You are on page 1of 17

Computers and Geotechnics 101 (2018) 48–64

Contents lists available at ScienceDirect

Computers and Geotechnics


journal homepage: www.elsevier.com/locate/compgeo

Research Paper

Lateral behaviour of a pile group due to side-by-side twin tunnelling in dry T


sand: 3D centrifuge tests and numerical modelling
⁎,1
M.A. Soomroa, , C.W.W. Ngb, N.A. Memona, R. Bhanbhroa
a
Department of Civil Engineering, Quaid-e-Awam University of Engineering, Science & Technology, Sindh, Pakistan
b
Department of Civil and Environmental Engineering, The Hong Kong University of Science and Technology, Clear Water Bay, Kowloon, Hong Kong Special Administrative
Region

A R T I C LE I N FO A B S T R A C T

Keywords: This paper presents lateral responses of an existing 2 × 2 pile group to advancement of side-by-side twin tunnels
Centrifuge modelling (with 1% volume loss) at various depths in dry sand using 3D centrifuge and numerical modelling. The tunnels
Numerical modelling were located near mid-depth of the pile shaft (test SS), next to (test TT) and below the toe (test BB) of the pile
Twin tunnelling group. The largest and the smallest lateral movement of the pile cap was induced after first tunnelling in test TT
Piles, deflection
and test SS, respectively. The shearing force was induced in piles as a reaction of pile deflection in tests TT and
BB.

1. Introduction typical sectional view of the project). A maximum dragload of up to 42%


and 66% of the pile structural capacity was observed after single tunnel and
Underground construction such as tunnels and excavations supports the twin tunnel advancement, respectively. In this case history, field measure-
quality of life in cities by improving the availability and quality of the space ments include only axial load and bending moments along a limited portion
above ground [26,30,55]. Construction of tunnels is likely to encounter of the pile shafts. Other important pile responses, such as settlement and
existing underground structures such as pile foundations [31,39,40,47]. It is deflection of the pile foundation, were also not reported. To further explore
well recognised that the capacity of a pile group depends on mobilised twin tunnelling effects on an existing single pile and a pile group in dry
stresses in the ground while tunnelling is essentially a stress release process sand, some centrifuge model tests and back-analysis of the tests were also
[7,55]. Stress release caused by tunnels may lead to excessive ground carried out at the Hong Kong University of Science and Technology [47,48].
movements. The interaction of these ground movements with nearby ex- Side-by-side twin tunnels were simulated in-flight, either adjacent to or
isting pile foundations develop additional loading in vertical as well as below the pile toe. The existing single pile and pile group stood between the
horizontal direction on them [32,36,39]. Therefore, it is vital to investigate twin tunnels, which were excavated one after the other. It was concluded
the adverse effects of tunnelling on existing pile foundations. To understand that owing to twin tunnelling, no significant bending moment was induced
influence of tunnelling on existing piles, extensive numbers of studies have in either case (i.e. no more than 17% of the pile bending moment capacity).
been carried out based on field monitoring and centrifuge modelling In addition, the twin tunnelling resulted in a maximum increase in axial
[4,5,8,9,10,13,28,35,25,53,30,39,46–49,51] numerical analysis and analy- force in the single pile by 27%, due to load transfer within the pile. Fur-
tical analysis [6,42–44,7,20,57,38,31–33,26,3,41,55,56,21,22,27,58]. They thermore, the second tunnelling reversed almost completely the tilting of
all concluded that tunnelling adjacent to existing pile foundations caused the existing pile group caused by the first tunnelling.
pile settlement, additional axial load on piles and induced bending mo- In spite of the numerous previous investigations on this subject,
ments along piles, which is unfavourable for piled foundations. The mag- little attention was paid to behaviour of an existing pile group in lateral
nitudes of likely depended on the relative locations of tunnels and piles. direction due to tunnelling. It is well recognised that soil exhibits highly
However, most previous studies have focused on the effects of a single non-linear behaviour and stiffness of the soil depends upon stress or
tunnel on single piles and pile groups. In fact, twin tunnelling is particularly strain level, stress path and on the recent stress or strain history of the
favoured across the world when developing underground transportation soil [1,2]. Owing to non-linear soil behaviour, a tunnel excavation can
systems [22,53]. Pang et al. [53] carried out field monitoring on a metro cause reduction in the stiffness of the ground. Therefore, it is vital to
project in Singapore (i.e. North-East Line Contract 704) (Fig. 1 shows a investigate the lateral pile responses not only to first tunnel but also


Corresponding author.
E-mail addresses: eng.soomro@gmail.com (M.A. Soomro), cecwwng@ust.hk (C.W.W. Ng), nahmedmemon@gmail.com (N.A. Memon), riaz@quest.edu.pk (R. Bhanbhro).
1
Formerly The Hong Kong University of Science and Technology, Clear Water Bay, Kowloon, Hong Kong Special Administrative Region.

https://doi.org/10.1016/j.compgeo.2018.04.010
Received 4 January 2018; Received in revised form 16 February 2018; Accepted 7 April 2018
0266-352X/ © 2018 Elsevier Ltd. All rights reserved.
M.A. Soomro et al. Computers and Geotechnics 101 (2018) 48–64

Table 1
Scaling factors relevant to centrifuge tests in this study.
Physical quantity Scaling factor (model/prototype)

Gravitational acceleration n
Length 1/n
Area 1/n2
Volume 1/n3
Settlement n
Stress 1
Strain 1
Force 1/n2
Density 1
Mass 1/n3
Axial rigidity 1/n2
Bending rigidity 1/n4

respectively. The twin tunnelling was carried out near and below the
toe of the pile group in test TT (i.e. C/D = 2.7) and BB (i.e. C/D = 3.7),
Fig. 1. A sectional view showing MRT North East Line viaduct bridge,
respectively.
Singapore [53].
In each test (i.e. tests SS, TT and BB), in-flight three-dimensional
advancement of twin tunnels were simulated. Fig. 3(a) illustrates the
subsequent tunnel in a twin-tunnelling transportation system. plan view of a typical test (i.e. test SS). As illustrated, the length of each
In view of the aforementioned issues, this study aims at system- model tunnel (along its longitudinal direction) is 380 mm, which was
atically investigating the induced lateral behaviour (i.e. lateral move- equivalent to 2.5D. Each tunnel excavation consisted of five construc-
ment of pile cap, deflection of piles, bending moment and lateral forces tion stages, with the tunnel face advancing by a distance of 0.5D in each
in the piles) of an existing pile group due to side-by-side twin tunnels in stage and a volume loss of 1%. More details are given by Ng et al. [49].
dry sand. To achieve these objectives, three 3D centrifuge experiments The centrifuge test programme of this study is summarised in Table 2.
were carried out to simulate in-flight advancement of side-by-side twin
tunnels (one after the other) on both sides of an axially loaded 2 × 2 2.2. In-flight simulation of tunnel excavation
pile group in dry sand. The only variable that differed between the
three tests was depth of the twin tunnels relative to the pile shaft. The Each model tunnel was simulated by five independent cylindrical
tunnels were located near mid-depth of the pile shaft (test SS), next to rubber bags. Water was filled inside each rubber bag (without any air
(test TT) and below the toe (test BB) of the pile group. The centrifuge bubble left in the bags). The rubber bags are placed in a frame with five
tests were back-analysed by three-dimensional finite element analyses, partitions separated by six rigid aluminium plates in order to stop any
in which a hypoplastic constitutive soil model was employed. Measured soil movement towards tunnel face (see Fig. 4). Thus, the soil move-
and computed results are compared and interpreted, with particular ment towards tunnel face not allowed in each excavation stage. The
attention paid to understand the mechanism of lateral effects on the pile induced movement of soil due to tunnelling is in radial direction. Three-
group due to twin tunnelling. dimensional tunnel advancement was modelled by draining away a
controlled amount of water, which was equivalent to a volume loss of
2. Three-dimensional centrifuge model test 1.0%, one after another from the rubber bags.

