PART - A STRUCTURE

ITEM NO.: 804 (1) UNIT: Cubic Meter


DESCRIPTION: EMBANKMENT QUANTITY: 552.42

COMPUTATION OF OUTPUT PER DAY


Manpower/Equipment Requirement
Quantites Manpower/Equipment Activity
Types No. of unit
Required (m3) Output (cu.m/day)Duration (days)
Foreman 1 552.42
Road Grader 1 400 1.00
Road Roller 1 400 1.00
Water Truck 1 0.25

PART - C EARTH WORKS


ITEM NO.: 103 UNIT: Cubic Meter
DESCRIPTION: Structure Excavation QUANTITY: 75.30

Summary of Derived Quantities


Structure Excavation
Wall Footing 75.30 cu.m
Volume = 75.30 cu.m
See Computation on RCBC & Catch Basin
COMPUTATION OF EQUIPMENT OUTPUT PER DAY
Labor Requirement
Quantites Activity
Type of Labor No. of unit Output/Day
Required (m3) Duration (days)
Laborer 6 75.30 18.00 1.00

PART - C EARTH WORKS


ITEM No.: 104 UNIT: Cubic Meter
DESCRIPTION: Embankment QUANTITY: 690.00

Summary of Derived Quantities


Embankment 690
Volume = 690.00 cu.m
See Earthworks for Volume Computation
COMPUTATION OF EQUIPMENT OUTPUT PER DAY
Equipment Requirment
Quantites Activity
Type of Equipment No. of unit Output/Day
Required (m3) Duration (hours)
Road Grader 1 690.00 14
50
Road Roller 1 690.00 14
Water Truck 1 690.00 3.50

PART - D SUBBASE & BASE COURSES


ITEM No.: 200 UNIT: Cubic Meter
DESCRIPTION: Sub-Base Course QUANTITY: 66.00

Summary of Derived Quantities


Sub-Base Course 72.6
Volume = 72.60 cu.m
See Base Course & PCCP for Computation

Case 1: Materials delivered on site (Price of material is high, limited use of equipment)
Case 2: Materials is quarried from a source (Use of additional equipment and lower price of material)

COMPUTATION OF EQUIPMENT OUTPUT PER DAY

Equipment Requirement Case 1 Used


Quantites Activity
Type of Equipment No. of unit Output/Hour
Required Duration (hour)
Road Grader 1 72.60 400 0.50
Road Roller 1 72.60 320 0.50
Water Truck 1 72.60 200 0.50

PART - C CONCRETE STRUCTURE


ITEM No.: 404 UNIT: kgs.
DESCRIPTION: Reinforcing Steel QUANTITY: 1,547.84

Summary of Derived Quantities


Reinforcing Steel
Slab 1227.17 kgs
Footing
Continous Bar 246.67 kgs
Sectional Bar 61.79 kgs
Dowel Bar 12.21 kgs
Volume = 1,547.84 kgs
See RCBC & Catch Basin for Computation

Manpower/ Quantities Duration


Equipment
No. of Unit Output/Day
kgs ( day )
Bar Cutter 1
2880.0 1
Bar Bender 1
1547.84
Steelman 2
1440.0 1
Laborer 8

PART - C CONCRETE STRUCTURE


ITEM No.: 405 UNIT: Cubic Meter
DESCRIPTION: Structural Concrete QUANTITY: 98.82

Summary of Derived Quantities


Structural Concrete
Slab 90.00 cu.m.
Footing 8.82 cu.m.
Volume = 98.82 cu.m.
See RCBC, Catch Basin & RCPC for Computation
For Fabrication, Placing and Dismatling of Forms
Quantities Duration
Manpower No. of Unit Output/Day
cu.m. ( day )
Carpenter 4 98.82
11.2 9
11.2 9
Laborer 8 98.82

