5 6 7 8 9 LOCATION PLAN
UG Ramp
KAPODRA
LABHESHWARCHOWK
CENTRALWAREHOUSE
SURATRAILWAYSTATION
ISSUED FOR
AS BUILT DRAWING DEFINITIVE DESIGN
GOOD FOR CONSTRUCTION - WD PRELIMINARY DESIGN
PLINTH / TERRACE / ROOF /
NUMBER CONSTRUCTION REFERENCE DRAWING FOR REFERENCE / DISCUSSION
GROUND WATER TANK MUMTY
EL. 19.49
1 1 EL. 15.48 REFERENCE DESIGN DOCUMENT WITH REVISION NO. & DATE :-
C11 C21
10
2 2
LEGENDS : ABBREVIATIONS
NUMBER BASEMENT GROUND TO ABOVE
TO GROUND TERRACE TERRACE
CORNER COLUMNS
EDGE COLUMNS
NOTES :-
INTERIOR COLUMNS
C8 C3 C4
AC STUB COLUMNS
C12 C20 PLUNGE COLUMNS
REVISION CONTROL
3 3 KPS-A-P5
[Formerly known as Metro-Link Express for Gandhinagar And Ahmedabad (MEGA) Company Limited]
KPS-A-P14
THE DESIGN & DRAWING AS CERTIFIED BELOW AND SUBMITTED BY THE CONTRACTOR HAVE BEEN PROOF CHECKED BY
GENERAL ENGINEERING CONSULTANT ON BEHALF OF MEGA AND IS RECOMMENDED TO MEGA FOR REFERENCE OF :
S12
C.ARCH/SR.ARCH/(UG) CPM(CIVIL & SYSTEM/UG) DY.PD(CIVIL & TRACK) DY.PD(SYSTEM) PROJECT DIRECTOR
A1 A2 A3 A4 A5 A6 A7
5 6 7 8 9 INTERFACE MANAGER
CHECKED BY
ARCHITECT
CHECKED BY
STRUCTURE ENGINEER
REVIEWED BY
DY PROJECT MANGER
APPROVED BY
PROJECT MANAGER
ISSUED BY
INDEPENDENT LEAD
IT IS CERTIFIED THAT DETAILED DRAWING PREPARED BY "DDC" HAS BEEN INDEPENDENTLY ANALYZED & DESIGNED FOR CHECKING BY
"I-LDC" & IT IS COMPLIED WITH THE TERM & CONDITIONS OF CONTRACT REQUIREMENTS AND I-LDC OWNS FULL RESPONSIBILITY FOR
ACCURACY OF DESIGN AS PER ODS & OCS, ADEQUACY & MEETING FUNCTIONAL, PERFORMANCE AND OPERATIONAL REQUIREMENTS
NOTES :- INCLUDING CONSIDERATION FOR INTERFACE REQUIREMENTS WITH OTHER CONCERNED DESIGNERS & CONTRACTORS AND COMPLIANCE
TO STANDARD, SPECIFICATIONS, SAFETY AND STATUTORY RULES & REGULATIONS APPLICABLE. IT IS CERTIFIED THAT, THIS DRAWING
1. ALL DIMENSIONS ARE IN MILLIMETERS, ELEVATIONS AND COORDINATES IN METERS UNLESS HAS NO EXCEPTIONS UNLESS DEFINED AS ABOVE EXPLICITLY.IT IS CERTIFIED BY I-LDC FOR ONWARD SUBMISSION OF THIS DRAWING BY
OTHERWISE SPECIFIED. CONTRACTOR TO ENGINEER.
PROJECT NAME : DESIGN, CONSTRUCTION AND COMPLETION OF UNDERGROUND STATIONS AND TUNNEL INCLUDING FINISHES
FROM KAPODRA RAMP TO SURAT RAILWAY STATION FROM CHAINAGE 3700M TO CHAINAGE 7160.6M, COMPRISING TWIN BORED
UNDERGROUND TUNNEL BETWEEN NORTHERN RAMP AND SURAT RAILWAY METRO STATION, ALL CUT AND COVER PORTION
INCLUDING THREE UNDERGROUND STATIONS VIZ. KAPODRA, LABHESHWAR CHOWK AND CENTRAL WAREHOUSE WITH ENTRY/EXITS
NOTES :- & CONNECTING SUBWAY BY BOX PUSHING METHOD AND A PORTION OF NATM AND LAUNCHING AND RECEIVING CHAMBERS OF TBM
FOR SURAT METRO RAIL PROJECT, PHASE-I
1. STRUCTURAL FRAMING DRAWINGS ARE FOR STRUCTURAL ELEMENT SIZES (D-WALL, CONTRACT ID : GMRC/CONS/UG-01/PKG-CS2/PH-01/2020
COLUMNS, RC WALL,BEAMS, SLAB, STAIRCASE). SETTING OUT DIMENSIONS ARE INDICATIVE, DRAWING
MUST BE READ IN CONJUNCTION WITH ARCHITECTURAL DRAWINGS. ANY DISCREPANCIES NAME/TITLE : FRAMING PLAN AT PLINTH LEVEL OF ANCILLARY BUILDING SIZE : A1
SHOULD BE VERIFIED BY DESIGN TEAM PRIOR TO EXECUTION. LOCATION : KAPODRA STATION SHEET NO. : --
2. STRUCTURAL FRAMING DRAWINGS ARE FOR STRUCTURAL ELEMENT SIZES (LIFT PIT, REV. NO. : R-0
DRAWING NO. : D-EUGP1-TPT-F-KPS-CST-FWG-1103
ESCALATOR PIT, LIFTING HOOK) SETTING OUT DIMENSIONS ARE INDICATIVE, MUST BE READ IN
SCALE : 1/100 DATE : 08-03-2023
CONJUNCTION WITH ARCHITECTURAL DRAWINGS. ANY DISCREPANCIES SHOULD BE VERIFIED
IT IS CERTIFIED THAT DETAILED DRAWING PREPARED IS COMPLIED WITH THE TERM & CONDITIONS OF CONTRACT WITH MEGA AND DDC
BY DESIGN TEAM PRIOR TO EXECUTION. OWNS FULL RESPONSIBILITY FOR DESIGN AS PER ODS & OCS, ADEQUACY & MEETING FUNCTIONAL, PERFORMANCE AND OPERATIONAL
REQUIREMENTS INCLUDING CONSIDERATION FOR INTERFACE REQUIREMENTS WITH OTHER CONCERNED DESIGNERS & CONTRACTORS
3. STRUCTURAL FRAMING DRAWINGS ARE FOR STRUCTURAL ELEMENT SIZES (FLOOR OPENINGS) AND COMPLIANCE TO STANDARD, SPECIFICATIONS, SAFETY AND STATUTORY RULES & REGULATIONS APPLICABLE. IT IS CERTIFIED THAT,
SETTING OUT DIMENSIONS ARE INDICATIVE, MUST BE READ IN CONJUNCTION WITH THIS DRAWING HAS NO EXCEPTIONS UNLESS DEFINED AS ABOVE EXPLICITLY. THIS DRAWING WITH RELEVANT ANALYSIS & DESIGN HAS
BEEN PRODUCED BY DDC AND INDEPENDENTLY CHECKED BY I-LDC & CONTRACTOR BEFORE SUBMISSION TO ENGINEER.
ARCHITECTURAL DRAWINGS. ANY DISCREPANCIES SHOULD BE VERIFIED BY DESIGN TEAM
PRIOR TO EXECUTION. 08-03-2023 08-03-2023 08-03-2023