2.1. Experimental programme and setup of centrifuge modelling 2.3. Model pile group and instrumentation

The centrifuge tests reported in this paper were carried out at the As shown in Fig. 4, the 2 × 2 pile group was used in the centrifuge
Geotechnical Centrifuge Facility at the Hong Kong University of Science tests. The pile group was installed between twin tunnels with each row
and Technology. The 8.5 m diameter centrifuge has a payload of 400 g- of piles parallel to tunnels. The four piles were firmly fixed to a rela-
ton and is equipped with a biaxial hydraulic shaker and a computer tively rigid pile cap. The flexural rigidity of the cap was 15 GNm2 (in
controlled four-axial robotic manipulator [50]. All of centrifuge tests prototype), being equivalent to a 1 m thick (in prototype) reinforced
reported herein were carried out at a centrifugal acceleration of 40 g. concrete cap.
Scaling factors relevant to the centrifuge tests are summarised in Each model pile was fabricated from a 600 mm (24 m in prototype)
Table 1. long aluminum tube with an outer and inner diameter of 20 mm and
An in-flight pile load test (test L) was firstly carried out in “green- 15 mm, respectively. Based on the scaling factors summarised in
field” conditions (i.e. with absence of tunnels) to obtain the ultimate Table 1, each model pile corresponds to a 0.8 m diameter (in prototype)
capacity of the pile group, and hence working load to be applied on the cylindrical reinforced concrete (grade 40, reinforcement ratio = 1%)
pile group in the three tests simulating twin tunnelling. pile with flexural stiffness and bending moment capacity of 721 MN m2
Fig. 2(a) shows elevation view of test SS. In this test, both the and 800 kN m, respectively. To measure change of axial load in the
tunnels were simulated near the mid-depth of pile shaft. Each tunnel model piles, ten levels of Full Wheatstone bridge semiconductor strain
had a diameter (D) of 152 mm (6.08 m in prototype). Cover-to-diameter gauges (SGs) were bonded on the external surface of each pile. The
ratios (C/D) of both the tunnels were 1.5. The closest distance between vertical spacing between each level of SGs was 60 mm (2.4 m in pro-
the centreline of the tunnel and the pile group was 114 mm, being totype scale). Gauge factor (GF) of each semiconductor strain gauge
equivalent to 0.75D. The diameter and the length of each pile were was 150, being much higher than conventional foil gauges (GF = 2).
20 mm (0.8 m in prototype) and 600 mm (24.0 m in prototype), re- The resolution of each SG was as low as 1 micro-strain. Prior to each
spectively. The pile cap was elevated by 110 mm (above the ground test, the axial load measurement of each pile was calibrated, by in-
surface) and hence the embedded depth of each pile was 490 mm crementally applying axial force to each pile with a hydraulic actuator.
(19.6 m in prototype). Each pile was calibrated for axial and bending measurement prior to
Fig. 2(b) and (c) shows the elevation view of tests TT and BB, each test. For axial calibration, each pile had a known force applied

49
M.A. Soomro et al. Computers and Geotechnics 101 (2018) 48–64

applied to the shaft of each pile. The interface property between


Toyoura sand and the epoxy-coated pile shaft were measured by car-
rying out two direct shear tests [54]. The measured average friction
angle of the Toyoura sand-epoxy interface was 29°. Surface roughness
of the epoxy-coating was measured using an optical profiler. An abso-
lute interface roughness Rmax of about 15 µm was measured. By nor-
malising the measured Rmax with the mean particle size
(D50 = 0.17 mm) of Toyoura sand, the normalised roughness Rn (de-
fined by Kishida and Uesugi [28]) is 0.09. According to Fioravante [11],
interfaces with Rn smaller than 0.02 and larger than 0.10 can be re-
garded as smooth and rough interfaces, respectively. The epoxy-coated
pile shaft in this study may, therefore, be described as relatively rough.
To measure lateral pile cap movement due to twin tunnelling, a
potentiometer were installed on right top of the pile cap (see Fig. 5).

2.4. Pile loading system

In the pile load test (test L), an incrementally increased vertical load
(loading increment = 400 N in model scale, or 640 kN in prototype)
was applied to the pile cap using a hydraulic jack. The load-controlled
pile load test was achieved by a closed loop system, which consists of a
servo-valve, a load cell (attached to the hydraulic jack) and a control
unit. During the load test, settlement of the pile group was measured by
a LVDT installed at the centre of the pile cap.
Based on the pile load test, the working load of the pile group can be
determined according to a displacement controlled criterion (discussed
in detail by Ng et al. [49]). The obtained working load (i.e. 5.5 MN) was
then applied to the three tests involving twin tunnelling simulation
(Tests SS, TT, BB), by mounting a dead weight of 8.6 kg (i.e. equivalent
to the working load at 40 g) on top of the pile cap before centrifuge
testing (at 1 g).

2.5. Testing material and model preparation

Dry Toyoura sand, which consists of sub-angular particles with a


mean diameter (D50) of 0.17 mm, was adopted for the centrifuge tests.
It was found by Fuglsang and Ovesen [16] that in small-scaled model
tests, particle size of soil became insignificant when it was less than 1/
30th of an important model dimension such as pile diameter. In this
study, the ratio of grain size of Toyoura sand to pile diameter (20 mm)
was 1/129, which was much smaller than the allowable limit proposed
by Fuglsang and Ovesen [15]. This implies that the particle size effect is
likely to be negligible in the centrifuge tests reported in this study.
To prepare sandy ground in each centrifuge test, pluvial deposition
method (i.e. raining dry Toyoura sand into the model box) was adopted,
with a constant falling height of sand (i.e. 500 mm). By doing so,
medium-dense sand (with relative density of about 65%) was obtained.
Once the sandy ground level reached the elevation where the invert of
the tunnel should be positioned, the model tunnel was placed in, prior
to continuing the sand raining process. Similarly, when the sand bed
reached the elevation of the pile toe, the pile group was temporarily
fixed at its designed location by mounting the pile cap firmly to a
temporary support beam (see Fig. 4). Then the sand raining process was
preceded until final elevation is achieved (i.e. 750 mm). After the pre-
Fig. 2. Elevation view of centrifuge tests: (a) SS; (b) TT and (c) TT. All di- paration of each layer, the average density of the layer was deduced by
mensions are in mm in model scale. measuring the weight and volume of sand used. Fig. 6 shows the
measured distributions of the sand density with depth in all four cen-
trifuge tests at 1 g. It can be seen from the figure that the density of sand
incrementally on the top of pile using an actuator. Each strain gauge
in the regions with the presence of model tunnel and piles are generally
output was then related to the applied axial force. For bending cali-
less than that in the regions without the model structures. However, the
bration, each pile was simply supported at two ends, and a point load
maximum difference in each test was less than 0.6%. For example, the
was incrementally applied at the centre of the pile. Strain gauge outputs
minimum density at the location of SS was 1526 kg/m3, which is 0.4%
were then related to calculated bending moments. Similar procedures
smaller than the maximum density of 1533 kg/m3 obtained at about
were repeated by applying point loads incrementally on the pile at
640 mm below the same bed. Since the vertical and horizontal stresses
distances of one-third and two-third from the left support.
should be approximately proportional to the soil density, the initial
To protect the SGs, a 1.5 mm thick epoxy coating was uniformly
vertical and horizontal stresses are likely to be affected by less than

50
M.A. Soomro et al. Computers and Geotechnics 101 (2018) 48–64

Fig. 3. (a) Plan view of a typical centrifuge test, i.e., test SS (all dimensions are in mm in model scale); (b) arrangement of potentiometer on the pile cap.

Table 2 around the pile also increased under the Ko condition, which was si-
Centrifuge test programme. milar to that surrounding a non-displacement pile.
Test ID C/D Remark
Table 3 summarises the deduced average relative density (i.e. Dr) in
each test. The difference of Dr between each test was less than 2%,
L N/A Pile group load test suggesting that the sand beds prepared in the four tests were likely to be
SS 1.5, 1.5 Side-by-side twin tunnelling near pile shaft comparable.
TT 2.7, 2.7 Side-by-side twin tunnelling near pile toe
BB 3.7, 3.7 Side-by-side twin tunnelling below pile toe
2.6. Test procedure
N/A denotes not applicable.
After assembling the centrifuge model package, a dead weight (i.e.
0.6% in the regions where the model tunnel and piles are located. The 8.6 kg) was fixed on top of the pile cap to serve as working load. Then
pluvial deposition at 1 g resulted in relative small stress level around the whole package was mounted onto the swinging platform and spun
the pile. During the spinning up process of the soil model, the stress up to 40 g. Owing to incompressibility of water no any reduction in of

Fig. 4. Model tunnels and pile group in a typical test (i.e., test SS for this case).

