95,000.00 570.00
B Bahan 873,429.84
230 Kg Portland Semen 1,520.00 349,600.00
893 kg Pasir Beton 268.57 239,834.29
1,027 kg Kerikil (maksimum 30 mm) 275.56 282,995.56
200 ltr Air 5.00 1,000.00
C PERALATAN
D Jumlah A + B + C 992,299.84
E Overhead & Profit (contoh 10%) 10% 99,229.98
F Harga Satuan Pekerjaan (D+E) 1,091,529.83

5 A.4.1.1.5 1 m3 Pembuatan 1 m3 beton mutu fc 14,5 Mpa (KI75) 1,270,336.05

A Tenaga 170,595.00
L.01 1.65 OH Pekerja 82,000.00 135,300.00
L.02 0.275 OH Tukang Batu 90,000.00 24,750.00
L.03 0.028 OH Kepala Tukang 95,000.00 2,660.00
L.04 0.083 OH Mandor 95,000.00 7,885.00
B Bahan 984,255.95
326 Kg Portland Semen 1,520.00 495,520.00
760 Kg Pasir Beton 268.57 204,114.29
1,029 Kg Kerikil (maksimum 30 mm) 275.56 283,546.67
215 ltr Air 5.00 1,075.00
C PERALATAN
D Jumlah A + B + C 1,154,850.95
E Overhead & Profit (contoh 10%) 10% 115,485.10
F Harga Satuan Pekerjaan (D+E) 1,270,336.05

6 A.4.1.1.6 1 m3 Pembuatan 1 m3 beton mutu fc 16,9 Mpa (K200) 1,305,846.84

A Tenaga 170,595.00
L.01 1.650 OH Pekerja 82,000.00 135,300.00
L.02 0.275 OH Tukang Batu 90,000.00 24,750.00
L.03 0.028 OH Kepala Tukang 95,000.00 2,660.00
L.04 0.083 OH Mandor 95,000.00 7,885.00
B Bahan 1,016,538.49
352 Kg Portland Semen 1,520.00 535,040.00
731 Kg Pasir Beton 268.57 196,325.71
1,031 Kg Kerikil (maksimum 30 mm) 275.56 284,097.78
215 ltr Air 5.00 1,075.00
C PERALATAN
D Jumlah A + B + C 1,187,133.49
E Overhead & Profit (contoh 10%) 10% 118,713.35
F Harga Satuan Pekerjaan (D+E) 1,305,846.84
7 A.4.1.1.7 1 m3 Pembuatan 1 m3 beton mutu fc 19,3 Mpa (K225) 1,332,715.48

A Tenaga 170,595.00
L.01 1.650 OH Pekerja 82,000.00 135,300.00
L.02 0.275 OH Tukang Batu 90,000.00 24,750.00
L.03 0.028 OH Kepala Tukang 95,000.00 2,660.00
L.04 0.083 OH Mandor 95,000.00 7,885.00
B Bahan 1,040,964.52
371 Kg Portland Semen 1,520.00 563,920.00
698 Kg Pasir Beton 268.57 187,462.86
1,047 Kg Kerikil (maksimum 30 mm) 275.56 288,506.67
215 ltr Air 5.00 1,075.00
C PERALATAN
D Jumlah A + B + C 1,211,559.52
E Overhead & Profit (contoh 10%) 10% 121,155.95
F Harga Satuan Pekerjaan (D+E) 1,332,715.48

8 A.4.1.1.8 1 m3 Pembuatan 1 m3 beton mutu fc 21,7 Mpa (K250) 1,350,254.02

A Tenaga 170,595.00
L.01 1.650 OH Pekerja 82,000.00 135,300.00
L.02 0.275 OH Tukang Batu 90,000.00 24,750.00
L.03 0.028 OH Kepala Tukang 95,000.00 2,660.00
L.04 0.083 OH Mandor 95,000.00 7,885.00
B Bahan 1,056,908.65
384 Kg Portland Semen 1,520.00 583,680.00
692 Kg Pasir Beton 268.57 185,851.43
1,039 Kg Kerikil (maksimum 30 mm) 275.56 286,302.22
215 ltr Air 5.00 1,075.00
C PERALATAN
D Jumlah A + B + C 1,227,503.65
E Overhead & Profit (contoh 10%) 10% 122,750.37
F Harga Satuan Pekerjaan (D+E) 1,350,254.02

9 A.4.1.1.9 1 m3 Pembuatan 1 m3 beton mutu fc 24,0 Mpa (K275) 1,380,734.14

A Tenaga 170,595.00
L.01 1.650 OH Pekerja 82,000.00 135,300.00
L.02 0.275 OH Tukang Batu 90,000.00 24,750.00
L.03 0.028 OH Kepala Tukang 95,000.00 2,660.00
L.04 0.083 OH Mandor 95,000.00 7,885.00
B Bahan 1,084,617.86
406 Kg Portland Semen 1,520.00 617,120.00
684 kg Pasir Beton 268.57 183,702.86
1,026 kg Kerikil (maksimum 30 mm) 275.56 282,720.00
215 ltr Air 5.00 1,075.00
C PERALATAN
D Jumlah A + B + C 1,255,212.86
E Overhead & Profit (contoh 10%) 10% 125,521.29
F Harga Satuan Pekerjaan (D+E) 1,380,734.14
10 A.4.1.1.10 1 m3 Pembuatan 1 m3 beton mutu fc 26,4 Mpa (K300) 1,390,036.30

A Tenaga 170,595.00
L.01 1.650 OH Pekerja 82,000.00 135,300.00
L.02 0.275 OH Tukang Batu 90,000.00 24,750.00
L.03 0.028 OH Kepala Tukang 95,000.00 2,660.00
L.04 0.083 OH Mandor 95,000.00 7,885.00
B Bahan 1,093,074.37
413 Kg Portland Semen 1,520.00 627,760.00
681 Kg Pasir Beton 268.57 182,897.14
1,021 Kg Kerikil (maksimum 30 mm) 275.56 281,342.22
215 ltr Air 5.00 1,075.00
C PERALATAN
D Jumlah A + B + C 1,263,669.37
E Overhead & Profit (contoh 10%) 10% 126,366.94
F Harga Satuan Pekerjaan (D+E) 1,390,036.30

11 A.4.1.1.11 1 m3 Pembuatan 1m3 Beton mutu f'c=28,8 MPa (K325) 1,476,757.42

A Tenaga 217,000.00
L.01 2.1 OH Pekerja 82,000.00 172,200.00
L.02 0.35 OH Tukang Batu 90,000.00 31,500.00
L.03 0.035 OH Kepala Tukang 95,000.00 3,325.00
L.04 0.105 OH Mandor 95,000.00 9,975.00
B Bahan 1,125,506.75
439 Kg Portland Semen 1,520.00 667,280.00
670 Kg Pasir Beton 268.57 179,942.86
1,006 Kg Kerikil (maksimum 30 mm) 275.56 277,208.89
215 ltr Air 5.00 1,075.00
C PERALATAN
D Jumlah A + B + C 1,342,506.75
E Overhead & Profit (contoh 10%) 10% 134,250.67
F Harga Satuan Pekerjaan (D+E) 1,476,757.42

12 A.4.1.1.12 1 m3 Pembuatan 1m3 Beton mutu f'c=31,2 MPa (K350) 1,489,100.47

A Tenaga 217,000.00
L.01 2.10 OH Pekerja 82,000.00 172,200.00
L.02 0.350 OH Tukang Batu 90,000.00 31,500.00
L.03 0.035 OH Kepala Tukang 95,000.00 3,325.00
L.04 0.105 OH Mandor 95,000.00 9,975.00
B Bahan 1,136,727.70
448 Kg Portland Semen 1,520.00 680,960.00
667 Kg Pasir Beton 268.57 179,137.14
1,000 Kg Kerikil (maksimum 30 mm) 275.56 275,555.56
215 ltr Air 5.00 1,075.00
C PERALATAN
D Jumlah A + B + C 1,353,727.70
E Overhead & Profit (contoh 10%) 10% 135,372.77
F Harga Satuan Pekerjaan (D+E) 1,489,100.47

Pembuatan 1 m3 Beton Kedap Air dengan Aditif


13 A.4.1.1.13 1 m3 985,626.79
Kedap Air
A Tenaga 217,000.00
L.01 2.100 OH Pekerja 82,000.00 172,200.00
L.02 0.350 OH Tukang Batu 90,000.00 31,500.00
L.03 0.035 OH Kepala Tukang 95,000.00 3,325.00
L.04 0.105 OH Mandor 95,000.00 9,975.00
B Bahan 679,024.36
400 Kg Portland Semen 1,520.00 608,000.00
0.480 Kg Pasir Beton 268.57 128.91
0.800 Kg Kerikil (maksimum 30 mm) 275.56 220.44
1.2 Kg Strorox – 100 58,000.00 69,600.00
215 ltr Air 5.00 1,075.00
C PERALATAN
D Jumlah A + B + C 896,024.36
E Overhead & Profit (contoh 10%) 10% 89,602.44
F Harga Satuan Pekerjaan (D+E) 985,626.79
14 A.4.1.1.15 10 Kg Pembesian 10 kg dengan Besi Polos atau Ulir 215,363.50
A Tenaga 13,085.00
L.01 0.07 OH Pekerja 82,000.00 5,740.00
L.02 0.07 OH Tukang Besi 90,000.00 6,300.00
L.03 0.007 OH Kepala Tukang 95,000.00 665.00
L.04 0.004 OH Mandor 95,000.00 380.00
B Bahan 182,700.00
10.50 Kg Besi Beton (polos/ulir) 17,000.00 178,500.00
0.150 Kg Kawat Beton 28,000.00 4,200.00
C PERALATAN
D Jumlah A + B + C 195,785.00
E Overhead & Profit (contoh 10%) 10% 19,578.50
F Harga Satuan Pekerjaan (D+E) 215,363.50

15 A.4.1.1.16 10 Kg Pemasangan 10 kg kabel prategang (Prestressed) Polos/strands 209,726.00


A Tenaga 9,360.00
L.01 0.05 OH Pekerja 82,000.00 4,100.00
L.02 0.05 OH Tukang Besi 90,000.00 4,500.00
L.03 0.005 OH Kepala Tukang 95,000.00 475.00
L.04 0.003 OH Mandor 95,000.00 285.00
B Bahan 181,300.00
10.5 Kg Besi presstred polos 17,000.00 178,500.00
0.1 Kg Kawat Beton 28,000.00 2,800.00
C PERALATAN
D Jumlah A + B + C 190,660.00
E Overhead & Profit (contoh 10%) 10% 19,066.00
F Harga Satuan Pekerjaan (D+E) 209,726.00

Pemasangan 1 kg Jaring Anyaman Tulangan Tunggal (Wiremesh) M6-


16 A.4.1.1.17 1 Kg 32,314.70
M8
A Tenaga 677.00
L.01 0.0025 OH Pekerja 82,000.00 205.00
L.02 0.0025 OH Tukang Besi 90,000.00 225.00
L.03 0.0025 OH Kepala Tukang 95,000.00 237.50
L.04 0.0001 OH Mandor 95,000.00 9.50
B Bahan 28,700.00
1.02 Kg Jaring Kawat Baja dilas 28,000.00 28,560.00
0.005 Kg Kawat Bendrat 28,000.00 140.00
C PERALATAN
D Jumlah A + B + C 29,377.00
E Overhead & Profit (contoh 10%) 10% 2,937.70
F Harga Satuan Pekerjaan (D+E) 32,314.70

Pemasangan 1 m2 Bekisting untuk Pondasi Telapak Beton Bangunan


17 A.4.1.1.18 1 m2 219,865.80
Gedung
A Tenaga 70,980.00
L.01 0.52 OH Pekerja 82,000.00 42,640.00
L.02 0.26 OH Tukang Kayu 90,000.00 23,400.00
L.03 0.026 OH Kepala Tukang 95,000.00 2,470.00
L.04 0.026 OH Mandor 95,000.00 2,470.00
B Bahan 128,898.00
0.04 m3 Kayu Klas III (Terentang) 3,008,200.00 120,328.00
0.3 Kg Paku Biasa 2" - 5" 20,000.00 6,000.00
0.1 Ltr Minyak Bekisting 25,700.00 2,570.00
C PERALATAN
D Jumlah A + B + C 199,878.00
E Overhead & Profit (contoh 10%) 10% 19,987.80
F Harga Satuan Pekerjaan (D+E) 219,865.80
18 A.4.1.1.19 1 m2 Pemasangan 1 m2 Bekisting untuk Sloof Beton Bangunan Gedung 236,410.90
A Tenaga 70,980.00
L.01 0.52 OH Pekerja 82,000.00 42,640.00
L.02 0.26 OH Tukang Kayu 90,000.00 23,400.00
L.03 0.026 OH Kepala Tukang 95,000.00 2,470.00
L.04 0.026 OH Mandor 95,000.00 2,470.00
B Bahan 143,939.00
0.045 m3 Kayu Klas III (Terentang) 3,008,200.00 135,369.00
0.3 Kg Paku Biasa 2" - 5" 20,000.00 6,000.00
0.1 Ltr Minyak Bekisting 25,700.00 2,570.00
C PERALATAN
D Jumlah A + B + C 214,919.00
E Overhead & Profit (contoh 10%) 10% 21,491.90
F Harga Satuan Pekerjaan (D+E) 236,410.90

19 A.4.1.1.20 1 m2 Pemasangan 1 m2 Bekisting untuk Kolom Beton Bangunan Gedung 489,715.05


A Tenaga 90,090.00
L.01 0.66 OH Pekerja 82,000.00 54,120.00
L.02 0.33 OH Tukang Kayu 90,000.00 29,700.00
L.03 0.033 OH Kepala Tukang 95,000.00 3,135.00
L.04 0.033 OH Mandor 95,000.00 3,135.00
B Bahan 355,105.50
0.04 m3 Kayu Klas III (Terentang) 3,008,200.00 120,328.00
0.4 Kg Paku Biasa 2" - 5" 20,000.00 8,000.00
0.2 Ltr Minyak Bekisting 25,700.00 5,140.00
0.015 m3 Balok Kayu Klas II (kruwing) 9,887,500.00 148,312.50
0.35 Lbr Plywood tebal 9mm 129,500.00 45,325.00
2 Btg Dolken Kayu Galam diameter 8 - 10 cm / 4 m 14,000.00 28,000.00
C PERALATAN
D Jumlah A + B + C 445,195.50
E Overhead & Profit (contoh 10%) 10% 44,519.55
F Harga Satuan Pekerjaan (D+E) 489,715.05

20 A.4.1.1.21 1 m2 Pemasangan 1 m2 Bekisting untuk Balok Bangunan Gedung 522,343.80


A Tenaga 90,090.00
L.01 0.66 OH Pekerja 82,000.00 54,120.00
L.02 0.33 OH Tukang Kayu 90,000.00 29,700.00
L.03 0.033 OH Kepala Tukang 95,000.00 3,135.00
L.04 0.033 OH Mandor 95,000.00 3,135.00
B Bahan 384,768.00
0.04 m3 Kayu Klas III (Terentang) 3,008,200.00 120,328.00
0.4 Kg Paku Biasa 2" - 5" 20,000.00 8,000.00
0.2 Ltr Minyak Bekisting 25,700.00 5,140.00
0.018 m3 Balok Kayu Klas II (kruwing) 9,887,500.00 177,975.00
0.35 Lbr Plywood tebal 9mm 129,500.00 45,325.00
2 Btg Dolken Kayu Galam diameter 8 - 10 cm / 4 m 14,000.00 28,000.00
C PERALATAN
D Jumlah A + B + C 474,858.00
E Overhead & Profit (contoh 10%) 10% 47,485.80
F Harga Satuan Pekerjaan (D+E) 522,343.80
21 A.4.1.1.22 1 m2 Pemasangan 1 m2 Bekisting untuk Plat lantai Beton Bangunan Gedung 551,315.05

A Tenaga 90,090.00
L.01 0.66 OH Pekerja 82,000.00 54,120.00
L.02 0.33 OH Tukang Kayu 90,000.00 29,700.00
L.03 0.033 OH Kepala Tukang 95,000.00 3,135.00
L.04 0.033 OH Mandor 95,000.00 3,135.00
B Bahan 411,105.50
0.04 m3 Kayu Klas III (Terentang) 3,008,200.00 120,328.00
0.4 Kg Paku Biasa 2" - 5" 20,000.00 8,000.00
0.2 Ltr Minyak Bekisting 25,700.00 5,140.00
0.015 m3 Balok Kayu Klas II (Borneo) 9,887,500.00 148,312.50
0.35 Lbr Plywood tebal 9mm 129,500.00 45,325.00
6 Btg Dolken Kayu Galam diameter 8 - 10 cm / 4 m 14,000.00 84,000.00
C PERALATAN
D Jumlah A + B + C 501,195.50
E Overhead & Profit (contoh 10%) 10% 50,119.55
F Harga Satuan Pekerjaan (D+E) 551,315.05

22 A.4.1.1.23 1 m2 Pemasangan 1 m2 Bekisting untuk Dinding Sheerwall 561,606.10


A Tenaga 90,090.00
L.01 0.66 OH Pekerja 82,000.00 54,120.00
L.02 0.33 OH Tukang Kayu 90,000.00 29,700.00
L.03 0.033 OH Kepala Tukang 95,000.00 3,135.00
L.04 0.033 OH Mandor 95,000.00 3,135.00
B Bahan 420,461.00
0.03 m3 Kayu Klas III (Terentang) 3,008,200.00 90,246.00
0.4 Kg Paku Biasa 2" - 5" 20,000.00 8,000.00
0.2 Ltr Minyak Bekisting 25,700.00 5,140.00
0.02 m3 Balok Kayu Klas II 9,887,500.00 197,750.00
0.35 Lbr Plywood tebal 9mm 129,500.00 45,325.00
3 Btg Dolken Kayu Galam diameter 8 - 10 cm / 4 m 14,000.00 42,000.00
4 Buah Formite/Penjaga jarak / Spacer (alat bantu) 8,000.00 32,000.00
C PERALATAN
D Jumlah A + B + C 510,551.00
E Overhead & Profit (contoh 10%) 10% 51,055.10
F Harga Satuan Pekerjaan (D+E) 561,606.10

23 A.4.1.1.25 1 m2 Pemasangan 1 m2 Bekisting untuk Tangga Beton Bangunan Gedung 455,211.35


A Tenaga 90,090.00
L.01 0.66 OH Pekerja 82,000.00 54,120.00
L.02 0.33 OH Tukang Kayu 90,000.00 29,700.00
L.03 0.033 OH Kepala Tukang 95,000.00 3,135.00
L.04 0.033 OH Mandor 95,000.00 3,135.00
B Bahan 323,738.50
0.03 m3 Kayu Klas III (Terentang) 3,008,200.00 90,246.00
0.4 Kg Paku Biasa 2" - 5" 20,000.00 8,000.00
0.15 Ltr Minyak Bekisting 25,700.00 3,855.00
0.015 m3 Balok Kayu Klas II 9,887,500.00 148,312.50
0.35 Lbr Plywood tebal 9mm 129,500.00 45,325.00
2 Btg Dolken Kayu Galam diameter 8 - 10 cm / 4 m 14,000.00 28,000.00
C PERALATAN
D Jumlah A + B + C 413,828.50
E Overhead & Profit (contoh 10%) 10% 41,382.85
F Harga Satuan Pekerjaan (D+E) 455,211.35

24 A.4.1.1.26 1 m' Pembuatan 1 m' kolom praktis beton bertulang (11 x 11) cm 113,417.04
A Tenaga 21,585.00
L.01 0.180 OH Pekerja 82,000.00 14,760.00
L.02 0.020 OH Tukang batu 90,000.00 1,800.00
L.02 0.020 OH Tukang Kayu 90,000.00 1,800.00
L.02 0.020 OH Tukang Besi 90,000.00 1,800.00
L.03 0.006 OH Kepala Tukang 95,000.00 570.00
L.04 0.009 OH Mandor 95,000.00 855.00
B Bahan 81,521.40
0.002 m3 Kayu Klas III 3,176,200.00 6,352.40
0.01 Kg Paku Biasa 2" - 5" 20,000.00 200.00
3.0 Kg Besi Beton Polos 17,000.00 51,000.00
0.45 Kg Kawat Beton 28,000.00 12,600.00
4.0 Kg Portland Semen 1,520.00 6,080.00
0.006 m3 Pasir Beton 376,000.00 2,256.00
0.009 m3 Kerikil 337,000.00 3,033.00
C PERALATAN
D Jumlah A + B + C 103,106.40
E Overhead & Profit (contoh 10%) 10% 10,310.64
F Harga Satuan Pekerjaan (D+E) 113,417.04
25 A.4.1.1.27 1 m' Pembuatan 1 m' Ring Balok Beton Bertulang (10 x 15) cm 137,463.26
A Tenaga 35,639.00
L.01 0.297 OH Pekerja 82,000.00 24,354.00
L.02 0.033 OH Tukang batu 90,000.00 2,970.00
L.02 0.033 OH Tukang Kayu 90,000.00 2,970.00
L.02 0.033 OH Tukang Besi 90,000.00 2,970.00
L.03 0.01 OH Kepala Tukang 95,000.00 950.00
L.04 0.015 OH Mandor 95,000.00 1,425.00
B Bahan 89,327.60
0.003 m3 Kayu Klas III 3,176,200.00 9,528.60
0.02 Kg Paku Biasa 2" - 5" 20,000.00 400.00
3.6 Kg Besi Beton Polos 17,000.00 61,200.00
0.05 Kg Kawat Beton 28,000.00 1,400.00
5.5 Kg Portland Semen 1,520.00 8,360.00
0.009 m3 Pasir Beton 376,000.00 3,384.00
0.015 m3 Kerikil 337,000.00 5,055.00
C PERALATAN
D Jumlah A + B + C 124,966.60
E Overhead & Profit (contoh 10%) 10% 12,496.66
F Harga Satuan Pekerjaan (D+E) 137,463.26
HARGA
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN BAHAN/UPAH
Rp

DIVISI IV A.4.2.1 HARGA SATUAN PEKERJAAN BESI DAN ALLUMUNIUM


1 A.4.2.1.1 1 Kg Pembuatan 1 kg Baja Profil
A Tenaga
L.01 0.06 OH Pekerja 82,000.00
L.02 0.06 OH Tukang Besi 90,000.00
L.03 0.006 OH Kepala Tukang 95,000.00
L.04 0.003 OH Mandor 95,000.00
B Bahan
1.15 Kg Besi Profil 17,000.00
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit (contoh 10%) 10%
F Harga Satuan Pekerjaan (D+E)

2 A.4.2.1.2 1 Kg Pemasangan Rangka Kuda-kuda Baja IWF


A Tenaga
L.01 0.06 OH Pekerja 82,000.00
L.02 0.06 OH Tukang Besi 90,000.00
L.03 0.006 OH Kepala Tukang 95,000.00
L.04 0.003 OH Mandor 95,000.00
B Bahan
1.15 kg Besi Baja IWF 20,200.00
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit (contoh 10%) 10%
F Harga Satuan Pekerjaan (D+E)

3 A.4.2.1.3 100 kg Pengerjaan Perakitan Baja


A Tenaga
L.01 0.100 OH Pekerja 82,000.00
L.02 0.100 OH Tukang Besi 90,000.00
L.03 0.001 OH Kepala Tukang 95,000.00
L.04 0.005 OH Mandor 95,000.00
B Bahan
1 ltr Solar 11,700.00
0.1 ltr Minyak Pelumas 36,000.00
C PERALATAN
0.800 jam Sewa Alat (las listrik) 13,000
D Jumlah A + B + C
E Overhead & Profit (contoh 10%) 10%
F Harga Satuan Pekerjaan (D+E)
4 A.4.2.1.4 1 m2 Pembuatan Pintu Pelat Baja tebal 2 mm rangkap

A Tenaga
L.01 1.05 OH Pekerja 82,000.00
L.02 1.05 OH Tukang Besi 90,000.00
L.03 0.105 OH Kepala Tukang 95,000.00
L.04 0.052 OH Mandor 95,000.00
B Bahan
15 Kg Besi Siku L.30.30.3 17,000.00
32.8 Kg Besi Plat Baja 19,000.00
0.05 Kg Kawat Las 55,000.00
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit (contoh 10%) 10%
F Harga Satuan Pekerjaan (D+E)

5 A.4.2.1.5 10 cm Pengerjaan Pengelasan dengan Las Listrik


A Tenaga
L.01 0.04 OH Pekerja 82,000.00
L.02 0.02 OH Tukang Besi 90,000.00
L.03 0.002 OH Kepala Tukang 95,000.00
L.04 0.002 OH Mandor 95,000.00
B Bahan
0.04 kg Kawat Las 55,000.00
0.03 ltr Solar 11,700.00
0.004 ltr Minyak Pelumas 36,000.00
C PERALATAN
0.170 jam Sewa Alat 13,000
D Jumlah A + B + C
E Overhead & Profit (contoh 10%) 10%
F Harga Satuan Pekerjaan (D+E)

6 A.4.2.1.6 1 m2 Pembuatan Rangka Jendela Squaretube


A Tenaga
L.01 0.65 OH Pekerja 82,000.00
L.02 0.65 OH Tukang Las Biasa 90,000.00
L.03 0.065 OH Kepala Tukang 95,000.00
L.04 0.032 OH Mandor 95,000.00
B Bahan
4.760 m' Besi Scuare tube 10,000.00
4.522 m' Besi List Kaca 1 x 1 cm 8,000.00
20.000 cm Pengelasan 1,140.15
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit (contoh 10%) 10%
F Harga Satuan Pekerjaan (D+E)
7 A.4.2.1.7 1 m2 Pemasangan 1 m2 Pintu Rolling Door Besi
A Tenaga
L.01 1.2 OH Pekerja 82,000.00
L.02 1.2 OH Tukang Besi 90,000.00
L.03 0.12 OH Kepala Tukang 95,000.00
L.04 0.006 OH Mandor 95,000.00
B Bahan
1 m2 Pintu Gulung Besi 440,000.00
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit (contoh 10%) 10%
F Harga Satuan Pekerjaan (D+E)

8 A.4.2.1.8 1 m2 Pemasangan Pintu Folding door Bahan Plastik/PVC


A Tenaga
L.01 0.44 OH Pekerja 82,000.00
L.02 0.44 OH Tukang Besi 90,000.00
L.03 0.044 OH Kepala Tukang 95,000.00
L.04 0.022 OH Mandor 95,000.00
B Bahan
1 m2 Pintu Lipat 440,000.00
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit (contoh 10%) 10%
F Harga Satuan Pekerjaan (D+E)

9 A.4.2.1.9 1 m2 Pemasangan 1 m2 Sunscreen Aluminium


A Tenaga
L.01 0.08 OH Pekerja 82,000.00
L.02 0.8 OH Tukang Besi 90,000.00
L.03 0.08 OH Kepala Tukang 95,000.00
L.04 0.004 OH Mandor 95,000.00
B Bahan
1 m2 Sunscreen Allumunium 115,500.00
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit (contoh 10%) 10%
F Harga Satuan Pekerjaan (D+E)

10 A.4.2.1.10 1 m2 Pemasangan Rolling Door Allumunium


A Tenaga
L.01 1 OH Pekerja 82,000.00
L.02 1 OH Tukang Besi 90,000.00
L.03 0.1 OH Kepala Tukang 95,000.00
L.04 0.05 OH Mandor 95,000.00
B Bahan
1 m2 Rolling door Allumunium 450,000.00
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit (contoh 10%) 10%
F Harga Satuan Pekerjaan (D+E)
11 A.4.2.1.15 1 m2 Pemasangan 1 m2 Teralis Besi strip (20 x 3) mm
A Tenaga
L.01 1.67 OH Pekerja 82,000.00
L.02 1.67 OH Tukang Las 90,000.00
L.03 0.167 OH Kepala Tukang 95,000.00
L.04 0.083 OH Mandor 95,000.00
B Bahan
6.177 kg Besi Strip 19,000.00
27.08 cm Pengelasan 1,140.15
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit (contoh 10%) 10%
F Harga Satuan Pekerjaan (D+E)

12 A.4.2.1.16 1 m2 Pemasangan 1 m2 Kawat Nyamuk


A Tenaga
L.01 0.1 OH Pekerja 82,000.00
L.02 0.1 OH Tukang 90,000.00
L.03 0.01 OH Kepala Tukang 95,000.00
L.04 0.005 OH Mandor 95,000.00
B Bahan
1.1 m2 Kawat Nyamuk nylon 25,000.00
11.11 cm Pengelasan 1,140.15
1.716 kg Baja Strip (0,2x2) cm 19,000.00
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit (contoh 10%) 10%
F Harga Satuan Pekerjaan (D+E)
13 A.4.2.1.17 1 m2 Pemasangan 1 m2 Jendela Nako dan Tralis
A Tenaga
L.01 0.2 OH Pekerja 82,000.00
L.02 0.2 OH Tukang Kayu 90,000.00
L.03 0.02 OH Kepala Tukang 95,000.00
L.04 0.001 OH Mandor 95,000.00
B Bahan
1.1 m2 Jendela Nako 218,000.00
10 buah Paku Skrup 1 - 2,5 cm 640.00
7 m' Besi Strip 6,000.00
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit (contoh 10%) 10%
F Harga Satuan Pekerjaan (D+E)

Pemasangan 1 m’ Talang Datar/Jurai Seng bjls 28 Lebar


14 A.4.2.1.18 1 m'
90cm

A Tenaga
L.01 0.20 OH Pekerja 82,000.00
L.02 0.4 OH Tukang Kayu 90,000.00
L.03 0.025 OH Kepala Tukang 95,000.00
L.04 0.01 OH Mandor 95,000.00
B Bahan
1.05 Lbr Seng Plaat 23,700.00
0.015 Kg Paku Biasa 1 - 2,5 cm 20,000.00
0.019 m3 Kayu Papan Klas II atau III 6,979,000.00
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit (contoh 10%) 10%
F Harga Satuan Pekerjaan (D+E)

Pemasangan 1 m Talang ½ Lingkaran D-15cm. Seng Pelat


15 A.4.2.1.19 1 m'
bjls 30

A Tenaga
L.01 0.20 OH Pekerja 82,000.00
L.02 0.20 OH Tukang Kayu 90,000.00
L.03 0.02 OH Kepala Tukang 95,000.00
L.04 0.001 OH Mandor 95,000.00
B Bahan
1.05 Lbr Seng Plaat 23,700.00
0.01 Kg Paku Biasa 1 - 2,5 cm 20,000.00
0.5 Kg Besi strip 19,000.00
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit (contoh 10%) 10%
F Harga Satuan Pekerjaan (D+E)
Pemasangan 1 m2 Rangka Besi Hollow Galvanis 40.40 mm.
16 A.4.2.1.20 1 m2
Modul 60x120cm. untuk Partisi

A Tenaga
L.01 0.250 OH Pekerja 82,000.00
L.02 0.250 OH Tukang Besi 90,000.00
L.03 0.025 OH Kepala Tukang 95,000.00
L.04 0.013 OH Mandor 95,000.00
B Bahan
3.50 m' Rangka metal hollow 40.40.2 mm 28,333.33
1.00 **) Assesoris (perkuatan; las dll) 99,166.67
**) 100% x rangka
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit (contoh 10%) 10%
F Harga Satuan Pekerjaan (D+E)

Pemasangan 1 m2 Rangka Besi Hollow Galvanis 40.40 mm.


17 A.4.2.1.21 1 m2
Modul 60x60cm. untuk Plafond

A Tenaga
L.01 0.350 OH Pekerja 82,000.00
L.02 0.350 OH Tukang Besi 90,000.00
L.03 0.035 OH Kepala Tukang 95,000.00
L.04 0.018 OH Mandor 95,000.00
B Bahan
4.00 m' Rangka metal hollow 40.40.2 mm 28,333.33
1.00 **) Assesoris (perkuatan; las dll) 113,333.33
**) 100% x rangka
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit (contoh 10%) 10%
F Harga Satuan Pekerjaan (D+E)

Pemasangan 1 m2 Atap Pelana Rangka Atap Baja Ringan


18 A.4.2.1.22 1 m2
(Canai Dingin) Profil C75

A Tenaga
L.01 0.734 OH Pekerja 82,000.00
L.02 0.734 OH Tukang Besi 90,000.00
L.03 0.073 OH Kepala Tukang 95,000.00
L.04 0.037 OH Mandor 95,000.00
B Bahan
0.873 btng Baja Ringan Canal Dingin C75 111,000.00
C PERALATAN
10 % Aksesoris *) harga bahan 96,903.00
D Jumlah A + B + C
E Overhead & Profit (contoh 10%) 10%
F Harga Satuan Pekerjaan (D+E)
Pemasangan 1 m2 Atap Jurai/Limasan Rangka Atap Baja
19 A.4.2.1.23 1 m2
Ringan (Canai Dingin) Profil C75

A Tenaga
L.01 0.7604 OH Pekerja 82,000.00
L.02 0.7604 OH Tukang Besi 90,000.00
L.03 0.0760 OH Kepala Tukang 95,000.00
L.04 0.0380 OH Mandor 95,000.00
B Bahan
0.873 btng Baja Ringan Canal Dingin C75 111,000.00
C PERALATAN
10 % Aksesoris *) harga bahan 96,903.00
D Jumlah A + B + C
E Overhead & Profit (contoh 10%) 10%
F Harga Satuan Pekerjaan (D+E)
JUMLAH

Rp

33,797.50
11,175.00
4,920.00
5,400.00
570.00
285.00
19,550.00
19,550.00

30,725.00
3,072.50
33,797.50

37,845.50
11,175.00
4,920.00
5,400.00
570.00
285.00
23,230.00
23,230.00

34,405.00
3,440.50
37,845.50

47,817.00
17,770.00
8,200.00
9,000.00
95.00
475.00
15,300.00
11,700.00
3,600.00
10,400
10,400
43,470.00
4,347.00
47,817.00
1,184,111.50

195,515.00
86,100.00
94,500.00
9,975.00
4,940.00
880,950.00
255,000.00
623,200.00
2,750.00

1,076,465.00
107,646.50
1,184,111.50

11,401.50
5,460.00
3,280.00
1,800.00
190.00
190.00
2,695.00
2,200.00
351.00
144.00
2,210
2,210
10,365.00
1,036.50
11,401.50

250,353.40
121,015.00
53,300.00
58,500.00
6,175.00
3,040.00
106,579.00
47,600.00
36,176.00
22,803.00

227,594.00
22,759.40
250,353.40
724,207.00
218,370.00
98,400.00
108,000.00
11,400.00
570.00
440,000.00
440,000.00

658,370.00
65,837.00
724,207.00

574,145.00
81,950.00
36,080.00
39,600.00
4,180.00
2,090.00
440,000.00
440,000.00

521,950.00
52,195.00
574,145.00

222,244.00
86,540.00
6,560.00
72,000.00
7,600.00
380.00
115,500.00
115,500.00

202,040.00
20,204.00
222,244.00

699,875.00
186,250.00
82,000.00
90,000.00
9,500.00
4,750.00
450,000.00
450,000.00

636,250.00
63,625.00
699,875.00
505,151.09
310,990.00
136,940.00
150,300.00
15,865.00
7,885.00
148,238.26
117,363.00
30,875.26

459,228.26
45,922.83
505,151.09

100,535.67
18,625.00
8,200.00
9,000.00
950.00
475.00
72,771.07
27,500.00
12,667.07
32,604.00

91,396.07
9,139.61
100,535.67
357,054.50
36,395.00
16,400.00
18,000.00
1,900.00
95.00
288,200.00
239,800.00
6,400.00
42,000.00

324,595.00
32,459.50
357,054.50

234,862.10

55,725.00
16,400.00
36,000.00
2,375.00
950.00
157,786.00
24,885.00
300.00
132,601.00

213,511.00
21,351.10
234,862.10

78,078.00

36,395.00
16,400.00
18,000.00
1,900.00
95.00
34,585.00
24,885.00
200.00
9,500.00

70,980.00
7,098.00
78,078.00
269,437.67

46,610.00
20,500.00
22,500.00
2,375.00
1,235.00
198,333.33
99,166.67
99,166.67

244,943.33
24,494.33
269,437.67

321,091.83

65,235.00
28,700.00
31,500.00
3,325.00
1,710.00
226,666.67
113,333.33
113,333.33

291,901.67
29,190.17
321,091.83

288,939.09

136,698.00
60,188.00
66,060.00
6,935.00
3,515.00
116,283.60
96,903.00
9,690.30
9,690.30
262,671.90
26,267.19
288,939.09
294,351.97

141,618.80
62,352.80
68,436.00
7,220.00
3,610.00
116,283.60
96,903.00
9,690.30
9,690.30
267,592.70
26,759.27
294,351.97
HARGA
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN BAHAN/UPAH
Rp

DIVISI IV A.4.4.1 HARGA SATUAN PEKERJAAN PASANGAN DINDING

Pemasangan 1m2 Dinding Bata Merah (5x11x22) cm Tebal


1 Batu
1 A.4.4.1.1 1 m2
dengan Mortar tipe M.fc’ 17. 2 Mpa ( Setara Campuran
1SP : 2PP).

A Tenaga
L.01 0.6 OH Pekerja 82,000.00
L.02 0.2 OH Tukang Batu 90,000.00
L.03 0.02 OH Kepala Tukang Batu 95,000.00
L.04 0.03 OH Mandor 95,000.00
B Bahan
140 Buah Bata Merah 900.00
43.5 Kg Portland Semen (PC) 1,520.00
0.08 m3 Pasir Pasang (PP) 313,000.00
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit (contoh 10%) 10%
F Harga Satuan Pekerjaan (D+E)
Overhead & Profit (contoh 10%)
Pemasangan 1m2 Dinding Bata Merah (5x11x22) cm Tebal
1 Batu
2 A.4.4.1.2 1 m2
dengan Mortar tipe S.fc’ 12. 5 Mpa ( Setara Campuran 1SP :
3PP)
A Tenaga
L.01 0.6 OH Pekerja 82,000.00
L.02 0.2 OH Tukang Batu 90,000.00
L.03 0.02 OH Kepala Tukang Batu 95,000.00
L.04 0.03 OH Mandor 95,000.00
B Bahan
140 Buah Bata Merah 900.00
32.95 Kg Portland Semen (PC) 1,520.00
0.091 m3 Pasir Pasang (PP) 313,000.00
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit (contoh 10%) 10%
F Harga Satuan Pekerjaan (D+E)

Pemasangan 1m2 Dinding Bata Merah (5x11x22) cm tebal 1 Batu dengan


Mortar tipe N.fc’ 5.2 Mpa ( Setara Campuran 1SP : 4PP)
3 A.4.4.1.3 1 m2

A Tenaga
L.01 0.6 OH Pekerja 82,000.00
L.02 0.2 OH Tukang Batu 90,000.00
L.03 0.02 OH Kepala Tukang Batu 95,000.00
L.04 0.03 OH Mandor 95,000.00
B Bahan
140 Buah Bata Merah 900.00
26.55 Kg Portland Semen (PC) 1,520.00
0.093 m3 Pasir Pasang (PP) 313,000.00
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit (contoh 10%) 10%
F Harga Satuan Pekerjaan (D+E)
Pemasangan 1m2 Dinding Bata Merah (5x11x22) cm tebal 1
4 A.4.4.1.4 1 m2 Batu dengan
Mortar tipe O. fc’ 2.4 Mpa ( Setara Campuran 1SP : 5PP)

A Tenaga
L.01 0.6 OH Pekerja 82,000.00
L.02 0.2 OH Tukang Batu 90,000.00
L.03 0.02 OH Kepala Tukang Batu 95,000.00
L.04 0.03 OH Mandor 95,000.00
B Bahan
140 Buah Bata Merah 900.00
22.2 Kg Portland Semen (PC) 1,520.00
0.102 m3 Pasir Pasang (PP) 313,000.00
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit (contoh 10%) 10%
F Harga Satuan Pekerjaan (D+E)

Pemasangan 1m2 Dinding Bata Merah (5x11x22) cm tebal 1


5 A.4.4.1.5 1 m2 batu
Campuran 1SP : 6PP
A Tenaga
L.01 0.6 OH Pekerja 82,000.00
L.02 0.2 OH Tukang Batu 90,000.00
L.03 0.02 OH Kepala Tukang Batu 95,000.00
L.04 0.03 OH Mandor 95,000.00
B Bahan
140 Buah Bata Merah 900.00
18.5 Kg Portland Semen (PC) 1,520.00
0.122 m3 Pasir Pasang (PP) 313,000.00
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit (contoh 10%) 10%
F Harga Satuan Pekerjaan (D+E)

Pemasangan Dinding Bata Merah Ukuran (5x11x22) cm


6 A.4.4.1.6 1 m2
Tebal 1 Bata Camp. 1SP : 3 KP :10PP

A Tenaga
L.01 0.6 OH Pekerja 82,000.00
L.02 0.2 OH Tukang Batu 90,000.00
L.03 0.02 OH Kepala Tukang Batu 95,000.00
L.04 0.03 OH Mandor 95,000.00
B Bahan
140 Buah Bata Merah 900.00
10.08 Kg Portland Semen (PC) 1,520.00
0.0925 m3 Pasir Pasang (PP) 313,000.00
0.0275 m3 Kapur Pasang (KP) 363,000.00
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit (contoh 10%) 10%
F Harga Satuan Pekerjaan (D+E)
Pemasangan 1m2 Dinding Bata Merah (5x11x22) cm Tebal
7 A.4.4.1.7 1 m2 ½ Batu dengan
Mortar tipe M.fc’ 17. 7 Mpa ( Setara Campuran 1SP : 2PP).

A Tenaga
L.01 0.30 OH Pekerja 82,000.00
L.02 0.1 OH Tukang Batu 90,000.00
L.03 0.01 OH Kepala Tukang 95,000.00
L.04 0.015 OH Mandor 95,000.00
B Bahan
70 Buah Bata Merah 5 x 11 x 22 900.00
18.95 Kg Portland Semen 1,520.00
0.038 m3 Pasir Pasang 313,000.00
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit (contoh 10%) 10%
F Harga Satuan Pekerjaan (D+E)

Pemasangan 1m2 Dinding Bata Merah (5x11x22) cm tebal


8 A.4.4.1.8 1 m2 ½ Batu dengan
Mortar tipe S. fc’ 12. 5 Mpa ( Setara Campuran 1SP : 3PP).

A Tenaga
L.01 0.30 OH Pekerja 82,000.00
L.02 0.1 OH Tukang Batu 90,000.00
L.03 0.01 OH Kepala Tukang 95,000.00
L.04 0.015 OH Mandor 95,000.00
B Bahan
70 Buah Bata Merah 5 x 11 x 22 900.00
14.37 Kg Portland Semen 1,520.00
0.04 m3 Pasir Pasang 313,000.00
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit (contoh 10%) 10%
F Harga Satuan Pekerjaan (D+E)

Pemasangan 1m2 Dinding Bata Merah (5x11x22) cm Tebal


9 A.4.4.1.9 1 m2 ½ Batu dengan
Mortar tipe N.fc’ 5.2 Mpa ( Setara Campuran 1SP : 4PP)

A Tenaga
L.01 0.30 OH Pekerja 82,000.00
L.02 0.1 OH Tukang Batu 90,000.00
L.03 0.01 OH Kepala Tukang 95,000.00
L.04 0.015 OH Mandor 95,000.00
B Bahan
70 Buah Bata Merah 5 x 11 x 22 900.00
11.50 Kg Portland Semen 1,520.00
0.043 m3 Pasir Pasang 313,000.00
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit (contoh 10%) 10%
F Harga Satuan Pekerjaan (D+E)
Pemasangan 1m2 Dinding Bata Merah (5x11x22)cm Tebal
10 A.4.4.1.10 1 m2 ½ Batu dengan
Mortar tipe O. fc’ 2.4 Mpa ( Setara Campuran 1SP : 5PP)

A Tenaga
L.01 0.30 OH Pekerja 82,000.00
L.02 0.1 OH Tukang Batu 90,000.00
L.03 0.01 OH Kepala Tukang 95,000.00
L.04 0.015 OH Mandor 95,000.00
B Bahan
70 Buah Bata Merah 5 x 11 x 22 900.00
9.68 Kg Portland Semen 1,520.00
0.045 m3 Pasir Pasang 313,000.00
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit (contoh 10%) 10%
F Harga Satuan Pekerjaan (D+E)

Pemasangan 1m2 Dinding Bata Merah (5x11x22)cm tebal ½


11 A.4.4.1.11 1 m2 Batu
Campuran 1SP : 6PP

A Tenaga
L.01 0.30 OH Pekerja 82,000.00
L.02 0.1 OH Tukang Batu 90,000.00
L.03 0.01 OH Kepala Tukang 95,000.00
L.04 0.015 OH Mandor 95,000.00
B Bahan
70 Buah Bata Merah 5 x 11 x 22 900.00
8.32 Kg Portland Semen 1,520.00
0.049 m3 Pasir Pasang 313,000.00
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit (contoh 10%) 10%
F Harga Satuan Pekerjaan (D+E)

12 A.4.4.1.12 1 m2 Pemasangan Dinding Bata Merah 1/2 Batu 1SP : 8PP

A Tenaga
L.01 0.30 OH Pekerja 82,000.00
L.02 0.1 OH Tukang Batu 90,000.00
L.03 0.01 OH Kepala Tukang 95,000.00
L.04 0.015 OH Mandor 95,000.00
B Bahan
70 Buah Bata Merah 5 x 11 x 22 900.00
6.50 Kg Portland Semen 1,520.00
0.05 m3 Pasir Pasang 313,000.00
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit (contoh 10%) 10%
F Harga Satuan Pekerjaan (D+E)
Pemasangan Dinding Bata Merah 1/2 Batu 1SP : 3KP :
13 A.4.4.1.13 1 m2
10PP

A Tenaga
L.01 0.30 OH Pekerja 82,000.00
L.02 0.1 OH Tukang Batu 90,000.00
L.03 0.01 OH Kepala Tukang 95,000.00
L.04 0.015 OH Mandor 95,000.00
B Bahan
70 Buah Bata Merah 5 x 11 x 22 900.00
4.5 Kg Portland Semen 1,520.00
0.05 m3 Pasir Pasang 313,000.00
0.015 m3 Kapur Padam 283,000.00
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit (contoh 10%) 10%
F Harga Satuan Pekerjaan (D+E)

Pemasangan Dinding Bata Merah 1/2 Batu Camp. 1SP :


14 A.4.4.1.14 1 m2
1KP : 1PP

A Tenaga
L.01 0.30 OH Pekerja 82,000.00
L.02 0.1 OH Tukang Batu 90,000.00
L.03 0.01 OH Kepala Tukang 95,000.00
L.04 0.015 OH Mandor 95,000.00
B Bahan
70 Buah Bata Merah 5 x 11 x 22 900.00
0.018 m3 Semen Merah 158,500.00
0.018 m3 Pasir Pasang 313,000.00
0.018 m3 Kapur Padam 283,000.00
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit (contoh 10%) 10%
F Harga Satuan Pekerjaan (D+E)

Pemasangan Dinding Bata Merah 1/2 Batu 1SM : 1KP :


15 A.4.4.1.15 1 m2
2PP

A Tenaga
L.01 0.30 OH Pekerja 82,000.00
L.02 0.1 OH Tukang Batu 90,000.00
L.03 0.01 OH Kepala Tukang 95,000.00
L.04 0.015 OH Mandor 95,000.00
B Bahan
70 Buah Bata Merah 5 x 11 x 22 900.00
0.014 m3 Semen Merah 158,500.00
0.028 m3 Pasir Pasang 313,000.00
0.014 m3 Kapur Padam 283,000.00
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit (contoh 10%) 10%
F Harga Satuan Pekerjaan (D+E)
Pemasangan 1m2 Dinding Conblock HB20 dengan Mortar Tipe S.fc’ 12.
16 A.4.4.1.16 1 m2
5 Mpa ( Setara Campuran 1SP : 3PP)

A Tenaga
L.01 0.350 OH Pekerja 82,000.00
L.02 0.150 OH Tukang Batu 90,000.00
L.03 0.015 OH Kepala Tukang 95,000.00
L.04 0.018 OH Mandor 95,000.00
B Bahan
12.500 buah HB-20 6,000.00
30.320 kg PC 1,520.00
0.728 m3 Pasir Pasang 313,000.00
0.280 kg Besi Angkur Ø 8 mm 17,000.00
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit (contoh 10%) 10%
F Harga Satuan Pekerjaan (D+E)

HB20 : Hollow Block tebal 20cm

Pemasangan 1m2 Dinding Conblock HB20 Campuran1SP :4PP dengan


17 A.4.4.1.17 1 m2
Mortar Tipe N.fc’ 5.2 Mpa ( Setara Campuran 1SP : 4PP)

A Tenaga
L.01 0.350 OH Pekerja 82,000.00
L.02 0.150 OH Tukang Batu 90,000.00
L.03 0.015 OH Kepala Tukang 95,000.00
L.04 0.018 OH Mandor 95,000.00

B Bahan
12.500 buah Batako 6,000.00
24.260 kg PC 1,520.00
0.772 m3 Pasir Pasang 313,000.00
0.280 kg Besi Angkur Ø 8 mm 17,000.00
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit (contoh 10%) 10%
F Harga Satuan Pekerjaan (D+E)

HB20 : Hollow Block tebal 20cm

Pemasangan 1m2 Dinding Conblock HB15 dengan Mortar Tipe S. fc’ 12.
18 A.4.4.1.18 1 m2
5 Mpa ( Setara Campuran 1SP : 3PP)

A Tenaga
L.01 0.320 OH Pekerja 82,000.00
L.02 0.120 OH Tukang Batu 90,000.00
L.03 0.012 OH Kepala Tukang 95,000.00
L.04 0.016 OH Mandor 95,000.00
B Bahan
12.500 buah HB-15 6,000.00
22.740 kg PC 1,520.00
0.550 m3 Pasir Pasang 313,000.00
0.280 kg Besi Angkur Ø 8 mm 17,000.00
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit (contoh 10%) 10%
F Harga Satuan Pekerjaan (D+E)

HB15: Hollow Block tebal 15cm


Pemasangan 1 m2 Dinding Conblock HB15 dengan Mortar Tipe N. fc’
19 A.4.4.1.19 1 m2
5.2 Mpa ( Setara Campuran 1SP : 4PP)

A Tenaga
L.01 0.320 OH Pekerja 82,000.00
L.02 0.120 OH Tukang Batu 90,000.00
L.03 0.012 OH Kepala Tukang 95,000.00
L.04 0.016 OH Mandor 95,000.00
B Bahan
12.500 buah HB-15 6,000.00
18.200 kg PC 1,520.00
0.582 m3 Pasir Pasang 313,000.00
0.280 kg Besi Angkur Ø 8 mm 17,000.00
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit (contoh 10%) 10%
F Harga Satuan Pekerjaan (D+E)
HB15: Hollow Block tebal 15cm

Pemasangan 1 m2 Dinding Conblock HB10 dengan Mortar Tipe S. fc’ 12.


20 A.4.4.1.20 1 m2
5 Mpa (Setara Campuran 1SP : 3PP)

A Tenaga
L.01 0.300 OH Pekerja 82,000.00
L.02 0.100 OH Tukang Batu 90,000.00
L.03 0.010 OH Kepala Tukang 95,000.00
L.04 0.015 OH Mandor 95,000.00
B Bahan
12.500 buah HB-10 6,000.00
15.160 kg PC 1,520.00
0.364 m3 Pasir Pasang 313,000.00
0.280 kg Besi Angkur Ø 8 mm 17,000.00
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit (contoh 10%) 10%
F Harga Satuan Pekerjaan (D+E)

Hb10 : Hollow Block tebal 10cm

Pemasangan 1 m2 Dinding Conblock HB10 dengan Mortar Tipe N. fc’


21 A.4.4.1.21 1 m2
5.2 Mpa (Setara Campuran 1SP : 4PP)

A Tenaga
L.01 0.300 OH Pekerja 82,000.00
L.02 0.100 OH Tukang Batu 90,000.00
L.03 0.010 OH Kepala Tukang 95,000.00
L.04 0.015 OH Mandor 95,000.00

B Bahan
12.500 buah HB-10 6,000.00
12.130 kg PC 1,520.00
0.388 m3 Pasir Pasang 313,000.00
0.280 kg Besi Angkur Ø 8 mm 17,000.00
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit (contoh 10%) 10%
F Harga Satuan Pekerjaan (D+E)
Hb10 : Hollow Block tebal 10cm
Pemasangan 1 m2 Dinding Terawang (rooster) 12x11x24
22 A.4.4.1.22 1 m2 dengan
Mortar Tipe S.fc’ 12. 5 Mpa ( Setara Campuran 1SP : 3PP)

A Tenaga
L.01 0.30 OH Pekerja 82,000.00
L.02 0.1 OH Tukang Batu 90,000.00
L.03 0.01 OH Kepala Tukang 95,000.00
L.04 0.015 OH Mandor 95,000.00
B Bahan
30 Buah Bata rooster 7,666.67
11 kg Portland Semen 1,520.00
0.035 m3 Pasir Pasang 313,000.00
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit (contoh 10%) 10%
F Harga Satuan Pekerjaan (D+E)

Pemasangan 1 m2 Dinding Terawang (rooster) 12x11x24


23 A.4.4.1.23 1 m2 dengan Mortar
Tipe N.fc’ 5.2 Mpa ( Setara Campuran 1SP : 4PP)

A Tenaga
L.01 0.30 OH Pekerja 82,000.00
L.02 0.1 OH Tukang Batu 90,000.00
L.03 0.01 OH Kepala Tukang 95,000.00
L.04 0.015 OH Mandor 95,000.00
B Bahan
30 Buah Bata Terawang 7,666.67
11 kg Portland Semen 1,520.00
0.035 m3 Pasir Pasang 313,000.00
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit (contoh 10%) 10%
F Harga Satuan Pekerjaan (D+E)

Pemasangan 1 m2 Dinding bata Berongga Ekspose


24 A.4.4.1.24 1 m2 12x11x24 dengan
Mortar Tipe S.fc’ 12. 5 Mpa ( Setara Campuran 1SP : 3PP)

m2 Tenaga
L.01 0.30 OH Pekerja 82,000.00
L.02 0.1 OH Tukang Batu 90,000.00
L.03 0.01 OH Kepala Tukang 95,000.00
L.04 0.015 OH Mandor 95,000.00
OH Bahan
70 Buah Bata Berongga 4,000.00
14 kg Portland Semen 1,520.00
0.032 m3 Pasir Pasang 313,000.00
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit (contoh 10%) 10%
F Harga Satuan Pekerjaan (D+E)
Pemasangan 1 m2 Dinding Bata Ringan Tebal 7.5cm
25 A.4.4.1.25 1 m2
dengan Mortar Siap Pakai

m2 Tenaga 0.075
L.01 0.67 OH Pekerja 0.12 725000 82,000.00
L.02 1.3 OH Tukang Batu 1 6525 90,000.00
L.03 0.13 OH Kepala Tukang 13.3333333333333 95,000.00
L.04 0.003 OH Mandor 111.111111111111 95,000.00
OH Bahan
8.40 Buah Bata Ringan Tebal 7,5 cm 90000 8,200.00
0.473 kg Mortar Siap Pakai 3,125.00

C PERALATAN
D Jumlah A + B + C
E Overhead & Profit (contoh 10%) 10%
F Harga Satuan Pekerjaan (D+E)

Pemasangan 1m2 Dinding Bata Ringan Tebal 10cm dengan


26 A.4.4.1.26 1 m2
Mortar Siap Pakai
m2 Tenaga 0.075
L.01 0.671 OH Pekerja 0.12 700000 82,000.00
L.02 1.300 OH Tukang Batu 0.1 8400 90,000.00
L.03 0.013 OH Kepala Tukang 10 95,000.00
L.04 0.003 OH Mandor 83.3333333333333 95,000.00
OH Bahan
8.40 Buah Bata Ringan Tebal 10 cm 90000 10,100.00
0.063 kg Mortar Siap Pakai 3,125.00

C PERALATAN
D Jumlah A + B + C
E Overhead & Profit (contoh 10%) 10%
F Harga Satuan Pekerjaan (D+E)
JUMLAH

Rp

318,021.00

71,950.00
49,200.00
18,000.00
1,900.00
2,850.00
217,160.00
126,000.00
66,120.00
25,040.00

289,110.00
28,911.00
318,021.00

304,168.70

71,950.00
49,200.00
18,000.00
1,900.00
2,850.00
204,567.00
126,000.00
50,084.00
28,483.00

276,517.00
27,651.70
304,168.70

294,156.50

71,950.00
49,200.00
18,000.00
1,900.00
2,850.00
195,465.00
126,000.00
40,356.00
29,109.00

267,415.00
26,741.50
294,156.50
289,982.00

71,950.00
49,200.00
18,000.00
1,900.00
2,850.00
191,670.00
126,000.00
33,744.00
31,926.00

263,620.00
26,362.00
289,982.00

290,681.60

71,950.00
49,200.00
18,000.00
1,900.00
2,850.00
192,306.00
126,000.00
28,120.00
38,186.00

264,256.00
26,425.60
290,681.60

277,427.26

71,950.00
49,200.00
18,000.00
1,900.00
2,850.00
180,256.60
126,000.00
15,321.60
28,952.50
9,982.50

252,206.60
25,220.66
277,427.26
153,640.30

35,975.00
24,600.00
9,000.00
950.00
1,425.00
103,698.00
63,000.00
28,804.00
11,894.00

139,673.00
13,967.30
153,640.30

146,671.14

35,975.00
24,600.00
9,000.00
950.00
1,425.00
97,362.40
63,000.00
21,842.40
12,520.00

133,337.40
13,333.74
146,671.14

142,905.40

35,975.00
24,600.00
9,000.00
950.00
1,425.00
93,939.00
63,000.00
17,480.00
13,459.00

129,914.00
12,991.40
142,905.40
140,550.96

35,975.00
24,600.00
9,000.00
950.00
1,425.00
91,798.60
63,000.00
14,713.60
14,085.00

127,773.60
12,777.36
140,550.96

139,654.24

35,975.00
24,600.00
9,000.00
950.00
1,425.00
90,983.40
63,000.00
12,646.40
15,337.00

126,958.40
12,695.84
139,654.24

136,955.50

35,975.00
24,600.00
9,000.00
950.00
1,425.00
88,530.00
63,000.00
9,880.00
15,650.00

124,505.00
12,450.50
136,955.50
138,281.00

35,975.00
24,600.00
9,000.00
950.00
1,425.00
89,735.00
63,000.00
6,840.00
15,650.00
4,245.00

125,710.00
12,571.00
138,281.00

123,811.60

35,975.00
24,600.00
9,000.00
950.00
1,425.00
76,581.00
63,000.00
2,853.00
5,634.00
5,094.00

112,556.00
11,255.60
123,811.60

125,312.00

35,975.00
24,600.00
9,000.00
950.00
1,425.00
77,945.00
63,000.00
2,219.00
8,764.00
3,962.00

113,920.00
11,392.00
125,312.00
438,949.94

45,335.00
28,700.00
13,500.00
1,425.00
1,710.00
353,710.40
75,000.00
46,086.40
227,864.00
4,760.00

399,045.40
39,904.54
438,949.94

443,966.82

45,335.00
28,700.00
13,500.00
1,425.00
1,710.00
358,271.20
75,000.00
36,875.20
241,636.00
4,760.00

403,606.20
40,360.62
443,966.82

358,792.28

39,700.00
26,240.00
10,800.00
1,140.00
1,520.00
286,474.80
75,000.00
34,564.80
172,150.00
4,760.00

326,174.80
32,617.48
358,792.28
362,219.00

39,700.00
26,240.00
10,800.00
1,140.00
1,520.00
289,590.00
75,000.00
27,664.00
182,166.00
4,760.00

329,290.00
32,929.00
362,219.00

277,981.22

35,975.00
24,600.00
9,000.00
950.00
1,425.00
216,735.20
75,000.00
23,043.20
113,932.00
4,760.00

252,710.20
25,271.02
277,981.22

281,178.26

35,975.00
24,600.00
9,000.00
950.00
1,425.00
219,641.60
75,000.00
18,437.60
121,444.00
4,760.00

255,616.60
25,561.66
281,178.26
323,015.00

35,975.00
24,600.00
9,000.00
950.00
1,425.00
257,675.00
230,000.00
16,720.00
10,955.00

293,650.00
29,365.00
323,015.00

323,015.00

35,975.00
24,600.00
9,000.00
950.00
1,425.00
257,675.00
230,000.00
16,720.00
10,955.00

293,650.00
29,365.00
323,015.00

381,998.10

35,975.00
24,600.00
9,000.00
950.00
1,425.00
311,296.00
280,000.00
21,280.00
10,016.00

347,271.00
34,727.10
381,998.10
280,426.44

184,575.00
54,940.00
117,000.00
12,350.00
285.00
70,358.13
68,880.00
1,478.13

254,933.13
25,493.31
280,426.44

284,436.76

173,542.00
55,022.00
117,000.00
1,235.00
285.00
85,036.88
84,840.00
196.88

258,578.88
25,857.89
284,436.76
HARGA
JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN BAHAN/UPAH
Rp Rp
DIVISI IV A.4.4.2 HARGA SATUAN PEKERJAAN PLESTERAN
1 A.4.4.2.1 1 m2 Pemasangan Plesteran 1 Pc : 1 Pp Tebal 15 mm 76,476.49
A Tenaga 40,950.00

L.01 0.3 OH Pekerja 82,000.00 24,600.00

L.02 0.15 OH Tukang batu 90,000.00 13,500.00

L.03 0.015 OH Kepala Tukang 95,000.00 1,425.00

L.04 0.015 OH Mandor 95,000.00 1,425.00


B Bahan 28,574.08
15.504 Kg Portland Semen 1,520.00 23,566.08
0.016 m3 Pasir Pasang 313,000.00 5,008.00
C PERALATAN
D Jumlah A + B + C 69,524.08
E Overhead & Profit (contoh 10%) 10% 6,952.41
F Harga Satuan Pekerjaan (D+E) 76,476.49
Overhead & Profit (contoh 10%)
2 A.4.4.2.2 1 m2 Pemasangan Plesteran 1 Pc : 2 Pp Tebal 15 mm 69,025.53
A Tenaga 40,950.00

L.01 0.3 OH Pekerja 82,000.00 24,600.00

L.02 0.15 OH Tukang batu 90,000.00 13,500.00

L.03 0.015 OH Kepala Tukang 95,000.00 1,425.00

L.04 0.015 OH Mandor 95,000.00 1,425.00


B Bahan 21,800.48
10.224 Kg Portland Semen 1,520.00 15,540.48
0.020 m3 Pasir Pasang 313,000.00 6,260.00
C PERALATAN
D Jumlah A + B + C 62,750.48
E Overhead & Profit (contoh 10%) 10% 6,275.05
F Harga Satuan Pekerjaan (D+E) 69,025.53

3 A.4.4.2.3 1 m2 Pemasangan Plesteran 1 Pc : 3 Pp Tebal 15 mm 65,965.37


A Tenaga 40,950.00

L.01 0.3 OH Pekerja 82,000.00 24,600.00

L.02 0.15 OH Tukang batu 90,000.00 13,500.00

L.03 0.015 OH Kepala Tukang 95,000.00 1,425.00

L.04 0.015 OH Mandor 95,000.00 1,425.00


B Bahan 19,018.52
7.776 Kg Portland Semen 1,520.00 11,819.52
0.023 m3 Pasir Pasang 313,000.00 7,199.00
C PERALATAN
D Jumlah A + B + C 59,968.52
E Overhead & Profit (contoh 10%) 10% 5,996.85
F Harga Satuan Pekerjaan (D+E) 65,965.37
4 A.4.4.2.4 1 m2 Pemasangan Plesteran 1 Pc : 4 Pp Tebal 15 mm 63,741.48
A Tenaga 40,950.00

L.01 0.3 OH Pekerja 82,000.00 24,600.00

L.02 0.15 OH Tukang batu 90,000.00 13,500.00

L.03 0.015 OH Kepala Tukang 95,000.00 1,425.00

L.04 0.015 OH Mandor 95,000.00 1,425.00


B Bahan 16,996.80
6.240 Kg Portland Semen 1,520.00 9,484.80
0.024 m3 Pasir Pasang 313,000.00 7,512.00
C PERALATAN
D Jumlah A + B + C 57,946.80
E Overhead & Profit (contoh 10%) 10% 5,794.68
F Harga Satuan Pekerjaan (D+E) 63,741.48

5 A.4.4.2.5 1 m2 Pemasangan Plesteran 1 Pc : 5 Pp Tebal 15 mm 62,664.45


A Tenaga 40,950.00

L.01 0.3 OH Pekerja 82,000.00 24,600.00

L.02 0.15 OH Tukang batu 90,000.00 13,500.00

L.03 0.015 OH Kepala Tukang 95,000.00 1,425.00

L.04 0.015 OH Mandor 95,000.00 1,425.00


B Bahan 16,017.68
5.184 Kg Portland Semen 1,520.00 7,879.68
0.026 m3 Pasir Pasang 313,000.00 8,138.00
C PERALATAN
D Jumlah A + B + C 56,967.68
E Overhead & Profit (contoh 10%) 10% 5,696.77
F Harga Satuan Pekerjaan (D+E) 62,664.45

6 A.4.4.2.6 1 m2 Pemasangan Plesteran 1 Pc : 6 Pp Tebal 15 mm 61,724.65


Tenaga 40,950.00

L.01 0.3 OH Pekerja 82,000.00 24,600.00

L.02 0.15 OH Tukang batu 90,000.00 13,500.00

L.03 0.015 OH Kepala Tukang 95,000.00 1,425.00

L.04 0.015 OH Mandor 95,000.00 1,425.00


Bahan 15,163.32
4.416 Kg Portland Semen 1,520.00 6,712.32
0.027 m3 Pasir Pasang 313,000.00 8,451.00
C PERALATAN
D Jumlah A + B + C 56,113.32
E Overhead & Profit (contoh 10%) 10% 5,611.33
F Harga Satuan Pekerjaan (D+E) 61,724.65
7 A.4.4.2.7 1 m2 Pemasangan Plesteran 1 Pc : 7 Pp Tebal 15 mm 61,266.39
A Tenaga 40,950.00

L.01 0.3 OH Pekerja 82,000.00 24,600.00

L.02 0.15 OH Tukang batu 90,000.00 13,500.00

L.03 0.015 OH Kepala Tukang 95,000.00 1,425.00

L.04 0.015 OH Mandor 95,000.00 1,425.00


B Bahan 14,746.72
3.936 Kg Portland Semen 1,520.00 5,982.72
0.028 m3 Pasir Pasang 313,000.00 8,764.00
C PERALATAN
D Jumlah A + B + C 55,696.72
E Overhead & Profit (contoh 10%) 10% 5,569.67
F Harga Satuan Pekerjaan (D+E) 61,266.39

8 A.4.4.2.8 1 m2 Pemasangan Plesteran 1 Pc : 8 Pp Tebal 15 mm 60,808.13


A Tenaga 40,950.00

L.01 0.30 OH Pekerja 82,000.00 24,600.00

L.02 0.15 OH Tukang batu 90,000.00 13,500.00

L.03 0.015 OH Kepala Tukang 95,000.00 1,425.00

L.04 0.015 OH Mandor 95,000.00 1,425.00


B Bahan 14,330.12
3.456 Kg Portland Semen 1,520.00 5,253.12
0.029 m3 Pasir Pasang 313,000.00 9,077.00
C PERALATAN
D Jumlah A + B + C 55,280.12
E Overhead & Profit (contoh 10%) 10% 5,528.01
F Harga Satuan Pekerjaan (D+E) 60,808.13

9 A.4.4.2.9 1 m2 Pemasangan Plesteran 1 Pc :1/2 Kp:3 Pp Tebal 15 mm 62,791.52


A Tenaga 43,170.00

L.01 0.36 OH Pekerja 82,000.00 29,520.00

L.02 0.12 OH Tukang batu 90,000.00 10,800.00

L.03 0.012 OH Kepala Tukang 95,000.00 1,140.00

L.04 0.018 OH Mandor 95,000.00 1,710.00


B Bahan 13,913.20
5.760 Kg Portland Semen 1,520.00 8,755.20
0.003 m3 Kapur Pasang 363,000.00 1,089.00
0.013 m3 Pasir Pasang 313,000.00 4,069.00
C PERALATAN
D Jumlah A + B + C 57,083.20
E Overhead & Profit (contoh 10%) 10% 5,708.32
F Harga Satuan Pekerjaan (D+E) 62,791.52
10 A.4.4.2.10 1 m2 Pemasangan Plesteran 1 Pc : 2 Kp : 8 Pp Tebal 15 mm 60,945.50
A Tenaga 43,170.00

L.01 0.36 OH Pekerja 82,000.00 29,520.00

L.02 0.12 OH Tukang batu 90,000.00 10,800.00

L.03 0.012 OH Kepala Tukang 95,000.00 1,140.00

L.04 0.018 OH Mandor 95,000.00 1,710.00


B Bahan 12,235.00
3 kg Portland Semen 1,520.00 4,560.00
0.005 m3 Kapur Padam 283,000.00 1,415.00
0.020 m3 Pasir Pasang 313,000.00 6,260.00
C PERALATAN
D Jumlah A + B + C 55,405.00
E Overhead & Profit (contoh 10%) 10% 5,540.50
F Harga Satuan Pekerjaan (D+E) 60,945.50

11 A.4.4.2.11 1 m2 Pemasangan Plesteran 1 SM : 1 Kp : 1 Pp Tebal 15 mm 54,956.55


A Tenaga 43,170.00

L.01 0.36 OH Pekerja 82,000.00 29,520.00

L.02 0.12 OH Tukang batu 90,000.00 10,800.00

L.03 0.012 OH Kepala Tukang 95,000.00 1,140.00

L.04 0.018 OH Mandor 95,000.00 1,710.00


B Bahan 6,790.50
0.009 m3 Semen Merah 158,500.00 1,426.50
0.009 m3 Kapur Padam 283,000.00 2,547.00
0.009 m3 Pasir Pasang 313,000.00 2,817.00
C PERALATAN
D Jumlah A + B + C 49,960.50
E Overhead & Profit (contoh 10%) 10% 4,996.05
F Harga Satuan Pekerjaan (D+E) 54,956.55

12 A.4.4.2.12 1 m2 Pemasangan Plesteran 1 SM : 1 Kp : 2 Pp Tebal 15 mm 56,051.05


A Tenaga 43,170.00

L.01 0.36 OH Pekerja 82,000.00 29,520.00

L.02 0.12 OH Tukang batu 90,000.00 10,800.00

L.03 0.012 OH Kepala Tukang 95,000.00 1,140.00

L.04 0.018 OH Mandor 95,000.00 1,710.00


B Bahan 7,785.50
0.007 m3 Semen Merah 158,500.00 1,109.50
0.007 m3 Kapur Padam 283,000.00 1,981.00
0.015 m3 Pasir Pasang 313,000.00 4,695.00
C PERALATAN
D Jumlah A + B + C 50,955.50
E Overhead & Profit (contoh 10%) 10% 5,095.55
F Harga Satuan Pekerjaan (D+E) 56,051.05
13 A.4.4.2.13 1 m2 Pemasangan Plesteran 1 Pc : 2 Pp Tebal 20 mm 92,357.80
A Tenaga 54,790.00

L.01 0.40 OH Pekerja 82,000.00 32,800.00

L.02 0.20 OH Tukang batu 90,000.00 18,000.00

L.03 0.020 OH Kepala Tukang 95,000.00 1,900.00

L.04 0.022 OH Mandor 95,000.00 2,090.00


B Bahan 29,171.64
13.632 kg Portland Semen 1,520.00 20,720.64
0.027 m3 Pasir Pasang 313,000.00 8,451.00
C PERALATAN
D Jumlah A + B + C 83,961.64
E Overhead & Profit (contoh 10%) 10% 8,396.16
F Harga Satuan Pekerjaan (D+E) 92,357.80

14 A.4.4.2.14 1 m2 Pemasangan Plesteran 1Pc : 3Pp Tebal 20 mm 67,917.36


A Tenaga 42,455.00
L.01 0.26 OH Pekerja 82,000.00 21,320.00
L.02 0.2 OH Tukang batu 90,000.00 18,000.00
L.03 0.02 OH Kepala Tukang 95,000.00 1,900.00
L.04 0.013 OH Mandor 95,000.00 1,235.00
B Bahan 25,462.36
10.368 Kg Portland Semen 1,520.00 15,759.36
0.031 m3 Pasir Pasang 313,000.00 9,703.00
C PERALATAN
D Jumlah A + B + C 69,152.36
E Overhead & Profit (contoh 10%) 10% 6,915.24
F Harga Satuan Pekerjaan (D+E) 76,067.60

15 A.4.4.2.15 1 m2 Pemasangan Plesteran 1 Pc : 4 Pp Tebal 20 mm 85,197.64


A Tenaga 54,790.00

L.01 0.40 OH Pekerja 82,000.00 32,800.00

L.02 0.20 OH Tukang batu 90,000.00 18,000.00

L.03 0.020 OH Kepala Tukang 95,000.00 1,900.00

L.04 0.022 OH Mandor 95,000.00 2,090.00


B Bahan 22,662.40
8.320 kg Portland Semen 1,520.00 12,646.40
0.032 m3 Pasir Pasang 313,000.00 10,016.00
C PERALATAN
D Jumlah A + B + C 77,452.40
E Overhead & Profit (contoh 10%) 10% 7,745.24
F Harga Satuan Pekerjaan (D+E) 85,197.64
16 A.4.4.2.16 1 m2 Pemasangan Plesteran 1Pc : 5Pp Tebal 20 mm 83,876.36
A Tenaga 54,790.00

L.01 0.400 OH Pekerja 82,000.00 32,800.00

L.02 0.200 OH Tukang batu 90,000.00 18,000.00

L.03 0.020 OH Kepala Tukang 95,000.00 1,900.00

L.04 0.022 OH Mandor 95,000.00 2,090.00


B Bahan 21,461.24
6.912 Kg Portland Semen 1,520.00 10,506.24
0.035 m3 Pasir Pasang 313,000.00 10,955.00
C PERALATAN
D Jumlah A + B + C 76,251.24
E Overhead & Profit (contoh 10%) 10% 7,625.12
F Harga Satuan Pekerjaan (D+E) 83,876.36

17 A.4.4.2.17 1 m2 Pemasangan Plesteran 1Pc : 6Pp Tebal 20 mm 82,508.54


A Tenaga 54,790.00

L.01 0.40 OH Pekerja 82,000.00 32,800.00

L.02 0.2 OH Tukang batu 90,000.00 18,000.00

L.03 0.02 OH Kepala Tukang 95,000.00 1,900.00

L.04 0.022 OH Mandor 95,000.00 2,090.00


B Bahan 20,217.76
5.888 Kg Portland Semen 1,520.00 8,949.76
0.036 m3 Pasir Pasang 313,000.00 11,268.00
C PERALATAN
D Jumlah A + B + C 75,007.76
E Overhead & Profit (contoh 10%) 10% 7,500.78
F Harga Satuan Pekerjaan (D+E) 82,508.54

18 A.4.4.2.18 1 m2 Pemasangan Plesteran 1 SM : 2 Kp : 2 Pp Tebal 20 mm 76,634.25


A Tenaga 60,060.00

L.01 0.440 OH Pekerja 82,000.00 36,080.00

L.02 0.22 OH Tukang batu 90,000.00 19,800.00

L.03 0.022 OH Kepala Tukang 95,000.00 2,090.00

L.04 0.022 OH Mandor 95,000.00 2,090.00


B Bahan 9,607.50
0.009 m3 Semen Merah 158,500.00 1,426.50
0.009 m3 Kapur Padam 283,000.00 2,547.00
0.018 m3 Pasir Pasang 313,000.00 5,634.00
C PERALATAN
D Jumlah A + B + C 69,667.50
E Overhead & Profit (contoh 10%) 10% 6,966.75
F Harga Satuan Pekerjaan (D+E) 76,634.25
19 A.4.4.2.19 1 m2 Pemasangan 1 m2 Berapen 1SP : 5PP Tebal 15 mm 40,246.45
A Tenaga 20,570.00

L.01 0.15 OH Pekerja 82,000.00 12,300.00

L.02 0.075 OH Tukang batu 90,000.00 6,750.00

L.03 0.008 OH Kepala Tukang 95,000.00 760.00

L.04 0.008 OH Mandor 95,000.00 760.00


B Bahan 16,017.68
5.184 Kg Portland Semen 1,520.00 7,879.68
0.026 m3 Pasir Pasang 313,000.00 8,138.00
C PERALATAN
D Jumlah A + B + C 36,587.68
E Overhead & Profit (contoh 10%) 10% 3,658.77
F Harga Satuan Pekerjaan (D+E) 40,246.45

20 A.4.4.2.20 1 m' Pemasangan Plesteran Skoning 1 Pc : 2Pp, lebar 10 mm 56,725.90

A Tenaga 46,740.00

L.01 0.080 OH Pekerja 82,000.00 6,560.00

L.02 0.40 OH Tukang batu 90,000.00 36,000.00

L.03 0.040 OH Kepala Tukang 95,000.00 3,800.00

L.04 0.004 OH Mandor 95,000.00 380.00


B Bahan 4,829.00
0.5 Kg Portland Semen 1,520.00 760.00
0.013 m3 Pasir Pasang 313,000.00 4,069.00
C PERALATAN
D Jumlah A + B + C 51,569.00
E Overhead & Profit (contoh 10%) 10% 5,156.90
F Harga Satuan Pekerjaan (D+E) 56,725.90

21 A.4.4.2.21 1 m' Pemasangan Plesteran Granit 1Pc : 2 Granit , Tebal 10 mm 199,892.00

A Tenaga 61,520.00
L.01 0.450 OH Pekerja 82,000.00 36,900.00
L.02 0.225 OH Tukang batu 90,000.00 20,250.00
L.03 0.023 OH Kepala Tukang 95,000.00 2,185.00
L.04 0.023 OH Mandor 95,000.00 2,185.00
B Bahan 120,200.00
10 Kg Portland Semen 1,520.00 15,200.00
15 Kg Batu Granit 7,000.00 105,000.00
C PERALATAN
D Jumlah A + B + C 181,720.00
E Overhead & Profit (contoh 10%) 10% 18,172.00
F Harga Satuan Pekerjaan (D+E) 199,892.00
22 A.4.4.2.22 1 m' Pemasangan Plesteran Traso 1Pc : 2Traso, lebar 10 mm 210,287.00

A Tenaga 61,520.00
L.01 0.450 OH Pekerja 82,000.00 36,900.00
L.02 0.225 OH Tukang batu 90,000.00 20,250.00
L.03 0.023 OH Kepala Tukang 95,000.00 2,185.00
L.04 0.023 OH Mandor 95,000.00 2,185.00
B Bahan 129,650.00
10 Kg Portland Semen 1,520.00 15,200.00
15 m3 Batu Traso 7,630.00 114,450.00
C PERALATAN
D Jumlah A + B + C 191,170.00
E Overhead & Profit (contoh 10%) 10% 19,117.00
F Harga Satuan Pekerjaan (D+E) 210,287.00

23 A.4.4.2.23 1 m2 Pemasangan Plesteran Ciprat (kamprotan) 1Pc : 2 Pp 48,861.34


Tenaga 35,975.00

L.01 0.30 OH Pekerja 82,000.00 24,600.00

L.02 0.1 OH Tukang batu 90,000.00 9,000.00

L.03 0.01 OH Kepala Tukang 95,000.00 950.00

L.04 0.015 OH Mandor 95,000.00 1,425.00


Bahan 8,444.40
4.32 Kg Portland Semen 1,520.00 6,566.40
0.006 m3 Pasir Pasang 313,000.00 1,878.00
C PERALATAN
D Jumlah A + B + C 44,419.40
E Overhead & Profit (contoh 10%) 10% 4,441.94
F Harga Satuan Pekerjaan (D+E) 48,861.34

Pemasangan Finishing 1 m2 Dinding Siar Pasangan Bata


24 A.4.4.2.24 1 m2 27,823.58
Merah

A Tenaga 20,570.00

L.01 0.15 OH Pekerja 82,000.00 12,300.00

L.02 0.075 OH Tukang batu 90,000.00 6,750.00

L.03 0.008 OH Kepala Tukang 95,000.00 760.00

L.04 0.008 OH Mandor 95,000.00 760.00


B Bahan 4,724.16
3.108 Kg Portland Semen 1,520.00 4,724.16
C PERALATAN
D Jumlah A + B + C 25,294.16
E Overhead & Profit (contoh 10%) 10% 2,529.42
F Harga Satuan Pekerjaan (D+E) 27,823.58
Pemasangan Finishing 1m2 Dinding Siar Pasangan
25 A.4.4.2.25 1 m2 13,290.20
Conblock Ekspose

A Tenaga 9,650.00

L.01 0.070 OH Pekerja 82,000.00 5,740.00

L.02 0.035 OH Tukang batu 90,000.00 3,150.00

L.03 0.004 OH Kepala Tukang 95,000.00 380.00

L.04 0.004 OH Mandor 95,000.00 380.00


B Bahan 2,432.00
1.600 Kg Portland Semen 1,520.00 2,432.00
C PERALATAN
D Jumlah A + B + C 12,082.00
E Overhead & Profit (contoh 10%) 10% 1,208.20
F Harga Satuan Pekerjaan (D+E) 13,290.20

Pemasangan 1m2 Finishing Siar Pasangan Batu Kali.


26 A.4.4.2.26 1 m2 59,777.08
Campuran 1SP : 2PP

Tenaga 40,950.00

L.01 0.3 OH Pekerja 82,000.00 24,600.00

L.02 0.15 OH Tukang batu 90,000.00 13,500.00

L.03 0.015 OH Kepala Tukang 95,000.00 1,425.00

L.04 0.015 OH Mandor 95,000.00 1,425.00


Bahan 13,392.80
6.34 Kg Portland Semen 1,520.00 9,636.80
0.012 m3 Pasir Pasang 313,000.00 3,756.00
C PERALATAN
D Jumlah A + B + C 54,342.80
E Overhead & Profit (contoh 10%) 10% 5,434.28
F Harga Satuan Pekerjaan (D+E) 59,777.08

27 A.4.4.2.27 1 m2 Pemasangan Acian 35,464.00

Tenaga 27,300.00
L.01 0.20 OH Pekerja 82,000.00 16,400.00
L.02 0.10 OH Tukang batu 90,000.00 9,000.00
L.03 0.010 OH Kepala Tukang 95,000.00 950.00
L.04 0.010 OH Mandor 95,000.00 950.00
Bahan 4,940.00
3.25 Kg Portland Semen 1,520.00 4,940.00
C PERALATAN
D Jumlah A + B + C 32,240.00
E Overhead & Profit (contoh 10%) 10% 3,224.00
F Harga Satuan Pekerjaan (D+E) 35,464.00
28 A.4.4.2.28 1 m2 Pemasangan Plesteran dg Mortar Siap Pakai (MSP) 51,823.75

Tenaga 27,300.00
L.01 0.20 OH Pekerja 82,000.00 16,400.00
L.02 0.10 OH Tukang batu 90,000.00 9,000.00
L.03 0.010 OH Kepala Tukang 95,000.00 950.00
L.04 0.010 OH Mandor 95,000.00 950.00
Bahan 19,812.50
6.34 Kg Mortar Siap Pakai 3,125.00 19,812.50
C PERALATAN
D Jumlah A + B + C 47,112.50
E Overhead & Profit (contoh 10%) 10% 4,711.25
F Harga Satuan Pekerjaan (D+E) 51,823.75

29 A.4.4.2.29 1 m2 Pemasangan Acian dg Mortar Siap Pakai (MSP) 41,201.88

Tenaga 27,300.00
L.01 0.20 OH Pekerja 82,000.00 16,400.00
L.02 0.10 OH Tukang batu 90,000.00 9,000.00
L.03 0.010 OH Kepala Tukang 95,000.00 950.00
L.04 0.010 OH Mandor 95,000.00 950.00
Bahan 10,156.25
3.25 Kg Mortar Siap Pakai 3,125.00 10,156.25
C PERALATAN
D Jumlah A + B + C 37,456.25
E Overhead & Profit (contoh 10%) 10% 3,745.63
F Harga Satuan Pekerjaan (D+E) 41,201.88
HARGA JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN BAHAN/UPAH
Rp Rp

DIVISI IV A.4.4.3 HARGA SATUAN PEKERJAAN PENUTUP LANTAI dan DINDING

1 A.4.4.3.1 1 m2 Pemasangan 1 m2 lantai Ubin PC Abu-abu 40 x 40 cm 69,521.10

A Tenaga 34,220.00

L.01 0.25 OH Pekerja 82,000.00 20,500.00

L.02 0.125 OH Tukang Batu 90,000.00 11,250.00

L.03 0.013 OH Kepala Tukang 95,000.00 1,235.00

L.04 0.013 OH Mandor 95,000.00 1,235.00

B Bahan 28,981.00

6.63 Buah Ubin Abu-abu 40x40 cm - -

9.8 Kg Portland Semen 1,520.00 14,896.00

0.045 m3 Pasir Pasang 313,000.00 14,085.00

C PERALATAN

D Jumlah A + B + C 63,201.00

E Overhead & Profit (contoh 10%) 10% 6,320.10

F Harga Satuan Pekerjaan (D+E) 69,521.10

2 A.4.4.3.2 1 m2 Pemasangan 1 m2 lantai Ubin PC Abu-abu 30 x 30 cm 150,571.50

A Tenaga 34,220.00

L.01 0.25 OH Pekerja 82,000.00 20,500.00

L.02 0.125 OH Tukang Batu 90,000.00 11,250.00

L.03 0.013 OH Kepala Tukang 95,000.00 1,235.00

L.04 0.013 OH Mandor 95,000.00 1,235.00

B Bahan 102,663.18

11.87 Buah Ubin Abu-abu 30x30 cm 11.1111 6,181.82 73,378.18

10.0 Kg Portland Semen 0.3 1,520.00 15,200.00

0.0450 m3 Pasir Pasang 0.09 313,000.00 14,085.00

C PERALATAN

D Jumlah A + B + C 136,883.18

E Overhead & Profit (contoh 10%) 10% 13,688.32

F Harga Satuan Pekerjaan (D+E) 150,571.50

3 A.4.4.3.3 1 m2 Pemasangan 1 m2 lantai Ubin PC Abu-abu 20 x 20 cm 163,309.30

A Tenaga 36,950.00

L.01 0.27 OH Pekerja 82,000.00 22,140.00

L.02 0.135 OH Tukang Batu 90,000.00 12,150.00

L.03 0.014 OH Kepala Tukang 95,000.00 1,330.00

L.04 0.014 OH Mandor 95,000.00 1,330.00

B Bahan 111,513.00

26.5 Buah Ubin Abu-abu 20x20 cm 3,080.00 81,620.00

10.4 Kg Portland Semen 1,520.00 15,808.00

0.0450 m3 Pasir Pasang 313,000.00 14,085.00

C PERALATAN

D Jumlah A + B + C 148,463.00

E Overhead & Profit (contoh 10%) 10% 14,846.30


F Harga Satuan Pekerjaan (D+E) 163,309.30
4 A.4.4.3.5 1 m2 Pemasangan 1m2 Lantai ubin Warna Ukuran 30cm x 30cm 192,019.00

A Tenaga 35,490.00

L.01 0.26 OH Pekerja 82,000.00 21,320.00

L.02 0.130 OH Tukang Batu 90,000.00 11,700.00

L.03 0.013 OH Kepala Tukang 95,000.00 1,235.00

L.04 0.013 OH Mandor 95,000.00 1,235.00

B Bahan 139,072.73

11.87 Buah Ubin Warna 30x30 cm 7,227.27 85,787.73


10.0 Kg Portland Semen 1,520.00 15,200.00
1.50 Kg Semen warna 16,000.00 24,000.00

0.0450 m3 Pasir Pasang 313,000.00 14,085.00

C PERALATAN

D Jumlah A + B + C 174,562.73

E Overhead & Profit (contoh 10%) 10% 17,456.27

F Harga Satuan Pekerjaan (D+E) 192,019.00

5 A.4.4.3.6 1 m2 Pemasangan 1m2 Lantai ubin Warna Ukuran 20cm x 20cm 195,902.30

A Tenaga 36,950.00

L.01 0.27 OH Pekerja 82,000.00 22,140.00

L.02 0.135 OH Tukang Batu 90,000.00 12,150.00

L.03 0.014 OH Kepala Tukang 95,000.00 1,330.00

L.04 0.014 OH Mandor 95,000.00 1,330.00

B Bahan 141,143.00

26.5 Buah Ubin Warna 20x20 cm 3,220.00 85,330.00

10.4 Kg Portland Semen 1,520.00 15,808.00

1.62 Kg Semen warna 16,000.00 25,920.00

0.0450 m3 Pasir Pasang 313,000.00 14,085.00

C PERALATAN

D Jumlah A + B + C 178,093.00

E Overhead & Profit (contoh 10%) 10% 17,809.30

F Harga Satuan Pekerjaan (D+E) 195,902.30

6 A.4.4.3.7 1 m2 Pemasangan 1m2 Lantai Ubin Teraso Ukuran 40cm x 40cm 92,401.10

A Tenaga 34,220.00

L.01 0.25 OH Pekerja 82,000.00 20,500.00

L.02 0.125 OH Tukang Batu 90,000.00 11,250.00

L.03 0.013 OH Kepala Tukang 95,000.00 1,235.00

L.04 0.013 OH Mandor 95,000.00 1,235.00

B Bahan 49,781.00

6.63 Buah Ubin Teraso - -

9.8 Kg Portland Semen 1,520.00 14,896.00

1.3 Kg Semen warna 16,000.00 20,800.00

0.045 m3 Pasir Pasang 313,000.00 14,085.00

C PERALATAN

D Jumlah A + B + C 84,001.00

E Overhead & Profit (contoh 10%) 10% 8,400.10

F Harga Satuan Pekerjaan (D+E) 92,401.10


7 A.4.4.3.8 1 m2 Pemasangan 1m2 Lantai Ubin Teraso Ukuran 30cm x 30cm 203,889.00

A Tenaga 35,490.00

L.01 0.26 OH Pekerja 82,000.00 21,320.00

L.02 0.13 OH Tukang Batu 90,000.00 11,700.00

L.03 0.013 OH Kepala Tukang 95,000.00 1,235.00

L.04 0.013 OH Mandor 95,000.00 1,235.00

B Bahan 149,863.64

11.87 Buah Ubin Teraso 8,136.36 96,578.64

10 Kg Portland Semen 1,520.00 15,200.00

1.5 Kg Semen warna 16,000.00 24,000.00

0.045 m3 Pasir Pasang 313,000.00 14,085.00

C PERALATAN

D Jumlah A + B + C 185,353.64

E Overhead & Profit (contoh 10%) 10% 18,535.36

F Harga Satuan Pekerjaan (D+E) 203,889.00

8 A.4.4.3.9 1 m2 Pemasangan 1m2 Lantai Ubin Granit Ukuran 40cm x 40cm 303,533.45

A Tenaga 34,220.00

L.01 0.250 OH Pekerja 82,000.00 20,500.00

L.02 0.125 OH Tukang Batu 90,000.00 11,250.00

L.03 0.013 OH Kepala Tukang 95,000.00 1,235.00

L.04 0.013 OH Mandor 95,000.00 1,235.00

B Bahan 241,719.50

6.63 Buah Ubin Granito 40x40 cm 28,950.00 191,938.50

9.8 Kg Portland Semen 1,520.00 14,896.00

1.300 Kg Semen warna 16,000.00 20,800.00

0.045 m3 Pasir Pasang 313,000.00 14,085.00

C PERALATAN

D Jumlah A + B + C 275,939.50

E Overhead & Profit (contoh 10%) 10% 27,593.95

F Harga Satuan Pekerjaan (D+E) 303,533.45

9 A.4.4.3.10 1 m2 Pemasangan 1m2 Lantai Ubin Granit Ukuran 30cm x 30cm 294,694.50

A Tenaga 35,490.00

L.01 0.260 OH Pekerja 82,000.00 21,320.00

L.02 0.130 OH Tukang Batu 90,000.00 11,700.00

L.03 0.013 OH Kepala Tukang 95,000.00 1,235.00

L.04 0.013 OH Mandor 95,000.00 1,235.00

B Bahan 232,414.09

11.87 Buah Ubin Granito 30x30 cm 0.4 15,090.91 179,129.09

10.0 Kg Portland Semen 0.16 1,520.00 15,200.00

1.500 Kg Semen warna 6.25 16,000.00 24,000.00

0.045 m3 Pasir Pasang 313,000.00 14,085.00

C PERALATAN

D Jumlah A + B + C 267,904.09

E Overhead & Profit (contoh 10%) 10% 26,790.41

F Harga Satuan Pekerjaan (D+E) 294,694.50


9 A.4.4.3.11 1 m2 Pemasangan 1m2 Lantai Ubin Granit Ukuran 60cm x 60cm 425,036.33

A Tenaga 34,220.00

L.01 0.250 OH Pekerja 82,000.00 20,500.00

L.02 0.125 OH Tukang Batu 90,000.00 11,250.00

L.03 0.013 OH Kepala Tukang 95,000.00 1,235.00

L.04 0.013 OH Mandor 95,000.00 1,235.00

B Bahan 352,176.67

2.92 Buah Ubin Granito 60x60 cm 0.4 103,666.67 302,395.67

9.8 Kg Portland Semen 0.16 1,520.00 14,896.00

1.300 Kg Semen warna 6.25 16,000.00 20,800.00

0.045 m3 Pasir Pasang 313,000.00 14,085.00

C PERALATAN

D Jumlah A + B + C 386,396.67

E Overhead & Profit (contoh 10%) 10% 38,639.67

F Harga Satuan Pekerjaan (D+E) 425,036.33

9 A.4.4.3.12 1 m' Pemasangan 1m' plint Ubin Ukuran 10cm x 40cm 71,724.73

A Tenaga 16,810.00

L.01 0.090 OH Pekerja 82,000.00 7,380.00

L.02 0.090 OH Tukang Batu 90,000.00 8,100.00

L.03 0.009 OH Kepala Tukang 95,000.00 855.00

L.04 0.005 OH Mandor 95,000.00 475.00

B Bahan 48,394.30

2.65 Buah Plint granit 10cmx40cm 0.4 16,650.00 44,122.50

1.1 Kg Portland Semen 0.16 1,520.00 1,732.80

0.100 Kg Semen warna 6.25 16,000.00 1,600.00

0.003 m3 Pasir Pasang 313,000.00 939.00

C PERALATAN

D Jumlah A + B + C 65,204.30

E Overhead & Profit (contoh 10%) 10% 6,520.43

F Harga Satuan Pekerjaan (D+E) 71,724.73

9 A.4.4.3.13 1 m; Pemasangan 1m' plint Ubin Ukuran 10cm x 30cm 87,841.93

A Tenaga 16,810.00

L.01 0.090 OH Pekerja 82,000.00 7,380.00

L.02 0.090 OH Tukang Batu 90,000.00 8,100.00

L.03 0.009 OH Kepala Tukang 95,000.00 855.00

L.04 0.005 OH Mandor 95,000.00 475.00

B Bahan 63,046.30

3.53 Buah Plint granit 10cmx30cm 0.4 16,650.00 58,774.50

1.1 Kg Portland Semen 0.16 1,520.00 1,732.80

0.100 Kg Semen warna 6.25 16,000.00 1,600.00

0.003 m3 Pasir Pasang 313,000.00 939.00

C PERALATAN

D Jumlah A + B + C 79,856.30

E Overhead & Profit (contoh 10%) 10% 7,985.63


F Harga Satuan Pekerjaan (D+E) 87,841.93
10 A.4.4.3.16 1 m' Pemasangan 1 m’ Plint Ubin PC Abu-abu Ukuran 20 s.d. <30 cm 31,372.00