For Concreting

Manpower/ Quantities Manpower Duration


Equipment
No. of Unit
l.m. ( Output/Day ) ( day )
One-Bagger Mixer 1
Concrete Vibrator 1
Concrete Saw 1
Foreman 1 98.82 3.5 28
Mason 4
Laborer 8

PART - G DRAINAGE AND SLOPE PROTECTION


ITEM No.: 506 UNIT: Cubic Meter
DESCRIPTION: Stone Masonry QUANTITY: 33.98

Summary of Derived Quantities


Stone Masonry

Stone Masonry 33.98 cu.m


Volume = 33.98 cu.m
See Following Pages for Computation

Crew

Manpower/ Quantities Duration


Equipment
No. Output/Day
cu.m. ( day )

Bagger Mixer 1
Foreman 1 33.98
7.5 5.00
Mason 2
Laborer 8
Note: Excavation Works wil be included to Item 102(2), 3 gangs for Lesser Activity Duration

PART - A EARTH WORKS


ITEM NO.: 103 UNIT: Cubic Meter
DESCRIPTION: Structure Excavation QUANTITY: 0.00

Summary of Derived Quantities


Structure Excavation
Wall Footing 0.00 cu.m
Volume = - cu.m
See Computation on RCBC & Catch Basin
COMPUTATION OF EQUIPMENT OUTPUT PER DAY
Labor Requirement
Quantites Activity
Type of Labor No. of unit Output/Day
Required (m ) 3
Duration (days)
Laborer 6 0.00 18.00 0.00
Note: Don’t use DT if materials to be excavated will be utilized as backfill.
PART - A EARTH WORKS
ITEM No.: 104 UNIT: Cubic Meter
DESCRIPTION: Embankment QUANTITY: 0.00

Summary of Derived Quantities


Embankment 0
Volume = 690.00 cu.m
See Earthworks for Volume Computation
COMPUTATION OF EQUIPMENT OUTPUT PER DAY
Equipment Requirment
Quantites Activity
Type of Equipment No. of unit Output/Day
Required (m3) Duration (hours)
Road Grader 1 690.00 14
50
Road Roller 1 690.00 14
Water Truck 1 690.00 3.50
Note: Use time and motion study for the output of DT if it exceeds the FHD (600 m.)

PART - B SUBBASE & BASE COURSES


ITEM No.: 200 UNIT: Cubic Meter
DESCRIPTION: Sub-Base Course QUANTITY: 66.00

Summary of Derived Quantities


Sub-Base Course 72.6
Volume = 72.60 cu.m
See Base Course & PCCP for Computation

Case 1: Materials delivered on site (Price of material is high, limited use of equipment)
Case 2: Materials is quarried from a source (Use of additional equipment and lower price of material)

COMPUTATION OF EQUIPMENT OUTPUT PER DAY

Equipment Requirement Case 1 Used


Quantites Activity
Type of Equipment No. of unit Output/Hour
Required Duration (hour)
Road Grader 1 72.60 400 0.50
Road Roller 1 72.60 320 0.50
Water Truck 1 72.60 200 0.50

PART - C CONCRETE STRUCTURE


ITEM No.: 404 UNIT: kgs.
DESCRIPTION: Reinforcing Steel QUANTITY: 0.00

Summary of Derived Quantities


Reinforcing Steel
slab 1227.17 kgs
footing
continous bar 246.67 kgs
sectional bar 61.79 kgs
dowels 12.21 kgs
Volume = 1,547.84 kgs
See RCBC & Catch Basin for Computation

Manpower/ Quantities Duration


Equipment
No. of Unit Output/Day
kgs ( day )
Bar Cutter 1
2880.0 0
Bar Bender 1
0.00
Steelman 2
1440.0 0
Laborer 8