51
M.A. Soomro et al. Computers and Geotechnics 101 (2018) 48–64

During the entire testing process, lateral movement of pile cap and
bending moment in piles were recorded.

3. Three-dimensional finite element analysis

To obtain better understanding of the centrifuge tests, three-di-


mensional finite element back-analyses of the tests were undertaken
using the finite element program ABAQUS [20]. As the model ground in
centrifuge tests is dry sand therefore, the drained analyses were
adopted in back-analyses.
A user-defined hypoplastic model, which accounts for strain-de-
pendent and path-dependent of soil stiffness, was incorporated in the
finite element program ABAQUS.

3.1. Finite element mesh and boundary conditions

Fig. 7(a) and (b) shows plan and elevation view of a typical finite
element mesh (for back-analysing test TT). In the mesh, all dimensions
are in model scale and are identical to those in the centrifuge tests.
Displacements perpendicular to the outer boundaries of the mesh is
restrained. The soil and the deadweight are modelled by using eight-
Fig. 5. Model pile group and arrangement of potentiometer on the pile cap. noded brick elements while the pile is modelled by four-noded shell
elements, respectively. Regarding the mesh size, a numerical test shows
that further halving current mesh size can only lead to a change of

Fig. 6. Distributions of initial density of sand bed with depth in all four tests.

Table 3
Parameters of the soil deposit (at 1 g) in all four centrifuge tests.
Test identity Initial void ratio Initial density (ρ): Initial relative density
(e) kg/m3 (Dr): %

Test L 0.730 1531 65


Test SS 0.732 1529 64
Test TT 0.726 1532 66
Test BB 0.732 1529 64

volume of rubber bag was observed with increase of gravity (1–40 g).
Upon reaching 40 g, in-flight twin tunnel excavations were simulated
one after the other. Each tunnel was simulated in five stages, by
draining away water from five rubber bags (with 1% volume loss for Fig. 7. Finite element mesh for test TT. (a) Plan view and (b) Elevation view (all
each), respectively. dimensions are in mm).

52
M.A. Soomro et al. Computers and Geotechnics 101 (2018) 48–64

Fig. 8. Displacement controlled method [8] adopted in this study.

computed results of no more than 0.2%. Based on this method, displacement boundaries around the tunnel
The tunnel excavation was simulated by deactivating soil elements in tests SS, TT and BB are calculated and imposed in the numerical
inside the tunnel and applying non-uniform inward displacements to analyses. By going through a trial-and-error process, with 1% of volume
nodes around the boundary of the tunnel, with a pre-defined 1% vo- loss the location of the convergence point (point A), which resulted in
lume loss (i.e. difference between original volumes to reduced volume). the best-fit ground settlements, was obtained. In tests SS, TT and BB, the
The face of each tunnel section was fixed by applying zero displacement calibrated convergence points were located at 0.15, 0.3 and 0.4D above
boundary condition to restrain the inward tunnel face movement si- the tunnel invert, respectively.
milar to that in centrifuge tests. Although tunnel lining was not ex-
plicitly simulated in the numerical analysis, the effect of this was im-
plicitly included by controlling an equivalent volume loss. 3.2. Constitutive model and model parameters
Pattern of the applied non-uniform displacement boundaries was
determined according to Cheng et al. [8]’s displacement controlled The hypoplastic model was developed to describe non-linear re-
model (DCM), as shown in Fig. 8. The DCM was proposed based on sponse of granular material [17,18,29]. It consists of eight model
deformation mechanisms (in green-field) observed in the field and in parameters (ϕ′c, hs, n, ed0, ec0, ei0, α and β). The first six parameters (ϕ′c,
centrifuge tests. The validity of the DCM in modelling tunnel–soil–pile hs, n, ed0, ec0, ei0) of Toyoura sand were calibrated by Herle and Gu-
interaction problems had been demonstrated through back analysis of a dehus [19]. The remaining two parameters (α and β) were obtained by
centrifuge test and a case history. According to DCM, displacement curving fitting Maeda and Miura [38]’s triaxial test results (at large
pattern around a tunnel can be determined by knowing ground surface strains).
settlement and volume loss and by assuming: To account for strain-dependency and path-dependency of soil
stiffness (at small strains), Niemunis and Herle [52] further improved
(a) The volume loss is distributed non-uniformly around the tunnel, i.e. the hypoplastic model by incorporating intergranular strain concept
with zero displacement occurring at the invert of the tunnel and the into the model. Five additional parameters (mR, mT, R, βr and χ) are
maximum displacement at the crown; required. These five parameters were obtained by curve fitting stiffness
(b) The final profile of the tunnel is similar to the excavated shape degradation curves of Toyoura sand measured in this study. Fig. 9
(which can be taken as circular). This assumption is justified as compares the measured and the computed variation of stiffness of
deformations are usually small compared to tunnel size under Toyoura sand by the Hypoplastic model (sand) with the deviatoric
working conditions [8]. strain. The measured and computed stiffness results show a reasonable
(c) Displacements of nodes around the boundary of the tunnel all agreement in both trend and magnitude with maximum difference
converge to a single point A (see Fig. 8), which is located between being 10%. The good match of computed results (with calibrated
the centre and the invert of the tunnel. The point of convergence parameters) with that of the measured implies the capability of the
depends on tunnel cover (distance between ground surface and Hypoplastic model (sand) to capture the small strain stiffness and de-
tunnel crown) to diameter ratio (C/D) and predefined volume loss. gradation of the soil stiffness with strain, which is an important aspect
As the tunnel becomes shallower (i.e. cover to tunnel diameter (C/ of soil behaviour to predict the soil movement during tunnelling [1,3].
D) ratio decreases), with a given volume loss the convergence point The coefficient of at-rest earth pressure (K0 = 0.5) was estimated based
shift downwards within the bounds of the tunnel centre and the on effective angle of shearing resistance at critical state (ϕ′ = 31°, as
invert. As the convergence point moves to invert of the tunnel, the reported by Ishihara [24]) and Jáky [25]’s equation. Table 4 sum-
maximum settlement increases and settlement trough becomes marises model parameters of Toyoura sand adopted in the numerical
narrower. On the contrary, in deeper tunnel, with the same value of analyses.
volume loss the convergence point moves upward which will result The model pile group (made of aluminum) was modelled as a linear
in wider settlement trough and smaller maximum settlement. elastic material with Young’s modulus, Poisson ratio and unit weight of
70 GPa, 0.2 and 27 kN/m3, respectively.
The soil-pile interface was simulated as zero thickness elements by