A Tenaga 16,810.00

L.01 0.090 OH Pekerja 82,000.00 7,380.00

L.02 0.090 OH Tukang Batu 90,000.00 8,100.00

L.03 0.009 OH Kepala Tukang 95,000.00 855.00

L.04 0.005 OH Mandor 95,000.00 475.00

B Bahan 11,710.00

5.30 Buah Plint Ubin PC 1,500.00 7,950.00

1.7 Kg Portland Semen 1,520.00 2,508.00

0.004 m3 Pasir Pasang 313,000.00 1,252.00

C PERALATAN

D Jumlah A + B + C 28,520.00

E Overhead & Profit (contoh 10%) 10% 2,852.00

F Harga Satuan Pekerjaan (D+E) 31,372.00

11 A.4.4.3.19 1 m' Pemasangan 1 m’ Plint Ubin Warna Ukuran 20 s.d. <30cm 33,100.98

A Tenaga 16,810.00

L.01 0.090 OH Pekerja 82,000.00 7,380.00

L.02 0.090 OH Tukang Batu 90,000.00 8,100.00

L.03 0.009 OH Kepala Tukang 95,000.00 855.00

L.04 0.005 OH Mandor 95,000.00 475.00

B Bahan 13,281.80

5.30 Buah Plint Ubin warna 1,700.00 9,010.00

1.14 Kg Portland Semen 1,520.00 1,732.80

0.100 Kg Semen Warna 16,000.00 1,600.00

0.003 m3 Pasir Pasang 313,000.00 939.00

C PERALATAN

D Jumlah A + B + C 30,091.80

E Overhead & Profit (contoh 10%) 10% 3,009.18

F Harga Satuan Pekerjaan (D+E) 33,100.98

11 A.4.4.3.20 1 m2 Pemasangan 1 m2 lantai keramik 60x60 cm 237,894.43

A Tenaga 34,220.00

L.01 0.250 OH Pekerja 82,000.00 20,500.00

L.02 0.125 OH Tukang Batu 90,000.00 11,250.00

L.03 0.013 OH Kepala Tukang 95,000.00 1,235.00

L.04 0.013 OH Mandor 95,000.00 1,235.00

B Bahan 182,047.67

3.10 Buah Keramik 60x60 cm 42,666.67 132,266.67

9.80 Kg Portland Semen 1,520.00 14,896.00

1.300 Kg Semen Warna 16,000.00 20,800.00

0.045 m3 Pasir Pasang 313,000.00 14,085.00

C PERALATAN

D Jumlah A + B + C 216,267.67

E Overhead & Profit (contoh 10%) 10% 21,626.77

F Harga Satuan Pekerjaan (D+E) 237,894.43


11 A.4.4.3.21 1 m2 Pemasangan 1 m2 lantai keramik 40x40 cm 248,803.50

A Tenaga 95,550.00

L.01 0.700 OH Pekerja 82,000.00 57,400.00

L.02 0.350 OH Tukang Batu 90,000.00 31,500.00

L.03 0.035 OH Kepala Tukang 95,000.00 3,325.00

L.04 0.035 OH Mandor 95,000.00 3,325.00

B Bahan 130,635.00

6.63 Buah Keramik 40x40 cm 11,666.67 77,350.00

10.00 Kg Portland Semen 1,520.00 15,200.00

1.500 Kg Semen Warna 16,000.00 24,000.00

0.045 m3 Pasir Pasang 313,000.00 14,085.00

C PERALATAN

D Jumlah A + B + C 226,185.00

E Overhead & Profit (contoh 10%) 10% 22,618.50

F Harga Satuan Pekerjaan (D+E) 248,803.50

12 A.4.4.3.32 1 m2 Pemasangan Lantai Keramik 10x 20 cm 294,278.38

A Tenaga 95,550.00

L.01 0.70 OH Pekerja 82,000.00 57,400.00

L.02 0.350 OH Tukang Batu 90,000.00 31,500.00

L.03 0.035 OH Kepala Tukang 95,000.00 3,325.00

L.04 0.035 OH Mandor 95,000.00 3,325.00

B Bahan 171,975.80

53.00 Buah Keramik 10 x 20 cm 1,914.00 101,442.00

8.19 Kg Portland Semen 1,520.00 12,448.80

2.75 Kg Semen Warna 16,000.00 44,000.00

0.0450 m3 Pasir Pasang 313,000.00 14,085.00

C PERALATAN

D Jumlah A + B + C 267,525.80

E Overhead & Profit (contoh 10%) 10% 26,752.58

F Harga Satuan Pekerjaan (D+E) 294,278.38


13 A.4.4.3.33 1 m2 Pemasangan lantai Keramik Uk. 10 x 10 cm / 5 x 20 cm 302,198.38

A Tenaga 95,550.00

L.01 0.70 OH Pekerja 82,000.00 57,400.00

L.02 0.350 OH Tukang Batu 90,000.00 31,500.00

L.03 0.035 OH Kepala Tukang 95,000.00 3,325.00

L.04 0.035 OH Mandor 95,000.00 3,325.00

B Bahan 179,175.80

106.00 Buah Keramik 10 x 10 cm / 5 x 20 cm 957.00 101,442.00

8.19 Kg Portland Semen 1,520.00 12,448.80

3.20 Kg Semen Warna 16,000.00 51,200.00

0.0450 m3 Pasir Pasang 313,000.00 14,085.00

C PERALATAN

D Jumlah A + B + C 274,725.80

E Overhead & Profit (contoh 10%) 10% 27,472.58

F Harga Satuan Pekerjaan (D+E) 302,198.38

14 A.4.4.3.34 1 m2 Pemasangan Lantai Keramik 33 x 33 cm 249,581.96

A Tenaga 95,550.00

L.01 0.70 OH Pekerja 82,000.00 57,400.00

L.02 0.35 OH Tukang Batu 90,000.00 31,500.00

L.03 0.035 OH Kepala Tukang 95,000.00 3,325.00

L.04 0.035 OH Mandor 95,000.00 3,325.00

B Bahan 131,342.69

10 Buah Ubin Keramik 33 x 33 cm 7,888.89 78,888.89

8.19 Kg Portland Semen 1,520.00 12,448.80

0.045 m3 Pasir Pasang 313,000.00 14,085.00

1.62 Kg Semen Warna 16,000.00 25,920.00

C PERALATAN

D Jumlah A + B + C 226,892.69

E Overhead & Profit (contoh 10%) 10% 22,689.27

F Harga Satuan Pekerjaan (D+E) 249,581.96

15 A.4.4.3.35 1 m2 Pemasangan Lantai Keramik 30 x 30 cm 231,971.00

A Tenaga 95,550.00

L.01 0.70 OH Pekerja 82,000.00 57,400.00

L.02 0.35 OH Tukang Batu 90,000.00 31,500.00

L.03 0.035 OH Kepala Tukang 95,000.00 3,325.00

L.04 0.035 OH Mandor 95,000.00 3,325.00

B Bahan 115,332.73

11.87 Buah Ubin Keramik 30 x 30 cm 5,227.27 62,047.73

10.00 Kg Portland Semen 1,520.00 15,200.00

0.045 m3 Pasir Pasang 313,000.00 14,085.00

1.50 Kg Semen Warna 16,000.00 24,000.00

C PERALATAN

D Jumlah A + B + C 210,882.73

E Overhead & Profit (contoh 10%) 10% 21,088.27

F Harga Satuan Pekerjaan (D+E) 231,971.00


16 A.4.4.3.36 1 m2 Pemasangan Lantai Keramik 20 x 20 cm 241,706.30

A Tenaga 95,550.00

L.01 0.70 OH Pekerja 82,000.00 57,400.00

L.02 0.35 OH Tukang Batu 90,000.00 31,500.00

L.03 0.035 OH Kepala Tukang 95,000.00 3,325.00

L.04 0.035 OH Mandor 95,000.00 3,325.00

B Bahan 124,183.00

26.5 Buah Ubin Keramik 20 x 20 cm 2,580.00 68,370.00

10.40 Kg Portland Semen 1,520.00 15,808.00

1.62 Kg Semen Warna 16,000.00 25,920.00

0.045 m3 Pasir Pasang 313,000.00 14,085.00

C PERALATAN

D Jumlah A + B + C 219,733.00

E Overhead & Profit (contoh 10%) 10% 21,973.30

F Harga Satuan Pekerjaan (D+E) 241,706.30

Pemasangan Lantai Keramik uk.10 x 33 cm, untuk variasi


17 A.4.4.3.37 1 m2 373,572.10
/ border
A Tenaga 141,710.00

L.01 1.05 OH Pekerja 82,000.00 86,100.00

L.02 0.525 OH Tukang Batu 90,000.00 47,250.00

L.03 0.053 OH Kepala Tukang 95,000.00 5,035.00

L.04 0.035 OH Mandor 95,000.00 3,325.00

B Bahan 197,901.00

33.0 Buah Ubin Keramik 3,000.00 99,000.00

9.80 Kg Portland Semen 1,520.00 14,896.00

4.37 Kg Semen Warna 16,000.00 69,920.00

0.045 m3 Pasir Pasang 313,000.00 14,085.00

C PERALATAN

D Jumlah A + B + C 339,611.00

E Overhead & Profit (contoh 10%) 10% 33,961.10

F Harga Satuan Pekerjaan (D+E) 373,572.10

18 A.4.4.3.39 1 m' Pemasangan Plint Keramik Ukuran 10x20 cm 74,339.98

A Tenaga 16,810.00

L.01 0.09 OH Pekerja 82,000.00 7,380.00

L.02 0.09 OH Tukang Batu 90,000.00 8,100.00

L.03 0.009 OH Kepala Tukang 95,000.00 855.00

L.04 0.005 OH Mandor 95,000.00 475.00

B Bahan 50,771.80

5.3 Buah Ubin Keramik 9,000.00 47,700.00

1.14 Kg Portland Semen 1,520.00 1,732.80

0.003 m3 Pasir Pasang 313,000.00 939.00

0.025 Kg Semen Warna 16,000.00 400.00

C PERALATAN

D Jumlah A + B + C 67,581.80

E Overhead & Profit (contoh 10%) 10% 6,758.18

F Harga Satuan Pekerjaan (D+E) 74,339.98


19 A.4.4.3.40 1 m' Pemasangan Plint Keramik Ukuran 10x10 cm 80,609.98

A Tenaga 16,810.00

L.01 0.09 OH Pekerja 82,000.00 7,380.00

L.02 0.09 OH Tukang Batu 90,000.00 8,100.00

L.03 0.009 OH Kepala Tukang 95,000.00 855.00

L.04 0.005 OH Mandor 95,000.00 475.00

B Bahan 56,471.80

10.6 Buah Ubin Keramik 5,000.00 53,000.00

1.14 Kg Portland Semen 1,520.00 1,732.80

0.003 m3 Pasir Pasang 313,000.00 939.00

0.05 Kg Semen Warna 16,000.00 800.00

C PERALATAN

D Jumlah A + B + C 73,281.80

E Overhead & Profit (contoh 10%) 10% 7,328.18

F Harga Satuan Pekerjaan (D+E) 80,609.98

20 A.4.4.3.41 1 m' Pemasangan Plint Keramik Ukuran 5x20 cm 86,439.98

A Tenaga 16,810.00

L.01 0.09 OH Pekerja 82,000.00 7,380.00

L.02 0.09 OH Tukang Batu 90,000.00 8,100.00

L.03 0.009 OH Kepala Tukang 95,000.00 855.00

L.04 0.005 OH Mandor 95,000.00 475.00

B Bahan 61,771.80

10.6 Buah Ubin Keramik 5,500.00 58,300.00

1.14 Kg Portland Semen 1,520.00 1,732.80

0.003 m3 Pasir Pasang 313,000.00 939.00

0.05 Kg Semen Warna 16,000.00 800.00

C PERALATAN

D Jumlah A + B + C 78,581.80

E Overhead & Profit (contoh 10%) 10% 7,858.18

F Harga Satuan Pekerjaan (D+E) 86,439.98

21 A.4.4.3.43 1 m2 Pemasangan Lantai Marmer Ukuran 1.00x1.00 cm 1,204,110.38

A Tenaga 95,550.00

L.01 0.7 OH Pekerja 82,000.00 57,400.00

L.02 0.35 OH Tukang Batu 90,000.00 31,500.00

L.03 0.035 OH Kepala Tukang 95,000.00 3,325.00

L.04 0.035 OH Mandor 95,000.00 3,325.00

B Bahan 999,095.80

1.06 buah Marmer 907,700.00 962,162.00

8.19 kg Portland Semen 1,520.00 12,448.80

0.045 m3 Pasir Pasang 313,000.00 14,085.00

0.65 kg Semen Warna 16,000.00 10,400.00

C PERALATAN

D Jumlah A + B + C 1,094,645.80

E Overhead & Profit (contoh 10%) 10% 109,464.58

F Harga Satuan Pekerjaan (D+E) 1,204,110.38


22 A.4.4.3.44 1 m2 Pemasangan Lantai Karpet 120,543.50

A Tenaga 31,710.00

L.01 0.17 OH Pekerja 82,000.00 13,940.00

L.02 0.17 OH Tukang Batu 90,000.00 15,300.00

L.03 0.017 OH Kepala Tukang 95,000.00 1,615.00

L.04 0.009 OH Mandor 95,000.00 855.00

B Bahan 77,875.00

1.05 m2 Karpet 65,000.00 68,250.00

0.35 kg Lem 27,500.00 9,625.00

C PERALATAN

D Jumlah A + B + C 109,585.00

E Overhead & Profit (contoh 10%) 10% 10,958.50

F Harga Satuan Pekerjaan (D+E) 120,543.50

22 A.4.4.3.45 1 m2 Pemasangan 1 m2 underlayer (pelapis bawah karpet) 57,326.50

A Tenaga 22,540.00

L.01 0.12 OH Pekerja 82,000.00 9,840.00

L.02 0.12 OH Tukang Kayu 90,000.00 10,800.00

L.03 0.01 OH Kepala Tukang 95,000.00 950.00

L.04 0.01 OH Mandor 95,000.00 950.00

B Bahan 29,575.00

1.05 m2 Underlayer 19,000.00 19,950.00

0.35 kg Lem 27,500.00 9,625.00

C PERALATAN

D Jumlah A + B + C 52,115.00

E Overhead & Profit (contoh 10%) 10% 5,211.50

F Harga Satuan Pekerjaan (D+E) 57,326.50

23 A.4.4.3.46 1 m2 Pemasangan Lantai Parquet Jati 493,086.00

A Tenaga 95,550.00

L.01 0.70 OH Pekerja 82,000.00 57,400.00

L.02 0.35 OH Tukang Batu 90,000.00 31,500.00

L.03 0.035 OH Kepala Tukang 95,000.00 3,325.00

L.04 0.035 OH Mandor 95,000.00 3,325.00

B Bahan 352,710.00

1.05 m2 Parquet Jati 320,200.00 336,210.00

0.6 Kg Lem Vynil 27,500.00 16,500.00

C PERALATAN

D Jumlah A + B + C 448,260.00

E Overhead & Profit (contoh 10%) 10% 44,826.00

F Harga Satuan Pekerjaan (D+E) 493,086.00

24 A.4.4.3.48 1 m2 Pemasangan Dinding Porselen 11 x 11 cm 316,281.39

A Tenaga 136,500.00

L.01 1.00 OH Pekerja 82,000.00 82,000.00

L.02 0.50 OH Tukang Batu 90,000.00 45,000.00

L.03 0.050 OH Kepala Tukang 95,000.00 4,750.00

L.04 0.050 OH Mandor 95,000.00 4,750.00


B Bahan 151,028.54

86 bh Porselen 1,014.63 87,258.54

9.30 Kg Portland Semen 82.6446 1,520.00 14,136.00

2.750 Kg Semen Warna 0.0121 16,000.00 44,000.00

0.018 m3 Pasir Pasang 0.11 313,000.00 5,634.00

C PERALATAN

D Jumlah A + B + C 287,528.54

E Overhead & Profit (contoh 10%) 10% 28,752.85

F Harga Satuan Pekerjaan (D+E) 316,281.39


25 A.4.4.3.49 1 m2 Pemasangan Dinding Porselen 10x20 cm, 316,868.20

A Tenaga 122,850.00

L.01 0.9 OH Pekerja 82,000.00 73,800.00

L.02 0.45 OH Tukang Batu 90,000.00 40,500.00

L.03 0.045 OH Kepala Tukang 95,000.00 4,275.00

L.04 0.045 OH Mandor 95,000.00 4,275.00

B Bahan 165,212.00

53 Buah Keramik 1,914.00 101,442.00

9.3 Kg Portland Semen 1,520.00 14,136.00

0.018 m3 Pasir Pasang 313,000.00 5,634.00

2.75 Kg Semen Warna 16,000.00 44,000.00

C PERALATAN

D Jumlah A + B + C 288,062.00

E Overhead & Profit (contoh 10%) 10% 28,806.20

F Harga Satuan Pekerjaan (D+E) 316,868.20

26 A.4.4.3.50 1 m2 Pemasangan Dinding Porselen 20x20 cm, 312,290.00

A Tenaga 122,850.00

L.01 0.9 OH Pekerja 82,000.00 73,800.00

L.02 0.45 OH Tukang Batu 90,000.00 40,500.00

L.03 0.045 OH Kepala Tukang 95,000.00 4,275.00

L.04 0.045 OH Mandor 95,000.00 4,275.00

B Bahan 161,050.00

26.0 Buah Keramik 4,240.00 110,240.00

9.3 Kg Portland Semen 1,520.00 14,136.00

0.018 m3 Pasir Pasang 313,000.00 5,634.00

1.94 Kg Semen Warna 16,000.00 31,040.00

C PERALATAN

D Jumlah A + B + C 283,900.00

E Overhead & Profit (contoh 10%) 10% 28,390.00

F Harga Satuan Pekerjaan (D+E) 312,290.00

27 A.4.4.3.53 1 m2 Pemasangan Dinding Keramik 10x20 cm, 316,868.20

A Tenaga 122,850.00

L.01 0.9 OH Pekerja 82,000.00 73,800.00

L.02 0.45 OH Tukang Batu 90,000.00 40,500.00

L.03 0.045 OH Kepala Tukang 95,000.00 4,275.00

L.04 0.045 OH Mandor 95,000.00 4,275.00

B Bahan 165,212.00

53.0 Buah Keramik 1,914.00 101,442.00

9.3 Kg Portland Semen 1,520.00 14,136.00

0.018 m3 Pasir Pasang 313,000.00 5,634.00

2.75 Kg Semen Warna 16,000.00 44,000.00

C PERALATAN

D Jumlah A + B + C 288,062.00

E Overhead & Profit (contoh 10%) 10% 28,806.20

F Harga Satuan Pekerjaan (D+E) 316,868.20


28 A.4.4.3.54 1 m2 Pemasangan Dinding Keramik 20x20 cm, 314,622.00

A Tenaga 122,850.00

L.01 0.9 OH Pekerja 82,000.00 73,800.00

L.02 0.45 OH Tukang Batu 90,000.00 40,500.00

L.03 0.045 OH Kepala Tukang 95,000.00 4,275.00

L.04 0.045 OH Mandor 95,000.00 4,275.00

B Bahan 163,170.00

26.5 Buah Keramik 4,240.00 112,360.00

9.3 Kg Portland Semen 1,520.00 14,136.00

0.018 m3 Pasir Pasang 313,000.00 5,634.00

1.94 Kg Semen Warna 16,000.00 31,040.00

C PERALATAN

D Jumlah A + B + C 286,020.00

E Overhead & Profit (contoh 10%) 10% 28,602.00

F Harga Satuan Pekerjaan (D+E) 314,622.00

29 A.4.4.3.55 1 m2 Pemasangan Dinding Marmer Ukuran 1.00x1.00 cm 1,297,723.68

A Tenaga 177,450.00

L.01 1.3 OH Pekerja 82,000.00 106,600.00

L.02 0.65 OH Tukang Batu 90,000.00 58,500.00

L.03 0.065 OH Kepala Tukang 95,000.00 6,175.00

L.04 0.065 OH Mandor 95,000.00 6,175.00

B Bahan 1,002,298.80

1.06 buah Marmer 907,700.00 962,162.00

3.003 buah Paku 12 cm 1,000.00 3,003.00

12.44 kg Portlan Semen 1,520.00 18,908.80

0.025 m3 Pasir Pasang 313,000.00 7,825.00

0.65 kg Semen Warna 16,000.00 10,400.00

C PERALATAN

D Jumlah A + B + C 1,179,748.80

E Overhead & Profit (contoh 10%) 10% 117,974.88

F Harga Satuan Pekerjaan (D+E) 1,297,723.68

29 A.4.4.3.56 1 m2 Pemasangan Dinding Keramik uk 20 x 25 cm 316,954.00

A Tenaga 122,850.00

L.01 0.9 OH Pekerja 82,000.00 73,800.00

L.02 0.45 OH Tukang Batu 90,000.00 40,500.00

L.03 0.045 OH Kepala Tukang 95,000.00 4,275.00

L.04 0.045 OH Mandor 95,000.00 4,275.00

B Bahan 165,290.00

21.2 buah Keramik 20 x 25 cm 5,400.00 114,480.00

9.3 kg Portlan Semen 1,520.00 14,136.00

0.018 m3 Pasir Pasang 313,000.00 5,634.00

1.94 kg Semen Warna 16,000.00 31,040.00

C PERALATAN

D Jumlah A + B + C 288,140.00

E Overhead & Profit (contoh 10%) 10% 28,814.00


F Harga Satuan Pekerjaan (D+E) 316,954.00

29 A.4.4.3.57 1 m2 Pemasangan Dinding Keramik uk 30 x 60 cm 385,363.00

A Tenaga 122,850.00

L.01 0.9 OH Tenaga 82,000.00 73,800.00

L.02 0.45 OH Pekerja 90,000.00 40,500.00

L.03 0.045 OH Tukang Batu 95,000.00 4,275.00

L.04 0.045 OH Kepala Tukang 95,000.00 4,275.00

B Bahan 227,480.00

5.889 buah Keramik 30 x 60 cm 30,000.00 176,670.00

9.3 kg Portlan Semen 1,520.00 14,136.00

0.018 m3 Pasir Pasang 313,000.00 5,634.00

1.94 kg Semen Warna 16,000.00 31,040.00

C PERALATAN

D Jumlah A + B + C 350,330.00

E Overhead & Profit (contoh 10%) 10% 35,033.00

F Harga Satuan Pekerjaan (D+E) 385,363.00

30 A.4.4.3.58 1 m2 Pemasangan Dinding Batu Paros / Batu Tempel Hitam 299,183.50

A Tenaga 95,550.00

L.01 0.70 OH Pekerja 82,000.00 57,400.00

L.02 0.35 OH Tukang Batu 90,000.00 31,500.00

L.03 0.035 OH Kepala Tukang 95,000.00 3,325.00

L.04 0.035 OH Mandor 95,000.00 3,325.00

B Bahan 176,435.00

1.10 m2 Batu Paros 134,200.00 147,620.00

11.75 Kg Portland Semen 1,520.00 17,860.00

0.035 m3 Pasir Pasang 313,000.00 10,955.00

C PERALATAN

D Jumlah A + B + C 271,985.00

E Overhead & Profit (contoh 10%) 10% 27,198.50

F Harga Satuan Pekerjaan (D+E) 299,183.50


31 A.4.4.3.59 1 m2 Pemasangan Lantai Vynil uk.30 x 30 cm 189,013.00

A Tenaga 46,255.00

L.01 0.35 OH Pekerja 82,000.00 28,700.00

L.02 0.175 OH Tukang Batu 90,000.00 15,750.00

L.03 0.017 OH Kepala Tukang 95,000.00 1,615.00

L.04 0.002 OH Mandor 95,000.00 190.00

B Bahan 125,575.00

11.87 bh Vynil 30x30cm 10,000.00 118,700.00

0.25 kg Lem 27,500.00 6,875.00

C PERALATAN

D Jumlah A + B + C 171,830.00

E Overhead & Profit (contoh 10%) 10% 17,183.00

F Harga Satuan Pekerjaan (D+E) 189,013.00

32 A.4.4.3.60 1 m2 Pemasangan Wallpaper Lebar 50 Cm 156,920.50

A Tenaga 46,255.00

L.01 0.35 OH Pekerja 82,000.00 28,700.00

L.02 0.175 OH Tukang Batu 90,000.00 15,750.00

L.03 0.017 OH Kepala Tukang 95,000.00 1,615.00

L.04 0.002 OH Mandor 95,000.00 190.00

B Bahan 96,400.00

2.2 m' Wallpaper 42,000.00 92,400.00

0.25 kg Lem 16,000.00 4,000.00

C PERALATAN

D Jumlah A + B + C 142,655.00

E Overhead & Profit (contoh 10%) 10% 14,265.50

F Harga Satuan Pekerjaan (D+E) 156,920.50

32 A.4.4.3.62 1 m' Pemasangan 1 m' plint vynil 15cm x 30cm 31,394.00

A Tenaga 14,900.00

L.01 0.08 OH Pekerja 82,000.00 6,560.00

L.02 0.08 OH Tukang Batu 90,000.00 7,200.00

L.03 0.008 OH Kepala Tukang 95,000.00 760.00

L.04 0.004 OH Mandor 95,000.00 380.00

B Bahan 13,640.00

1.76 buah Vynil 6,500.00 11,440.00

0.08 kg Lem 27,500.00 2,200.00

C PERALATAN

D Jumlah A + B + C 28,540.00

E Overhead & Profit (contoh 10%) 10% 2,854.00

F Harga Satuan Pekerjaan (D+E) 31,394.00

33 A.4.4.3.63 1 m' Pemasangan Plint Kayu Klas II Ukuran 2x10 cm 67,648.46

Tenaga 22,350.00

L.01 0.12 OH Pekerja 82,000.00 9,840.00

L.02 0.12 OH Tukang Batu 90,000.00 10,800.00


L.03 0.012 OH Kepala Tukang 95,000.00 1,140.00

L.04 0.006 OH Mandor 95,000.00 570.00

Bahan 39,148.60

0.003 m3 Papan Kayu Klas II 12,196,200.00 36,588.60

0.05 kg Paku Sekrup 5 cm 51,200.00 2,560.00

C PERALATAN

D Jumlah A + B + C 61,498.60

E Overhead & Profit (contoh 10%) 10% 6,149.86

F Harga Satuan Pekerjaan (D+E) 67,648.46


34 A.4.4.3.64 1 m2 Pemasangan Paving Block Natural Tebal 6 Cm 193,282.87

Tenaga 70,373.50

L.01 0.25 OH Pekerja 82,000.00 20,500.00

L.02 0.5 OH Tukang Batu 90,000.00 45,000.00

L.03 0.05 OH Kepala Tukang 95,000.00 4,750.00

L.04 0.0013 OH Mandor 95,000.00 123.50

Bahan 95,762.00

1.01 m2 Paving Block Tebal 6 Cm 76,200.00 76,962.00

0.05 m3 Pasir Beton 376,000.00 18,800.00

C PERALATAN 9,576.20

10 % Peralatan 95,762.00 9,576.20

D Jumlah A + B + C 175,711.70

E Overhead & Profit (contoh 10%) 10% 17,571.17

F Harga Satuan Pekerjaan (D+E) 193,282.87

35 A.4.4.3.65 1 m2 Pemasangan Paving Block Natural Tebal 8 Cm 238,375.17

Tenaga 90,873.50

L.01 0.5 OH Pekerja 82,000.00 41,000.00

L.02 0.5 OH Tukang Batu 90,000.00 45,000.00

L.03 0.05 OH Kepala Tukang 95,000.00 4,750.00

L.04 0.0013 OH Mandor 95,000.00 123.50

Bahan 114,392.00

1.01 m2 Paving Block Tebal 8 Cm 87,200.00 88,072.00

0.07 m3 Pasir Beton 376,000.00 26,320.00


C PERALATAN 11,439.20
10 % Peralatan 114,392.00 11,439.20
D Jumlah A + B + C 216,704.70
E Overhead & Profit (contoh 10%) 10% 21,670.47
F Harga Satuan Pekerjaan (D+E) 238,375.17

36 A.4.4.3.66 1 m2 Pemasangan Paving Block Berwarna Tebal 6 Cm 206,725.97


Tenaga 70,373.50
L.01 0.25 OH Pekerja 82,000.00 20,500.00
L.02 0.5 OH Tukang Batu 90,000.00 45,000.00
L.03 0.05 OH Kepala Tukang 95,000.00 4,750.00
L.04 0.0013 OH Mandor 95,000.00 123.50
Bahan 106,872.00
1.01 m2 Paving Block Berwarna Tebal 6 Cm 87,200.00 88,072.00
0.05 m3 Pasir Beton 376,000.00 18,800.00
C PERALATAN 10,687.20
10 % Peralatan 106,872.00 10,687.20
D Jumlah A + B + C 187,932.70
E Overhead & Profit (contoh 10%) 10% 18,793.27
F Harga Satuan Pekerjaan (D+E) 206,725.97
37 A.4.4.3.67 1 m2 Pemasangan Paving Block Berwarna Tebal 8 Cm 242,041.47
Tenaga 90,873.50
L.01 0.5 OH Pekerja 82,000.00 41,000.00
L.02 0.5 OH Tukang Batu 90,000.00 45,000.00
L.03 0.05 OH Kepala Tukang 95,000.00 4,750.00
L.04 0.0013 OH Mandor 95,000.00 123.50
Bahan 117,422.00
1.01 m2 Paving Block Tebal Berwarna 8 Cm 90,200.00 91,102.00
0.07 m3 Pasir Beton 376,000.00 26,320.00
C PERALATAN 11,742.20
10 % Peralatan 117,422.00 11,742.20
D Jumlah A + B + C 220,037.70
E Overhead & Profit (contoh 10%) 10% 22,003.77
F Harga Satuan Pekerjaan (D+E) 242,041.47
HARGA
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN BAHAN/UPAH
Rp

DIVISI IV A.4.5.1 HARGA SATUAN PEKERJAAN LANGIT-LANGIT (PLAFON)

Pemasangan Langit-langit Asbes (1,00x1,00) m, tebal 4


1 A.4.5.1.1 1 m2
mm, 5 mm & 6 mm

A Tenaga

L.01 0.03 OH Pekerja 82,000.00

L.02 0.07 OH Tukang Kayu 90,000.00

L.03 0.007 OH Kepala Tukang 95,000.00

L.04 0.004 OH Mandor 95,000.00

B Bahan

1.1 Lbr Plat Asbes 19,500.00

0.01 Kg Paku 20,000.00

C PERALATAN

D Jumlah A + B + C

E Overhead & Profit (contoh 10%) 10%

F Harga Satuan Pekerjaan (D+E)


Overhead & Profit (contoh 10%)
2 A.4.5.1.2 1 m2 Pemasangan 1 m2 Langit-langit Akustik Ukuran 30 x 30 cm

A Tenaga

L.01 0.12 OH Pekerja 82,000.00

L.02 0.12 OH Tukang Kayu 90,000.00

L.03 0.012 OH Kepala Tukang 95,000.00

L.04 0.006 OH Mandor 95,000.00

B Bahan

12.0 Lbr Akustik Uk.30 x 30 cm 7,000.00

0.05 Kg Paku 20,000.00

C PERALATAN

D Jumlah A + B + C

E Overhead & Profit (contoh 10%) 10%

F Harga Satuan Pekerjaan (D+E)

3 A.4.5.1.3 1 m2 Pemasangan 1 m2 Langit-langit Akustik Ukuran 30 x 60 cm

A Tenaga

L.01 0.10 OH Pekerja 82,000.00

L.02 0.10 OH Tukang Kayu 90,000.00

L.03 0.01 OH Kepala Tukang 95,000.00

L.04 0.005 OH Mandor 95,000.00

B Bahan

5.80 Lbr Akustik 19,000.00

0.05 Kg Paku 20,000.00

C PERALATAN

D Jumlah A + B + C

E Overhead & Profit (contoh 10%) 10%

F Harga Satuan Pekerjaan (D+E)


4 A.4.5.1.4 1 m2 Pemasangan 1 m2 Langit-langit Akustik Ukuran 60 x 120 cm

A Tenaga

L.01 0.10 OH Pekerja 82,000.00

L.02 0.10 OH Tukang Kayu 90,000.00

L.03 0.01 OH Kepala Tukang 95,000.00

L.04 0.005 OH Mandor 95,000.00

B Bahan

1.50 Lbr Akustik 57,000.00

0.05 Kg Paku 20,000.00

C PERALATAN

D Jumlah A + B + C

E Overhead & Profit (contoh 10%) 10%

F Harga Satuan Pekerjaan (D+E)

Pemasangan 1 m2 Langit-langit Kayu Lapis. Tebal 3 mm. 4


5 A.4.5.1.5 1 m2
mm dan 6

A Tenaga

L.01 0.10 OH Pekerja 82,000.00

L.02 0.10 OH Tukang Kayu 90,000.00

L.03 0.01 OH Kepala Tukang 95,000.00

L.04 0.005 OH Mandor 95,000.00

B Bahan

0.375 Lbr Tripleks (4 mm) 76,000.00

0.03 Kg Paku Tripleks 20,000.00

C PERALATAN

D Jumlah A + B + C

E Overhead & Profit (contoh 10%) 10%

F Harga Satuan Pekerjaan (D+E)

6 A.4.5.1.6 1 m2 Memasang Langit-langit Lambriziring Kayu Jati, tebal 6 mm

A Tenaga

L.01 0.8 OH Pekerja 82,000.00

L.02 0.8 OH Tukang Kayu 90,000.00

L.03 0.08 OH Kepala Tukang 95,000.00

L.04 0.04 OH Mandor 95,000.00

B Bahan

0.015 m3 Kayu Jati,Papan 20,183,200.00

0.01 Kg Paku 20,000.00

C PERALATAN

D Jumlah A + B + C

E Overhead & Profit (contoh 10%) 10%

F Harga Satuan Pekerjaan (D+E)


Memasang Langit-langit Gypsu Board, Ukuran (120x240)
7 A.4.5.1.7 1 m2
tebal 9 mm

A Tenaga

L.01 0.1 OH Pekerja 82,000.00

L.02 0.05 OH Tukang Kayu 90,000.00

L.03 0.005 OH Kepala Tukang 95,000.00

L.04 0.005 OH Mandor 95,000.00

B Bahan

0.364 Lbr Gypsum Board 69,000.00

0.11 Kg Paku Sekrup 51,200.00

C PERALATAN

D Jumlah A + B + C

E Overhead & Profit (contoh 10%) 10%

F Harga Satuan Pekerjaan (D+E)

Memasang Langit-langit Kalsiboard, Ukuran (120x240)


8 A.4.5.1.8 1 m2
tebal 3.5 mm

A Tenaga

L.01 0.1 OH Pekerja 82,000.00

L.02 0.05 OH Tukang Kayu 90,000.00

L.03 0.005 OH Kepala Tukang 95,000.00

L.04 0.005 OH Mandor 95,000.00

B Bahan

0.364 Lbr Kalsiboard 62,160.00

0.11 Kg Paku Sekrup 51,200.00

C PERALATAN

D Jumlah A + B + C

E Overhead & Profit (contoh 10%) 10%

F Harga Satuan Pekerjaan (D+E)

Memasang Langit-langit Akustik Uk (60x120) cm & Berikut


9 A.4.5.1.9 1 m2
Rangka Allumunium

A Tenaga

L.01 0.5 OH Pekerja 82,000.00

L.02 0.5 OH Tukang Kayu 90,000.00

L.03 0.05 OH Kepala Tukang 95,000.00

L.04 0.025 OH Mandor 95,000.00

B Bahan

3.6 m' Profil Allumunium "T" 13,000.00


0.15 kg Kawat Ø 4 mm 28,000.00
1.05 bh Ramset 13,000.00
1.5 lmb Akustik 60 x 120 cm 57,000.00
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit (contoh 10%) 10%
F Harga Satuan Pekerjaan (D+E)

10 A.4.5.1.10 1 m1 List Langit-langit Kayu Profil


A Tenaga
L.01 0.05 OH Pekerja 82,000.00
L.02 0.05 OH Tukang Kayu 90,000.00
L.03 0.005 OH Kepala Tukang 95,000.00
L.04 0.003 OH Mandor 95,000.00
B Bahan
1.05 m1 List Kayu Profil 18,500.00
0.01 Kg Paku 20,000.00
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit (contoh 10%) 10%
F Harga Satuan Pekerjaan (D+E)

11 A.4.5.1.11 1 m1 List Langit-langit Gypsum Profil


A Tenaga
L.01 0.05 OH Pekerja 82,000.00
L.02 0.05 OH Tukang Kayu 90,000.00
L.03 0.005 OH Kepala Tukang 95,000.00
L.04 0.003 OH Mandor 95,000.00
B Bahan
1.10 m1 List Gypsum Profil 16,000.00
0.11 Kg Paku 20,000.00
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit (contoh 10%) 10%
F Harga Satuan Pekerjaan (D+E)

12 A.4.5.1.12 1 m2 Pembongkaran 1 m2 langit - langit (plafon)


A Tenaga
L.01 0.25 OH Pekerja 82,000.00
L.04 0.025 OH Mandor 95,000.00
B Bahan
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit (contoh 10%) 10%
F Harga Satuan Pekerjaan (D+E)

Memasang Langit-langit Tripleks, Ukuran (120x240) tebal


13 A.4.5.1.13 1 m2
4 mm

A Tenaga
L.01 0.1 OH Pekerja 82,000.00
L.02 0.10 OH Tukang Kayu 90,000.00
L.03 0.010 OH Kepala Tukang 95,000.00
L.04 0.005 OH Mandor 95,000.00
B Bahan
0.375 Lbr Tripleks t=4mm, 120x240 cm 76,000.00
0.03 Kg Paku 20,000.00
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit (contoh 10%) 10%
F Harga Satuan Pekerjaan (D+E)
JUMLAH

Rp

34,600.50

9,805.00

2,460.00

6,300.00

665.00

380.00

21,650.00

21,450.00

200.00

31,455.00

3,145.50

34,600.50

118,085.00

22,350.00

9,840.00

10,800.00

1,140.00

570.00

85,000.00

84,000.00

1,000.00

107,350.00

10,735.00

118,085.00

142,807.50

18,625.00

8,200.00

9,000.00

950.00

475.00

111,200.00

110,200.00

1,000.00

129,825.00

12,982.50

142,807.50
115,637.50

18,625.00

8,200.00

9,000.00

950.00

475.00

86,500.00

85,500.00

1,000.00

105,125.00

10,512.50

115,637.50

52,497.50

18,625.00

8,200.00

9,000.00

950.00

475.00

29,100.00

28,500.00

600.00

47,725.00

4,772.50

52,497.50

497,142.80

149,000.00

65,600.00

72,000.00

7,600.00

3,800.00

302,948.00

302,748.00

200.00

451,948.00

45,194.80

497,142.80
48,837.80

13,650.00

8,200.00

4,500.00

475.00

475.00

30,748.00

25,116.00

5,632.00

44,398.00

4,439.80

48,837.80

46,099.06

13,650.00

8,200.00

4,500.00

475.00

475.00

28,258.24

22,626.24

5,632.00

41,908.24

4,190.82

46,099.06

267,602.50

93,125.00

41,000.00

45,000.00

4,750.00

2,375.00

150,150.00

46,800.00
4,200.00
13,650.00
85,500.00

243,275.00
24,327.50
267,602.50

31,883.50
9,360.00
4,100.00
4,500.00
475.00
285.00
19,625.00
19,425.00
200.00

28,985.00
2,898.50
31,883.50

32,076.00
9,360.00
4,100.00
4,500.00
475.00
285.00
19,800.00
17,600.00
2,200.00

29,160.00
2,916.00
32,076.00

25,162.50
22,875.00
20,500.00
2,375.00
-

22,875.00
2,287.50
25,162.50

52,497.50

18,625.00
8,200.00
9,000.00
950.00
475.00
29,100.00
28,500.00
600.00

47,725.00
4,772.50
52,497.50
HARGA
JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN BAHAN/UPAH
Rp Rp

DIVISI IV A.4.5.2 HARGA SATUAN PEKERJAAN PENUTUP ATAP

1 A.4.5.2.1 1 m2 Pemasangan Atap Genteng Plentong Kecil 83,762.25

A Tenaga 20,522.50

L.01 0.15 OH Pekerja 82,000.00 12,300.00

L.02 0.075 OH Tukang Kayu 90,000.00 6,750.00

L.03 0.0075 OH Kepala Tukang 95,000.00 712.50

L.04 0.008 OH Mandor 95,000.00 760.00

B Bahan 55,625.00

25 Buah Genteng Plentong 2,225.00 55,625.00

C PERALATAN

D Jumlah A + B + C 76,147.50

E Overhead & Profit (contoh 10%) 10% 7,614.75

F Harga Satuan Pekerjaan (D+E) 83,762.25

#REF!
2 A.4.5.2.2 1 m2 Pemasangan Atap Genteng Kodok / Glazuur 179,377.00

A Tenaga 20,570.00

L.01 0.15 OH Pekerja 82,000.00 12,300.00

L.02 0.075 OH Tukang Kayu 90,000.00 6,750.00

L.03 0.008 OH Kepala Tukang 95,000.00 760.00

L.04 0.008 OH Mandor 95,000.00 760.00

B Bahan 142,500.00

25 Buah Genteng Kodok / Glasur 5,700.00 142,500.00

C PERALATAN

D Jumlah A + B + C 163,070.00

E Overhead & Profit (contoh 10%) 10% 16,307.00

F Harga Satuan Pekerjaan (D+E) 179,377.00

3 A.4.5.2.3 1 m2 Pemasangan1 m2 Atap Genteng Palentong Besar/Morando 72,787.00

A Tenaga 20,570.00

L.01 0.15 OH Pekerja 82,000.00 12,300.00

L.02 0.075 OH Tukang Kayu 90,000.00 6,750.00

L.03 0.008 OH Kepala Tukang 95,000.00 760.00

L.04 0.008 OH Mandor 95,000.00 760.00

B Bahan 45,600.00

12 Buah Genteng Plentong Besar (morando) 3,800.00 45,600.00

C PERALATAN

D Jumlah A + B + C 66,170.00

E Overhead & Profit (contoh 10%) 10% 6,617.00

F Harga Satuan Pekerjaan (D+E) 72,787.00


4 A.4.5.2.4 1 m' Pemasangan 1 m’ Bubung Genteng Palentong Kecil 107,322.60

A Tenaga 52,890.00

L.01 0.4 OH Pekerja 82,000.00 32,800.00

L.02 0.2 OH Tukang Kayu 90,000.00 18,000.00

L.03 0.02 OH Kepala Tukang 95,000.00 1,900.00

L.04 0.002 OH Mandor 95,000.00 190.00

B Bahan 44,676.00

5 Buah Genteng Bubung Plentong 4,500.00 22,500.00

8 Kg Portland Semen 1,520.00 12,160.00

0.032 m3 Pasir Pasang 313,000.00 10,016.00

C PERALATAN

D Jumlah A + B + C 97,566.00

E Overhead & Profit (contoh 10%) 10% 9,756.60

F Harga Satuan Pekerjaan (D+E) 107,322.60

5 A.4.5.2.5 1 m' Pemasangan 1 m’ Bubung Genteng Kodok Glazuur 109,522.60

A Tenaga 52,890.00

L.01 0.4 OH Pekerja 82,000.00 32,800.00

L.02 0.2 OH Tukang Kayu 90,000.00 18,000.00

L.03 0.02 OH Kepala Tukang 95,000.00 1,900.00

L.04 0.002 OH Mandor 95,000.00 190.00

B Bahan 46,676.00

5 Buah Genteng Bubung Kodok / Glasur 4,900.00 24,500.00

8 Kg Portland Semen 1,520.00 12,160.00

0.032 m3 Pasir Pasang 313,000.00 10,016.00

C PERALATAN

D Jumlah A + B + C 99,566.00

E Overhead & Profit (contoh 10%) 10% 9,956.60

F Harga Satuan Pekerjaan (D+E) 109,522.60

6 A.4.5.2.6 1 m' Pemasangan 1 m’ Bubung Genteng Palentong Besar 102,372.60

A Tenaga 52,890.00

L.01 0.4 OH Pekerja 82,000.00 32,800.00

L.02 0.2 OH Tukang Kayu 90,000.00 18,000.00

L.03 0.02 OH Kepala Tukang 95,000.00 1,900.00

L.04 0.002 OH Mandor 95,000.00 190.00

B Bahan 40,176.00

4 Buah Genteng Bubung Plentong Besar 4,500.00 18,000.00

8 Kg Portland Semen 1,520.00 12,160.00

0.032 m3 Pasir Pasang 313,000.00 10,016.00

C PERALATAN

D Jumlah A + B + C 93,066.00

E Overhead & Profit (contoh 10%) 10% 9,306.60

F Harga Satuan Pekerjaan (D+E) 102,372.60


7 A.4.5.2.7 1 m2 Pemasangan 1 m2 Roof Light Fibreglass 90cm x180cm 137,324.00

A Tenaga 18,840.00

L.01 0.14 OH Pekerja 82,000.00 11,480.00

L.02 0.067 OH Tukang Kayu 90,000.00 6,030.00

L.03 0.007 OH Kepala Tukang 95,000.00 665.00

L.04 0.007 OH Mandor 95,000.00 665.00

B Bahan 106,000.00

0.6 Lbr Rooflight 90 x 180 175,000.00 105,000.00

0.05 Kg Paku Biasa 20,000.00 1,000.00

C PERALATAN

D Jumlah A + B + C 124,840.00

E Overhead & Profit (contoh 10%) 10% 12,484.00

F Harga Satuan Pekerjaan (D+E) 137,324.00

Pemasangan 1 m2 Atap Serat Semen Gelombang


8 A.4.5.2.8 1 m2 84,836.40
92cm x 250cm x 5mm

A Tenaga 19,750.00

L.01 0.14 OH Pekerja 82,000.00 11,480.00

L.02 0.075 OH Tukang Kayu 90,000.00 6,750.00

L.03 0.008 OH Kepala Tukang 95,000.00 760.00

L.04 0.008 OH Mandor 95,000.00 760.00

B Bahan 57,374.00

0.5 Lbr Asbes Gelombang 104,500.00 52,250.00

0.12 Kg Paku Pancing 60 x 230 42,700.00 5,124.00

C PERALATAN

D Jumlah A + B + C 77,124.00

E Overhead & Profit (contoh 10%) 10% 7,712.40

F Harga Satuan Pekerjaan (D+E) 84,836.40

Pemasangan 1 m2 Atap Serat Semen Gelombang


9 A.4.5.2.9 1 m2 86,387.40
92cm x 225cm x 5mm

A Tenaga 19,110.00

L.01 0.14 OH Pekerja 82,000.00 11,480.00

L.02 0.07 OH Tukang Kayu 90,000.00 6,300.00

L.03 0.007 OH Kepala Tukang 95,000.00 665.00

L.04 0.007 OH Mandor 95,000.00 665.00

B Bahan 59,424.00

0.6 Lbr Asbes Gelombang 90,500.00 54,300.00

0.12 Kg Paku Pancing 60 x 230 42,700.00 5,124.00

C PERALATAN

D Jumlah A + B + C 78,534.00

E Overhead & Profit (contoh 10%) 10% 7,853.40

F Harga Satuan Pekerjaan (D+E) 86,387.40


Pemasangan1 m2 Atap Serat Semen Gelombang
10 A.4.5.2.10 1 m2 86,057.40
92cm x 200cm x 5mm

A Tenaga 19,110.00

L.01 0.14 OH Pekerja 82,000.00 11,480.00

L.02 0.07 OH Tukang Kayu 90,000.00 6,300.00

L.03 0.007 OH Kepala Tukang 95,000.00 665.00

L.04 0.007 OH Mandor 95,000.00 665.00

B Bahan 59,124.00

0.6 Lbr Asbes Gelombang 90,000.00 54,000.00

0.12 Kg Paku Pancing 60 x 230 42,700.00 5,124.00

C PERALATAN

D Jumlah A + B + C 78,234.00

E Overhead & Profit (contoh 10%) 10% 7,823.40

F Harga Satuan Pekerjaan (D+E) 86,057.40

Pemasangan1 m2 Atap Serat Semen Gelombang


11 A.4.5.2.11 1 m2 91,832.40
92cm x 180cm x 5mm

A Tenaga 19,110.00

L.01 0.14 OH Pekerja 82,000.00 11,480.00

L.02 0.07 OH Tukang Kayu 90,000.00 6,300.00

L.03 0.007 OH Kepala Tukang 95,000.00 665.00

L.04 0.007 OH Mandor 95,000.00 665.00

B Bahan 64,374.00

0.75 Lbr Asbes Gelombang 79,000.00 59,250.00

0.12 Kg Paku Pancing 60 x 230 42,700.00 5,124.00

C PERALATAN

D Jumlah A + B + C 83,484.00

E Overhead & Profit (contoh 10%) 10% 8,348.40

F Harga Satuan Pekerjaan (D+E) 91,832.40

Pemasangan1 m2 Atap Serat Semen Gelombang


12 A.4.5.2.12 1 m2 61,499.90
105cm x 300cm x 5 mm

A Tenaga 19,110.00
L.01 0.14 OH Pekerja 82,000.00 11,480.00
L.02 0.07 OH Tukang Kayu 90,000.00 6,300.00
L.03 0.007 OH Kepala Tukang 95,000.00 665.00
L.04 0.007 OH Mandor 95,000.00 665.00
B Bahan 36,799.00
0.35 Lbr Asbes Gelombang 90,500.00 31,675.00
0.12 Kg Paku Pancing 60 x 230 42,700.00 5,124.00
C PERALATAN
D Jumlah A + B + C 55,909.00
E Overhead & Profit (contoh 10%) 10% 5,590.90
F Harga Satuan Pekerjaan (D+E) 61,499.90
Pemasangan1 m2 Atap Serat Semen Gelombang
13 A.4.5.2.13 1 m2 65,465.40
105cm x 270cm x 4 mm

A Tenaga 19,110.00
L.01 0.14 OH Pekerja 82,000.00 11,480.00
L.02 0.07 OH Tukang Kayu 90,000.00 6,300.00
L.03 0.007 OH Kepala Tukang 95,000.00 665.00
L.04 0.007 OH Mandor 95,000.00 665.00
B Bahan 40,404.00
0.42 Lbr Asbes Gelombang 84,000.00 35,280.00
0.12 Kg Paku Pancing 60 x 230 42,700.00 5,124.00
C PERALATAN
D Jumlah A + B + C 59,514.00
E Overhead & Profit (contoh 10%) 10% 5,951.40
F Harga Satuan Pekerjaan (D+E) 65,465.40

Pemasangan1 m2 Atap Serat Semen Gelombang


14 A.4.5.2.14 1 m2 55,213.40
105cm x 240cm x 4 mm

A Tenaga 19,110.00
L.01 0.14 OH Pekerja 82,000.00 11,480.00
L.02 0.070 OH Tukang Kayu 90,000.00 6,300.00
L.03 0.007 OH Kepala Tukang 95,000.00 665.00
L.04 0.007 OH Mandor 95,000.00 665.00
B Bahan 31,084.00
0.44 Lbr Asbes Gelombang 59,000.00 25,960.00
0.12 Kg Paku Pancing 60 x 230 42,700.00 5,124.00
C PERALATAN
D Jumlah A + B + C 50,194.00
E Overhead & Profit (contoh 10%) 10% 5,019.40
F Harga Satuan Pekerjaan (D+E) 55,213.40

Pemasangan 1 m2 Atap Serat Semen Gelombang


15 A.4.5.2.15 1 m2 56,166.00
105cm x 240cm x 5mm

A Tenaga 19,110.00
L.01 0.14 OH Pekerja 82,000.00 11,480.00
L.02 0.070 OH Tukang Kayu 90,000.00 6,300.00
L.03 0.007 OH Kepala Tukang 95,000.00 665.00
L.04 0.007 OH Mandor 95,000.00 665.00
B Bahan 31,950.00
0.51 Lbr Asbes Gelombang 52,600.00 26,826.00
0.12 Kg Paku Pancing 60 x 230 42,700.00 5,124.00
C PERALATAN
D Jumlah A + B + C 51,060.00
E Overhead & Profit (contoh 10%) 10% 5,106.00
F Harga Satuan Pekerjaan (D+E) 56,166.00
Pemasangan 1 m2 Atap Serat Semen Gelombang
16 A.4.5.2.16 1 m2 65,993.40
105cm x 105cm x 4mm

A Tenaga 19,110.00
L.01 0.14 OH Pekerja 82,000.00 11,480.00
L.02 0.070 OH Tukang Kayu 90,000.00 6,300.00
L.03 0.007 OH Kepala Tukang 95,000.00 665.00
L.04 0.007 OH Mandor 95,000.00 665.00
B Bahan 40,884.00
0.80 Lbr Asbes Gelombang 44,700.00 35,760.00
0.12 Kg Paku Pancing 60 x 230 42,700.00 5,124.00
C PERALATAN
D Jumlah A + B + C 59,994.00
E Overhead & Profit (contoh 10%) 10% 5,999.40
F Harga Satuan Pekerjaan (D+E) 65,993.40

Pemasangan 1 m2 Atap Serat Semen Gelombang


17 A.4.5.2.17 1 m2 56,166.00
105cm x 210cm x 5mm

A Tenaga 19,110.00
L.01 0.14 OH Pekerja 82,000.00 11,480.00
L.02 0.07 OH Tukang Kayu 90,000.00 6,300.00
L.03 0.007 OH Kepala Tukang 95,000.00 665.00
L.04 0.007 OH Mandor 95,000.00 665.00
B Bahan 31,950.00
0.51 Lbr Serat Semen Gel 105x210 52,600.00 26,826.00
0.12 Kg Paku Pancing 60 x 230 42,700.00 5,124.00
C PERALATAN
D Jumlah A + B + C 51,060.00
E Overhead & Profit (contoh 10%) 10% 5,106.00
F Harga Satuan Pekerjaan (D+E) 56,166.00

Pemasangan 1 m2 Atap Serat Semen Gelombang


18 A.4.5.2.18 1 m2 65,993.40
105cm x 150cm x 5mm

A Tenaga 19,110.00
L.01 0.14 OH Pekerja 82,000.00 11,480.00
L.02 0.07 OH Tukang Kayu 90,000.00 6,300.00
L.03 0.007 OH Kepala Tukang 95,000.00 665.00
L.04 0.007 OH Mandor 95,000.00 665.00
B Bahan 40,884.00
0.80 Lbr Serat semen gel 105x150 44,700.00 35,760.00
0.12 Kg Paku Pancing 60 x 230 42,700.00 5,124.00
C PERALATAN
D Jumlah A + B + C 59,994.00
E Overhead & Profit (contoh 10%) 10% 5,999.40
F Harga Satuan Pekerjaan (D+E) 65,993.40
Pemasangan 1 m2 Atap Serat Semen Gelombang
19 A.4.5.2.19 1 m2 70,613.40
108cm x 300cm x 6mm

A Tenaga 19,110.00
L.01 0.14 OH Pekerja 82,000.00 11,480.00
L.02 0.070 OH Tukang Kayu 90,000.00 6,300.00
L.03 0.007 OH Kepala Tukang 95,000.00 665.00
L.04 0.007 OH Mandor 95,000.00 665.00

B Bahan 45,084.00

0.37 Lbr Serat semen gel 108x300 108,000.00 39,960.00

0.12 Kg Paku Pancing 60 x 230 42,700.00 5,124.00

C PERALATAN

D Jumlah A + B + C 64,194.00

E Overhead & Profit (contoh 10%) 10% 6,419.40

F Harga Satuan Pekerjaan (D+E) 70,613.40

Pemasangan 1 m2 Atap Serat Semen Gelombang


20 A.4.5.2.20 1 m2 66,785.40
108cm x 270cm x 6mm

A Tenaga 19,110.00

L.01 0.14 OH Pekerja 82,000.00 11,480.00

L.02 0.070 OH Tukang Kayu 90,000.00 6,300.00

L.03 0.007 OH Kepala Tukang 95,000.00 665.00


L.04 0.007 OH Mandor 95,000.00 665.00
B Bahan 41,604.00
0.38 Lbr serat semen gel 108x270 96,000.00 36,480.00
0.12 Kg Paku Pancing 60 x 230 42,700.00 5,124.00
C PERALATAN
D Jumlah A + B + C 60,714.00
E Overhead & Profit (contoh 10%) 10% 6,071.40
F Harga Satuan Pekerjaan (D+E) 66,785.40

Pemasangan 1 m2 Atap Serat Semen Gelombang


21 A.4.5.2.21 1 m2 65,113.40
108cm x 240cm x 6mm

A Tenaga 19,110.00
L.01 0.14 OH Pekerja 82,000.00 11,480.00
L.02 0.070 OH Tukang Kayu 90,000.00 6,300.00
L.03 0.007 OH Kepala Tukang 95,000.00 665.00
L.04 0.007 OH Mandor 95,000.00 665.00
B Bahan 40,084.00
0.46 Lbr Serat Semen gel 108x240 76,000.00 34,960.00
0.12 Kg Paku Pancing 60 x 230 42,700.00 5,124.00
C PERALATAN
D Jumlah A + B + C 59,194.00
E Overhead & Profit (contoh 10%) 10% 5,919.40
F Harga Satuan Pekerjaan (D+E) 65,113.40

21 A.4.5.2.22 1 m2 Pemasangan 1 m2 Atap Galvalum berpasir 0.5mm 276,072.50

A Tenaga 26,445.00
L.01 0.20 OH Pekerja 82,000.00 16,400.00
L.02 0.100 OH Tukang Kayu 90,000.00 9,000.00
L.03 0.010 OH Kepala Tukang 95,000.00 950.00
L.04 0.001 OH Mandor 95,000.00 95.00
B Bahan 224,530.00
1.05 m2 Galvalum berpasir 0.5mm 213,120.00 223,776.00
0.02 kg Paku hak pnjang 15 cm 37,700.00 754.00
C PERALATAN
D Jumlah A + B + C 250,975.00
E Overhead & Profit (contoh 10%) 10% 25,097.50
F Harga Satuan Pekerjaan (D+E) 276,072.50
22 A.4.5.2.32 1 m2 Pemasangan 1 m2 Atap Genteng Beton 103,290.00
A Tenaga 27,300.00
L.01 0.2 OH Pekerja 82,000.00 16,400.00
L.02 0.1 OH Tukang Kayu 90,000.00 9,000.00
L.03 0.01 OH Kepala Tukang 95,000.00 950.00
L.04 0.01 OH Mandor 95,000.00 950.00
B Bahan 66,600.00
11 Lbr Genteng Beton Standrad 6,000.00 66,000.00
0.03 Kg Paku Biasa 2" - 5" 20,000.00 600.00
C PERALATAN
D Jumlah A + B + C 93,900.00
E Overhead & Profit (contoh 10%) 10% 9,390.00
F Harga Satuan Pekerjaan (D+E) 103,290.00

23 A.4.5.2.33 1 m2 Pemasangan 1 m2 Atap Genteng Aspal 80x100 cm 216,766.00


A Tenaga 44,635.00
L.01 0.2 OH Pekerja 82,000.00 16,400.00
L.02 0.3 OH Tukang Kayu 90,000.00 27,000.00
L.03 0.003 OH Kepala Tukang 95,000.00 285.00
L.04 0.01 OH Mandor 95,000.00 950.00
B Bahan 152,425.00
6.9 Buah Genteng Aspal 16,000.00 110,400.00
0.35 lbr Plywood 6 mm 85,500.00 29,925.00
0.03 kg Paku Biasa 2" - 5" 20,000.00 600.00
0.50 buah Plastic Aerotor 23,000.00 11,500.00
C PERALATAN
D Jumlah A + B + C 197,060.00
E Overhead & Profit (contoh 10%) 10% 19,706.00
F Harga Satuan Pekerjaan (D+E) 216,766.00

24 A.4.5.2.34 1 m2 Pemasangan 1 m2 Atap Genteng Metal 109,604.00


A Tenaga 27,300.00
L.01 0.2 OH Pekerja 82,000.00 16,400.00
L.02 0.1 OH Tukang Kayu 90,000.00 9,000.00
L.03 0.01 OH Kepala Tukang 95,000.00 950.00
L.04 0.01 OH Mandor 95,000.00 950.00
B Bahan 72,340.00
1.02 m2 Genteng Metal 67,000.00 68,340.00
0.20 Kg Paku Biasa 2" - 5" 20,000.00 4,000.00
C PERALATAN
D Jumlah A + B + C 99,640.00
E Overhead & Profit (contoh 10%) 10% 9,964.00
F Harga Satuan Pekerjaan (D+E) 109,604.00
25 A.4.5.2.35 1 m2 Pemasangan 1 m2 Atap Sirap Kayu 249,531.70
A Tenaga 39,247.00
L.01 0.166 OH Pekerja 82,000.00 13,612.00
L.02 0.25 OH Tukang Kayu 90,000.00 22,500.00
L.03 0.025 OH Kepala Tukang 95,000.00 2,375.00
L.04 0.008 OH Mandor 95,000.00 760.00
B Bahan 187,600.00
30 Lbr Genteng Sirap 6,120.00 183,600.00
0.2 Kg Paku Biasa 1/2" - 1" 20,000.00 4,000.00
C PERALATAN
D Jumlah A + B + C 226,847.00
E Overhead & Profit (contoh 10%) 10% 22,684.70
F Harga Satuan Pekerjaan (D+E) 249,531.70