PART - C CONCRETE STRUCTURE


ITEM No.: 405 UNIT: Cubic Meter
DESCRIPTION: Structural Concrete QUANTITY: 0.00

Summary of Derived Quantities


Structural Concrete
0 0.00 cu.m.
0 0.00 cu.m.
Volume = - cu.m.
See RCBC, Catch Basin & RCPC for Computation
For Fabrication, Placing and Dismatling of Forms
Quantities Duration
Manpower No. of Unit Output/Day
cu.m. ( day )
Carpenter 4 -
11.2 0
Laborer 8 -

For Concreting

Manpower/ Quantities Manpower Duration


Equipment
No. of Unit
l.m. ( Output/Day ) ( day )
One-Bagger Mixer 1
Concrete Vibrator 1
Concrete Saw 1
Foreman 1 - 3.5 0
Mason 4
Laborer 8

PART - E DRAINAGE AND SLOPE PROTECTION


ITEM No.: 506 UNIT: Cubic Meter
DESCRIPTION: Stone Masonry QUANTITY: 0.00

Summary of Derived Quantities


Stone Masonry

0 - cu.m
Volume = - cu.m
See Following Pages for Computation

Crew
Manpower/ Quantities Duration
Equipment
No. Output/Day
cu.m. ( day )

Bagger Mixer 1
Foreman 1 -
7.5 0.00
Mason 2
Laborer 8
Note: Excavation Works wil be included to Item 102(2), 3 gangs for Lesser Activity Duration
PART A - EARTHWORK
ITEM NO.: 803 (1) UNIT: Cubic Meter
DESCRIPTION: STRUCTURAL EXCAVATION QUANTITY: 122.42

COMPUTATION OF OUTPUT PER DAY


Manpower/Equipment Requirement
Quantites Manpower/Equipment Activity
Types No. of unit
Required (m3) Output (cu.m/day)Duration (days)
Foreman 1 122.42 8 15
Unskilled Laborer 4 15

PART A - EARTHWORK
ITEM NO.: 804 (1) UNIT: Cubic Meter
DESCRIPTION: EMBANKMENT QUANTITY: 552.42

COMPUTATION OF OUTPUT PER DAY


Manpower/Equipment Requirement
Quantites Manpower/Equipment Activity
Types No. of unit
Required (m3) Output (cu.m/day)Duration (days)
Foreman 1 552.42
Road Grader 1 400 1.00
Road Roller 1 400 1.00
Water Truck 1 0.25

PART B - PLAIN AND REINFORCED CONCRETE WORK


ITEM NO.: 900(1) UNIT: Cubic Meter
DESCRIPTION: STRUCTURAL CONCRETE QUANTITY: 227.70

COMPUTATION OF OUTPUT PER DAY


Manpower/Equipment Requirement
Quantites Manpower/Equipment Activity
Types No. of unit
Required (m ) Output (cu.m/day)Duration (days)
3

One-Bagger Mixer 2 227.70 2.856 80


Concrete Vibrator 2 80
Foreman 1 80
Mason 4 80
Unskilled Laborer 8 80
Quantites Manpower/Equipment Activity
Types No. of unit
Required (kg) Output (kg/day) Duration (day)
Bar Bender/Cutter 1 23,812 2880 8.00
Steelman 4 17.00
1400
Unskilled Laborer 8 17.00

PART C - FINISHING AND OTHER CIVIL WORKS


ITEM NO.: 1000 (1) UNIT: Liter
DESCRIPTION: SOIL POISONING QUANTITY: 27.20

COMPUTATION OF OUTPUT PER DAY


Manpower/Equipment Requirement
Quantites Manpower/Equipment Activity
Types No. of unit
Required (ltr) Output (ltr/day) Duration (days)
Foreman 1 0 40 0
Unskilled Laborer 4 0

PART C - FINISHING AND OTHER CIVIL WORKS


ITEM NO.: 1002 UNIT: lot
DESCRIPTION: PLUMBING QUANTITY: 1.00

COMPUTATION OF OUTPUT PER DAY


Manpower/Equipment Requirement
Quantites Manpower/Equipment Activity
Types No. of unit
Required (m2) Output (sq.m/day)Duration (days)