53
M.A. Soomro et al. Computers and Geotechnics 101 (2018) 48–64

due to advancement of the first tunnel and the second tunnel in all the
three tests (i.e. test SS, test TT and test BB). The advancement of both
tunnels is indicated by the distance (i.e. y) from the tunnel face to the
centreline of the pile group (defined as the monitoring section in the
inset of Fig. 3(a)). The x and y are normalised by pile diameter (dp) and
tunnel diameter (D), respectively. As a sign convention, lateral move-
ment of the pile cap towards the first tunnel is taken as positive.
It can be seen that the x of the pile cap increased almost linearly
with tunnelling stage (i.e. y/D) in test SS. However, non-linear lateral
movement characteristics of the pile group were observed during ad-
vancement of the first tunnel (T and B) in tests TT and BB. The rate of
lateral movement increases as the tunnel face approaches the mon-
itoring section (MS) and decreases as it moves away from the MS.
Among the three tests discussed, the largest and the smallest x resulted
from tunnelling below the pile toe (i.e. test TT) and near mid-depth of
Fig. 9. Measured and computed degradation curves of Toyoura sand subjected
to varying recent stress histories.
the pile shaft (i.e. test SS), respectively. This may be because of stress
release-induced shear strain due to tunnelling next to pile toe (ex-
plained in the section ‘‘Computed ground deformation mechanism and
using duplicated nodes in ABAQUS [20]. This interface was simulated deviatoric strain’’). The induced final cap movement after excavation of
by the Coulomb friction law, in which interface friction coefficient (μ) first tunnel in tests SS, TT and BB were 1.7, 9.5 and 2.8 mm (i.e. 0.21%,
and limiting displacement (γlim) are required. They are μ = 0.5 and 1.2% and 0.34% of pile diameter), respectively.
γlim = 5 mm), as reported by Peng [54] based on direct shear tests on During the second tunnelling (as shown in Fig. 11(b)), lateral
Toyoura sand-epoxy interface. movement of the pile cap decreased non-linearly with excavation stages
in tests TT and BB. As a result, the pile group almost moves back to its
3.3. Numerical modelling procedure original position after twin tunnelling. However, negligible movement
of the pile cap was observed due to second tunnelling in test SS. This
Procedures of numerical analysis are the same as those of the cen- may be attributed to two reasons. Firstly, the reduction of normal stress
trifuge test. Details are summarised as follows: difference on the pile in tests TT and BB is greater than that induced in
test SS (explained in the section ‘‘Computed normal stresses acting on
1. Set up the initial boundary and initial stress conditions (i.e. static pile”). Second reason is limited non-linearity in the soil response.
stress conditions with Ko = 0.5) at 1 g. It can be seen from Fig. 11(a) and (b) that during the entire process
2. Activate pile group (modelled as “wished-in-place”) and deadweight of twin tunnelling in all the three tests, the most significant lateral
on top of the pile cap. movement occurs at the end of the first tunnelling.
3. Increase stress level of the entire mesh (including soil, pile group Compared to the measured pile cap lateral movement, computed
and deadweight) by raising its gravitational acceleration from 1 g to results show good correspondence. In terms of magnitude, the max-
40 g. imum percentage difference between the measurements and the com-
4. Fix face of each tunnel section to be excavated. puted results is less than 15%.
5. Simulate tunnel excavation of the first segment, with a 1% volume
loss (by DCM as explained in Section 3.1).
6. Repeat step 5 to simulate advancement of the second tunnel. 4.2. Induced bending moments in piles

For further illustration, the steps of numerical modelling procedure The measured and computed bending moment of two typical piles
are depicted in Fig. 10. P1 (closest to the first tunnel) and P2 (closest to the second tunnel) (see
Fig. 3(b)) were selected for discussion in each test. A positive bending
4. Interpretation of computed results moment means that tensile stress was induced along the pile shaft fa-
cing the first tunnel.
4.1. Measured and computed lateral movement of the pile cap Fig. 12(a) and (b) illustrates the measured and computed bending
moment along pile P1 and pile P2 in response of twin tunnelling in test
Fig. 11(a) and (b) shows the lateral movement of the pile cap (x) SS, respectively. Owing to the first tunnel (S) induced stress release and

Table 4
Model parameters of Toyoura sand adopted in the numerical analyses.
Description Parameter Reference

Effective angle of shearing resistance at critical state: ϕ′ 31° Ishihara [24]


Coefficient of at-rest earth pressure, Ko 0.5 Estimated by Jáky [25]’s equation
Hardness of granulates, hs 2.6 GPa Herle and Gudehus [19]
Exponent n 0.27
Minimum void ratio at zero pressure, edo 0.61
Maximum void ratio at zero pressure, eio 1.10
Critical void ratio at zero pressure, eco 0.98
Exponent α 0.14
Exponent β 3
Parameter controlling initial shear modulus upon 180° strain path reversal, mR 8 Calibrated from stiffness degradation curve of Toyoura sand (see Fig. 9)
Parameter controlling initial shear modulus upon 90° strain path reversal, mT 4
Size of elastic range, R 2 × 10−5
Parameter controlling degradation rate of stiffness with strain, βr 0.1
Parameter controlling degradation rate of stiffness with strain, χ 1.0

54
M.A. Soomro et al. Computers and Geotechnics 101 (2018) 48–64

Fig. 10. Depicted numerical modelling procedure.

lateral soil movement (explained in the section ‘‘Computed ground measured data.
deformation mechanism and deviatoric strain’’), the maximum positive Fig. 14(a) and (b) shows that owing to stress-release and ground
bending moment was induced in pile P1 above the springline of the first movement after the first tunnel excavation in test BB, the maximum
tunnel. This positive bending moment was counter-balanced by the bending moment was also induced near the head of both piles P1 and
negative bending moment near pile head. The magnitude of maximum P2. The magnitude of the induced maximum bending moment was
positive bending moment at Z/Lp = 0.25 was 325 kN m. In contrast, 600 kN m near the pile head, which was 75% of the bending moment
negligible bending moment was induced below the tunnel springline. capacity of the pile (i.e. 800 kN m). Subsequently, the bending moment
This was because the tunnelling induced soil movement below the decreased as the second tunnel was excavated. The computed changes
tunnel springline was insignificant [26]. Subsequently, the pile group in induced bending moment in each pile showed a broadly consistent
was subjected to stress release on the other side due to the second trend with that of measured induced bending moment.
tunnel (S), the bending moment near the pile head P1 decreased. Fi- Among the three tests reported, the first tunnelling in test TT in-
nally, a positive bending moment 65 kN m was induced. The measured duced the largest bending moment which exceeds the pile BM capacity
and computed bending moment profile of pile P2 was almost similar to (i.e. 850 kN m) near the pile head. However, the induced bending
that of pile P1 (see Fig. 12(b)). Compared to measured induced bending moment along the pile decreased significantly due to the excavation of
moment in each pile after the first and second tunnel, the computed the second tunnel in each case. This is because of the side-by-side twin
results show a broad agreement qualitatively. tunnelling configuration in which the second tunnel caused a stress
Fig. 13(a) and (b) shows the measured and computed bending release on the opposite side of the pile.
moment along pile P1 and pile P2 in response of twin tunnelling in test
TT, respectively. It can be observed from Fig. 13(a) that the most sig-
4.3. Induced pile lateral displacement
nificant bending moment (i.e. 850 kN m) was induced in pile P1 near
the pile cap after the completion of the first tunnel (T) near the pile toe.
To substantiate the discussion in the previous section, induced
The measured maximum bending moment exceeded the ultimate ca-
computed displacement of pile P1 and pile P2 is interpreted in this
pacity of a prototype reinforced concrete pile (i.e. 800 kN m, as dis-
section.
cussed) with corresponding flexural rigidity. This implies that tunnel-
Fig. 15(a), (b) and (c) illustrates the computed induced lateral pile
ling with a volume loss of 1% close to the toe of a pile group may cause
displacement (x) along the front pile P1 and the rear pile P2 after the
structural failure near the pile head. In contrast, a much smaller
completion of first and second tunnels in tests SS, TT and BB, respec-
bending moment was induced in a single pile subjected to tunnelling
tively. Pile deflection towards the first tunnel is regarded as the positive
near the pile toe [48], as no rigid constraint was applied near the single
direction.
pile head. The induced bending moment reduced to zero near the pile
It can be seen from Fig. 15(a) that pile P1 and pile P2 deflected
head after the second tunnel (T) excavation. However, a net bending
towards first tunnel with pile displacement decreasing along the pile
moment of magnitude 174 kN m at Z/Lp = 0.25 induced in pile P1. The
length. The maximum lateral displacement of 0.1% of pile diameter was
measured and computed bending moment profile of pile P2 was almost
induced at the pile head as there was no constraint at the pile cap. This
similar to that of pile P1 (see Fig. 13(b)). The computed induced
is because the piles were subjected to tunnelling-induced stress release
bending moments in both the piles were broadly consistent with the
and lateral movement towards the first tunnel (explained in the section

55
M.A. Soomro et al. Computers and Geotechnics 101 (2018) 48–64

‘‘Computed ground deformation mechanism and deviatoric strain’’).


