You are on page 1of 1

Built-Environment - Sri Lanka - Vol.

08, Issue 02 : 2008

kept up a very responsive cooperation with the in- -


surer, 4). Claimant had revealed all the information surance, insurance companies should investigate the
regarding the project to the insurer, 5). If there was site in order to assess the risk, before computing the
any discrepancy a negotiated settlement was sought. premium. Local contractor’s knowledge and experi-
ence on risk management seem to be poor compared
winning a claim. to foreign contractors. It was seen that claims with-
out proper documentation will be either rejected or
4.6 Remaining Cost of Claims under-settled. Therefore contractors need to maintain
records through out the project. In drafting a claim a
After the claim was settled partially, it was found that legal and domain expert’s advice would be very use-
there was a considerable remaining amount other ful.
than the deductible amount agreed. Even if the claim
is fully settled, there is a deductible amount which is Insurance companies and contractors should main-
a liability to the contractor. If the claim is rejected, the tain a cordial relationship by means of active commu-
full amount claimed is taken as remaining cost. In this nication especially with underwriters, loss adjusters,
study, it was discovered that in every claim, except in etc. Contractors should implement maximum safety
a few, the contractor had to suffer losses. measures as a priority especially if it can be foreseen
as a potential risk of damage.
There was a very low probability shown for transferring
remaining cost of CAR claims that were under-settled Acknowledgement
or rejected. However, there was a question, “was the
- The facilities provided by the University of Moratuwa
to carry out this research, comments and sugges-
taking into consideration the cost of administration. tions made by the referees to improve this paper and
the editorial assistance are gratefully acknowledged.
Conclusions Moreover, We extend our gratitude towards other of-
-
ed institutes who have extended their cooperation in
forms of contract, most of projects implemented in obtaining valuable information for this research.
Sri Lanka, CAR policy has become a mandatory in-
surance requirement. CAR policy covers most of the
References
-
surance policy. However, foreign contractors showed Ahmed, S.M., Ahmad, R. & Saram, D.D. (1999)
an interest in obtaining CAR insurance on their own. Risk management trends in Hong Kong
From the contractors point of view, wordings of the construction industry: a comparison
policy was more important than the premium. In addi- of contractors and owners perceptions,
tion to wordings and premium, quality of the service of Journal of Engineering, Construction and
the insurer, strength of re-insurers, economic poten- Architectural Management, vol.6, no. 3, pp.
tial and reputation of the insurer are the other factors 225-234.

Willingness of the insurer to take on contractor’s risks Akintoye, A.S. & MacLeod, M.J. (1997) Risk
mostly depend on the magnitude of the risks, followed analysis and management in construction,
by the potential for long term corporation and future International Journal of Project Manage
projects. ment, vol. 15, no. 1, pp. 31-38.

Ashworth, A. (2001) Contractual Procedures in the


insurance policies, 189 claims from ongoing civil en- Construction Industry. 4th ed, Longman,
gineering were analyzed. The Most frequent type of London.
damage found to be third party property damage
and the source of risk, Act of Man. When the most Bunni, N.G. (1986) Construction Insurance, Elsevier
Applied Science, Essex.
and rain found to be the most frequent. In third party
claims, damage to houses and boundary walls was Bunni, N.G.
high as 94%. Overall, the percentage of settlements edn, BSP Professional, Oxford.
was only 47%.
De Silva, C. (2003) Risk Management in Engineer

Authority, Sri Lanka.

30

You might also like