Skilled Laborer 4
Unskilled Laborer 8

PART C - FINISHING AND OTHER CIVIL WORKS


ITEM NO.: 1002(8) UNIT: Lump Sum
DESCRIPTION: PLUMBING FIXTURES QUANTITY: 1.00

COMPUTATION OF OUTPUT PER DAY


Manpower/Equipment Requirement
Quantites Manpower/Equipment Activity
Types No. of unit
Required (m ) Output (sq.m/day)Duration (days)
2

Skilled Laborer 4
Unskilled Laborer 2

PART C - FINISHING AND OTHER CIVIL WORKS


ITEM NO.: 1003 (1) UNIT: sq.m.
CARPENTRY AND JOINERY WORKS
DESCRIPTION: (Ceiling, Second Floor, Stairs & Louver QUANTITY: 493.00
Window Screen)

COMPUTATION OF OUTPUT PER DAY


Manpower/Equipment Requirement
Quantites Manpower/Equipment Activity
Types No. of unit
Required (m2) Output (sq.m/day)Duration (days)
493 18.88 26
Foreman 1
Skilled Laborer 3
Unskilled Laborer 2
Note: Ceiling Joist is included in Item 1047: Metal Structures
PART C - FINISHING AND OTHER CIVIL WORKS
ITEM NO.: 1005 (1) UNIT: sq.m
DESCRIPTION: STEEL WINDOWS (Residential Casement)QUANTITY: 24.48

COMPUTATION OF OUTPUT PER DAY


Manpower/Equipment Requirement
Quantites Manpower/Equipment Activity
Types No. of unit
Required (m2) Output (sq.m/day)Duration (days)
Foreman 1 24.48 6 4
Skilled Laborer 2
Unskilled Laborer 1

PART C - FINISHING AND OTHER CIVIL WORKS


ITEM NO.: 1006(6) UNIT: Square Meter
DESCRIPTION: STEEL DOORS AND FRAMES QUANTITY: 79.04

COMPUTATION OF OUTPUT PER DAY


Manpower/Equipment Requirement
Quantites Manpower/Equipment Activity
Types No. of unit
Required (m ) Output (sq.m/day)Duration (days)
2

Foreman 1 79.04 5.69 14


Skilled Laborer 2
Unskilled Laborer 1

PART C - FINISHING AND OTHER CIVIL WORKS


ITEM NO.: 1007(b) UNIT: Square Meter
DESCRIPTION: ALUMIUM GLASS DOORS QUANTITY: 12.60

COMPUTATION OF OUTPUT PER DAY


Manpower/Equipment Requirement
Quantites Manpower/Equipment Activity
Types No. of unit
Required (m2) Output (sq.m/day)Duration (days)
Foreman 1 12.60 5.69 2
Skilled Laborer 2
Unskilled Laborer 1

PART C - FINISHING AND OTHER CIVIL WORKS


ITEM NO.: 1014 (1) UNIT: Square Meter
DESCRIPTION: PRE-PAINTED METAL SHEETS QUANTITY: 685.88

COMPUTATION OF OUTPUT PER DAY


Manpower/Equipment Requirement
Quantites Manpower/Equipment Activity
Types No. of unit
Required (m2) Output (sq.m/day)Duration (days)
Scaffolds 8 685.88 40 17
Foreman 1 17
Skilled Laborer 2 17
Unskilled Laborer 6 17

PART C - FINISHING AND OTHER CIVIL WORKS


ITEM NO.: 1018 (1) UNIT: Square Meter
DESCRIPTION: CERAMIC TILES QUANTITY: 109.28

COMPUTATION OF OUTPUT PER DAY


Manpower/Equipment Requirement
Quantites Manpower/Equipment Activity
Types No. of unit
Required (m ) Output (sq.m/day)Duration (days)
2

