Name of Work : -
Soil Investigation Work at Sewage Project at Nasrullaganj M.P.
Location:- 4.2MLD STP & IPS Site, Under Sewage Project at Nasrullaganj
1 Introduction. 2
6 References. 8
10 Annexure 43-58
1
Name of Project:- Soil Investigation Work for Construction of 4.2MLD STP & IPS Site, Under Sewage Project at
Nasrullaganj.
1 INTRODUCTION :
M/s. Abeinsa Infraestructuras Medio Ambiente S. A. (Abeima) And M/s Bhugan
Infracon Pvt. Ltd. (JV) Mumbai. (MH) , have been awarded the Sewage Project at Nasrullaganj
M.P. M/s. Abeinsa Infraestructuras Medio Ambiente S. A. (Abeima) And M/s Bhugan Infracon
Pvt. Ltd. (JV) Mumbai has been appoint to M/S Beacon Infralab India Pvt. Ltd. to Undertake the
work of Geotechnical Investigation. The present report is about the results of one bore log
exploration at,
4.2 MLD STP at Nasrullaganj (07 No. Bore Log)
IPS at Nasrullaganj (01 No. Bore Log)
Scope of work for the present investigation includes boring at specified locations Excavation at
Site. During boring collection of disturbed/ undisturbed/ Core samples, carrying out field (SPT)
tests and laboratory tests on undisturbed, disturbed soil sample & core samples and submission
of report including recommendation for design of foundation for the proposed structure .The
geotechnical engineer and geologist of BILIPL have collected the soil samples from the
boreholes along with the other filed data. The location of drilling the boreholes was provided by
the officials of the client. The drilling, sample collections and Standard Penetration test was
performed in the presence of officials of the client.
2. Field Work
Boring:
Boring was done with the combination of rotary drilling technique. Flush joined steel casing
pipes were provided (when required) to prevent side collapse. The borehole depths & description
of Soil. N values from SPT and the depth at which ground water was encountered are shown in
table-1A to 5A of this report & test result of bore hole is shown in table-1B to 5B.
Sampling:
Undisturbed Samples, disturbed samples & core samples were collected at regular intervals. The
disturbed samples including penetrometer samples were collected and stored in polythene bags
after proper labeling. Undisturbed samples were collected in 100mm. diameter sample tubes. The
area ratio of each tube was kept within 14% to minimize possible disturbances during sampling
the tubes were scaled with paraffin wax at both ends, labeled depth wise and dispatched to the
laboratory for testing. The disturbed samples were collected from the cutting shoe of sample
tubes & split spoon sampler. Core samples were collected by core – catcher and stored in
polythene bags/core box after proper labeling.
2
Name of Project:- Soil Investigation Work for Construction of 4.2MLD STP & IPS Site, Under Sewage Project at
Nasrullaganj.
Standard penetration Test:-
Standard penetration tests were done within each borehole at suitable interval of depth shown in
the bore log data sheets. The tests were done with the standard split-spoon sampler as per IS:
2131. The N values were obtained by counting the number of blows required to drive the spoon
30cm in soil.
3. LABORATORY TESTS :
The soil samples were extracted from 100mm. diameter sampling tubes in the laboratory by
pushing out the soil core in the extractor frame with the help of a jack the core was jacked out in
a direction the corresponded to the soil movement within the tube during sampling. The
following test was carried out on soil samples collected from the boreholes:
a) Bulk Density
b) Natural Moisture Content.
c) Atterberg Limits
d) Specific Gravity.
e) Grain Size analysis.
f) Consolidation test.
g) Direct Shear Test.
h) Triaxial Test.
i) Swelling Pressure Test
For triaxial test 38mm. diameter x 76 mm. long specimens were obtained by jacking out
the soil. Core into the walled brass tubes, each having a wall thickness of 0.8 mm. The inside of
the tube was coated with a thin of silicon oil. To obtain specimens for consolidation test, the
odometer ring was placed on the trimmed horizontal face of the soil within the sampling tube and
the soil within the spatula as the ring was gently pushed into the soil the ring with the soil was
then removed by cutting across the soil core with help of a piano wire saw.
The laboratory tests as tabulated below were done to ascertain the engineering properties of the
subsoil and necessary data required for design of the foundation. In addition grain size
distribution & Atterberg Limits was carried out on samples collected from the shoe of SPT
sampler.
Atterberg limits and natural water content:
3
Name of Project:- Soil Investigation Work for Construction of 4.2MLD STP & IPS Site, Under Sewage Project at
Nasrullaganj.
Liquid limit. Plastic limit and natural water content of the silty clay/clayey silts. Samples were
determined (a) to classify the soil the M.I.T. classification system and (b) qualitatively asses their
constancy and compressibility of the soil samples.
Undrained triaxial test:
These tests were done on the silty clay /clayey silt samples to determine their undrained shear
strength. The cell pressure employed in the triaxial test was 0.5 1.0 and 1.5 kg/cm2. Then
samples were tested under quick condition at a rate of 1.25 mm/min.
Grain size analysis :
The grain-size distribution of some representative samples were determined from sieve analysis /
combined sieve and hydrometer analysis. The grain size distribution curve is shown in Fig.
Consolidation test:
Consolidation tests were run in floating ring type odometer. Under standard load increment.
Starting from 0.05 kg/cm2 to 8.0 kg/cm2 in general the soil samples were tested to represent in
relevant silty clay/clayey silt strata encountered.
Direct shear test :
These tests were done on the sandy soil to determine the angle of shearing resistance. The
normal stress uses employed in the test were 0.5. 1.0 &1.5 kg/cm2
Swelling Pressure Test
In case of soil having swilling properties swelling pressure test is conducted on the sample
collected from trial pits.
In case of rock is encountered at bore hole following tests were conducted on rock samples
collected from the site:
a) Specific Gravity
b) Water absorption
c) Crushing strength.
Core samples were collected from the rock strata. Diameter of the samples is 55mm. cylindrical
samples of length 110mm were prepared from these samples. Bulk density of these samples was
determined by taking weight of the cylindrical samples. Before determination of crushing
strength samples were saturated in water for 24 hours.
4. COMPUTATIONS OF SAFE BEARING CAPACITY
4
Name of Project:- Soil Investigation Work for Construction of 4.2MLD STP & IPS Site, Under Sewage Project at
Nasrullaganj.