26 A.4.5.2.36 1 m' Pemasangan 1 m’ Nok/Bubung Genteng Beton 120,357.60


A Tenaga 54,600.00
L.01 0.4 OH Pekerja 82,000.00 32,800.00
L.02 0.2 OH Tukang Kayu 90,000.00 18,000.00
L.03 0.02 OH Kepala Tukang 95,000.00 1,900.00
L.04 0.02 OH Mandor 95,000.00 1,900.00
B Bahan 54,816.00
3.5 Buah Nok Genteng Beton 7,500.00 26,250.00
0.05 Kg Paku Biasa 2" - 5" 20,000.00 1,000.00
10.8 Kg Portland Semen 1,625.00 17,550.00
0.032 m3 Pasir Pasang 313,000.00 10,016.00
1 Kg Semen Warna 16,000.00 16,000.00
C PERALATAN
D Jumlah A + B + C 109,416.00
E Overhead & Profit (contoh 10%) 10% 10,941.60
F Harga Satuan Pekerjaan (D+E) 120,357.60

27 A.4.5.2.37 1 m' Pemasangan 1 m’ Nok/Bubung Genteng Aspal 224,731.38


A Tenaga 35,695.00
L.01 0.125 OH Pekerja 82,000.00 10,250.00
L.02 0.250 OH Tukang Kayu 90,000.00 22,500.00
L.03 0.025 OH Kepala Tukang 95,000.00 2,375.00
L.04 0.006 OH Mandor 95,000.00 570.00
B Bahan 168,606.25
2.0 Buah Nok Genteng Aspal 66,500.00 133,000.00
0.05 Kg Paku Biasa 2" - 5" 20,000.00 1,000.00
0.0035 m3 Balok Kayu 9,887,500.00 34,606.25
C PERALATAN
D Jumlah A + B + C 204,301.25
E Overhead & Profit (contoh 10%) 10% 20,430.13
F Harga Satuan Pekerjaan (D+E) 224,731.38
28 A.4.5.2.38 1 m' Pemasangan 1 m’ Nok/Bubung Genteng Metal 99,506.00
A Tenaga 36,660.00
L.01 0.250 OH Pekerja 82,000.00 20,500.00
L.02 0.150 OH Tukang Kayu 90,000.00 13,500.00
L.03 0.015 OH Kepala Tukang 95,000.00 1,425.00
L.04 0.013 OH Mandor 95,000.00 1,235.00
B Bahan 53,800.00
1.1 Buah Nok Genteng 48,000.00 52,800.00
0.05 Kg Paku Biasa 1/2" - 1" 20,000.00 1,000.00
C PERALATAN
D Jumlah A + B + C 90,460.00
E Overhead & Profit (contoh 10%) 10% 9,046.00
F Harga Satuan Pekerjaan (D+E) 99,506.00

29 A.4.5.2.39 1 m' Pemasangan 1 m’ Nok/Bubung Atap Sirap 56,512.50


A Tenaga 35,695.00
L.01 0.125 OH Pekerja 82,000.00 10,250.00
L.02 0.25 OH Tukang Kayu 90,000.00 22,500.00
L.03 0.025 OH Kepala Tukang 95,000.00 2,375.00
L.04 0.006 OH Mandor 95,000.00 570.00
B Bahan 15,680.00
0.4 Lbr Seng Plaat 3" x 6" BJLS 28 33,700.00 13,480.00
0.06 Kg Paku Biasa 1/2" - 1" 20,000.00 1,200.00
0.05 Kg Paku Biasa 2" - 5" 20,000.00 1,000.00

C PERALATAN
D Jumlah A + B + C 51,375.00
E Overhead & Profit (contoh 10%) 10% 5,137.50
F Harga Satuan Pekerjaan (D+E) 56,512.50

30 A.4.5.2.40 1 m2 Pemasangan 1 m2 Atap Seng Gelombang 105cm x180cm 44,407.00


A Tenaga 16,380.00
L.01 0.12 OH Pekerja 82,000.00 9,840.00
L.02 0.06 OH Tukang Kayu 90,000.00 5,400.00
L.03 0.006 OH Kepala Tukang 95,000.00 570.00
L.04 0.006 OH Mandor 95,000.00 570.00
B Bahan 23,990.00
0.7 Lbr Seng Gelombang 3" x 6" BJLS 28 33,700.00 23,590.00
0.02 Kg Paku Biasa 1/2" - 1" 20,000.00 400.00
C PERALATAN
D Jumlah A + B + C 40,370.00
E Overhead & Profit (contoh 10%) 10% 4,037.00
F Harga Satuan Pekerjaan (D+E) 44,407.00
31 A.4.5.2.41 1 m' Pemasangan 1 m’ Nok/Bubung Atap Seng 33,819.50
A Tenaga 19,835.00
L.01 0.15 OH Pekerja 82,000.00 12,300.00
L.02 0.07 OH Tukang Kayu 90,000.00 6,300.00
L.03 0.007 OH Kepala Tukang 95,000.00 665.00
L.04 0.006 OH Mandor 95,000.00 570.00
B Bahan 10,910.00
0.3 Lbr Seng Plaat 3" x 6" BJLS 28 33,700.00 10,110.00
0.04 Kg Paku Biasa 1/2" - 1" 20,000.00 800.00
C PERALATAN
D Jumlah A + B + C 30,745.00
E Overhead & Profit (contoh 10%) 10% 3,074.50
F Harga Satuan Pekerjaan (D+E) 33,819.50

32 A.4.5.2.44 1 m2 Pemasangan 1 m2 Lapisan Aluminium Foil 38,318.50


A Tenaga 18,035.00
L.01 0.15 OH Pekerja 82,000.00 12,300.00
L.02 0.05 OH Tukang Kayu 90,000.00 4,500.00
L.03 0.005 OH Kepala Tukang 95,000.00 475.00
L.04 0.008 OH Mandor 95,000.00 760.00
B Bahan 16,800.00
1.05 m2 Sisalation / Allumunium Foil 16,000.00 16,800.00
C PERALATAN
D Jumlah A + B + C 34,835.00
E Overhead & Profit (contoh 10%) 10% 3,483.50
F Harga Satuan Pekerjaan (D+E) 38,318.50
HARGA
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN BAHAN/UPAH

Rp
DIVISI IV A.4.6.1 HARGA SATUAN PEKERJAAN KAYU

Pembuatan dan Pemasangan 1 m3 Kusen Pintu


1 A.4.6.1.1 1 m3
dan Kusen Jendela. Kayu Kelas I

A Tenaga
L.01 7 OH Pekerja 82,000.00
L.02 21 OH Tukang Kayu 90,000.00
L.03 2.10 OH Kepala Tukang 95,000.00
L.04 0.35 OH Mandor 95,000.00
B Bahan
1.1 m3 Kayu Klas I (Jati) , Balok 19,863,000.00
1.25 kg Paku Biasa 2" - 5 " 20,000.00
1 kg Lem Kayu 20,000.00
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit (contoh 10%) 10%
F Harga Satuan Pekerjaan (D+E)

Pembuatan dan Pemasangan 1 m3 Kusen Pintu


2 A.4.6.1.2 1 m3
dan Kusen Jendela Kayu Kelas II atau III

Tenaga
L.01 6.00 OH Pekerja 82,000.00
L.02 18.00 OH Tukang Kayu 90,000.00
L.03 1.80 OH Kepala Tukang 95,000.00
L.04 0.30 OH Mandor 95,000.00
Bahan
1.2 m3 Kayu Klas II (Kamfer) , Balok 12,174,000.00
1.25 kg Paku Biasa 2" - 5 " 20,000.00
1 kg Lem Kayu 20,000.00
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit (contoh 10%) 10%
F Harga Satuan Pekerjaan (D+E)

Pembuatan dan Pemasangan 1 m2 Pintu Klamp


3 A.4.6.1.3 1 m2
Standar Kayu Kelas II

A Tenaga
L.01 0.35 OH Pekerja 82,000.00
L.02 1.05 OH Tukang Kayu 90,000.00
L.03 0.105 OH Kepala Tukang 95,000.00
L.04 0.018 OH Mandor 95,000.00
B Bahan
0.040 m3 Kayu Klas II (Kamfer), papan 14,096,500.00
0.05 Kg Paku Biasa 2" - 5 " 20,000.00
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit (contoh 10%) 10%
F Harga Satuan Pekerjaan (D+E)
Pembuatan dan Pemasangan 1 m2 Pintu Klamp
4 A.4.6.1.4 1 m2
Sederhana Kayu Kelas III
Tenaga
L.01 0.35 OH Pekerja 82,000.00
L.02 1.05 OH Tukang Kayu 90,000.00
L.03 0.105 OH Kepala Tukang 95,000.00
L.04 0.018 OH Mandor 95,000.00
Bahan
0.040 m3 Kayu Klas II (Kamfer), papan 14,096,500.00
0.05 Kg Paku Biasa 2" - 5 " 20,000.00
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit (contoh 10%) 10%
F Harga Satuan Pekerjaan (D+E)

Pembuatan 1 m2 Daun Pintu Panel. Kayu Kelas I


5 A.4.6.1.5 1 m2
atau II
A Tenaga
L.01 1.00 OH Pekerja 82,000.00
L.02 3.00 OH Tukang Kayu 90,000.00
L.03 0.30 OH Kepala Tukang 95,000.00
L.04 0.05 OH Mandor 95,000.00
B Bahan
0.04 m3 Kayu Klas II (Kamfer), papan 14,096,500.00
0.050 kg Lem Kayu 20,000.00
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit (contoh 10%) 10%
F Harga Satuan Pekerjaan (D+E)

Pembuatan 1 m2 Pintu dan Jendela Kaca. Kayu


6 A.4.6.1.6 1 m2
Kelas I atau II
A Tenaga
L.01 0.800 OH Pekerja 82,000.00
L.02 2.400 OH Tukang Kayu 90,000.00
L.03 0.240 OH Kepala Tukang 95,000.00
L.04 0.040 OH Mandor 95,000.00
B Bahan
0.024 m3 Kayu Klas II (Kamfer), papan 14,096,500.00
0.300 kg Lem Kayu 20,000.00
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit (contoh 10%) 10%
F Harga Satuan Pekerjaan (D+E)
Pembuatan 1 m2 Pintu dan Jendela Jalusi Kayu
7 A.4.6.1.7 1 m2
Kelas I atau II
A Tenaga
L.01 1 OH Pekerja 82,000.00
L.02 3 OH Tukang Kayu 90,000.00
L.03 0.3 OH Kepala Tukang 95,000.00
L.04 0.05 OH Mandor 95,000.00
B Bahan
0.064 m3 Kayu Klas I (Jati), papan 19,863,000.00
0.5 kg Lem Kayu 20,000.00
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit (contoh 10%) 10%
F Harga Satuan Pekerjaan (D+E)

Pembuatan 1 m2 Daun pintu Plywood Rangkap.


8 A.4.6.1.8 1 m2 Rangka Kayu Kelas II Tertutup (Lebar Sampai
90cm)
A Tenaga
L.01 0.700 OH Pekerja 82,000.00
L.02 2.100 OH Tukang Kayu 90,000.00
L.03 0.210 OH Kepala Tukang 95,000.00
L.04 0.035 OH Mandor 95,000.00
B Bahan
0.025 m3 Kayu Klas II (Kamfer), papan 14,096,500.00
0.030 Kg Paku Biasa 1/2" - 1" 20,000.00
0.500 Ltr Lem Kayu 20,000.00
1.000 Lbr Plywood tebal 4 mm uk.90x220cm 106,200.00
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit (contoh 10%) 10%
F Harga Satuan Pekerjaan (D+E)

Pembuatan 1m2 Pintu Plywood Rangkap. Rangka


9 A.4.6.1.9 1 m2
Expose Kayu Kelas I atau II
A Tenaga
L.01 0.800 OH Pekerja 82,000.00
L.02 2.400 OH Tukang Kayu 90,000.00
L.03 0.240 OH Kepala Tukang 95,000.00
L.04 0.040 OH Mandor 95,000.00
B Bahan
0.0256 m3 Kayu Klas II (Kamfer), papan 14,096,500.00
0.03 Kg Paku Biasa 1/2" - 1" 20,000.00
0.5 Ltr Lem Kayu 20,000.00
1 Lbr Plywood tebal 4 mm uk.90x220cm 106,200.00
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit (contoh 10%) 10%
F Harga Satuan Pekerjaan (D+E)
Pembuatan dan Pemasangan 1 m2 Jalusi Kusen
10 A.4.6.1.10 1 m2
Kayu Kelas I atau II
A Tenaga
L.01 0.670 OH Pekerja 82,000.00
L.02 2.000 OH Tukang Kayu 90,000.00
L.03 0.200 OH Kepala Tukang 95,000.00
L.04 0.335 OH Mandor 95,000.00
B Bahan
0.06 m3 Kayu Klas I (Jati), papan 19,863,000.00
0.15 Kg Paku Biasa 1/2" - 1" 20,000.00
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit (contoh 10%) 10%
F Harga Satuan Pekerjaan (D+E)

Pembuatan 1 m2 Teakwood Rangkap. Rangka


11 A.4.6.1.11 1 m2
Expose Kayu Kelas I

A Tenaga
L.01 0.80 OH Pekerja 82,000.00
L.02 2.40 OH Tukang Kayu 90,000.00
L.03 0.24 OH Kepala Tukang 95,000.00
L.04 0.04 OH Mandor 95,000.00
B Bahan
0.025 m3 Kayu Klas I (Jati), papan 19,863,000.00
0.03 Kg Paku Biasa 1/2" - 1" 20,000.00
0.3 kg Lem Kayu 20,000.00
1 Lbr Teakwood (90 x 220) cm x 4 mm 106,200.00
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit (contoh 10%) 10%
F Harga Satuan Pekerjaan (D+E)

Pembuatan 1 m2 Teakwood Rangkap Lapis


12 A.4.6.1.12 1 m2
Formika. Rangka Expose Kayu Kelas II

A Tenaga
L.01 0.850 OH Pekerja 82,000.00
L.02 2.550 OH Tukang Kayu 90,000.00
L.03 0.255 OH Kepala Tukang 95,000.00
L.04 0.043 OH Mandor 95,000.00
B Bahan
0.025 m3 Kayu Klas II (Kamfer), papan 14,096,500.00
0.03 Kg Paku Biasa 1/2" - 1" 20,000.00
0.08 kg Lem Kayu 20,000.00
1 Lbr Teakwood (90 x 220) cm x 4 mm 106,200.00
0.5 Lbr Formika 126,000.00
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit (contoh 10%) 10%
F Harga Satuan Pekerjaan (D+E)
Pemasangan 1 m3 Konstruksi Kuda-kuda
13 A.4.6.1.13 1 m3 Konvensional. Kayu Kelas I.
II dan III Bentang Sampai Dengan 6 Meter
A Tenaga
L.01 4 OH Pekerja 82,000.00
L.02 12 OH Tukang Kayu 90,000.00
L.03 1.2 OH Kepala Tukang 95,000.00
L.04 0.2 OH Mandor 95,000.00
B Bahan
1.1 m3 Kayu Kamfer, balok 12,174,000.00
15 Kg Besi Strip 19,000.00
5.6 Kg Paku Biasa 2" - 5" 20,000.00
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit (contoh 10%) 10%
F Harga Satuan Pekerjaan (D+E)

Pemasangan 1 m3 Konstruksi Kuda-kuda Expose.


14 A.4.6.1.14 1 m3
Kayu Kelas I
A Tenaga
L.01 6.7 OH Pekerja 82,000.00
L.02 20.1 OH Tukang Kayu 90,000.00
L.03 2.01 OH Kepala Tukang 95,000.00
L.04 0.335 OH Mandor 95,000.00
B Bahan
1.2 m3 Kayu Klas I (jati), balok 19,863,000.00
15 Kg Besi Strip 19,000.00
5.6 Kg Paku Biasa 2" - 5" 20,000.00
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit (contoh 10%) 10%
F Harga Satuan Pekerjaan (D+E)

15 A.4.6.1.15 1 m3 Pemasangan 1 m3 Konstruksi Gordeng. Kayu kelas II


A Tenaga
L.01 2.4 OH Pekerja 82,000.00
L.02 7.2 OH Tukang Kayu 90,000.00
L.03 0.72 OH Kepala Tukang 95,000.00
L.04 0.12 OH Mandor 95,000.00
B Bahan
1.1 m3 Kayu Klas I (Kamfer), balok 14,096,500.00
15 Kg Besi Strip 19,000.00
3 Kg Paku Biasa 2" - 5" 20,000.00
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit (contoh 10%) 10%
F Harga Satuan Pekerjaan (D+E)
Pemasangan 1 m2 Rangka Atap Genteng Keramik.
16 A.4.6.1.16 1 m2
Kayu kelas II
A Tenaga
L.01 0.1 OH Pekerja 82,000.00
L.02 0.1 OH Tukang Kayu 90,000.00
L.03 0.01 OH Kepala Tukang 95,000.00
L.04 0.005 OH Mandor 95,000.00
B Bahan
0.014 m3 Kayu Klas II (Kamfer), Kaso-kaso (5x7) cm 12,174,000.00
0.0036 m3 Reng (2x3) cm 12,174,000.00
0.25 Kg Paku Biasa 2" - 5" 20,000.00
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit (contoh 10%) 10%
F Harga Satuan Pekerjaan (D+E)

Pemasangan 1 m2 Rangka Atap Genteng Beton


17 A.4.6.1.17 1 m2
Kayu Kelas II
A Tenaga
L.01 0.1 OH Pekerja 82,000.00
L.02 0.1 OH Tukang Kayu 90,000.00
L.03 0.01 OH Kepala Tukang 95,000.00
L.04 0.005 OH Mandor 95,000.00
B Bahan
0.014 m3 Kayu Klas II (Kamfer), Kaso-kaso (5x7) cm 12,174,000.00
0.0072 m3 Reng (2x3) cm 12,174,000.00
0.25 Kg Paku Biasa 2" - 5" 20,000.00
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit (contoh 10%) 10%
F Harga Satuan Pekerjaan (D+E)

18 A.4.6.1.18 1 m2 Pemasangan 1 m2 Rangka Atap Sirap. Kayu Kelas II


A Tenaga
L.01 0.12 OH Pekerja 82,000.00
L.02 0.12 OH Tukang Kayu 90,000.00
L.03 0.012 OH Kepala Tukang 95,000.00
L.04 0.006 OH Mandor 95,000.00
B Bahan
0.014 m3 Kayu Klas II (Kamfer), balok 12,174,000.00
0.2 Kg Paku Biasa 2" - 5" 20,000.00
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit (contoh 10%) 10%
F Harga Satuan Pekerjaan (D+E)
Pemasangan 1 m2 Rangka Langit-Langit
19 A.4.6.1.19 1 m2
50x100cm. Kayu kelas II atau III
A Tenaga
L.01 0.15 OH Pekerja 82,000.00
L.02 0.30 OH Tukang Kayu 90,000.00
L.03 0.030 OH Kepala Tukang 95,000.00
L.04 0.075 OH Mandor 95,000.00
B Bahan
0.0154 m3 Kayu Klas II (Kamfer), balok 12,174,000.00
0.2 Kg Paku Biasa 2" - 5" 20,000.00
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit (contoh 10%) 10%
F Harga Satuan Pekerjaan (D+E)

Pemasangan 1 m2 Rangka Langit-Langit


20 A.4.6.1.20 1 m2
60x60cm. Kayu Kelas II atau III
A Tenaga
L.01 0.2 OH Pekerja 82,000.00
L.02 0.3 OH Tukang Kayu 90,000.00
L.03 0.03 OH Kepala Tukang 95,000.00
L.04 0.01 OH Mandor 95,000.00
B Bahan
0.0163 m3 Kayu Klas II (Kamfer), balok 12,174,000.00
0.25 Kg Paku Biasa 2" - 5" 20,000.00
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit (contoh 10%) 10%
F Harga Satuan Pekerjaan (D+E)

Pemasangan 1 m’ Lisplank Ukuran 3x20cm. Kayu


21 A.4.6.1.21 1 m'
Kelas I atau Kelas II
A Tenaga
L.01 0.1 OH Pekerja 82,000.00
L.02 0.2 OH Tukang Kayu 90,000.00
L.03 0.020 OH Kepala Tukang 95,000.00
L.04 0.005 OH Mandor 95,000.00
B Bahan
0.0108 m3 Kayu klas I (Jati), papan 19,863,000.00
0.10 Kg Paku Biasa 2" - 5" 20,000.00
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit (contoh 10%) 10%
F Harga Satuan Pekerjaan (D+E)
Pemasangan 1 m’ Lisplank Ukuran 3x30cm. Kayu
22 A.4.6.1.22 1 m'
Kelas I atau Kelas II
A Tenaga
L.01 0.1 OH Pekerja 82,000.00
L.02 0.2 OH Tukang Kayu 90,000.00
L.03 0.02 OH Kepala Tukang 95,000.00
L.04 0.005 OH Mandor 95,000.00
B Bahan
0.011 m3 Kayu klas II (Kamfer), papan 14,096,500.00
0.05 Kg Paku Biasa 2" - 5" 20,000.00
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit (contoh 10%) 10%
F Harga Satuan Pekerjaan (D+E)

Pemasangan 1 m2 Rangka Dinding Pemisah


23 A.4.6.1.23 1 m2
60x120cm Kayu kelas II atau III
A Tenaga
L.01 0.15 OH Pekerja 82,000.00
L.02 0.45 OH Tukang Kayu 90,000.00
L.03 0.045 OH Kepala Tukang 95,000.00
L.04 0.008 OH Mandor 95,000.00
B Bahan
0.028 m3 Kayu klas II (Kamfer), balok 12,174,000.00
0.15 Kg Paku Biasa 2" - 5" 20,000.00
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit (contoh 10%) 10%
F Harga Satuan Pekerjaan (D+E)

Pemasangan 1 m2 Dinding Pemisah Teakwood


24 A.4.6.1.24 1 m2
Rangkap Rangka Kayu Klas II
A Tenaga
L.01 0.15 OH Pekerja 82,000.00
L.02 0.45 OH Tukang Kayu 90,000.00
L.03 0.045 OH Kepala Tukang 95,000.00
L.04 0.008 OH Mandor 95,000.00
B Bahan
0.028 m3 Kayu klas II (Kamfer), balok 12,174,000.00
0.15 Kg Paku Biasa 2" - 5" 20,000.00
0.86 Lbr Plywood 120 x 240 cm tebal 4mm 76,000.00
0.56 Ltr Lem 20,000.00
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit (contoh 10%) 10%
F Harga Satuan Pekerjaan (D+E)
Pemasangan 1 m2 Dinding Pemisah Plywood
25 A.4.6.1.25 1 m2
Rangkap Rangka Kayu Kelas II
A Tenaga
L.01 0.020 OH Pekerja 82,000.00
L.02 0.600 OH Tukang Kayu 90,000.00
L.03 0.060 OH Kepala Tukang 95,000.00
L.04 0.010 OH Mandor 95,000.00
B Bahan
0.028 m3 Kayu klas II (Kamfer), balok 12,174,000.00
0.15 Kg Paku Biasa 2" - 5" 20,000.00
0.86 Lbr Plywood 120 x 240 cm tebal 4mm 76,000.00
0.56 Ltr Lem 20,000.00
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit (contoh 10%) 10%
F Harga Satuan Pekerjaan (D+E)

Pemasangan 1 m2 Dinding Lambrisering dari


26 A.4.6.1.26 1 m2
Papan Kayu Kelas I
A Tenaga
L.01 0.6 OH Pekerja 82,000.00
L.02 1.8 OH Tukang Kayu 90,000.00
L.03 0.18 OH Kepala Tukang 95,000.00
L.04 0.03 OH Mandor 95,000.00
B Bahan
0.007 m3 Kayu klas I (Jati), papan 19,863,000.00
0.1 Kg Paku Biasa 2" - 5" 20,000.00
0.15 Kg Paku Sekrup 3,5" 51,200.00
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit (contoh 10%) 10%
F Harga Satuan Pekerjaan (D+E)

Pemasangan 1 m2 Dinding Lambrisering dari


27 A.4.6.1.27 1 m2
Plywood (Kayu Lapis) Ukuran 120x240cm
A Tenaga
L.01 0.025 OH Pekerja 82,000.00
L.02 0.075 OH Tukang Kayu 90,000.00
L.03 0.0080 OH Kepala Tukang 95,000.00
L.04 0.0010 OH Mandor 95,000.00
B Bahan
0.4 Lbr Plywood (120 X 240) cm x 4mm 76,000.00
0.05 Kg Paku Biasa 1/2" - 1" 20,000.00
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit (contoh 10%) 10%
F Harga Satuan Pekerjaan (D+E)
Pemasangan 1 m2 Dinding Bilik. Rangka Kayu
28 A.4.6.1.28 1 m2
Kelas III atau IV
A Tenaga
L.01 0.1 OH Pekerja 82,000.00
L.02 0.05 OH Tukang Kayu 90,000.00
L.03 0.005 OH Kepala Tukang 95,000.00
L.04 0.005 OH Mandor 95,000.00
B Bahan
1.500 m2 Bilik Bambu 56,500.00
0.014 m3 Kayu Klas III (Meranti) 6,979,000.00
0.012 Kg Paku Biasa 1/2" - 1" 20,000.00
0.003 m' List Kayu 2/4 18,500.00
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit (contoh 10%) 10%
F Harga Satuan Pekerjaan (D+E)
JUMLAH

Rp

27,050,155.00

2,696,750.00
574,000.00
1,890,000.00
199,500.00
33,250.00
21,894,300.00
21,849,300.00
25,000.00
20,000.00

24,591,050.00
2,459,105.00
27,050,155.00

18,661,830.00

2,311,500.00
492,000.00
1,620,000.00
171,000.00
28,500.00
14,653,800.00
14,608,800.00
25,000.00
20,000.00

16,965,300.00
1,696,530.00
18,661,830.00

769,719.50

134,885.00
28,700.00
94,500.00
9,975.00
1,710.00
564,860.00
563,860.00
1,000.00

699,745.00
69,974.50
769,719.50
769,719.50

134,885.00
28,700.00
94,500.00
9,975.00
1,710.00
564,860.00
563,860.00
1,000.00

699,745.00
69,974.50
769,719.50

1,045,121.00

385,250.00
82,000.00
270,000.00
28,500.00
4,750.00
564,860.00
563,860.00
1,000.00

950,110.00
95,011.00
1,045,121.00

717,767.60

308,200.00
65,600.00
216,000.00
22,800.00
3,800.00
344,316.00
338,316.00
6,000.00

652,516.00
65,251.60
717,767.60
1,833,130.20

385,250.00
82,000.00
270,000.00
28,500.00
4,750.00
1,281,232.00
1,271,232.00
10,000.00

1,666,482.00
166,648.20
1,833,130.20

812,776.25

269,675.00
57,400.00
189,000.00
19,950.00
3,325.00
469,212.50
352,412.50
600.00
10,000.00
106,200.00

738,887.50
73,888.75
812,776.25

864,457.44

308,200.00
65,600.00
216,000.00
22,800.00
3,800.00
477,670.40
360,870.40
600.00
10,000.00
106,200.00

785,870.40
78,587.04
864,457.44
1,628,599.50

285,765.00
54,940.00
180,000.00
19,000.00
31,825.00
1,194,780.00
1,191,780.00
3,000.00

1,480,545.00
148,054.50
1,628,599.50

1,009,332.50

308,200.00
65,600.00
216,000.00
22,800.00
3,800.00
609,375.00
496,575.00
600.00
6,000.00
106,200.00

917,575.00
91,757.50
1,009,332.50

936,454.75

327,510.00
69,700.00
229,500.00
24,225.00
4,085.00
523,812.50
352,412.50
600.00
1,600.00
106,200.00
63,000.00

851,322.50
85,132.25
936,454.75
16,862,340.00

1,541,000.00
328,000.00
1,080,000.00
114,000.00
19,000.00
13,788,400.00
13,391,400.00
285,000.00
112,000.00

15,329,400.00
1,532,940.00
16,862,340.00

29,495,152.50

2,581,175.00
549,400.00
1,809,000.00
190,950.00
31,825.00
24,232,600.00
23,835,600.00
285,000.00
112,000.00

26,813,775.00
2,681,377.50
29,495,152.50

18,453,325.00
924,600.00
196,800.00
648,000.00
68,400.00
11,400.00
15,851,150.00
15,506,150.00
285,000.00
60,000.00

16,775,750.00
1,677,575.00
18,453,325.00
261,676.14

18,625.00
8,200.00
9,000.00
950.00
475.00
219,262.40
170,436.00
43,826.40
5,000.00

237,887.40
23,788.74
261,676.14

309,885.18

18,625.00
8,200.00
9,000.00
950.00
475.00
263,088.80
170,436.00
87,652.80
5,000.00

281,713.80
28,171.38
309,885.18

216,464.60
22,350.00
9,840.00
10,800.00
1,140.00
570.00
174,436.00
170,436.00
4,000.00

196,786.00
19,678.60
216,464.60
264,830.06

49,275.00
12,300.00
27,000.00
2,850.00
7,125.00
191,479.60
187,479.60
4,000.00

240,754.60
24,075.46
264,830.06

275,699.82

47,200.00
16,400.00
27,000.00
2,850.00
950.00
203,436.20
198,436.20
5,000.00

250,636.20
25,063.62
275,699.82

269,604.94

28,575.00
8,200.00
18,000.00
1,900.00
475.00
216,520.40
214,520.40
2,000.00

245,095.40
24,509.54
269,604.94
203,100.15

28,575.00
8,200.00
18,000.00
1,900.00
475.00
156,061.50
155,061.50
1,000.00

184,636.50
18,463.65
203,100.15

441,877.70

57,835.00
12,300.00
40,500.00
4,275.00
760.00
343,872.00
340,872.00
3,000.00

401,707.00
40,170.70
441,877.70

526,093.70

57,835.00
12,300.00
40,500.00
4,275.00
760.00
420,432.00
340,872.00
3,000.00
65,360.00
11,200.00

478,267.00
47,826.70
526,093.70
530,994.20

62,290.00
1,640.00
54,000.00
5,700.00
950.00
420,432.00
340,872.00
3,000.00
65,360.00
11,200.00

482,722.00
48,272.20
530,994.20

417,858.10

231,150.00
49,200.00
162,000.00
17,100.00
2,850.00
148,721.00
139,041.00
2,000.00
7,680.00

379,871.00
37,987.10
417,858.10

45,160.50

9,655.00
2,050.00
6,750.00
760.00
95.00
31,400.00
30,400.00
1,000.00

41,055.00
4,105.50
45,160.50
216,041.65

13,650.00
8,200.00
4,500.00
475.00
475.00
182,751.50
84,750.00
97,706.00
240.00
55.50

196,401.50
19,640.15
216,041.65
HARGA
BAHAN/UPA
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN H
Rp

DIVISI IV A.4.6.2 HARGA SATUAN PEKERJAAN KUNCI dan KACA

1 A.4.6.2.1 1 Buah Pemasangan 1 Buah Kunci Tanam Antik

A Tenaga

L.01 0.06 OH Pekerja 82,000.00

L.02 0.6 OH Tukang Kayu 90,000.00

L.03 0.06 OH Kepala Tukang 95,000.00

L.04 0.003 OH Mandor 95,000.00

B Bahan

1 Buah Kunci Tanam Antik 170,000.00

C PERALATAN

D 0

E Pemasangan 1 m2 Dinding Bilik. Rangka Kayu Kelas 10%

F Harga Satuan Pekerjaan (D+E)

2 A.4.6.2.2 1 Buah Pemasangan 1 Buah Kunci Tanam Biasa

A Tenaga

L.01 0.01 OH Pekerja 82,000.00

L.02 0.5 OH Tukang Kayu 90,000.00

L.03 0.01 OH Kepala Tukang 95,000.00

L.04 0.005 OH Mandor 95,000.00

B Bahan

1 Buah Kunci Tanam Biasa 144,700.00

C PERALATAN

D Jumlah A + B + C

E Overhead & Profit (contoh 10%) 10%

F Harga Satuan Pekerjaan (D+E)

Overhead & Profit (contoh 10%)

3 A.4.6.2.3 1 Buah Pemasangan 1 Buah Kunci Tanam Kamar Mandi

A Tenaga

L.01 0.005 OH Pekerja 82,000.00

L.02 0.5 OH Tukang Kayu 90,000.00

L.03 0.005 OH Kepala Tukang 95,000.00

L.04 0.0025 OH Mandor 95,000.00

B Bahan

1 Buah Kunci Tanam Kamar Mandi 120,200.00

C PERALATAN

D Jumlah A + B + C

E Overhead & Profit (contoh 10%) 10%

F Harga Satuan Pekerjaan (D+E)

4 A.4.6.2.4 1 Buah Pemasangan 1 Buah Kunci Tanam Silinder

A Tenaga

L.01 0.005 OH Pekerja 82,000.00

L.02 0.5 OH Tukang Kayu 90,000.00

L.03 0.005 OH Kepala Tukang 95,000.00

L.04 0.0025 OH Mandor 95,000.00


B Bahan

1 Buah Kunci Selinder 144,700.00

C PERALATAN

D Jumlah A + B + C

E Overhead & Profit (contoh 10%) 10%

F Harga Satuan Pekerjaan (D+E)


5 A.4.6.2.5 1 Buah Pemasangan 1 Buah Engsel Pintu

A Tenaga

L.01 0.015 OH Pekerja 82,000.00

L.02 0.15 OH Tukang Kayu 90,000.00

L.03 0.015 OH Kepala Tukang 95,000.00

L.04 0.0075 OH Mandor 95,000.00

B Bahan

1 Buah Engsel pintu 9,500.00

C PERALATAN

D Jumlah A + B + C

E Overhead & Profit (contoh 10%) 10%

F Harga Satuan Pekerjaan (D+E)

6 A.4.6.2.6 1 Buah Pemasangan 1 Buah Engsel Jendela Kupu-Kupu

A Tenaga

L.01 0.01 OH Pekerja 82,000.00

L.02 0.1 OH Tukang Kayu 90,000.00

L.03 0.01 OH Kepala Tukang 95,000.00

L.04 0.005 OH Mandor 95,000.00

B Bahan

1 Buah Engsel Jendela 17,000.00

C PERALATAN

D Jumlah A + B + C

E Overhead & Profit (contoh 10%) 10%

F Harga Satuan Pekerjaan (D+E)

7 A.4.6.2.7 1 Buah Pemasangan 1 Buah Engsel Angin

A Tenaga

L.01 0.10 OH Pekerja 82,000.00

L.02 0.20 OH Tukang Kayu 90,000.00

L.03 0.02 OH Kepala Tukang 95,000.00

L.04 0.0005 OH Mandor 95,000.00

B Bahan

1 Buah Engsel Angin 19,200.00

C PERALATAN

D Jumlah A + B + C

E Overhead & Profit (contoh 10%) 10%

F Harga Satuan Pekerjaan (D+E)


8 A.4.6.2.8 1 Buah Pemasangan 1 Buah Spring Knip

A Tenaga

L.01 0.02 OH Pekerja 82,000.00

L.02 0.15 OH Tukang Kayu 90,000.00

L.03 0.02 OH Kepala Tukang 95,000.00

L.04 0.0080 OH Mandor 95,000.00

B Bahan

1 Buah Spring Knip 61,050.00

C PERALATAN

D Jumlah A + B + C

E Overhead & Profit (contoh 10%) 10%

F Harga Satuan Pekerjaan (D+E)

9 A.4.6.2.9 1 Buah Pemasangan 1 Buah Kait Angin

A Tenaga

L.01 0.015 OH Pekerja 82,000.00

L.02 0.15 OH Tukang Kayu 90,000.00

L.03 0.015 OH Kepala Tukang 95,000.00

L.04 0.008 OH Mandor 95,000.00

B Bahan

1 Buah Kait Angin 16,000.00

C PERALATAN

D Jumlah A + B + C

E Overhead & Profit (contoh 10%) 10%

F Harga Satuan Pekerjaan (D+E)

10 A.4.6.2.10 1 Buah Pemasangan 1 Buah Doorcloser

A Tenaga

L.01 0.05 OH Pekerja 82,000.00

L.02 0.5 OH Tukang Kayu 90,000.00

L.03 0.05 OH Kepala Tukang 95,000.00

L.04 0.0025 OH Mandor 95,000.00

B Bahan

1 Buah Door Closer 702,200.00

C PERALATAN

D Jumlah A + B + C

E Overhead & Profit (contoh 10%) 10%

F Harga Satuan Pekerjaan (D+E)

11 A.4.6.2.11 1 Buah Pemasangan 1 Buah Kunci Slot (Grendel) untuk Jendela

A Tenaga

L.01 0.02 OH Pekerja 82,000.00

L.02 0.2 OH Tukang Kayu 90,000.00

L.03 0.02 OH Kepala Tukang 95,000.00

L.04 0.001 OH Mandor 95,000.00

B Bahan

1 Buah Kunci Selot 121,700.00


C PERALATAN

D Jumlah A + B + C

E Overhead & Profit (contoh 10%) 10%

F Harga Satuan Pekerjaan (D+E)


12 A.4.6.2.12 1 Buah Pemasangan 1 Buah Door Holder

A Tenaga

L.01 0.05 OH Pekerja 82,000.00

L.02 0.5 OH Tukang Kayu 90,000.00

L.03 0.05 OH Kepala Tukang 95,000.00

L.04 0.003 OH Mandor 95,000.00

B Bahan

1 Buah Door Holder 28,416.00

C PERALATAN

D Jumlah A + B + C

E Overhead & Profit (contoh 10%) 10%

F Harga Satuan Pekerjaan (D+E)

13 A.4.6.2.13 1 Buah Pemasangan 1 Buah Doorstop

A Tenaga

L.01 0.01 OH Pekerja 82,000.00

L.02 0.1 OH Tukang Kayu 90,000.00

L.03 0.01 OH Kepala Tukang 95,000.00

L.04 0.0005 OH Mandor 95,000.00

B Bahan

1 Buah Door Stop 78,200.00

C PERALATAN

D Jumlah A + B + C

E Overhead & Profit (contoh 10%) 10%

F Harga Satuan Pekerjaan (D+E)

14 A.4.6.2.14 1 Buah Pemasangan 1 Buah Rel Pintu Dorong

A Tenaga

L.01 0.06 OH Pekerja 82,000.00

L.02 0.6 OH Tukang Kayu 90,000.00

L.03 0.06 OH Kepala Tukang 95,000.00

L.04 0.003 OH Mandor 95,000.00

B Bahan

1 Buah Rel Pintu Dorong 247,000.00

C PERALATAN

D Jumlah A + B + C

E Overhead & Profit (contoh 10%) 10%

F Harga Satuan Pekerjaan (D+E)

15 A.4.6.2.15 1 Buah Pemasangan 1 Buah Kunci Lemari

A Tenaga

L.01 0.025 OH Pekerja 82,000.00

L.02 0.25 OH Tukang Kayu 90,000.00

L.03 0.025 OH Kepala Tukang 95,000.00

L.04 0.00130 OH Mandor 95,000.00

B Bahan

1 Buah Kunci Lemari 13,000.00


C PERALATAN

D Jumlah A + B + C

E Overhead & Profit (contoh 10%) 10%

F Harga Satuan Pekerjaan (D+E)


16 A.4.6.2.16 1 m2 Pemasangan 1 m2 Kaca Polos Tebal 3 mm

A Tenaga

L.01 0.015 OH Pekerja 82,000.00

L.02 0.15 OH Tukang Kayu 90,000.00

L.03 0.015 OH Kepala Tukang 95,000.00

L.04 0.00075 OH Mandor 95,000.00

B Bahan

1.1 m2 Kaca tebal 3mm 89,000.00

C PERALATAN

D Jumlah A + B + C

E Overhead & Profit (contoh 10%) 10%

F Harga Satuan Pekerjaan (D+E)

17 A.4.6.2.17 1 m2 Pemasangan 1 m2 Kaca Polos Tebal 5 mm

A Tenaga

L.01 0.015 OH Pekerja 82,000.00

L.02 0.15 OH Tukang Kayu 90,000.00

L.03 0.015 OH Kepala Tukang 95,000.00

L.04 0.00075 OH Mandor 95,000.00

B Bahan

1.1 m2 Kaca tebal 5mm 118,000.00

C PERALATAN

D Jumlah A + B + C

E Overhead & Profit (contoh 10%) 10%

F Harga Satuan Pekerjaan (D+E)

18 A.4.6.2.18 1 m2 Pemasangan 1 m2 KacaPolos Tebal 8 mm

A Tenaga

L.01 0.017 OH Pekerja 82,000.00

L.02 0.17 OH Tukang Kayu 90,000.00

L.03 0.017 OH Kepala Tukang 95,000.00

L.04 0.00090 OH Mandor 95,000.00

B Bahan

1.1 m2 Kaca Tebal 8 mm 277,500.00

C PERALATAN

D Jumlah A + B + C

E Overhead & Profit (contoh 10%) 10%

F Harga Satuan Pekerjaan (D+E)

19 A.4.6.2.19 1 m2 Pemasangan 1 m2 Kaca Rayben Tebal 12 mm

A Tenaga

L.01 0.025 OH Pekerja 82,000.00

L.02 0.25 OH Tukang Kayu 90,000.00

L.03 0.025 OH Kepala Tukang 95,000.00

L.04 0.13000 OH Mandor 95,000.00

B Bahan

1.1 m2 Kaca Rayben Tebal 12 mm 344,100.00


C PERALATAN

D Jumlah A + B + C

E Overhead & Profit (contoh 10%) 10%

F Harga Satuan Pekerjaan (D+E)

20 A.4.6.2.20 1 m2 Pemasangan 1 m2 Kaca Cermin Tebal 5mm

A Tenaga

L.01 0.015 OH Pekerja 82,000.00

L.02 0.15 OH Tukang Kayu 90,000.00

L.03 0.015 OH Kepala Tukang 95,000.00

L.04 0.00075 OH Mandor 95,000.00

B Bahan

1.1 m2 Kaca Cermin 175,000.00

C PERALATAN

D Jumlah A + B + C

E Overhead & Profit (contoh 10%) 10%

F Harga Satuan Pekerjaan (D+E)


JUMLAH

Rp

258,395.50

64,905.00

4,920.00

54,000.00

5,700.00

285.00

170,000.00

170,000.00

234,905.00

23,490.50

258,395.50

211,139.50

47,245.00

820.00

45,000.00

950.00

475.00

144,700.00

144,700.00

191,945.00

19,194.50

211,139.50

182,954.75

46,122.50

410.00

45,000.00

475.00

237.50

120,200.00

120,200.00

166,322.50

16,632.25

182,954.75

209,904.75

46,122.50

410.00

45,000.00

475.00

237.50
144,700.00

144,700.00

190,822.50

19,082.25

209,904.75
29,004.25

16,867.50

1,230.00

13,500.00

1,425.00

712.50

9,500.00

9,500.00

26,367.50

2,636.75

29,004.25

31,069.50

11,245.00

820.00

9,000.00

950.00

475.00

17,000.00

17,000.00

28,245.00

2,824.50

31,069.50

52,082.25

28,147.50

8,200.00

18,000.00

1,900.00

47.50

19,200.00

19,200.00

47,347.50

4,734.75

52,082.25
85,761.50

16,915.00

1,230.00

13,500.00

1,425.00

760.00

61,050.00

61,050.00

77,965.00

7,796.50

85,761.50

36,206.50

16,915.00

1,230.00

13,500.00

1,425.00

760.00

16,000.00

16,000.00

32,915.00

3,291.50

36,206.50

831,916.25

54,087.50

4,100.00

45,000.00

4,750.00

237.50

702,200.00

702,200.00

756,287.50

75,628.75

831,916.25

157,668.50

21,635.00

1,640.00

18,000.00

1,900.00

95.00

121,700.00

121,700.00
143,335.00

14,333.50

157,668.50
90,806.10

54,135.00

4,100.00

45,000.00

4,750.00

285.00

28,416.00

28,416.00

82,551.00

8,255.10

90,806.10

97,919.25

10,817.50

820.00

9,000.00

950.00

47.50

78,200.00

78,200.00

89,017.50

8,901.75

97,919.25

343,095.50

64,905.00

4,920.00

54,000.00

5,700.00

285.00

247,000.00

247,000.00

311,905.00

31,190.50

343,095.50

44,053.35

27,048.50

2,050.00

22,500.00

2,375.00

123.50

13,000.00

13,000.00
40,048.50

4,004.85

44,053.35
125,538.88

16,226.25

1,230.00

13,500.00

1,425.00

71.25

97,900.00

97,900.00

114,126.25

11,412.63

125,538.88

160,628.88

16,226.25

1,230.00

13,500.00

1,425.00

71.25

129,800.00

129,800.00

146,026.25

14,602.63

160,628.88

356,008.95

18,394.50

1,394.00

15,300.00

1,615.00

85.50

305,250.00

305,250.00

323,644.50

32,364.45

356,008.95

459,563.50

39,275.00

2,050.00

22,500.00

2,375.00

12,350.00

378,510.00

378,510.00
417,785.00

41,778.50

459,563.50

229,598.88

16,226.25

1,230.00

13,500.00

1,425.00

71.25

192,500.00

192,500.00

208,726.25

20,872.63

229,598.88
HARGA
JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN BAHAN/UPAH
Rp Rp

DIVISI IV A.4.7.1 HARGA SATUAN PEKERJAAN PENGECATAN

Pengikisan / pengerokan 1 m2 Permukaan Cat


1 A.4.7.1.1 1 m2 15,218.50
Tembok Lama

A Tenaga 12,585.00

L.01 0.15 OH Pekerja 82,000.00 12,300.00

L.04 0.0030 OH Mandor 95,000.00 285.00

B Bahan 1,250.00

0.05 Kg Soda Api 25,000.00 1,250.00

C PERALATAN

D Jumlah A + B + C 13,835.00

E Overhead & Profit (contoh 10%) 10% 1,383.50

F Harga Satuan Pekerjaan (D+E) 15,218.50

Pencucian 1 m2 Bidang Permukaan Tembok yang


2 A.4.7.1.2 1 m2 15,862.00
Pernah dicat

A Tenaga 12,585.00

L.01 0.15 OH Pekerja 82,000.00 12,300.00

L.04 0.0030 OH Mandor 95,000.00 285.00

B Bahan 1,835.00

0.05 Kg Sabun 36,700.00 1,835.00

C PERALATAN

D Jumlah A + B + C 14,420.00

E Overhead & Profit (contoh 10%) 10% 1,442.00

F Harga Satuan Pekerjaan (D+E) 15,862.00

Pengerokan 1 m2 Karat Cat Lama permukaan Baja


3 A.4.7.1.3 1 m2 16,384.50
dg cara manual

A Tenaga 13,060.00

L.01 0.15 OH Pekerja 82,000.00 12,300.00

L.04 0.0080 OH Mandor 95,000.00 760.00

B Bahan 1,835.00

0.05 Kg Sabun 36,700.00 1,835.00

C PERALATAN

D Jumlah A + B + C 14,895.00

E Overhead & Profit (contoh 10%) 10% 1,489.50

F Harga Satuan Pekerjaan (D+E) 16,384.50


Pengecatan Bidang Kayu Baru (1 lp Plamuur, 1 lp
4 A.4.7.1.4 1 m2 45,224.30
Cat dasar, 2 Lp Cat Penutup)