Foreman 1 109 8 14
Skilled Laborer 4 14
Unskilled Laborer 4 14

PART C - FINISHING AND OTHER CIVIL WORKS


ITEM NO.: 1021(a) UNIT: Cubic Meter
DESCRIPTION: CEMENT FLOOR FINISHED QUANTITY: 320.00

COMPUTATION OF OUTPUT PER DAY


Manpower/Equipment Requirement
Quantites Manpower/Equipment Activity
Types No. of unit
Required (m ) Output (cu.m/day)Duration (days)
3

One-Bagger Mixer 1 320.00 47.6 7


Concrete Vibrator 1 7
Foreman 1 7
Mason 4 7
Unskilled Laborer 8 7

PART C - FINISHING AND OTHER CIVIL WORKS


ITEM NO.: 1027 (1) UNIT: Square Meter
DESCRIPTION: CEMENT PLASTER FINISH QUANTITY: 935.60

COMPUTATION OF OUTPUT PER DAY


Manpower/Equipment Requirement
Quantites Manpower/Equipment Activity
Types No. of unit
Required (m2) Output (sq.m/day)Duration (days)
Foreman 1 936 57 16
Skilled Laborer 4 16
Unskilled Laborer 4 16

PART C - FINISHING AND OTHER CIVIL WORKS


ITEM NO.: 1032 (1)a UNIT: Square Meter
DESCRIPTION: PAINTING WORKS QUANTITY: 1,334.00

COMPUTATION OF OUTPUT PER DAY


Manpower/Equipment Requirement
Quantites Manpower/Equipment Activity
Types No. of unit
Required (m2) Output (sq.m/day)Duration (days)
Scaffolds 10 1,334 125 11
Foreman 1 11
Skilled Laborer 3 11
Unskilled Laborer 6 11

PART C - FINISHING AND OTHER CIVIL WORKS


ITEM NO.: 1046 UNIT: Square Meter
DESCRIPTION: MASONRY WORKS (CHB) QUANTITY: 525.96

COMPUTATION OF OUTPUT PER DAY


Manpower/Equipment Requirement
Quantites Manpower/Equipment Activity
Types No. of unit
Required (m ) Output (sq.m/day)Duration (days)
2

Foreman 1 525.96 30.6 9


Skilled Laborer 2 9
Unskilled Laborer 4 9

PART C - FINISHING AND OTHER CIVIL WORKS


ITEM NO.: 1047 UNIT: Kilograms
METAL STRUCTURES (ROOF FRAMING
DESCRIPTION: QUANTITY: 27,189.04
& SLAB STEEL GIRDER)

COMPUTATION OF OUTPUT PER DAY


Manpower/Equipment Requirement
Quantites Manpower/Equipment Activity
Types No. of unit
Required (kg) Output (kg/day) Duration (days)
Cutting Machine 1 27,189 2720 10
Welding Machine 2 907 30
Acetheline Machine 1 680 30
Truck-mounted crane 1 1388 20
Foreman 1 680 40
Skilled Laborer 4 680 40
Note: Electric Bill for Cutting Machine is Included

PART C - FINISHING AND OTHER CIVIL WORKS


ITEM NO.: 1051(5) UNIT: Linear Meter
DESCRIPTION: METAL RAILINGS (w/ Steel Stair Frame) QUANTITY: 47.80

COMPUTATION OF OUTPUT PER DAY


Manpower/Equipment Requirement
Quantites Manpower/Equipment Activity
Types No. of unit
Required (lm) Output (lm/day) Duration (days)
Cutting Machine 1 47.80 5 10
Welding Machine 2 5 10
Foreman 1 5 10
Skilled Laborer 4 5 10
Note: Electric Bill for Cutting Machine is Included

PART D - ELECTRICAL
ITEM NO.: 1100 UNIT: Lump Sum
DESCRIPTION: CONDUITS, BOXES & FITTINGS QUANTITY: 1.00

COMPUTATION OF OUTPUT PER DAY


Manpower/Equipment Requirement
Quantites Manpower/Equipment Activity
Types No. of unit
Required (l.m) Output (l.m/man-day) Duration (days)
Electrician 4 1 18 0

