You are on page 1of 7

[Company header / Kop perusahaan]

BILL OF QUANTITY
PROJECT : SITE IMPROVEMENT OF ROHINGYA CAMP
ACTIVITY : WASH INFRASTRUCTURE
LOCATION : MINA RAYA CAMP, ACEH PIDIE
DATE : 2023
* English language is official version
* Site visit must be conducted prior submitted the unit prices

No Description Deskripsi Unit Qty Unit Price Total Price

SCOPE OF WORK LINGKUP PEKERJAAN


Provision of WASH system (water, sanitation, and Penyediaan sistem WASH (air, sanitasi, dan
hygiene), including deep well, pump, piping, and kebersihan), termasuk sumur dalam, pompa,
water tank. Works include all requirements in pemipaan, dan tangki air. Pekerjaan termasuk semua
drawing, bill of quantities, and technical specification item pekerjaan yang tertera dalam gambar, rencana
follows. biaya, dan spesifikasi teknis berikut ini.

A Preparation works Pekerjaan Persiapan 7,500,000

1 Geo-electrical survey Survey Geolistrik lot 1.00 7,500,000 7,500,000


The purpose is to determine the general description of Bertujuan untuk mengetahui gambaran secara umum
the geology below the surface, especially for the rock mengenai geologi bawah permukaan tanah, terutama
which contain aquifer, both in vertical and horizontal batuan yang mengandung akuifer (air bawah tanah) baik
aspect at the site. secara vertical maupun horizontal di lokasi kerja.

Scope of works: Lingkup pekerjaan:


1.1 Geo-electrical test and application, Field data collection Tes dan Aplikasi Geolistrik, Pengambilan dan proses
and processing, Report & Recommendation data lapangan, Laporan & Rekomendasi

B Deep Well Sumur Dalam 113,156,500

1 Deep Well Drilling works, depth minimum 60m or Pengeboran Sumur dalam, kedalaman minimal 60m atau lot 1.00 33,000,000 33,000,000
Production capacity minimum 2000 liter/hour kapasitas produksi minimal 2000 liter/jam
Scope of works: Lingkup pekerjaan:
1.1 Setting up the drilling rig and mud pit Pembuatan Spull Bak dan Setting up Mesin Bor
1.2 Drilling of pilot hole dia. 6 inch Pengeboran Pilot hole dia. 6 inch
1.3 Drilling of Reaming Hole from dia. 5 inch ke dia. 6 inch Pengeboran reaming Hole dari dia. 5 inch ke dia. 6 inch

1.4 Taking dan examination of rock specimens Pengambilan dan Pemeriksaan contoh batuan (cutting)
1.5 Measuring Electrical well logging consist of Pengukuran Electrical well logging terdiri dari
Spontaneous Potential (SP) and Resistivity Spontaneous Potential (SP) dan Resistivity

2 Deep Well Construction, depth minimum 60m or Konstruksi Sumur dalam, kedalaman minimal 60m atau lot 1.00 12,000,000 12,000,000
Production capacity minimum 2000 liter/hour kapasitas produksi minimal 2000 liter/jam
Scope of works: Lingkup pekerjaan:
2.1 PVC Pipe dia. 4 inch for casing Pipa PVC dia. 4 inch untuk casing
2.2 PVC Pipe dia. 2 inch for supply Pipa PVC dia. 2 inch untuk pipa suplai
2.3 Bottom Plug (end cup) Penutup ujung pipa bawah
2.4 PVC Flanges dia. 4 inch Penutup sumur atau pipa atas dia. 4 inch
2.5 Screen production pipe Saringan produksi dalam pipa
2.6 Gravel pack to prevent sand and fine particles moving Pengisian kerikil untuk mencegah pasir dan material
from the aquifer formation into the well halus lain masuk dari formasi aquifer ke sumur

2.7 Grouting Works (cement grout) Supply grouting Pengisian mortar semen, Menyediakan material
material and grout annular space between bore hole pengisi celah antara sumur bor dan casing untuk
and casing to prevent surface water from drainage mencegah air permukaan mengalir kebawah
downward and contaminating the well and aquifer. The disekeliling luar casing dan mengkontaminasi sumur
grout must be added from the bottom of the annular dan aquifer. Material grout ini diisi dari bawah naik
space upward in one continuous operation until the keatas secara terus menerus tanpa terputus hingga
annular space is filled. seluruh celah terisi.

