You are on page 1of 121

IRRIGATION ENGINEERING

UNIT – I

IRRIGATION: Irrigation is the art and science of applying water artificially to

the land for producing crops.

SCOPE: It is old age time art, as old as civilization. Civilization of any country

has followed the development of irrigation. Irrigation in modern world is also

said to be the science of survival.

India is the vast country having total land area of 326 million hectares

and cultivable area of 194 million hectares (1 hect. = 10 4 m2). More than 65%

population of India depends upon agriculture which clearly shows that India’s

development in the field of agriculture largely depends upon development of

irrigation.

HYDROLOGY: Hydrology is the science which deals with the occurrence,

distribution and movement of water on the earth. Water occur in the atmosphere

in the form of vapour, on the surface as water, snow or ice and below the

surface as groundwater.

1
Hydrological cycle: It is the process of transfer of moisture from the

atmosphere to the earth, in the form of precipitation, conveying of precipitated

water by streams, rivers to ocean, seas and lakes and evaporation of water back

to the atmosphere.

Hydrological cycle consist of the following processes.

(1) Precipitation: It may be defined as fall of moisture from the atmosphere

to the earth surface in any form, precipitation may be in two forms:

(a) Liquid precipitation (b) Frozen precipitation

(a) Liquid Precipitation: This type of precipitation is further divided in

three types.

(i) Rain: When the size of drops is more than 0.5 mm.

The upper size of water drops is generally 6.25 mm as drops greater than

this size tends to break up as they fall through air.

2
(ii) Drizzle: When the size of the water droplets is under 0.5 mm and its

intensity is less than 0.01 mm/hr.

(iii) Sleet: They are frozen rain drops coded to ice stage by falling through air

at sub freezing temperature.

(b) Frozen precipitation:

(i) Snow: Precipitate in the form of ice crystals resulting from sublimation

i.e. water vapour changes directly to ice.

(ii) Hail: It is a lump or bulk of ice over 5 mm dia formed by alternate

freezing or melting as they are carried up and down in highly turbulent air

currents.

(2) RUN OFF: It is that part of precipitation which is available on earth

surface after loss, to the atmosphere.

Let P = Precipitate in mm

R = Runoff in mm

E = Loss to the atmosphere (Evaporation & transpiration)

Then mathematically P=R+E

(i) Surface runoff: It is that part of precipitation which flows on the earth

surface after loss to the atmosphere and loss to the ground. In other words if the

rate of infiltration is less than the rate of precipitation, excess water flows on the

surface of the earth. This surplus water which flows on the surface of earth is

called surface runoff.

3
(ii) Sub surface runoff: It is that portion of precipitation which flows below

the surface of the earth through the inter connecting voids of the soils as far as

the slope is available or it joins nearby ponds, stream. This is known as sub-

surface runoff.

(iii) Base flow or groundwater flow: It is that portion of precipitation which

after infiltration percolates down and joins the groundwater table.

(3) INTERCEPTION: It is that portion of precipitation, which is being

retained by the trees, plants and bushes available on the earth surface.

Interception is the function of intensity of rainfall. If intensity of rain fall is

more interception will be less.

(4) SURFACE DETENTION: It is that portion of precipitation which is

being detained in the natural depressions available on the earth surface.

(5) EVAPORATION AND TRANSPIRATION: Water from the surface of

oceans, rivers, lakes and moist soil evaporate. The vapours are carried over the

land by air in the form of clouds.

Transpiration is the process of water being lost from the leaves of plant.

WATERSHED:

4
It is an imaginary line passing in an area formed by intersection of two

opposite slopes that is having downward sloping ground on both sides. Water

shed is always found between two successive drainages or drainage line.

Drainage/Drainage line: It is an imaginary line passing in an area having

upward sloping ground on both its side. There is always one drainage line

between two consecutive watersheds.

Catchment area/catchment: It is the entire area all around drainage, lake,

ponds etc. which contributes to the runoff flowing in them. The rain fall on this

area will flow into these water bodies.

Measurement of Rainfall:

Rainfall is the source of all water used for irrigation purposes, therefore a

knowledge of its amount, character, reasons and periods is of prime importance

5
to the irrigation engineer. The amount of precipitation is expressed as depth of

water in cms or mms which falls on a level surface and is measured by rain

gauge.

Types of rain gauge:

(1) Symon’s rain gauge

(2) Weighing bucket type rain gauge.

(3) Tipping bucket type rain gauge

(4) Float type rain gauge

1. Symon’s rain gauge: Symon’s rain gauge is the most common type of

non-automatic rain gauge and is used by meteorological department of

government of India. It consist of a cylindrical vessel 127 mm in diameter. The

top section is a funnel provided with circular brass rim of 127 mm diameter.

