Q INPUT
VOLUME PLAN ROF
PLAN VOLUME SUMP ESTIMATION
CATCHMENT (m2) SUMP PUMP DAY REMARK
(m3) PUMPING (Day)
RAIN RAIN AIR TANAH (m3) (m3/Day)
(mm) (m3/day) (m3/day)
61,702.00 22,176.00 56,222.11 1.00
56,222.11 22,176.00 50,742.21 2.00
50,742.21 22,176.00 45,262.32 3.00
45,262.32 22,176.00 39,782.42 4.00
39,782.42 22,176.00 34,302.53 5.00 RAIN CONDITION
34,302.53 22,176.00 28,822.64 6.00
10.78 14,752.11 1,944.00
28,822.64 22,176.00 23,342.74 7.00
23,342.74 22,176.00 17,862.85 8.00
17,862.85 22,176.00 12,382.95 9.00
506,639.00
12,382.95 22,176.00 6,903.06 10.00
6,903.06 22,176.00 1,423.17 11.00
1,423.17 22,176.00 -4,056.73 12.00
Total Pumping Days 11.26
61,702.00 22,176.00 41,470.00 1.00
41,470.00 22,176.00 21,238.00 2.00
1,944.00
21,238.00 22,176.00 1,006.00 3.00 NO RAIN
1,006.00 22,176.00 -19,226.00 4.00
Total Pumping Days 3.05
Simulasi pemompaan Sump utama Pit Timur HHI dengan menggunakan kombinasi Pompa SIS (MF-385) & RJP 2
(MF-420) pada kondisi hujan dengan curah hujan maksimum sump bisa kering dalam kurun waktu 12 hari
sementara jika tidak ada hujan maka sump bisa kering dalam kurun waktu 3 hari