(I) BASED ON SHEAR CONSIDERATION
The various kinds of shear tests are there but here we have performed the unconsolidated-
undrained (UU) tests were performed to get shear parameters for all samples. The Safe Bearing
Capacity is calculated as per IS: 6403- 1981 (determination of bearing capacity of shallow
foundations). For local and general shear failure the net safe bearing capacity is given as follows:
Qns = [C Nc Sc dc ic+q (Nq-1) Sq dq iq+ ½ B γ Nγ dγ iγ W]/F (In case of General shear
failure)
Qns = [2/3 C N’c Sc dc ic+q (N’q-1) Sq dq iq+ ½ B γ N’γ Sγdγ iγ W]/F (In case of local shear
failure)
Where qns = Net Safe Bearing Capacity
C = Cohesion (for Non cohesive material C = 0)
Ǿ = Angle of internal friction
Ǿ’ = tan-1(0.67 tan (Ø)) for local shear failure
γ = Average density of over burden
Nc,Nq,Nγ = Bearing Capacity factors for General Shear Failure
N’c,N’q,N’γ = Bearing Capacity factors for Local Shear Failure
Sc,Sq,Sγ = Shape factors
dc ,dq ,dγ = depth factors
ic ,iq ,iγ = inclination factors ( 1 in the case of vertical loads)
q = Effective surcharge at depth of” X” Mt below ground level.
W = Water Table correction factor is ½ (When WT is at base of footing)
B = Width of footing in Mts. (3.0x 3.0 m assumed)
F = Factor of safety considered as 2.50
The tests for determination of shear parameters are performed on undisturbed specimen.
The samplers were drawn in the boreholes and the undisturbed samples were collected wherever
possible and on these samples Triaxial Compression Tests were conducted.
5
Name of Project:- Soil Investigation Work for Construction of 4.2MLD STP & IPS Site, Under Sewage Project at
Nasrullaganj.
The elastic or immediate settlement:- According to Terzaghi (1943)
Si = qB ( 1-μ2)If/E
As per the clause 9.5 of IS 8009 part I, 1976 reaffirmed in 1998 the total settlement is to be
reduced for depth factor as found from Fig. 12 pp 22 of IS 8009 .
6
Name of Project:- Soil Investigation Work for Construction of 4.2MLD STP & IPS Site, Under Sewage Project at
Nasrullaganj.
5.0 CONCLUSION & RECOMMENDATION
7
Name of Project:- Soil Investigation Work for Construction of 4.2MLD STP & IPS Site, Under Sewage Project at
Nasrullaganj.
8
Name of Project:- Soil Investigation Work for Construction of 4.2MLD STP & IPS Site, Under Sewage Project at
Nasrullaganj.
AUTHORAISED SIGNATORY
CLOSURE:
We appreciate the opportunity given to us to submit this report. This presented report is based on
observations and tests on samples collected from the boreholes. In case any difference is
noticed in the field subsoil strata and reported subsoil strata during excavation of
foundation, please contact us before proceeding with further construction.
9
Name of Project:- Soil Investigation Work for Construction of 4.2MLD STP & IPS Site, Under Sewage Project at
Nasrullaganj.
REFERENCES
10
Name of Project:- Soil Investigation Work for Construction of 4.2MLD STP & IPS Site, Under Sewage Project at
Nasrullaganj.
9
Name of Project:- Soil Investigation Work for Construction of 4.2MLD STP & IPS Site, Under Sewage Project at
Nasrullaganj.
Designation (RQD) %
Dia of Bore / Casing
% Core Recovery
Drill Depth
Soil Classification
each 30cm in minutes
DESCRIPTION
Color of Returned
SAMPLES
(m)
Rock Quality
OF STRATA
Used (mm)
SPT ‘N’
Water
(Description of core
Value / rock type color grain
Remarks size texture mineral
From To Type Depth composition degree
of weathering)
0.5 1.5 SPT-1 1.0-1.45 3,4,4=8 150 55 Nil Nil ----------do--------- --do-- --do--
1.5 3.0 SPT-2 1.5-1.95 4,5,6=11 150 55 Nil Nil ----------do--------- --do-- --do--
Clayey Soil of
UDS-1 3.0-3.5 - 150 55 Nil Nil Intermediated CI Yellow
3.0 4.5 Plasticity
4.5 6.0 SPT-4 4.5-4.95 7,9,11=20 150 55 Nil Nil ----------do--------- --do-- --do--
6.0 7.5 SPT-5 6.0-6.45 8,10,13=23 150 55 Nil Nil ----------do--------- --do-- --do--
7.5 9.0 SPT-6 7.5-7.95 10,12,15=27 150 55 Nil Nil ----------do--------- --do-- --do--
9.0 10.0 SPT-7 9.0-9.45 12,14,16=30 150 55 Nil Nil ----------do--------- --do-- --do--
DS : Disturbed Sample
UDS : Undisturbed Sample
SPT : Standard Penetration Test
10
Name of Project:- Soil Investigation Work for Construction of 4.2MLD STP & IPS Site, Under Sewage Project at
Nasrullaganj.
11
Name of Project:- Soil Investigation Work for Construction of 4.2MLD STP & IPS Site, Under Sewage Project at
Nasrullaganj.
TABLE–1B, SOIL/ROCK TEST RESULTS FOR
BH -1 (4.2MLD STP at Ward No. 6, Miya Mohalla)
SHEARING
STRENGTH
Mechanical Analysis Consistency Limit
SPECIFIC GRAVITY
Bulk Density (g/cc)
Type of Sample
COMPRESSION
INDEX CC
ANGLE OF SHEARING
Depth
S. No
COHESON ‘C’
RESISTANCE
2
IN kg/cm
Gravel %
Sand%
P.L. %
Clay%
L.L %
P.I.%
1 DS-1 0.5 CH - - 0 5 Silt%
47 48 56 27 29 - - - -
2 SPT-2 1.5 CH - - 2 8 44 46 54 26 28 - - - -
0
3 UDS-1 3.0 CI 15 1.78 3 15 40 42 49 26 23 2.69 0.46 9 0.265
4 SPT-4 4.5 CI - - 10 33 28 29 42 22 20 - - - -
5 SPT-5 6.0 CI - - 12 37 24 27 41 21 20 - - - -
12
Name of Project:- Soil Investigation Work for Construction of 4.2MLD STP & IPS Site, Under Sewage Project at
Nasrullaganj.
13
Name of Project:- Soil Investigation Work for Construction of 4.2MLD STP & IPS Site, Under Sewage Project at
Nasrullaganj.
Designation (RQD) %
Dia of Bore / Casing
% Core Recovery
Drill Depth
Soil Classification
each 30cm in minutes
DESCRIPTION
Color of Returned
SAMPLES
(m)
Rock Quality
OF STRATA
Used (mm)
SPT ‘N’
Water
(Description of core
Value / rock type color grain
Remarks size texture mineral
From To Type Depth composition degree
of weathering)
0.5 1.5 SPT-1 1.0-1.45 3,3,4=7 150 55 Nil Nil ----------do--------- --do-- --do--
1.5 2.8 SPT-2 1.5-1.95 3,4,5=9 150 55 Nil Nil ----------do--------- --do-- --do--
Clayey Soil of
SPT-3 3.0-3.5 5,6,7=13 150 55 Nil Nil Intermediated CI Yellow
2.8 4.5 Plasticity
4.5 6.0 SPT-4 4.5-4.95 7,8,10=18 150 55 Nil Nil ----------do--------- --do-- --do--
6.0 7.5 SPT-5 6.0-6.45 8,9,12=21 150 55 Nil Nil ----------do--------- --do-- --do--
7.5 9.0 SPT-6 7.5-7.95 9,11,15=26 150 55 Nil Nil ----------do--------- --do-- --do--
9.0 10.0 SPT-7 9.0-9.45 11,13,15=28 150 55 Nil Nil ----------do--------- --do-- --do--
DS : Disturbed Sample
UDS : Undisturbed Sample
SPT : Standard Penetration Test
14
Name of Project:- Soil Investigation Work for Construction of 4.2MLD STP & IPS Site, Under Sewage Project at
Nasrullaganj.