A Tenaga 7,405.00

L.01 0.070 OH Pekerja 82,000.00 5,740.00

L.02 0.009 OH Tukang Cat 90,000.00 810.00

L.03 0.006 OH Kepala Tukang 95,000.00 570.00

L.04 0.003 OH Mandor 95,000.00 285.00

B Bahan 33,708.00

0.2000 kg Cat Menie 14,000.00 2,800.00

0.1500 kg Plamuur 38,000.00 5,700.00

0.1700 kg Cat Dasar 51,000.00 8,670.00

0.2600 kg Cat Penutup 46,200.00 12,012.00

0.0100 bh Kuas 18,000.00 180.00

0.0300 kg Pengencer 28,200.00 846.00

0.2000 lbr Amplas 17,500.00 3,500.00

C PERALATAN

D Jumlah A + B + C 41,113.00

E Overhead & Profit (contoh 10%) 10% 4,111.30

F Harga Satuan Pekerjaan (D+E) 45,224.30

Pengecatan Bidang Kayu Baru (1 lp Plamuur, 1 lp


5 A.4.7.1.5 1 m2 59,093.10
Cat dasar, 3 Lp Cat Penutup)

A Tenaga 15,855.00

L.01 0.070 OH Pekerja 82,000.00 5,740.00

L.02 0.105 OH Tukang Cat 90,000.00 9,450.00

L.03 0.004 OH Kepala Tukang 95,000.00 380.00

L.04 0.003 OH Mandor 95,000.00 285.00

B Bahan 37,866.00

0.2000 kg Cat Menie 14,000.00 2,800.00

0.1500 kg Plamuur 38,000.00 5,700.00

0.1700 kg Cat Dasar 51,000.00 8,670.00

0.3500 kg Cat Penutup 46,200.00 16,170.00

0.0100 bh Kuas 18,000.00 180.00

0.0300 kg Pengencer 28,200.00 846.00

0.2000 lbr Amplas 17,500.00 3,500.00

C PERALATAN

D Jumlah A + B + C 53,721.00

E Overhead & Profit (contoh 10%) 10% 5,372.10

F Harga Satuan Pekerjaan (D+E) 59,093.10


6 A.4.7.1.6 1 m2 Pelaburan Bidang Kayu dg Teak Oil 35,354.00

A Tenaga 15,220.00

L.01 0.04 OH Pekerja 82,000.00 3,280.00

L.02 0.063 OH Tukang Cat 90,000.00 5,670.00

L.03 0.063 OH Kepala Tukang 95,000.00 5,985.00

L.04 0.0030 OH Mandor 95,000.00 285.00

B Bahan 16,920.00

0.36 Ltr Teak Oil 47,000.00 16,920.00

C PERALATAN

D Jumlah A + B + C 32,140.00

E Overhead & Profit (contoh 10%) 10% 3,214.00

F Harga Satuan Pekerjaan (D+E) 35,354.00

7 A.4.7.1.7 1 m2 Pelaburan 1 m2 Bidang Kayu dg Politur 88,504.90

A Tenaga 10,485.00

L.01 0.04 OH Pekerja 82,000.00 3,280.00

L.02 0.06 OH Tukang Cat 90,000.00 5,400.00

L.03 0.016 OH Kepala Tukang 95,000.00 1,520.00

L.04 0.0030 OH Mandor 95,000.00 285.00

B Bahan 69,974.00

0.15 Ltr Politur 67,000.00 10,050.00

0.372 Ltr Politur Jadi 67,000.00 24,924.00

2 Lbr Ampelas 17,500.00 35,000.00

C PERALATAN

D Jumlah A + B + C 80,459.00

E Overhead & Profit (contoh 10%) 10% 8,045.90

F Harga Satuan Pekerjaan (D+E) 88,504.90

8 A.4.7.1.8 1 m2 Pelaburan 1 m2 Bidang Kayu dg Cat Residu & Ter 10,003.13

A Tenaga 8,770.00

L.01 0.1 OH Pekerja 82,000.00 8,200.00

L.04 0.006 OH Mandor 95,000.00 570.00

B Bahan 323.75

0.35 Ltr Residu atau Ter 925.00 323.75

C PERALATAN

D Jumlah A + B + C 9,093.75

E Overhead & Profit (contoh 10%) 10% 909.38

F Harga Satuan Pekerjaan (D+E) 10,003.13


9 A.4.7.1.9 1 m2 Pelaburan 1 m2 Bidang Kayu dg Vernis 49,472.50

A Tenaga 29,325.00

L.01 0.16 OH Pekerja 82,000.00 13,120.00

L.02 0.16 OH Tukang Cat 90,000.00 14,400.00

L.03 0.016 OH Kepala Tukang 95,000.00 1,520.00

L.04 0.0030 OH Mandor 95,000.00 285.00

B Bahan 15,650.00

0.15 Ltr Vernis 80,000.00 12,000.00

0.05 Ltr Dempul 38,000.00 1,900.00

0.1 Lbr Ampelas 17,500.00 1,750.00

C PERALATAN

D Jumlah A + B + C 44,975.00

E Overhead & Profit (contoh 10%) 10% 4,497.50

F Harga Satuan Pekerjaan (D+E) 49,472.50

Pengecat 1 m2 Tembok Baru (1lap.Plamir, 1lap Cat


10 A.4.7.1.10 1 m2 28,263.16
Dasar 2 Lap.Cat Penutup) Interior

A Tenaga 8,193.50

L.01 0.02 OH Pekerja 82,000.00 1,640.00

L.02 0.063 OH Tukang Cat 90,000.00 5,670.00

L.03 0.0063 OH Kepala Tukang 95,000.00 598.50

L.04 0.0030 OH Mandor 95,000.00 285.00

B Bahan 17,500.28

0.1 Kg Plamir 38,000.00 3,800.00

0.1 Kg Cat Dasar 51,000.00 5,100.00

0.26 Kg Cat Penutup 2 kali 33,078.00 8,600.28

C PERALATAN

D Jumlah A + B + C 25,693.78

E Overhead & Profit (contoh 10%) 10% 2,569.38

F Harga Satuan Pekerjaan (D+E) 28,263.16

Pengecat 1 m2 Tembok Baru (1lap Cat Dasar 2


11 A.4.7.1.11 1 m2 30,495.85
Lap.Cat Penutup) - exterior

A Tenaga 8,193.50

L.01 0.02 OH Pekerja 82,000.00 1,640.00

L.02 0.063 OH Tukang Cat 90,000.00 5,670.00

L.03 0.0063 OH Kepala Tukang 95,000.00 598.50

L.04 0.0030 OH Mandor 95,000.00 285.00

B Bahan 19,530.00

0.1 Kg Cat Dasar (cat tembok exterior) 51,000.00 5,100.00

0.26 Kg Cat Penutup 2 kali (cat tembok exterior) 55,500.00 14,430.00

C PERALATAN

D Jumlah A + B + C 27,723.50

E Overhead & Profit (contoh 10%) 10% 2,772.35

F Harga Satuan Pekerjaan (D+E) 30,495.85

Pengecatan 1 m2 Tembok Lama (1lap. Cat dasar,


12 A.4.7.1.12 1 m2 20,717.44
2lap Cat Penutup) interior

A Tenaga 6,760.00

L.01 0.028 OH Pekerja 82,000.00 2,296.00


L.02 0.042 OH Tukang Cat 90,000.00 3,780.00

L.03 0.0042 OH Kepala Tukang 95,000.00 399.00

L.04 0.0030 OH Mandor 95,000.00 285.00

B Bahan 12,074.04

0.12 Kg Cat Dasar 51,000.00 6,120.00

0.18 Kg Cat Penutup 2 kali 33,078.00 5,954.04

C PERALATAN

D Jumlah A + B + C 18,834.04

E Overhead & Profit (contoh 10%) 10% 1,883.40

F Harga Satuan Pekerjaan (D+E) 20,717.44

Pengecatan 1 m2 Tembok Lama (1lap.cat dasar,


13 A.4.7.1.13 1 m2 25,157.00
2lap Cat Penutup) - exterior
A Tenaga 6,760.00

L.01 0.028 OH Pekerja 82,000.00 2,296.00

L.02 0.042 OH Tukang Cat 90,000.00 3,780.00

L.03 0.0042 OH Kepala Tukang 95,000.00 399.00

L.04 0.0030 OH Mandor 95,000.00 285.00

B Bahan 16,110.00

0.12 Kg Cat Dasar (cat tembok exterior) 51,000.00 6,120.00

0.18 Kg Cat Penutup 2 kali (cat tembok exterior) 55,500.00 9,990.00

C PERALATAN

D Jumlah A + B + C 22,870.00

E Overhead & Profit (contoh 10%) 10% 2,287.00

F Harga Satuan Pekerjaan (D+E) 25,157.00


14 A.4.7.1.14 1 m2 Pelaburan 1 m2 Tembok dengan Kalkarium 8,239.00

A Tenaga 6,760.00

L.01 0.028 OH Pekerja 82,000.00 2,296.00

L.02 0.042 OH Tukang Cat 90,000.00 3,780.00

L.03 0.0042 OH Kepala Tukang 95,000.00 399.00

L.04 0.0030 OH Mandor 95,000.00 285.00

B Bahan 730.00

0.1 Kg Kalkarium 7,300.00 730.00

C PERALATAN

D Jumlah A + B + C 7,490.00

E Overhead & Profit (contoh 10%) 10% 749.00

F Harga Satuan Pekerjaan (D+E) 8,239.00

15 A.4.7.1.15 1 m2 Pelaburan 1 m2 Tembok dengan Kapur Sirih 17,244.70

A Tenaga 12,637.00

L.01 0.150 OH Pekerja 82,000.00 12,300.00

L.02 0.001 OH Tukang Cat 90,000.00 90.00

L.03 0.0001 OH Kepala Tukang 95,000.00 9.50

L.04 0.0025 OH Mandor 95,000.00 237.50

B Bahan 3,040.00

0.15 Kg Kapur Sirih 3,600.00 540.00

0.1 lbr Amplas 17,500.00 1,750.00

0.25 ikat Alang-alang 3,000.00 750.00

C PERALATAN

D Jumlah A + B + C 15,677.00

E Overhead & Profit (contoh 10%) 10% 1,567.70

F Harga Satuan Pekerjaan (D+E) 17,244.70

16 A.4.7.1.16 1 m2 Pelaburan 1 m2 Tembok lama dengan Kapur 10,279.50

A Tenaga 4,015.00

L.01 0.040 OH Pekerja 82,000.00 3,280.00

L.02 0.005 OH Tukang Cat 90,000.00 450.00

L.03 0.0005 OH Kepala Tukang 95,000.00 47.50

L.04 0.0025 OH Mandor 95,000.00 237.50

B Bahan 5,330.00

0.30 Kg Kapur Sirih 3,600.00 1,080.00

0.2 lbr Amplas 17,500.00 3,500.00

0.25 ikat Alang-alang 3,000.00 750.00

C PERALATAN

D Jumlah A + B + C 9,345.00

E Overhead & Profit (contoh 10%) 10% 934.50

F Harga Satuan Pekerjaan (D+E) 10,279.50


17 A.4.7.1.17 1 m2 Pemasangan Wallpaper 140,885.25

A Tenaga 21,777.50

L.01 0.020 OH Pekerja 82,000.00 1,640.00

L.02 0.200 OH Tukang Cat 90,000.00 18,000.00

L.03 0.0200 OH Kepala Tukang 95,000.00 1,900.00

L.04 0.0025 OH Mandor 95,000.00 237.50

B Bahan 106,300.00

1.20 m2 WallPaper 84,000.00 100,800.00

0.2 kg Lem 27,500.00 5,500.00

C PERALATAN

D Jumlah A + B + C 128,077.50

E Overhead & Profit (contoh 10%) 10% 12,807.75

F Harga Satuan Pekerjaan (D+E) 140,885.25

Pengecatan 1 m2 Permukaan Baja dg Meni Besi &


18 A.4.7.1.18 1 m2 56,951.29
Perancah

A Tenaga 41,462.50

L.01 0.25 OH Pekerja 82,000.00 20,500.00

L.02 0.225 OH Tukang Cat 90,000.00 20,250.00

L.04 0.0075 OH Mandor 95,000.00 712.50

B Bahan 10,311.40

0.1 Kg Meni Besi 40,200.00 4,020.00

0.01 Kg Perekat / Lem 27,500.00 275.00

0.002 m3 Perancah Kayu 3,008,200.00 6,016.40

C PERALATAN

D Jumlah A + B + C 51,773.90

E Overhead & Profit (contoh 10%) 10% 5,177.39

F Harga Satuan Pekerjaan (D+E) 56,951.29

Pengecatan 1 m2 dengan cat kedap air ( 2 kali


19 A.4.7.1.19 1 m2 137,659.50
lapis)

A Tenaga 15,475.00

L.01 0.07 OH Pekerja 82,000.00 5,740.00

L.02 0.105 OH Tukang Cat 90,000.00 9,450.00

L.03 0.004 OH Kepala Tukang 95,000.00

L.04 0.0030 OH Mandor 95,000.00 285.00

B Bahan 109,670.00

1.0 Kg Cat kedap air (water base) 105,450.00 105,450.00

0.04 buh Kuas 3" 18,000.00 720.00

0.200 m Amplas 17,500.00 3,500.00

C PERALATAN

D Jumlah A + B + C 125,145.00

E Overhead & Profit (contoh 10%) 10% 12,514.50

F Harga Satuan Pekerjaan (D+E) 137,659.50


HARGA
JUMLAH
BAHAN/UPAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN
Rp Rp

DIVISI V A.5.1.1 HARGA SATUAN PEKERJAAN SANITASI DALAM GEDUNG

1 A.5.1.1.1 1 Unit Pemasangan 1 Buah Closet Duduk/MoNoblock 2,178,797.50


A Tenaga 384,895.00
L.01 3.3 OH Pekerja 82,000.00 270,600.00
L.02 1.1 OH Tukang Batu 90,000.00 99,000.00
L.03 0.001 OH Kepala Tukang 95,000.00 95.00
L.04 0.16 OH Mandor 95,000.00 15,200.00
Buah Bahan 1,595,830.00
1 Buah Kloset Duduk / Monoblok 1,505,500.00 1,505,500.00
0.06 Kelengkapan 6% dari harga Kloset 1,505,500.00 90,330.00
C PERALATAN
D Jumlah A + B + C 1,980,725.00
E Overhead & Profit (contoh 10%) 10% 198,072.50
F Harga Satuan Pekerjaan (D+E) 2,178,797.50
Overhead & Profit (contoh 10%)
2 A.5.1.1.2 1 Unit Pemasangan 1 Buah Closet Jongkok Porselen 631,345.00
A Tenaga 374,700.00
L.01 1 OH Pekerja 82,000.00 82,000.00
L.02 1.5 OH Tukang Batu 90,000.00 135,000.00
L.03 1.5 OH Kepala Tukang 95,000.00 142,500.00
L.04 0.16 OH Mandor 95,000.00 15,200.00
B Bahan 199,250.00
1 Buah Kloset Jongkok 187,000.00 187,000.00
6 Kg Portland Semen 1,520.00 9,120.00
0.01 m3 Pasir Pasang 313,000.00 3,130.00
C PERALATAN
D Jumlah A + B + C 573,950.00
E Overhead & Profit (contoh 10%) 10% 57,395.00
F Harga Satuan Pekerjaan (D+E) 631,345.00

3 A.5.1.1.4 1 Unit Pemasangan 1 Buah Urinoir 370,150.00


A Tenaga 191,000.00
L.01 1 OH Pekerja 82,000.00 82,000.00
L.02 1 OH Tukang Batu 90,000.00 90,000.00
L.03 0.1 OH Kepala Tukang 95,000.00 9,500.00
L.04 0.1 OH Mandor 95,000.00 9,500.00
B Bahan 145,500.00
1 Buah Urinoir 102,500.00 102,500.00
0.3 - Perlengkapan 30% Harga Urinoir 102,500.00 30,750.00
6 Kg Portland Semen 1,520.00 9,120.00
0.01 m3 Pasir Pasang 313,000.00 3,130.00
C PERALATAN
D Jumlah A + B + C 336,500.00
E Overhead & Profit (contoh 10%) 10% 33,650.00
F Harga Satuan Pekerjaan (D+E) 370,150.00
4 A.5.1.1.5 1 Unit Pemasangan 1 Buah Wastafel 792,110.00
A Tenaga 135,200.00
L.01 1.2 OH Pekerja 82,000.00 98,400.00
L.02 0.145 OH Tukang Batu 90,000.00 13,050.00
L.03 0.15 OH Kepala Tukang 95,000.00 14,250.00
L.04 0.1 OH Mandor 95,000.00 9,500.00
B Bahan 584,900.00
1 Buah Wastafel 440,500.00 440,500.00
0.3 - Perlengkapan 30% Harga Wastafel 440,500.00 132,150.00
6 Kg Portland Semen 1,520.00 9,120.00
0.01 m3 Pasir Pasang 313,000.00 3,130.00
C PERALATAN
D Jumlah A + B + C 720,100.00
E Overhead & Profit (contoh 10%) 10% 72,010.00
F Harga Satuan Pekerjaan (D+E) 792,110.00

5 A.5.1.1.6 1 Unit Pemasangan 1 Buah Bak Mandi Teraso Volume 0.30 m3 1,298,550.00

A Tenaga 81,060.00
L.01 0.075 OH Pekerja 82,000.00 6,150.00
L.02 0.75 OH Tukang Batu 90,000.00 67,500.00
L.03 0.075 OH Kepala Tukang 95,000.00 7,125.00
L.04 0.003 OH Mandor 95,000.00 285.00

B Bahan 1,099,440.00
1 Buah Bak Teraso 916,200.00 916,200.00
0.2 ls Perlengkapan 916,200.00 183,240.00
C PERALATAN
D Jumlah A + B + C 1,180,500.00
E Overhead & Profit (contoh 10%) 10% 118,050.00
F Harga Satuan Pekerjaan (D+E) 1,298,550.00

6 A.5.1.1.7 1 Unit Pemasangan 1 Buah Bak Fibreglass Volume 0.3 m3 1,226,863.00


A Tenaga 741,250.00
L.01 3 OH Pekerja 82,000.00 246,000.00
L.02 4.5 OH Tukang Batu 90,000.00 405,000.00
L.03 0.05 OH Kepala Tukang 95,000.00 4,750.00
L.04 0.9 OH Mandor 95,000.00 85,500.00
B Tukang Batu 374,080.00
1 Buah Bak Fibreglass 334,000.00 334,000.00
0.12 ls Perlengkapan 334,000.00 40,080.00
C PERALATAN
D Jumlah A + B + C 1,115,330.00
E Overhead & Profit (contoh 10%) 10% 111,533.00
F Harga Satuan Pekerjaan (D+E) 1,226,863.00
7 A.5.1.1.8 1 Unit Pemasangan 1buah Bak Mandi Pasangan Bata Volume 0.30 m3 1,832,510.12
A Tenaga 793,350.00
L.01 6.00 OH Pekerja 82,000.00 492,000.00
L.02 3.00 OH Tukang Batu 90,000.00 270,000.00
L.03 0.30 OH Kepala Tukang 95,000.00 28,500.00
L.04 0.03 OH Mandor 95,000.00 2,850.00
B Bahan 872,568.29
150.0 bh Batu Bata 900.00 135,000.00
120 Kg Portland Semen 0.11 1,520.00 182,400.00
0.3 m3 Pasir Pasang 0.0121 313,000.00 93,900.00
360 buah Porselen 11 x 11 cm 82.644628 1,014.63 365,268.29
6 Kg Semen Nat (warna) 16,000.00 96,000.00
C PERALATAN
D Jumlah A + B + C 1,665,918.29
E Overhead & Profit (contoh 10%) 10% 166,591.83
F Harga Satuan Pekerjaan (D+E) 1,832,510.12

8 A.5.1.1.11 1 Unit Pemasangan Bak Beton Bertulang Vol. 1 m3 7,784,604.05


A Tenaga 698,460.00
L.01 3.50 OH Pekerja 82,000.00 287,000.00
L.02 4.50 OH Tukang Batu 90,000.00 405,000.00
L.03 0.05 OH Kepala Tukang 95,000.00 4,750.00
L.04 0.018 OH Mandor 95,000.00 1,710.00
B Bahan 1,407,913.01 6,378,452.77
0.9 m3 Beton K.150 1,233,076.43 1,109,768.79
180 Kg Baja Tulangan 0.11 17,000.00 3,060,000.00
8.0 m2 Kayu Bekisting 0.05 0.0121 156,200.00 1,249,600.00
500 buah Porselen 11 x 11 cm 20 82.644628 1,636.59 818,292.68
10 % Perlengkapan 1,407,913.01 140,791.30
C PERALATAN
D Jumlah A + B + C 7,076,912.77
E Overhead & Profit (contoh 10%) 10% 707,691.28
F Harga Satuan Pekerjaan (D+E) 7,784,604.05

9 A.5.1.1.12 1 buah Pemasangan Bak Cuci Piring Stainless stell 328,828.50


A Tenaga 33,735.00
L.01 0.030 OH Pekerja 82,000.00 2,460.00
L.02 0.300 OH Tukang Batu 90,000.00 27,000.00
L.03 0.030 OH Kepala Tukang 95,000.00 2,850.00
L.04 0.015 OH Mandor 95,000.00 1,425.00
B Bahan 265,200.00
1 unit Bak Cuci Piring 208,200.00 208,200.00
1 bh Water drain 57,000.00 57,000.00
C PERALATAN
D Jumlah A + B + C 298,935.00
E Overhead & Profit (contoh 10%) 10% 29,893.50
F Harga Satuan Pekerjaan (D+E) 328,828.50
10 A.5.1.1.14 1 buah Pemasangan Floor Drain 56,369.50
A Tenaga 11,245.00
L.01 0.010 OH Pekerja 82,000.00 820.00
L.02 0.100 OH Tukang Batu 90,000.00 9,000.00
L.03 0.010 OH Kepala Tukang 95,000.00 950.00
L.04 0.005 OH Mandor 95,000.00 475.00
B Bahan 40,000.00
1 bh Floor Drain 40,000.00 40,000.00

C PERALATAN
D Jumlah A + B + C 51,245.00
E Overhead & Profit (contoh 10%) 10% 5,124.50
F Harga Satuan Pekerjaan (D+E) 56,369.50

Pemasangan 1 buah Bak Kontrol Pasangan Bata


11 A.5.1.1.16 1 bh 487,080.00
30x30cm Tinggi 35cm dengan Tutup Beton

A Tenaga 249,805.00
L.01 2.160 OH Pekerja 82,000.00 177,120.00
L.02 0.720 OH Tukang Batu 90,000.00 64,800.00
L.03 0.072 OH Kepala Tukang 95,000.00 6,840.00
L.04 0.011 OH Mandor 95,000.00 1,045.00
B Bahan 192,995.00
40.00 bh Batu Bata 900.00 36,000.00
44.00 kg Semen Portland 1,520.00 66,880.00
0.07 m3 Pasir Pasang 313,000.00 21,910.00
0.06 m3 Pasir Beton 376,000.00 22,560.00
0.07 m3 Kerikil 263,500.00 18,445.00
1.60 kg Baja Tulangan 17,000.00 27,200.00
C PERALATAN
D Jumlah A + B + C 442,800.00
E Overhead & Profit (contoh 10%) 10% 44,280.00
F Harga Satuan Pekerjaan (D+E) 487,080.00

Pemasangan 1 buah Bak Kontrol Pasangan Bata


12 A.5.1.1.17 1 bh 721,055.50
45cm x 45cm tinggi 50cm dengan Tutup Beton
A Tenaga 368,465.00
L.01 3.200 OH Pekerja 82,000.00 262,400.00
L.02 1.150 OH Tukang Batu 90,000.00 103,500.00
L.03 0.011 OH Kepala Tukang 95,000.00 1,045.00
L.04 0.016 OH Mandor 95,000.00 1,520.00
B Bahan 287,040.00
70.00 bh Batu Bata 900.00 63,000.00
77.00 kg Semen Portland 1,520.00 117,040.00
0.13 m3 Pasir Pasang 313,000.00 40,690.00
0.09 m3 Pasir Beton 376,000.00 33,840.00
0.02 m3 Kerikil 263,500.00 5,270.00
1.60 kg Baja Tulangan 17,000.00 27,200.00
C PERALATAN
D Jumlah A + B + C 655,505.00
E Overhead & Profit (contoh 10%) 10% 65,550.50
F Harga Satuan Pekerjaan (D+E) 721,055.50
Pemasangan 1 buah Bak Kontrol Pasangan Bata 60cm
13 A.5.1.1.18 1 bh 921,367.70
x 60cm Tinggi 65cm dengan Tutup Beton
A Tenaga 368,465.00
L.01 3.200 OH Pekerja 82,000.00 262,400.00
L.02 1.150 OH Tukang Batu 90,000.00 103,500.00
L.03 0.011 OH Kepala Tukang 95,000.00 1,045.00
L.04 0.016 OH Mandor 95,000.00 1,520.00
B Bahan 469,142.00
123.00 bh Batu Bata 900.00 110,700.00
114.00 kg Semen Portland 1,520.00 173,280.00
0.18 m3 Pasir Pasang 313,000.00 57,592.00
0.12 m3 Pasir Beton 376,000.00 45,120.00
4.85 kg Baja Tulangan 17,000.00 82,450.00
C PERALATAN
D Jumlah A + B + C 837,607.00
E Overhead & Profit (contoh 10%) 10% 83,760.70
F Harga Satuan Pekerjaan (D+E) 921,367.70

14 A.5.1.1.19 1 m' Pemasangan 1 m’ Pipa Galvanis Diameter ½” 49,653.63


A Tenaga 15,948.00
L.01 0.054 OH Pekerja 82,000.00 4,428.00
L.02 0.090 OH Tukang Batu 90,000.00 8,100.00
L.03 0.009 OH Kepala Tukang 95,000.00 855.00
L.04 0.027 OH Mandor 95,000.00 2,565.00
B Bahan 29,191.67
1.20 m' Pipa Galvanis Ø ½" 18,833.33 22,600.00
0.35 Ls Perlengkapan 35% x pipa 18,833.33 6,591.67
C PERALATAN
D Jumlah A + B + C 45,139.67
E Overhead & Profit (contoh 10%) 10% 4,513.97
F Harga Satuan Pekerjaan (D+E) 49,653.63

15 A.5.1.1.20 1 bh Pemasangan 1 m’ Pipa Galvanis Diameter ¾ ” 79,328.43


A Tenaga 41,095.00
L.01 0.010 OH Pekerja 82,000.00 820.00
L.02 0.400 OH Tukang Batu 90,000.00 36,000.00
L.03 0.040 OH Kepala Tukang 95,000.00 3,800.00
L.04 0.005 OH Mandor 95,000.00 475.00
B Bahan 31,021.75
1.00 bh Kran Air 31,000.00 31,000.00
0.0025 bh Sealtape 8,700.00 21.75
C PERALATAN
D Jumlah A + B + C 72,116.75
E Overhead & Profit (contoh 10%) 10% 7,211.68
F Harga Satuan Pekerjaan (D+E) 79,328.43
16 A.5.1.1.20.a 1 m' Pemasangan Pipa Galvanis Ø ¾" 56,189.47
A Tenaga 15,948.00
L.01 0.054 OH Pekerja 82,000.00 4,428.00
L.02 0.090 OH Tukang Batu 90,000.00 8,100.00
L.03 0.009 OH Kepala Tukang 95,000.00 855.00
L.04 0.027 OH Mandor 95,000.00 2,565.00
B Bahan 35,133.33
1.20 m' Pipa Galvanis Ø ¾" 22,666.67 27,200.00
0.35 Ls Perlengkapan 35% x pipa 22,666.67 7,933.33
C PERALATAN
D Jumlah A + B + C 51,081.33
E Overhead & Profit (contoh 10%) 10% 5,108.13
F Harga Satuan Pekerjaan (D+E) 56,189.47

17 A.5.1.1.21 1 m' Pemasangan 1 m’ Pipa Galvanis Diameter 1” 71,534.47


A Tenaga 15,948.00
L.01 0.054 OH Pekerja 82,000.00 4,428.00
L.02 0.090 OH Tukang Batu 90,000.00 8,100.00
L.03 0.009 OH Kepala Tukang 95,000.00 855.00
L.04 0.027 OH Mandor 95,000.00 2,565.00
B Bahan 49,083.33
1.20 m' Pipa Galvanis Ø 1" 31,666.67 38,000.00
0.35 Ls Perlengkapan 35% x pipa 31,666.67 11,083.33
C PERALATAN
D Jumlah A + B + C 65,031.33
E Overhead & Profit (contoh 10%) 10% 6,503.13
F Harga Satuan Pekerjaan (D+E) 71,534.47

18 A.5.1.1.22 1 m' Pemasangan 1 m’ Pipa Galvanis Diameter 1 ½” 108,110.93


A Tenaga 27,241.00
L.01 0.108 OH Pekerja 82,000.00 8,856.00
L.02 0.180 OH Tukang Batu 90,000.00 16,200.00
L.03 0.018 OH Kepala Tukang 95,000.00 1,710.00
L.04 0.005 OH Mandor 95,000.00 475.00
B Bahan 71,041.67
1.20 m' Pipa Galvanis Ø 1½" 45,833.33 55,000.00
0.35 Ls Perlengkapan 35% x pipa 45,833.33 16,041.67
C PERALATAN
D Jumlah A + B + C 98,282.67
E Overhead & Profit (contoh 10%) 10% 9,828.27
F Harga Satuan Pekerjaan (D+E) 108,110.93
19 A.5.1.1.23 1 m' Pemasangan 1 m’ Pipa Galvanis Diameter 3” 222,579.50
A Tenaga 34,170.00
L.01 0.135 OH Pekerja 82,000.00 11,070.00
L.02 0.225 OH Tukang Batu 90,000.00 20,250.00
L.03 0.023 OH Kepala Tukang 95,000.00 2,185.00
L.04 0.007 OH Mandor 95,000.00 665.00
B Bahan 168,175.00
1.20 m' Pipa Galvanis Ø 3" 108,500.00 130,200.00
0.35 Ls Perlengkapan 35% x pipa 108,500.00 37,975.00
C PERALATAN
D Jumlah A + B + C 202,345.00
E Overhead & Profit (contoh 10%) 10% 20,234.50
F Harga Satuan Pekerjaan (D+E) 222,579.50

20 A.5.1.1.24 1 m' Pemasangan 1 m’ Pipa Galvanis Diameter 4” 351,875.33


A Tenaga 34,170.00
L.01 0.135 OH Pekerja 82,000.00 11,070.00
L.02 0.225 OH Tukang Batu 90,000.00 20,250.00
L.03 0.023 OH Kepala Tukang 95,000.00 2,185.00
L.04 0.007 OH Mandor 95,000.00 665.00
B Bahan 285,716.67
1.20 m' Pipa Galvanis Ø 4" 184,333.33 221,200.00
0.35 Ls Perlengkapan 35% x pipa 184,333.33 64,516.67
C PERALATAN
D Jumlah A + B + C 319,886.67
E Overhead & Profit (contoh 10%) 10% 31,988.67
F Harga Satuan Pekerjaan (D+E) 351,875.33

21 A.5.1.1.25 1 m' Pemasangan 1 m’ Pipa PVC tipe AW Diameter ½” 21,745.08


A Tenaga 9,112.00
L.01 0.036 OH Pekerja 82,000.00 2,952.00
L.02 0.060 OH Tukang Batu 90,000.00 5,400.00
L.03 0.006 OH Kepala Tukang 95,000.00 570.00
L.04 0.002 OH Mandor 95,000.00 190.00
B Bahan 10,656.25
1.20 m' Pipa PVC Ø ½" 6,875.00 8,250.00
0.35 Ls Perlengkapan 35% x pipa 6,875.00 2,406.25
C PERALATAN
D Jumlah A + B + C 19,768.25
E Overhead & Profit (contoh 10%) 10% 1,976.83
F Harga Satuan Pekerjaan (D+E) 21,745.08
22 A.5.1.1.26 1 m' Pemasangan 1 m’ Pipa PVC tipe AW Diameter ¾ ” 25,027.20
A Tenaga 9,112.00
L.01 0.036 OH Pekerja 82,000.00 2,952.00
L.02 0.060 OH Tukang Batu 90,000.00 5,400.00
L.03 0.006 OH Kepala Tukang 95,000.00 570.00
L.04 0.002 OH Mandor 95,000.00 190.00
B Bahan 13,640.00
1.20 m' Pipa PVC Ø ¾" 8,800.00 10,560.00
0.35 Ls Perlengkapan 35% x pipa 8,800.00 3,080.00
C PERALATAN
D Jumlah A + B + C 22,752.00
E Overhead & Profit (contoh 10%) 10% 2,275.20
F Harga Satuan Pekerjaan (D+E) 25,027.20

23 A.5.1.1.27 1 m' Pemasangan 1 m’ Pipa PVC tipe AW Diameter 1” 33,680.08


A Tenaga 9,112.00
L.01 0.036 OH Pekerja 82,000.00 2,952.00
L.02 0.060 OH Tukang Batu 90,000.00 5,400.00
L.03 0.006 OH Kepala Tukang 95,000.00 570.00
L.04 0.002 OH Mandor 95,000.00 190.00
B Bahan 21,506.25
1.20 m' Pipa PVC Ø 1" 13,875.00 16,650.00
0.35 Ls Perlengkapan 35% x pipa 13,875.00 4,856.25
C PERALATAN
D Jumlah A + B + C 30,618.25
E Overhead & Profit (contoh 10%) 10% 3,061.83
F Harga Satuan Pekerjaan (D+E) 33,680.08

24 A.5.1.1.28 1 m' Pemasangan 1 m’ Pipa PVC tipe AW Diameter 1½” 48,282.30


A Tenaga 13,668.00
L.01 0.054 OH Pekerja 82,000.00 4,428.00
L.02 0.090 OH Tukang Batu 90,000.00 8,100.00
L.03 0.009 OH Kepala Tukang 95,000.00 855.00
L.04 0.003 OH Mandor 95,000.00 285.00
B Bahan 30,225.00
1.20 m' Pipa PVC Ø 1½" 19,500.00 23,400.00
0.35 Ls Perlengkapan 35% x pipa 19,500.00 6,825.00
C PERALATAN
D Jumlah A + B + C 43,893.00
E Overhead & Profit (contoh 10%) 10% 4,389.30
F Harga Satuan Pekerjaan (D+E) 48,282.30
25 A.5.1.1.29 1 m' Pemasangan 1 m’ Pipa PVC tipe AW Diameter 2” 58,086.05
A Tenaga 13,668.00
L.01 0.054 OH Pekerja 82,000.00 4,428.00
L.02 0.090 OH Tukang Batu 90,000.00 8,100.00
L.03 0.009 OH Kepala Tukang 95,000.00 855.00
L.04 0.003 OH Mandor 95,000.00 285.00
B Bahan 39,137.50
1.20 m' Pipa PVC Ø 2" 25,250.00 30,300.00
0.35 Ls Perlengkapan 35% x pipa 25,250.00 8,837.50
C PERALATAN
D Jumlah A + B + C 52,805.50
E Overhead & Profit (contoh 10%) 10% 5,280.55
F Harga Satuan Pekerjaan (D+E) 58,086.05

26 A.5.1.1.30 1 m' Pemasangan 1 m’ Pipa PVC tipe AW Diameter 2½” 86,437.45


A Tenaga 20,454.50
L.01 0.081 OH Pekerja 82,000.00 6,642.00
L.02 0.135 OH Tukang Batu 90,000.00 12,150.00
L.03 0.014 OH Kepala Tukang 95,000.00 1,282.50
L.04 0.004 OH Mandor 95,000.00 380.00
B Bahan 58,125.00
1.20 m' Pipa PVC Ø 2½" 37,500.00 45,000.00
0.35 Ls Perlengkapan 35% x pipa 37,500.00 13,125.00
C PERALATAN
D Jumlah A + B + C 78,579.50
E Overhead & Profit (contoh 10%) 10% 7,857.95
F Harga Satuan Pekerjaan (D+E) 86,437.45

27 A.5.1.1.31 1 m' Pemasangan 1 m’ Pipa PVC tipe AW Diameter 3” 106,897.45


A Tenaga 20,454.50
L.01 0.081 OH Pekerja 82,000.00 6,642.00
L.02 0.135 OH Tukang Batu 90,000.00 12,150.00
L.03 0.0135 OH Kepala Tukang 95,000.00 1,282.50
L.04 0.004 OH Mandor 95,000.00 380.00
B Bahan 76,725.00
1.20 m' Pipa PVC Ø 3" 49,500.00 59,400.00
0.35 Ls Perlengkapan 35% x pipa 49,500.00 17,325.00
C PERALATAN
D Jumlah A + B + C 97,179.50
E Overhead & Profit (contoh 10%) 10% 9,717.95
F Harga Satuan Pekerjaan (D+E) 106,897.45

28 A.5.1.1.32 1 m' Pemasangan 1 m’ Pipa PVC tipe AW Diameter 4” 134,488.20


A Tenaga 9,112.00
L.01 0.036 OH Pekerja 82,000.00 2,952.00
L.02 0.060 OH Tukang Batu 90,000.00 5,400.00
L.03 0.006 OH Kepala Tukang 95,000.00 570.00
L.04 0.002 OH Mandor 95,000.00 190.00
B Bahan 113,150.00
1.20 m' Pipa PVC Ø 4" 73,000.00 87,600.00
0.35 Ls Perlengkapan 35% x pipa 73,000.00 25,550.00
C PERALATAN
D Jumlah A + B + C 122,262.00
E Overhead & Profit (contoh 10%) 10% 12,226.20
F Harga Satuan Pekerjaan (D+E) 134,488.20

28 A.5.1.1.33 1 m' Pemasangan 1 m’ Pipa PVC tipe D Diameter 2” 44,842.46


A Tenaga 13,668.00
L.01 0.054 OH Pekerja 82,000.00 4,428.00
L.02 0.090 OH Tukang Batu 90,000.00 8,100.00
L.03 0.009 OH Kepala Tukang 95,000.00 855.00
L.04 0.003 OH Mandor 95,000.00 285.00
B Bahan 27,097.88
1.20 m' Pipa PVC type D Ø 2" pnjang 4 meter 17,482.50 20,979.00
0.35 Ls Perlengkapan 35% x pipa 17,482.50 6,118.88
C PERALATAN
D Jumlah A + B + C 40,765.88
E Overhead & Profit (contoh 10%) 10% 4,076.59
F Harga Satuan Pekerjaan (D+E) 44,842.46

28 A.5.1.1.34 1 m' Pemasangan 1 m’ Pipa PVC tipe D Diameter 2 ½” 63,189.78


A Tenaga 20,454.50
L.01 0.081 OH Pekerja 82,000.00 6,642.00
L.02 0.135 OH Tukang Batu 90,000.00 12,150.00
L.03 0.014 OH Kepala Tukang 95,000.00 1,282.50
L.04 0.004 OH Mandor 95,000.00 380.00
B Bahan 36,990.75
1.20 m' Pipa PVC type D Ø 2 ½" pnjang 4 meter 23,865.00 28,638.00
0.35 Ls Perlengkapan 35% x pipa 23,865.00 8,352.75
C PERALATAN
D Jumlah A + B + C 57,445.25
E Overhead & Profit (contoh 10%) 10% 5,744.53
F Harga Satuan Pekerjaan (D+E) 63,189.78

28 A.5.1.1.35 1 m' Pemasangan 1 m’ Pipa PVC tipe D Diameter 3” 76,201.06


A Tenaga 20,454.50
L.01 0.081 OH Pekerja 82,000.00 6,642.00
L.02 0.135 OH Tukang Batu 90,000.00 12,150.00
L.03 0.014 OH Kepala Tukang 95,000.00 1,282.50
L.04 0.004 OH Mandor 95,000.00 380.00
B Bahan 48,819.19
1.20 m' Pipa PVC type D Ø 3" pnjang 4 meter 31,496.25 37,795.50
0.35 Ls Perlengkapan 35% x pipa 31,496.25 11,023.69
C PERALATAN
D Jumlah A + B + C 69,273.69
E Overhead & Profit (contoh 10%) 10% 6,927.37
F Harga Satuan Pekerjaan (D+E) 76,201.06

28 A.5.1.1.36 1 m' Pemasangan 1 m’ Pipa PVC tipe D Diameter 4” 106,718.43


A Tenaga 20,454.50
L.01 0.081 OH Pekerja 82,000.00 6,642.00
L.02 0.135 OH Tukang Batu 90,000.00 12,150.00
L.03 0.014 OH Kepala Tukang 95,000.00 1,282.50
L.04 0.004 OH Mandor 95,000.00 380.00
B Bahan 76,562.25
1.20 m' Pipa PVC type D Ø 4" pnjang 4 meter 49,395.00 59,274.00
0.35 Ls Perlengkapan 35% x pipa 49,395.00 17,288.25
C PERALATAN
D Jumlah A + B + C 97,016.75
E Overhead & Profit (contoh 10%) 10% 9,701.68
F Harga Satuan Pekerjaan (D+E) 106,718.43
29 A.5.1.1.37 1 m' Pemasangan 1 m’ Pipa Air Limbah Jenis Pipa 437,142.20
Tanah Ǿ 20 cm
A Tenaga 10,920.00
L.01 0.080 OH Pekerja 82,000.00 6,560.00
L.02 0.040 OH Tukang Batu 90,000.00 3,600.00
L.03 0.004 OH Kepala Tukang 95,000.00 380.00
L.04 0.004 OH Mandor 95,000.00 380.00
B Bahan 386,482.00
1.60 m' pipa tanah (Pipa air limbah SDR - 41 (Rucika Lite)) 203,900.00 326,240.00
35.00 kg Semen Portlan 1,520.00 53,200.00
0.014 m3 Pasir Pasang 313,000.00 4,382.00
0.014 m3 Pasir Urug 190,000.00 2,660.00
-
C PERALATAN
D Jumlah A + B + C 397,402.00
E Overhead & Profit (contoh 10%) 10% 39,740.20
F Harga Satuan Pekerjaan (D+E) 437,142.20

Pemasangan 1 m’ Pipa Air Limbah Jenis Pipa


30 A.5.1.1.38 1 m' 203,153.50
Tanah diameter 15 cm
A Tenaga 8,190.00
L.01 0.060 OH Pekerja 82,000.00 4,920.00
L.02 0.030 OH Tukang Batu 90,000.00 2,700.00
L.03 0.003 OH Kepala Tukang 95,000.00 285.00
L.04 0.003 OH Mandor 95,000.00 285.00
B Bahan 176,495.00
1.60 bh pipa tanah 100,000.00 160,000.00
6.80 kg Semen Portlan 1,520.00 10,336.00
0.013 m3 Pasir Pasang 313,000.00 4,069.00
0.011 m3 Pasir Urug 190,000.00 2,090.00

C PERALATAN
D Jumlah A + B + C 184,685.00
E Overhead & Profit (contoh 10%) 10% 18,468.50
F Harga Satuan Pekerjaan (D+E) 203,153.50

31 A.5.1.1.39 1 m' Pemasangan 1 m’ Pipa Beton Diameter 15 – 20 cm 195,339.54


A Tenaga 19,110.00
L.01 0.140 OH Pekerja 82,000.00 11,480.00
L.02 0.070 OH Tukang Batu 90,000.00 6,300.00
L.03 0.007 OH Kepala Tukang 95,000.00 665.00
L.04 0.007 OH Mandor 95,000.00 665.00
B Bahan 158,471.40
1.10 bh pipa beton 102,000.00 112,200.00
0.027 m3 Batu Bata 675,000.00 18,225.00
3.920 kg Semen Portlan 1,520.00 5,958.40
0.056 m3 Pasir Pasang 313,000.00 17,528.00
0.024 m3 Pasir Urug 190,000.00 4,560.00
C PERALATAN
D Jumlah A + B + C 177,581.40
E Overhead & Profit (contoh 10%) 10% 17,758.14
F Harga Satuan Pekerjaan (D+E) 195,339.54
32 A.5.1.1.40 1 m' Pemasangan 1 m’ Pipa Beton Diameter 30 – 100 cm 639,780.90
A Tenaga 51,870.00
L.01 0.380 OH Pekerja 82,000.00 31,160.00
L.02 0.190 OH Tukang Batu 90,000.00 17,100.00
L.03 0.019 OH Kepala Tukang 95,000.00 1,805.00
L.04 0.019 OH Mandor 95,000.00 1,805.00
B Bahan 529,749.00
1.10 bh pipa beton 112,500.00 123,750.00
0.55 m3 Batu Bata 675,000.00 371,250.00
10.300 kg Semen Portlan 1,520.00 15,656.00
0.061 m3 Pasir Pasang 313,000.00 19,093.00
0.069 m3 Pasir Urug 190,000.00 13,110.00
C PERALATAN
D Jumlah A + B + C 581,619.00
E Overhead & Profit (contoh 10%) 10% 58,161.90
F Harga Satuan Pekerjaan (D+E) 639,780.90
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN

DIVISI VI A.6.1.1 HARGA SATUAN PEKERJAAN SISTEM DISTRIBUSI J


1 A.6.1.1.1 1 Buah Pemasangan 1 buah MCCB
A Tenaga
100 % Upah
B Bahan
3 btg Pipa listrik 5/8”
15 m Kabel
1 buah T Dus
2 buah L Bow
24 buah Klem biasa
1 buah MCCB (Boks MCB)
2.00 buah MCB
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit (contoh 10%)
F Harga Satuan Pekerjaan (D+E)

1 A.6.1.1.2 1 Buah Pemasangan 1 buah Stop kontak


A Tenaga
100 % Upah
B Bahan
3 btg Pipa listrik 5/8”
15 m Kabel
1 buah T Dus
2 buah L Bow
24 buah Klem biasa
1 buah Stop kontak
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit (contoh 10%)
F Harga Satuan Pekerjaan (D+E)
32 A.6.1.1.3 1 buah Pemasangan 1 buah led monitor 55", smart tv
A Tenaga
L.01 1.000 OH Pekerja
L.02 0.500 OH Tukang Listrik
L.03 0.050 OH Kepala Tukang
L.04 0.005 OH Mandor
B Bahan
1.00 buah Led Monitor 55"
C PERALATAN
D Harga Satuan Pekerjaan (D+E)
E 0
F Harga Satuan Pekerjaan (D+E)

32 A.6.1.1.5 1 buah Pemasangan 1 buah NVR 16 chanel


A Tenaga
L.01 1.000 OH Pekerja
L.02 0.500 OH Tukang Listrik
L.03 0.050 OH Kepala Tukang
L.04 0.005 OH Mandor
B Bahan
1.00 buah NVR 16 chanel
C PERALATAN
D Harga Satuan Pekerjaan (D+E)
E 0
F Harga Satuan Pekerjaan (D+E)
HARGA
JUMLAH
BAHAN/UPAH
URAIAN PEKERJAAN
Rp Rp

UAN PEKERJAAN SISTEM DISTRIBUSI JARINGAN LISTRIK


1 buah MCCB 462,000.00
-
-
420,000.00
0.00 -
18,000.00 270,000.00
0.00 -
0.00 - OK
0.00 -
46,000.00 46,000.00
52,000.00 104,000.00

420,000.00
Profit (contoh 10%) 10% 42,000.00
n Pekerjaan (D+E) 462,000.00

1 buah Stop kontak 316,470.00


-
-
287,700.00
0.00 -
18,000.00 270,000.00
0.00 -
0.00 - OK
0.00 -
17,700.00 17,700.00

287,700.00
Profit (contoh 10%) 10% 28,770.00
n Pekerjaan (D+E) 316,470.00
1 buah led monitor 55", smart tv 9,495,447.50
132,225.00
82,000.00 82,000.00
90,000.00 45,000.00
95,000.00 4,750.00
95,000.00 475.00
8,500,000.00
8,500,000.00 8,500,000.00

Pekerjaan (D+E) 8,632,225.00


10% 863,222.50
Pekerjaan (D+E) 9,495,447.50

1 buah NVR 16 chanel 26,744,547.50


132,225.00
82,000.00 82,000.00
90,000.00 45,000.00
95,000.00 4,750.00
95,000.00 475.00
24,181,000.00
24,181,000.00 24,181,000.00

Pekerjaan (D+E) 24,313,225.00


10% 2,431,322.50
Pekerjaan (D+E) 26,744,547.50
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN

DIVISI VI A.6.2.1 HARGA SATUAN PEKERJAAN SISTEM PENCAHAYA


1 A.6.2.1.1 1 Buah Pemasangan 1 Buah Titik Lampu
A Tenaga
100 % bahan Upah
B Bahan
3 btg Pipa listrik 5/8”
24 m Kabel
3 buah T Dus
4 buah L Bow
3 buah Las Dop
24 buah Klem
1 buah Mongkok
1 buah Saklar
1 buah Fitting
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit (contoh 10%)
F Harga Satuan Pekerjaan (D+E)

32 A.6.2.1.2 1 buah Pemasangan 1 buah lampu RD 150 E27 LEDBULB 6W


A Tenaga
L.01 0.125 OH Pekerja
L.02 0.063 OH Tukang Listrik
L.03 0.006 OH Kepala Tukang
L.04 0.001 OH Mandor
B Bahan
1.00 buah Lampu RD 150 E27 LEDBULB 6W
C PERALATAN
D Harga Satuan Pekerjaan (D+E)
E 0
F Harga Satuan Pekerjaan (D+E)

32 A.6.2.1.3 1 buah Pemasangan 1 buah lampu RD 150 E27 LEDBULB 10W


A Tenaga
L.01 0.125 OH Pekerja
L.02 0.063 OH Tukang Listrik
L.03 0.006 OH Kepala Tukang
L.04 0.001 OH Mandor
B Bahan
1.00 buah Lampu RD 150 E27 LEDBULB 10W
C PERALATAN
D Harga Satuan Pekerjaan (D+E)
E 0
F Harga Satuan Pekerjaan (D+E)

32 A.6.2.1.4 1 buah Pemasangan 1 buah lampu RD 150 E27 LEDBULB 12W


A Tenaga
L.01 0.125 OH Pekerja
L.02 0.063 OH Tukang Listrik
L.03 0.006 OH Kepala Tukang
L.04 0.001 OH Mandor
B Bahan
1.00 buah Lampu RD 150 E27 LEDBULB 12W
C PERALATAN
D Harga Satuan Pekerjaan (D+E)
E 0
F Harga Satuan Pekerjaan (D+E)

32 A.6.2.1.12 1 buah Pemasangan 1 buah RM M4 2XTL LED MASTER 18 W


A Tenaga
L.01 0.125 OH Pekerja
L.02 0.063 OH Tukang Listrik
L.03 0.006 OH Kepala Tukang
L.04 0.001 OH Mandor
B Bahan
1.00 buah RM M4 2XTL LED MASTER 18 W
C PERALATAN
D Harga Satuan Pekerjaan (D+E)
E 0
F Harga Satuan Pekerjaan (D+E)

32 A.6.2.1.14 1 buah Pemasangan 1 buah EXIT LED


A Tenaga
L.01 0.125 OH Pekerja
L.02 0.063 OH Tukang Listrik
L.03 0.006 OH Kepala Tukang
L.04 0.001 OH Mandor
B Bahan
1.00 buah EXIT LED
C PERALATAN
D Harga Satuan Pekerjaan (D+E)
E 0
F Harga Satuan Pekerjaan (D+E)

32 A.6.2.1.23 1 buah Pemasangan 1 buah stop kontak 16A, 1ph, umum(wall typ
A Tenaga
L.01 0.040 OH Pekerja
L.02 0.020 OH Tukang Listrik
L.03 0.002 OH Kepala Tukang
L.04 0.0002 OH Mandor
B Bahan
1.00 buah stop kontak 16A, 1ph, umum(wall type)
C PERALATAN
D Harga Satuan Pekerjaan (D+E)
E 0
F Harga Satuan Pekerjaan (D+E)

32 A.6.2.1.24 1 buah Pemasangan 1 buah stop kontak 16A, 1ph, tipe lantai
A Tenaga
L.01 0.040 OH Pekerja
L.02 0.020 OH Tukang Listrik
L.03 0.002 OH Kepala Tukang
L.04 0.0002 OH Mandor
B Bahan
1.00 buah stop kontak 16A, 1ph, tipe lantai
C PERALATAN
D Harga Satuan Pekerjaan (D+E)
E 0
F Harga Satuan Pekerjaan (D+E)

32 A.6.2.1.26 1 m' Pemasangan 1 m' tray cable uk 200mm x 100mm


A Tenaga
L.01 0.300 OH Pekerja
L.02 0.150 OH Tukang Listrik
L.03 0.015 OH Kepala Tukang
L.04 0.0020 OH Mandor
B Bahan
1 m' Tray cable uk 200mm x 100mm
1.00 ls Suport, jointing, elbow, tee dan asesoris lainnya
C PERALATAN
D Harga Satuan Pekerjaan (D+E)
E 0
F Harga Satuan Pekerjaan (D+E)

32 A.6.2.1.27 1 m' Pemasangan 1 m' tray cable uk 300mm x 100mm


A Tenaga
L.01 0.300 OH Pekerja
L.02 0.150 OH Tukang Listrik
L.03 0.015 OH Kepala Tukang
L.04 0.0020 OH Mandor
B Bahan
1 m' Tray cable uk 300mm x 100mm
1.00 ls Suport, jointing, elbow, tee dan asesoris lainnya
C PERALATAN
D Harga Satuan Pekerjaan (D+E)
E 0
F Harga Satuan Pekerjaan (D+E)

32 A.6.2.1.28 1 m' Pemasangan 1 m' tray cable uk 400mm x 100mm


A Tenaga
L.01 0.300 OH Pekerja
L.02 0.150 OH Tukang Listrik
L.03 0.015 OH Kepala Tukang
L.04 0.0020 OH Mandor
B Bahan
1 m' Tray cable uk 400mm x 100mm
1.00 ls Suport, jointing, elbow, tee dan asesoris lainnya
C PERALATAN
D Harga Satuan Pekerjaan (D+E)
E 0
F Harga Satuan Pekerjaan (D+E)

32 A.6.2.1.29 1 m' Pemasangan 1 m' cable ladder uk 400mm x 100mm


A Tenaga
L.01 0.300 OH Pekerja
L.02 0.150 OH Tukang Listrik
L.03 0.015 OH Kepala Tukang
L.04 0.0020 OH Mandor
B Bahan
1 m' cable ladder uk 400mm x 100mm
1.00 ls Suport, jointing, elbow, tee dan asesoris lainnya
C PERALATAN
D Harga Satuan Pekerjaan (D+E)
E 0
F Harga Satuan Pekerjaan (D+E)

32 A.6.2.1.30 1 m' Pemasangan 1 m' cable ladder uk 200mm x 100mm


A Tenaga
L.01 0.300 OH Pekerja
L.02 0.150 OH Tukang Listrik
L.03 0.015 OH Kepala Tukang
L.04 0.0020 OH Mandor
B Bahan
1 m' cable ladder uk 200mm x 100mm
1.00 ls Suport, jointing, elbow, tee dan asesoris lainnya
C PERALATAN
D Harga Satuan Pekerjaan (D+E)
E 0
F Harga Satuan Pekerjaan (D+E)

32 A.6.2.1.31 1 m' Pemasangan 1 m' cable ladder uk 300mm x 100mm


A Tenaga
L.01 0.300 OH Pekerja
L.02 0.150 OH Tukang Listrik
L.03 0.015 OH Kepala Tukang
L.04 0.0020 OH Mandor
B Bahan
1 m' cable ladder uk 300mm x 100mm
1.00 ls Suport, jointing, elbow, tee dan asesoris lainnya
C PERALATAN
D Harga Satuan Pekerjaan (D+E)
E 0
F Harga Satuan Pekerjaan (D+E)

32 A.6.2.1.32 1 titik Pemasangan 1 titik instalasi exhaust fan


A Tenaga
L.01 0.400 OH Pekerja
L.02 0.200 OH Tukang Listrik
L.03 0.020 OH Kepala Tukang
L.04 0.0020 OH Mandor
B Bahan
8 m' Kabel NYM 2X2.5 MM
8 m' Pipa Conduit
2 bh Soket Pipa
2 bh Tee Doos
5 bh Klem Pipa
5 bh Fhiser
0.25 bh Osolasi ban
C PERALATAN
D Harga Satuan Pekerjaan (D+E)
E 0
F Harga Satuan Pekerjaan (D+E)

32 A.6.2.1.33 1 titik Pemasangan 1 titik stopkontak lantai


A Tenaga
L.01 0.400 OH Pekerja
L.02 0.200 OH Tukang Listrik
L.03 0.020 OH Kepala Tukang
L.04 0.0020 OH Mandor
B Bahan
10 m' Kabel NYM 2X2.5 MM
10 m' Pipa Conduit
2 bh Soket Pipa
2 bh Tee Doos
2 bh Klem Pipa
0.25 bh Osolasi ban
C PERALATAN
D Harga Satuan Pekerjaan (D+E)
E 0
F Harga Satuan Pekerjaan (D+E)