However, no lateral movement was computed at the pile toe.
After the subsequent tunnelling in test SS, both the piles P1 and P2
were deflected back to their original positions. This ‘‘elastic’’ response
implies that the plastic strains generated adjacent to the two tunnels did
not overlap with each other (evidence is given in ‘‘Computed ground
deformation mechanism and deviatoric strain’’).
In test TT (see Fig. 15(b)), the heads and toes of pile P1 and P2
displaced towards the first tunnel after completion of the first tunnel.
Due to rigid connection of the pile with pile cap and no constraint of the
pile, both the pile heads displaced with same magnitude of 0.75% of
pile diameter. However, the lateral movement of the toe of pile P1 is
larger than that of pile P2. This is because of pile P1 is subjected to
higher stress release and soil movement due to first tunnelling as
compared to pile P2.
On the completion of the second tunnel in test TT, the upper portion
of pile P1 (0 ≤ Z/Lp ≤ 0.56) was displaced back to its original position.
However, negligible lateral displacement of the toe of pile P1 was in-
duced after second tunnelling. On the contrary, pile P2 displaced back
to its original position entirely along its length. This is because of the
overlapping of plastic strain developed adjacent the toe of the pile
group due to twin tunnelling as discussed later.
It can be observed from Fig. 15(c) that twin tunnelling-induced
lateral displacement profiles of pile P1 and pile P2 in test BB are similar
to that of observed in test TT. However, quantitatively the induced
lateral displacements in test BB are less than that in test TT. The
maximum computed lateral displacements of 0.2%dp and 0.13%dp at
the head and at the toe were induced in pile P1, respectively.
Among all the three tests, the pile deflection profile after second
tunnelling is consistent with induced bending moment which returned
to zero after excavation of the second tunnel.

4.4. Induced tilting of the pile cap

Fig. 16 illustrates the measured and computed transverse tilting of


the pile cap after the first and twin tunnels due to tunnelling at different
Fig. 11. Lateral movement of pile cap during twin tunnelling: (a) the first cover to diameter (C/D) ratios (i.e. 1.5, 2.7 and 3.7). The tilting was
tunnel (i.e., tunnels S, T and B); (b) the second tunnel (i.e., tunnels S, T and B). defined as the ratio of differential settlement at two edges of the pile
cap (measured by L1 and L2, see Fig. 3(b)) to the distance between

Fig. 12. Measured and computed induced bending moment due to twin tunnelling in test SS: (a) pile P1; (b) pile P2.

56
M.A. Soomro et al. Computers and Geotechnics 101 (2018) 48–64

Fig. 13. Measured and computed induced bending moment due to twin tunnelling in test TT: (a) pile P1; (b) pile P2.

them. As a sign convention, tilting of the pile cap towards the first agreement in both trend and magnitude, with the maximum difference
tunnel is taken as positive. Owing to soil displacement and shear strain being 10%.
due to first tunnelling stress release, the positive tilting was induced in
the pile cap in each case. The maximum titling (i.e. 0.2%) was observed 4.5. Computed soil displacement vectors and deviatoric strain
when tunnel was excavated adjacent to the pile group toe (i.e. at C/
D = 2.7). This is because of the toe of pile P1 is subjected to major part Fig. 17(a) and (b) shows computed incremental soil displacement
of stress which resulted in intensive shear strain zone around the pile vectors resulting from stress reliefs after the first tunnelling and twin
toe. Consequently, significant positive tilting of the pile cap occurred tunnelling in test SS, respectively. In addition, computed incremental
due to first tunnel at C/D = 2.7. Hence lateral forces were developed on deviatoric strain contours developed after the first and twin tunnelling
the pile as a reaction of the movement of the pile group (explained in are superimposed in the figure. Loganathan et al. [37] assumed tun-
Section 4.6). After second tunnelling in each case the pile cap almost nelling-induced ground movement in sand is mainly bounded by a
tilts back to its original position. This is because of the same reasons as wedge with an inclined angle of 45° + ϕ′/2 (calculated to be 61° for this
due to the first tunnel. The second tunnelling induced stress release study) drawn from the tunnel springline to the ground surface. The
generated shear strain zone on the other side of the pile group (ex- major influence zone proposed by Loganathan et al. [37] is included in
plained in Section 4.6). the figure for comparison. It can be seen that the tunnelling-induced
The measured and computed tilting results show reasonable ground movement occurs predominantly within a 60° wedge (inclined

Fig. 14. Measured and computed induced bending moment due to twin tunnelling in test BB: (a) pile P1; (b) pile P2.

57
M.A. Soomro et al. Computers and Geotechnics 101 (2018) 48–64

Fig. 15. Computed lateral displacement in pile P1 and pile P2 due to twin tunnelling (a) test SS (b) test TT (c) test BB.

to the horizontal) starting from the tunnel springline to the ground It can be seen from Fig. 17(a) that the toes of the pile group are
surface. This is similar to that proposed by Loganathan et al. [37] in located outside the major influence zone of ground movement and
their analytical solution. In addition to ground movement, significant shear strain zone. Furthermore, the soil within the sliding wedge dis-
shear strain (up to 2.4%) is also developed in two ear-shaped zones placed towards the first tunnel resulting in the deflection and bending
extending nearly vertically from the tunnel shoulders. This computed moment in the piles. Since the first tunnel is located at mid depth of the
distribution of shear strain is similar to that measured from centrifuge pile (Z/Lp = 0.61) in test SS, only upper portion of the pile (0 ≤ Z/
tests simulating tunnelling in sand [39,40]. Lp ≤ 0.61) is deflected (see Fig. 15(a)).

58
M.A. Soomro et al. Computers and Geotechnics 101 (2018) 48–64

are directed towards the second tunnel. Furthermore, shear strain zones
generated due to twin tunneling are overlapping each other resulting in
an intensive shear strain zone around the pile group toe. Different from
that in test SS, this ground deformation and shear strain mechanism
inducing a net bending moment in the pile group after the completion
of the both tunnels.
Fig. 19(a) shows computed incremental displacement vectors due to
the first tunnelling in test BB. Computed incremental shear strain re-
sulting from the first tunnelling is also included in the figure. Similar to
tests SS and TT tunnelling-induced ground movement occurred pre-
dominantly within a 60° wedge (inclined to the horizontal) starting
from the tunnel springline to the ground surface. Tunnelling-induced
significant shear strain (up to 2.4%) was also developed in two ear-
shaped zones which extend upwards from the shoulders of the tunnel.
Different from tests SS and TT, the entire pile group in test BB is located
within the major influence zone of ground movement. On the other
hand, toes of the pile group in test BB are located beyond the shear
strain zone. Consequently, smaller tilting of the pile cap (see Fig. 16)
Fig. 16. Induced transverse tilting of the pile cap due to tunnels at different (C/
was induced as compared with that in test TT. Hence the maximum
D) ratios. bending moment induced near pile heads in test BB is less than that of
induced in test TT. Similar to test TT, lateral forces (earth pressure)
were induced in the piles as reaction resulting from the tilting of the
It can be clearly seen from Fig. 17(b) that shear strain zone devel-
pile cap (explained in Section 4.6). Moreover, the directions of soil
oped resulting after twin tunnelling is not overlapping each other.
displacement vectors are towards the first tunnel. As a result of this,
Moreover, the soil displacement occurred vertically towards the twin
lateral movement of the pile toes was observed (see Fig. 15(c)). After
tunnels. This is the evidence of elastic response of the pile group to
the second tunnelling in test BB, tunnelling-induced incremental dis-
second tunnelling in test SS resulting deflection of the pile to its original
placement are directing vertically. This causing the pile group deflects
position (see Fig. 15(a)).
to its original position (see Fig. 15(c)). The overlapping of shear strain
Fig. 18(a) and (b) shows computed incremental soil displacement
zone (as observed from Fig. 19(b)) resulting in a net bending moment of
vectors resulting from stress reliefs after the first tunnelling and twin
340 kN m at Z/Lp = 0.75 (see Fig. 14(b)).
tunnelling in test TT, respectively. Similar to test SS tunnelling-induced
ground movement occurs predominantly within a 60° wedge (inclined
4.6. Comparison of computed induced lateral force due to twin tunnelling
to the horizontal) starting from the tunnel springline to the ground
surface. Significant shear strain (up to 2.4%) is also developed in two
To further explore lateral response of the pile group to twin tun-
ear-shaped zones which extend upwards from the shoulders of the
nelling, computed induced lateral forces (i.e. shearing force) along the
tunnel. Similar to test SS, the toes of the pile group are located outside
pile length is interpreted in this section. Since bending moment and pile
the major influence zone of ground movement. However, the toe of pile
deflection profiles are similar in piles P1 and P2 in each test, this section
P1 is located within the localised region where significant shear strain is
only reports induced lateral forces in pile P1 for illustration.
developed. Since toe of pile P1 is located within the localised intensive
shear strain zone while P2 is located beyond, a relatively large tilting of
4.6.1. Lateral force distribution in test SS
the pile group occurred (see Fig. 16). Due to significant tilting of the
Fig. 20(a) shows the computed induced lateral forces (Fx) in the pile
pile group, large bending moment (see Fig. 13) and deflection (see
P1 after first and second tunnelling in test SS. A positive value of force
Fig. 15(b)) was induced in the piles near the pile head. In addition to
indicates the direction of the force towards the first tunnel. After twin
bending moment and deflection, lateral forces were induced along the
tunnelling, a highly non-linear distribution of lateral force is computed.
piles as reaction to a forced movement of the pile group (explained in
Along the middle portion of the pile (i.e. 0.25 ≤ Z/Lp ≤ 0.61) negative
Section 4.6). After the completion of twin tunnelling in test TT (see
lateral force was induced. This is because of tunnelling induced stress
Fig. 18(b)), tunnelling-induced incremental soil displacement vectors
released and inward soil inward movement towards the first tunnel.