15
Name of Project:- Soil Investigation Work for Construction of 4.2MLD STP & IPS Site, Under Sewage Project at
Nasrullaganj.
TABLE–2B, SOIL/ROCK TEST RESULTS FOR
BH -2 (4.2MLD STP at Ward No. 6, Miya Mohalla)
SHEARING
STRENGTH
Mechanical Analysis Consistency Limit
SPECIFIC GRAVITY
Bulk Density (g/cc)
Type of Sample
COMPRESSION
INDEX CC
ANGLE OF SHEARING
Depth
S. No
COHESON ‘C’
RESISTANCE
2
IN kg/cm
Gravel %
Sand%
P.L. %
Clay%
L.L %
P.I.%
1 DS-1 0.5 CH - - 2 9 Silt%
44 45 58 26 32 - - - -
2 SPT-2 1.5 CH - - 1 13 41 45 54 28 26 - - - -
0
3 UDS-1 3.0 CI 11 1.79 3 18 37 42 48 25 23 2.68 0.40 11 0.232
4 SPT-4 4.5 CI - - 1 23 36 40 49 25 24 - - - -
5 SPT-5 6.0 CI - - 2 31 33 34 46 24 22 - - - -
16
Name of Project:- Soil Investigation Work for Construction of 4.2MLD STP & IPS Site, Under Sewage Project at
Nasrullaganj.
17
Name of Project:- Soil Investigation Work for Construction of 4.2MLD STP & IPS Site, Under Sewage Project at
Nasrullaganj.
Designation (RQD) %
Dia of Bore / Casing
% Core Recovery
Drill Depth
Soil Classification
each 30cm in minutes
DESCRIPTION
Color of Returned
SAMPLES
(m)
Rock Quality
OF STRATA
Used (mm)
SPT ‘N’
Water
(Description of core
Value / rock type color grain
Remarks size texture mineral
From To Type Depth composition degree
of weathering)
0.5 1.5 SPT-1 1.0-1.45 3,4,4=8 150 55 Nil Nil ----------do--------- --do-- --do--
1.5 3.0 SPT-2 1.5-1.95 4,4,6=11 150 55 Nil Nil ----------do--------- --do-- --do--
Clayey Soil of
UDS-1 3.0-3.5 - 150 55 Nil Nil Intermediated CI Yellow
3.0 4.5 Plasticity
4.5 6.0 SPT-4 4.5-4.95 7,7,11=18 150 55 Nil Nil ----------do--------- --do-- --do--
6.0 7.5 SPT-5 6.0-6.45 8,10,12=22 150 55 Nil Nil ----------do--------- --do-- --do--
7.5 9.0 SPT-6 7.5-7.95 9,13,15=28 150 55 Nil Nil ----------do--------- --do-- --do--
9.0 10.0 SPT-7 9.0-9.45 10,14,16=30 150 55 Nil Nil ----------do--------- --do-- --do--
DS : Disturbed Sample
UDS : Undisturbed Sample
SPT : Standard Penetration Test
18
Name of Project:- Soil Investigation Work for Construction of 4.2MLD STP & IPS Site, Under Sewage Project at
Nasrullaganj.
19
Name of Project:- Soil Investigation Work for Construction of 4.2MLD STP & IPS Site, Under Sewage Project at
Nasrullaganj.
TABLE–3B, SOIL/ROCK TEST RESULTS FOR
BH-3 (4.2MLD STP at Ward No. 6, Miya Mohalla)
SHEARING
STRENGTH
Mechanical Analysis Consistency Limit
SPECIFIC GRAVITY
Bulk Density (g/cc)
Type of Sample
COMPRESSION
INDEX CC
ANGLE OF SHEARING
Depth
S. No
COHESON ‘C’
RESISTANCE
2
IN kg/cm
Gravel %
Sand%
P.L. %
Clay%
L.L %
P.I.%
1 DS-1 0.5 CH - - 1 9 Silt%
44 46 55 27 28 - - - -
2 SPT-2 1.5 CH - - 2 11 43 44 54 28 26 - - - -
0
3 UDS-1 3.0 CI 14 1.77 7 14 39 40 46 24 22 2.66 0.38 10 0.199
4 SPT-4 4.5 CI - - 2 22 36 40 44 23 21 - - - -
5 SPT-5 6.0 CI - - 3 26 38 33 42 22 20 - - - -
20
Name of Project:- Soil Investigation Work for Construction of 4.2MLD STP & IPS Site, Under Sewage Project at
Nasrullaganj.
21
Name of Project:- Soil Investigation Work for Construction of 4.2MLD STP & IPS Site, Under Sewage Project at
Nasrullaganj.
Designation (RQD) %
Dia of Bore / Casing
% Core Recovery
Drill Depth
Soil Classification
each 30cm in minutes
DESCRIPTION
Color of Returned
SAMPLES
(m)
Rock Quality
OF STRATA
Used (mm)
SPT ‘N’
Water
(Description of core
Value / rock type color grain
Remarks size texture mineral
From To Type Depth composition degree
of weathering)
0.5 1.5 SPT-1 1.0-1.45 3,4,5=9 150 55 Nil Nil ----------do--------- --do-- --do--
1.5 2.9 SPT-2 1.5-1.95 5,5,6=11 150 55 Nil Nil ----------do--------- --do-- --do--
Clayey Soil of
UDS-1 3.0-3.5 - 150 55 Nil Nil Intermediated CI Yellow
2.9 4.5 Plasticity
4.5 6.0 SPT-4 4.5-4.95 7,8,11=19 150 55 Nil Nil ----------do--------- --do-- --do--
6.0 7.5 SPT-5 6.0-6.45 8,11,13=24 150 55 Nil Nil ----------do--------- --do-- --do--
7.5 9.0 SPT-6 7.5-7.95 10,12,13=25 150 55 Nil Nil ----------do--------- --do-- --do--
9.0 10.0 SPT-7 9.0-9.45 12,14,15=29 150 55 Nil Nil ----------do--------- --do-- --do--
DS : Disturbed Sample
UDS : Undisturbed Sample
SPT : Standard Penetration Test
22
Name of Project:- Soil Investigation Work for Construction of 4.2MLD STP & IPS Site, Under Sewage Project at
Nasrullaganj.