PART D - ELECTRICAL
ITEM NO.: 1101 UNIT: Lump Sum
DESCRIPTION: WIRES AND WIRING DEVICES QUANTITY: 1.00

COMPUTATION OF OUTPUT PER DAY


Manpower/Equipment Requirement
Quantites Manpower/Equipment Activity
Types No. of unit
Required (roll) Output (roll/man-day) Duration (days)
Electrician 4 1.00 0.5 1

PART D - ELECTRICAL
ITEM NO.: 1102 UNIT: Lump Sum
POWER LOAD CENTER, SWITCHGEAR
DESCRIPTION: QUANTITY: 1.00
AND PANELBOARDS

COMPUTATION OF OUTPUT PER DAY


Manpower/Equipment Requirement
Quantites Manpower/Equipment Activity
Types No. of unit
Required (sets) Output (sets/man-day) Duration (days)
Electrician 2 1 5 0

PART D - ELECTRICAL
ITEM NO.: 1103 UNIT: Lump Sum
DESCRIPTION: LIGHTING FIXTURE QUANTITY: 1.00

COMPUTATION OF OUTPUT PER DAY


Manpower/Equipment Requirement
Quantites Manpower/Equipment Activity
Types No. of unit
Types No. of unit
Required (sets) Output (set/man-day) Duration (days)
Electrician 4 1 1 0

PART C - FINISHING AND OTHER CIVIL WORKS


ITEM NO.: 1001(9) UNIT: Each
DESCRIPTION: STORM DRAINAGE AND DOWNSPOUT QUANTITY: 18.00

COMPUTATION OF OUTPUT PER DAY


Manpower/Equipment Requirement
Quantites Manpower/Equipment Activity
Types No. of unit
Required (m3) Output (cu.m/day)Duration (days)
0 1 0.00 4 0
Foreman 1 0
Mason 2 0
Unskilled Laborer 4 0
Quantites Manpower/Equipment Activity
Types No. of unit
Required (kg) Output (kg/day) Duration (day)
Bar Bender/Cutter 1 0 1440 0.00
Steelman 1 0.00
700
Unskilled Laborer 4 0.00

PART - C OTHER GENERAL REQUIREMENTS


ITEM NO.: B.5 UNIT: each
DESCRIPTION: PROJECT BILLBOARD / SIGNBOARD QUANTITY: 3.00

COMPUTATION OF MANPOWER OUTPUT PER DAY


Quantities Manpower Duration
Manpower
lot. ( Output/hr ) ( hour ) NOTE:
1 - Foreman 1 Sets - COA Billboard
1 - Carpenter 3.00 2.0 2.00 1 Set -Grievance Redress Mechanism
4 - Laborer

PART - C OTHER GENERAL REQUIREMENTS


ITEM No.: B.7 UNIT: Lump Sum
OCCUPATIONAL SAFETY AND HEALTH
DESCRIPTION: QUANTITY: 1.0
PROGRAM

Crew

Manpower/ Quantities Duration


Equipment
No. Output/Day
l.s ( day )
First Aider 1 1.00 1.0 0

PART - C OTHER GENERAL REQUIREMENTS


ITEM No.: B.9 UNIT: Lump Sum
DESCRIPTION: MOBILIZATION & DEMOBILIZATION QUANTITY: 1.00

COMPUTATION OF EQUIPMENT OUTPUT PER DAY


Equipment Requirment
Activity Activity
Type of Equipment No. of unit Type of Equipment No. of unit
Duration (days) Duration (days)

Water truck 1 2
Road Grader 1 2
Road Roller 1 2
Low Bed (Prime 1 2
Mover 25T Cap)

