Professional Documents
Culture Documents
Paragraph 4: Following a series of negotiations, the contract was finally awarded to Bina Maju. Abdul
was asked by Megah Holding to issue a letter of award to Bina Baik to record, among other things, the
parties’ agreement that the project would be completed in 3 sections, each with different and separate
Completion Dates and liquidated damages. The letter should also confirm several items supposedly
discussed and negotiated directly between Megah Holding and Bina Maju, some of which were variations
to the terms of the initial offer. For purposes of the contract, Ar. Abu, principal partner of Razak Arkitek
was named as the Architect. However, as Ar. Abu was away on an overseas assignment, Megah Holding
instructed Prima Kos to formalize the award. Prima Kos wrote to Bina Maju as follows: “We refer to your
revised tender submitted on 01 October 2023. It is the client’s intention to accept your offer of RM75
million based on an overall contract period of 36 months for the works which would be executed under
the agreed Contract”. Bina Maju’s letter was stated to be ‘subject to contract’ and it mentioned that Razak
Arkitek would subsequently follow up with the issue of a letter of award.
● Clause 11.0
● Clause 21.1 , 21.2 , 21.3
Paragraph 5:The letter from Prima Kos stated a Date of Commencement of 15 November 2023 and a
Completion Date of 15 November 2025 for the last section of the works. Bina Maju was requested to sign
and return the duplicate copy of the letter as acknowledgement and acceptance of the terms and
conditioned but instead, a senior manager from Bina Maju responded by writing “Noted - OK” on the
first page of the letter which was returned to Razak Arkitek. Anxious to see some physical construction
activity at the site, Megah Holding handed possession of the site to Bina Maju who was instructed to
commence work first - which they did- on the assurance that the letter of award would be formally
issued by Razak Arkitek (on behalf of Megah Holding and the contract documents prepared for
execution.
1) Validity of Bina Maju’s argument that the ‘notice’ recorded in the site meeting
minutes qualifies as their notice of an intention to apply for an extension of time.
YI SHENG
Law Case:
1. In the Scottish case of John L. Haley Ltd v. Dumfries & Galloway Regional Council
(1988), the claimants (John L. Haley Ltd) sought an extension of time for building works
on a school under the JCT 63 standard form of contract. The contract period of 78 weeks
was exceeded by 31 weeks, with a six-week extension initially granted. Further extension
requests were denied, leading to arbitration. The claimants argued for an extension based
on specific clauses, while the arbiter (Dumfries & Galloway Regional Council) granted a
four-week extension relying on site meeting minutes. However, the Court of Session
ruled that the minutes did not constitute valid notice under clause 23 of the contract. The
claimants, having conceded that notice was a condition precedent, ultimately lost their
case.
(JCT is considered the older version of Standard Form of Contract which is then developed
into PAM 1998)
2. In the Steria Ltd v. Sigma Wireless Communications Ltd (2007) case, the court had to
decide whether site meeting minutes constituted proper notice under the contract. The
court clarified that the written notice must come from Steria, and a note in minutes from
the main contractor or employer did not automatically qualify. The court left unanswered
whether minutes or progress reports by Steria would suffice, emphasizing that, if
accepted, they must meet the required level of detail outlined in the contract conditions
for delay notice.
Reference:
https://drahmedelyamany.weebly.com/uploads/7/0/1/0/7010103/200_contractual_problems_and_
their_solutions.pdf
2) Possible valid grounds by Megah Holding for determination of Bina Maju’s employment,
their rights and duties in the event Megah Holding decides to proceed with such determination,
the arrangements for completing the works and how the costs incurred and loss and expense
suffered by Megah Holding could be recovered. BOON
Law Cases:
Case 1:
3) Course of action to be taken by Razak Arkitek following Megah Holding’s decision to
take possession and occupation of the completed lecture theatres before practical completion of
the works. BOON
Law Cases 1:
1)
Law Case 2:
4) Options available to Razak Arkitek in respect of the work that was not constructed in
accordance with the contract requirements. AMMAR
Law Case 4:
Issues
● The sole issue here is whether there is money due or payable from the Defendant to KMD
at the material time the s.30(1) notice was served by the Plaintiff on the Defendant.
Decision
Law Case:
1. In the case of Thorn v. Mayor and Commonalty of London (1876), the judge said, ‘If the
additional or varied work is so peculiar, so unexpected, and so different from what any
person reckoned or calculated on, it may not be within the contract at all.’ A mere
increase in the quantities of the work will not invalidate the original contract, even
though substantial. The work ordered must be totally different from that contracted for.
This being the case, the contractor will be entitled to payment on a quantum meruit basis
and not the contract rates
2. In the case of Blue Circle v. Holland Dredging Co (1987), the contractor was required to
remove large quantities of excavated material from the site as part of the contract. A
variation was issued by the engineer, to the effect that the excavated material should be
used to form a bird island, instead of removing it from the site. Again, the court held that
this variation amounted to a separate contract.
Reference:
https://drahmedelyamany.weebly.com/uploads/7/0/1/0/7010103/200_contractual_problems_and_
their_solutions.pdf
6) Remedies available to Megah Holding arising from Bina Maju’s failure and refusal
to comply with the instructions of Architect. AIMI
● Clause 2.4, Clause 4.4, Clause 25.1 , Clause 25.2 , Clause 30.4,6.5,6.7
Law case :
7) When are the works deemed to be “Practically Completed”? What are the obligations of
all parties when the works have reached practical completion? HANI
QIMONDA MALAYSIA SDN BHD vs SEDIABENA SDN BHD & APC CORPORATE
HOLDINGS SDN BHD
The case involves an appeal against a decision allowing the Respondents' application for a
declaration that the retention sum held by the Appellant is held on trust by the Appellant in favor
of the Respondents. The Appellant's counsel abandoned the argument on the issue of estoppel,
and the court found that the retention monies are trust monies held by the Appellant for the
Respondents for specific purposes. The court also found that the Respondents are entitled to their
claim. The High Court judge concluded that the retention monies belong to the Respondents and
are held by the Appellant on trust for the Respondents
The present appeal before this court is against the decision of the learned High Court judge dated
22 April 2011 in allowing the Respondents’ application for a declaration that the retention sum
held by the Appellant under the relevant contract is held on trust by the Appellant in favour of
the Respondents and granting injunctive reliefs as prayed with costs of RM25,000.00. The
Appellant was the Defendant and the Respondents were the Plaintiffs at the court below.
Reference:
chrome-extension://efaidnbmnnnibpcajpcglclefindmkaj/https://simplymalaysia.files.wordpress.co
m/2011/09/qimonda-malaysia-sediabena-apc-w-02ncc-1132-2011_306781.pdf