23
Name of Project:- Soil Investigation Work for Construction of 4.2MLD STP & IPS Site, Under Sewage Project at
Nasrullaganj.
TABLE–4B, SOIL/ROCK TEST RESULTS FOR
BH-4 (4.2MLD STP at Ward No. 6, Miya Mohalla)
SHEARING
STRENGTH
Mechanical Analysis Consistency Limit
SPECIFIC GRAVITY
Bulk Density (g/cc)
Type of Sample
COMPRESSION
INDEX CC
ANGLE OF SHEARING
Depth
S. No
COHESON ‘C’
RESISTANCE
2
IN kg/cm
Gravel %
Sand%
P.L. %
Clay%
L.L %
P.I.%
Silt%
1 DS-1 0.5 CH - - 1 7 44 48 52 24 28 - - - -
2 SPT-2 1.5 CH - - 3 11 41 45 52 25 27 - - - -
0
3 UDS-1 3.0 CI 9 1.75 2 15 40 43 50 26 24 2.67 0.50 8 0.265
4 SPT-4 4.5 CI - - 1 23 36 40 46 26 20 - - - -
5 SPT-5 6.0 CI - - 2 28 33 37 42 23 19 - - - -
24
Name of Project:- Soil Investigation Work for Construction of 4.2MLD STP & IPS Site, Under Sewage Project at
Nasrullaganj.
25
Name of Project:- Soil Investigation Work for Construction of 4.2MLD STP & IPS Site, Under Sewage Project at
Nasrullaganj.
Designation (RQD) %
Dia of Bore / Casing
% Core Recovery
Drill Depth
Soil Classification
each 30cm in minutes
DESCRIPTION
Color of Returned
SAMPLES
(m)
Rock Quality
OF STRATA
Used (mm)
SPT ‘N’
Water
(Description of core
Value / rock type color grain
Remarks size texture mineral
From To Type Depth composition degree
of weathering)
0.5 1.5 SPT-1 1.0-1.45 3,4,4=8 150 55 Nil Nil ----------do--------- --do-- --do--
1.5 3.0 SPT-2 1.5-1.95 4,5,7=12 150 55 Nil Nil ----------do--------- --do-- --do--
Clayey Soil of
UDS-1 3.0-3.5 - 150 55 Nil Nil Intermediated CI Yellow
3.0 4.5 Plasticity
4.5 6.0 SPT-4 4.5-4.95 8,9,11=20 150 55 Nil Nil ----------do--------- --do-- --do--
6.0 7.5 SPT-5 6.0-6.45 9,12,14=26 150 55 Nil Nil ----------do--------- --do-- --do--
7.5 9.0 SPT-6 7.5-7.95 10,13,17=30 150 55 Nil Nil ----------do--------- --do-- --do--
9.0 10.0 SPT-7 9.0-9.45 12,15,19=34 150 55 Nil Nil ----------do--------- --do-- --do--
DS : Disturbed Sample
UDS : Undisturbed Sample
SPT : Standard Penetration Test
26
Name of Project:- Soil Investigation Work for Construction of 4.2MLD STP & IPS Site, Under Sewage Project at
Nasrullaganj.
27
Name of Project:- Soil Investigation Work for Construction of 4.2MLD STP & IPS Site, Under Sewage Project at
Nasrullaganj.
TABLE–5B, SOIL/ROCK TEST RESULTS FOR
BH -5 (4.2MLD STP at Ward No. 6, Miya Mohalla)
SHEARING
STRENGTH
Mechanical Analysis Consistency Limit
SPECIFIC GRAVITY
Bulk Density (g/cc)
Type of Sample
COMPRESSION
INDEX CC
ANGLE OF SHEARING
Depth
S. No
COHESON ‘C’
RESISTANCE
2
IN kg/cm
Gravel %
Sand%
P.L. %
Clay%
L.L %
P.I.%
Silt%
1 DS-1 0.5 CH - - 2 10 42 46 56 27 29 - - - -
2 SPT-2 1.5 CH - - 1 12 43 44 54 26 28 - - - -
0
3 UDS-1 3.0 CI 13 1.80 4 23 43 30 42 22 22 2.68 0.42 13 0.199
4 SPT-4 4.5 CI - - 6 26 36 32 42 22 22 - - - -
5 SPT-5 6.0 CI - - 5 33 32 30 40 22 20 - - - -
28
Name of Project:- Soil Investigation Work for Construction of 4.2MLD STP & IPS Site, Under Sewage Project at
Nasrullaganj.
29
Name of Project:- Soil Investigation Work for Construction of 4.2MLD STP & IPS Site, Under Sewage Project at
Nasrullaganj.
Designation (RQD) %
Dia of Bore / Casing
% Core Recovery
Drill Depth
Soil Classification
each 30cm in minutes
DESCRIPTION
Color of Returned
SAMPLES
(m)
Rock Quality
OF STRATA
Used (mm)
SPT ‘N’
Water
(Description of core
Value / rock type color grain
Remarks size texture mineral
From To Type Depth composition degree
of weathering)
0.5 1.5 SPT-1 1.0-1.45 3,4,5=9 150 55 Nil Nil ----------do--------- --do-- --do--
1.5 2.8 SPT-2 1.5-1.95 5,5,6=11 150 55 Nil Nil ----------do--------- --do-- --do--
Clayey Soil of
UDS-1 3.0-3.5 - 150 55 Nil Nil Intermediated CI Yellow
2.8 4.5 Plasticity
4.5 6.0 SPT-4 4.5-4.95 7,8,11=19 150 55 Nil Nil ----------do--------- --do-- --do--
6.0 7.5 SPT-5 6.0-6.45 8,11,13=24 150 55 Nil Nil ----------do--------- --do-- --do--
7.5 9.0 SPT-6 7.5-7.95 10,12,16=28 150 55 Nil Nil ----------do--------- --do-- --do--
9.0 10.0 SPT-7 9.0-9.45 12,14,17=31 150 55 Nil Nil ----------do--------- --do-- --do--
DS : Disturbed Sample
UDS : Undisturbed Sample
SPT : Standard Penetration Test
30
Name of Project:- Soil Investigation Work for Construction of 4.2MLD STP & IPS Site, Under Sewage Project at
Nasrullaganj.
31
Name of Project:- Soil Investigation Work for Construction of 4.2MLD STP & IPS Site, Under Sewage Project at
Nasrullaganj.