Fig. 17. Computed incremental soil displacement vectors and shear strain in test SS after: (a) the first tunnel; (b) the twin tunnelling.

59
M.A. Soomro et al. Computers and Geotechnics 101 (2018) 48–64

Fig. 18. Computed incremental soil displacement vectors and shear strain in test TT after: (a) the first tunnel; (b) the twin tunnelling.

Fig. 19. Computed incremental soil displacement vectors and shear strain in test BB after: (a) the first tunnel; (b) the twin tunnelling.

The inward soil movement (discussed in section ‘‘Computed ground tunnelling the lateral force reduced 56% of that induced due to first
deformation mechanism and deviatoric strain’’) tends to push the pile tunnelling. This is because of pile group tilted back as result of that the
towards the first tunnel. Consequently the lateral forces are developed second tunnelling induced-shear strain generated at the toe of pile P2
in opposite direction of that of the first tunnel. To counterbalance the (see Fig. 18). The tilting of the pile group on the opposite side has re-
negative induced lateral force, positive lateral force were induced at the leased the reaction (i.e. lateral forces on the pile).
upper portion (i.e. Z/Lp ≥ 0.25) and lower portion of the pile (i.e.
0.61 ≤ Z/Lp ≤ 0.80). The maximum value of 200 kN induced at Z/ 4.6.3. Lateral force distribution in test BB
Lp ≤ 0.50. Since the soil movement after twin tunnelling is vertical, the Fig. 20(c) illustrates the computed induced lateral forces (Fx) in the
net induced negative lateral forces remains at the middle portion of the pile P1 after first and second tunnelling in test BB. Owing to tilting of
pile. However, at the upper portion (i.e. Z/Lp ≥ 0.25) of the pile the the pile cap (see Fig. 16), lateral forces on the pile induced as reaction
induced lateral forces changes the sign (i.e. from positive to negative) as of forced movement of the pile group. The negative lateral forces in-
result stress release induced shear strains (discussed in section ‘‘Com- duced along the entire pile length except near pile head where positive
puted ground deformation mechanism and deviatoric strain’’). After lateral forces were induced. It can be observed from the figure that
twin tunnelling in test SS, a net maximum lateral force of 150 kN was qualitatively, tunneling-induced lateral forces along the length of the
induced at Z/Lp = 0.67. pile in test BB are similar to that of in test TT. The maximum lateral
force of 136 kN induced at Z/Lp ≤ 0.21. During subsequent tunnelling
4.6.2. Lateral force distribution in test TT in test BB, the lateral force reduced to 50 kN (64% of that of due to first
Fig. 20(b) illustrates the computed induced lateral forces (Fx) in the tunnelling) at Z/Lp ≤ 0.21. However, the lateral force increased by
pile P1 after first and second tunnelling in test TT. It can be observed 200% of that during first tunnelling at the pile head.
from the figure that negative lateral force was induced at the lower
portion (i.e. Z/Lp ≥ 0.8) and upper middle portion (0 ≤ Z/Lp ≤ 0.62) of 4.7. Computed normal stresses acting on pile P1
pile P1 after the first tunnelling adjacent to the pile toe. This is because
of the soil displacement towards the first tunnelling-induced stress re- Fig. 21(a), (b) and (c) shows the computed normal stress (horizontal
lease and shear strain (see Fig. 18). Owing to tunnelling-induced in- pressure) acting on pile P1 before and after excavation in tests SS, TT
tensive shear strain zone generated, the pile group tilted towards the and BB, respectively. Two directions were investigated: the front (F)
first tunnel (see Fig. 16). The lateral forces on the piles are hence a and back (B) of the pile, which correspond to their location relative to
reaction to a forced movement of the pile group. The maximum lateral the tunnels. Earth pressure at rest and Rankine active and passive earth
force of 180 kN was induced at Z/Lp ≤ 0.31. After subsequent pressure (Ko, Ka and Kp lines, respectively) are included for comparison.

60
M.A. Soomro et al. Computers and Geotechnics 101 (2018) 48–64

Fig. 20. Computed induced lateral forces along the length of pile P1 after first and second tunnelling (a) test SS (b) test TT (c) test BB.

Considering the normally consolidated condition, Ko is estimated by tunnel (S), normal stress in both direction F and B decreased (with
K 0 = (1−sinφ′) [43]. Ka and Kp are calculated by K a = tan2 (45−φ′/2) maximum percentage reduction of 78% and 52%, respectively at tunnel
and Kp = tan2 (45 + φ′/2) , respectively. In these equations, φ′ is de- springline) dramatically at the middle portion of the pile (i.e. 0.30 ≤ Z/
termined as 31° [23]. Thus Ko, Ka and Kp are 0.51, 0.32, and 3.12, re- Lp ≤ 0.8) which are lower than Rankine active earth pressure. Owing to
spectively. Before twin tunnel excavation, normal stress along the pile reduction in normal stresses in direction F and direction B, soil would
length in directions B and F was approximately equal to the Ko pressure. displace towards the first tunnel (see Fig. 17) and resulted in inducing
It can be observed from Fig. 21(a) that after completion of first lateral force (see Fig. 20(a)), deflection (see Fig. 15(a)) and bending

61
M.A. Soomro et al. Computers and Geotechnics 101 (2018) 48–64

Fig. 21. Computed normal stress acting on the pile in (a) test SS (b) test TT (c) test BB.

moment (see Fig. 12) in the pile. However, after subsequent tunnelling TT) on the other side of the pile group, the normal stress at the lower
on the other side of the pile group, the difference between normal portion of the pile recovered slightly but with the difference in normal
stresses in direction F and direction B decreased. Due to this reason, the stress in the pile in both directions. However, normal stresses at the
induced bending moment and deflection in the pile were reduced. upper part of the pile further increased and reached to Rankine passive
During twin tunnelling near the shaft (test SS), negligible changes in earth pressure at Z/Lp > 0.03. As result of this, the pile toe displaced
normal stresses in both the directions were induced. towards almost its original position and induced lateral force near the
In test TT (see Fig. 21(b)), normal stresses in the pile decreased pile toe reduced insignificantly. On contrary, induced lateral forces
(maximum reduction = 122 kPa) significantly in both directions at increased (with maximum increment of 16.5 kN) at upper part of the
lower portion of the pile (Z/Lp > 0.3) after first tunnelling. However, pile.
the normal stress increased in the upper part of the pile, approaching Similar to tunnelling adjacent to the pile toe, the normal stress in
the Rankine passive earth pressure at shallow depths. This can be at- the pile lower portion (Z/Lp > 0.36) decreased in both directions (di-
tributed to the reaction force generated as result of forced movement of rection F and direction B) with a difference of 10 kPa due to excavation
pile and soil arching as discussed by Jacobsz et al. [26], Ng and Lee of the twin tunnelling below the pile toe in test BB as shown in
[46]. Owing to the differences of normal stresses in the pile in at the Fig. 21(c). However, the normal stress increased at the upper portion of
lower portion direction F and B, the pile toe displaced towards the first the pile (Z/Lp < 0.36) as result of forced movement (i.e. titling see
tunnel and the lateral force was induced at the pile toe. In addition, Fig. 16) of the pile group the earth pressure on the pile. The normal
reduction of normal stresses in the pile at the lower portion, significant stresses became less than the Rankine active earth pressure (Ka). Due to
bending moment (see Fig. 13) induced near pile head. Similarly, owing the difference in normal stresses at the lower portion (Z/Lp > 0.45) of
to stress release due to second tunnelling adjacent to the pile toe (in test the pile, lateral forces and deflection in the pile was induced.