3 Well Development and pumping test Pekerjaan penyempurnaan sumur dan tes pemompaan lot 1.00 10,000,000 10,000,000

Scope of works: Lingkup pekerjaan:


3.1 Cleaning the well by water jetting method Pembersihan sumur dengan metode water jetting
3.2 Aquifer test Tes aquifer
3.3 Pumping test Uji pemompaan
3.4 Step drawdown test Uji bertingkat

Page 1 of 7
[Company header / Kop perusahaan]

BILL OF QUANTITY
PROJECT : SITE IMPROVEMENT OF ROHINGYA CAMP
ACTIVITY : WASH INFRASTRUCTURE
LOCATION : MINA RAYA CAMP, ACEH PIDIE
DATE : 2023
* English language is official version
* Site visit must be conducted prior submitted the unit prices

No Description Deskripsi Unit Qty Unit Price Total Price

3.5 Time recovery test Uji Pemulihan

4 Mechanical and Electrical Pekerjaan mekanikal dan listrik lot 1.00 54,406,500 54,406,500
Scope of works: Lingkup pekerjaan:
4.1 Supply and installation of Control Panel 3 phase (50 x Pengadaan dan pemasangan Panel kontrol 3 phase
60 cm) and automatic control unit for all pumps, MCB ukutan 50 x 60 cm dan unit kontrol otomatis untuk
and all Water Level Control (WLC) including indicator semua pompa air terpasang, MCB dan semua WLC
lamp termasuk lampu indikator

4.2 Wire sling f 12mm Kabel baja sling f 12mm gantungan pompa celup
4.3 Water resistant cable for submersible pump Kabel tahan air untuk pompa submersible
4.4 Electroda cable Kabel elektroda
4.5 Electrode at well and raw water reservoir Elektroda pada sumur dan reservoir
4.6 Cable NYM 3x2.5mm for 3 unit WLC Kabel NYM 3x2.5mm untuk 3 unit WLC
4.7 Water Level Control (WLC) incl. all accessories Water Level Control (WLC) termasuk aksesoris
4.8 High quality Submersible pump 1 HP, 3 phase, Pompa submersible 1 HP, 3 Phase kualitas tinggi,
stainlessteel, Capacity 2m3/hr, Total Head min. 70m for stainlessteel, kapasitas min. 2m3/jam, total head min.
deep well 70m untuk sumur dalam

4.9 Supply and installation of Booster Pump, head 20m, 2 Pengadaan dan pemasangan Pompa dorong, head
units, including pump house made of metal frame and 20m, 2 unit, termasuk rumah pompa terbuat dari
zinc cover for protection from weather. rangka besi dan tutup seng sebagai pelindung dari
Both the pumps installed to each water tank, include cuaca.
gate valves to allow the pump working alternately Kedua pompa dipasang paralel termasuk stop kran
(Clean water tank to all distribution pipeline) sehingga pompa bisa bekerja bergantian.

4.10 Supply and install control pit for well 50cm x 50cm x Pembuatan bak kontrol sumur uk. 50cm x 50cm x 50cm
50cm, brick wall, plaster including steel plate 5mm dari pasangan bata, plaster dan termasuk plat besi
cover penutup tebal 5mm.

5 Pipeline Installation Pekerjaan plumbing lot 1.00 3,750,000 3,750,000


Scope of works: Lingkup pekerjaan:
5.1 Excavation works and Backfilling excavation trench Pekerjaan galian dan Penimbunan galian pipa