32 A.6.2.1.34 1 titik Pemasangan 1 titik stopkontak AC


A Tenaga
L.01 0.400 OH Pekerja
L.02 0.200 OH Tukang Listrik
L.03 0.020 OH Kepala Tukang
L.04 0.0020 OH Mandor
B Bahan
14 m' Kabel NYM 2X2.5 MM
14 m' Pipa Conduit
4 bh Soket Pipa
4 bh Tee Doos
6 bh Klem Pipa
14 bh Fhiser
8 bh Las Doop
0.25 bh Osolasi ban
C PERALATAN
D Harga Satuan Pekerjaan (D+E)
E 0
F Harga Satuan Pekerjaan (D+E)

32 A.6.2.1.53 1 bh Pemasangan 1 buah penangkal petir elektro statis radius 1


A Tenaga
L.01 0.600 OH Pekerja
L.02 0.600 OH Tukang Listrik
L.03 0.060 OH Kepala Tukang
L.04 0.0060 OH Mandor
B Bahan
1.00 bh Head penangkal petir elektro statis radius 135 m
C PERALATAN
D Harga Satuan Pekerjaan (D+E)
E 0
F Harga Satuan Pekerjaan (D+E)
HARGA
JUMLAH
BAHAN/UPAH
URAIAN PEKERJAAN
Rp Rp

UAN PEKERJAAN SISTEM PENCAHAYAAN


1 Buah Titik Lampu 510,950.00
-
-
464,500.00
0.00 -
18,000.00 432,000.00
0.00 -
0.00 -
0.00 -
0.00 -
0.00 -
16,000.00 16,000.00
16,500.00 16,500.00

464,500.00
Profit (contoh 10%) 10% 46,450.00
n Pekerjaan (D+E) 510,950.00

1 buah lampu RD 150 E27 LEDBULB 6W 77,643.50


16,585.00
82,000.00 10,250.00
90,000.00 5,670.00
95,000.00 570.00
95,000.00 95.00
54,000.00
E27 LEDBULB 6W 54,000.00 54,000.00

Pekerjaan (D+E) 70,585.00


10% 7,058.50
Pekerjaan (D+E) 77,643.50

1 buah lampu RD 150 E27 LEDBULB 10W 93,043.50


16,585.00
82,000.00 10,250.00
90,000.00 5,670.00
95,000.00 570.00
95,000.00 95.00
68,000.00
E27 LEDBULB 10W 68,000.00 68,000.00

Pekerjaan (D+E) 84,585.00


10% 8,458.50
Pekerjaan (D+E) 93,043.50

1 buah lampu RD 150 E27 LEDBULB 12W 108,443.50


16,585.00
82,000.00 10,250.00
90,000.00 5,670.00
95,000.00 570.00
95,000.00 95.00
82,000.00
E27 LEDBULB 12W 82,000.00 82,000.00

Pekerjaan (D+E) 98,585.00


10% 9,858.50
Pekerjaan (D+E) 108,443.50

1 buah RM M4 2XTL LED MASTER 18 W 744,243.50


16,585.00
82,000.00 10,250.00
90,000.00 5,670.00
95,000.00 570.00
95,000.00 95.00
660,000.00
ED MASTER 18 W 660,000.00 660,000.00

Pekerjaan (D+E) 676,585.00


10% 67,658.50
Pekerjaan (D+E) 744,243.50

1 buah EXIT LED 296,543.50


16,585.00
82,000.00 10,250.00
90,000.00 5,670.00
95,000.00 570.00
95,000.00 95.00
253,000.00
253,000.00 253,000.00

Pekerjaan (D+E) 269,585.00


10% 26,958.50
Pekerjaan (D+E) 296,543.50

1 buah stop kontak 16A, 1ph, umum(wall type) 23,417.90


5,289.00
82,000.00 3,280.00
90,000.00 1,800.00
95,000.00 190.00
95,000.00 19.00
16,000.00
A, 1ph, umum(wall type) 16,000.00 16,000.00

Pekerjaan (D+E) 21,289.00


10% 2,128.90
Pekerjaan (D+E) 23,417.90

1 buah stop kontak 16A, 1ph, tipe lantai 949,617.90


5,289.00
82,000.00 3,280.00
90,000.00 1,800.00
95,000.00 190.00
95,000.00 19.00
858,000.00
A, 1ph, tipe lantai 858,000.00 858,000.00

Pekerjaan (D+E) 863,289.00


10% 86,328.90
Pekerjaan (D+E) 949,617.90

1 m' tray cable uk 200mm x 100mm 117,606.50


39,715.00
82,000.00 24,600.00
90,000.00 13,500.00
95,000.00 1,425.00
95,000.00 190.00
67,200.00
00mm x 100mm 24,200.00 24,200.00
, elbow, tee dan asesoris lainnya 43,000.00 43,000.00

Pekerjaan (D+E) 106,915.00


10% 10,691.50
Pekerjaan (D+E) 117,606.50

1 m' tray cable uk 300mm x 100mm 123,106.50


39,715.00
82,000.00 24,600.00
90,000.00 13,500.00
95,000.00 1,425.00
95,000.00 190.00
72,200.00
00mm x 100mm 29,200.00 29,200.00
, elbow, tee dan asesoris lainnya 43,000.00 43,000.00

Pekerjaan (D+E) 111,915.00


10% 11,191.50
Pekerjaan (D+E) 123,106.50

1 m' tray cable uk 400mm x 100mm 129,838.50


39,715.00
82,000.00 24,600.00
90,000.00 13,500.00
95,000.00 1,425.00
95,000.00 190.00
78,320.00
00mm x 100mm 35,320.00 35,320.00
, elbow, tee dan asesoris lainnya 43,000.00 43,000.00

Pekerjaan (D+E) 118,035.00


10% 11,803.50
Pekerjaan (D+E) 129,838.50

1 m' cable ladder uk 400mm x 100mm 126,318.50


39,715.00
82,000.00 24,600.00
90,000.00 13,500.00
95,000.00 1,425.00
95,000.00 190.00
75,120.00
400mm x 100mm 21,120.00 21,120.00
, elbow, tee dan asesoris lainnya 54,000.00 54,000.00

Pekerjaan (D+E) 114,835.00


10% 11,483.50
Pekerjaan (D+E) 126,318.50

1 m' cable ladder uk 200mm x 100mm 122,446.50


39,715.00
82,000.00 24,600.00
90,000.00 13,500.00
95,000.00 1,425.00
95,000.00 190.00
71,600.00
200mm x 100mm 17,600.00 17,600.00
, elbow, tee dan asesoris lainnya 54,000.00 54,000.00

Pekerjaan (D+E) 111,315.00


10% 11,131.50
Pekerjaan (D+E) 122,446.50

1 m' cable ladder uk 300mm x 100mm 122,666.50


39,715.00
82,000.00 24,600.00
90,000.00 13,500.00
95,000.00 1,425.00
95,000.00 190.00
71,800.00
300mm x 100mm 19,800.00 19,800.00
, elbow, tee dan asesoris lainnya 52,000.00 52,000.00

Pekerjaan (D+E) 111,515.00


10% 11,151.50
Pekerjaan (D+E) 122,666.50

1 titik instalasi exhaust fan 368,984.00


52,890.00
82,000.00 32,800.00
90,000.00 18,000.00
95,000.00 1,900.00
95,000.00 190.00
282,550.00
10,000.00 80,000.00
17,600.00 140,800.00
3,300.00 6,600.00
13,200.00 26,400.00
3,800.00 19,000.00
1,500.00 7,500.00
9,000.00 2,250.00

Pekerjaan (D+E) 335,440.00


10% 33,544.00
Pekerjaan (D+E) 368,984.00

1 titik stopkontak lantai 408,914.00


52,890.00
82,000.00 32,800.00
90,000.00 18,000.00
95,000.00 1,900.00
95,000.00 190.00
318,850.00
10,000.00 100,000.00
17,600.00 176,000.00
3,300.00 6,600.00
13,200.00 26,400.00
3,800.00 7,600.00
9,000.00 2,250.00

Pekerjaan (D+E) 371,740.00


10% 37,174.00
Pekerjaan (D+E) 408,914.00

1 titik stopkontak AC 738,474.00


52,890.00
82,000.00 32,800.00
90,000.00 18,000.00
95,000.00 1,900.00
95,000.00 190.00
618,450.00
10,000.00 140,000.00
17,600.00 246,400.00
3,300.00 13,200.00
13,200.00 52,800.00
3,800.00 22,800.00
1,500.00 21,000.00
15,000.00 120,000.00
9,000.00 2,250.00

Pekerjaan (D+E) 671,340.00


10% 67,134.00
Pekerjaan (D+E) 738,474.00

1 buah penangkal petir elektro statis radius 135 meter 7,501,417.00


109,470.00
82,000.00 49,200.00
90,000.00 54,000.00
95,000.00 5,700.00
95,000.00 570.00
6,710,000.00
al petir elektro statis radius 135 m 6,710,000.00 6,710,000.00

Pekerjaan (D+E) 6,819,470.00


10% 681,947.00
Pekerjaan (D+E) 7,501,417.00
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN

1 A.7.1.1.1 1 m' Pemasangan Pipa PVC Ø63 mm


A Tenaga
L.01 0.081 OH Pekerja
L.02 0.004 OH Tukang Pipa
L.04 0.008 OH Mandor
B Bahan
1.00 m' Pipa PVC Ø63 mm
C PERALATAN
0.019 hari Sewa Tripot/Tackel & handle crane 2T
D Jumlah A + B + C
E Overhead & Profit (contoh 10% 10%
F Harga Satuan Pekerjaan (D+E)

1 A.7.1.1.1 1 m' Pemasangan Pipa PVC Ø90 mm


A Tenaga
L.01 0.094 OH Pekerja
L.02 0.047 OH Tukang Pipa
L.04 0.009 OH Mandor
B Bahan
1.00 m' Pipa PVC Ø90 mm
C PERALATAN
0.019 hari Sewa Tripot/Tackel & handle crane 2T
D Jumlah A + B + C
E Overhead & Profit (contoh 10% 10%
F Harga Satuan Pekerjaan (D+E)

1 A.7.1.1.1 1 m' Pemasangan Pipa PVC Ø 110 mm


A Tenaga
L.01 0.105 OH Pekerja
L.02 0.053 OH Tukang Pipa
L.04 0.110 OH Mandor
B Bahan
1.00 m' Pipa PVC Ø 110mm
C PERALATAN
0.019 hari Sewa Tripot/Tackel & handle crane 2T
D Jumlah A + B + C
E Overhead & Profit (contoh 10% 10%
F Harga Satuan Pekerjaan (D+E)

1 A.7.1.1.1 1 m' Pemasangan Pipa PVC Ø 150 mm


A Tenaga
L.01 0.118 OH Pekerja
L.02 0.059 OH Tukang Pipa
L.04 0.012 OH Mandor
B Bahan
1.00 m' Pipa PVC Ø 150mm
C PERALATAN
0.019 hari Sewa Tripot/Tackel & handle crane 2T
D Jumlah A + B + C
E Overhead & Profit (contoh 10% 10%
F Harga Satuan Pekerjaan (D+E)

1 A.7.1.1.1 1 m' Pemasangan Pipa PVC Ø 200 mm


A Tenaga
L.01 0.189 OH Pekerja
L.02 0.095 OH Tukang Pipa
L.04 0.019 OH Mandor
B Bahan
1.00 m' Pipa PVC Ø 200mm
C PERALATAN
0.019 hari Sewa Tripot/Tackel & handle crane 2T
D Jumlah A + B + C
E Overhead & Profit (contoh 10% 10%
F Harga Satuan Pekerjaan (D+E)

1 A.7.1.1.1 1 m' Pemasangan Pipa PVC Ø 250 mm


A Tenaga
L.01 0.256 OH Pekerja
L.02 0.128 OH Tukang Pipa
L.04 0.026 OH Mandor
B Bahan
1.00 m' Pipa PVC Ø 250mm
C PERALATAN
0.019 hari Sewa Tripot/Tackel & handle crane 2T
D Jumlah A + B + C
E Overhead & Profit (contoh 10% 10%
F Harga Satuan Pekerjaan (D+E)

1 A.7.1.1.1 1 m' Pemasangan Pipa PVC Ø 300 mm


A Tenaga
L.01 0.294 OH Pekerja
L.02 0.147 OH Tukang Pipa
L.04 0.029 OH Mandor
B Bahan
1.00 m' Pipa PVC Ø 300mm
C PERALATAN
0.019 hari Sewa Tripot/Tackel & handle crane 2T
D Jumlah A + B + C
E Overhead & Profit (contoh 10% 10%
F Harga Satuan Pekerjaan (D+E)

1 A.7.1.1.1 1 m' Pemasangan Pipa PVC Ø 400 mm


A Tenaga
L.01 0.544 OH Pekerja
L.02 0.272 OH Tukang Pipa
L.04 0.540 OH Mandor
B Bahan
1.00 m' Pipa PVC Ø 400mm
C PERALATAN
0.019 hari Sewa Tripot/Tackel & handle crane 2T
D Jumlah A + B + C
E Overhead & Profit (contoh 10% 10%
F Harga Satuan Pekerjaan (D+E)

1 A.7.1.1.1 1 m' Pemasangan Pipa PVC Ø 450 mm


A Tenaga
L.01 0.669 OH Pekerja
L.02 0.335 OH Tukang Pipa
L.04 0.067 OH Mandor
B Bahan
1.00 m' Pipa PVC Ø 450mm
C PERALATAN
0.019 hari Sewa Tripot/Tackel & handle crane 2T
D Jumlah A + B + C
E Overhead & Profit (contoh 10% 10%
F Harga Satuan Pekerjaan (D+E)

1 A.7.1.1.1 1 m' Pemasangan Pipa PVC Ø 500 mm


A Tenaga
L.01 0.809 OH Pekerja
L.02 0.405 OH Tukang Pipa
L.04 0.081 OH Mandor
B Bahan
1.00 m' Pipa PVC Ø 500mm
C PERALATAN
0.019 hari Sewa Tripot/Tackel & handle crane 2T
D Jumlah A + B + C
E Overhead & Profit (contoh 10% 10%
F Harga Satuan Pekerjaan (D+E)

1 A.7.1.1.1 1 m' Pemasangan Pipa PVC Ø 600 mm


A Tenaga
L.01 0.957 OH Pekerja
L.02 0.476 OH Tukang Pipa
L.04 0.096 OH Mandor
B Bahan
1.00 m' Pipa PVC Ø 600mm
C PERALATAN
0.019 hari Sewa Tripot/Tackel & handle crane 2T
D Jumlah A + B + C
E Overhead & Profit (contoh 10% 10%
F Harga Satuan Pekerjaan (D+E)

1 A.7.1.1.1 1 m' Pemasangan Pipa PVC Ø 800 mm


A Tenaga
L.01 1.618 OH Pekerja
L.02 0.809 OH Tukang Pipa
L.04 0.162 OH Mandor
B Bahan
1.00 m' Pipa PVC Ø 800mm
C PERALATAN
0.019 hari Sewa Tripot/Tackel & handle crane 2T
D Jumlah A + B + C
E Overhead & Profit (contoh 10% 10%
F Harga Satuan Pekerjaan (D+E)

1 A.7.1.1.1 1 m' Pemasangan Pipa PVC Ø 900 mm


A Tenaga
L.01 1.691 OH Pekerja
L.02 0.846 OH Tukang Pipa
L.04 0.169 OH Mandor
B Bahan
1.00 m' Pipa PVC Ø 900mm
C PERALATAN
0.019 hari Sewa Tripot/Tackel & handle crane 2T
D Jumlah A + B + C
E Overhead & Profit (contoh 10% 10%
F Harga Satuan Pekerjaan (D+E)
1 A.7.1.1.1 1 m' Pemasangan Pipa PVC Ø 1000 mm
A Tenaga
L.01 1.895 OH Pekerja
L.02 0.948 OH Tukang Pipa
L.04 0.190 OH Mandor
B Bahan
1.00 m' Pipa PVC Ø 1000mm
C PERALATAN
0.019 hari Sewa Tripot/Tackel & handle crane 2T
D Jumlah A + B + C
E Overhead & Profit (contoh 10% 10%
F Harga Satuan Pekerjaan (D+E)

1 A.7.1.1.1 1 m' Pemasangan Pipa PVC Ø 1100 mm


A Tenaga
L.01 2.099 OH Pekerja
L.02 1.050 OH Tukang Pipa
L.04 0.210 OH Mandor
B Bahan
1.00 m' Pipa PVC Ø 1100mm
C PERALATAN
0.019 hari Sewa Tripot/Tackel & handle crane 2T
D Jumlah A + B + C
E Overhead & Profit (contoh 10% 10%
F Harga Satuan Pekerjaan (D+E)

1 A.7.1.1.1 1 m' Pemasangan Pipa PVC Ø 1200 mm


A Tenaga
L.01 2.303 OH Pekerja
L.02 1.152 OH Tukang Pipa
L.04 0.230 OH Mandor
B Bahan
1.00 m' Pipa PVC Ø 1200mm
C PERALATAN
0.019 hari Sewa Tripot/Tackel & handle crane 2T
D Jumlah A + B + C
E Overhead & Profit (contoh 10% 10%
F Harga Satuan Pekerjaan (D+E)

1 A.7.1.1.1 1 m' Pemasangan 1 m' pipa HDPE Ø63 mm


A Tenaga
L.01 0.035 OH Pekerja
L.02 0.017 OH Tukang Batu
L.04 0.003 OH Mandor
B Bahan
1.00 m' Pipa HDPE Ø63 mm
C PERALATAN
0.019 hari Sewa Tripot/Tackel & handle crane 2T
D Jumlah A + B + C
E Overhead & Profit (contoh 10% 10%
F Harga Satuan Pekerjaan (D+E)

2 A.7.1.1.2 1 m' Pemasangan 1 m’ pipa HDPE Ø100 mm


A Tenaga
L.01 0.039 OH Pekerja
L.02 0.019 OH Tukang Batu
L.04 0.003 OH Mandor
B Bahan
1.00 m' Pipa HDPE Ø 100 mm
C PERALATAN
0.019 hari Sewa Tripot/Tackel & handle crane 2T
D Jumlah A + B + C
E Overhead & Profit (contoh 10% 10%
F Harga Satuan Pekerjaan (D+E)

3 A.7.1.1.3 1 m' Pemasangan 1 m’ pipa HDPE Ø 125 mm


A Tenaga
L.01 0.045 OH Pekerja
L.02 0.023 OH Tukang Batu
L.04 0.005 OH Mandor
B Bahan
1.00 m' Pipa HDPE Ø 125 mm
C PERALATAN
0.019 hari Sewa Tripot/Tackel & handle crane 2T
D Jumlah A + B + C
E Overhead & Profit (contoh 10% 10%
F Harga Satuan Pekerjaan (D+E)

4 A.7.1.1.4 1 m' Pemasangan 1 m' pipa HDPE Ø 150 mm


A Tenaga
L.01 0.062 OH Pekerja
L.02 0.031 OH Tukang Batu
L.04 0.006 OH Mandor
B Bahan
1.00 m' Pipa HDPE Ø 150 mm
C PERALATAN
0.019 hari Sewa Tripot/Tackel & handle crane 2T
D Jumlah A + B + C
E Overhead & Profit (contoh 10% 10%
F Harga Satuan Pekerjaan (D+E)

5 A.7.1.1.5 1 m' Pemasangan 1 m’ pipa HDPE Ø 200 mm


A Tenaga
L.01 0.102 OH Pekerja
L.02 0.051 OH Tukang Batu
L.04 0.010 OH Mandor
B Bahan
1.00 m' Pipa HDPE Ø 200 mm
C PERALATAN
0.019 hari Sewa Tripot/Tackel & handle crane 2T
D Jumlah A + B + C
E Overhead & Profit (contoh 10% 10%
F Harga Satuan Pekerjaan (D+E)

6 A.7.1.1.6 1 m' Pemasangan 1 m’ pipa HDPE Ø 250 mm


A Tenaga
L.01 0.133 OH Pekerja
L.02 0.067 OH Tukang Batu
L.04 0.013 OH Mandor
B Bahan
1.00 m' Pipa HDPE Ø 250 mm
C PERALATAN
0.019 hari Sewa Tripot/Tackel & handle crane 2T
D Jumlah A + B + C
E Overhead & Profit (contoh 10% 10%
F Harga Satuan Pekerjaan (D+E)

6 A.7.1.1.7 1 m' Pemasangan 1 m’ pipa HDPE Ø 300 mm


A Tenaga
L.01 0.170 OH Pekerja
L.02 0.085 OH Tukang Batu
L.04 0.017 OH Mandor
B Bahan
1.00 m' Pipa HDPE Ø 300 mm
C PERALATAN
0.019 hari Sewa Tripot/Tackel & handle crane 2T
D Jumlah A + B + C
E Overhead & Profit (contoh 10% 10%
F Harga Satuan Pekerjaan (D+E)

6 A.7.1.1.8 1 m' Pemasangan 1 m’ pipa HDPE Ø 400 mm


A Tenaga
L.01 0.290 OH Pekerja
L.02 0.145 OH Tukang Batu
L.04 0.029 OH Mandor
B Bahan
1.00 m' Pipa HDPE Ø 400 mm
C PERALATAN
0.019 hari Sewa Tripot/Tackel & handle crane 2T
D Jumlah A + B + C
E Overhead & Profit (contoh 10% 10%
F Harga Satuan Pekerjaan (D+E)

6 A.7.1.1.9 1 m' Pemasangan 1 m’ pipa HDPE Ø 450 mm


A Tenaga
L.01 0.359 OH Pekerja
L.02 0.180 OH Tukang Batu
L.04 0.360 OH Mandor
B Bahan
1.00 m' Pipa HDPE Ø 450 mm
C PERALATAN
0.019 hari Sewa Tripot/Tackel & handle crane 2T
D Jumlah A + B + C
E Overhead & Profit (contoh 10% 10%
F Harga Satuan Pekerjaan (D+E)

6 A.7.1.1.10 1 m' Pemasangan 1 m’ pipa HDPE Ø 500 mm


A Tenaga
L.01 0.433 OH Pekerja
L.02 0.216 OH Tukang Batu
L.04 0.043 OH Mandor
B Bahan
1.00 m' Pipa HDPE Ø 500 mm
C PERALATAN
0.019 hari Sewa Tripot/Tackel & handle crane 2T
D Jumlah A + B + C
E Overhead & Profit (contoh 10% 10%
F Harga Satuan Pekerjaan (D+E)

6 A.7.1.1.11 1 m' Pemasangan 1 m’ pipa HDPE Ø 600 mm


A Tenaga
L.01 0.512 OH Pekerja
L.02 0.256 OH Tukang Batu
L.04 0.051 OH Mandor
B Bahan
1.00 m' Pipa HDPE Ø 600 mm
C PERALATAN
0.019 hari Sewa Tripot/Tackel & handle crane 2T
D Jumlah A + B + C
E Overhead & Profit (contoh 10% 10%
F Harga Satuan Pekerjaan (D+E)
6 A.7.1.1.12 1 m' Pemasangan 1 m’ pipa HDPE Ø 800 mm
A Tenaga
L.01 0.893 OH Pekerja
L.02 0.446 OH Tukang Batu
L.04 0.089 OH Mandor
B Bahan
1.00 m' Pipa HDPE Ø 800 mm
C PERALATAN
0.019 hari Sewa Tripot/Tackel & handle crane 2T
D Jumlah A + B + C
E Overhead & Profit (contoh 10% 10%
F Harga Satuan Pekerjaan (D+E)

6 A.7.1.1.13 1 m' Pemasangan 1 m’ pipa HDPE Ø 900 mm


A Tenaga
L.01 1.353 OH Pekerja
L.02 0.677 OH Tukang Batu
L.04 0.135 OH Mandor
B Bahan
1.00 m' Pipa HDPE Ø 900 mm
C PERALATAN
0.019 hari Sewa Tripot/Tackel & handle crane 2T
D Jumlah A + B + C
E Overhead & Profit (contoh 10% 10%
F Harga Satuan Pekerjaan (D+E)

6 A.7.1.1.14 1 m' Pemasangan 1 m’ pipa HDPE Ø 1000 mm


A Tenaga
L.01 1.659 OH Pekerja
L.02 0.830 OH Tukang Batu
L.04 0.166 OH Mandor
B Bahan
1.00 m' Pipa HDPE Ø 1000 mm
C PERALATAN
0.019 hari Sewa Tripot/Tackel & handle crane 2T
D Jumlah A + B + C
E Overhead & Profit (contoh 10% 10%
F Harga Satuan Pekerjaan (D+E)

6 A.7.1.1.15 1 m' Pemasangan 1 m’ pipa HDPE Ø 1100 mm


A Tenaga
L.01 1.818 OH Pekerja
L.02 0.909 OH Tukang Batu
L.04 0.182 OH Mandor
B Bahan
1.00 m' Pipa HDPE Ø 1100 mm
C PERALATAN
0.019 hari Sewa Tripot/Tackel & handle crane 2T
D Jumlah A + B + C
E Overhead & Profit (contoh 10% 10%
F Harga Satuan Pekerjaan (D+E)

6 A.7.1.1.16 1 m' Pemasangan 1 m’ pipa HDPE Ø 1200 mm


A Tenaga
L.01 2.370 OH Pekerja
L.02 1.185 OH Tukang Batu
L.04 0.237 OH Mandor
B Bahan
1.00 m' Pipa HDPE Ø 1200 mm
C PERALATAN
0.019 hari Sewa Tripot/Tackel & handle crane 2T
D Jumlah A + B + C
E Overhead & Profit (contoh 10% 10%
F Harga Satuan Pekerjaan (D+E)

6 A.7.1.1.16 1 m' Pemasangan Pipa GIP Ø 63 mm


A Tenaga
L.01 0.345 OH Pekerja
L.02 0.172 OH Tukang Pipa
L.04 0.034 OH Mandor
B Bahan
1.00 m' Pipa GIP Ø 63 mm
C PERALATAN
0.019 hari Sewa Tripot/Tackel & handle crane 2T
D Jumlah A + B + C
E Overhead & Profit (contoh 10% 10%
F Harga Satuan Pekerjaan (D+E)

6 A.7.1.1.16 1 m' Pemasangan Pipa GIP Ø 100 mm


A Tenaga
L.01 0.400 OH Pekerja
L.02 0.200 OH Tukang Pipa
L.04 0.040 OH Mandor
B Bahan
1.00 m' Pipa GIP Ø 100 mm
C PERALATAN
0.019 hari Sewa Tripot/Tackel & handle crane 2T
D Jumlah A + B + C
E Overhead & Profit (contoh 10% 10%
F Harga Satuan Pekerjaan (D+E)

6 A.7.1.1.16 1 m' Pemasangan Pipa GIP Ø 125 mm


A Tenaga
L.01 0.448 OH Pekerja
L.02 0.224 OH Tukang Pipa
L.04 0.045 OH Mandor
B Bahan
1.00 m' Pipa GIP Ø 125 mm
C PERALATAN
0.019 hari Sewa Tripot/Tackel & handle crane 2T
D Jumlah A + B + C
E Overhead & Profit (contoh 10% 10%
F Harga Satuan Pekerjaan (D+E)
6 A.7.1.1.16 1 m' Pemasangan Pipa GIP Ø 150 mm
A Tenaga
L.01 0.506 OH Pekerja
L.02 0.253 OH Tukang Pipa
L.04 0.051 OH Mandor
B Bahan
1.00 m' Pipa GIP Ø 150 mm
C PERALATAN
0.019 hari Sewa Tripot/Tackel & handle crane 2T
D Jumlah A + B + C
E Overhead & Profit (contoh 10% 10%
F Harga Satuan Pekerjaan (D+E)

6 A.7.1.1.16 1 m' Pemasangan Pipa GIP Ø 200 mm


A Tenaga
L.01 0.796 OH Pekerja
L.02 0.398 OH Tukang Pipa
L.04 0.080 OH Mandor
B Bahan
1.00 m' Pipa GIP Ø 200 mm
C PERALATAN
0.019 hari Sewa Tripot/Tackel & handle crane 2T
D Jumlah A + B + C
E Overhead & Profit (contoh 10% 10%
F Harga Satuan Pekerjaan (D+E)

6 A.7.1.1.16 1 m' Pemasangan Pipa GIP Ø 250 mm


A Tenaga
L.01 0.949 OH Pekerja
L.02 0.475 OH Tukang Pipa
L.04 0.095 OH Mandor
B Bahan
1.00 m' Pipa GIP Ø 250 mm
C PERALATAN
0.019 hari Sewa Tripot/Tackel & handle crane 2T
D Jumlah A + B + C
E Overhead & Profit (contoh 10% 10%
F Harga Satuan Pekerjaan (D+E)

6 A.7.1.1.16 1 m' Pemasangan Pipa GIP Ø 300 mm


A Tenaga
L.01 0.958 OH Pekerja
L.02 0.479 OH Tukang Pipa
L.04 0.096 OH Mandor
B Bahan
1.00 m' Pipa GIP Ø 300 mm
C PERALATAN
0.019 hari Sewa Tripot/Tackel & handle crane 2T
D Jumlah A + B + C
E Overhead & Profit (contoh 10% 10%
F Harga Satuan Pekerjaan (D+E)

6 A.7.1.1.16 1 m' Pemasangan Pipa GIP Ø 400 mm


A Tenaga
L.01 1.212 OH Pekerja
L.02 0.606 OH Tukang Pipa
L.04 0.121 OH Mandor
B Bahan
1.00 m' Pipa GIP Ø 400 mm
C PERALATAN
0.019 hari Sewa Tripot/Tackel & handle crane 2T
D Jumlah A + B + C
E Overhead & Profit (contoh 10% 10%
F Harga Satuan Pekerjaan (D+E)

6 A.7.1.1.16 1 m' Pemasangan Pipa GIP Ø 450 mm


A Tenaga
L.01 1.353 OH Pekerja
L.02 0.676 OH Tukang Pipa
L.04 0.135 OH Mandor
B Bahan
1.00 m' Pipa GIP Ø 450 mm
C PERALATAN
0.019 hari Sewa Tripot/Tackel & handle crane 2T
D Jumlah A + B + C
E Overhead & Profit (contoh 10% 10%
F Harga Satuan Pekerjaan (D+E)

6 A.7.1.1.16 1 m' Pemasangan Pipa GIP Ø 500 mm


A Tenaga
L.01 1.469 OH Pekerja
L.02 0.735 OH Tukang Pipa
L.04 0.147 OH Mandor
B Bahan
1.00 m' Pipa GIP Ø 500 mm
C PERALATAN
0.019 hari Sewa Tripot/Tackel & handle crane 2T
D Jumlah A + B + C
E Overhead & Profit (contoh 10% 10%
F Harga Satuan Pekerjaan (D+E)

6 A.7.1.1.16 1 m' Pemasangan Pipa GIP Ø 600 mm


A Tenaga
L.01 1.327 OH Pekerja
L.02 0.664 OH Tukang Pipa
L.04 0.133 OH Mandor
B Bahan
1.00 m' Pipa GIP Ø 600 mm
C PERALATAN
0.019 hari Sewa Tripot/Tackel & handle crane 2T
D Jumlah A + B + C
E Overhead & Profit (contoh 10% 10%
F Harga Satuan Pekerjaan (D+E)

6 A.7.1.1.16 1 m' Pemasangan Pipa GIP Ø 800 mm


A Tenaga
L.01 2.327 OH Pekerja
L.02 1.163 OH Tukang Pipa
L.04 0.233 OH Mandor
B Bahan
1.00 m' Pipa GIP Ø 800 mm
C PERALATAN
0.019 hari Sewa Tripot/Tackel & handle crane 2T
D Jumlah A + B + C
E Overhead & Profit (contoh 10% 10%
F Harga Satuan Pekerjaan (D+E)

6 A.7.1.1.16 1 m' Pemasangan Pipa GIP Ø 900 mm


A Tenaga
L.01 2.623 OH Pekerja
L.02 1.312 OH Tukang Pipa
L.04 0.262 OH Mandor
B Bahan
1.00 m' Pipa GIP Ø 900 mm
C PERALATAN
0.019 hari Sewa Tripot/Tackel & handle crane 2T
D Jumlah A + B + C
E Overhead & Profit (contoh 10% 10%
F Harga Satuan Pekerjaan (D+E)

6 A.7.1.1.16 1 m' Pemasangan Pipa GIP Ø 1000 mm


A Tenaga
L.01 2.911 OH Pekerja
L.02 1.456 OH Tukang Pipa
L.04 0.291 OH Mandor
B Bahan
1.00 m' Pipa GIP Ø 1000 mm
C PERALATAN
0.019 hari Sewa Tripot/Tackel & handle crane 2T
D Jumlah A + B + C
E Overhead & Profit (contoh 10% 10%
F Harga Satuan Pekerjaan (D+E)

6 A.7.1.1.16 1 m' Pemasangan Pipa GIP Ø 1100 mm


A Tenaga
L.01 3.200 OH Pekerja
L.02 1.600 OH Tukang Pipa
L.04 0.320 OH Mandor
B Bahan
1.00 m' Pipa GIP Ø 1100 mm
C PERALATAN
0.019 hari Sewa Tripot/Tackel & handle crane 2T
D Jumlah A + B + C
E Overhead & Profit (contoh 10% 10%
F Harga Satuan Pekerjaan (D+E)

6 A.7.1.1.16 1 m' Pemasangan Pipa GIP Ø 1200 mm


A Tenaga
L.01 3.488 OH Pekerja
L.02 1.744 OH Tukang Pipa
L.04 0.349 OH Mandor
B Bahan
1.00 m' Pipa GIP Ø 1200 mm
C PERALATAN
0.019 hari Sewa Tripot/Tackel & handle crane 2T
D Jumlah A + B + C
E Overhead & Profit (contoh 10% 10%
F Harga Satuan Pekerjaan (D+E)

6 A.7.1.1.16 1 m' Pemasangan Pipa Baja Ø 63 mm


A Tenaga
L.01 0.499 OH Pekerja
L.02 0.100 OH Tukang Pipa
L.04 0.050 OH Mandor
B Bahan
1.00 m' Pipa Baja Ø 63 mm
C PERALATAN
0.019 hari Sewa Tripot/Tackel & handle crane 2T
D Jumlah A + B + C
E Overhead & Profit (contoh 10% 10%
F Harga Satuan Pekerjaan (D+E)

6 A.7.1.1.16 1 m' Pemasangan Pipa Baja Ø 100 mm


A Tenaga
L.01 0.579 OH Pekerja
L.02 0.116 OH Tukang Pipa
L.04 0.058 OH Mandor
B Bahan
1.00 m' Pipa Baja Ø 100 mm
C PERALATAN
0.019 hari Sewa Tripot/Tackel & handle crane 2T
D Jumlah A + B + C
E Overhead & Profit (contoh 10% 10%
F Harga Satuan Pekerjaan (D+E)

6 A.7.1.1.16 1 m' Pemasangan Pipa Baja Ø 125 mm


A Tenaga
L.01 0.648 OH Pekerja
L.02 0.130 OH Tukang Pipa
L.04 0.065 OH Mandor
B Bahan
1.00 m' Pipa Baja Ø 125 mm
C PERALATAN
0.019 hari Sewa Tripot/Tackel & handle crane 2T
D Jumlah A + B + C
E Overhead & Profit (contoh 10% 10%
F Harga Satuan Pekerjaan (D+E)

6 A.7.1.1.16 1 m' Pemasangan Pipa Baja Ø 150 mm


A Tenaga
L.01 0.708 OH Pekerja
L.02 0.142 OH Tukang Pipa
L.04 0.071 OH Mandor
B Bahan
1.00 m' Pipa Baja Ø 150 mm
C PERALATAN
0.019 hari Sewa Tripot/Tackel & handle crane 2T
D Jumlah A + B + C
E Overhead & Profit (contoh 10% 10%
F Harga Satuan Pekerjaan (D+E)

6 A.7.1.1.16 1 m' Pemasangan Pipa Baja Ø 200 mm


A Tenaga
L.01 1.113 OH Pekerja
L.02 0.223 OH Tukang Pipa
L.04 0.111 OH Mandor
B Bahan
1.00 m' Pipa Baja Ø 200 mm
C PERALATAN
0.019 hari Sewa Tripot/Tackel & handle crane 2T
D Jumlah A + B + C
E Overhead & Profit (contoh 10% 10%
F Harga Satuan Pekerjaan (D+E)

6 A.7.1.1.16 1 m' Pemasangan Pipa Baja Ø 250 mm


A Tenaga
L.01 1.325 OH Pekerja
L.02 0.265 OH Tukang Pipa
L.04 0.133 OH Mandor
B Bahan
1.00 m' Pipa Baja Ø 250 mm
C PERALATAN
0.019 hari Sewa Tripot/Tackel & handle crane 2T
D Jumlah A + B + C
E Overhead & Profit (contoh 10% 10%
F Harga Satuan Pekerjaan (D+E)

6 A.7.1.1.16 1 m' Pemasangan Pipa Baja Ø 300 mm


A Tenaga
L.01 1.415 OH Pekerja
L.02 0.283 OH Tukang Pipa
L.04 0.141 OH Mandor
B Bahan
1.00 m' Pipa Baja Ø 300 mm
C PERALATAN
0.019 hari Sewa Tripot/Tackel & handle crane 2T
D Jumlah A + B + C
E Overhead & Profit (contoh 10% 10%
F Harga Satuan Pekerjaan (D+E)

6 A.7.1.1.16 1 m' Pemasangan Pipa Baja Ø 400 mm


A Tenaga
L.01 2.231 OH Pekerja
L.02 0.446 OH Tukang Pipa
L.04 0.223 OH Mandor
B Bahan
1.00 m' Pipa Baja Ø 400 mm
C PERALATAN
0.019 hari Sewa Tripot/Tackel & handle crane 2T
D Jumlah A + B + C
E Overhead & Profit (contoh 10% 10%
F Harga Satuan Pekerjaan (D+E)

6 A.7.1.1.16 1 m' Pemasangan Pipa Baja Ø 450 mm


A Tenaga
L.01 2.366 OH Pekerja
L.02 0.473 OH Tukang Pipa
L.04 0.237 OH Mandor
B Bahan
1.00 m' Pipa Baja Ø 450 mm
C PERALATAN
0.019 hari Sewa Tripot/Tackel & handle crane 2T
D Jumlah A + B + C
E Overhead & Profit (contoh 10% 10%
F Harga Satuan Pekerjaan (D+E)

6 A.7.1.1.16 1 m' Pemasangan Pipa Baja Ø 500 mm


A Tenaga
L.01 2.432 OH Pekerja
L.02 0.486 OH Tukang Pipa
L.04 0.243 OH Mandor
B Bahan
1.00 m' Pipa Baja Ø 500 mm
C PERALATAN
0.019 hari Sewa Tripot/Tackel & handle crane 2T
D Jumlah A + B + C
E Overhead & Profit (contoh 10% 10%
F Harga Satuan Pekerjaan (D+E)

6 A.7.1.1.16 1 m' Pemasangan Pipa Baja Ø 600 mm


A Tenaga
L.01 2.208 OH Pekerja
L.02 0.442 OH Tukang Pipa
L.04 0.221 OH Mandor
B Bahan
1.00 m' Pipa Baja Ø 600 mm
C PERALATAN
0.019 hari Sewa Tripot/Tackel & handle crane 2T
D Jumlah A + B + C
E Overhead & Profit (contoh 10% 10%
F Harga Satuan Pekerjaan (D+E)

6 A.7.1.1.16 1 m' Pemasangan Pipa Baja Ø 800 mm


A Tenaga
L.01 3.897 OH Pekerja
L.02 0.779 OH Tukang Pipa
L.04 0.390 OH Mandor
B Bahan
1.00 m' Pipa Baja Ø 800 mm
C PERALATAN
0.019 hari Sewa Tripot/Tackel & handle crane 2T
D Jumlah A + B + C
E Overhead & Profit (contoh 10% 10%
F Harga Satuan Pekerjaan (D+E)

6 A.7.1.1.16 1 m' Pemasangan Pipa Baja Ø 900 mm


A Tenaga
L.01 4.403 OH Pekerja
L.02 0.810 OH Tukang Pipa
L.04 0.440 OH Mandor
B Bahan
1.00 m' Pipa Baja Ø 900 mm
C PERALATAN
0.019 hari Sewa Tripot/Tackel & handle crane 2T
D Jumlah A + B + C
E Overhead & Profit (contoh 10% 10%
F Harga Satuan Pekerjaan (D+E)

6 A.7.1.1.16 1 m' Pemasangan Pipa Baja Ø 1000 mm


A Tenaga
L.01 4.895 OH Pekerja
L.02 0.979 OH Tukang Pipa
L.04 0.489 OH Mandor
B Bahan
1.00 m' Pipa Baja Ø 1000 mm
C PERALATAN
0.019 hari Sewa Tripot/Tackel & handle crane 2T
D Jumlah A + B + C
E Overhead & Profit (contoh 10% 10%
F Harga Satuan Pekerjaan (D+E)
6 A.7.1.1.16 1 m' Pemasangan Pipa Baja Ø 1100 mm
A Tenaga
L.01 5.387 OH Pekerja
L.02 1.077 OH Tukang Pipa
L.04 0.539 OH Mandor
B Bahan
1.00 m' Pipa Baja Ø 1100 mm
C PERALATAN
0.019 hari Sewa Tripot/Tackel & handle crane 2T
D Jumlah A + B + C
E Overhead & Profit (contoh 10% 10%
F Harga Satuan Pekerjaan (D+E)

6 A.7.1.1.16 1 m' Pemasangan Pipa Baja Ø 1200 mm


A Tenaga
L.01 5.897 OH Pekerja
L.02 1.176 OH Tukang Pipa
L.04 0.588 OH Mandor
B Bahan
1.00 m' Pipa Baja Ø 1200 mm
C PERALATAN
0.019 hari Sewa Tripot/Tackel & handle crane 2T
D Jumlah A + B + C
E Overhead & Profit (contoh 10% 10%
F Harga Satuan Pekerjaan (D+E)

7 A.7.1.1.17 1 m' Pemasangan 1 m' pipa air limbah Ø4"


A Tenaga
L.01 0.081 OH Pekerja
L.02 0.135 OH Tukang Batu
L.04 0.004 OH Mandor
B Bahan
1.20 m' Pipa Air Limbah Ø4"
0.35 ls Perlengkapan 35%xpipa
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit (contoh 10% 10%
F Harga Satuan Pekerjaan (D+E)

8 A.7.1.1.18 1 m' Pemasangan 1 m' pipa air limbah Ø6"


A Tenaga
L.01 0.081 OH Pekerja
L.02 0.135 OH Tukang Batu
L.04 0.004 OH Mandor
B Bahan
1.20 m' Pipa Air Limbah Ø6"
0.35 ls Perlengkapan 35%xpipa
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit (contoh 10% 10%
F Harga Satuan Pekerjaan (D+E)

9 A.7.1.1.19 1 m' Pemasangan 1 m' pipa air limbah Ø8"


A Tenaga
L.01 0.081 OH Pekerja
L.02 0.135 OH Tukang Batu
L.04 0.004 OH Mandor
B Bahan
1.20 m' Pipa Air Limbah Ø8"
0.35 ls Perlengkapan 35%xpipa
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit (contoh 10% 10%
F Harga Satuan Pekerjaan (D+E)

10 A.7.1.1.20 1 bh Pemasangan bak kontrol Precast Ø 30 cm


A Tenaga
L.01 0.250 OH Pekerja
L.02 0.025 OH Tukang Batu
L.04 0.015 OH Mandor
B Bahan
1.00 bh Bak Kontrol Precast Ø 30 cm
0.35 ls Perlengkapan 35%xpipa
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit (contoh 10% 10%
F Harga Satuan Pekerjaan (D+E)

11 A.7.1.1.21 1 bh Pemasangan bak kontrol Precast Ø 40 cm


A Tenaga
L.01 0.250 OH Pekerja
L.02 0.025 OH Tukang Batu
L.04 0.015 OH Mandor
B Bahan
1.00 bh Bak Kontrol Precast Ø 40 cm
0.35 ls Perlengkapan 35%xpipa
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit (contoh 10% 10%
F Harga Satuan Pekerjaan (D+E)

12 A.7.1.1.22 1 bh Pemasangan bak kontrol Precast Ø 60 cm


A Tenaga
L.01 0.250 OH Pekerja
L.02 0.025 OH Tukang Batu
L.04 0.015 OH Mandor
B Bahan
1.00 bh Bak Kontrol Precast Ø 60 cm
0.35 ls Perlengkapan 35%xpipa
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit (contoh 10% 10%
F Harga Satuan Pekerjaan (D+E)
13 A.7.1.1.23 1 bh Pemasangan bak kontrol Precast Ø 32 cm (penangkap lemak/greasc
A Tenaga
L.01 0.250 OH Pekerja
L.02 0.025 OH Tukang Batu
L.04 0.015 OH Mandor
B Bahan
1.00 bh Bak Kontrol Precast Ø 32 cm (penangkap lemak/greacetrap)
0.35 ls Perlengkapan 35%xpipa
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit (contoh 10% 10%
F Harga Satuan Pekerjaan (D+E)

14 A.7.1.1.24 1 bh Pemasangan Leher Angsa Precast


A Tenaga
L.01 0.250 OH Pekerja
L.02 0.025 OH Tukang Batu
L.04 0.015 OH Mandor
B Bahan
1.00 bh Leher Angsa Precast
0.35 ls Perlengkapan 35%xpipa
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit (contoh 10% 10%
F Harga Satuan Pekerjaan (D+E)
HARGA
JUMLAH
BAHAN/UPAH

Rp Rp
105,338.20
7,762.00
82,000.00 6,642.00
90,000.00 360.00
95,000.00 760.00
88,000.00
88,000.00 88,000.00

0
95,762.00
9,576.20
105,338.20

58,072.30
12,793.00
82,000.00 7,708.00
90,000.00 4,230.00
95,000.00 855.00
40,000.00
40,000.00 40,000.00

0
52,793.00
5,279.30
58,072.30

9,960,313.00
23,830.00
82,000.00 8,610.00
90,000.00 4,770.00
95,000.00 10,450.00
9,031,000.00
9,031,000.00 9,031,000.00

0
9,054,830.00
905,483.00
9,960,313.00

17,738.60
16,126.00
82,000.00 9,676.00
90,000.00 5,310.00
95,000.00 1,140.00
-
- -

0
16,126.00
1,612.60
17,738.60

28,438.30
25,853.00
82,000.00 15,498.00
90,000.00 8,550.00
95,000.00 1,805.00
-
- -

0
25,853.00
2,585.30
28,438.30

61,580.20
34,982.00
82,000.00 20,992.00
90,000.00 11,520.00
95,000.00 2,470.00
21,000.00
21,000.00 21,000.00

0
55,982.00
5,598.20
61,580.20

93,602.30
40,093.00
82,000.00 24,108.00
90,000.00 13,230.00
95,000.00 2,755.00
45,000.00
45,000.00 45,000.00

0
85,093.00
8,509.30
93,602.30

159,926.80
120,388.00
82,000.00 44,608.00
90,000.00 24,480.00
95,000.00 51,300.00
25,000.00
25,000.00 25,000.00

0
145,388.00
14,538.80
159,926.80

111,510.30
91,373.00
82,000.00 54,858.00
90,000.00 30,150.00
95,000.00 6,365.00
10,000.00
10,000.00 10,000.00

0
101,373.00
10,137.30
111,510.30

130,331.30
110,483.00
82,000.00 66,338.00
90,000.00 36,450.00
95,000.00 7,695.00
8,000.00
8,000.00 8,000.00

0
118,483.00
11,848.30
130,331.30

272,177.40
130,434.00
82,000.00 78,474.00
90,000.00 42,840.00
95,000.00 9,120.00
117,000.00
117,000.00 117,000.00

0
247,434.00
24,743.40
272,177.40

298,183.60
220,876.00
82,000.00 132,676.00
90,000.00 72,810.00
95,000.00 15,390.00
50,200.00
50,200.00 50,200.00

0
271,076.00
27,107.60
298,183.60

261,422.70
230,857.00
82,000.00 138,662.00
90,000.00 76,140.00
95,000.00 16,055.00
6,800.00
6,800.00 6,800.00

0
237,657.00
23,765.70
261,422.70
303,336.00
258,760.00
82,000.00 155,390.00
90,000.00 85,320.00
95,000.00 18,050.00
17,000.00
17,000.00 17,000.00

0
275,760.00
27,576.00
303,336.00

352,624.80
286,568.00
82,000.00 172,118.00
90,000.00 94,500.00
95,000.00 19,950.00
34,000.00
34,000.00 34,000.00

0
320,568.00
32,056.80
352,624.80

360,113.60
314,376.00
82,000.00 188,846.00
90,000.00 103,680.00
95,000.00 21,850.00
13,000.00
13,000.00 13,000.00

0
327,376.00
32,737.60
360,113.60

60,153.50
4,685.00
82,000.00 2,870.00
90,000.00 1,530.00
95,000.00 285.00
50,000.00
50,000.00 50,000.00

0
54,685.00
5,468.50
60,153.50

118,462.30
5,193.00
82,000.00 3,198.00
90,000.00 1,710.00
95,000.00 285.00
102,500.00
102,500.00 102,500.00

0
107,693.00
10,769.30
118,462.30

191,108.50
6,235.00
82,000.00 3,690.00
90,000.00 2,070.00
95,000.00 475.00
167,500.00
167,500.00 167,500.00

0
173,735.00
17,373.50
191,108.50

361,508.40
8,444.00
82,000.00 5,084.00
90,000.00 2,790.00
95,000.00 570.00
320,200.00
320,200.00 320,200.00

0
328,644.00
32,864.40
361,508.40

564,964.40
13,904.00
82,000.00 8,364.00
90,000.00 4,590.00
95,000.00 950.00
499,700.00
499,700.00 499,700.00

0
513,604.00
51,360.40
564,964.40

887,338.10
18,171.00
82,000.00 10,906.00
90,000.00 6,030.00
95,000.00 1,235.00
788,500.00
788,500.00 788,500.00
0
806,671.00
80,667.10
887,338.10

1,406,575.50
23,205.00
82,000.00 13,940.00
90,000.00 7,650.00
95,000.00 1,615.00
1,255,500.00
1,255,500.00 1,255,500.00

0
1,278,705.00
127,870.50
1,406,575.50

2,157,743.50
39,585.00
82,000.00 23,780.00
90,000.00 13,050.00
95,000.00 2,755.00
1,922,000.00
1,922,000.00 1,922,000.00

0
1,961,585.00
196,158.50
2,157,743.50

2,907,121.80
79,838.00
82,000.00 29,438.00
90,000.00 16,200.00
95,000.00 34,200.00
2,563,000.00
2,563,000.00 2,563,000.00

0
2,642,838.00
264,283.80
2,907,121.80

3,518,384.10
59,031.00
82,000.00 35,506.00
90,000.00 19,440.00
95,000.00 4,085.00
3,139,500.00
3,139,500.00 3,139,500.00

0
3,198,531.00
319,853.10
3,518,384.10

5,503,925.90
69,869.00
82,000.00 41,984.00
90,000.00 23,040.00
95,000.00 4,845.00
4,933,700.00
4,933,700.00 4,933,700.00

0
5,003,569.00
500,356.90
5,503,925.90
8,802,773.10
121,821.00
82,000.00 73,226.00
90,000.00 40,140.00
95,000.00 8,455.00
7,880,700.00
7,880,700.00 7,880,700.00

0
8,002,521.00
800,252.10
8,802,773.10

10,137,271.10
184,701.00
82,000.00 110,946.00
90,000.00 60,930.00
95,000.00 12,825.00
9,031,000.00
9,031,000.00 9,031,000.00

0
9,215,701.00
921,570.10
10,137,271.10

11,385,558.80
226,508.00
82,000.00 136,038.00
90,000.00 74,700.00
95,000.00 15,770.00
10,124,000.00
10,124,000.00 10,124,000.00
0
10,350,508.00
1,035,050.80
11,385,558.80

12,886,693.60
248,176.00
82,000.00 149,076.00
90,000.00 81,810.00
95,000.00 17,290.00
11,467,000.00
11,467,000.00 11,467,000.00