PART - C SPECIAL ITEMS


ITEM NO.: 1001(8) UNIT: Lump Sum
DESCRIPTION: SEWER LINE WORKS QUANTITY: 1.00

COMPUTATION OF OUTPUT PER DAY


Manpower/Equipment Requirement
Quantites Manpower/Equipment Activity
Types No. of unit
Required (m ) Output (cu.m/day)Duration (days)
3

Foreman 1 46 8.96 5
Skilled Laborer 1
Unskilled Laborer 2
STANDARD EQUIPMENT CAPABILITY ESTIMATES
Bulldozer Clearing 500 sq.m./hr 4000 sq.m./day
Stripping 200 sq.m./hr 1600 sq.m./day
Quarrying 50 sq.m./hr 400 sq.m./day
Excavation 25 sq.m./hr 200 sq.m./day
Pushing 3 cu.m./hr 24 cu.m./day
Grader Sub-grading 300 sq.m./hr 2400 sq.m./day
Spreading 50 cu.m./hr 400 cu.m./day
Pay Loader Loading 30 cu.m./hr 240 cu.m./day
Crane Shovel Loading 35 cu.m./hr 280 cu.m./day
Backhoe Loading 30 cu.m./hr 240 cu.m./day
Static Rolling (12 passes-15
Sheep Foot Roller cm lift) 45 cu.m./hr 360 cu.m./day
Vibratory Rolling (4 passes-15
cm lift) 135 cu.m./hr 280 cu.m./day
Static Rolling (6 passes-15 cm
No. 3 Road Roller lift) 24 cu.m./hr 192 cu.m./day
Vibratory Rolling (6 passes – 2
Tractor-drawn cm lift) 240 cu.m./hr 1920 cu.m./day
Roller (1-D) cu.m./hr cu.m./day
Static Rolling 96 passes-20 cm
Tander Roller lift) 24 cu.m./hr 192 cu.m./day
5-T Dump truck Hauling Common Borrow 3.5 cu.m./hr 28 cu.m./day
Hauling SEBC (Selected
borrow, basecourse) 5 cu.m./trip
Hauling Concrete batch class
“A” 3 batch/trip
2 ½ DT Hauling Common Borrow 2.5 cu.m./trip
Hauling SEBC (Selected
borrow, 2 cu.m./trip
basecourse) cu.m./trip
Hauling Concrete batch class
“A” 2 batch/trip
1-Bagger Mixer Mixing concrete 3 cu.m./hr 24 cu.m./day
165 Conc. Mixer Mixing concrete 9 cu.m./hr 72 cu.m./day
Water Truck Watering 1000 sq.m./hr 8000 sq.m./day
Crushing mixed sand and
Rock Crusher gravel 30 cu.m./hr 240 cu.m./day
Conc. Vibrator Vibrating concrete mix 40 cu.m./hr 320 cu.m./day
Percussion Drilling hard rock 0.75 f/hr
Drilling loose rock 1 f/hr
Drilling lime stone 1.25 f/hr
Drilling sticky clay 1.6 f/hr
Drilling loose clay 2.5 f/hr
Bar Cutter 444 kg./day
2014 ACEL RATES
(Minimum Operation = 8 hrs. per day)