5.2 Supply and installation of PVC pipe dia. 2 inch and all Sediakan dan pasang pipa PVC dia. 2 inchi, dan semua
acessories, as listed below aksesoris lain seperti tersebut dibawah ini.
5.3 PVC pipe dia 2 inch from deep well to water tank Pemasangan pipa PVC dia. 2 inch dari sumur dalam ke
tangki air
5.4 Steel Socket 2" Pemasangan sambungan pipa 2"
5.5 GIP Gate Valve 2" (wash out) Pemasangan stop kran GIP Gate 2" (pembuang)
5.6 GIP Gate Valves flange 2" Pemasangan stop kran galvanis 2" dengan flange
5.7 GIP Tee 2" at top of deep weel Pemasangan simpang tiga galvanis 2" pd sumur
5.8 GIP elbow 2" Pemasangan elbow galvanis 2"

C Water Tanks and Tower Tangki Air dan Menara 72,000,000

1 Water tanks Tangki Air lot 2.00 3,500,000 7,000,000


Scope of works: Lingkup pekerjaan:
1.1 Fiber water tanks cap. 1000 liter, ex. Penguin or equal Tangki air fiber cap. 1000 liter, ex. Penguin atau setara

1.2 Including all required plumbing and accessories Termasuk seluruh pipa dan aksesoris yang diperlukan

2 Tower for water tanks Menara tangki air lot 1.00 65,000,000 65,000,000
Scope of works: Lingkup pekerjaan:
2.1 Angle bar construction 50x50x5 mm, welded, anti-rust Konstruksi besi siku 50x50x5 mm, sambungan las,
paint finishing finishing cat anti karat
2.2 Concete foundation Pondasi beton
2.3 Height 4m from ground surface Tinggi 4m dari permukaan tanah
2.4 To support 2 units water tanks @ 1000 liter Daya tampung 2 unit tangki air @ 1000 liter
Location: Lokasi kerja:

Page 2 of 7
[Company header / Kop perusahaan]

BILL OF QUANTITY
PROJECT : SITE IMPROVEMENT OF ROHINGYA CAMP
ACTIVITY : WASH INFRASTRUCTURE
LOCATION : MINA RAYA CAMP, ACEH PIDIE
DATE : 2023
* English language is official version
* Site visit must be conducted prior submitted the unit prices

No Description Deskripsi Unit Qty Unit Price Total Price

Near to new deep well Berdekatan dengan sumur dalam baru

D Improvement of Distribution Pipe Perbaikan Pipa Distribusi 6,500,000

1 Distribition pipe Pipa distribusi lot 1.00 6,500,000 6,500,000


Scope of works: Lingkup pekerjaan:
1.1 Replace broken PVC pipe and joint Mengganti seluruh pipa PVC yang rusak termasuk
sambungannya
1.2 PVC Pipe dia. 1/2 inch up to dia. 1 inch Pipa PVC dia. 1/2 inchi hingga dia. 1 inchi
1.3 Maximum up to 100 pcs pipe and joint Maximum hingga 100 batang pipa dan sambungan

Location: Lokasi kerja:


1. Male toilet 1. Toilet laki-laki
2. Male washing area 2. Area pemandian laki-laki
3. Female toilet 3. Toilet perempuan
4. Female washing area 4. Area pemandian perempuan
RECAPITULATION REKAPITULASI 199,156,500

A Preparation works Pekerjaan Persiapan 7,500,000


B Deep Well Sumur Dalam 113,156,500
C Water Tanks and Tower Tangki Air dan Menara 72,000,000
D Improvement of Distribution Pipe Perbaikan Pipa Distribusi 6,500,000
VAT 11% 19,915,650
TOTAL 219,072,150

IN AMOUNT / TERBILANG …………………………………………………………… Rupiah

Note:
All supply and delivery cost to the work's site is contractor reponsibility.
IOM is not responsible for the government tax, fees, and other miscellaneous fee. All the work stated above must be in accordance with scope of works.
Catatan:
Semua harga pengangkutan dan penyediaan material ke lapangan akan menjadi tanggung jawab kontraktor.
IOM tidak bertanggung jawab terhadap pajak, potongan dan biaya lainnya dari pemerintah RI. Semua pekerjaan di atas harus mengacu pada " lingkupan kerja"

Submitted by
PT / CV …...............................

......[Name & Signature]………


Director

Page 3 of 7
[Company header / Kop perusahaan]

BILL OF QUANTITY
PROJECT : SITE IMPROVEMENT OF ROHINGYA CAMP
ACTIVITY : REFURBISHMENT OF EXISTING TOILET (M/F)
LOCATION : MINA RAYA CAMP, ACEH PIDIE
DATE : 2023
* English language is official version
* Site visit must be conducted prior submitted the unit prices

No Description Deskripsi Unit Qty Unit Price Total Price

SCOPE OF WORK LINGKUP PEKERJAAN


To improve existing toilets at Male and Female area, Peningkatan kondisi fasilitas toilet eksisting area Laki-
in general aspect to create better environtment. laki dan Perempuan, secara umum untuk menciptakan
Works include all requirements in drawing, bill of linkungan yang lebih baik. Pekerjaan termasuk semua
quantities, and technical specification follows. item pekerjaan yang tertera dalam gambar, rencana
biaya, dan spesifikasi teknis berikut ini.

A Preparation works Pekerjaan Persiapan 20,000,000

1 To provide tools and equipment required to complete the Menyediakan seluruh peralatan dan perlengkapan kerja, lot 1.00 20,000,000 20,000,000
works, including housekeeping and removal of excess termasuk pembersihan area kerja dari sampah dan sisa
material from the working area during and after works material selama pekerjaan berlangsung dan setelah
completion. pekerjaan selesai

B Toilet Male Shelter: Septic Tank and Soak Pit 53,005,700


Toilet Hunian Laki-laki: Septic Tank dan Sumur Resapan

1 Excavation for septic tank Galian tanah septic tank m3 - - -


● Septic tank dimension L 4,5m, W 2,5m, H 2,5m ● Ukuran Septic tank P 4,5m, L 2,5m, T 2,5m
*Excavation is inlcuded in the provision of heavy *Galian sudah termasuk dalam pekerjaan penyediaan alat
equipement and land clearing works berat dan pembersihan lahan
2 Lean concrete for foundation, mortar 1:2:3 (K125) Lantai kerja untuk pondasi, campuran 1:2:3 (K125) m3 0.56 1,200,000 675,000
● Thickness 5cm ● Ketebalan 5cm
● Location: all pedestal foundation, tie beam, and floor ● Lokasi: seluruh pondasi umpak, sloof, dan lantai

3 Concrete foundation (pedestal), mortar 1:2:3 (K-175) Pondasi beton cor (umpak), campuran 1:2:3 (K-175) m3 0.10 1,200,000 115,200

● Size: 20x20x40cm ● Ukuran: 20x20x40cm


● Location: 6 points, for all pole at corner and middle ● Lokasi: 6 titik, setiap tiang sudut dan tengah

4 Reinforced concrete tie beam, mortar 1:2:3 (K-175) Sloof beton bertulang, campuran 1:2:3 (K-175) m3 0.66 5,300,000 3,498,000
● Size: 20x20cm, Length as shown in drawing ● Ukuran: 20x20cm, Panjang sesuai petunjuk gambar
● Rebar 4 x dia.10mm ● Pembesian 4 x dia. 10mm
● Location: all area with walls ● Lokasi: seluruh area berdinding
5 Reinforced concrete column, mortar 1:2:3 (K-175) Kolom beton bertulang, campuran 1:2:3 (K-175) m3 0.60 5,300,000 3,180,000
● Size: 20x20cm, Height as shown in drawing ● Ukuran: 20x20cm, Tinggi sesuai petunjuk gambar
● Rebar 4 x dia.10mm ● Pembesian 4 x dia. 10mm
● Location: all corners and wall joints ● Lokasi: seluruh sudut dan sambungan dinding
6 Reinforced concrete floor, thickness 7cm, mortar 1:2:3 Lantai beton bertulang tebal 7cm, campuran 1:2:3 (K-175) m3 0.79 6,000,000 4,725,000
(K-175)
● Septic tank dimension L 4,5m, W 2,5m ● Ukuran Septic tank P 4,5m, L 2,5m
● Rebar dia.8mm, 15cm x 15cm, 1 layer ● Pembesian dia. 8mm, 15cm x 15cm, 1 lapis
● Location: bottom floor of septic tank ● Lokasi: lantai bagian dasar septic tank
7 Half brick masonry walls, mortar 1:4 Dinding pasangan 1/2 bata, campuran 1:4 m2 41.25 300,000 12,375,000
● Including plastering on both sides, mortar 1:4 ● Termasuk pekerjaan plaster di kedua sisi, campuran 1:4
● Size: height 2,5m, length as shown in drawing ● Ukuran: tinggi 2,5m, panjang sesuai petunjuk gambar
9 Reinforced concrete floor (top cover), thickness 10cm, Lantai beton bertulang (tutup atas) tebal 10cm, campuran m3 1.13 6,500,000 7,312,500
mortar 1:2:3 (K225) 1:2:3 (K225)
● Septic tank dimension L 4,5m, W 2,5m ● Ukuran Septic tank P 4,5m, L 2,5m
● Rebar dia.8mm, 15cm x 15cm, 1 layer ● Pembesian dia. 8mm, 15cm x 15cm, 1 lapis
● Including manhole 60x60 cm and it's cover, 2 units ● Termasuk lubang 60x60 cm dan tutupnya, 2 unit