TABLE–6B, SOIL/ROCK TEST RESULTS FOR
BH -6 (4.2MLD STP at Ward No. 6, Miya Mohalla)
SHEARING
STRENGTH
Mechanical Analysis Consistency Limit
SPECIFIC GRAVITY
Bulk Density (g/cc)
Type of Sample
COMPRESSION
INDEX CC
ANGLE OF SHEARING
Depth
S. No
COHESON ‘C’
RESISTANCE
2
IN kg/cm
Gravel %
Sand%
P.L. %
Clay%
L.L %
P.I.%
1 DS-1 0.5 CH - - 3 6 Silt%
45 46 53 26 27 - - - -
2 SPT-2 1.5 CH - - 2 9 44 45 51 26 25 - - - -
0
3 UDS-1 2.0 CH 11 1.78 4 15 38 43 50 26 24 2.66 0.44 12 0.232
4 SPT-4 4.5 CI - - 3 24 36 37 43 22 21 - - - -
5 SPT-5 6.0 CI - - 2 29 34 35 42 22 20 - - - -
32
Name of Project:- Soil Investigation Work for Construction of 4.2MLD STP & IPS Site, Under Sewage Project at
Nasrullaganj.
33
Name of Project:- Soil Investigation Work for Construction of 4.2MLD STP & IPS Site, Under Sewage Project at
Nasrullaganj.
Designation (RQD) %
Dia of Bore / Casing
% Core Recovery
Drill Depth
Soil Classification
each 30cm in minutes
DESCRIPTION
Color of Returned
SAMPLES
(m)
Rock Quality
OF STRATA
Used (mm)
SPT ‘N’
Water
(Description of core
Value / rock type color grain
Remarks size texture mineral
From To Type Depth composition degree
of weathering)
0.5 1.5 SPT-1 1.0-1.45 4,4,6=10 150 55 Nil Nil ----------do--------- --do-- --do--
Clayey Soil of
3.0 4.5 SPT-3 3.0-3.45 7,7,9=16 150 55 Nil Nil Intermediated CI Yellow
Plasticity
4.5 6.0 SPT-4 4.5-4.95 8,10,11=21 150 55 Nil Nil ----------do--------- --do-- --do--
6.0 7.5 SPT-5 6.0-6.45 9,11,14=25 150 55 Nil Nil ----------do--------- --do-- --do--
7.5 9.0 SPT-6 7.5-7.95 10,12,16=28 150 55 Nil Nil ----------do--------- --do-- --do--
9.0 10.0 SPT-7 9.0-9.45 11,13,17=30 150 55 Nil Nil ----------do--------- --do-- --do--
DS : Disturbed Sample
UDS : Undisturbed Sample
SPT : Standard Penetration Test
34
Name of Project:- Soil Investigation Work for Construction of 4.2MLD STP & IPS Site, Under Sewage Project at
Nasrullaganj.
35
Name of Project:- Soil Investigation Work for Construction of 4.2MLD STP & IPS Site, Under Sewage Project at
Nasrullaganj.
TABLE–7B, SOIL/ROCK TEST RESULTS FOR
BH -7 (4.2MLD STP at Ward No. 6, Miya Mohalla)
SHEARING
STRENGTH
Mechanical Analysis Consistency Limit
SPECIFIC GRAVITY
Bulk Density (g/cc)
Type of Sample
COMPRESSION
INDEX CC
ANGLE OF SHEARING
Depth
S. No
COHESON ‘C’
RESISTANCE
2
IN kg/cm
Gravel %
Sand%
P.L. %
Clay%
L.L %
P.I.%
Silt%
1 DS-1 0.5 CH - - 2 6 45 47 53 25 28 - - - -
2 SPT-2 1.5 CH - - 1 9 44 46 53 26 27 - - - -
0
3 UDS-1 2.0 CH 9 1.75 5 12 41 42 52 27 25 2.66 0.37 9 0.221
4 SPT-3 3.0 CI - - 0 30 34 36 42 24 18 - - - -
5 SPT-4 4.5 CI - - 2 44 26 28 37 23 14 - - - -
36
Name of Project:- Soil Investigation Work for Construction of 4.2MLD STP & IPS Site, Under Sewage Project at
Nasrullaganj.
37
Name of Project:- Soil Investigation Work for Construction of 4.2MLD STP & IPS Site, Under Sewage Project at
Nasrullaganj.
38
Name of Project:- Soil Investigation Work for Construction of 4.2MLD STP & IPS Site, Under Sewage Project at
Nasrullaganj.
Designation (RQD) %
Dia of Bore / Casing
% Core Recovery
Drill Depth
Soil Classification
each 30cm in minutes
DESCRIPTION
Color of Returned
SAMPLES
(m)
Rock Quality
OF STRATA
Used (mm)
SPT ‘N’
Water
(Description of core
Value / rock type color grain
Remarks size texture mineral
From To Type Depth composition degree
of weathering)
0.5 1.5 SPT-1 1.0-1.45 3,4,4=8 150 55 Nil Nil ----------do--------- --do-- --do--
1.5 3.0 SPT-2 1.5-1.95 4,5,6=11 150 55 Nil Nil ----------do--------- --do-- --do--
Clayey Soil of
UDS-1 3.0-3.5 - 150 55 Nil Nil Intermediated CI Yellow
3.0 4.5 Plasticity
4.5 6.0 SPT-4 4.5-4.95 7,9,11=20 150 55 Nil Nil ----------do--------- --do-- --do--
6.0 7.5 SPT-5 6.0-6.45 8,10,13=23 150 55 Nil Nil ----------do--------- --do-- --do--
7.5 9.0 SPT-6 7.5-7.95 10,12,15=27 150 55 Nil Nil ----------do--------- --do-- --do--
9.0 10.0 SPT-7 9.0-9.45 12,14,16=30 150 55 Nil Nil ----------do--------- --do-- --do--
DS : Disturbed Sample
UDS : Undisturbed Sample
SPT : Standard Penetration Test
39
Name of Project:- Soil Investigation Work for Construction of 4.2MLD STP & IPS Site, Under Sewage Project at
Nasrullaganj.
40
Name of Project:- Soil Investigation Work for Construction of 4.2MLD STP & IPS Site, Under Sewage Project at
Nasrullaganj.
TABLE–1B, SOIL/ROCK TEST RESULTS FOR
BH -1 (Inter Pump Station at Ward)
SHEARING
STRENGTH
Mechanical Analysis Consistency Limit
SPECIFIC GRAVITY
Bulk Density (g/cc)
Type of Sample
COMPRESSION
INDEX CC
ANGLE OF SHEARING
Depth
S. No
COHESON ‘C’
RESISTANCE
2
IN kg/cm
Gravel %
Sand%
P.L. %
Clay%
L.L %
P.I.%
1 DS-1 0.5 CH - - 2 7 Silt%
45 46 57 27 30 - - - -
2 SPT-2 1.5 CH - - 1 10 44 45 55 27 28 - - - -
0
3 UDS-1 3.0 CI 9 1.79 2 22 41 35 47 24 23 2.65 0.45 12 0.199
4 SPT-4 4.5 CI - - 6 24 37 33 39 23 16 - - - -
5 SPT-5 6.0 CI - - 8 20 38 34 36 21 15 - - - -
41
Name of Project:- Soil Investigation Work for Construction of 4.2MLD STP & IPS Site, Under Sewage Project at
Nasrullaganj.