No. Name & Capacity Description Bare Rental


Hourly Rate Daily Rate
1 Air Compressor 86-125 cfm/42Hp 965 7720
2 Asphalt Batching Plant 1139.63 9117.04
3 Asphalt Distributor 10 ft wide 936 7488
4 Asphalt Paver/Finisher PF-180 1349 10792
5 Backhoe SE 130 LC-2, 0.80 cu.m. 1537 12296
6 Backhoe, Wheel Type PW60-3, 0.28 cu.m. 922 7376
7 Backhoe with Pavement Breaker 1998 15984
8 Bulldozer D65A-8/155Hp 3379 27032
9 Clampshell 315 2520
10 Chain Saw 120 960
11 Concrete Paver/Finisher GP-2500 Slipform 6237 49896
12 Concrete Batching Plant 30 cu.m. 1208.03 9664.24
13 Crawler Crane 46-50T 1956 15648
14 Crawler Crane 36-40T 1729 13832
15 Concrete Vibrator 148.88 1191.04
16 Concrete Mixer 1.5-2 Bagger 190 1520
17 Concrete Mixer 1-Bagger 172 1376
18 Concrete Screeder 545 4360
19 Concrete Saw 167.38 1339.04
20 Dump Truck (Cap. 10-11 cu.m.) 1420 11360
21 Payloader 1.5 cu.m. 1773 14184
22 Plate Compactor 123 984
23 Rebar Bender 351.5 2812
24 Rebar Cutter 219.75 1758
25 Road Grader 135Hp / GD511R-1 2173 17384
26 Road Roller, Vibratory Single Smooth Drum, CA2 1507 12056
27 Transit Mixer 5-6 cu.m. 1279 10232
28 Water Truck (1000 Gal.) 2450 19600
29 Cargo Truck (5T) 781 6248
30 TM Crane, 35T Capacity 1572 12576
31 Cutting Outfit (Gas Type) 110 880
32 Kneading Machine 200 1600
33 Applicator 106.25 850
34 Low Bed (Prime Mover 25T Cap) 514.43 4115.45
Prices of Construction Materials
(Based on Regional Price Monitoring Report - 2nd Quarter CY 13)

No. Description Unit Unit Price Hauling Cost Total Price


1 Portland Cement bag 285 6.75796996997 291.76
2 Fine Aggregates cu.m. 476.2 300.05386666667 776.25
3 Coarse Aggregates cu.m. 571.4 300.05386666667 871.45
4 Agg. Subbase Course cu.m. 390 300.05386666667 690.05
5 Embankment Materials cu.m. 300 300.05386666667 600.05
6 RSB, Grade 40 kg. 55 0.1765022745098 55.18
7 RSB, Grade 60 kg. 60 0.1765022745098 60.18
Plain Round Rebar,10mm
8 dia.x6m pcs 171.1 0.1765022745098 171.28
9 Tie Wire, #16 kg. 85.7 85.7
10 Boulders (Rock Class "A") cu.m. 560 300.05386666667 860.05
11 PVC Pipe, 2" Ø l.m. 97 97
12 RCPC, 910mm Ø pc. 2170 2170
13 Form Lumber, Coco bd.ft. 28 28
14 Good Lumber, False Work bd.ft. 75 75
15 Marine Plywood, 4'x8'x1/2" pc. 857.1 857.1

16 Ordinary Plywood, 4'x8'x1/2" pc. 809.5 809.5


17 CW Nails, Assorted kg. 80.5 80.5
18 Tarpauline (Printed), 8'x8' pc. 553 553
19 Tarpauline (Printed), 4'x8' pc. 277 277
20 Filter Cloth sq.m. 160 160

Field Office (rental), including


21 electric and water bills 0 6200 6200

Warning Sign 3mm


22 thk.Triangle 600mm pc 4972 4972
Informative Sign
(457mmx1219mmx3mm
26 School Zone) pc 7150 7150
27 Acetylene/Oxygen set 3000 3000
28 Thermoplastic White bag 2700 2700
29 Glass Beads bag 800 800
30 Primer ltr 130 130
31 Rope (Cotton 1/4" ø x 30m.) l.m. 150 150
32 LPG kg. 53.45 53.45
33 Calsumie kg. 24 24
Traffic Signages, Paraphernalia
34 and Lightings l.s 10000 10000
35 Asphalt Sealant lit 75 75
3)

Remarks
Summary of Labor Rates
No. Designation Hourly Rate Daily Rate
1 Foreman 65.545 524.36
2 Highly Skilled Laborer 54.36 434.88
3 Skilled Laborer 47.62375 380.99
4 Semi-Skilled Laborer 43.56 348.48
5 Part-time Safety Practitioner 75 600
6 First Aider 55 440
7 Unskilled Laborer 36.745 293.96