JSA

JOB TITLE /AIM Pigiging and hydro static testing of 6" inch diameter /Condensate pipeline from BHP Zamzama to Procon Bo
JSA DATE 10/12/2006 JSA NO./ REVISION
SUPERVISOR / JSA LEADER Shakeel Ahmed SCRIBE: Israr Ahmed
PARTICIPANTS A. Samad Lakhani (Procon) Naveed Ahmed(procon) Khalid (procon) Ameen Shah (procon) Kamran (procon)
LIST ASSOCIATED PROCEDURES/WORK INSTRUCTIONS OR TEMPORARY Wis:
Attach copies of any relevant documentation/drawings
Part 2: Job Safety Analysis
Jop Steps:
1 Mobilization of Equipment
2 Pigging
3 Water filling pressuring dewatering and drying
4 Demobilization

Part 3: Contingency Plans. Standard PPE,S : First aid kit must be present at the area and the HSE personnel is the first respo

Part 4: Review. After the job has been completed, JSA leader should note: any hazards, which were identified in the original J
captured in the OMS? List action items, changes and transfer any changes to the Change Management System
rom BHP Zamzama to Procon Boobak

Israr Ahmed
n Shah (procon) Kamran (procon) Ali Mohd(Procon) Sahkeel(Procon)

ntation/drawings

e HSE personnel is the first response in case of emergency

ch were identified in the original JSA? Any practices that need to be


anagement System
JSA NO: JOB TITLE: PIGGING HYDROSTATIC
Step Describe Job Step Potential Hazards Hazard Controls
No. (Copy from part 2 of form (Use Hazard Checklist)
1 Mobilization of workes & equipment Unauthorized equipment brought out to site Before mobilization any equipment make sure that the E & P
Perosnnel got inspected the equipment.
Ensure that all the tools shall be colour coded.

unskilled and uniducted personnal starting the Ensure that all personnel prior to start the have been inducted
job. and oriented about the hazard in the job site.
Workers starting the job unfit to work. All pesonnel not fit to work shall not be allowed to work at the
project site.
workes starting the job with out JSA JSA must be in place prior to work. Ensure all the persons
take part in the toolbox meeting discussion. JSA was
discussed to workers and signedat the back.
Pumps Ensure that suitable capacities filling and pressursing pumps
are used.
Ensure proper type & size of pigs are used.
2 Pigging Pig traps
exposure of workers to various hazard like Ensure workers are complying with the min. PPE req. Safety
hand injury, dust, eye injury. shoes helmet, safety glass, Dust mask, reflective vest,

3 Hydro static testing water filling potable water Ensur ethat ptable water is available. Addition of inhibitor to
pressuring dewatering and drying test water be done if required. Ensure pressure recording.

Communication Ensure that proper communication is maintained during


pigging and testing.
Ventes and drain Vents and drain are provided on pipeline at proper locations.

Water disposal proper disposing arrainged for testing and water be used.
Improper PPE
4 Demobilization Same as Mobilization Same as Demobilization