62
M.A. Soomro et al. Computers and Geotechnics 101 (2018) 48–64

controlling 1% volume loss at three critical locations relative to the pile


group, namely near the mid-depth of pile shaft (test SS), next to (test
TT), and below (test BB) the toe of the pile group. Based on the ground
conditions, geometries and tunnelling method simulated, the following
conclusions can be drawn

(a) The most significant lateral movement of the pile cap induced after
the completion of the first tunnel in each test. Among the three
tests, the largest and the smallest lateral movement of the pile cap
resulted from tunnelling below the pile toe (i.e. test TT) and near
mid-depth of the pile shaft (i.e. test SS), respectively. The induced
final cap movement after excavation of first tunnel in tests SS, TT
and BB were 1.7, 9.5 and 2.8 mm (i.e. 0.21%, 1.2% and 0.34% of
pile diameter), respectively.
(b) Among the three tests reported, induced bending moment (which
exceeds the pile BM capacity of 850 kN m) and pile deflection can
be critical when first tunnelling advanced adjacent to pile toe (i.e.
test TT). The maximum lateral displacement of 0.75% of pile dia-
meter was induced at the pile head after completion of the first
tunnelling. However, the induced bending moment along the pile
decreased significantly due to the excavation of the second tunnel
in each case. This is because of the side-by-side twin tunnelling
configuration in which the second tunnel caused a stress release on
the opposite side of the pile.
(c) This suggests that structural integrity of piles should be carefully
Fig. 22. K/Ko variation a column between the first tunnel and pile P1.
checked and protected in the design and construction of tunnelling
adjacent to existing pile foundations, especially for piles in group
Subsequent tunnelling caused further reduction in the normal stresses and pile-raft foundations.
at the lower portion (Z/Lp > 0.45) of the pile. However, normal (d) In addition to vertical load transfer along each pile and load re-
stresses increase at the upper portion of the pile approaching Rankine’s distribution among piles in the group (discussed by Ng et al. [48]),
passive earth pressure (Kp). This increment resulted additional induced lateral forces (shearing forces to the pile group) also induced in
lateral forces at the upper part of the pile. piles during twin tunnelling. This can be because of reaction to pile
group lateral movement. Among three test, maximum lateral force
4.8. Variation of K/Ko along soil column near pile P1 of 200 kN (i.e. 15% of the working load shared by each pile) in-
duced in the pile at Z/Lp ≤ 0.50 in test SS.
Fig. 22 shows the K/Ko variation along a soil column between the
first tunnel and pile P1 before and after excavation in tests SS, TT and Readers should be reminded that the above conclusions are drawn
BB, where K and K0 denote the lateral earth pressure coefficient and the from four centrifuge tests and back-analyses of the tests in dry sand
earth pressure coefficient at rest, respectively. K is calculated by di- only. Any extrapolation from these results should be treated with cau-
viding the horizontal stress by the vertical stress of soil along the soil tion.”
column. In addition, the Ka/Ko line (i.e. Ka/Ko = 0.64) is also shown for
comparison. Before tunnelling, the soil column experienced almost at- Acknowledgements
rest earth pressure. However, the K/Ko increases near the pile head and
toe due to pile group loading. The authors would like to acknowledge the financial support pro-
Owing to the stress relief due to twin tunnelling in test SS, the earth vided by Quaid-e-Awam University of Engineering, Science &
pressure coefficient decreased at along the mid-portion of the soil Technology, Sindh and Pakistan and the Research Grants Council of the
column (i.e. 0 ≤ Z/Lp ≤ 0.62). The value of K approached Rankine HKSAR (General Research Fund Project No. 16207414).
active earth pressure coefficient (Ka). In contrast, the value of K in-
creased at the upper and lower parts of the soil column. This can be References
attributed to the force pile group movement towards tunnelling (i.e.
tilting) generating reaction force and soil arching as discussed by [1] Atkinson JH, Richardson D, Stallebrass SE. Effect of recent stress history on the
Jacobsz et al. [26] and Ng and Lee [46]. During subsequent tunnel on stiffness of over consolidated soil. Géotechnique 1990;40(4):531–40.
[2] Atkinson JH, Sällfors G. Experimental determination of stress-strain-time char-
the other of the pile group in test SS, the value of K decrease slightly at
acteristics in laboratory and in-situ tests. General report. In: Proceedings of 10th
the upper part of the pile. In contrast to reduction of the value of K in European conference on soil mechanics and foundation engineering, Florence, Italy,
the soil column at the tunnel springline (at Z/Lp = 0.67) due to twin vol. 3; 1991. p. 915–56.
tunnelling in test SS, the values of K increased substantially along entire [3] Avgerinos V, Potts DM, Standing JR. Numerical investigation on existing tunnels.
Géotechnique 2017;67(9):808–22.
length of the soil column in tests TT and BB. [4] Basile F. Effects of tunnelling on pile foundations. Soils Found 2014;54(3):280–95.
[5] Bezuijen A, Van der Schrier JS. The influence of a bored tunnel on pile foundations.
In: Proceedings of centrifuge’94, Belkema, Rotterdam, The Netherlands; 1994. p.
5. Summary and conclusions
681–6.
[6] Boonyarak T, Phisitkul K, Ng CWW, Teparaksa W, Aye ZZ. Observed ground and
In this paper, a series of three-dimensional centrifuge model tests pile group responses due to tunneling in Bangkok stiff clay. Can Geotech J
2014;51(5):479–95.
and numerical simulations using an advanced hypoplastic soil model
[7] Chen LT, Poulos HG, Loganathan N. Pile responses caused by tunneling. J Geotech
were carried out to investigate the lateral response of an existing 2 × 2 Geoenviron Eng 1999;125(3):207–15.
pile group to advancement of side-by-side twin tunnels at various [8] Cheng CY, Dasari GR, Chow YK, Leung CF. Finite element analysis of tunnel-soil-pile
depths in dry sand. Side-by-side twin tunnels (excavated one after the interaction using displacement controlled model. Tunn Undergr Space Technol
2007;22:450–66.
other on both sides of the pile group) were simulated in-flight by