0
11,715,176.00
1,171,517.60
12,886,693.60

14,468,855.50
323,505.00
82,000.00 194,340.00
90,000.00 106,650.00
95,000.00 22,515.00
12,830,000.00
12,830,000.00 12,830,000.00

0
13,153,505.00
1,315,350.50
14,468,855.50

3,469,950.00
47,000.00
82,000.00 28,290.00
90,000.00 15,480.00
95,000.00 3,230.00
3,107,500.00
3,107,500.00 3,107,500.00

0
3,154,500.00
315,450.00
3,469,950.00

126,060.00
54,600.00
82,000.00 32,800.00
90,000.00 18,000.00
95,000.00 3,800.00
60,000.00
60,000.00 60,000.00

0
114,600.00
11,460.00
126,060.00

319,188.10
61,171.00
82,000.00 36,736.00
90,000.00 20,160.00
95,000.00 4,275.00
229,000.00
229,000.00 229,000.00

0
290,171.00
29,017.10
319,188.10
81,517.70
69,107.00
82,000.00 41,492.00
90,000.00 22,770.00
95,000.00 4,845.00
5,000.00
5,000.00 5,000.00

0
74,107.00
7,410.70
81,517.70

183,361.20
108,692.00
82,000.00 65,272.00
90,000.00 35,820.00
95,000.00 7,600.00
58,000.00
58,000.00 58,000.00

0
166,692.00
16,669.20
183,361.20

166,752.30
129,593.00
82,000.00 77,818.00
90,000.00 42,750.00
95,000.00 9,025.00
22,000.00
22,000.00 22,000.00

0
151,593.00
15,159.30
166,752.30

147,714.60
130,786.00
82,000.00 78,556.00
90,000.00 43,110.00
95,000.00 9,120.00
3,500.00
3,500.00 3,500.00

0
134,286.00
13,428.60
147,714.60

185,260.90
165,419.00
82,000.00 99,384.00
90,000.00 54,540.00
95,000.00 11,495.00
3,000.00
3,000.00 3,000.00

0
168,419.00
16,841.90
185,260.90

209,672.10
184,611.00
82,000.00 110,946.00
90,000.00 60,840.00
95,000.00 12,825.00
6,000.00
6,000.00 6,000.00

0
190,611.00
19,061.10
209,672.10

232,730.30
200,573.00
82,000.00 120,458.00
90,000.00 66,150.00
95,000.00 13,965.00
11,000.00
11,000.00 11,000.00

0
211,573.00
21,157.30
232,730.30

223,529.90
181,209.00
82,000.00 108,814.00
90,000.00 59,760.00
95,000.00 12,635.00
22,000.00
22,000.00 22,000.00

0
203,209.00
20,320.90
223,529.90

393,380.90
317,619.00
82,000.00 190,814.00
90,000.00 104,670.00
95,000.00 22,135.00
40,000.00
40,000.00 40,000.00

0
357,619.00
35,761.90
393,380.90

451,061.60
358,056.00
82,000.00 215,086.00
90,000.00 118,080.00
95,000.00 24,890.00
52,000.00
52,000.00 52,000.00

0
410,056.00
41,005.60
451,061.60

696,725.70
397,387.00
82,000.00 238,702.00
90,000.00 131,040.00
95,000.00 27,645.00
236,000.00
236,000.00 236,000.00

0
633,387.00
63,338.70
696,725.70

566,280.00
436,800.00
82,000.00 262,400.00
90,000.00 144,000.00
95,000.00 30,400.00
78,000.00
78,000.00 78,000.00

0
514,800.00
51,480.00
566,280.00

629,344.10
476,131.00
82,000.00 286,016.00
90,000.00 156,960.00
95,000.00 33,155.00
96,000.00
96,000.00 96,000.00

0
572,131.00
57,213.10
629,344.10

60,134.80
54,668.00
82,000.00 40,918.00
90,000.00 9,000.00
95,000.00 4,750.00
-
- -

0
54,668.00
5,466.80
60,134.80

802,370.80
63,428.00
82,000.00 47,478.00
90,000.00 10,440.00
95,000.00 5,510.00
666,000.00
666,000.00 666,000.00

0
729,428.00
72,942.80
802,370.80

3,885,212.10
71,011.00
82,000.00 53,136.00
90,000.00 11,700.00
95,000.00 6,175.00
3,461,000.00
3,461,000.00 3,461,000.00

0
3,532,011.00
353,201.10
3,885,212.10

93,039.10
77,581.00
82,000.00 58,056.00
90,000.00 12,780.00
95,000.00 6,745.00
7,000.00
7,000.00 7,000.00

0
84,581.00
8,458.10
93,039.10

246,819.10
121,881.00
82,000.00 91,266.00
90,000.00 20,070.00
95,000.00 10,545.00
102,500.00
102,500.00 102,500.00

0
224,381.00
22,438.10
246,819.10

398,348.50
145,135.00
82,000.00 108,650.00
90,000.00 23,850.00
95,000.00 12,635.00
217,000.00
217,000.00 217,000.00

0
362,135.00
36,213.50
398,348.50

221,204.50
154,895.00
82,000.00 116,030.00
90,000.00 25,470.00
95,000.00 13,395.00
46,200.00
46,200.00 46,200.00

0
201,095.00
20,109.50
221,204.50

310,493.70
244,267.00
82,000.00 182,942.00
90,000.00 40,140.00
95,000.00 21,185.00
38,000.00
38,000.00 38,000.00

0
282,267.00
28,226.70
310,493.70

285,006.70
259,097.00
82,000.00 194,012.00
90,000.00 42,570.00
95,000.00 22,515.00
-
- -
0
259,097.00
25,909.70
285,006.70

417,943.90
266,249.00
82,000.00 199,424.00
90,000.00 43,740.00
95,000.00 23,085.00
113,700.00
113,700.00 113,700.00

0
379,949.00
37,994.90
417,943.90

277,014.10
241,831.00
82,000.00 181,056.00
90,000.00 39,780.00
95,000.00 20,995.00
10,000.00
10,000.00 10,000.00

0
251,831.00
25,183.10
277,014.10

499,635.40
426,714.00
82,000.00 319,554.00
90,000.00 70,110.00
95,000.00 37,050.00
27,500.00
27,500.00 27,500.00

0
454,214.00
45,421.40
499,635.40

588,770.60
475,746.00
82,000.00 361,046.00
90,000.00 72,900.00
95,000.00 41,800.00
59,500.00
59,500.00 59,500.00

0
535,246.00
53,524.60
588,770.60

602,200.50
535,955.00
82,000.00 401,390.00
90,000.00 88,110.00
95,000.00 46,455.00
11,500.00
11,500.00 11,500.00

0
547,455.00
54,745.50
602,200.50
669,975.90
589,869.00
82,000.00 441,734.00
90,000.00 96,930.00
95,000.00 51,205.00
19,200.00
19,200.00 19,200.00

0
609,069.00
60,906.90
669,975.90

2,365,829.40
645,254.00
82,000.00 483,554.00
90,000.00 105,840.00
95,000.00 55,860.00
1,505,500.00
1,505,500.00 1,505,500.00

0
2,150,754.00
215,075.40
2,365,829.40

198,767.25
19,172.00
82,000.00 6,642.00
90,000.00 12,150.00
95,000.00 380.00
161,525.50
104,210.00 125,052.00
104,210.00 36,473.50

180,697.50
18,069.75
198,767.25

365,690.16
19,172.00
82,000.00 6,642.00
90,000.00 12,150.00
95,000.00 380.00
313,273.60
202,112.00 242,534.40
202,112.00 70,739.20

332,445.60
33,244.56
365,690.16

547,692.09
19,172.00
82,000.00 6,642.00
90,000.00 12,150.00
95,000.00 380.00
478,729.90
308,858.00 370,629.60
308,858.00 108,100.30

497,901.90
49,790.19
547,692.09

402,297.50
24,175.00
82,000.00 20,500.00
90,000.00 2,250.00
95,000.00 1,425.00
341,550.00
253,000.00 253,000.00
253,000.00 88,550.00

365,725.00
36,572.50
402,297.50

598,317.50
24,175.00
82,000.00 20,500.00
90,000.00 2,250.00
95,000.00 1,425.00
519,750.00
385,000.00 385,000.00
385,000.00 134,750.00

543,925.00
54,392.50
598,317.50

925,017.50
24,175.00
82,000.00 20,500.00
90,000.00 2,250.00
95,000.00 1,425.00
816,750.00
605,000.00 605,000.00
605,000.00 211,750.00

840,925.00
84,092.50
925,017.50
m (penangkap lemak/greascetrap) 402,297.50
24,175.00
82,000.00 20,500.00
90,000.00 2,250.00
95,000.00 1,425.00
341,550.00
253,000.00 253,000.00
253,000.00 88,550.00

365,725.00
36,572.50
402,297.50

204,792.50
24,175.00
82,000.00 20,500.00
90,000.00 2,250.00
95,000.00 1,425.00
162,000.00
120,000.00 120,000.00
120,000.00 42,000.00

186,175.00
18,617.50
204,792.50
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN

1 A.8.1.1.1 1 m' Pemasangan 1 m' Pagar Kawat Duri Tinngi m


A Tenaga
L.01 0.165 OH Pekerja
L.02 0.110 OH Tukang Batu
L.03 0.011 OH Kepala Tukang
L.04 0.011 OH Mandor
B Bahan
0.55 btg Dolken Kayu Ø 8-10 / 400 cm
1.1 kg Portland Cement
1.375 kg Kawat Duri
0.003 m3 Pasir pasang
0.005 m3 Batu Pecah 2/3
0.03 kg Paku
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit (contoh 10%)
F Harga Satuan Pekerjaan (D+E)

3 A.8.1.1.3 1 m2 Pemasangan 1 m2 Roster R1


A Tenaga
L.01 0.375 OH Pekerja
L.02 0.125 OH Tukang Batu
L.04 0.019 OH Mandor
B Bahan
30 buah Roster / terawang
11 kg Portland Cement
0.035 m3 Pasir pasang
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit (contoh 10%)
F Harga Satuan Pekerjaan (D+E)
4 A.8.1.1.4 1 buah Pemasangan 1 buah pompa Jet Pump
A Tenaga
L.01 0.250 OH Pekerja
L.04 0.125 OH Mandor
B Bahan
1 buah Jet Pump 2"
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit (contoh 10%)
F Harga Satuan Pekerjaan (D+E)

5 A.8.1.1.5 1 buah Pemasangan 1 buah pompa Submersible Grounfosh SP 5A-17


A Tenaga
L.01 0.250 OH Pekerja
L.04 0.125 OH Mandor
B Bahan
1 buah Pompa Submersible Grounfosh SP 5A-17
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit (contoh 10%)
F Harga Satuan Pekerjaan (D+E)

6 A.8.1.1.6 1 buah Pemasangan 1 buah pompa Submersible Grounfosh SP 5A-25


A Tenaga
L.01 0.250 OH Pekerja
L.04 0.125 OH Mandor
B Bahan
1 buah Pompa Submersible Grounfosh SP 5A-25
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit (contoh 10%)
F Harga Satuan Pekerjaan (D+E)

7 A.8.1.1.7 1 buah Pemasangan 1 buah pompa Grounfosh Sp 5A-52/5,5 kw/380 V/1,5" (


A Tenaga
L.01 0.250 OH Pekerja
L.04 0.125 OH Mandor
B Bahan
1 buah Groundfosh Sp 5A - 52/5,5 kw/380 V/1,5" (210 m)
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit (contoh 10%)
F Harga Satuan Pekerjaan (D+E)

8 A.8.1.1.8 1 buah Pemasangan 1 buah pompa Grounfosh Sp 9A - 36/7,5 kw/380 V/2" (2


A Tenaga
L.01 0.250 OH Pekerja
L.04 0.125 OH Mandor
B Bahan
1 buah Groundfosh Sp 9A - 36/7,5 kw/380 V/2" (200 m)
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit (contoh 10%)
F Harga Satuan Pekerjaan (D+E)

9 A.8.1.1.9 1 buah Pemasangan 1 buah pompa Grounfosh Sp 9A - 56/11 kw/380 V/2" (3


A Tenaga
L.01 0.250 OH Pekerja
L.04 0.125 OH Mandor
B Bahan
1 buah Groundfosh Sp 9A - 56/11 kw/380 V/2" (300 m)
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit (contoh 10%)
F Harga Satuan Pekerjaan (D+E)

10 A.8.1.1.10 1 buah Pemasangan 1 buah pompa Grounfosh Sp 9A - 75/15 kw/380 V/2" (4


A Tenaga
L.01 0.250 OH Pekerja
L.04 0.125 OH Mandor
B Bahan
1 buah Groundfosh Sp 9A - 75/15 kw/380 V/2" (400 m)
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit (contoh 10%)
F Harga Satuan Pekerjaan (D+E)

11 A.8.1.1.11 1 buah Pemasangan 1 buah pompa Grounfosh N5 4 - 23 M/1"/175 watt


A Tenaga
L.01 0.250 OH Pekerja
L.04 0.125 OH Mandor
B Bahan
1 buah Groundfosh N5 4 - 23 M/1"/175 watt/dlm sumur 8m/daya dorong 1
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit (contoh 10%)
F Harga Satuan Pekerjaan (D+E)

12 A.8.1.1.12 1 buah Pemasangan 1 buah pompa Grounfosh N5 13 - 18 M/1,5"/400 watt


A Tenaga
L.01 0.250 OH Pekerja
L.04 0.125 OH Mandor
B Bahan
1 buah Groundfosh N5 13 - 18 M/1,5"/400 watt/dlm sumur 8m/daya doron
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit (contoh 10%)
F Harga Satuan Pekerjaan (D+E)
HARGA
JUMLAH
BAHAN/UPAH
ERJAAN
Rp Rp
uri Tinngi m 49,237.38
24,475.00
82,000.00 13,530.00
90,000.00 9,900.00
95,000.00 -
95,000.00 1,045.00
20,286.25
14,000.00 7,700.00
1,360.00 1,496.00
5,550.00 7,631.25
313,000.00 939.00
372,000.00 1,860.00
20,000.00 660.00

44,761.25
10% 4,476.13
49,237.38

901,692.00
43,805.00
82,000.00 30,750.00
90,000.00 11,250.00
95,000.00 1,805.00
775,915.00
25,000.00 750,000.00
1,360.00 14,960.00
313,000.00 10,955.00

819,720.00
10% 81,972.00
901,692.00
2,056,312.50
32,375.00
82,000.00 20,500.00
95,000.00 11,875.00
1,837,000.00
1,837,000.00 1,837,000.00

1,869,375.00
10% 186,937.50
2,056,312.50

mersible Grounfosh SP 5A-17 27,535,612.50


32,375.00
82,000.00 20,500.00
95,000.00 11,875.00
25,000,000.00
25,000,000.00 25,000,000.00

25,032,375.00
10% 2,503,237.50
27,535,612.50

mersible Grounfosh SP 5A-25 44,035,612.50


32,375.00
82,000.00 20,500.00
95,000.00 11,875.00
40,000,000.00
40,000,000.00 40,000,000.00

40,032,375.00
10% 4,003,237.50
44,035,612.50

nfosh Sp 5A-52/5,5 kw/380 V/1,5" (210m) 131,804,612.50


32,375.00
82,000.00 20,500.00
95,000.00 11,875.00
119,790,000.00
V/1,5" (210 m) 119,790,000.00 119,790,000.00

119,822,375.00
10% 11,982,237.50
131,804,612.50

nfosh Sp 9A - 36/7,5 kw/380 V/2" (200 m) 124,445,612.50


32,375.00
82,000.00 20,500.00
95,000.00 11,875.00
113,100,000.00
V/2" (200 m) 113,100,000.00 113,100,000.00

113,132,375.00
10% 11,313,237.50
124,445,612.50

nfosh Sp 9A - 56/11 kw/380 V/2" (300 m) 278,214,612.50


32,375.00
82,000.00 20,500.00
95,000.00 11,875.00
252,890,000.00
V/2" (300 m) 252,890,000.00 252,890,000.00

252,922,375.00
10% 25,292,237.50
278,214,612.50

nfosh Sp 9A - 75/15 kw/380 V/2" (400 m) 351,419,612.50


32,375.00
82,000.00 20,500.00
95,000.00 11,875.00
319,440,000.00
V/2" (400 m) 319,440,000.00 319,440,000.00

319,472,375.00
10% 31,947,237.50
351,419,612.50

nfosh N5 4 - 23 M/1"/175 watt 3,842,712.50


32,375.00
82,000.00 20,500.00
95,000.00 11,875.00
3,461,000.00
t/dlm sumur 8m/daya dorong 1 3,461,000.00 3,461,000.00

3,493,375.00
10% 349,337.50
3,842,712.50

nfosh N5 13 - 18 M/1,5"/400 watt 5,160,512.50


32,375.00
82,000.00 20,500.00
95,000.00 11,875.00
4,659,000.00
watt/dlm sumur 8m/daya doron 4,659,000.00 4,659,000.00

4,691,375.00
10% 469,137.50
5,160,512.50
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN

1 A.7.1.2.1 1 buah Pemasangan 1 buah Pipa Fiting PVC - ELBOW (D-DL) 1 1/4"
A Tenaga
L.01 0.020 OH Pekerja
L.02 0.020 OH Tukang Pipa
L.04 0.010 OH Mandor
B Bahan
1.00 buah Pipa Fiting PVC - ELBOW (D-DL) 1 1/4"
C PERALATAN
D JUMLAH A + B + C
E Over Head & Profit 10%
F Harga Satuan Pekerjaan (D+E)

2 A.7.1.2.2 1 buah Pemasangan 1 buah Pipa Fiting PVC - ELBOW (D-DL) 1 1/2"
A Tenaga
L.01 0.020 OH Pekerja
L.02 0.020 OH Tukang Pipa
L.04 0.010 OH Mandor
B Bahan
1.00 buah Pipa Fiting PVC - ELBOW (D-DL) 1 1/2"
C PERALATAN
D JUMLAH A + B + C
E Over Head & Profit 10%
F Harga Satuan Pekerjaan (D+E)

3 A.7.1.2.3 1 buah Pemasangan 1 buah Pipa Fiting PVC - ELBOW (D-DL) 2"
A Tenaga
L.01 0.020 OH Pekerja
L.02 0.020 OH Tukang Pipa
L.04 0.010 OH Mandor
B Bahan
1.00 buah Pipa Fiting PVC - ELBOW (D-DL) 2"
C PERALATAN
D JUMLAH A + B + C
E Over Head & Profit 10%
F Harga Satuan Pekerjaan (D+E)

4 A.7.1.2.4 1 buah Pemasangan 1 buah Pipa Fiting PVC - ELBOW (D-DL) 2 1/2"
A Tenaga
L.01 0.020 OH Pekerja
L.02 0.020 OH Tukang Pipa
L.04 0.010 OH Mandor
B Bahan
1.00 buah Pipa Fiting PVC - ELBOW (D-DL) 2 1/2"
C PERALATAN
D JUMLAH A + B + C
E Over Head & Profit 10%
F Harga Satuan Pekerjaan (D+E)

5 A.7.1.2.5 1 buah Pemasangan 1 buah Pipa Fiting PVC - ELBOW (D-DL) 3"
A Tenaga
L.01 0.020 OH Pekerja
L.02 0.020 OH Tukang Pipa
L.04 0.010 OH Mandor
B Bahan
1.00 buah Pipa Fiting PVC - ELBOW (D-DL) 3"
C PERALATAN
D JUMLAH A + B + C
E Over Head & Profit 10%
F Harga Satuan Pekerjaan (D+E)

6 A.7.1.2.6 1 buah Pemasangan 1 buah Pipa Fiting PVC - ELBOW (D-DL) 4"
A Tenaga
L.01 0.020 OH Pekerja
L.02 0.020 OH Tukang Pipa
L.04 0.010 OH Mandor
B Bahan
1.00 buah Pipa Fiting PVC - ELBOW (D-DL) 4"
C PERALATAN
D JUMLAH A + B + C
E Over Head & Profit 10%
F Harga Satuan Pekerjaan (D+E)

7 A.7.1.2.7 1 buah Pemasangan 1 buah Pipa Fiting PVC - ELBOW (D-DL) 5"
A Tenaga
L.01 0.020 OH Pekerja
L.02 0.020 OH Tukang Pipa
L.04 0.010 OH Mandor
B Bahan
1.00 buah Pipa Fiting PVC - ELBOW (D-DL) 5"
C PERALATAN
D JUMLAH A + B + C
E Over Head & Profit 10%
F Harga Satuan Pekerjaan (D+E)

8 A.7.1.2.8 1 buah Pemasangan 1 buah Pipa Fiting PVC - ELBOW (D-DL) 6"
A Tenaga
L.01 0.020 OH Pekerja
L.02 0.020 OH Tukang Pipa
L.04 0.010 OH Mandor
B Bahan
1.00 buah Pipa Fiting PVC - ELBOW (D-DL) 6"
C PERALATAN
D JUMLAH A + B + C
E Over Head & Profit 10%
F Harga Satuan Pekerjaan (D+E)

9 A.7.1.2.9 1 buah Pemasangan 1 buah Pipa Fiting PVC - ELBOW (D-DL) 8"
A Tenaga
L.01 0.020 OH Pekerja
L.02 0.020 OH Tukang Pipa
L.04 0.010 OH Mandor
B Bahan
1.00 buah Pipa Fiting PVC - ELBOW (D-DL) 8"
C PERALATAN
D JUMLAH A + B + C
E Over Head & Profit 10%
F Harga Satuan Pekerjaan (D+E)

10 A.7.1.2.10 1 buah Pemasangan 1 buah Pipa Fiting PVC - ELBOW (D-DL) 10"
A Tenaga
L.01 0.020 OH Pekerja
L.02 0.020 OH Tukang Pipa
L.04 0.010 OH Mandor
B Bahan
1.00 buah Pipa Fiting PVC - ELBOW (D-DL) 10"
C PERALATAN
D JUMLAH A + B + C
E Over Head & Profit 10%
F Harga Satuan Pekerjaan (D+E)

11 A.7.1.2.11 1 buah Pemasangan 1 buah Pipa Fiting PVC - ELBOW (D-DL) 12"
A Tenaga
L.01 0.020 OH Pekerja
L.02 0.020 OH Tukang Pipa
L.04 0.010 OH Mandor
B Bahan
1.00 buah Pipa Fiting PVC - ELBOW (D-DL) 12"
C PERALATAN
D JUMLAH A + B + C
E Over Head & Profit 10%
F Harga Satuan Pekerjaan (D+E)

12 A.7.1.2.12 1 buah Pemasangan 1 buah Pipa Fiting PVC - SOCKET (D-DS) 1 1/4"
A Tenaga
L.01 0.020 OH Pekerja
L.02 0.020 OH Tukang Pipa
L.04 0.010 OH Mandor
B Bahan
1.00 buah Pipa Fiting PVC - SOCKET (D-DS) 1 1/4"
C PERALATAN
D JUMLAH A + B + C
E Over Head & Profit 10%
F Harga Satuan Pekerjaan (D+E)

13 A.7.1.2.13 1 buah Pemasangan 1 buah Pipa Fiting PVC - SOCKET (D-DS) 1 1/2"
A Tenaga
L.01 0.020 OH Pekerja
L.02 0.020 OH Tukang Pipa
L.04 0.010 OH Mandor
B Bahan
1.00 buah Pipa Fiting PVC - SOCKET (D-DS) 1 1/2"
C PERALATAN
D JUMLAH A + B + C
E Over Head & Profit 10%
F Harga Satuan Pekerjaan (D+E)

14 A.7.1.2.14 1 buah Pemasangan 1 buah Pipa Fiting PVC - SOCKET (D-DS) 2"
A Tenaga
L.01 0.020 OH Pekerja
L.02 0.020 OH Tukang Pipa
L.04 0.010 OH Mandor
B Bahan
1.00 buah Pipa Fiting PVC - SOCKET (D-DS) 2"
C PERALATAN
D JUMLAH A + B + C
E Over Head & Profit 10%
F Harga Satuan Pekerjaan (D+E)

15 A.7.1.2.15 1 buah Pemasangan 1 buah Pipa Fiting PVC - SOCKET (D-DS) 2 1/2"
A Tenaga
L.01 0.020 OH Pekerja
L.02 0.020 OH Tukang Pipa
L.04 0.010 OH Mandor
B Bahan
1.00 buah Pipa Fiting PVC - SOCKET (D-DS) 2 1/2"
C PERALATAN
D JUMLAH A + B + C
E Over Head & Profit 10%
F Harga Satuan Pekerjaan (D+E)

16 A.7.1.2.16 1 buah Pemasangan 1 buah Pipa Fiting PVC - SOCKET (D-DS) 3"
A Tenaga
L.01 0.020 OH Pekerja
L.02 0.020 OH Tukang Pipa
L.04 0.010 OH Mandor
B Bahan
1.00 buah Pipa Fiting PVC - SOCKET (D-DS) 3"
C PERALATAN
D JUMLAH A + B + C
E Over Head & Profit 10%
F Harga Satuan Pekerjaan (D+E)

17 A.7.1.2.17 1 buah Pemasangan 1 buah Pipa Fiting PVC - SOCKET (D-DS) 4"
A Tenaga
L.01 0.020 OH Pekerja
L.02 0.020 OH Tukang Pipa
L.04 0.010 OH Mandor
B Bahan
1.00 buah Pipa Fiting PVC - SOCKET (D-DS) 4"
C PERALATAN
D JUMLAH A + B + C
E Over Head & Profit 10%
F Harga Satuan Pekerjaan (D+E)

18 A.7.1.2.18 1 buah Pemasangan 1 buah Pipa Fiting PVC - SOCKET (D-DS) 5"
A Tenaga
L.01 0.020 OH Pekerja
L.02 0.020 OH Tukang Pipa
L.04 0.010 OH Mandor
B Bahan
1.00 buah Pipa Fiting PVC - SOCKET (D-DS) 5"
C PERALATAN
D JUMLAH A + B + C
E Over Head & Profit 10%
F Harga Satuan Pekerjaan (D+E)

19 A.7.1.2.19 1 buah Pemasangan 1 buah Pipa Fiting PVC - SOCKET (D-DS) 6"
A Tenaga
L.01 0.020 OH Pekerja
L.02 0.020 OH Tukang Pipa
L.04 0.010 OH Mandor
B Bahan
1.00 buah Pipa Fiting PVC - SOCKET (D-DS) 6"
C PERALATAN
D JUMLAH A + B + C
E Over Head & Profit 10%
F Harga Satuan Pekerjaan (D+E)

20 A.7.1.2.20 1 buah Pemasangan 1 buah Pipa Fiting PVC - SOCKET (D-DS) 8"
A Tenaga
L.01 0.020 OH Pekerja
L.02 0.020 OH Tukang Pipa
L.04 0.010 OH Mandor
B Bahan
1.00 buah Pipa Fiting PVC - SOCKET (D-DS) 8"
C PERALATAN
D JUMLAH A + B + C
E Over Head & Profit 10%
F Harga Satuan Pekerjaan (D+E)

21 A.7.1.2.21 1 buah Pemasangan 1 buah Pipa Fiting PVC - SOCKET (D-DS) 10"
A Tenaga
L.01 0.020 OH Pekerja
L.02 0.020 OH Tukang Pipa
L.04 0.010 OH Mandor
B Bahan
1.00 buah Pipa Fiting PVC - SOCKET (D-DS) 10"
C PERALATAN
D JUMLAH A + B + C
E Over Head & Profit 10%
F Harga Satuan Pekerjaan (D+E)

22 A.7.1.2.22 1 buah Pemasangan 1 buah Pipa Fiting PVC - TEE (D-DT) 1 1/4"
A Tenaga
L.01 0.020 OH Pekerja
L.02 0.020 OH Tukang Pipa
L.04 0.010 OH Mandor
B Bahan
1.00 buah Pipa Fiting PVC - TEE (D-DT) 1 1/4"
C PERALATAN
D JUMLAH A + B + C
E Over Head & Profit 10%
F Harga Satuan Pekerjaan (D+E)

23 A.7.1.2.23 1 buah Pemasangan 1 buah Pipa Fiting PVC - TEE (D-DT) 1 1/2"
A Tenaga
L.01 0.020 OH Pekerja
L.02 0.020 OH Tukang Pipa
L.04 0.010 OH Mandor
B Bahan
1.00 buah Pipa Fiting PVC - TEE (D-DT) 1 1/2"
C PERALATAN
D JUMLAH A + B + C
E Over Head & Profit 10%
F Harga Satuan Pekerjaan (D+E)

24 A.7.1.2.24 1 buah Pemasangan 1 buah Pipa Fiting PVC - TEE (D-DT) 2"
A Tenaga
L.01 0.020 OH Pekerja
L.02 0.020 OH Tukang Pipa
L.04 0.010 OH Mandor
B Bahan
1.00 buah Pipa Fiting PVC - TEE (D-DT) 2"
C PERALATAN
D JUMLAH A + B + C
E Over Head & Profit 10%
F Harga Satuan Pekerjaan (D+E)

25 A.7.1.2.25 1 buah Pemasangan 1 buah Pipa Fiting PVC - TEE (D-DT) 2 1/2"
A Tenaga
L.01 0.020 OH Pekerja
L.02 0.020 OH Tukang Pipa
L.04 0.010 OH Mandor
B Bahan
1.00 buah Pipa Fiting PVC - TEE (D-DT) 2 1/2"
C PERALATAN
D JUMLAH A + B + C
E Over Head & Profit 10%
F Harga Satuan Pekerjaan (D+E)

26 A.7.1.2.26 1 buah Pemasangan 1 buah Pipa Fiting PVC - TEE (D-DT) 3" x 1 1/2"
A Tenaga
L.01 0.020 OH Pekerja
L.02 0.020 OH Tukang Pipa
L.04 0.010 OH Mandor
B Bahan
1.00 buah Pipa Fiting PVC - TEE (D-DT) 3" x 1 1/2"
C PERALATAN
D JUMLAH A + B + C
E Over Head & Profit 10%
F Harga Satuan Pekerjaan (D+E)

27 A.7.1.2.27 1 buah Pemasangan 1 buah Pipa Fiting PVC - TEE (D-DT) 3" x 2"
A Tenaga
L.01 0.020 OH Pekerja
L.02 0.020 OH Tukang Pipa
L.04 0.010 OH Mandor
B Bahan
1.00 buah Pipa Fiting PVC - TEE (D-DT) 3" x 2"
C PERALATAN
D JUMLAH A + B + C
E Over Head & Profit 10%
F Harga Satuan Pekerjaan (D+E)

28 A.7.1.2.28 1 buah Pemasangan 1 buah Pipa Fiting PVC - TEE (D-DT) 3" 2 1/2"
A Tenaga
L.01 0.020 OH Pekerja
L.02 0.020 OH Tukang Pipa
L.04 0.010 OH Mandor
B Bahan
1.00 buah Pipa Fiting PVC - TEE (D-DT) 3" x 2 1/2"
C PERALATAN
D JUMLAH A + B + C
E Over Head & Profit 10%
F Harga Satuan Pekerjaan (D+E)

29 A.7.1.2.29 1 buah Pemasangan 1 buah Pipa Fiting PVC - TEE (D-DT) 3"
A Tenaga
L.01 0.020 OH Pekerja
L.02 0.020 OH Tukang Pipa
L.04 0.010 OH Mandor
B Bahan
1.00 buah Pipa Fiting PVC - TEE (D-DT) 3"
C PERALATAN
D JUMLAH A + B + C
E Over Head & Profit 10%
F Harga Satuan Pekerjaan (D+E)
30 A.7.1.2.30 1 buah Pemasangan 1 buah Pipa Fiting PVC - TEE (D-DT) 4" x 2"
A Tenaga
L.01 0.020 OH Pekerja
L.02 0.020 OH Tukang Pipa
L.04 0.010 OH Mandor
B Bahan
1.00 buah Pipa Fiting PVC - TEE (D-DT) 4" x 2"
C PERALATAN
D JUMLAH A + B + C
E Over Head & Profit 10%
F Harga Satuan Pekerjaan (D+E)

31 A.7.1.2.31 1 buah Pemasangan 1 buah Pipa Fiting PVC - TEE (D-DT) 4" x 3"
A Tenaga
L.01 0.020 OH Pekerja
L.02 0.020 OH Tukang Pipa
L.04 0.010 OH Mandor
B Bahan
1.00 buah Pipa Fiting PVC - TEE (D-DT) 4" x 3"
C PERALATAN
D JUMLAH A + B + C
E Over Head & Profit 10%
F Harga Satuan Pekerjaan (D+E)

32 A.7.1.2.32 1 buah Pemasangan 1 buah Pipa Fiting PVC - TEE (D-DT) 4"
A Tenaga
L.01 0.020 OH Pekerja
L.02 0.020 OH Tukang Pipa
L.04 0.010 OH Mandor
B Bahan
1.00 buah Pipa Fiting PVC - TEE (D-DT) 4"
C PERALATAN
D JUMLAH A + B + C
E Over Head & Profit 10%
F Harga Satuan Pekerjaan (D+E)
33 A.7.1.2.33 1 buah Pemasangan 1 buah Pipa Fiting PVC - TEE (D-DT) 5" x 4"
A Tenaga
L.01 0.020 OH Pekerja
L.02 0.020 OH Tukang Pipa
L.04 0.010 OH Mandor
B Bahan
1.00 buah Pipa Fiting PVC - TEE (D-DT) 5" x 4"
C PERALATAN
D JUMLAH A + B + C
E Over Head & Profit 10%
F Harga Satuan Pekerjaan (D+E)

34 A.7.1.2.34 1 buah Pemasangan 1 buah Pipa Fiting PVC - TEE (D-DT) 5"
A Tenaga
L.01 0.020 OH Pekerja
L.02 0.020 OH Tukang Pipa
L.04 0.010 OH Mandor
B Bahan
1.00 buah Pipa Fiting PVC - TEE (D-DT) 5"
C PERALATAN
D JUMLAH A + B + C
E Over Head & Profit 10%
F Harga Satuan Pekerjaan (D+E)

35 A.7.1.2.35 1 buah Pemasangan 1 buah Pipa Fiting PVC - TEE (D-DT) 6" x 4"
A Tenaga
L.01 0.020 OH Pekerja
L.02 0.020 OH Tukang Pipa
L.04 0.010 OH Mandor
B Bahan
1.00 buah Pipa Fiting PVC - TEE (D-DT) 6" x 4"
C PERALATAN
D JUMLAH A + B + C
E Over Head & Profit 10%
F Harga Satuan Pekerjaan (D+E)

36 A.7.1.2.36 1 buah Pemasangan 1 buah Pipa Fiting PVC - TEE (D-DT) 6"
A Tenaga
L.01 0.020 OH Pekerja
L.02 0.020 OH Tukang Pipa
L.04 0.010 OH Mandor
B Bahan
1.00 buah Pipa Fiting PVC - TEE (D-DT) 6"
C PERALATAN
D JUMLAH A + B + C
E Over Head & Profit 10%
F Harga Satuan Pekerjaan (D+E)

37 A.7.1.2.37 1 buah Pemasangan 1 buah Pipa Fiting PVC - TEE (D-DT) 8" x 4"
A Tenaga
L.01 0.020 OH Pekerja
L.02 0.020 OH Tukang Pipa
L.04 0.010 OH Mandor
B Bahan
1.00 buah Pipa Fiting PVC - TEE (D-DT) 8" x 4"
C PERALATAN
D JUMLAH A + B + C
E Over Head & Profit 10%
F Harga Satuan Pekerjaan (D+E)

38 A.7.1.2.38 1 buah Pemasangan 1 buah Pipa Fiting PVC - TEE (D-DT) 8"
A Tenaga
L.01 0.020 OH Pekerja
L.02 0.020 OH Tukang Pipa
L.04 0.010 OH Mandor
B Bahan
1.00 buah Pipa Fiting PVC - TEE (D-DT) 8"
C PERALATAN
D JUMLAH A + B + C
E Over Head & Profit 10%
F Harga Satuan Pekerjaan (D+E)

39 A.7.1.2.39 1 buah Pemasangan 1 buah Pipa Fiting PVC - INCREASER (D-IN) 1 1/2"
A Tenaga
L.01 0.020 OH Pekerja
L.02 0.020 OH Tukang Pipa
L.04 0.010 OH Mandor
B Bahan
1.00 buah Pipa Fiting PVC - INCREASER (D-IN) 1 1/2" X 1
C PERALATAN
D JUMLAH A + B + C
E Over Head & Profit 10%
F Harga Satuan Pekerjaan (D+E)

40 A.7.1.2.40 1 buah Pemasangan 1 buah Pipa Fiting PVC - INCREASER (D-IN) 2" X 1
A Tenaga
L.01 0.020 OH Pekerja
L.02 0.020 OH Tukang Pipa
L.04 0.010 OH Mandor
B Bahan
1.00 buah Pipa Fiting PVC - INCREASER (D-IN) 2" X 1 1/4
C PERALATAN
D JUMLAH A + B + C
E Over Head & Profit 10%
F Harga Satuan Pekerjaan (D+E)

41 A.7.1.2.41 1 buah Pemasangan 1 buah Pipa Fiting PVC - INCREASER (D-IN) 2" X 1
A Tenaga
L.01 0.020 OH Pekerja
L.02 0.020 OH Tukang Pipa
L.04 0.010 OH Mandor
B Bahan
1.00 buah Pipa Fiting PVC - INCREASER (D-IN) 2" X 1 1/2
C PERALATAN
D JUMLAH A + B + C
E Over Head & Profit 10%
F Harga Satuan Pekerjaan (D+E)

42 A.7.1.2.42 1 buah Pemasangan 1 buah Pipa Fiting PVC - INCREASER (D-IN) 2 1/2"
A Tenaga
L.01 0.020 OH Pekerja
L.02 0.020 OH Tukang Pipa
L.04 0.010 OH Mandor
B Bahan
1.00 buah Pipa Fiting PVC - INCREASER (D-IN) 2 1/2" X 1
C PERALATAN
D JUMLAH A + B + C
E Over Head & Profit 10%
F Harga Satuan Pekerjaan (D+E)

43 A.7.1.2.43 1 buah Pemasangan 1 buah Pipa Fiting PVC - INCREASER (D-IN) 2 1/2"
A Tenaga
L.01 0.020 OH Pekerja
L.02 0.020 OH Tukang Pipa
L.04 0.010 OH Mandor
B Bahan
1.00 buah Pipa Fiting PVC - INCREASER (D-IN) 2 1/2" X 2
C PERALATAN
D JUMLAH A + B + C
E Over Head & Profit 10%
F Harga Satuan Pekerjaan (D+E)

44 A.7.1.2.44 1 buah Pemasangan 1 buah Pipa Fiting PVC - INCREASER (D-IN) 3" X 1
A Tenaga
L.01 0.020 OH Pekerja
L.02 0.020 OH Tukang Pipa
L.04 0.010 OH Mandor
B Bahan
1.00 buah Pipa Fiting PVC - INCREASER (D-IN) 3" X 1 1/2
C PERALATAN
D JUMLAH A + B + C
E Over Head & Profit 10%
F Harga Satuan Pekerjaan (D+E)

45 A.7.1.2.45 1 buah Pemasangan 1 buah Pipa Fiting PVC - INCREASER (D-IN) 3" X 2
A Tenaga
L.01 0.020 OH Pekerja
L.02 0.020 OH Tukang Pipa
L.04 0.010 OH Mandor
B Bahan
1.00 buah Pipa Fiting PVC - INCREASER (D-IN) 3" X 2"
C PERALATAN
D JUMLAH A + B + C
E Over Head & Profit 10%
F Harga Satuan Pekerjaan (D+E)

46 A.7.1.2.46 1 buah Pemasangan 1 buah Pipa Fiting PVC - INCREASER (D-IN) 3" X 2
A Tenaga
L.01 0.020 OH Pekerja
L.02 0.020 OH Tukang Pipa
L.04 0.010 OH Mandor
B Bahan
1.00 buah Pipa Fiting PVC - INCREASER (D-IN) 3" X 2 1/2
C PERALATAN
D JUMLAH A + B + C
E Over Head & Profit 10%
F Harga Satuan Pekerjaan (D+E)

47 A.7.1.2.47 1 buah Pemasangan 1 buah Pipa Fiting PVC - INCREASER (D-IN) 4" X 2
A Tenaga
L.01 0.020 OH Pekerja
L.02 0.020 OH Tukang Pipa
L.04 0.010 OH Mandor
B Bahan
1.00 buah Pipa Fiting PVC - INCREASER (D-IN) 4" X 2"
C PERALATAN
D JUMLAH A + B + C
E Over Head & Profit 10%
F Harga Satuan Pekerjaan (D+E)

48 A.7.1.2.48 1 buah Pemasangan 1 buah Pipa Fiting PVC - INCREASER (D-IN) 4" X 2
A Tenaga
L.01 0.020 OH Pekerja
L.02 0.020 OH Tukang Pipa
L.04 0.010 OH Mandor
B Bahan
1.00 buah Pipa Fiting PVC - INCREASER (D-IN) 4" X 2 1/2
C PERALATAN
D JUMLAH A + B + C
E Over Head & Profit 10%
F Harga Satuan Pekerjaan (D+E)

49 A.7.1.2.49 1 buah Pemasangan 1 buah Pipa Fiting PVC - INCREASER (D-IN) 4" X 3
A Tenaga
L.01 0.020 OH Pekerja
L.02 0.020 OH Tukang Pipa
L.04 0.010 OH Mandor
B Bahan
1.00 buah Pipa Fiting PVC - INCREASER (D-IN) 4" X 3"
C PERALATAN
D JUMLAH A + B + C
E Over Head & Profit 10%
F Harga Satuan Pekerjaan (D+E)

50 A.7.1.2.50 1 buah Pemasangan 1 buah Pipa Fiting PVC - INCREASER (D-IN) 5" X 4
A Tenaga
L.01 0.020 OH Pekerja
L.02 0.020 OH Tukang Pipa
L.04 0.010 OH Mandor
B Bahan
1.00 buah Pipa Fiting PVC - INCREASER (D-IN) 5" X 4"
C PERALATAN
D JUMLAH A + B + C
E Over Head & Profit 10%
F Harga Satuan Pekerjaan (D+E)

51 A.7.1.2.51 1 buah Pemasangan 1 buah Pipa Fiting PVC - INCREASER (D-IN) 6" X 3
A Tenaga
L.01 0.020 OH Pekerja
L.02 0.020 OH Tukang Pipa
L.04 0.010 OH Mandor
B Bahan
1.00 buah Pipa Fiting PVC - INCREASER (D-IN) 6" X 3"
C PERALATAN
D JUMLAH A + B + C
E Over Head & Profit 10%
F Harga Satuan Pekerjaan (D+E)

52 A.7.1.2.52 1 buah Pemasangan 1 buah Pipa Fiting PVC - INCREASER (D-IN) 6" X 4
A Tenaga
L.01 0.020 OH Pekerja
L.02 0.020 OH Tukang Pipa
L.04 0.010 OH Mandor
B Bahan
1.00 buah Pipa Fiting PVC - INCREASER (D-IN) 6" X 4"
C PERALATAN
D JUMLAH A + B + C
E Over Head & Profit 10%
F Harga Satuan Pekerjaan (D+E)

53 A.7.1.2.53 1 buah Pemasangan 1 buah Pipa Fiting PVC - INCREASER (D-IN) 6" X 5
A Tenaga
L.01 0.020 OH Pekerja
L.02 0.020 OH Tukang Pipa
L.04 0.010 OH Mandor
B Bahan
1.00 buah Pipa Fiting PVC - INCREASER (D-IN) 6" X 5"
C PERALATAN
D JUMLAH A + B + C
E Over Head & Profit 10%
F Harga Satuan Pekerjaan (D+E)

54 A.7.1.2.54 1 buah Pemasangan 1 buah Pipa Fiting PVC - INCREASER (D-IN) 8" X 4
A Tenaga
L.01 0.020 OH Pekerja
L.02 0.020 OH Tukang Pipa
L.04 0.010 OH Mandor
B Bahan
1.00 buah Pipa Fiting PVC - INCREASER (D-IN) 8" X 4"
C PERALATAN
D JUMLAH A + B + C
E Over Head & Profit 10%
F Harga Satuan Pekerjaan (D+E)

55 A.7.1.2.55 1 buah Pemasangan 1 buah Pipa Fiting PVC - INCREASER (D-IN) 8" X 6
A Tenaga
L.01 0.020 OH Pekerja
L.02 0.020 OH Tukang Pipa
L.04 0.010 OH Mandor
B Bahan
1.00 buah Pipa Fiting PVC - INCREASER (D-IN) 8" X 6"
C PERALATAN
D JUMLAH A + B + C
E Over Head & Profit 10%
F Harga Satuan Pekerjaan (D+E)

56 A.7.1.2.56 1 buah Pemasangan 1 buah Pipa Fiting PVC - CAP (D) 1 1/4"
A Tenaga
L.01 0.020 OH Pekerja
L.02 0.020 OH Tukang Pipa
L.04 0.010 OH Mandor
B Bahan
1.00 buah Pipa Fiting PVC - CAP (D) 1 1/4"
C PERALATAN
D JUMLAH A + B + C
E Over Head & Profit 10%
F Harga Satuan Pekerjaan (D+E)

57 A.7.1.2.57 1 buah Pemasangan 1 buah Pipa Fiting PVC - CAP (D) 1 1/2"
A Tenaga
L.01 0.020 OH Pekerja
L.02 0.020 OH Tukang Pipa
L.04 0.010 OH Mandor
B Bahan
1.00 buah Pipa Fiting PVC - CAP (D) 1 1/2"
C PERALATAN
D JUMLAH A + B + C
E Over Head & Profit 10%
F Harga Satuan Pekerjaan (D+E)

58 A.7.1.2.58 1 buah Pemasangan 1 buah Pipa Fiting PVC - CAP (D) 2"
A Tenaga
L.01 0.020 OH Pekerja
L.02 0.020 OH Tukang Pipa
L.04 0.010 OH Mandor
B Bahan
1.00 buah Pipa Fiting PVC - CAP (D) 2"
C PERALATAN
D JUMLAH A + B + C
E Over Head & Profit 10%
F Harga Satuan Pekerjaan (D+E)

59 A.7.1.2.59 1 buah Pemasangan 1 buah Pipa Fiting PVC - CAP (D) 3"
A Tenaga
L.01 0.020 OH Pekerja
L.02 0.020 OH Tukang Pipa
L.04 0.010 OH Mandor
B Bahan
1.00 buah Pipa Fiting PVC - CAP (D) 3"
C PERALATAN
D JUMLAH A + B + C
E Over Head & Profit 10%
F Harga Satuan Pekerjaan (D+E)

60 A.7.1.2.60 1 buah Pemasangan 1 buah Pipa Fiting PVC - CAP (D) 4"
A Tenaga
L.01 0.020 OH Pekerja
L.02 0.020 OH Tukang Pipa
L.04 0.010 OH Mandor
B Bahan
1.00 buah Pipa Fiting PVC - CAP (D) 4"
C PERALATAN
D JUMLAH A + B + C
E Over Head & Profit 10%
F Harga Satuan Pekerjaan (D+E)

61 A.7.1.2.61 1 buah Pemasangan 1 buah Fiting PVC - SOCKET (AW) 1/2"


A Tenaga
L.01 0.020 OH Pekerja
L.02 0.020 OH Tukang Pipa
L.04 0.010 OH Mandor
B Bahan
1.00 buah Fiting PVC - SOCKET (AW) 1/2"
C PERALATAN
D JUMLAH A + B + C
E Over Head & Profit 10%
F Harga Satuan Pekerjaan (D+E)

62 A.7.1.2.62 1 buah Pemasangan 1 buah Fiting PVC - SOCKET (AW) 3/4"


A Tenaga
L.01 0.020 OH Pekerja
L.02 0.020 OH Tukang Pipa
L.04 0.010 OH Mandor
B Bahan
1.00 buah Fiting PVC - SOCKET (AW) 3/4"
C PERALATAN
D JUMLAH A + B + C
E Over Head & Profit 10%
F Harga Satuan Pekerjaan (D+E)

63 A.7.1.2.63 1 buah Pemasangan 1 buah Fiting PVC - SOCKET (AW) 1"


A Tenaga
L.01 0.020 OH Pekerja
L.02 0.020 OH Tukang Pipa
L.04 0.010 OH Mandor
B Bahan
1.00 buah Fiting PVC - SOCKET (AW) 1"
C PERALATAN
D JUMLAH A + B + C
E Over Head & Profit 10%
F Harga Satuan Pekerjaan (D+E)

64 A.7.1.2.64 1 buah Pemasangan 1 buah Fiting PVC - SOCKET (AW) 1 1/4"


A Tenaga
L.01 0.020 OH Pekerja
L.02 0.020 OH Tukang Pipa
L.04 0.010 OH Mandor
B Bahan
1.00 buah Fiting PVC - SOCKET (AW) 1 1/4"
C PERALATAN
D JUMLAH A + B + C
E Over Head & Profit 10%
F Harga Satuan Pekerjaan (D+E)
65 A.7.1.2.65 1 buah Pemasangan 1 buah Fiting PVC - SOCKET (AW) 1 1/2"
A Tenaga
L.01 0.020 OH Pekerja
L.02 0.020 OH Tukang Pipa
L.04 0.010 OH Mandor
B Bahan
1.00 buah Fiting PVC - SOCKET (AW) 1 1/2"
C PERALATAN
D JUMLAH A + B + C
E Over Head & Profit 10%
F Harga Satuan Pekerjaan (D+E)

66 A.7.1.2.66 1 buah Pemasangan 1 buah Fiting PVC - SOCKET (AW) 2"


A Tenaga
L.01 0.020 OH Pekerja
L.02 0.020 OH Tukang Pipa
L.04 0.010 OH Mandor
B Bahan
1.00 buah Fiting PVC - SOCKET (AW) 2"
C PERALATAN
D JUMLAH A + B + C
E Over Head & Profit 10%
F Harga Satuan Pekerjaan (D+E)

67 A.7.1.2.67 1 buah Pemasangan 1 buah Fiting PVC - SOCKET (AW) 2 1/2"


A Tenaga
L.01 0.020 OH Pekerja
L.02 0.020 OH Tukang Pipa
L.04 0.010 OH Mandor
B Bahan
1.00 buah Fiting PVC - SOCKET (AW) 2 1/2"
C PERALATAN
D JUMLAH A + B + C
E Over Head & Profit 10%
F Harga Satuan Pekerjaan (D+E)
68 A.7.1.2.68 1 buah Pemasangan 1 buah Fiting PVC - SOCKET (AW) 3"
A Tenaga
L.01 0.020 OH Pekerja
L.02 0.020 OH Tukang Pipa
L.04 0.010 OH Mandor
B Bahan
1.00 buah Fiting PVC - SOCKET (AW) 3"
C PERALATAN
D JUMLAH A + B + C
E Over Head & Profit 10%
F Harga Satuan Pekerjaan (D+E)

69 A.7.1.2.69 1 buah Pemasangan 1 buah Fiting PVC - SOCKET (AW) 4"


A Tenaga
L.01 0.020 OH Pekerja
L.02 0.020 OH Tukang Pipa
L.04 0.010 OH Mandor
B Bahan
1.00 buah Fiting PVC - SOCKET (AW) 4"
C PERALATAN
D JUMLAH A + B + C
E Over Head & Profit 10%
F Harga Satuan Pekerjaan (D+E)

70 A.7.1.2.70 1 buah Pemasangan 1 buah Fiting PVC - SOCKET (AW) 6"


A Tenaga
L.01 0.020 OH Pekerja
L.02 0.020 OH Tukang Pipa
L.04 0.010 OH Mandor
B Bahan
1.00 buah Fiting PVC - SOCKET (AW) 6"
C PERALATAN
D JUMLAH A + B + C
E Over Head & Profit 10%
F Harga Satuan Pekerjaan (D+E)

71 A.7.1.2.71 1 buah Pemasangan 1 buah Fiting PVC - SOCKET (AW) 8"


A Tenaga
L.01 0.020 OH Pekerja
L.02 0.020 OH Tukang Pipa
L.04 0.010 OH Mandor
B Bahan
1.00 buah Fiting PVC - SOCKET (AW) 8"
C PERALATAN
D JUMLAH A + B + C
E Over Head & Profit 10%
F Harga Satuan Pekerjaan (D+E)