42
Annexure-1
BC3=0.5.Y.B.NY.dY.SY.IY.W’
Length of footing in m
BC2=Y.D(Nq-1)dq.iq.sq
BC1=2/3C.NC.dc.sc.ic
Cohesion ‘c’ Kn /m2
BC=BC1+BC2+BC3
resistance degree
Angle of shearing
Bearing capacity
Bearing capacity
Bearing capacity
BC/FOS
Bearing capacity
S. No
1 3.0 3.0 3.0 17.8 46.0 9 6.81 1.72 0.57 1.22 1.00 1.00 1.3 1.2 0.8 331 20.2 6.1 357 143
2 4.0 3.0 3.0 17.8 46.0 9 6.81 1.72 0.57 1.30 1.00 1.00 1.3 1.2 0.8 353 27.0 6.1 386 154
3 5.0 3.0 3.0 17.8 46.0 9 6.81 1.72 0.57 1.37 1.00 1.00 1.3 1.2 0.8 372 33.7 6.1 412 165
4 6.0 3.0 3.0 17.8 46.0 9 6.81 1.72 0.57 1.44 1.00 1.00 1.3 1.2 0.8 391 40.4 6.1 438 175
∆p= R= 1.693
Page-43
Depth-3.0m to 6.0 Assuming same strata after 6.0m to effected Loaded Area depth
Z H0 po Cc x H0 p0+∆p Consolidation
Depth y Cc ∆p (kPa) e0 Sc = x Log10
(M) (M) (kPa) 1+e0 p0 Settlement mm
3.00 17.8 0.265 3.00 6.00 14.40 106.80 0.74 0.0502 50.20
4.00 17.8 0.265 3.00 6.00 16.80 124.60 0.74 0.0502 50.20
5.00 17.8 0.265 3.00 6.00 19.20 142.40 0.74 0.0502 50.20
6.00 17.8 0.265 3.00 6.00 20.40 160.20 0.74 0.0476 47.60
TOTAL SETTLEMENT
S. No Depth (M) Immediate Consolidation Total Depth Corrected Permissible
settlement (mm) Settlement Settlement Factor Settlement Settlement As
(mm) (mm) (mm) per IS 1904-1986
1 3.00 34.20 50.20 84.40 0.725 61.19 75mm
2 4.00 39.90 50.20 90.10 0.725 65.32 75mm
3 5.00 45.60 50.20 95.80 0.725 69.46 75mm
4 6.00 48.45 47.60 96.05 0.725 69.64 75mm
Page-44
Annexure-2
BC3=0.5.Y.B.NY.dY.SY.IY.W’
Length of footing in m
BC2=Y.D(Nq-1)dq.iq.sq
BC1=2/3C.NC.dc.sc.ic
Cohesion ‘c’ Kn /m2
BC=BC1+BC2+BC3
resistance degree
Angle of shearing
Bearing capacity
Bearing capacity
Bearing capacity
BC/FOS
Bearing capacity
S. No
1 3.0 3.0 3.0 17.9 40.0 11 7.16 1.88 0.71 1.23 1.00 1.00 1.3 1.2 0.8 305 25.0 7.6 338 135
2 4.0 3.0 3.0 17.9 40.0 11 7.16 1.88 0.71 1.30 1.00 1.00 1.3 1.2 0.8 323 33.4 7.6 364 146
3 5.0 3.0 3.0 17.9 40.0 11 7.16 1.88 0.71 1.38 1.00 1.00 1.3 1.2 0.8 343 41.7 7.6 392 157
4 6.0 3.0 3.0 17.9 40.0 11 7.16 1.88 0.71 1.45 1.00 1.00 1.3 1.2 0.8 360 50.1 7.6 418 167
∆p= R= 1.693
Page-45
Depth-3.0m to 6.0 Assuming same strata after 6.0m to effected Loaded Area depth
Z H0 po Cc x H0 p0+∆p Consolidation
Depth y Cc ∆p (kPa) e0 Sc = x Log10
(M) (M) (kPa) 1+e0 p0 Settlement mm
3.00 17.9 0.232 3.00 6.00 13.20 107.40 0.66 0.0422 42.20
4.00 17.9 0.232 3.00 6.00 15.60 125.30 0.66 0.0427 42.70
5.00 17.9 0.232 3.00 6.00 18.00 143.20 0.66 0.0431 43.10
6.00 17.9 0.232 3.00 6.00 21.60 161.10 0.66 0.0458 45.80
TOTAL SETTLEMENT
S. No Depth (M) Immediate Consolidation Total Depth Corrected Permissible
settlement (mm) Settlement Settlement Factor Settlement Settlement As
(mm) (mm) (mm) per IS 1904-1986
1 3.00 31.35 42.20 73.55 0.725 53.32 75mm
2 4.00 37.05 42.70 79.75 0.725 57.82 75mm
3 5.00 42.75 43.10 85.85 0.725 62.24 75mm
4 6.00 51.30 45.80 97.10 0.725 70.40 75mm
Page-46
Annexure-3
Location BH-3
SBC CALCULATION BASED ON SHEAR CRIETERIA
(As per IS 6403: 1981)
Water table correction
Type of Shear Failure- Local Shear Failure Type of foundation –Open, Squire F.O.S-2.5
factor = 0.5
SBC= 2/3 cN'c scdcic+q(N'q-1) sqdqiq+1/2 BY N'Y sydyiy W'
BC3=0.5.Y.B.NY.dY.SY.IY.W’
Length of footing in m
BC2=Y.D(Nq-1)dq.iq.sq
BC1=2/3C.NC.dc.sc.ic
Cohesion ‘c’ Kn /m2
BC=BC1+BC2+BC3
resistance degree
Angle of shearing
Bearing capacity
Bearing capacity
Bearing capacity
BC/FOS
Bearing capacity
S. No
1 3.0 3.0 3.0 17.7 38.0 10 7.16 1.88 0.71 1.23 1.00 1.00 1.3 1.2 0.8 290 24.4 7.5 322 129
2 4.0 3.0 3.0 17.7 38.0 10 7.16 1.88 0.71 1.30 1.00 1.00 1.3 1.2 0.8 307 32.5 7.5 347 139
3 5.0 3.0 3.0 17.7 38.0 10 7.16 1.88 0.71 1.38 1.00 1.00 1.3 1.2 0.8 325 40.7 7.5 373 149
4 6.0 3.0 3.0 17.7 38.0 10 7.16 1.88 0.71 1.45 1.00 1.00 1.3 1.2 0.8 342 48.8 7.5 398 159
∆p= R= 1.693
Page-47
Depth-3.0m to 6.0 Assuming same strata after 6.0m to effected Loaded Area depth
Z H0 po Cc x H0 p0+∆p Consolidation
Depth y Cc ∆p (kPa) e0 Sc = x Log10
(M) (M) (kPa) 1+e0 p0 Settlement mm
