Professional Documents
Culture Documents
Intro Quantitative Risk Assessment and Decision Making 1678032444
Intro Quantitative Risk Assessment and Decision Making 1678032444
Introducing
Quantitative Risk Assessment
into decision making
Dr Marcos Tabacow
Risk management: What does ‘good’ look like?
•…
“…they can be ‘worse than useless’”
For a summary of issues, see Krisper, M. (2021). Problems
Anthony (Tony) Cox, L., Jr (2008), What's
with risk matrices using ordinal scales. arXiv preprint
arXiv:2103.05440. Wrong with Risk Matrices?. Risk Analysis,
28: 497-512.
Case Study: Simple development project
Start with the project schedule … then add risks to the schedule
1 Consequence
Task Months Likelihood / Risk
Risk (months
2 Frequency exposure
1. Feasibility study 3 delayed)
2. Design 2 Risk 1: Change in
3 10% 4 0.4
3. Contract negotiation 1 government
4 Risk 2: Change orders 3 1 3
4. Development approval 4
5. Pre construction 2 Risk 3 : Workforce shortage 30% 2 0.6
5
6. Construction 9 Risk contingency (months) 4
6
7. Completion 3
Risk-adjusted schedule = 28 months
7 Expected duration 24
… is this the best we can do?
Case Study: Simple development project
Most likely
case
X
• Initial estimate of risk impact: 4 months delay • Initial schedule estimate: 100% chance of delivering in 24
months (before risk contingency)
• Actual risk impact: between 15 and 26 months
delay with 90% confidence • Schedule with uncertainty: Actually, there’s only a 29%
chance of delivering in 24 months (before considering risks)
Informing real-time decisions
• Virtually no chance of
meeting original ‘risk
adjusted’ schedule of
28 months (0.02%)
• 46 month average
completion time
• 90% chance of
completing between
38 and 54 months
• Board escalation if
delayed more than 52
months (P90)?
• Bonus if delivered
under 39 months (P10)?
Risk appetite: should this project even go ahead?
Risk mitigation: What to prioritise?
• For example,
Construction should be
prioritised first, even
though it only had the
second highest risk
(Risk 3: Workforce
shortage)
Some discussion points
• What use cases have you encountered for applying quantitative risk analysis?
• What competencies does the risk team need to develop to embed QRA in organisations?
Thanks!
Marcos Tabacow