● Location: top floor of septic tank ● Lokasi: lantai bagian atas septic tank
9 Waste water pipe, SEPTIC TANK & SOAK PIT Pipa air kotoran, SEPTIC TANK & RESAPAN m' 22.00 100,000 2,200,000
● Pipa PVC dia. 4 inch ● PVC pipe dia. 4 inch
● Icluding all required accessories ● Termasuk seluruh aksesoris yang dibutuhkan
● Location: as shown in drawing ● Lokasi: sesuai petunjuk gambar
10 Ventilation pipe Pipa ventilasi pcs 3.00 75,000 225,000
● Pipa PVC dia. 3 inch ● PVC pipe dia. 3 inch
● Height 1m from top cover ● Tinggi 1m dari permukaan lantai atas
● Location: as shown in drawing ● Lokasi: sesuai petunjuk gambar

Page 4 of 7
[Company header / Kop perusahaan]

BILL OF QUANTITY
PROJECT : SITE IMPROVEMENT OF ROHINGYA CAMP
ACTIVITY : REFURBISHMENT OF EXISTING TOILET (M/F)
LOCATION : MINA RAYA CAMP, ACEH PIDIE
DATE : 2023
* English language is official version
* Site visit must be conducted prior submitted the unit prices

No Description Deskripsi Unit Qty Unit Price Total Price

11 Waste water pipe, from each Toilet to SEPTIC TANK Pipa air kotoran, dari tiap Toilet ke SEPTIC TANK m' 27.00 100,000 2,700,000
● Pipa PVC dia. 4 inch ● PVC pipe dia. 4 inch
● Icluding all required accessories ● Termasuk seluruh aksesoris yang dibutuhkan
● Location: as shown in drawing ● Lokasi: sesuai petunjuk gambar
12 Soak pit Sumur resapan lot 4.00 4,000,000 16,000,000
● Soak pit dimension dia. 0,9m, H 2m ● Ukuran Sumur Resapan dia. 0,9m, T 2m
● 2 units for septic tank, 2 units for drainage ● 2 unit untuk septic tank, 2 unit untuk saluran air
● Concrete ring dia.90cm, thickness 7cm ● Cincin sumur beton dia. 90cm, tebal 7cm
● Reinforced concrete cover, thickness 7cm ● Tutup sumur beton bertulang tebal 7cm
● Works include supply of filters: ● Pekerjaan termasuk penyediaan filter resapan:
1. lime stone 1. batu kapur
2. gravel and sand 2. kerikil dan pasir
3. Coconut fiber 3. Ijuk kelapa

C Toilet Female Shelter: Septic Tank and Soak Pit 53,005,700


Toilet Hunian Perempuan: Septic Tank dan Sumur Resapan

Scope of work, dimension, specification, and price refer Lingkup kerja, ukuran, spesifikasi, dan harga mengacu pada lot 1.00 53,005,700 53,005,700
to point B. Toilet Male Shelter: Septic Tank and Soak Pit poin B. Toilet Hunian Laki-laki: Septic Tank dan Sumur
Resapan

