Case 1: Materials delivered on site (Price of material is high, limited use of equipment)
Case 2: Materials is quarried from a source (Use of additional equipment and lower price of material)
For Concreting
Crew
Bagger Mixer 1
Foreman 1 33.98
7.5 5.00
Mason 2
Laborer 8
Note: Excavation Works wil be included to Item 102(2), 3 gangs for Lesser Activity Duration
Case 1: Materials delivered on site (Price of material is high, limited use of equipment)
Case 2: Materials is quarried from a source (Use of additional equipment and lower price of material)
For Concreting
0 - cu.m
Volume = - cu.m
See Following Pages for Computation
Crew
Manpower/ Quantities Duration
Equipment
No. Output/Day
cu.m. ( day )
Bagger Mixer 1
Foreman 1 -
7.5 0.00
Mason 2
Laborer 8
Note: Excavation Works wil be included to Item 102(2), 3 gangs for Lesser Activity Duration
PART A - EARTHWORK
ITEM NO.: 803 (1) UNIT: Cubic Meter
DESCRIPTION: STRUCTURAL EXCAVATION QUANTITY: 122.42
PART A - EARTHWORK
ITEM NO.: 804 (1) UNIT: Cubic Meter
DESCRIPTION: EMBANKMENT QUANTITY: 552.42
Skilled Laborer 4
Unskilled Laborer 8
Skilled Laborer 4
Unskilled Laborer 2
Foreman 1 109 8 14
Skilled Laborer 4 14
Unskilled Laborer 4 14
PART D - ELECTRICAL
ITEM NO.: 1100 UNIT: Lump Sum
DESCRIPTION: CONDUITS, BOXES & FITTINGS QUANTITY: 1.00
PART D - ELECTRICAL
ITEM NO.: 1101 UNIT: Lump Sum
DESCRIPTION: WIRES AND WIRING DEVICES QUANTITY: 1.00
PART D - ELECTRICAL
ITEM NO.: 1102 UNIT: Lump Sum
POWER LOAD CENTER, SWITCHGEAR
DESCRIPTION: QUANTITY: 1.00
AND PANELBOARDS
PART D - ELECTRICAL
ITEM NO.: 1103 UNIT: Lump Sum
DESCRIPTION: LIGHTING FIXTURE QUANTITY: 1.00
Crew
Water truck 1 2
Road Grader 1 2
Road Roller 1 2
Low Bed (Prime 1 2
Mover 25T Cap)
Foreman 1 46 8.96 5
Skilled Laborer 1
Unskilled Laborer 2
STANDARD EQUIPMENT CAPABILITY ESTIMATES
Bulldozer Clearing 500 sq.m./hr 4000 sq.m./day
Stripping 200 sq.m./hr 1600 sq.m./day
Quarrying 50 sq.m./hr 400 sq.m./day
Excavation 25 sq.m./hr 200 sq.m./day
Pushing 3 cu.m./hr 24 cu.m./day
Grader Sub-grading 300 sq.m./hr 2400 sq.m./day
Spreading 50 cu.m./hr 400 cu.m./day
Pay Loader Loading 30 cu.m./hr 240 cu.m./day
Crane Shovel Loading 35 cu.m./hr 280 cu.m./day
Backhoe Loading 30 cu.m./hr 240 cu.m./day
Static Rolling (12 passes-15
Sheep Foot Roller cm lift) 45 cu.m./hr 360 cu.m./day
Vibratory Rolling (4 passes-15
cm lift) 135 cu.m./hr 280 cu.m./day
Static Rolling (6 passes-15 cm
No. 3 Road Roller lift) 24 cu.m./hr 192 cu.m./day
Vibratory Rolling (6 passes – 2
Tractor-drawn cm lift) 240 cu.m./hr 1920 cu.m./day
Roller (1-D) cu.m./hr cu.m./day
Static Rolling 96 passes-20 cm
Tander Roller lift) 24 cu.m./hr 192 cu.m./day
5-T Dump truck Hauling Common Borrow 3.5 cu.m./hr 28 cu.m./day
Hauling SEBC (Selected
borrow, basecourse) 5 cu.m./trip
Hauling Concrete batch class
“A” 3 batch/trip
2 ½ DT Hauling Common Borrow 2.5 cu.m./trip
Hauling SEBC (Selected
borrow, 2 cu.m./trip
basecourse) cu.m./trip
Hauling Concrete batch class
“A” 2 batch/trip
1-Bagger Mixer Mixing concrete 3 cu.m./hr 24 cu.m./day
165 Conc. Mixer Mixing concrete 9 cu.m./hr 72 cu.m./day
Water Truck Watering 1000 sq.m./hr 8000 sq.m./day
Crushing mixed sand and
Rock Crusher gravel 30 cu.m./hr 240 cu.m./day
Conc. Vibrator Vibrating concrete mix 40 cu.m./hr 320 cu.m./day
Percussion Drilling hard rock 0.75 f/hr
Drilling loose rock 1 f/hr
Drilling lime stone 1.25 f/hr
Drilling sticky clay 1.6 f/hr
Drilling loose clay 2.5 f/hr
Bar Cutter 444 kg./day
2014 ACEL RATES
(Minimum Operation = 8 hrs. per day)
Remarks
Summary of Labor Rates
No. Designation Hourly Rate Daily Rate
1 Foreman 65.545 524.36
2 Highly Skilled Laborer 54.36 434.88
3 Skilled Laborer 47.62375 380.99
4 Semi-Skilled Laborer 43.56 348.48
5 Part-time Safety Practitioner 75 600
6 First Aider 55 440
7 Unskilled Laborer 36.745 293.96