72 A.7.1.2.72 1 buah Pemasangan 1 buah Fiting PVC - SOCKET (AW) 10"


A Tenaga
L.01 0.020 OH Pekerja
L.02 0.020 OH Tukang Pipa
L.04 0.010 OH Mandor
B Bahan
1.00 buah Fiting PVC - SOCKET (AW) 10"
C PERALATAN
D JUMLAH A + B + C
E Over Head & Profit 10%
F Harga Satuan Pekerjaan (D+E)

73 A.7.1.2.73 1 buah Pemasangan 1 buah Fiting PVC - VALVE SOCKET (AW) 1/2"
A Tenaga
L.01 0.020 OH Pekerja
L.02 0.020 OH Tukang Pipa
L.04 0.010 OH Mandor
B Bahan
1.00 buah Fiting PVC - VALVE SOCKET (AW) 1/2"
C PERALATAN
D JUMLAH A + B + C
E Over Head & Profit 10%
F Harga Satuan Pekerjaan (D+E)

74 A.7.1.2.74 1 buah Pemasangan 1 buah Fiting PVC - VALVE SOCKET (AW) 1/2" X 3
A Tenaga
L.01 0.020 OH Pekerja
L.02 0.020 OH Tukang Pipa
L.04 0.010 OH Mandor
B Bahan
1.00 buah Fiting PVC - VALVE SOCKET (AW) 1/2" X 3/4"
C PERALATAN
D JUMLAH A + B + C
E Over Head & Profit 10%
F Harga Satuan Pekerjaan (D+E)

75 A.7.1.2.75 1 buah Pemasangan 1 buah Fiting PVC - VALVE SOCKET (AW) 3/4"
A Tenaga
L.01 0.020 OH Pekerja
L.02 0.020 OH Tukang Pipa
L.04 0.010 OH Mandor
B Bahan
1.00 buah Fiting PVC - VALVE SOCKET (AW) 3/4"
C PERALATAN
D JUMLAH A + B + C
E Over Head & Profit 10%
F Harga Satuan Pekerjaan (D+E)

76 A.7.1.2.76 1 buah Pemasangan 1 buah Fiting PVC - VALVE SOCKET (AW) 1" x 1/
A Tenaga
L.01 0.020 OH Pekerja
L.02 0.020 OH Tukang Pipa
L.04 0.010 OH Mandor
B Bahan
1.00 buah Fiting PVC - VALVE SOCKET (AW) 1" x 1/2"
C PERALATAN
D JUMLAH A + B + C
E Over Head & Profit 10%
F Harga Satuan Pekerjaan (D+E)

77 A.7.1.2.77 1 buah Pemasangan 1 buah Fiting PVC - VALVE SOCKET (AW) 1" x 3/
A Tenaga
L.01 0.020 OH Pekerja
L.02 0.020 OH Tukang Pipa
L.04 0.010 OH Mandor
B Bahan
1.00 buah Fiting PVC - VALVE SOCKET (AW) 1" x 3/4"
C PERALATAN
D JUMLAH A + B + C
E Over Head & Profit 10%
F Harga Satuan Pekerjaan (D+E)

78 A.7.1.2.78 1 buah Pemasangan 1 buah Fiting PVC - VALVE SOCKET (AW) 1"
A Tenaga
L.01 0.020 OH Pekerja
L.02 0.020 OH Tukang Pipa
L.04 0.010 OH Mandor
B Bahan
1.00 buah Fiting PVC - VALVE SOCKET (AW) 1"
C PERALATAN
D JUMLAH A + B + C
E Over Head & Profit 10%
F Harga Satuan Pekerjaan (D+E)

79 A.7.1.2.79 1 buah Pemasangan 1 buah Fiting PVC - VALVE SOCKET (AW) 1 1/4"
A Tenaga
L.01 0.020 OH Pekerja
L.02 0.020 OH Tukang Pipa
L.04 0.010 OH Mandor
B Bahan
1.00 buah Fiting PVC - VALVE SOCKET (AW) 1 1/4"
C PERALATAN
D JUMLAH A + B + C
E Over Head & Profit 10%
F Harga Satuan Pekerjaan (D+E)

80 A.7.1.2.80 1 buah Pemasangan 1 buah Fiting PVC - VALVE SOCKET (AW) 1 1/2"
A Tenaga
L.01 0.020 OH Pekerja
L.02 0.020 OH Tukang Pipa
L.04 0.010 OH Mandor
B Bahan
1.00 buah Fiting PVC - VALVE SOCKET (AW) 1 1/2"
C PERALATAN
D JUMLAH A + B + C
E Over Head & Profit 10%
F Harga Satuan Pekerjaan (D+E)

81 A.7.1.2.81 1 buah Pemasangan 1 buah Fiting PVC - VALVE SOCKET (AW) 2"
A Tenaga
L.01 0.020 OH Pekerja
L.02 0.020 OH Tukang Pipa
L.04 0.010 OH Mandor
B Bahan
1.00 buah Fiting PVC - VALVE SOCKET (AW) 2"
C PERALATAN
D JUMLAH A + B + C
E Over Head & Profit 10%
F Harga Satuan Pekerjaan (D+E)

82 A.7.1.2.82 1 buah Pemasangan 1 buah Fiting PVC - VALVE SOCKET (AW) 3"
A Tenaga
L.01 0.020 OH Pekerja
L.02 0.020 OH Tukang Pipa
L.04 0.010 OH Mandor
B Bahan
1.00 buah Fiting PVC - VALVE SOCKET (AW) 3"
C PERALATAN
D JUMLAH A + B + C
E Over Head & Profit 10%
F Harga Satuan Pekerjaan (D+E)

83 A.7.1.2.83 1 buah Pemasangan 1 buah Fiting PVC - VALVE SOCKET (AW) 4"
A Tenaga
L.01 0.020 OH Pekerja
L.02 0.020 OH Tukang Pipa
L.04 0.010 OH Mandor
B Bahan
1.00 buah Fiting PVC - VALVE SOCKET (AW) 4"
C PERALATAN
D JUMLAH A + B + C
E Over Head & Profit 10%
F Harga Satuan Pekerjaan (D+E)

84 A.7.1.2.84 1 buah Pemasangan 1 buah Fiting PVC - FAUCET SOCKET (AW) 1/2"
A Tenaga
L.01 0.020 OH Pekerja
L.02 0.020 OH Tukang Pipa
L.04 0.010 OH Mandor
B Bahan
1.00 buah Fiting PVC - FAUCET SOCKET (AW) 1/2"
C PERALATAN
D JUMLAH A + B + C
E Over Head & Profit 10%
F Harga Satuan Pekerjaan (D+E)

85 A.7.1.2.85 1 buah Pemasangan 1 buah Fiting PVC - FAUCET SOCKET (AW) 1/2" x
A Tenaga
L.01 0.020 OH Pekerja
L.02 0.020 OH Tukang Pipa
L.04 0.010 OH Mandor
B Bahan
1.00 buah Fiting PVC - FAUCET SOCKET (AW) 1/2" x 3/4"
C PERALATAN
D JUMLAH A + B + C
E Over Head & Profit 10%
F Harga Satuan Pekerjaan (D+E)

86 A.7.1.2.86 1 buah Pemasangan 1 buah Fiting PVC - FAUCET SOCKET (AW) 3/4"
A Tenaga
L.01 0.020 OH Pekerja
L.02 0.020 OH Tukang Pipa
L.04 0.010 OH Mandor
B Bahan
1.00 buah Fiting PVC - FAUCET SOCKET (AW) 3/4"
C PERALATAN
D JUMLAH A + B + C
E Over Head & Profit 10%
F Harga Satuan Pekerjaan (D+E)

87 A.7.1.2.87 1 buah Pemasangan 1 buah Fiting PVC - FAUCET SOCKET (AW) 1" x 1
A Tenaga
L.01 0.020 OH Pekerja
L.02 0.020 OH Tukang Pipa
L.04 0.010 OH Mandor
B Bahan
1.00 buah Fiting PVC - FAUCET SOCKET (AW) 1" x 1/2"
C PERALATAN
D JUMLAH A + B + C
E Over Head & Profit 10%
F Harga Satuan Pekerjaan (D+E)

88 A.7.1.2.88 1 buah Pemasangan 1 buah Fiting PVC - FAUCET SOCKET (AW) 1" x 3
A Tenaga
L.01 0.020 OH Pekerja
L.02 0.020 OH Tukang Pipa
L.04 0.010 OH Mandor
B Bahan
1.00 buah Fiting PVC - FAUCET SOCKET (AW) 1" x 3/4"
C PERALATAN
D JUMLAH A + B + C
E Over Head & Profit 10%
F Harga Satuan Pekerjaan (D+E)

89 A.7.1.2.89 1 buah Pemasangan 1 buah Fiting PVC - FAUCET SOCKET (AW) 1"
A Tenaga
L.01 0.020 OH Pekerja
L.02 0.020 OH Tukang Pipa
L.04 0.010 OH Mandor
B Bahan
1.00 buah Fiting PVC - FAUCET SOCKET (AW) 1"
C PERALATAN
D JUMLAH A + B + C
E Over Head & Profit 10%
F Harga Satuan Pekerjaan (D+E)

90 A.7.1.2.90 1 buah Pemasangan 1 buah Fiting PVC - FAUCET SOCKET (AW) 1 1/4"
A Tenaga
L.01 0.020 OH Pekerja
L.02 0.020 OH Tukang Pipa
L.04 0.010 OH Mandor
B Bahan
1.00 buah Fiting PVC - FAUCET SOCKET (AW) 1 1/4"
C PERALATAN
D JUMLAH A + B + C
E Over Head & Profit 10%
F Harga Satuan Pekerjaan (D+E)

91 A.7.1.2.91 1 buah Pemasangan 1 buah Fiting PVC - FAUCET SOCKET (AW) 1 1/2"
A Tenaga
L.01 0.020 OH Pekerja
L.02 0.020 OH Tukang Pipa
L.04 0.010 OH Mandor
B Bahan
1.00 buah Fiting PVC - FAUCET SOCKET (AW) 1 1/2"
C PERALATAN
D JUMLAH A + B + C
E Over Head & Profit 10%
F Harga Satuan Pekerjaan (D+E)

92 A.7.1.2.92 1 buah Pemasangan 1 buah Fiting PVC - FAUCET SOCKET (AW) 2"
A Tenaga
L.01 0.020 OH Pekerja
L.02 0.020 OH Tukang Pipa
L.04 0.010 OH Mandor
B Bahan
1.00 buah Fiting PVC - FAUCET SOCKET (AW) 2"
C PERALATAN
D JUMLAH A + B + C
E Over Head & Profit 10%
F Harga Satuan Pekerjaan (D+E)

93 A.7.1.2.93 1 buah Pemasangan 1 buah Fiting PVC - TEE (AW) 1/2"


A Tenaga
L.01 0.020 OH Pekerja
L.02 0.020 OH Tukang Pipa
L.04 0.010 OH Mandor
B Bahan
1.00 buah Fiting PVC - TEE (AW) 1/2"
C PERALATAN
D JUMLAH A + B + C
E Over Head & Profit 10%
F Harga Satuan Pekerjaan (D+E)

94 A.7.1.2.94 1 buah Pemasangan 1 buah Fiting PVC - TEE (AW) 3/4" x 1/2"
A Tenaga
L.01 0.020 OH Pekerja
L.02 0.020 OH Tukang Pipa
L.04 0.010 OH Mandor
B Bahan
1.00 buah Fiting PVC - TEE (AW) 3/4" x 1/2"
C PERALATAN
D JUMLAH A + B + C
E Over Head & Profit 10%
F Harga Satuan Pekerjaan (D+E)

95 A.7.1.2.95 1 buah Pemasangan 1 buah Fiting PVC - TEE (AW) 3/4"


A Tenaga
L.01 0.020 OH Pekerja
L.02 0.020 OH Tukang Pipa
L.04 0.010 OH Mandor
B Bahan
1.00 buah Fiting PVC - TEE (AW) 3/4"
C PERALATAN
D JUMLAH A + B + C
E Over Head & Profit 10%
F Harga Satuan Pekerjaan (D+E)

96 A.7.1.2.96 1 buah Pemasangan 1 buah Fiting PVC - TEE (AW) 1" x 1/2"
A Tenaga
L.01 0.020 OH Pekerja
L.02 0.020 OH Tukang Pipa
L.04 0.010 OH Mandor
B Bahan
1.00 buah Fiting PVC - TEE (AW) 1" x 1/2"
C PERALATAN
D JUMLAH A + B + C
E Over Head & Profit 10%
F Harga Satuan Pekerjaan (D+E)

97 A.7.1.2.97 1 buah Pemasangan 1 buah Fiting PVC - TEE (AW) 1" x 3/4"
A Tenaga
L.01 0.020 OH Pekerja
L.02 0.020 OH Tukang Pipa
L.04 0.010 OH Mandor
B Bahan
1.00 buah Fiting PVC - TEE (AW) 1" x 3/4"
C PERALATAN
D JUMLAH A + B + C
E Over Head & Profit 10%
F Harga Satuan Pekerjaan (D+E)

98 A.7.1.2.98 1 buah Pemasangan 1 buah Fiting PVC - TEE (AW) 1"


A Tenaga
L.01 0.020 OH Pekerja
L.02 0.020 OH Tukang Pipa
L.04 0.010 OH Mandor
B Bahan
1.00 buah Fiting PVC - TEE (AW) 1"
C PERALATAN
D JUMLAH A + B + C
E Over Head & Profit 10%
F Harga Satuan Pekerjaan (D+E)

99 A.7.1.2.99 1 buah Pemasangan 1 buah Fiting PVC - TEE (AW) 1 1/4" x 1/2"
A Tenaga
L.01 0.020 OH Pekerja
L.02 0.020 OH Tukang Pipa
L.04 0.010 OH Mandor
B Bahan
1.00 buah Fiting PVC - TEE (AW) 1 1/4" x 1/2"
C PERALATAN
D JUMLAH A + B + C
E Over Head & Profit 10%
F Harga Satuan Pekerjaan (D+E)
100 A.7.1.2.100 1 buah Pemasangan 1 buah Fiting PVC - TEE (AW) 1 1/4" x 3/4"
A Tenaga
L.01 0.020 OH Pekerja
L.02 0.020 OH Tukang Pipa
L.04 0.010 OH Mandor
B Bahan
1.00 buah Fiting PVC - TEE (AW) 1 1/4" x 3/4"
C PERALATAN
D JUMLAH A + B + C
E Over Head & Profit 10%
F Harga Satuan Pekerjaan (D+E)

101 A.7.1.2.101 1 buah Pemasangan 1 buah Fiting PVC - TEE (AW) 1 1/4" x 1"
A Tenaga
L.01 0.020 OH Pekerja
L.02 0.020 OH Tukang Pipa
L.04 0.010 OH Mandor
B Bahan
1.00 buah Fiting PVC - TEE (AW) 1 1/4" x 1"
C PERALATAN
D JUMLAH A + B + C
E Over Head & Profit 10%
F Harga Satuan Pekerjaan (D+E)

102 A.7.1.2.102 1 buah Pemasangan 1 buah Fiting PVC - TEE (AW) 1 1/4"
A Tenaga
L.01 0.020 OH Pekerja
L.02 0.020 OH Tukang Pipa
L.04 0.010 OH Mandor
B Bahan
1.00 buah Fiting PVC - TEE (AW) 1 1/4"
C PERALATAN
D JUMLAH A + B + C
E Over Head & Profit 10%
F Harga Satuan Pekerjaan (D+E)
103 A.7.1.2.103 1 buah Pemasangan 1 buah Fiting PVC - TEE (AW) 1 1/2" x 1/2"
A Tenaga
L.01 0.020 OH Pekerja
L.02 0.020 OH Tukang Pipa
L.04 0.010 OH Mandor
B Bahan
1.00 buah Fiting PVC - TEE (AW) 1 1/2" x 1/2"
C PERALATAN
D JUMLAH A + B + C
E Over Head & Profit 10%
F Harga Satuan Pekerjaan (D+E)

104 A.7.1.2.104 1 buah Pemasangan 1 buah Fiting PVC - TEE (AW) 1 1/2" x 3/4"
A Tenaga
L.01 0.020 OH Pekerja
L.02 0.020 OH Tukang Pipa
L.04 0.010 OH Mandor
B Bahan
1.00 buah Fiting PVC - TEE (AW) 1 1/2" x 3/4"
C PERALATAN
D JUMLAH A + B + C
E Over Head & Profit 10%
F Harga Satuan Pekerjaan (D+E)

105 A.7.1.2.105 1 buah Pemasangan 1 buah Fiting PVC - TEE (AW) 1 1/2" x 1"
A Tenaga
L.01 0.020 OH Pekerja
L.02 0.020 OH Tukang Pipa
L.04 0.010 OH Mandor
B Bahan
1.00 buah Fiting PVC - TEE (AW) 1 1/2" x 1"
C PERALATAN
D JUMLAH A + B + C
E Over Head & Profit 10%
F Harga Satuan Pekerjaan (D+E)

106 A.7.1.2.106 1 buah Pemasangan 1 buah Fiting PVC - TEE (AW) 1 1/2" x 1 1/4"
A Tenaga
L.01 0.020 OH Pekerja
L.02 0.020 OH Tukang Pipa
L.04 0.010 OH Mandor
B Bahan
1.00 buah Fiting PVC - TEE (AW) 1 1/2" x 1 1/4"
C PERALATAN
D JUMLAH A + B + C
E Over Head & Profit 10%
F Harga Satuan Pekerjaan (D+E)

107 A.7.1.2.107 1 buah Pemasangan 1 buah Fiting PVC - TEE (AW) 1 1/2"
A Tenaga
L.01 0.020 OH Pekerja
L.02 0.020 OH Tukang Pipa
L.04 0.010 OH Mandor
B Bahan
1.00 buah Fiting PVC - TEE (AW) 1 1/2"
C PERALATAN
D JUMLAH A + B + C
E Over Head & Profit 10%
F Harga Satuan Pekerjaan (D+E)

108 A.7.1.2.108 1 buah Pemasangan 1 buah Fiting PVC - TEE (AW) 2" x 1/2"
A Tenaga
L.01 0.020 OH Pekerja
L.02 0.020 OH Tukang Pipa
L.04 0.010 OH Mandor
B Bahan
1.00 buah Fiting PVC - TEE (AW) 2" x 1/2"
C PERALATAN
D JUMLAH A + B + C
E Over Head & Profit 10%
F Harga Satuan Pekerjaan (D+E)

109 A.7.1.2.109 1 buah Pemasangan 1 buah Fiting PVC - TEE (AW) 2" x 3/4"
A Tenaga
L.01 0.020 OH Pekerja
L.02 0.020 OH Tukang Pipa
L.04 0.010 OH Mandor
B Bahan
1.00 buah Fiting PVC - TEE (AW) 2" x 3/4"
C PERALATAN
D JUMLAH A + B + C
E Over Head & Profit 10%
F Harga Satuan Pekerjaan (D+E)

110 A.7.1.2.110 1 buah Pemasangan 1 buah Fiting PVC - TEE (AW) 2" x 1"
A Tenaga
L.01 0.020 OH Pekerja
L.02 0.020 OH Tukang Pipa
L.04 0.010 OH Mandor
B Bahan
1.00 buah Fiting PVC - TEE (AW) 2" x 1"
C PERALATAN
D JUMLAH A + B + C
E Over Head & Profit 10%
F Harga Satuan Pekerjaan (D+E)

111 A.7.1.2.111 1 buah Pemasangan 1 buah Fiting PVC - TEE (AW) 2" x 1 1/4"
A Tenaga
L.01 0.020 OH Pekerja
L.02 0.020 OH Tukang Pipa
L.04 0.010 OH Mandor
B Bahan
1.00 buah Fiting PVC - TEE (AW) 2" x 1 1/4"
C PERALATAN
D JUMLAH A + B + C
E Over Head & Profit 10%
F Harga Satuan Pekerjaan (D+E)

112 A.7.1.2.112 1 buah Pemasangan 1 buah Fiting PVC - TEE (AW) 2" x 1 1/2"
A Tenaga
L.01 0.020 OH Pekerja
L.02 0.020 OH Tukang Pipa
L.04 0.010 OH Mandor
B Bahan
1.00 buah Fiting PVC - TEE (AW) 2" x 1 1/2"
C PERALATAN
D JUMLAH A + B + C
E Over Head & Profit 10%
F Harga Satuan Pekerjaan (D+E)

113 A.7.1.2.113 1 buah Pemasangan 1 buah Fiting PVC - TEE (AW) 2"
A Tenaga
L.01 0.020 OH Pekerja
L.02 0.020 OH Tukang Pipa
L.04 0.010 OH Mandor
B Bahan
1.00 buah Fiting PVC - TEE (AW) 2"
C PERALATAN
D JUMLAH A + B + C
E Over Head & Profit 10%
F Harga Satuan Pekerjaan (D+E)

114 A.7.1.2.114 1 buah Pemasangan 1 buah Fiting PVC - TEE (AW) 2 1/2"
A Tenaga
L.01 0.020 OH Pekerja
L.02 0.020 OH Tukang Pipa
L.04 0.010 OH Mandor
B Bahan
1.00 buah Fiting PVC - TEE (AW) 2 1/2"
C PERALATAN
D JUMLAH A + B + C
E Over Head & Profit 10%
F Harga Satuan Pekerjaan (D+E)

115 A.7.1.2.115 1 buah Pemasangan 1 buah Fiting PVC - TEE (AW) 3" x 2"
A Tenaga
L.01 0.020 OH Pekerja
L.02 0.020 OH Tukang Pipa
L.04 0.010 OH Mandor
B Bahan
1.00 buah Fiting PVC - TEE (AW) 3" x 2"
C PERALATAN
D JUMLAH A + B + C
E Over Head & Profit 10%
F Harga Satuan Pekerjaan (D+E)

116 A.7.1.2.116 1 buah Pemasangan 1 buah Fiting PVC - TEE (AW) 3"
A Tenaga
L.01 0.020 OH Pekerja
L.02 0.020 OH Tukang Pipa
L.04 0.010 OH Mandor
B Bahan
1.00 buah Fiting PVC - TEE (AW) 3"
C PERALATAN
D JUMLAH A + B + C
E Over Head & Profit 10%
F Harga Satuan Pekerjaan (D+E)

117 A.7.1.2.117 1 buah Pemasangan 1 buah Fiting PVC - TEE (AW) 4"
A Tenaga
L.01 0.020 OH Pekerja
L.02 0.020 OH Tukang Pipa
L.04 0.010 OH Mandor
B Bahan
1.00 buah Fiting PVC - TEE (AW) 4"
C PERALATAN
D JUMLAH A + B + C
E Over Head & Profit 10%
F Harga Satuan Pekerjaan (D+E)

118 A.7.1.2.118 1 buah Pemasangan 1 buah Fiting PVC - TEE (AW) 6"
A Tenaga
L.01 0.020 OH Pekerja
L.02 0.020 OH Tukang Pipa
L.04 0.010 OH Mandor
B Bahan
1.00 buah Fiting PVC - TEE (AW) 6"
C PERALATAN
D JUMLAH A + B + C
E Over Head & Profit 10%
F Harga Satuan Pekerjaan (D+E)

119 A.7.1.2.119 1 buah Pemasangan 1 buah Fiting PVC - TEE (AW) 8"
A Tenaga
L.01 0.020 OH Pekerja
L.02 0.020 OH Tukang Pipa
L.04 0.010 OH Mandor
B Bahan
1.00 buah Fiting PVC - TEE (AW) 8"
C PERALATAN
D JUMLAH A + B + C
E Over Head & Profit 10%
F Harga Satuan Pekerjaan (D+E)
HARGA
JUMLAH
BAHAN/UPAH
Rp Rp
VC - ELBOW (D-DL) 1 1/4" 9,229.00
4,390.00
82,000.00 1,640.00
90,000.00 1,800.00
95,000.00 950.00
4,000.00
4,000.00 4,000.00

8,390.00
839.00
9,229.00

VC - ELBOW (D-DL) 1 1/2" 14,069.00


4,390.00
82,000.00 1,640.00
90,000.00 1,800.00
95,000.00 950.00
8,400.00
8,400.00 8,400.00

12,790.00
1,279.00
14,069.00

VC - ELBOW (D-DL) 2" 19,129.00


4,390.00
82,000.00 1,640.00
90,000.00 1,800.00
95,000.00 950.00
13,000.00
13,000.00 13,000.00

17,390.00
1,739.00
19,129.00

VC - ELBOW (D-DL) 2 1/2" 20,449.00


4,390.00
82,000.00 1,640.00
90,000.00 1,800.00
95,000.00 950.00
14,200.00
14,200.00 14,200.00

18,590.00
1,859.00
20,449.00

VC - ELBOW (D-DL) 3" 27,929.00


4,390.00
82,000.00 1,640.00
90,000.00 1,800.00
95,000.00 950.00
21,000.00
21,000.00 21,000.00

25,390.00
2,539.00
27,929.00

VC - ELBOW (D-DL) 4" 44,979.00


4,390.00
82,000.00 1,640.00
90,000.00 1,800.00
95,000.00 950.00
36,500.00
36,500.00 36,500.00
40,890.00
4,089.00
44,979.00

VC - ELBOW (D-DL) 5" 99,979.00


4,390.00
82,000.00 1,640.00
90,000.00 1,800.00
95,000.00 950.00
86,500.00
86,500.00 86,500.00

90,890.00
9,089.00
99,979.00

VC - ELBOW (D-DL) 6" 104,929.00


4,390.00
82,000.00 1,640.00
90,000.00 1,800.00
95,000.00 950.00
91,000.00
91,000.00 91,000.00

95,390.00
9,539.00
104,929.00

VC - ELBOW (D-DL) 8" 256,729.00


4,390.00
82,000.00 1,640.00
90,000.00 1,800.00
95,000.00 950.00
229,000.00
229,000.00 229,000.00
233,390.00
23,339.00
256,729.00

VC - ELBOW (D-DL) 10" 490,479.00


4,390.00
82,000.00 1,640.00
90,000.00 1,800.00
95,000.00 950.00
441,500.00
441,500.00 441,500.00

445,890.00
44,589.00
490,479.00

VC - ELBOW (D-DL) 12" 667,029.00


4,390.00
82,000.00 1,640.00
90,000.00 1,800.00
95,000.00 950.00
602,000.00
602,000.00 602,000.00

606,390.00
60,639.00
667,029.00

VC - SOCKET (D-DS) 1 1/4" 11,429.00


4,390.00
82,000.00 1,640.00
90,000.00 1,800.00
95,000.00 950.00
6,000.00
6,000.00 6,000.00

10,390.00
1,039.00
11,429.00

VC - SOCKET (D-DS) 1 1/2" 13,629.00


4,390.00
82,000.00 1,640.00
90,000.00 1,800.00
95,000.00 950.00
8,000.00
8,000.00 8,000.00

12,390.00
1,239.00
13,629.00

VC - SOCKET (D-DS) 2" 16,489.00


4,390.00
82,000.00 1,640.00
90,000.00 1,800.00
95,000.00 950.00
10,600.00
10,600.00 10,600.00

14,990.00
1,499.00
16,489.00

VC - SOCKET (D-DS) 2 1/2" 10,329.00


4,390.00
82,000.00 1,640.00
90,000.00 1,800.00
95,000.00 950.00
5,000.00
5,000.00 5,000.00

9,390.00
939.00
10,329.00

VC - SOCKET (D-DS) 3" 26,279.00


4,390.00
82,000.00 1,640.00
90,000.00 1,800.00
95,000.00 950.00
19,500.00
19,500.00 19,500.00

23,890.00
2,389.00
26,279.00

VC - SOCKET (D-DS) 4" 41,129.00


4,390.00
82,000.00 1,640.00
90,000.00 1,800.00
95,000.00 950.00
33,000.00
33,000.00 33,000.00

37,390.00
3,739.00
41,129.00

VC - SOCKET (D-DS) 5" 54,329.00


4,390.00
82,000.00 1,640.00
90,000.00 1,800.00
95,000.00 950.00
45,000.00
45,000.00 45,000.00

49,390.00
4,939.00
54,329.00

VC - SOCKET (D-DS) 6" 60,929.00


4,390.00
82,000.00 1,640.00
90,000.00 1,800.00
95,000.00 950.00
51,000.00
51,000.00 51,000.00

55,390.00
5,539.00
60,929.00

VC - SOCKET (D-DS) 8" 128,029.00


4,390.00
82,000.00 1,640.00
90,000.00 1,800.00
95,000.00 950.00
112,000.00
112,000.00 112,000.00

116,390.00
11,639.00
128,029.00

VC - SOCKET (D-DS) 10" 192,929.00


4,390.00
82,000.00 1,640.00
90,000.00 1,800.00
95,000.00 950.00
171,000.00
171,000.00 171,000.00

175,390.00
17,539.00
192,929.00

VC - TEE (D-DT) 1 1/4" 10,329.00


4,390.00
82,000.00 1,640.00
90,000.00 1,800.00
95,000.00 950.00
5,000.00
5,000.00 5,000.00

9,390.00
939.00
10,329.00

VC - TEE (D-DT) 1 1/2" 19,899.00


4,390.00
82,000.00 1,640.00
90,000.00 1,800.00
95,000.00 950.00
13,700.00
13,700.00 13,700.00

18,090.00
1,809.00
19,899.00

VC - TEE (D-DT) 2" 25,179.00


4,390.00
82,000.00 1,640.00
90,000.00 1,800.00
95,000.00 950.00
18,500.00
18,500.00 18,500.00

22,890.00
2,289.00
25,179.00

VC - TEE (D-DT) 2 1/2" 26,829.00


4,390.00
82,000.00 1,640.00
90,000.00 1,800.00
95,000.00 950.00
20,000.00
20,000.00 20,000.00

24,390.00
2,439.00
26,829.00

VC - TEE (D-DT) 3" x 1 1/2" 16,929.00


4,390.00
82,000.00 1,640.00
90,000.00 1,800.00
95,000.00 950.00
11,000.00
11,000.00 11,000.00

15,390.00
1,539.00
16,929.00

VC - TEE (D-DT) 3" x 2" 38,929.00


4,390.00
82,000.00 1,640.00
90,000.00 1,800.00
95,000.00 950.00
31,000.00
31,000.00 31,000.00

35,390.00
3,539.00
38,929.00

VC - TEE (D-DT) 3" 2 1/2" 20,229.00


4,390.00
82,000.00 1,640.00
90,000.00 1,800.00
95,000.00 950.00
14,000.00
14,000.00 14,000.00

18,390.00
1,839.00
20,229.00

VC - TEE (D-DT) 3" 48,829.00


4,390.00
82,000.00 1,640.00
90,000.00 1,800.00
95,000.00 950.00
40,000.00
40,000.00 40,000.00

44,390.00
4,439.00
48,829.00
VC - TEE (D-DT) 4" x 2" 27,379.00
4,390.00
82,000.00 1,640.00
90,000.00 1,800.00
95,000.00 950.00
20,500.00
20,500.00 20,500.00

24,890.00
2,489.00
27,379.00

VC - TEE (D-DT) 4" x 3" 32,329.00


4,390.00
82,000.00 1,640.00
90,000.00 1,800.00
95,000.00 950.00
25,000.00
25,000.00 25,000.00

29,390.00
2,939.00
32,329.00

VC - TEE (D-DT) 4" 81,279.00


4,390.00
82,000.00 1,640.00
90,000.00 1,800.00
95,000.00 950.00
69,500.00
69,500.00 69,500.00

73,890.00
7,389.00
81,279.00
VC - TEE (D-DT) 5" x 4" 48,829.00
4,390.00
82,000.00 1,640.00
90,000.00 1,800.00
95,000.00 950.00
40,000.00
40,000.00 40,000.00

44,390.00
4,439.00
48,829.00

VC - TEE (D-DT) 5" 53,229.00


4,390.00
82,000.00 1,640.00
90,000.00 1,800.00
95,000.00 950.00
44,000.00
44,000.00 44,000.00

48,390.00
4,839.00
53,229.00

VC - TEE (D-DT) 6" x 4" 68,629.00


4,390.00
82,000.00 1,640.00
90,000.00 1,800.00
95,000.00 950.00
58,000.00
58,000.00 58,000.00

62,390.00
6,239.00
68,629.00

VC - TEE (D-DT) 6" 219,329.00


4,390.00
82,000.00 1,640.00
90,000.00 1,800.00
95,000.00 950.00
195,000.00
195,000.00 195,000.00

199,390.00
19,939.00
219,329.00

VC - TEE (D-DT) 8" x 4" 91,729.00


4,390.00
82,000.00 1,640.00
90,000.00 1,800.00
95,000.00 950.00
79,000.00
79,000.00 79,000.00

83,390.00
8,339.00
91,729.00

VC - TEE (D-DT) 8" 298,529.00


4,390.00
82,000.00 1,640.00
90,000.00 1,800.00
95,000.00 950.00
267,000.00
267,000.00 267,000.00

271,390.00
27,139.00
298,529.00

VC - INCREASER (D-IN) 1 1/2" 9,229.00


4,390.00
82,000.00 1,640.00
90,000.00 1,800.00
95,000.00 950.00
4,000.00
4,000.00 4,000.00

8,390.00
839.00
9,229.00

VC - INCREASER (D-IN) 2" X 1 11,429.00


4,390.00
82,000.00 1,640.00
90,000.00 1,800.00
95,000.00 950.00
6,000.00
6,000.00 6,000.00

10,390.00
1,039.00
11,429.00

VC - INCREASER (D-IN) 2" X 1 12,529.00


4,390.00
82,000.00 1,640.00
90,000.00 1,800.00
95,000.00 950.00
7,000.00
7,000.00 7,000.00
11,390.00
1,139.00
12,529.00

VC - INCREASER (D-IN) 2 1/2" 13,629.00


4,390.00
82,000.00 1,640.00
90,000.00 1,800.00
95,000.00 950.00
8,000.00
8,000.00 8,000.00

12,390.00
1,239.00
13,629.00

VC - INCREASER (D-IN) 2 1/2" 14,729.00


4,390.00
82,000.00 1,640.00
90,000.00 1,800.00
95,000.00 950.00
9,000.00
9,000.00 9,000.00

13,390.00
1,339.00
14,729.00

VC - INCREASER (D-IN) 3" X 1 15,829.00


4,390.00
82,000.00 1,640.00
90,000.00 1,800.00
95,000.00 950.00
10,000.00
10,000.00 10,000.00
14,390.00
1,439.00
15,829.00

VC - INCREASER (D-IN) 3" X 2 18,029.00


4,390.00
82,000.00 1,640.00
90,000.00 1,800.00
95,000.00 950.00
12,000.00
12,000.00 12,000.00

16,390.00
1,639.00
18,029.00

VC - INCREASER (D-IN) 3" X 2 24,409.00


4,390.00
82,000.00 1,640.00
90,000.00 1,800.00
95,000.00 950.00
17,800.00
17,800.00 17,800.00

22,190.00
2,219.00
24,409.00

VC - INCREASER (D-IN) 4" X 2 31,669.00


4,390.00
82,000.00 1,640.00
90,000.00 1,800.00
95,000.00 950.00
24,400.00
24,400.00 24,400.00

28,790.00
2,879.00
31,669.00

VC - INCREASER (D-IN) 4" X 2 29,029.00


4,390.00
82,000.00 1,640.00
90,000.00 1,800.00
95,000.00 950.00
22,000.00
22,000.00 22,000.00

26,390.00
2,639.00
29,029.00

VC - INCREASER (D-IN) 4" X 3 31,229.00


4,390.00
82,000.00 1,640.00
90,000.00 1,800.00
95,000.00 950.00
24,000.00
24,000.00 24,000.00

28,390.00
2,839.00
31,229.00

VC - INCREASER (D-IN) 5" X 4 56,529.00


4,390.00
82,000.00 1,640.00
90,000.00 1,800.00
95,000.00 950.00
47,000.00
47,000.00 47,000.00

51,390.00
5,139.00
56,529.00

VC - INCREASER (D-IN) 6" X 3 75,229.00


4,390.00
82,000.00 1,640.00
90,000.00 1,800.00
95,000.00 950.00
64,000.00
64,000.00 64,000.00

68,390.00
6,839.00
75,229.00

VC - INCREASER (D-IN) 6" X 4 92,829.00


4,390.00
82,000.00 1,640.00
90,000.00 1,800.00
95,000.00 950.00
80,000.00
80,000.00 80,000.00

84,390.00
8,439.00
92,829.00

VC - INCREASER (D-IN) 6" X 5 89,529.00


4,390.00
82,000.00 1,640.00
90,000.00 1,800.00
95,000.00 950.00
77,000.00
77,000.00 77,000.00

81,390.00
8,139.00
89,529.00

VC - INCREASER (D-IN) 8" X 4 130,779.00


4,390.00
82,000.00 1,640.00
90,000.00 1,800.00
95,000.00 950.00
114,500.00
114,500.00 114,500.00

118,890.00
11,889.00
130,779.00

VC - INCREASER (D-IN) 8" X 6 145,299.00


4,390.00
82,000.00 1,640.00
90,000.00 1,800.00
95,000.00 950.00
127,700.00
127,700.00 127,700.00

132,090.00
13,209.00
145,299.00

VC - CAP (D) 1 1/4" 9,229.00


4,390.00
82,000.00 1,640.00
90,000.00 1,800.00
95,000.00 950.00
4,000.00
4,000.00 4,000.00

8,390.00
839.00
9,229.00

VC - CAP (D) 1 1/2" 13,629.00


4,390.00
82,000.00 1,640.00
90,000.00 1,800.00
95,000.00 950.00
8,000.00
8,000.00 8,000.00

12,390.00
1,239.00
13,629.00

VC - CAP (D) 2" 14,729.00


4,390.00
82,000.00 1,640.00
90,000.00 1,800.00
95,000.00 950.00
9,000.00
9,000.00 9,000.00

13,390.00
1,339.00
14,729.00

VC - CAP (D) 3" 19,899.00


4,390.00
82,000.00 1,640.00
90,000.00 1,800.00
95,000.00 950.00
13,700.00
13,700.00 13,700.00

18,090.00
1,809.00
19,899.00

VC - CAP (D) 4" 32,329.00


4,390.00
82,000.00 1,640.00
90,000.00 1,800.00
95,000.00 950.00
25,000.00
25,000.00 25,000.00

29,390.00
2,939.00
32,329.00

SOCKET (AW) 1/2" 8,679.00


4,390.00
82,000.00 1,640.00
90,000.00 1,800.00
95,000.00 950.00
3,500.00
3,500.00 3,500.00

7,890.00
789.00
8,679.00

SOCKET (AW) 3/4" 9,449.00


4,390.00
82,000.00 1,640.00
90,000.00 1,800.00
95,000.00 950.00
4,200.00
4,200.00 4,200.00

8,590.00
859.00
9,449.00

SOCKET (AW) 1" 11,209.00


4,390.00
82,000.00 1,640.00
90,000.00 1,800.00
95,000.00 950.00
5,800.00
5,800.00 5,800.00

10,190.00
1,019.00
11,209.00

SOCKET (AW) 1 1/4" 12,749.00


4,390.00
82,000.00 1,640.00
90,000.00 1,800.00
95,000.00 950.00
7,200.00
7,200.00 7,200.00

11,590.00
1,159.00
12,749.00
SOCKET (AW) 1 1/2" 14,729.00
4,390.00
82,000.00 1,640.00
90,000.00 1,800.00
95,000.00 950.00
9,000.00
9,000.00 9,000.00

13,390.00
1,339.00
14,729.00

SOCKET (AW) 2" 14,729.00


4,390.00
82,000.00 1,640.00
90,000.00 1,800.00
95,000.00 950.00
9,000.00
9,000.00 9,000.00

13,390.00
1,339.00
14,729.00

SOCKET (AW) 2 1/2" 29,029.00


4,390.00
82,000.00 1,640.00
90,000.00 1,800.00
95,000.00 950.00
22,000.00
22,000.00 22,000.00

26,390.00
2,639.00
29,029.00
SOCKET (AW) 3" 52,129.00
4,390.00
82,000.00 1,640.00
90,000.00 1,800.00
95,000.00 950.00
43,000.00
43,000.00 43,000.00

47,390.00
4,739.00
52,129.00

SOCKET (AW) 4" 81,279.00


4,390.00
82,000.00 1,640.00
90,000.00 1,800.00
95,000.00 950.00
69,500.00
69,500.00 69,500.00

73,890.00
7,389.00
81,279.00

SOCKET (AW) 6" 133,529.00


4,390.00
82,000.00 1,640.00
90,000.00 1,800.00
95,000.00 950.00
117,000.00
117,000.00 117,000.00

121,390.00
12,139.00
133,529.00

SOCKET (AW) 8" 278,729.00


4,390.00
82,000.00 1,640.00
90,000.00 1,800.00
95,000.00 950.00
249,000.00
249,000.00 249,000.00

253,390.00
25,339.00
278,729.00

SOCKET (AW) 10" 399,729.00


4,390.00
82,000.00 1,640.00
90,000.00 1,800.00
95,000.00 950.00
359,000.00
359,000.00 359,000.00

363,390.00
36,339.00
399,729.00

VALVE SOCKET (AW) 1/2" 8,129.00


4,390.00
82,000.00 1,640.00
90,000.00 1,800.00
95,000.00 950.00
3,000.00
3,000.00 3,000.00

7,390.00
739.00
8,129.00

VALVE SOCKET (AW) 1/2" X 3 8,129.00


4,390.00
82,000.00 1,640.00
90,000.00 1,800.00
95,000.00 950.00
3,000.00
3,000.00 3,000.00

7,390.00
739.00
8,129.00

VALVE SOCKET (AW) 3/4" 9,229.00


4,390.00
82,000.00 1,640.00
90,000.00 1,800.00
95,000.00 950.00
4,000.00
4,000.00 4,000.00

8,390.00
839.00
9,229.00

VALVE SOCKET (AW) 1" x 1/ 9,229.00


4,390.00
82,000.00 1,640.00
90,000.00 1,800.00
95,000.00 950.00
4,000.00
4,000.00 4,000.00
8,390.00
839.00
9,229.00

VALVE SOCKET (AW) 1" x 3/ 10,329.00


4,390.00
82,000.00 1,640.00
90,000.00 1,800.00
95,000.00 950.00
5,000.00
5,000.00 5,000.00

9,390.00
939.00
10,329.00

VALVE SOCKET (AW) 1" 11,429.00


4,390.00
82,000.00 1,640.00
90,000.00 1,800.00
95,000.00 950.00
6,000.00
6,000.00 6,000.00

10,390.00
1,039.00
11,429.00

VALVE SOCKET (AW) 1 1/4" 9,449.00


4,390.00
82,000.00 1,640.00
90,000.00 1,800.00
95,000.00 950.00
4,200.00
4,200.00 4,200.00
8,590.00
859.00
9,449.00

VALVE SOCKET (AW) 1 1/2" 16,379.00


4,390.00
82,000.00 1,640.00
90,000.00 1,800.00
95,000.00 950.00
10,500.00
10,500.00 10,500.00

14,890.00
1,489.00
16,379.00

VALVE SOCKET (AW) 2" 19,129.00


4,390.00
82,000.00 1,640.00
90,000.00 1,800.00
95,000.00 950.00
13,000.00
13,000.00 13,000.00

17,390.00
1,739.00
19,129.00

VALVE SOCKET (AW) 3" 46,629.00


4,390.00
82,000.00 1,640.00
90,000.00 1,800.00
95,000.00 950.00
38,000.00
38,000.00 38,000.00

42,390.00
4,239.00
46,629.00

VALVE SOCKET (AW) 4" 60,049.00


4,390.00
82,000.00 1,640.00
90,000.00 1,800.00
95,000.00 950.00
50,200.00
50,200.00 50,200.00

54,590.00
5,459.00
60,049.00

FAUCET SOCKET (AW) 1/2" 9,229.00


4,390.00
82,000.00 1,640.00
90,000.00 1,800.00
95,000.00 950.00
4,000.00
4,000.00 4,000.00

8,390.00
839.00
9,229.00

FAUCET SOCKET (AW) 1/2" x 9,229.00


4,390.00
82,000.00 1,640.00
90,000.00 1,800.00
95,000.00 950.00
4,000.00
4,000.00 4,000.00

8,390.00
839.00
9,229.00

FAUCET SOCKET (AW) 3/4" 9,229.00


4,390.00
82,000.00 1,640.00
90,000.00 1,800.00
95,000.00 950.00
4,000.00
4,000.00 4,000.00

8,390.00
839.00
9,229.00

FAUCET SOCKET (AW) 1" x 1 11,429.00


4,390.00
82,000.00 1,640.00
90,000.00 1,800.00
95,000.00 950.00
6,000.00
6,000.00 6,000.00

10,390.00
1,039.00
11,429.00

FAUCET SOCKET (AW) 1" x 3 11,979.00


4,390.00
82,000.00 1,640.00
90,000.00 1,800.00
95,000.00 950.00
6,500.00
6,500.00 6,500.00

10,890.00
1,089.00
11,979.00

FAUCET SOCKET (AW) 1" 11,979.00


4,390.00
82,000.00 1,640.00
90,000.00 1,800.00
95,000.00 950.00
6,500.00
6,500.00 6,500.00

10,890.00
1,089.00
11,979.00

FAUCET SOCKET (AW) 1 1/4" 13,629.00


4,390.00
82,000.00 1,640.00
90,000.00 1,800.00
95,000.00 950.00
8,000.00
8,000.00 8,000.00

12,390.00
1,239.00
13,629.00

FAUCET SOCKET (AW) 1 1/2" 9,229.00


4,390.00
82,000.00 1,640.00
90,000.00 1,800.00
95,000.00 950.00
4,000.00
4,000.00 4,000.00

8,390.00
839.00
9,229.00

FAUCET SOCKET (AW) 2" 16,929.00


4,390.00
82,000.00 1,640.00
90,000.00 1,800.00
95,000.00 950.00
11,000.00
11,000.00 11,000.00

15,390.00
1,539.00
16,929.00

TEE (AW) 1/2" 10,329.00


4,390.00
82,000.00 1,640.00
90,000.00 1,800.00
95,000.00 950.00
5,000.00
5,000.00 5,000.00

9,390.00
939.00
10,329.00

TEE (AW) 3/4" x 1/2" 10,329.00


4,390.00
82,000.00 1,640.00
90,000.00 1,800.00
95,000.00 950.00
5,000.00
5,000.00 5,000.00

9,390.00
939.00
10,329.00

TEE (AW) 3/4" 10,329.00


4,390.00
82,000.00 1,640.00
90,000.00 1,800.00
95,000.00 950.00
5,000.00
5,000.00 5,000.00

9,390.00
939.00
10,329.00

TEE (AW) 1" x 1/2" 12,309.00


4,390.00
82,000.00 1,640.00
90,000.00 1,800.00
95,000.00 950.00
6,800.00
6,800.00 6,800.00

11,190.00
1,119.00
12,309.00

TEE (AW) 1" x 3/4" 13,189.00


4,390.00
82,000.00 1,640.00
90,000.00 1,800.00
95,000.00 950.00
7,600.00
7,600.00 7,600.00

11,990.00
1,199.00
13,189.00

TEE (AW) 1" 13,849.00


4,390.00
82,000.00 1,640.00
90,000.00 1,800.00
95,000.00 950.00
8,200.00
8,200.00 8,200.00

12,590.00
1,259.00
13,849.00

TEE (AW) 1 1/4" x 1/2" 16,269.00


4,390.00
82,000.00 1,640.00
90,000.00 1,800.00
95,000.00 950.00
10,400.00
10,400.00 10,400.00

14,790.00
1,479.00
16,269.00
TEE (AW) 1 1/4" x 3/4" 16,929.00
4,390.00
82,000.00 1,640.00
90,000.00 1,800.00
95,000.00 950.00
11,000.00
11,000.00 11,000.00

15,390.00
1,539.00
16,929.00

TEE (AW) 1 1/4" x 1" 18,029.00


4,390.00
82,000.00 1,640.00
90,000.00 1,800.00
95,000.00 950.00
12,000.00
12,000.00 12,000.00

16,390.00
1,639.00
18,029.00

TEE (AW) 1 1/4" 18,689.00


4,390.00
82,000.00 1,640.00
90,000.00 1,800.00
95,000.00 950.00
12,600.00
12,600.00 12,600.00

16,990.00
1,699.00
18,689.00
TEE (AW) 1 1/2" x 1/2" 20,229.00
4,390.00
82,000.00 1,640.00
90,000.00 1,800.00
95,000.00 950.00
14,000.00
14,000.00 14,000.00

18,390.00
1,839.00
20,229.00

TEE (AW) 1 1/2" x 3/4" 20,229.00


4,390.00
82,000.00 1,640.00
90,000.00 1,800.00
95,000.00 950.00
14,000.00
14,000.00 14,000.00

18,390.00
1,839.00
20,229.00

TEE (AW) 1 1/2" x 1" 20,229.00


4,390.00
82,000.00 1,640.00
90,000.00 1,800.00
95,000.00 950.00
14,000.00
14,000.00 14,000.00

18,390.00
1,839.00
20,229.00

TEE (AW) 1 1/2" x 1 1/4" 23,529.00


4,390.00
82,000.00 1,640.00
90,000.00 1,800.00
95,000.00 950.00
17,000.00
17,000.00 17,000.00

21,390.00
2,139.00
23,529.00

TEE (AW) 1 1/2" 22,429.00


4,390.00
82,000.00 1,640.00
90,000.00 1,800.00
95,000.00 950.00
16,000.00
16,000.00 16,000.00

20,390.00
2,039.00
22,429.00

TEE (AW) 2" x 1/2" 24,079.00


4,390.00
82,000.00 1,640.00
90,000.00 1,800.00
95,000.00 950.00
17,500.00
17,500.00 17,500.00

21,890.00
2,189.00
24,079.00

TEE (AW) 2" x 3/4" 23,529.00


4,390.00
82,000.00 1,640.00
90,000.00 1,800.00
95,000.00 950.00
17,000.00
17,000.00 17,000.00

21,390.00
2,139.00
23,529.00

TEE (AW) 2" x 1" 23,529.00


4,390.00
82,000.00 1,640.00
90,000.00 1,800.00
95,000.00 950.00
17,000.00
17,000.00 17,000.00

21,390.00
2,139.00
23,529.00

TEE (AW) 2" x 1 1/4" 34,529.00


4,390.00
82,000.00 1,640.00
90,000.00 1,800.00
95,000.00 950.00
27,000.00
27,000.00 27,000.00
31,390.00
3,139.00
34,529.00

TEE (AW) 2" x 1 1/2" 29,029.00


4,390.00
82,000.00 1,640.00
90,000.00 1,800.00
95,000.00 950.00
22,000.00
22,000.00 22,000.00

26,390.00
2,639.00
29,029.00

TEE (AW) 2" 29,029.00


4,390.00
82,000.00 1,640.00
90,000.00 1,800.00
95,000.00 950.00
22,000.00
22,000.00 22,000.00

26,390.00
2,639.00
29,029.00

TEE (AW) 2 1/2" 44,429.00


4,390.00
82,000.00 1,640.00
90,000.00 1,800.00
95,000.00 950.00
36,000.00
36,000.00 36,000.00
40,390.00
4,039.00
44,429.00

TEE (AW) 3" x 2" 51,029.00


4,390.00
82,000.00 1,640.00
90,000.00 1,800.00
95,000.00 950.00
42,000.00
42,000.00 42,000.00

46,390.00
4,639.00
51,029.00

TEE (AW) 3" 63,129.00


4,390.00
82,000.00 1,640.00
90,000.00 1,800.00
95,000.00 950.00
53,000.00
53,000.00 53,000.00

57,390.00
5,739.00
63,129.00

TEE (AW) 4" 112,629.00


4,390.00
82,000.00 1,640.00
90,000.00 1,800.00
95,000.00 950.00
98,000.00
98,000.00 98,000.00

102,390.00
10,239.00
112,629.00

TEE (AW) 6" 289,729.00


4,390.00
82,000.00 1,640.00
90,000.00 1,800.00
95,000.00 950.00
259,000.00
259,000.00 259,000.00

263,390.00
26,339.00
289,729.00

TEE (AW) 8" 571,329.00


4,390.00
82,000.00 1,640.00
90,000.00 1,800.00
95,000.00 950.00
515,000.00
515,000.00 515,000.00

519,390.00
51,939.00
571,329.00

You might also like