D Toilet Family Shelter: Septic Tank and Soak Pit 28,750,000


Toilet Hunian Keluarga: Septic Tank dan Sumur Resapan

1 Septic tank Septic tank lot 3.00 4,000,000 12,000,000


● Septic tank dimension dia. 0,9m, H 2m ● Ukuran Septic tank dia. 0,9m, T 2m
● Concrete ring dia.90cm, thickness 7cm ● Cincin sumur beton dia. 90cm, tebal 7cm
● Concrete floor thickness 7cm at bottom part ● Lantai beton tebal 7cm pada bagian dasar
● Reinforced concrete cover, thickness 7cm ● Tutup sumur beton bertulang tebal 7cm
2 Waste water pipe, SEPTIC TANK & SOAK PIT Pipa air kotoran, SEPTIC TANK & RESAPAN m' 6.00 100,000 600,000
● Pipa PVC dia. 4 inch ● PVC pipe dia. 4 inch
● Icluding all required accessories ● Termasuk seluruh aksesoris yang dibutuhkan
● Location: as shown in drawing ● Lokasi: sesuai petunjuk gambar
3 Ventilation pipe Pipa ventilasi pcs 2.00 75,000 150,000
● Pipa PVC dia. 3 inch ● PVC pipe dia. 3 inch
● Height 1m from top cover ● Tinggi 1m dari permukaan lantai atas
● Location: as shown in drawing ● Lokasi: sesuai petunjuk gambar
4 Waste water pipe, from each Toilet to SEPTIC TANK Pipa air kotoran, dari tiap Toilet ke SEPTIC TANK m' 40.00 100,000 4,000,000
● Pipa PVC dia. 4 inch ● PVC pipe dia. 4 inch
● Icluding all required accessories ● Termasuk seluruh aksesoris yang dibutuhkan
● Location: as shown in drawing ● Lokasi: sesuai petunjuk gambar
5 Soak pit Sumur resapan lot 3.00 4,000,000 12,000,000
● Soak pit dimension dia. 0,9m, H 2m ● Ukuran Sumur Resapan dia. 0,9m, T 2m
● 2 units for septic tank, 1 units for drainage ● 2 unit untuk septic tank, 1 unit untuk saluran air
● Concrete ring dia.90cm, thickness 7cm ● Cincin sumur beton dia. 90cm, tebal 7cm
● Reinforced concrete cover, thickness 7cm ● Tutup sumur beton bertulang tebal 7cm
● Works include supply of filters: ● Pekerjaan termasuk penyediaan filter resapan:
1. lime stone 1. batu kapur
2. gravel and sand 2. kerikil dan pasir
3. Coconut fiber 3. Ijuk kelapa

RECAPITULATION REKAPITULASI 154,761,400

A Preparation works Pekerjaan Persiapan 20,000,000


B Toilet Male Shelter: Septic Tank and Soak Pit Toilet Hunian Laki-laki: Septic Tank dan Sumur Resapan 53,005,700
C Toilet Female Shelter: Septic Tank and Soak Pit Toilet Hunian Perempuan: Septic Tank dan Sumur Resapan 53,005,700
D Toilet Family Shelter: Septic Tank and Soak Pit Toilet Hunian Keluarga: Septic Tank dan Sumur Resapan 28,750,000
VAT 11% 15,476,140
TOTAL 170,237,540

Page 5 of 7
[Company header / Kop perusahaan]

BILL OF QUANTITY
PROJECT : SITE IMPROVEMENT OF ROHINGYA CAMP
ACTIVITY : REFURBISHMENT OF EXISTING TOILET (M/F)
LOCATION : MINA RAYA CAMP, ACEH PIDIE
DATE : 2023
* English language is official version
* Site visit must be conducted prior submitted the unit prices

No Description Deskripsi Unit Qty Unit Price Total Price

IN AMOUNT / TERBILANG …………………………………………………………… Rupiah

PROJECT : SITE IMPROVEMENT OF ROHINGYA CAMP


ACTIVITY : LAND CLEARING FOR TOILET AND WASHING AREA
LOCATION : MINA RAYA CAMP, ACEH PIDIE
DATE : 2023

No Description Deskripsi Unit Qty Unit Price Total Price


SCOPE OF WORK LINGKUP PEKERJAAN
Provision and operation of heavy equipment for land Penyediaan dan pengoperasian alat berat untuk
clearing and excavation around toilets and washing pembersihan lahan dan galian di sekitar toilet dan
area as preparation to new sanitation system, pemandian untuk persiapan pembangunan sistem
including septic tank and drainage. Works include all sanitasi baru, termasuk septic tank dan saluran air.
requirements in drawing, bill of quantities, and Pekerjaan termasuk semua item pekerjaan yang tertera
technical specification follows. dalam gambar, rencana biaya, dan spesifikasi teknis
berikut ini.

A Preparation works Pekerjaan Persiapan 32,500,000

1 To provide tools and equipment required to complete the Menyediakan seluruh peralatan dan perlengkapan kerja, lot 1.00 25,000,000 25,000,000
works, including housekeeping and removal of excess termasuk pembersihan area kerja dari sampah dan sisa
material from the working area during and after works material selama pekerjaan berlangsung dan setelah
completion. pekerjaan selesai

2 Mobilization and demobilization of heavy equipment: Mobilisasi dan demobilisasi alat berat: Excavator (Backhoe) lot 1.00 7,500,000 7,500,000
Excavator (backhoe)
B Land Clearing and Excavation Pembersihan Area dan Galian 45,500,000

1 Provision and operation of of heavy equipment: Penyerdiaan dan pengoperasian alat berat: Excavator lot 1.00 45,500,000 45,500,000
Excavator (backhoe) (backhoe)
● Excavator dimesion and spesification should be ● Dimensi dan spesifikasi excavator harus disesuaikan
adjusted with the condition and access of the site. dengan kondisi dan akses di lokasi kerja. Vendor diwajibkan
Vendor is required to do survey prior to the works. melakukan survey terlebih dahulu.

Scope of works: Lingkup pekerjaan:


1. To open and close access to the site. Including to 1. Membuka dan menutup kembali akses masuk ke lokasi
remove and reinstall existing fence, if any. kerja. Termasuk membongkar dan memasang kembali
pagar eksisting, jika ada.

2. Land clearing 2. Pembersihan lokasi


3. Excavation for septic tank (dimension as drawing) 3. Galian untuk septic tank (ukuran sesuai gambar)

4. Excavation for drainage (dimension as drawing) 4. Galian untuk saluran air (ukuran sesuai gambar)
5. Excavation for soak pit area (dimension as drawing) 5. Galian untuk area resapan (ukuran sesuai gambar)

6. Ensure waste water from washing area flows to the 6. Memastikan air kotor dari area mandi mengalir ke
drainage and soak pit area saluran dan resapan
7. Spread and leveling of all material result from the 7. Menebar dan meratakan sisa material dari galian di
excavation around the site sekitar area kerja
8. Final cleaning 8. Pembersihan akhir

Location: Lokasi kerja:

Page 6 of 7
[Company header / Kop perusahaan]

BILL OF QUANTITY
PROJECT : SITE IMPROVEMENT OF ROHINGYA CAMP
ACTIVITY : REFURBISHMENT OF EXISTING TOILET (M/F)
LOCATION : MINA RAYA CAMP, ACEH PIDIE
DATE : 2023
* English language is official version
* Site visit must be conducted prior submitted the unit prices

No Description Deskripsi Unit Qty Unit Price Total Price

1. Male toilet 1. Toilet laki-laki


2. Male washing area 2. Area pemandian laki-laki
3. Female toilet 3. Toilet perempuan
4. Female washing area 4. Area pemandian perempuan
RECAPITULATION REKAPITULASI 78,000,000

A Preparation works Pekerjaan Persiapan 32,500,000


B Land Clearing and Excavation Pembersihan Area dan Galian 45,500,000
VAT 11% 7,800,000
TOTAL 85,800,000
IN AMOUNT / TERBILANG …………………………………………………………… Rupiah

Submitted by
PT / CV …...............................

......[Name & Signature]………


Director

Page 7 of 7