CONSTRUCTION SURVEYING
CVT-211
DE =360°-295°
DE =N 65° W ;being in Q
Line AB can are given by N 60° E and 40.0m
respec vely. It can be plo ed using the protractor and
scale, but accuracy is not guaranteed. But calcula ng
the x and y coordinates of the line will be more accurate
because all people see the same dimensions.
𝐴𝐵 = 𝐴𝐵 sin 60°
𝐴𝐵 = 𝐴𝐵 cos 60°
𝑨𝑩𝒀 = 𝟐𝟎𝒎
𝐿𝐴𝑇 = −25.4
29 | P a g e
RECTANGULAR COORDINATES
CONSTRUCTION SURVEYING
CVT-211
BEARING
LINE LENGTH
(from +y axis)
AB 50 m 30°
BC 70 110°
CD 82 225°
DE 31.20 295°
30 | P a g e
RECTANGULAR COORDINATES
CONSTRUCTION SURVEYING
CVT-211
EXERCISE #9
WHOLE CIRCLE
LINE LENGTH
BEARING
AB 121.25 m 64° 45’
BC 236.83 143° 26’
CD 179.0 234° 15’
DA 246.97 336° 32’
WHOLE CIRCLE
LINE LENGTH
BEARING
PQ 262 m 69° 55’
QR 155 166° 57’
RS 268 244° 20’
31 | P a g e