63
M.A. Soomro et al. Computers and Geotechnics 101 (2018) 48–64

[9] Coutts DR, Wang J. Monitoring of reinforced concrete piles under horizontal and [40] Marshall AM, Mair RJ. Tunneling beneath driven or jacked end-bearing piles in
vertical loads. In: Proceeding of the international conference on tunnels and un- sand. Can Geotech J 2011;48(12):1757–71.
derground structures, Singapore; 2000. p. 541–6. [41] Marshall AM. Tunnel-pile interaction analysis using cavity expansion methods. J
[10] Dias TGS, Bezuijen A. Data analysis of pile tunnel interaction. J Geotech Geoenviron Geotech Geo Environ Eng 2012;138(10):1237–46.
Eng 2015:04015051. http://dx.doi.org/10.1061/(ASCE)GT.1943-5606.0001350. [42] Marshall AM, Haji T. An analytical study of tunnel-pile-interaction. Tunnell
[11] Fioravante V. On the shaft friction modelling of non-displacement piles in sand. Undergr Space Technol 2015;45(Jan):43–51.
Soils Found 2002;42(2):23–33. [43] Mayne P, Kulhawy F. K0-OCR relationships in soils. J Geotech Eng ASCE
[13] Franza A, Marshall AM. Centrifuge modelling of tunnelling beneath axially loaded 1982;108(6):851–72.
displacement and non-displacement piles in sand. In: Branson TL, Valentine RJ, [44] Mroueh H, Shahrour I. Three-dimensional finite element analysis of the interaction
editors. Proc, geotechnical frontiers. GSP 277: transportation facilities, structures, between tunnelling and pile foundations. Int J Numer Anal Meth Geomech
and site investigation. Reston (VA): ASCE; 2017b. p. 576–86. 2002;26:217–30.
[15] Franza A, Marshall AM. Centrifuge modeling study of the response of piled struc- [46] Ng CWW, Lee GTK. Three-dimensional ground settlements and stress transfer me-
tures to tunneling. J Geotech Geoenviron Eng 2018;144(2):04017109. chanisms due to open-face tunnelling. Can Geotech J 2005;42(4):1015–29.
[16] Fuglsang LD, Ovesen NK. The theory of modelling to centrifuge studies, centrifuge [47] Ng CWW, Lu H. Effects of construction sequence of twin tunnelling at different
in soil mechanics. Craig, James, Schofield, editors. Balkema, Rotterdam; 1988. depth on a single pile. Can Geotech J 2013;51(2):173–83.
[17] Gudehus G. A comprehensive constitutive equation for granular materials. Soils [48] Ng CWW, Lu H, Peng SY. Three-dimensional centrifuge modelling of effects of twin
Found 1996;36(1):1–12. tunnelling on as existing pile. Tunnell Undergr Space Technol 2013;35:189–99.
[18] Gudehus G, Mašín D. Graphical representation of constitutive equations. [49] Ng CWW, Soomro MA, Hong Y. Three-dimensional centrifuge modelling of pile
Géotechnique 2009;59(2):147–51. http://dx.doi.org/10.1680/geot.2007.00155. group responses to side-by-side twin tunnelling. Tunn Undergr Space Technol
[19] Herle I, Gudehus G. Determination of parameters of a hypoplastic constitutive 2014;43:350–61.
model from properties of grain assemblies. Mech Cohesive Frictional Mater [50] Ng CWW. The 6th ZENG Guo-xi Lecture: the State-of-the-Art centrifuge modelling
1999;4(5):461–86. of geotechnical problems at HKUST. J Zhejiang Univ – Sci A (Appl Phys Eng)
[20] Hibbitt, Karlsson, Sorensen. Abaqus user’s manual, version 6.8.2. Providence, RI, 2014;15:1–21.
USA: Hibbitt, Karlsson & Sorensen Inc; 2008. [51] Ng CWW, Hong Y, Soomro MA. Effects of piggyback twin tunnelling on a pile group:
[21] Huang M, Zhang C, Li Z. A simplified analysis method for the influence of tunnelling 3D centrifuge tests and numerical modelling. Géotechnique 2015;65(1):38–51.
on grouped piles. Tunn Undergr Space Technol 2009;24:410–22. [52] Niemunis A, Herle I. Hypoplastic model for cohesionless soils with elastic strain
[22] Hu ZF, Yue ZQ, Tham LG. Design and construction of a deep excavation in soft soils range. Mech Cohesive-Frict Mater 1997;2:279–99.
adjacent to the Shanghai Metro tunnels. Can Geotech J 2003;40:933–48. [53] Pang CH, Yong KY, Chow YK. Three dimensional numerical simulation of tunnel
[23] Hong Y, Soomro MA, Ng CWW. Settlement and load transfer mechanism of pile advancement on adjacent pile foundation. In: Erdem Y, Solak, T, editor.
group due to side-by-side twin tunnelling. Comput Geotech 2015;64(105):119. Underground space use: analysis of the past and lessons for the future. London:
[24] Ishihara K. Liquefaction and flow failure during earthquakes. Géotechnique Taylor and Francis; 2005. p. 1141–7.
1993;43(3):351–415. [54] Peng SY. Influence of stress relief due to deep excavation on capacity of pile
[25] Jáky J. The coefficient of earth pressure at rest. J Soc Hungarian Arch AndEng foundations [Ph.D. thesis]. Hong Kong University of Science and Technology; 2012.
1944;355–8 [in Hungarian]. [55] Selemetas D. The response of full-scale piles and pile structures to tunneling [Ph.D.
[26] Jacobsz SW, Standing JR, Mair RJ, Hahiwara T, Suiyama T. Centrifuge modeling of thesis]. Cambridge University; 2005.
tunnelling near driven piles. Soil Found 2004;44(1):49–56. [56] Soomro MA, Hong Y, Ng CWW, Lu H, Peng SY. Load transfer mechanism in pile
[27] Jongpradist P, Kaewsri T, Sawatparnich A, Suwansawat S, Youwai S, Kongkitkul W, group due to single tunnel advancement in stiff clay. Tunn Undergr Space Technol
et al. Development of tunneling influence zones for adjacent pile foundations by 2015;45:63–72.
numerical analyses. Tunnell Undergr Space Technol 2013;34(Feb):96–109. [57] Von Wolffersdorff PA. A hypoplastic relationship for granular materials with a
[28] Kishida H, Uesugi M. Tests of the interface between sand and steel in the simple predefined limit state surface. Mech. Cohesive-frictional Mater 1 1996;No. 3:251,
shear apparatus. Géotechnique 1987;37(1):45–52. 271.
[29] Kolymbas D. An outline of hypoplasticity. Arch Appl Mech 1991;61(3):143–51. [58] Zhang RJ, Zheng JJ, Zhang LM, Pu HF. An analysis method for the influence of
[30] Korff M, Mair RJ, Van Tol FAF. Pile-soil interaction and settlement effects induced tunneling on adjacent loaded pile groups with rigid elevated caps. Int J Numer Anal
by deep excavations. J Geotech Geoenviron Eng 2016;142(8):04016034. Methods Geomech 2011;35(18):1949–71.
[31] Lee CJ, Chiang KH. Responses of single piles to tunnelling-induced soil movements
in sandy ground. Can Geotech J 2007;44(10):1224–41.
[32] Lee CJ. Numerical analysis of the interface shear transfer mechanism of a single pile Further reading
to tunnelling in weathered residual soil. Comput Geotech 2002;42:193–203.
[33] Lee CJ. Three-dimensional numerical analyses of the response of a single pile and [12] Franza A, Marshall AM. A centrifuge modelling study of the response of piled
pile groups to tunnelling in weak weathered rock. Tunn Undergr Space Technol structures to tunneling. J Geotech Geoenviron Eng 2017http://dx.doi.org/10.
2012;32:132–42. 17639/nott.74.
[35] Lee GTK, Ng CWW. The effects of advancing open face tunneling on an existing [14] Franza A, Marshall AM, Haji T, Abdelatif AO, Carbonari S, Morici M. A simplified
loaded pile. J Geotech Geoenviron Eng, ASCE 2005;131(2):193–201. elastic analysis of tunnel-piled structure interaction. Tunnell Undergr Space
[36] Loganathan N, Poulos HG, Stewart DP. Centrifuge model testing of tunnelling-in- Technol 2017;61(Jan):104–21.
duced ground and pile deformations. Géotechnique 2000;50(3):283–94. [34] Lee CJ. Numerical analysis of pile response to open face tunnelling in stiff clay.
[37] Loganathan N, Poulos HG, Xu KJ. Ground and pile group responses due to tun- Comput Geotech 2013;42:116–27.
neling. Soils Found 2001;41(1):57–67. [45] Ng CWW, Yau TLY, Li JHM, Tang WH. New failure load criterion for large diameter
[38] Maeda K, Miura K. Relative density of dependency of mechanical properties of bored piles in weathered geomaterials. J Geotech Geoenviron Eng, ASCE
sands. Soils Found 1999;39(1):69–79. 2001;127(6):488–98.
[39] Marshal AM. Tunnelling in sand and its effect on pipelines and piles. Engineering
Department, Cambridge University; 2009.

64

You might also like