3.00 17.7 0.199 3.00 6.00 14.40 106.20 0.72 0.0383 38.30
4.00 17.7 0.199 3.00 6.00 16.80 123.90 0.72 0.0383 38.30
5.00 17.7 0.199 3.00 6.00 19.20 141.60 0.72 0.0383 38.30
6.00 17.7 0.199 3.00 6.00 22.80 159.30 0.72 0.0403 40.30
TOTAL SETTLEMENT
S. No Depth (M) Immediate Consolidation Total Depth Corrected Permissible
settlement (mm) Settlement Settlement Factor Settlement Settlement As
(mm) (mm) (mm) per IS 1904-1986
1 3.00 34.20 38.30 72.50 0.725 52.56 75mm
2 4.00 39.90 38.30 78.20 0.725 56.70 75mm
3 5.00 45.60 38.30 83.90 0.725 60.83 75mm
4 6.00 54.15 40.30 94.45 0.725 68.48 75mm
Page-48
Annexure-4
BC3=0.5.Y.B.NY.dY.SY.IY.W’
Length of footing in m
BC2=Y.D(Nq-1)dq.iq.sq
BC1=2/3C.NC.dc.sc.ic
Cohesion ‘c’ Kn /m2
BC=BC1+BC2+BC3
resistance degree
Angle of shearing
Bearing capacity
Bearing capacity
Bearing capacity
BC/FOS
Bearing capacity
S. No
1 3.0 3.0 3.0 17.5 50.0 8 6.49 1.57 0.45 1.22 1.00 1.00 1.3 1.2 0.8 343 15.4 4.7 363 145
2 4.0 3.0 3.0 17.5 50.0 8 6.49 1.57 0.45 1.29 1.00 1.00 1.3 1.2 0.8 363 20.5 4.7 388 155
3 5.0 3.0 3.0 17.5 50.0 8 6.49 1.57 0.45 1.36 1.00 1.00 1.3 1.2 0.8 382 25.7 4.7 412 165
4 6.0 3.0 3.0 17.5 50.0 8 6.49 1.57 0.45 1.44 1.00 1.00 1.3 1.2 0.8 405 30.8 4.7 441 176
∆p= R= 1.693
Page-49
Depth-3.0m to 6.0 Assuming same strata after 6.0m to effected Loaded Area depth
Z H0 po Cc x H0 p0+∆p Consolidation
Depth y Cc ∆p (kPa) e0 Sc = x Log10
(M) (M) (kPa) 1+e0 p0 Settlement mm
3.00 17.5 0.265 3.00 6.00 13.20 105.00 0.66 0.0493 49.30
4.00 17.5 0.265 3.00 6.00 15.60 122.50 0.66 0.0499 49.90
5.00 17.5 0.265 3.00 6.00 18.00 140.00 0.66 0.0503 50.30
6.00 17.5 0.265 3.00 6.00 20.40 157.50 0.66 0.0507 50.70
TOTAL SETTLEMENT
S. No Depth (M) Immediate Consolidation Total Depth Corrected Permissible
settlement (mm) Settlement Settlement Factor Settlement Settlement As
(mm) (mm) (mm) per IS 1904-1986
1 3.00 31.35 49.30 80.65 0.725 58.47 75mm
2 4.00 37.05 49.90 86.95 0.725 63.04 75mm
3 5.00 42.75 50.30 93.05 0.725 67.46 75mm
4 6.00 48.45 50.70 99.15 0.725 71.88 75mm
Page-50
Annexure-5
BC3=0.5.Y.B.NY.dY.SY.IY.W’
Length of footing in m
BC2=Y.D(Nq-1)dq.iq.sq
BC1=2/3C.NC.dc.sc.ic
Cohesion ‘c’ Kn /m2
BC=BC1+BC2+BC3
resistance degree
Angle of shearing
Bearing capacity
Bearing capacity
Bearing capacity
BC/FOS
Bearing capacity
S. No
1 3.0 3.0 3.0 18 42.0 13 7.53 2.06 0.86 1.23 1.00 1.00 1.3 1.2 0.8 337 30.5 9.3 377 151
2 4.0 3.0 3.0 18 42.0 13 7.53 2.06 0.86 1.31 1.00 1.00 1.3 1.2 0.8 359 40.7 9.3 409 164
3 5.0 3.0 3.0 18 42.0 13 7.53 2.06 0.86 1.38 1.00 1.00 1.3 1.2 0.8 378 50.9 9.3 438 175
4 6.0 3.0 3.0 18 42.0 13 7.53 2.06 0.86 1.46 1.00 1.00 1.3 1.2 0.8 400 61.1 9.3 470 188
∆p= R= 1.693
Page-51
Depth-3.0m to 6.0 Assuming same strata after 6.0m to effected Loaded Area depth
Z H0 po Cc x H0 p0+∆p Consolidation
Depth y Cc ∆p (kPa) e0 Sc = x Log10
(M) (M) (kPa) 1+e0 p0 Settlement mm
3.00 18.0 0.199 3.00 6.00 14.40 108.00 0.70 0.0382 38.20
4.00 18.0 0.199 3.00 6.00 16.80 126.00 0.70 0.0382 38.20
5.00 18.0 0.199 3.00 6.00 19.20 144.00 0.70 0.0382 38.20
6.00 18.0 0.199 3.00 6.00 21.60 162.00 0.70 0.0382 38.20
TOTAL SETTLEMENT
S. No Depth (M) Immediate Consolidation Total Depth Corrected Permissible
settlement (mm) Settlement Settlement Factor Settlement Settlement As
(mm) (mm) (mm) per IS 1904-1986
1 3.00 34.20 38.20 72.40 0.725 52.49 75mm
2 4.00 39.90 38.20 78.10 0.725 56.62 75mm
3 5.00 45.60 38.20 83.80 0.725 60.76 75mm
4 6.00 51.30 38.20 89.50 0.725 64.89 75mm
Page-52
Annexure-6
BC3=0.5.Y.B.NY.dY.SY.IY.W’
Length of footing in m
BC2=Y.D(Nq-1)dq.iq.sq
BC1=2/3C.NC.dc.sc.ic
Cohesion ‘c’ Kn /m2
BC=BC1+BC2+BC3
resistance degree
Angle of shearing
Bearing capacity
Bearing capacity
Bearing capacity
BC/FOS
Bearing capacity
S. No
1 3.0 3.0 3.0 17.8 44.0 12 7.53 2.06 0.86 1.23 1.00 1.00 1.3 1.2 0.8 353 29.8 9.2 392 157
2 4.0 3.0 3.0 17.8 44.0 12 7.53 2.06 0.86 1.31 1.00 1.00 1.3 1.2 0.8 376 39.7 9.2 425 170
3 5.0 3.0 3.0 17.8 44.0 12 7.53 2.06 0.86 1.38 1.00 1.00 1.3 1.2 0.8 396 49.6 9.2 455 182
