INTRODUCTION :
The purpose of the test is to determine the compliance of the above sources with the emission
standards. This test plan is prepared for review and approval by the DENR-EMB - CAR so that the
results of the emission tests can be used as basis of their accomplishment of self-monitoring report and
compliance to permit conditions of their permit to operate.
The parameters to be test are PM, SOX, NOX & CO the test will be conducted in three (3) runs.
FACILITY INFORMATION:
The above testing activity will be performed at the facility specified below with the following contact
information:
Emission testing will be conducted with a load of at least 90% of the rated capacity per unit.
TEST METHODOLOGIES:
The sampling will be conducted in three sampling runs per source. The following DENR Standard
Procedure (US-EPA Reference Methods) will be used in this stack-sampling program. These
procedures are based on the US-EPA 40 CFR 60, Appendix A – Reference Methods for Emission
Testing of Stationary Sources:
Methods 1 to 4 will be conducted in conjunction with Methods 5 and 6 which requires isokinetic
emission sampling. GREENTEK ENVIRONMENTAL PHILS. CO., (GREENTEK ENVIRONMENTAL
ENGINEERING SERVICES) will use stainless steel probe liner and sampling nozzle which is an
accepted alternative of the USEPA (DENR approved) methods.
In addition to PM and SOx sampling, the NOx testing will be conducted using three samples per test run
where one result may be disregarded if they are found to be an outlier from other values. CO samples
will be collected in a tedlar bag and will be analysed using a non-dispersive infra-red analyse
The table below describes the implementation of the above sampling procedures:
Test
Parameter Abbr. Test Method Notes
Duration
Minimum of 60
Volumetric Flow Performed concurrent with
VFR EPA Method 1-4 minutes per
Rate M5 test
run (3 Runs)
Minimum of 60
Performed concurrent with
Particulate Matter PM EPA Method 5 minutes per
M5 test Run
run (3 Runs)
SOx Minimum of 60
Performed concurrent with
Sulfur Oxides (as EPA Method 6 minutes per
M5 test Run
SO2) run (3 Runs)
Minimum of 60
EPA Method 3 Integrated Tedlar bag
Oxygen O2 minutes per
Fyrite sample during method 5
run (3 Runs)
Minimum of 60
EPA Method 3 Integrated Tedlar bag
Carbon Dioxide CO2 minutes per
Fyrite sample during method 5
run (3 Runs)
NOx Minimum of 60
Grab Sampling during
Nitrogen Oxides (as EPA Method 7 minutes per
Method 5 test run
NO2) run (3 Runs)
Integrated Tedlar bag
Minimum of 60
sample during Method 5,
Carbon Monoxide CO EPA Method 10 minutes per
same tedlar bag for
run (3 Runs) CO2/O2
The facility should operate the unit source continuously during testing. In case the boiler is operating
intermittently, or the stack test ports did not comply with the Method 1 requirements, only gaseous pollutants
will be tested such as SOx, NOx and CO including gas analysis of CO2 and O2. Three replicate test runs,
about 30minutes in duration shall be performed when the boilers are intermittently.
TEST SCHEDULE AND IMPLEMENTATION PLAN:
Test
Date Source Notes
Activities
The actual run date and time may vary based on the facility process conditions, weather and testing logistics.
The Test Team leader will coordinate the specific run plans with the designated facility representative.
TEST PERSONNEL:
Prepared by: