SAP S/4HANA – Presented by Mickael QUESNOT

Material Requirements Planning

PUBLIC

Table of Contents

1 Purpose 4

2 Prerequisites 5
2.1 System Access 5
2.2 Roles 5
2.3 Master Data, Organizational Data, and Other Data 6
2.4 Business Conditions 7
2.5 Preliminary Steps 7
2.5.1 Create Scheduling Agreement 7
2.5.2 Prerequisite for Material Exception (Optional) 9
2.5.2.1 Manage Teams and Responsibilities 9
2.5.2.2 Manage Situation Types 11
2.5.3 Prerequisite for Handover of Purchase Requisition (Optional) 13
2.5.3.1 Assign MRP Group 0011 to TG0011 13
2.5.4 Prerequisite for MRP Change Request (Optional) 14
2.5.4.1 Assign Business User 14
2.5.4.2 Create Purchasing Info Record 15
2.5.4.3 Clear PIRs for Material TG0099 17
2.5.4.4 Clear Purchase Requestions & Purchase Orders for Material TG0099 19

3 Overview Table 20

4 Test Procedure 22
4.1 Manage PIRs for Material TG0011 & TG0012 22
4.2 Monitor Material Coverage 23
4.2.1 Run Material Requirements Planning (MRP) 23
4.2.2 Evaluate MRP Result 25
4.2.2.1 Evaluate MRP Result (Purchase Requisitions) 25
4.2.2.2 Evaluate MRP Result (Delivery Schedule) 28
4.3 Display MRP Run Master Data Issues 29
4.4 Display MRP Run Key Figures 30
4.5 Time-dependent Safety Stock Levels 31
4.5.1 Time-dependent Safety Stock 31
4.5.1.1 Maintain MRP Safety Stock Method in Material 31
4.5.1.2 Maintain Time-Dependent Safety Stock 32
4.5.1.3 Check Material Coverage 33
4.5.2 Time-dependent Days of Supply 35
4.5.2.1 Maintain MRP Safety Stock Method in Material 35
4.5.2.2 Maintain Time-Dependent Days of Supply 36
4.5.2.3 Manage PIRs for Material TG0099 37
4.5.2.4 Check Material Coverage 39
4.5.2.5 Reset Material Master Data 40
4.6 Material Exception (Optional) 41
4.6.1 Clear Initial Stock 41
4.6.2 Clear Existing Purchase Requisitions 42
4.6.3 Manage PIRs for Material TG0099 43
4.6.4 Run Material Requirements Planning (MRP) and Firm Purchase Requisition 45
4.6.5 Increase Stock for TG0099 46
4.6.6 Detect MRP Situations 47
4.6.7 Check and React to Material Exception 48
4.6.8 Reduce Stock for TG0099 50
4.7 MRP Change Request (Optional) 51
4.7.1 Create Purchase Order 51
4.7.2 Manage PIRs for Material TG0099 52
4.7.3 MRP Rescheduling Check 53
4.7.4 Create and Send MRP Change Requests 55
4.7.5 Manage Change Requests 56
4.7.6 React to MRP Change Requests based on Vendor’s Response 57

5 Appendix 59
5.1 Process Chains 59
5.1.1 Preceding Processes 59
5.1.2 Succeeding Processes 59

Material Requirements Planning (J44_GB)


Purpose PUBLIC 2
1 Purpose

This process enables your material requirements planning (MRP) department to automate the procurement planning. The main function of MRP is to guarantee material availability and to avoid
delays in order fulfillment. The planning run checks availability of each material and, in case of shortages, creates purchase requisitions, or delivery schedules if a scheduling agreement exists.
Remaining shortages are displayed in the MRP app where the material planner can analyze the situation.
Procurement lead time can be longer than the time available to fulfill a demand. For this reason, you must procure the material in advance and cover your demand from stock. This process starts
by creating forecast demands that are interpreted as expected customer demand. The MRP schedule runs. The system creates purchase requisitions or scheduling lines that trigger external
procurement.
Optionally, you can handle time-dependent stock levels, purchase requisition handover and MRP material exceptions.
This document provides a detailed procedure for testing this scope item after solution activation, reflecting the predefined scope of the solution. Each process step, report, or item is covered in its
own section, providing the system interactions (test steps) in a table view. Steps that are not in scope of the process but are needed for testing are marked accordingly. Project-specific steps must
be added.

Note Values in this test script (decimal notation, date formats, and so on) are presented in U.S. standard notation. If your test system is set up to use a different notation, enter values as
appropriate.

Material Requirements Planning (J44_GB)


Purpose PUBLIC 3
2 Prerequisites

This section summarizes all the prerequisites for conducting the test in terms of systems, users, master data, organizational data, other test data and business conditions.

2.1 System Access

System Details

System Accessible via SAP Fiori launchpad. Your system administrator provides you with the URL to access the various apps assigned to your role.

2.2 Roles
Assign the following business roles to your individual test users. Alternatively, if available, you can create business roles using the following spaces with pages and predefined apps for the SAP Fiori
launchpad and assign the business roles to your individual test users.

Note These roles or spaces are examples provided by SAP. You can use them as templates to create your own roles or spaces.
For more information about business roles, refer to Assigning business roles to a user in the Administration Guide to Implementation of SAP S/4HANA with SAP Best Practices .

Name (Role) ID (Role) Name (Launchpad Space) ID (Launchpad Space) Log


On

Material Planner - External SAP_BR_MATL_PLNR_EXT_PROC Material Planner - External Procurement SAP_BR_MATL_PLNR_EXT_PROC


Procurement

Master Data Specialist - Product Data SAP_BR_PRODMASTER_SPECIALIST Master Data Specialist - Product Data SAP_BR_PRODMASTER_SPECIALIST

Purchaser SAP_BR_PURCHASER Materials Management - Purchasing / Materials Management SAP_MM_SPT_PURCHASING_PC /


- Sourcing and Contracting SAP_MM_SPT_SOURCING_PC

Business Process Specialist SAP_BR_BUSINESS_PROCESS_SPEC Business Process Specialist SAP_BR_BUSINESS_PROCESS_SPEC

Inventory Manager SAP_BR_INVENTORY_MANAGER Inventory Manager SAP_BR_INVENTORY_MANAGER

Material Requirements Planning (J44_GB)


Prerequisites PUBLIC 4
Name (Role) ID (Role) Name (Launchpad Space) ID (Launchpad Space) Log
On

Configuration Expert - Business Process SAP_BR_BPC_EXPERT Configuration Expert - Business Process Configuration SAP_BR_BPC_EXPERT
Configuration

2.3 Master Data, Organizational Data, and Other Data


The organizational structure and master data of your company have been created in your system during activation. The organizational structure reflects the structure of your company. The master
data represents materials, customers, and vendors, for example, depending on the operational focus of your company.
Use your own master data or the following sample data to go through the test procedure.
Material

Master Value Details Comments

Material TG0011 Trading Good 0011,PD,Regular Proc. Used for MRP procedure without scheduling agreement

Material TG0012 Trad. Good 0012,Reord. Pt.,Regular Proc. Used for MRP procedure with scheduling agreement

Material TG0099 Trading Good 0099,PD,Regular Proc. Used for Material Situation Handling

Org. Data

Master Value Details Comments

Plant 1110 Plant 1 GB

Vendor 11300001 Domestic GB Supplier 1

Vendor 11300002 Domestic GB Supplier 2

Company Code 1110 Company Code 1110

Purchasing Organization 1110 Purch. Org. 1110

For more information on creating these master data objects, see the following Master Data Scripts (MDS)

Material Requirements Planning (J44_GB)


Prerequisites PUBLIC 5
Table 1: Master Data Script Reference
Master Data ID Description

BNF Create Product Master of Type "Trading Good"

2.4 Business Conditions

Scope Item Business Condition

31N - Situation Handling Install this scope item for the situation handling steps.

2.5 Preliminary Steps


In this section, you are provided a detailed step-by-step description of technical or other prerequisites.

2.5.1 Create Scheduling Agreement

Purpose

This process step shows you how to create the scheduling agreement for the material/supplier combination, if it has not been maintained yet. If the scheduling agreement is already present in the
system you can skip this step.

Procedure

Test Step Test Step Name Instruction Expected Result Pass / Fail /
# Comment

1 Log On Log on to the SAP Fiori launchpad as a Purchaser. The SAP Fiori launchpad displays.

2 Access the App Open Manage Purchase Scheduling Agreements (F2179).

Material Requirements Planning (J44_GB)


Prerequisites PUBLIC 6
Test Step Test Step Name Instruction Expected Result Pass / Fail /
# Comment

3 Create Scheduling Agreement Select Create to create a scheduling agreement. The Purchase Scheduling Agreement screen
displays.

4 Enter Header Data Under General Information tab, create a scheduling agreement with the following data:
● Supplier: 11300001
● Agreement type: SA With Release doc
● Valid To: dd.mm.yyyy (for example: 01.01.2099)
● Purchasing Organization: 1110
● Purchasing Group: 001
● Target Value: <For example, 200000 EUR>

5 Enter Header Notes Navigate to the Notes tab, enter notes in some or all of the of the Header Notes elements for the
ones mentioned below:
● Header text
● Header note
● Pricing types
● Deadlines
● Terms of delivery
● Shipping instructions
● Terms of payment
● Warranties
● Penalty for breach of contract
● Guarantees
● Contract riders (clauses)
● Asset
● Other contractual stipulation
● Inbound Delivery
● Vendor memo (general)
● Vendor memo (pur. org.)

6 Add Items to Scheduling Choose the Items tab and choose Create. The Purchase Scheduling Agreement Item
Agreement screen displays.

7 Enter Item Data Make the following entries under General Information tab:
● Plant: 1110

Material Requirements Planning (J44_GB)


Prerequisites PUBLIC 7
Test Step Test Step Name Instruction Expected Result Pass / Fail /
# Comment

● Material: TG0012
In Quantity and Price tab, enter the following data:
● Target Quantity: 120 PC
● Net Order Price: 40
● Order Price Unit: PC or <defaulted value>
In Output Control tab, make the following entry:
● Creation Profile: S001

8 Enter Item Notes Enter notes in some or all of the of the Header Notes elements for the ones mentioned below:
● Item text
● Info record PO text
● Material PO text
● Delivery text
● Info record note
● ES Master Agreements (MA)
● ES Requests f. Proposals (RFP)
● Sequence Number LP
Choose Apply at the bottom of the view.

9 Save Return to the New Purchase Scheduling Agreement header view and choose Create at the bottom of A schedule agreement is created.
the view.
Make a note of the schedule agreement number.

2.5.2 Prerequisite for Material Exception (Optional)

2.5.2.1 Manage Teams and Responsibilities

Test Administration

Customer project: Fill in the project-specific parts.

Material Requirements Planning (J44_GB)


Prerequisites PUBLIC 8
Test Case ID <X.XX> Testing Date:

Tester Name: Duration:

Business Role(s): Responsibility: <State the Service Provider, Customer or Joint Service Provider and Customer>

Purpose

This process step shows you how to link the list of users who are supposed to receive material exception notifications.

Procedure

Test Test Step Instruction Expected Result Pass / Fail /


Step Name Comment
#

1 Log On Log on to the SAP Fiori launchpad as a Business Process Specialist. The SAP Fiori launchpad displays.

2 Access Open Manage Teams and Responsibilities (F2412). The Manage Teams and
the App Responsibilities screen displays.

3 Check Make following entries and choose Go: If there is no entry for Plant 1 GB
Existing ● Type: SMRPT on the Area of Responsibility screen,
Teams choose Add to select it and then
In Teams area, choose again the row of the filtered teams, check if MRPMaterial= TG0099 is maintained on Teams screen. If so, then the team is
choose OK.
created already and please skip the following steps; if not maintained, then continue the following steps.
For other plant entries on the Area of
Responsibility screen, choose Delete
Note If no filtered teams display in Teams area, please continue the following steps to create it. to remove them and then choose OK.

4 Create Choose Create and make the following entries: Then user MatlPlnrExtProc can
Teams ● Name: MRP MAT EXCEPTIONS TEAM receive the notification to handle the
critical situation.
● Status: Enabled
● Type: SMRPT
Go to the Responsibility Definitions section, and make the following entries:
● MRP Controller: 001
● MRP Material: TG0099
● MRP Plant: 1110
Go to the Team Owners area, and choose Create.

Material Requirements Planning (J44_GB)


Prerequisites PUBLIC 9
Test Test Step Instruction Expected Result Pass / Fail /
Step Name Comment
#

On the Select: Team Owner screen, search the employee you defined by following the note below, select the searched item and choose OK.

Note For On-Premise system, make sure that your system user has its own employee number and is assigned correctly. For detailed
procedure about how to create employee number and how to assign employee number to system user, refer to
https://help.sap.com/viewer/S4HANA_1909_AdminGuideAdministration Guide for the Implementation of SAP Best Practices for SAP
S/4HANA (1909 FPS0) in Chapter Implementation > Activating your solution > Carrying out post-activation steps > Creating approvers >
Creating an employee & Assigning a user to an employee & Business partner synchronization. If you have any question that related with
employee creation or assignment, create a BCP ticket on the component PA-PA-XX.

5 Save Choose Create. The team has been created.


Team

2.5.2.2 Manage Situation Types

Test Administration

Customer project: Fill in the project-specific parts.

Test Case ID <X.XX> Testing Date:

Tester Name: Duration:

Business Role(s): Responsibility: <State the Service Provider, Customer or Joint Service Provider and Customer>

Purpose

This process step shows you how to configure the situation type by using template.

Note Please make sure 31N is activated if you want to execute this step.

Material Requirements Planning (J44_GB)


Prerequisites PUBLIC 10
Procedure

Test Test Step Name Instruction Expected Result Pass / Fail /


Step # Comment

1 Log On Log on to the SAP Fiori launchpad as a Configuration Expert - Business Process Configuration. The SAP Fiori launchpad
displays.

2 Access the App Open Manage Situation Types (F2947) . The Manage Situation
Types (F2947) screen
displays.

3 Check Existing Select Situation Types tab. Make the following entries and choose Go:
Situation Types ● Name (In search box): MRP Material Exceptions
Choose again the row of the filtered Situation Types and check whether types related to MRP Material Exceptions already exist. If so,
skip step 4 and only maintain Start Batch Job in step 5; if not, continue the following steps.

Note If no filtered teams displays, please continue the following steps to create it.

4 Copy Situation On the Manage Situation Types screen, There are two tabs: Situation Templates and Situation Types.
Template Choose Situation Templates tab and choose Go to search for the situation template: SAP_PP_MRP_MATERIAL_EXCEPTION
Check the box before the situation template: SAP_PP_MRP_MATERIAL_EXCEPTION and choose Copy.

5 Create Custom In this step you create a situation type. The situation has been
Situation On the Situation Type screen, make the following entries: created.
Template
● ID: ZTEST_MRP_EXCEPTIONS
This field is the Unique Identifier of a situation type. The ID of a situation type should start with 'Z'. ID is a Mandatory Field and can't be left
blank.
● Name: MRP Material Exceptions
In the Recipients field, make the following entry:
● Member Function: MRP Planning
In the Situation Monitoring field, make the following entry:
● Monitor Instances: Yes
In the Batch Job Scheduling field, make the following entries:
● Time Zone: UTC
● Start Batch Job At: <Time you want your team members to get notification> (For example, if you want to let your team
members receive the notifica-tion at UTC 8:00, then enter UTC 8:00. But due to system clock settings issue, there maybe a 30 minutes lag, so
they get the notification around UTC 8:30.)
Choose Create .

Material Requirements Planning (J44_GB)


Prerequisites PUBLIC 11
Test Test Step Name Instruction Expected Result Pass / Fail /
Step # Comment

6 Enable Situation Choose Yes for the pop-up message: Do you want to enable situation type? The situation is enabled.
Template

2.5.3 Prerequisite for Handover of Purchase Requisition (Optional)

2.5.3.1 Assign MRP Group 0011 to TG0011

Test Administration

Customer project: Fill in the project-specific parts.

Test Case ID <X.XX> Testing Date:

Tester Name: Duration:

Business Role(s): Responsibility: <State the Service Provider, Customer or Joint Service Provider and Customer>

Purpose

This process step shows you how to assign MRP group to TG0011.

Procedure

Test Step # Test Step Name Instruction Expected Result Pass / Fail / Comment

1 Log On Log on to the SAP Fiori launchpad as a Master Data Specialist - Product Data. The SAP Fiori launchpad displays.

2 Access the App Open Change Material (MM02).

Material Requirements Planning (J44_GB)


Prerequisites PUBLIC 12
Test Step # Test Step Name Instruction Expected Result Pass / Fail / Comment

3 Specify Material On the Change Material (Initial Screen), enter following data and choose Continue: The Change Material TGXXXX (Material general) screen displays.
● Material: TG0011
In the Select View(s) dialog box, choose MRP 1, and press Enter.
In the Organization Levels dialog box, make the following data and press Enter:
● Plant: 1110

4 Assign MRP Group On the General Data tab, make the following entry and choose Save: The material change is saved.
● MRP Group:0011 External procurement (PReq Handover)

2.5.4 Prerequisite for MRP Change Request (Optional)

2.5.4.1 Assign Business User

Purpose

Create MRP Change Requests process needs an additional Purchaser role. This process step shows you how to assign business user if it has not been assigned yet.

Procedure

Test Step Test Step Name Instruction Expected Result Pass / Fail /
# Comment

1 Log On Log on to the SAP Fiori launchpad as an Administrator. The SAP Fiori launchpad displays.

2 Access the App Open Maintain Business Users (F1303). The Maintain Business Users screen displays.

3 Search for Business On the Maintain Business Users screen, search for MATL_PLNR_EXT_PROC, then choose Go. Line with MATL_PLNR_EXT_PROC displays.
User

4 Display Business User Tick the checkbox in front of the line and choose Edit. The Maintain Business User screen displays
Screen

Material Requirements Planning (J44_GB)


Prerequisites PUBLIC 13
Test Step Test Step Name Instruction Expected Result Pass / Fail /
# Comment

5 Check Business Role In the Assigned Business Roles section, check whether SAP_BR_PURCHASER exists. If the role already exists,
you can skip the next step.

6 Assign Business Role On Assigned Business Roles section, choose Add. Business Role SAP_BR_PURCHASER was
Search for SAP_BR_PURCHASER, tick the checkbox in front of the line and choose OK. assigned.

Then choose Save.

2.5.4.2 Create Purchasing Info Record

Test Administration

Customer project: Fill in the project-specific parts.

Test Case ID <X.XX> Testing Date:

Tester Name: Duration:

Business Role(s): Responsibility: <State the Service Provider, Customer or Joint Service Provider and Customer>

Purpose

This process step shows you how to create the purchasing info record for the material/supplier combination, if it has not been maintained yet.

Procedure

Test Test Step Name Instruction Expected Result Pass / Fail /


Step # Comment

1 Log On Log on to the SAP Fiori launchpad as an Purchaser. The SAP Fiori launchpad
displays.

Material Requirements Planning (J44_GB)


Prerequisites PUBLIC 14
Test Test Step Name Instruction Expected Result Pass / Fail /
Step # Comment

2 Access the App Open Manage Purchasing Info Records (F1982). The Manage Purchasing
Info Records screen
displays.

3 Check Existing Info On the Manage Purchasing Info Records screen, search for Material: TG0099, then choose Go.
Record If an info record for material TG0099 with supplier <11300001> already exists, choose against the info record and check the General
Information: Available From: and Available to. If you confirm this info record is valid, please skip the following step 4 to 10.

4 Open New Choose Create. The Purchasing Info Record


Purchasing Info Screen is displayed.
Record

5 Enter Header Data Make the following entries: Header data is added.
Purchasing Info Record Category: Standard
Purchasing Organization: 1110
Supplier: 11300001
Material: TG0099
Plant: 1110
Purchasing Group: 002

6 Enter General Make the following entries: General Information is


Information Available From: Today added.

Available To: 31.12.9999

7 Enter Purchasing Make the following entries: Purchasing Data is added.


Data Incoterm: EXW
Incoterm Location 1: VENDOR

8 Enter Delivery and Make the following entries: Delivery and Quantity Data
Quantity Data Delivery Time in Days: 1 are added.

Under Delivery Tolerance in %: 10.0


Over Delivery Tolerance in %: 10.0
Tax Code: <Input Tax Code>
Tax Rate Valid From (If required): Select value from F4 help
Tax Country/Region (If required): Select value from F4 help

Material Requirements Planning (J44_GB)


Prerequisites PUBLIC 15
Test Test Step Name Instruction Expected Result Pass / Fail /
Step # Comment

Note When the TDT (time dependent tax) is activated via SSCUI 101016 (Define Tax Codes for Sales and Purchases) for country of
company code and the tax code is given, the field Tax Rate Valid From is mandatory. You can enter current date, which will be adjusted to
validity start date of tax code according to the settings in SSCUI.

Order Unit: PC
Standard Order Quantity: 10
Goods-Receipt-Based Invoice Verification: select
No Evaluated Receipt Settlement: select

9 Enter Condition In the Conditions section, choose Create. Condition Data is added.
Data In the General Information area, make the following entries:
Valid From: Today
Valid To: 12.31.9999
Amount: 30.00
Pricing Unit: 1
Currency: GBP
Choose Apply.

10 Create Your Data Choose Create. The purchasing info record


is created.

2.5.4.3 Clear PIRs for Material TG0099

Test Administration

Customer project: Fill in the project-specific parts.

Test Case ID <X.XX> Testing Date:

Tester Name: Duration:

Business Role(s): Responsibility: <State the Service Provider, Customer or Joint Service Provider and Customer>

Material Requirements Planning (J44_GB)


Prerequisites PUBLIC 16
Purpose

This process step shows you how to clear the planned independent requirements directly for material TG0099.

Procedure

Test Step Test Step Name Instruction Expected Result Pass / Fail /
# Comment

1 Log On Log on to the SAP Fiori launchpad as a Material Planner - External Procurement. The SAP Fiori launchpad
displays.

2 Access the App Open Maintain PIRs (F3445).

3 Check Default Area of On the Maintain PIRs screen, choose your user name and choose the App Settings icon. On the MRP Settings screen,
Responsibility choose Area of Responsibility.
Check if only the following entry is assigned:
Plant 1 GB / 001 (MRP Controller 001)
Choose AOR status button of this entry if not assigned, choose AOR status button of the corresponding entry to unassign
any other entry then choose Back.

4 Select On the Maintain PIRs (F3445) screen, make the following entries:
● Plant: 1110
● Period Indicator: Monthly(M)
● Version Active: Yes, No
● Material: TG0099

5 Filter Result Choose Go to execute. Material item displays.

6 Check Material Item Select the line with TG0099.


Check the material item, if a PIR for a future data already exists, skip the following steps. If not, continue the steps.

7 Clear PIRs Choose Edit in the upper right. On the Edit PIRs screen, clear the existing PIRs. PIR for a data in the future
is zero.

8 Save PIRs Draft Choose Save on bottom right. The PIRs are saved.

Material Requirements Planning (J44_GB)


Prerequisites PUBLIC 17
2.5.4.4 Clear Purchase Requestions & Purchase Orders for Material TG0099

Purpose

This process step shows you how to clear a Purchase Order for material TG0099.

Procedure

Test Step # Test Step Name Instruction Expected Result Pass / Fail / Comment

1 Log On Log on to the SAP Fiori launchpad as a Material Planner - External Procurement. The SAP Fiori launchpad displays.

2 Access the App Open Check Material Coverage (F0251). The Find Material screen displays.

3 Select Material and Show Shortages In the Find Material dialog box, enter the following entries and choose OK: The Material Details screen displays.
● Material: TG0099
● Plant: 1110
● Shortage definition: MRP Standard

4 Clear existing MRP Element Under Stock / Requirements List, clear the existing MRP Element. MRP Elements have been cleared.
In column Actions, choose delete from drop-down list.

Material Requirements Planning (J44_GB)


Prerequisites PUBLIC 18
3 Overview Table

The Material Requirements Planning (J44) scope item consists of several process steps provided in the following table.

Note If your system administrator has enabled spaces and pages on the SAP Fiori launchpad, the homepage will only contain the essential apps for performing the typical tasks of a business
role.
You can find all other apps not included on the homepage using the search bar.
If you want to personalize the homepage and include the hidden apps, navigate to your user profile and choose App Finder.

Process Step Business Role Transaction/App Expected Results

Manage PIRs for Material TG0011 & TG0012 [page ] 22 Material Planner - External Maintain PIRs (F3445) PIRs for TG0011 & TG0012 are created.
Procurement

Monitor Material Coverage

Run Material Requirements Planning (MRP) [page ] 23 Material Planner - External Monitor Material Coverage MRP runs for TG0011 and TG0012.
Procurement (F2101A)

Evaluate MRP Result

Evaluate MRP Result (Purchase Requisitions) [page ] 25 Material Planner - External Monitor Material Coverage MRP results are reviewed for material without scheduling
Procurement (F2101A) agreement (TG0011).

Evaluate MRP Result (Delivery Schedule) [page ] 28 Material Planner - External Monitor Material Coverage MRP results are reviewed for material with scheduling agreement
Procurement (F2101A) (TG0012).

Display MRP Run Master Data Issues [page ] 29 Material Planner - External Display MRP Master Data Issues The Display MRP Master Data Issues list displays.
Procurement (F1425A)

Display MRP Run Key Figures [page ] 30 Material Planner - External Display MRP Key Figures (F1426) The Display MRP Key Figures list displays.
Procurement

Material Exception (Optional)

Clear Initial Stock [page ] 41 Inventory Manager Manage Stock (F1062).

Clear Existing Purchase Requisitions [page ] 42 Material Planner - External Check Material Coverage (F0251)
Procurement

Material Requirements Planning (J44_GB)


Overview Table PUBLIC 19
Process Step Business Role Transaction/App Expected Results

Manage PIRs for Material TG0099 [page ] 43 Material Planner - External Maintain PIRs (F3445)
Procurement

Run Material Requirements Planning (MRP) and Firm Purchase Material Planner - External Check Material Coverage (F0251)
Requisition [page ] 45 Procurement

Increase Stock for TG0099 [page ] 46 Inventory Manager Manage Stock (F1062).

Detect MRP Situations [page ] 47 Material Planner - External Detect MRP Situations (F3853)
Procurement

Check and React to Material Exception [page ] 48 Material Planner - External Notification
Procurement

Reduce Stock for TG0099 [page ] 50 Inventory Manager Manage Stock (F1062).

Material Requirements Planning (J44_GB)


Overview Table PUBLIC 20
4 Test Procedure

In this procedure, two MRP procedures are covered. One MRP procedure is for material(TG0011) without scheduling agreement, the other MRP procedure is for material (TG0012) with schedule
agreement. Please follow the steps to test both subscenarios independently.

4.1 Manage PIRs for Material TG0011 & TG0012

Test Administration

Customer project: Fill in the project-specific parts.

Test Case ID <X.XX> Testing Date:

Tester Name: Duration:

Business Role(s): Responsibility: <State the Service Provider, Customer or Joint Service Provider and Customer>

Purpose

This process step shows you how to create the planned independent requirements directly for material TG0011 and TG0012.

Procedure

Test Step Test Step Name Instruction Expected Result Pass / Fail /
# Comment

1 Log On Log on to the SAP Fiori launchpad as a Material Planner - External Procurement. The SAP Fiori launchpad
displays.

2 Access the App Open Maintain PIRs (F3445).

3 Check Default Area of On the Maintain PIRs screen, choose your user name and choose the App Settings icon. On the MRP Settings screen,
Responsibility choose Area of Responsibility.

Material Requirements Planning (J44_GB)


Test Procedure PUBLIC 21
Test Step Test Step Name Instruction Expected Result Pass / Fail /
# Comment

Check if only the following entry is assigned:


Plant 1 GB / 001 (MRP Controller 001)
Choose AOR status button of this entry if not assigned, choose AOR status button of the corresponding entry to unassign
any other entry then choose Back.

4 Select On the Maintain PIRs (F3445) screen, make the following entries:
Plant: 1110
Period Indicator: Monthly(M)
Version Active: Yes, No
Search: TG0011

5 Filter Result Choose Go to execute. Material item displays.

6 Select Material Item Check the material item, and choose Edit in the upper right.

7 Edit PIRs On the Edit PIRs screen, enter quantities per period, for example:
● PIR: 200 for next 12 periods
● Version is Active: YES

8 Save PIRs Draft Choose Save at bottom right. The PIRs are saved.

9 Repeat Steps Go back and repeat steps 4–8 for TG0012. In step 7, enter quantities per period, for example: PIR: 1000 for next 12
periods

4.2 Monitor Material Coverage

4.2.1 Run Material Requirements Planning (MRP)

Test Administration

Customer project: Fill in the project-specific parts.

Material Requirements Planning (J44_GB)


Test Procedure PUBLIC 22
Test Case ID <X.XX> Testing Date:

Tester Name: Duration:

Business Role(s): Responsibility: <State the Service Provider, Customer or Joint Service Provider and Customer>

Purpose

This process step shows you how to start MRP run for both material with scheduling agreement and material without scheduling agreement.

Procedure

Test Step Test Step Name Instruction Expected Result Pass / Fail /
# Comment

1 Log On Log on to the SAP Fiori launchpad as a Material Planner - The SAP Fiori launchpad displays.
External Procurement.

2 Access the App Open Monitor Material Coverage (F2101A). The Monitor Material Coverage (F2101A) screen displays.

3 Select Material and Show Shortages In the Materials tab, enter the following entries and choose The Material Details screen displays.
Go.
Material: TG0011
Material: TG0012
Select 2 filtered rows and choose Manage Materials.

4 Start MRP Run for Material without Choose MaterialTG0011 on left Materials screen. The MRP run in progress notification pop-out first, then MRP Run
Scheduling Agreement On the screen Material Details, choose Start MRP Run. completed notification pop-out.

5 Start MRP Run for Material with Scheduling Repeat step 4 for MaterialTG0012. The MRP run in progress notification pop-out first, then MRP Run
Agreement completed notification pop-out.

Material Requirements Planning (J44_GB)


Test Procedure PUBLIC 23
4.2.2 Evaluate MRP Result

4.2.2.1 Evaluate MRP Result (Purchase Requisitions)

Test Administration

Customer project: Fill in the project-specific parts.

Test Case ID <X.XX> Testing Date:

Tester Name: Duration:

Business Role(s): Responsibility: <State the Service Provider, Customer or Joint Service Provider and Customer>

Purpose

This process step shows you how to evaluate MRP results for material without scheduling agreement.

Procedure

Test Test Step Name Instruction Expected Result Pass / Fail /


Step # Comment

1 Log On Log on to the SAP Fiori launchpad as a Material Planner - External Procurement. The SAP Fiori launchpad displays.

2 Access the App Open Monitor Material Coverage (F2101A).

3 Select Material and Show In the Materials tab, enter the following entry and choose Go. The Material Details screen displays.
Shortages Materil: TG0011
Select the filtered row and choose Manage Materials.

4 Verify Purchase In the Stock/Requirements List, purchase requisitions are shown as MRP results. The MRP has created purchase requisitions that can be used for the
Requisitions that are Look for rows with PurRqs items to check more details. Procurement of Direct Materials test script.
Available

Material Requirements Planning (J44_GB)


Test Procedure PUBLIC 24
Test Test Step Name Instruction Expected Result Pass / Fail /
Step # Comment

You could click PurRqs item, choose Open, and click Purchase Requisition to
display more details for PR.

5 Handover of Purchase Check the PurRqs items with Handover Pending icon and choose Hand Over. Then The icon turns to Handed Over.
Requisition (Optional) choose Yes in the dialog box.

Note If you want to handover more than one purchase requisition at a time, you
could use Hand Over Purchase Requisitions (F4795) app. Refer to relevant
steps at the end of this section.

6 Rescheduling Check In the Stock/Requirements List, the Rescheduling column displays the rescheduling Corresponding actions perform.
(Optional) status of the following MRP Elements.
● PurReq
● Purchase Orders
● Planned Orders
● Production Orders
● Process Orders
If necessary actions can be performed, below Icons in the Rescheduling column are
displayed via pushing buttons. Push the buttons and corresponding actions
perform directly.
● Reschedule in (Bring operation forward if the receipt element lies after the
requirement date)
● Reschedule out (Postpone operation, if the receipt element lies before the
requirement date)
● Plan Process according to schedule
● Cancel Process
● Excess Stock
● Excess in individual segment

7 Check Planning Details In the Shortage Definition dropdown menu, choose MRP Standard, then select The Material Shortage screen displays.
(Optional) Table View. In the Available column, select an exception highlighted with a red View buttons are located in the upper right of the Stock/Requirements List
status
Shortage Definition: MRP Standard
View Button: Table View

Material Requirements Planning (J44_GB)


Test Procedure PUBLIC 25
Test Test Step Name Instruction Expected Result Pass / Fail /
Step # Comment

8 Change Style and Version On the Material Shortage screen, explore the display options (Table view/Chart Go back twice to Monitor Material Coverage - Net and Individual Segments
of the Material Detail List view) by selecting an icon located in the upper right. screen, navigate to row of material: TG0011, click against red/green charts in
Stock Availability column.
The Projected Stock screen displays the Availability per date. You can click
Check Material Coverage to go to the same Material Details list as in the
previous step.

9 Restore MRP group for Log on to the SAP Fiori launchpad as a Master Data Specialist - Product Data. Material TG0011 MRP group is restored.
TG0011 (Optional) Open Change Material (MM02).
Make the following entry and press Enter:
● Material: TG0011
On the Change Material (Initial Screen), in the Select View(s) dialog box, choose
MRP 1 and choose Continue (Enter) icon.
In the Organization Levels dialog box, make the following entry, and choose
Continue (Enter) icon:
● Plant: 1110
On the General Data tab, make the following entry and choose Save:
● MRP Group: <blank>

Hand Over Purchase Requisitions (Optional)

Test Step # Test Step Name Instruction Expected Result Pass / Fail / Comment

1 Log On Log on to the SAP Fiori launchpad as a Material Planner - External Procurement. The SAP Fiori launchpad displays.

2 Access the App Open Hand Over Purchase Requisitions (F4795).

3 Filter Result Choose following entries as filter, and choose Go:


● Status Description: Handover Pending
● Material: TG0011

4 Mass Handover Select the Purchase Requisitions you want, choose Hand Over. Then choose Yes in the dialog box. A message appears: Handover was successful

Material Requirements Planning (J44_GB)


Test Procedure PUBLIC 26
4.2.2.2 Evaluate MRP Result (Delivery Schedule)

Test Administration

Customer project: Fill in the project-specific parts.

Test Case ID <X.XX> Testing Date:

Tester Name: Duration:

Business Role(s): Responsibility: <State the Service Provider, Customer or Joint Service Provider and Customer>

Purpose

This process step shows you how to evaluate MRP results for material with scheduling agreement.

Procedure

Test Test Step Name Instruction Expected Result Pass / Fail /


Step # Comment

1 Log On Log on to the SAP Fiori Launchpad as a Material Planner - External The SAP Fiori launchpad displays.
Procurement.

2 Access the App Open Monitor Material Coverage (F2101A).

3 Select Material and In the Materials tab, enter the following entry and choose Go. The Material Details screen displays.
Show Shortages Material: TG0012
Select the filtered row and choose Manage Materials.

4 Verify Schedule Lines In the Stock/Requirements List, the MRP results show as schedule lines. The MRP created schedule lines.
that are Available Look for rows with SchLne items to show more details. You could click SchLne item, choose Open…, and click Delivery Schedule / Scheduling
Agreement to display more details.
If you click Delivery Schedule, the screen Display Sch. Agmt Schedule: Item Overview
shows, choose schedule agreement item and then click Delivery Schedule to display
delivery schedule information.

Material Requirements Planning (J44_GB)


Test Procedure PUBLIC 27
Test Test Step Name Instruction Expected Result Pass / Fail /
Step # Comment

If you click Scheduling Agreement, the screen Display Scheduling Agreement: Item
Overview shows.

5 Check Delivery Schedule Click Delivery Schedule on the bottom of screen to view Delivery Schedule. The screen Scheduling Agreement Delivery Schedule showed.
Button The SchLne items display with deviation chart and quantity.

6 Check Planning Details In the Shortage Definition dropdown menu, choose MRP Standard, then The Material Shortage screen displays.
(Optional) select the Table View button. In the Available column, select an exception View buttons are located in the upper right of the Stock/Requirements List
highlighted with a red status
Shortage Definition: MRP Standard
View Button: Table View

7 Change Style and Version On the Material Shortage screen, explore the display options (Table Go back twice to Monitor Material Coverage - Net and Individual Segments screen,
of the Material Detail List view/Chart view) by selecting an icon located in the upper right. navigate to row of material: TG0012, click against red/green charts in Stock
Availability column.
The Projected Stock screen displays the Availability per date. In the button line, you
can click Check Material Coverage. You would go to the same Material Details list as in
the previous step.

4.3 Display MRP Run Master Data Issues

Test Administration

Customer project: Fill in the project-specific parts.

Test Case ID <X.XX> Testing Date:

Tester Name: Duration:

Business Role(s): Responsibility: <State the Service Provider, Customer or Joint Service Provider and Customer>

Purpose

This process step shows you how to check MRP Run Master Data Issues.

Material Requirements Planning (J44_GB)


Test Procedure PUBLIC 28
Procedure

Test Step # Test Step Name Instruction Expected Result Pass / Fail / Comment

1 Log On Log on to the SAP Fiori launchpad as a Material Planner - External Procurement. The SAP Fiori launchpad displays.

2 Access the App Open Display MRP Master Data Issues (F1425A)

3 Check the Issues Select the issue to display the details. If there are any issues, choose the issue to display the details of the error.

4.4 Display MRP Run Key Figures

Test Administration

Customer project: Fill in the project-specific parts.

Test Case ID <X.XX> Testing Date:

Tester Name: Duration:

Business Role(s): Responsibility: <State the Service Provider, Customer or Joint Service Provider and Customer>

Purpose

This process step shows you how to check the key figures of the MRP run.

Procedure

Test Step # Test Step Name Instruction Expected Result Pass / Fail / Comment

1 Log On Log on to the SAP Fiori launchpad as a Material Planner - External Procurement. The SAP Fiori launchpad displays.

2 Access the App Open Display MRP Key Figures (F1426). The Display MRP Key Figures list displays.

Material Requirements Planning (J44_GB)


Test Procedure PUBLIC 29
Test Step # Test Step Name Instruction Expected Result Pass / Fail / Comment

3 Select MRP Run Open the log with name Material Requirements Planning (MRP). The details of MRP run displays.
Select the row with your user and the specific log name, i. e. Material Requirements Planning (MRP) job description.

4.5 Time-dependent Safety Stock Levels

4.5.1 Time-dependent Safety Stock

4.5.1.1 Maintain MRP Safety Stock Method in Material

Test Administration

Customer project: Fill in the project-specific parts.

Test Case ID <X.XX> Testing Date:

Tester Name: Duration:

Business Role(s): Responsibility: <State the Service Provider, Customer or Joint Service Provider and Customer>

Purpose

This process step shows you how to maintain MRP safety stock method in material master data.

Material Requirements Planning (J44_GB)


Test Procedure PUBLIC 30
Procedure

Test Step Test Step Name Instruction Expected Result Pass / Fail /
# Comment

1 Log On Log on to the SAP Fiori launchpad as a Master Data Specialist - Product Data. The SAP Fiori launchpad displays.

2 Access the App On the Home screen, click menu Master data – Products, then click the tile Manage Product The Manage Product Master Data standard selection
Master Data. screen displays.

3 Select Material In the Standard (selection) tab, enter the following entries and choose Go: The Material details screen displays.
● Material: TG0099
● In the Products tab, Click the line of the material TG0099.

4 Select Plant In TG009’s details view, click the menu plant. The Material in Plant 1110 details displays.
In the Plants tab, Click the line of the plant 1110.

5 Maintain MRP safety stock Click Edit button to switch to Edit mode. Then go to menu MRP Data > Lot size Data. The MRP safety stock method is assigned in material
method Go to the Lot size data tab, then in the field MRP safety stock Method, assign Time- master data.
dependent Safety stock.
Click Apply, then click Save.

4.5.1.2 Maintain Time-Dependent Safety Stock

Test Administration

Customer project: Fill in the project-specific parts.

Test Case ID <X.XX> Testing Date:

Tester Name: Duration:

Business Role(s): Responsibility: <State the Service Provider, Customer or Joint Service Provider and Customer>

Material Requirements Planning (J44_GB)


Test Procedure PUBLIC 31
Purpose

This process step shows you how to maintain Time-Dependent safety stock for material TG0099, which is assigned MRP safety stock method Time-dependent safety stock.

Procedure

Test Test Step Name Instruction Expected Result Pass / Fail /


Step # Comment

1 Log On Log on to the SAP Fiori launchpad as a Material Planner - External Procurement. The SAP Fiori launchpad displays.

2 Access the App On the Home screen, Click menu Material Planning, then click the tile Maintain Time-Dependent stock levels. The Maintain Time-Dependent stock levels
screen displays.

3 Select Material In the Standard (selection) tab, enter the following entries and choose Go: The Time-Dependent stock level details
● Material: TG0099 screen displays on the right side.

● In the Materials tab, Click the line of the material TG0099.

4 Maintain Validity In the Validity Intervals view, click the button Add interval for the first interval: Time-Dependent safety stock intervals are
Intervals In the Add New Validity Interval screen that pops up: enter today’s date in the field Date From. Then Click the button maintained.
Add and confirm any information. (Noted that the first interval must be from today).
Click the button Add interval for the second interval:
In the Add New Validity Interval screen that pops up: enter beginning of next Month in the field Date From; enter
100 in the field Safety Stock; Then Click the button Add and confirm any information.
Click the button Add interval for the third interval:
In the Add New Validity Interval screen that pops up: enter beginning of Month after in the field Date From;
enter 150 in the field Safety Stock; Then Click the button Add and confirm any information.

4.5.1.3 Check Material Coverage

Test Administration

Customer project: Fill in the project-specific parts.

Material Requirements Planning (J44_GB)


Test Procedure PUBLIC 32
Test Case ID <X.XX> Testing Date:

Tester Name: Duration:

Business Role(s): Responsibility: <State the Service Provider, Customer or Joint Service Provider and Customer>

Purpose

This process step shows you the Stock/Requirement List of TG0099 before and after running MRP, so that the functionality of Time-dependent safety stock is demonstrated.

Procedure

Test Test Step Name Instruction Expected Result Pass / Fail /


Step # Comment

1 Log On Log on to the SAP Fiori launchpad as a Material Planner - External Procurement. The SAP Fiori launchpad displays.

2 Access the App Open Check Material Coverage (F0251). The Check Material Coverage screen
displays.

3 Select Material AND In the Find Material dialog box, enter the following entries and choose OK. The Material Details screen displays.
● Material: TG0099
● Plant: 1110

4 Check the Stock/Requirement As a result of safety stock you input 2 validity intervals, then you can see 2 requirments with MRP element SfyReq: MRP element for Safety stock displays.
List before Run MRP The quantity of the first SfyReq is 100. The quantity of the second SfyReq is 50. In this case, the total safety stock in
the second interval is 100+50=150. This number matches the input in the second interval.

5 Run MRP to Create Purchase Choose Start MRP Run at the bottom right. The MRP run in progress notification first
Requisition pops up, then MRP Run completed
notification pops up.

6 Evaluate the Purchase If supply cannot cover requirement, MRP will generate Purchase Requisition. You can evaluate the MRP proposed MRP result is evaluated and testing
Requisition and delete them Purchase Requisition regarding scheduling and quantity. environment is cleaned up.
For testing purpose, you can choose the Edit button and delete them. As till now the sub-process for method Time-
dependent safety stock is completed, TG0099 can be reused in other sub-process.

Material Requirements Planning (J44_GB)


Test Procedure PUBLIC 33
4.5.2 Time-dependent Days of Supply

4.5.2.1 Maintain MRP Safety Stock Method in Material

Test Administration

Customer project: Fill in the project-specific parts.

Test Case ID <X.XX> Testing Date:

Tester Name: Duration:

Business Role(s): Responsibility: <State the Service Provider, Customer or Joint Service Provider and Customer>

Purpose

This process step shows you how to maintain MRP safety stock method in material master data.

Procedure

Test Step Test Step Name Instruction Expected Result Pass / Fail /
# Comment

1 Log On Log on to the SAP Fiori launchpad as a Master Data Specialist - Product Data. The SAP Fiori launchpad displays.

2 Access the App On the Home screen, click menu Master data – Products, then click the tile Manage Product The Manage Product Master Data standard selection
Master Data. screen displays.

3 Select Material In the Standard (selection) tab, enter the following entries and choose Go: The Material details screen displays.
● Material: TG0099
● In the Products tab, Click the line of the material TG0099.

4 Select Plant In TG009’s details view, click the menu plant. The Material in Plant 1110 details displays.
In the Plants tab, Click the line of the plant 1110.

Material Requirements Planning (J44_GB)


Test Procedure PUBLIC 34
Test Step Test Step Name Instruction Expected Result Pass / Fail /
# Comment

5 Maintain MRP safety stock Click Edit button to switch to Edit mode. Then go to menu MRP Data > Lot size Data. The MRP safety stock method is assigned in material
method Go to the Lot size data tab, then in the field MRP safety stock Method, assign Time- master data.
dependent Safety stock.
Click Apply, then click Save.

4.5.2.2 Maintain Time-Dependent Days of Supply

Test Administration

Customer project: Fill in the project-specific parts.

Test Case ID <X.XX> Testing Date:

Tester Name: Duration:

Business Role(s): Responsibility: <State the Service Provider, Customer or Joint Service Provider and Customer>

Purpose

This process step shows you how to maintain Time-Dependent Days of Supply for material TG0099, which has assigned MRP safety stock method Time-dependent safety stock.

Procedure

Test Test Step Name Instruction Expected Result Pass / Fail /


Step # Comment

1 Log On Log on to the SAP Fiori launchpad as a Material Planner - External Procurement. The SAP Fiori launchpad displays.

2 Access the App On the Home screen, Click the menu Production Planning, then click the tile Maintain The Maintain Time-Dependent Stock Levels screen displays
Time-Dependent Stock Levels.

Material Requirements Planning (J44_GB)


Test Procedure PUBLIC 35
Test Test Step Name Instruction Expected Result Pass / Fail /
Step # Comment

3 Select Material In the Standard (selection) tab, enter the following entries and choose Go: The details screen displays on the right side.
● Material: TG0099
In the Materials tab, click the line of the material TG0099.

4 Maintain In the Validity Intervals view, you can see the invervals you created in step Check Time-Depenent intervals maintained:
Validity Material Coverage [page ] 33, which can be reused. *In MRP, the PIR quantity in one interval is considered as Daily consumption,
Intervals Click Edit button to switch to Edit mode. Remove the safety stock quantity. Because Safety stock level = daily consumption * Safety DOS
the safety stock Method is changed to Days of Supply, the safety stock does not take
Target stock level = daily consumption * Target DOS
effect here.
In one interval, only if net supply (target stock level in last interval – PIR in current
For the first interval:
interval) < safety stock level, MRP will trigger replenishement to build up target
Keep all fields blank. stock level.
For the second interval:
Input 1 in the field Safety Dos. Input 2 in the field Target Dos.
For the third interval:
Input 1 in the field Safety Dos. Input 3 in the field Target Dos.
Click the Save button.

4.5.2.3 Manage PIRs for Material TG0099

Test Administration

Customer project: Fill in the project-specific parts.

Test Case ID <X.XX> Testing Date:

Tester Name: Duration:

Business Role(s): Responsibility: <State the Service Provider, Customer or Joint Service Provider and Customer>

Material Requirements Planning (J44_GB)


Test Procedure PUBLIC 36
Purpose

This process step shows you how to create the planned independent requirements directly for material TG0099.

Procedure

Test Test Step Name Instruction Expected Result Pass / Fail /


Step # Comment

1 Log On Log on to the SAP Fiori launchpad as a Material Planner - External Procurement. The SAP Fiori launchpad displays.

2 Access the App Open Maintain PIRs (F3445).

3 Check Default Area of On the Maintain PIRs screen, choose your user name and choose the App Settings icon. On
Responsibility the MRP Settings screen, choose Area of Responsibility.
Check if only the following entry is assigned:
Plant 1 GB / 002 (MRP Controller: 002)
Choose AOR status button of this entry if not assigned, choose AOR status button of the
corresponding entry to unassign any other entry then choose Back.

4 Select On the Maintain PIRs screen, make the following entries:


● Plant: 1110
● Period Indicator: Monthly(M)
● Version Active: Yes, No
● Material: TG0099

5 Filter Result Choose Go to execute. Material item displays.

6 Check Material Item Select the line with TG0099.


Check the material item, if a PIR for a future data already exists, clear it.

7 Edit PIRs Choose Edit in the upper right. On the Edit PIRs screen, enter quantities per period, for PIR for a data in the future is entered. The PIRs period should
example: match the interval you maintained in previous step.
● PIR: 100 for next period in the future
● PIR: 200 for the period after
● Version is Active: YES

8 Save PIRs Draft Choose Save on bottom right. The PIRs are saved.

Material Requirements Planning (J44_GB)


Test Procedure PUBLIC 37
4.5.2.4 Check Material Coverage

Test Administration

Customer project: Fill in the project-specific parts.

Test Case ID <X.XX> Testing Date:

Tester Name: Duration:

Business Role(s): Responsibility: <State the Service Provider, Customer or Joint Service Provider and Customer>

Purpose

This process step shows you the Stock/Requirement List of TG0099 before and after running MRP, so that the functionality of Time-dependent Days of supply is demonstrated.

Procedure

Test Test Step Name Instruction Expected Result Pass / Fail /


Step # Comment

1 Log On Log on to the SAP Fiori launchpad as a Material Planner - External Procurement. The SAP Fiori launchpad displays.

2 Access the App Open Check Material Coverage (F0251). The Check Material Coverage screen displays.

3 Select Material AND In the Find Material dialog box, enter the following entries and choose OK. The Material Details screen displays.
● Material: TG0099
● Plant: 1110

4 Check the Stock/Requirement List The PIRs you input in the previous step is displayed as requirements in stock/requirement list.
before Run MRP

Material Requirements Planning (J44_GB)


Test Procedure PUBLIC 38
Test Test Step Name Instruction Expected Result Pass / Fail /
Step # Comment

5 Run MRP to Create Purchase Choose Start MRP Run at the bottom right. The MRP run in progress notification first pops up, then
Requisition MRP Run completed notification pops up.

6 Evaluate the Purchase Requisition Regarding the data input in previous steps:
and delete them in interval next month: target stock level 100*2= 200 is built up.
In interval the month after next month: net supply = 200-200=0 < stock level 1*200=200 MRP,
which proposes replenishment to build up target stock level 200*3=600

4.5.2.5 Reset Material Master Data

Test Administration

Customer project: Fill in the project-specific parts.

Test Case ID <X.XX> Testing Date:

Tester Name: Duration:

Business Role(s): Responsibility: <State the Service Provider, Customer or Joint Service Provider and Customer>

Purpose

This process step shows you how to reset material master data to set up a clean environment for the succeeding testing.

Procedure

Test Test Step Name Instruction Expected Result Pass / Fail /


Step # Comment

1 Log On Log on to the SAP Fiori launchpad as a Master Data Specialist - Product The SAP Fiori launchpad displays.
Data.

Material Requirements Planning (J44_GB)


Test Procedure PUBLIC 39
Test Test Step Name Instruction Expected Result Pass / Fail /
Step # Comment

2 Access the App On the Home screen, click the menu Master data – Products, then click The Manage Product master data Standard selection screen displays.
the tile Manage Product Master data.

3 Select Material In the Standard (selection) tab, enter the following entries and choose The Material details screen displays.
Go:
● Material: TG0099
In the Products tab, click the line of the material TG0099.

4 Select Plant In the TG0099 details view, click the menu plant. The Material in Plant 1110 details displays.
In the Plants tab, click the line of the plant 1110

5 Maintain MRP safety Click Edit button to switch to Edit mode. Then go to menu MRP Data > Once MRP safety stock method is removed from material master data, the interval
stock method Lot size Data. maintained in the previous steps will not be considered in MRP.
Go to the Lot size data tab, then in the field MRP safety stock Method,
assign Time-dependent Safety stock.
Click Apply, then click Save.

4.6 Material Exception (Optional)

4.6.1 Clear Initial Stock

Test Administration

Customer project: Fill in the project-specific parts.

Test Case ID <X.XX> Testing Date:

Tester Name: Duration:

Business Role(s): Responsibility: <State the Service Provider, Customer or Joint Service Provider and Customer>

Material Requirements Planning (J44_GB)


Test Procedure PUBLIC 40
Purpose

This process step shows you how to ensure TG0099’s stock is empty.

Procedure

Test Step # Test Step Name Instruction Expected Result Pass / Fail / Comment

1 Log On Log on to the SAP Fiori launchpad as an Inventory Manager. The SAP Fiori launchpad displays.

2 Access the App Open Manage Stock (F1062).. The Manage Stock (F1062). screen displays.

3 Specify Material Make the following entries and choose Enter: The Stock overview for the product displays.
● Material: TG0099
● Plant: 1110

4 Clear Stock If current stock of TG0099 is zero, please skip this step. Unrestricted-Use Stock is 0.000 PC.
On the screen, you can check Storage Location, Unrestricted-Use Stock, Blocked Stock, Stock in Quality Inspection.
Choose the Unrestricted - Use Stock icon.
● Stock Change: Scrapping
● Quantity: <=“Current Quantity“>
● Cost Center: <Cost Center>, for example, 11101301
Choose Post.

4.6.2 Clear Existing Purchase Requisitions

Test Administration

Customer project: Fill in the project-specific parts.

Test Case ID <X.XX> Testing Date:

Tester Name: Duration:

Business Role(s): Responsibility: <State the Service Provider, Customer or Joint Service Provider and Customer>

Material Requirements Planning (J44_GB)


Test Procedure PUBLIC 41
Purpose

This process step shows you how to ensure TG0099’s purchase requisitions is empty.

Procedure

Test Step # Test Step Name Instruction Expected Result Pass / Fail / Comment

1 Log On Log on to the SAP Fiori launchpad as a Material Planner - External Procurement. The SAP Fiori launchpad displays.

2 Access the App Open Check Material Coverage (F0251) The Find Material screen displays.

3 Select Material and Show Shortages In the Find Material dialog box, enter the following entries and choose OK. The Material Details screen displays.
● Material: TG0099
● Plant: 1110
● Shortage definition: MRP Standard

4 Clear Purchase Requisitions Delete existing PurRqs. There is no purchase requisitions.

4.6.3 Manage PIRs for Material TG0099

Test Administration

Customer project: Fill in the project-specific parts.

Test Case ID <X.XX> Testing Date:

Tester Name: Duration:

Business Role(s): Responsibility: <State the Service Provider, Customer or Joint Service Provider and Customer>

Purpose

This process step shows you how to create the planned independent requirements directly for material TG0099.

Material Requirements Planning (J44_GB)


Test Procedure PUBLIC 42
Procedure

Test Step Test Step Name Instruction Expected Result Pass / Fail /
# Comment

1 Log On Log on to the SAP Fiori launchpad as a Material Planner - External Procurement. The SAP Fiori launchpad
displays.

2 Access the App Open Maintain PIRs (F3445).

3 Check Default Area of On the Maintain PIRs screen, choose your user name and choose the App Settings icon. On the MRP Settings screen,
Responsibility choose Area of Responsibility.
Check if only the following entry is assigned:
Plant 1 GB / 001 (MRP Controller 001)
Choose AOR status button of this entry if not assigned, choose AOR status button of the corresponding entry to unassign
any other entry then choose Back.

4 Select On the Maintain PIRs (F3445) screen, make the following entries:
● Plant: 1110
● Period Indicator: Monthly(M)
● Version Active: Yes, No
● Material: TG0099

5 Filter Result Choose Go to execute. Material item displays.

6 Check Material Item Select the line with TG0099.


Check the material item, if a PIR for a future data already exists, skip the following steps. If not, continue the steps.

7 Edit PIRs Choose Edit in the upper right. On the Edit PIRs screen, enter quantities per period, for example: PIR for a data in the future is
● PIR: 100 for next period in the future entered

● Version is Active: YES

8 Save PIRs Draft Choose Save on bottom right. The PIRs are saved.

Material Requirements Planning (J44_GB)


Test Procedure PUBLIC 43
4.6.4 Run Material Requirements Planning (MRP) and Firm Purchase Requisition

Test Administration

Customer project: Fill in the project-specific parts.

Test Case ID <X.XX> Testing Date:

Tester Name: Duration:

Business Role(s): Responsibility: <State the Service Provider, Customer or Joint Service Provider and Customer>

Purpose

This process step shows you how to start MRP run for material with scheduling agreement.

Procedure

Test Test Step Name Instruction Expected Result Pass / Fail /


Step # Comment

1 Log On Log on to the SAP Fiori launchpad as a Material Planner - External Procurement. The SAP Fiori launchpad displays.

2 Access the App Open Check Material Coverage (F0251). The Check Material Coverage (F0251) screen displays.

3 Select Material AND In the Find Material dialog box, enter the following entries and choose OK. The Material Details screen displays.
● Material: TG0099
● Plant: 1110
● Shortage definition: MRP Standard

4 Run MRP to Create Purchase Choose Start MRP Run at the bottom right. The MRP run in progress notification pop-out first, then MRP Run
Requisition completed notification pop-out.

5 Firm Purchase Requisition Check the generated PurRqs. Select Edit from Action dropdown list, and change The Purchase requisition has been changed notification pop-out first,
the delivery date to firm it. then the PurRqs are locked.

Material Requirements Planning (J44_GB)


Test Procedure PUBLIC 44
4.6.5 Increase Stock for TG0099

Test Administration

Customer project: Fill in the project-specific parts.

Test Case ID <X.XX> Testing Date:

Tester Name: Duration:

Business Role(s): Responsibility: <State the Service Provider, Customer or Joint Service Provider and Customer>

Purpose

This process step shows you how to increase stock and make it more than PIR.

Procedure

Test Step Test Step Instruction Expected Result Pass / Fail /


# Name Comment

1 Log On Log on to the SAP Fiori launchpad as an Inventory Manager. The SAP Fiori launchpad displays.

2 Access the Open Manage Stock (F1062).. The Manage Stock (F1062). screen
App displays.

3 Specify Make the following entries and choose The Stock overview for the product
Material Enter: displays.

● Material: TG0099
● Plant: 1110

4 Increase Stock Select the Unrestricted - Use Stock icon to add the initial stock for your chosen storage location (For example, Raw mat. Unrestricted-Use Stock is greater than
stoloc 171A), and choose Post. PIR.
● Quantity: <For example, 200>
● Document Data: Today

Material Requirements Planning (J44_GB)


Test Procedure PUBLIC 45
Test Step Test Step Instruction Expected Result Pass / Fail /
# Name Comment

● Posting Date: Today

4.6.6 Detect MRP Situations

Test Administration

Customer project: Fill in the project-specific parts.

Test Case ID <X.XX> Testing Date:

Tester Name: Duration:

Business Role(s): Responsibility: <State the Service Provider, Customer or Joint Service Provider and Customer>

Purpose

This process step shows you how to run job for MRP material exception.

Procedure

Test Test Step Name Instruction Expected Result Pass / Fail /


Step # Comment

1 Log On Log on to the SAP Fiori launchpad as a Material Planner - The SAP Fiori launchpad displays.
External Procurement.

2 Access the App Open Detect MRP Situations (F3853) The Application Jobs screen displays.

Note If the App is not available by default, please use the App
finder to add it to the SAP Fiori launchpad.

Material Requirements Planning (J44_GB)


Test Procedure PUBLIC 46
Test Test Step Name Instruction Expected Result Pass / Fail /
Step # Comment

3 Enter Basic Parameters On the Application Jobs screen, choose Create and make the
for New Job following entries:
For 1. Template Selection section:
● Job Template: MRP Situation Handling Template
● Job Name: <: MRP Situation Handling
for TG0099>
Choose Step 2.
For 2. Scheduling Options section:
● Start Immediately: <select>
● Choose Define Recurrence Pattern.
On the Scheduling Information screen, make the following
entries:
● Start Immediately: X
● Recurrence Pattern: Single Run
Choose OK.
Choose Step 3.
For 3. Parameters section:
● Material: TG0099
● MRP Controller: 001
● Plant: 1110
Choose Check at the bottom right, then choose Schedule.

4 Refresh Application To check the status of the job you created, choose Go on the top The Application Jobs table is refreshed.
Jobs List right section of the screen.

5 Verify the Job Results To see the outcome of the job, choose the icon in Results A Documents screen should list the purchase requisition created in chapter Run Material
column. Requirements Planning (MRP) and Firm Purchase Requisition [page ] 45 for cancellation.

4.6.7 Check and React to Material Exception

Test Administration

Customer project: Fill in the project-specific parts.

Material Requirements Planning (J44_GB)


Test Procedure PUBLIC 47
Test Case ID <X.XX> Testing Date:

Tester Name: Duration:

Business Role(s): Responsibility: <State the Service Provider, Customer or Joint Service Provider and Customer>

Purpose

By the prerequisite step, notification will be automatically sent to responsible team members. The detection process is automatically triggered by the system on a regular basis based on the Batch
Job Scheduling parameters maintained in section Create Situation Types and indicates material exception situations to the material planner (usually within one hour). This process step shows you
how to check and react to material exception.

Procedure

Test Test Step Name Instruction Expected Result Pass / Fail /


Step # Comment

1 Log On Log on to the SAP Fiori launchpad as a Material Planner - External Procurement. The SAP Fiori launchpad displays.

2 Check Notifications On the home screen, choose the Notifications icon in the upper right corner. The following notification displays:
Cancel process: PurchReq 1xxxxxx-000010
Material TG0099 Plant 1110.
It enables the material planner to proactively
take further action.

3 Navigate to Manage Choose the detailed notification line Cancel process: PurchReq 1xxxxxx-000010 The Manage Material Coverage screen for
Material Coverage App MaterialTG0099Plant1110., it navigates to Manage Material Coverage screen. discontinued product displays.

4 Delete Purchase Requisition On the Manage Material Coverage screen, select Delete from Action dropdown list. Then choose Delete in the The purchase requisition detected by the MRP
dialog box. Material Exception job disappears.

5 Dismiss the MRP Material Choose Close Situation in the yellow notification box and pick a reason for dismissing the situation. Choose The situation has been dismissed.
Exception Confirm.

6 Close the Notification On the home screen, choose the Notifications icon in the upper right corner and choose the cross sign in the The notification for the resolved MRP Material
Message upper right corner to close the notification message. Exception disappears from the list.
(You may need to repeat this step for notifications on the same purchase requisition and material issued for
days earlier than today.)

Material Requirements Planning (J44_GB)


Test Procedure PUBLIC 48
4.6.8 Reduce Stock for TG0099

Test Administration

Customer project: Fill in the project-specific parts.

Test Case ID <X.XX> Testing Date:

Tester Name: Duration:

Business Role(s): Responsibility: <State the Service Provider, Customer or Joint Service Provider and Customer>

Purpose

This process step shows you how to decrease stock and make it less than PIR.

Procedure

Test Step # Test Step Name Instruction Expected Result Pass / Fail / Comment

1 Log On Log on to the SAP Fiori launchpad as an Inventory Manager. The SAP Fiori launchpad displays.

2 Access the App Open Manage Stock (F1062).. The Manage Stock (F1062). screen displays.

3 Specify Material Make the following entries and choose Enter: The Stock overview for the product displays.
● Material: TG0099
● Plant: 1110

4 Reduce Stock On the screen, you can check Storage Location, Unrestricted-Use Stock, Blocked Stock, Stock in Quality Inspection. Unrestricted-Use Stock is less than PIR.
Choose the Unrestricted - Use Stock icon,
● Stock Change: Scrapping
● Quantity: <= "Current Quantity"> (make it less than PIR)
● Cost Center: <Cost Center>, for example, 11101301
Choose Post.

Material Requirements Planning (J44_GB)


Test Procedure PUBLIC 49
4.7 MRP Change Request (Optional)

4.7.1 Create Purchase Order

Purpose

This process step shows you how to create a purchase order for TG0099.

Procedure

Test Test Step Name Instruction Expected Result Pass / Fail /


Step # Comment

1 Log On Log on to the SAP Fiori launchpad as a Material Planner - External Procurement. The SAP Fiori launchpad
displays.

2 Access the App Open Check Material Coverage (F0251). The Find Material screen
displays.

3 Select Material and Show In the Find Material dialog box, enter the following entries and choose OK: The Material Details
Shortages ● Material: TG0099 screen displays.

● Plant: 1110
● Shortage definition: MRP Standard

4 Create a Purchase Requisition Under Stock / Requirements List, choose Create Order, enter the following entries and choose Create. Purchase requisition has
● Receipt Quantity: 100 PC been created.

● Availability Date: <Current + 2 Month>


● Source of Supply for Order: <Info Record with supplier 11300001>

5 Convert the Purchase Requisition Check the PurRqs items and choose Action button: Convert in the dropdown list. Check the information, then choose OK in the Purchase requisition has
into Purchase Order pop-up dialog: Change Purchase Requisition XXXXXXXX-XX. Note down this purchase order number. been converted.

Material Requirements Planning (J44_GB)


Test Procedure PUBLIC 50
4.7.2 Manage PIRs for Material TG0099

Test Administration

Customer project: Fill in the project-specific parts.

Test Case ID <X.XX> Testing Date:

Tester Name: Duration:

Business Role(s): Responsibility: <State the Service Provider, Customer or Joint Service Provider and Customer>

Purpose

This process step shows you how to create the planned independent requirements directly for material TG0099.

Procedure

Test Step Test Step Name Instruction Expected Result Pass / Fail /
# Comment

1 Log On Log on to the SAP Fiori launchpad as a Material Planner - External Procurement. The SAP Fiori launchpad
displays.

2 Access the App Open Maintain PIRs (F3445).

3 Check Default Area of On the Maintain PIRs screen, choose your user name and choose the App Settings icon. On the MRP Settings screen,
Responsibility choose Area of Responsibility.
Check if only the following entry is assigned:
Plant 1 GB / 001 (MRP Controller 001)
Choose AOR status button of this entry if not assigned, choose AOR status button of the corresponding entry to unassign
any other entry then choose Back.

4 Select On the Maintain PIRs (F3445) screen, make the following entries:
● Plant: 1110
● Period Indicator: Monthly(M)

Material Requirements Planning (J44_GB)


Test Procedure PUBLIC 51
Test Step Test Step Name Instruction Expected Result Pass / Fail /
# Comment

● Version Active: Yes, No


● Material: TG0099

5 Filter Result Choose Go to execute. Material item displays.

6 Check Material Item Select the line with TG0099.


Check the material item, if a PIR for a future data already exists, skip the following steps. If not, continue the steps.

7 Edit PIRs Choose Edit in the upper right. On the Edit PIRs screen, clear the existing PIRs and enter: PIR for a data in the future is
● PIR: 100 <for current + 1 Month> entered.

● Version is Active: YES

8 Save PIRs Draft Choose Save on bottom right. The PIRs are saved.

4.7.3 MRP Rescheduling Check

Test Administration

Customer project: Fill in the project-specific parts.

Test Case ID <X.XX> Testing Date:

Tester Name: Duration:

Business Role(s): Responsibility: <State the Service Provider, Customer or Joint Service Provider and Customer>

Purpose

This process helps you to identify the MRP exceptions, and shows you how to schedule MRP rescheduling check to collect MRP rescheduling information.

Material Requirements Planning (J44_GB)


Test Procedure PUBLIC 52
Procedure

Test Test Step Name Instruction Expected Result Pass / Fail /


Step # Comment

1 Log On Log on to the SAP Fiori launchpad as a Material Planner - External Procurement. The SAP Fiori launchpad displays.

2 Access the App Open Schedule MRP Rescheduling Checks (F5417) The Application Jobs screen displays.

3 Enter Parameters for On the Application Jobs screen, choose Create and make the following entries:
New Job For 1. Template Selection section:
● Job Template: MRP Rescheduling Checks
● Job Name: MRP Rescheduling Checks for TG0099
Choose Step 2.
For 2. Scheduling Options section:
● Start Immediately: <select>
● Recurrence Pattern: Single Run
Choose Step 3.
For 3. Parameters section:
● MRP Plant: 1110
● MRP Controller: 001
● Material: TG0099
Choose Check at the bottom right, then choose Schedule.

4 Check Result Choose Go to refresh the page. When the Status shows Finished, click the icon in On the Document (ID xxxxxxxxx) screen, item with Material: TG0099,
the column Results to see the result. Exception Message: Reschedule in appears.

Note Related APIs and Communication Arrangements


If you want to verify that the filtering of the SOAP outbound service MRP Change Request Message Outbound is working as intended, or to verify that one SOAP message does contain the
MRP change requests for one supplier of one company code, please utilize API for integration scenario. To set up relevant communication arrangement, refer to APIs and Communication
Arrangements for Scope Items in SAP S/4HANA Cloud.
For details regarding the interfaces, please access the SAP Best Practice Explorer for SAP S/4HANA cloud and navigate to Accelerators > Implementation > APIs.

Integration Scenario Integration Scenario Name

SAP_COM_0667 Communication arrangement for MRP Change Request Outbound

Material Requirements Planning (J44_GB)


Test Procedure PUBLIC 53
4.7.4 Create and Send MRP Change Requests

Test Administration

Customer project: Fill in the project-specific parts.

Test Case ID <X.XX> Testing Date:

Tester Name: Duration:

Business Role(s): Responsibility: <State the Service Provider, Customer or Joint Service Provider and Customer>

Purpose

This process step shows you how to create and send MRP Change Requests for TG0099.

Procedure

Test Test Step Name Instruction Expected Result Pass / Fail /


Step # Comment

1 Log On Log on to the SAP Fiori launchpad as a Material Planner - External The SAP Fiori launchpad displays.
Procurement.

2 Access the App Open Create MRP Change Requests (F5416) The Create MRP Change Requests screen displays.

3 Select Material and Show Purchase In the Create MRP Change Requests screen, enter the following entry and Purchase Order Schedule Line for TG0099 displays. The Requested
Order Schedule Lines choose Go. Date, Quantity and Request Status are empty.
Material: TG0099

4 Create Change Requests Tick the checkbox in front of the Purchase Order which was created in Change requests for the record created successfully.
pervious step and choose Create Change Requests. The Requested Date and Quantity were updated, and Request Status
become New.

Material Requirements Planning (J44_GB)


Test Procedure PUBLIC 54
4.7.5 Manage Change Requests

Test Administration

Customer project: Fill in the project-specific parts.

Test Case ID <X.XX> Testing Date:

Tester Name: Duration:

Business Role(s): Responsibility: <State the Service Provider, Customer or Joint Service Provider and Customer>

Purpose

This process step shows you how to manually set the MRP Change Request status to "Requested", and how to review the detailed requested MRP Change Requests for TG0099.
If you have already built the communication scenario "SAP_COM_0667: Manufacturing - MRP Change Request Integration", this step can also be done automatically with the app Create MRP
Change Requests (F5416).

Procedure

Test Test Step Name Instruction Expected Result Pass / Fail /


Step # Comment

1 Log On Log on to the SAP Fiori launchpad as a Material Planner - External Procurement. The SAP Fiori launchpad displays.

2 Access the App Open Manage Change Requests (F3406) The Manage Change Requests screen
displays.

3 Search for the Vendor In My Vendors / Contacts list, search for Vendor (Supplier)<11300001>. Change requests under Vendor<11300001>
were listed.

4 Set to Requested Tick the checkbox in front of the Order which was created in pervious step and choose Set to Requested. The Order Item was set to REQUESTED.

5 Review the requested change On the Change Requests table, choose the tab: REQUESTED. Click against the item that you requested in last Change Request Details are listed.
Requests step and review the change request detail.

Material Requirements Planning (J44_GB)


Test Procedure PUBLIC 55
Note Related APIs and Communication Arrangements
If you want to verify that the filtering of the SOAP outbound service MRP Change Request Message Outbound is working as intended, or to verify that one SOAP message does contain the
MRP change requests for one supplier of one company code, please utilize API for integration scenario. To set up relevant communication arrangement, refer to APIs and Communication
Arrangements for Scope Items in SAP S/4HANA Cloud.
For details regarding the interfaces, please access the SAP Best Practice Explorer for SAP S/4HANA cloud and navigate to Accelerators > Implementation > APIs.

Integration Scenario Integration Scenario Name

SAP_COM_0667 Communication arrangement for MRP Change Request Outbound

4.7.6 React to MRP Change Requests based on Vendor’s Response

Test Administration

Customer project: Fill in the project-specific parts.

Test Case ID <X.XX> Testing Date:

Tester Name: Duration:

Business Role(s): Responsibility: <State the Service Provider, Customer or Joint Service Provider and Customer>

Purpose

Suppose you already got the vendor’s response from Ariba. This process step shows you how to react to MRP Change Requests for TG0099 based on vendor’s response.

Procedure

Test Test Step Name Instruction Expected Result Pass / Fail /


Step # Comment

1 Log On Log on to the SAP Fiori launchpad as a Material Planner - External The SAP Fiori launchpad displays.
Procurement.

Material Requirements Planning (J44_GB)


Test Procedure PUBLIC 56
Test Test Step Name Instruction Expected Result Pass / Fail /
Step # Comment

2 Access the App Open Create MRP Change Requests (F5416) The Create MRP Change Requests screen displays.

3 Select Material and Show Purchase In the Create MRP Change Requests screen, enter the following entry Purchase Order Schedule Line for TG0099 displays. The Requested Date,
Order Schedule Lines and choose Go. Quantity and Request Status are empty.
Material: TG0099

4 Navigates to Manage Change Requests Click against the Request Status for the purchase order. The Manage Change Requests screen displays.
Navigates to Manage Change Requests screen.

5 React to Vendor’s Response In the RECEIPT/REQUIREMENT ITEMS List, select one of the vendor's The change request status become: Applied or Discarded.
response:
Pending/ Accepted/ Rejected/ New Proposal.
Assume you got Vendor’s response as Accepted. Choose tab: Accepted
then choose Apply Changes.
If you got vendor’s response as Rejected, choose tab: Rejected then
choose Discard.
You can also enter a New Proposal based on vendor’s response then
choose Apply Changes.
Choose OK in the pop-up dialog: Purchase Order XXXXXXXX-XX will be
changed.

Material Requirements Planning (J44_GB)


Test Procedure PUBLIC 57
5 Appendix

5.1 Process Chains


The process to be tested in this test case is part of a chain of integrated processes.

5.1.1 Preceding Processes


Complete the following business processes and conditions before you start with the test steps:

Process Business Condition

Master Data Maintenance

5.1.2 Succeeding Processes


After completing the activities in this test case, you can continue testing the following business processes:

Process Business Condition

J45 - Procurement of Direct A purchase requisition is created as part of the Material Requirements Planning (J44) test script. This purchase requisition is converted into a purchase order in the Procurement of
Materials Direct Materials (J45) process.

Material Requirements Planning (J44_GB)


Appendix PUBLIC 58
Typographic Conventions

Type Style Description

Example Words or characters quoted from the screen. These include field names, screen titles, pushbuttons labels, menu names, menu paths, and menu options.
Textual cross-references to other documents.

Example Emphasized words or expressions.

EXAMPLE Technical names of system objects. These include report names, program names, transaction codes, table names, and key concepts of a programming language when they
are surrounded by body text, for example, SELECT and INCLUDE.

Example Output on the screen. This includes file and directory names and their paths, messages, names of variables and parameters, source text, and names of installation,
upgrade and database tools.

Example Exact user entry. These are words or characters that you enter in the system exactly as they appear in the documentation.

<Example> Variable user entry. Angle brackets indicate that you replace these words and characters with appropriate entries to make entries in the system.

EXAMPLE Keys on the keyboard, for example, F 2 or E N T E R .

Material Requirements Planning (J44_GB)


Appendix PUBLIC 59
www.sap.com/contactsap

© 2022 SAP SE or an SAP affiliate company. All rights reserved.


No part of this publication may be reproduced or transmitted in any form or
for any purpose without the express permission of SAP SE or an SAP affiliate
company. The information contained herein may be changed without prior
notice.
Some software products marketed by SAP SE and its distributors contain
proprietary software components of other software vendors. National
product specifications may vary.
These materials are provided by SAP SE or an SAP affiliate company for
informational purposes only, without representation or warranty of any
kind, and SAP or its affiliated companies shall not be liable for errors or
omissions with respect to the materials. The only warranties for SAP or SAP
affiliate company products and services are those that are set forth in the
express warranty statements accompanying such products and services, if
any. Nothing herein should be construed as constituting an additional
warranty.
SAP and other SAP products and services mentioned herein as well as their
respective logos are trademarks or registered trademarks of SAP SE (or an
SAP affiliate company) in Germany and other countries. All other product
and service names mentioned are the trademarks of their respective
companies.

See www.sap.com/copyright for additional trademark


information and notices.