4 6.0 3.0 3.0 17.8 44.0 12 7.53 2.06 0.86 1.46 1.00 1.00 1.3 1.2 0.8 419 59.5 9.2 488 195
∆p= R= 1.693
Page-53
Depth-3.0m to 6.0 Assuming same strata after 6.0m to effected Loaded Area depth
Z H0 po Cc x H0 p0+∆p Consolidation
Depth y Cc ∆p (kPa) e0 Sc = x Log10
(M) (M) (kPa) 1+e0 p0 Settlement mm
3.00 17.8 0.232 3.00 6.00 14.40 106.80 0.70 0.0450 45.00
4.00 17.8 0.232 3.00 6.00 16.80 124.60 0.70 0.0450 45.00
5.00 17.8 0.232 3.00 6.00 19.20 142.40 0.70 0.0450 45.00
6.00 17.8 0.232 3.00 6.00 21.60 160.20 0.70 0.0450 45.00
TOTAL SETTLEMENT
S. No Depth (M) Immediate Consolidation Total Depth Corrected Permissible
settlement (mm) Settlement Settlement Factor Settlement Settlement As
(mm) (mm) (mm) per IS 1904-1986
1 3.00 34.20 45.00 79.20 0.725 57.42 75mm
2 4.00 39.90 45.00 84.90 0.725 61.55 75mm
3 5.00 45.60 45.00 90.60 0.725 65.69 75mm
4 6.00 51.30 45.00 96.30 0.725 69.82 75mm
Page-54
Annexure-7
BC3=0.5.Y.B.NY.dY.SY.IY.W’
Length of footing in m
BC2=Y.D(Nq-1)dq.iq.sq
BC1=2/3C.NC.dc.sc.ic
Cohesion ‘c’ Kn /m2
BC=BC1+BC2+BC3
resistance degree
Angle of shearing
Bearing capacity
Bearing capacity
Bearing capacity
BC/FOS
Bearing capacity
S. No
1 3.0 3.0 3.0 17.5 50.0 8 6.49 1.57 0.45 1.22 1.00 1.00 1.3 1.2 0.8 343 15.4 4.7 363 145
2 4.0 3.0 3.0 17.5 50.0 8 6.49 1.57 0.45 1.29 1.00 1.00 1.3 1.2 0.8 363 20.5 4.7 388 155
3 5.0 3.0 3.0 17.5 50.0 8 6.49 1.57 0.45 1.36 1.00 1.00 1.3 1.2 0.8 382 25.7 4.7 412 165
4 6.0 3.0 3.0 17.5 50.0 8 6.49 1.57 0.45 1.44 1.00 1.00 1.3 1.2 0.8 405 30.8 4.7 441 176
∆p= R= 1.693
Page-55
Depth-3.0m to 6.0 Assuming same strata after 6.0m to effected Loaded Area depth
Z H0 po Cc x H0 p0+∆p Consolidation
Depth y Cc ∆p (kPa) e0 Sc = x Log10
(M) (M) (kPa) 1+e0 p0 Settlement mm
3.00 17.5 0.265 3.00 6.00 13.20 105.00 0.66 0.0493 49.30
4.00 17.5 0.265 3.00 6.00 15.60 122.50 0.66 0.0499 49.90
5.00 17.5 0.265 3.00 6.00 18.00 140.00 0.66 0.0503 50.30
6.00 17.5 0.265 3.00 6.00 20.40 157.50 0.66 0.0507 50.70
TOTAL SETTLEMENT
S. No Depth (M) Immediate Consolidation Total Depth Corrected Permissible
settlement (mm) Settlement Settlement Factor Settlement Settlement As
(mm) (mm) (mm) per IS 1904-1986
1 3.00 31.35 49.30 80.65 0.725 58.47 75mm
2 4.00 37.05 49.90 86.95 0.725 63.04 75mm
3 5.00 42.75 50.30 93.05 0.725 67.46 75mm
4 6.00 48.45 50.70 99.15 0.725 71.88 75mm
Page-56
Annexure-8
BC3=0.5.Y.B.NY.dY.SY.IY.W’
Length of footing in m
BC2=Y.D(Nq-1)dq.iq.sq
BC1=2/3C.NC.dc.sc.ic
Cohesion ‘c’ Kn /m2
BC=BC1+BC2+BC3
resistance degree
Angle of shearing
Bearing capacity
Bearing capacity
Bearing capacity
BC/FOS
Bearing capacity
S. No
1 3.0 3.0 3.0 17.9 45.0 12 7.53 2.06 0.86 1.23 1.00 1.00 1.3 1.2 0.8 361 30.1 9.2 400 160
2 4.0 3.0 3.0 17.9 45.0 12 7.53 2.06 0.86 1.31 1.00 1.00 1.3 1.2 0.8 385 40.2 9.2 434 174
3 5.0 3.0 3.0 17.9 45.0 12 7.53 2.06 0.86 1.38 1.00 1.00 1.3 1.2 0.8 405 50.2 9.2 464 186
4 6.0 3.0 3.0 17.9 45.0 12 7.53 2.06 0.86 1.46 1.00 1.00 1.3 1.2 0.8 429 60.3 9.2 499 200
∆p= R= 1.693
Page-57
Depth-3.0m to 6.0 Assuming same strata after 6.0m to effected Loaded Area depth
Z H0 po Cc x H0 p0+∆p Consolidation
Depth y Cc ∆p (kPa) e0 Sc = x Log10
(M) (M) (kPa) 1+e0 p0 Settlement mm
3.00 17.9 0.199 3.00 6.00 14.40 107.40 0.70 0.0384 38.40
4.00 17.9 0.199 3.00 6.00 16.80 125.30 0.70 0.0384 38.40
5.00 17.9 0.199 3.00 6.00 19.20 143.20 0.70 0.0384 38.40
6.00 17.9 0.199 3.00 6.00 21.60 161.10 0.70 0.0384 38.40
TOTAL SETTLEMENT
S. No Depth (M) Immediate Consolidation Total Depth Corrected Permissible
settlement (mm) Settlement Settlement Factor Settlement Settlement As
(mm) (mm) (mm) per IS 1904-1986
1 3.00 34.20 38.40 72.60 0.725 52.64 75mm
2 4.00 39.90 38.40 78.30 0.725 56.77 75mm
3 5.00 45.60 38.40 84.00 0.725 60.90 75mm
4 6.00 51.30 38.40 89.70 0.725 65.03 75mm
Page-58
Live Photo at Site
Sewage Treatment Plant
59
Live Photo at Site
60
Live Photo at Site
61
Live Photo at Site
62
Live Photo at Site
Inter Pumping Station
63