The funnel is inserted into a receiving bottle of 75 to 100 mm diameter. The

receiving bottle has a capacity of 75 to 100 mm of rainfall and during heavy

rains. The rainfall should be measured 3-4 times to avoid over flow.

While selecting a site for a rain gauge station the following point should

be kept in mind.

(1) Rain gauge should be placed in an open area.

(2) The distance between rain gauge and the nearest object should be

atleast twice the height of the object. In no case the rain gauge should

be nearer to obstruction then 30 m.

6
(3) The rain gauge should never be situated on the side or top of a hill if a

suitable site on a level ground can be found.

(4) In the hills where it is difficult to find level space the site for the rain

gauge should be chosen where it is best shielded from high winds.

Estimation of Maximum rate of run-off or flood discharge:

Most of the formulae for estimation of flood discharge are in the form:

Q = CAn

where, Q = flood discharge

A = catchment area

n = flood index

C = flood coefficient

7
both C & n depends upon various factors such as (i) size, shape and location of

catchment (ii) topography of the catchment and (iii) intensity, duration of

rainfall and distribution pattern of the storm over the basin.

Dicken’s formula:

Q = C A3/4

where, Q = discharge in cumecs

A = area of basin in sq.km.

The value of C may be obtained from the following table.

Region C

Northern India 11.4

Central India 13.9 – 19.5

Western India 22.2 – 25

CROPS AND CROP SEASONS:

(1) Kharif season – Kharif crops:

(a) Food crops e.g. Maize, Rice, Great Millet, Spiked Millet

(b) Non-food crops Ground nut

(2) Rabi season – Rabi crops:

(a) Food crops – Wheat, potato, gram, peas

(b) Non-food crops – Mustard, tobacco, linseed

CROP SEASONS: In India mainly there are two types of crop seasons:

(1) Kharif season

8
(2) Rabi season

Kharif season starts from 1st week of April and ends in last week of

September. Therefore, for easy ploughing of the field a shower in third and

fourth week of March is very essential.

Rabi season starts from first week of October and ends in last week of

March. Therefore, in order to make the soil loose, a shower is essential in third

and fourth week of September.

Double Crops: When two crops of short duration are grown in same field in the

same season one after the other, they are known as double crops.

Mixed crops: When two crops are sown in the same field simultaneously the

resulting crop is known as mixed crop. E.g. combination of wheat & gram¸

wheat and mustard etc.

Rotation of crops: The method of growing different crops in a field year after

the year is known as rotation of crops. If in a field, same crop is sown year after

year, the soil becomes weak and less fertile. This is so because the constituents

of soil get more or less exhausted due to continuous feeding of the same crop.

Therefore, same crop should not be sown year after year in the same field.

The soil can gain strength by two ways:

(1) By leaving the field fallow for one season.

(2) By adding extra required manure.

But neither it is wise to leave the field fallow for one season nor to have extra

cost manure. So the crop rotation is preferred for regaining the strength of the

9
field. In this case all the constituents of the soil are taken up by different crops

and are consumed more or less to the same extent. This helps in preventing the

soil to become deficient in particular type of nutrient. The following rotation

pattern is adopted for different crops.

(1) Wheat – Millet – gram

(2) Rice gram

(3) Wheat – cotton – sugarcane

(4) Cotton – great millet – spiked millet

WATER REQUIREMENTS OF CROPS:

Gross Command Area (G.C.A.):

A canal usually runs on a water shed and water can flow from it on both

sides due to gravitational action, only upto drainage boundaries. Hence,

irrigation from a canal can only be done up to drainage boundaries. Gross

command area is the total area lying between the drainage boundaries which can

be commanded or irrigated by a canal system. G.C.A. includes unfertile barren

land, local ponds roads, villages etc.

Culturable command Area:

If we exclude the unculturable, area (barren lands, ponds, villages etc.)

from the gross command area, the remaining area will be culturable command

area. It is the area or which crops can be grown satisfactorily.

Base Period:

10
Base period for a crop refers to the whole period of cultivation from the

time when irrigation water is first applied for preparation of ground for planting

the crops to its last watering before harvesting. Base period is represented in

number of days.

Kor Depth and Kor Period:

Crops require maximum water during first watering. With the passage of

time quantity of water required decreases. The first watering is known as kor

watering. The depth of water applied is known as kor depth and the portion of

base period in which kor watering is needed is known as kor period.

Time Factor:

Time factor of a canal is the ratio of the number of days the canal has

actually run to the no. of days of irrigation period.

Duty (D): Duty represents the irrigating capacity of a unit of water. It is the

relation between the area of crop irrigated and the quantity of irrigation water

required for the growth of crops during the entire period. E.g. If 3 cumec of

water supply is required for an agricultural land of 6000 hectares, the duty of

irrigation water will be = 6000/3 = 2000 hect/cumec.

Delta(s): Delta is the total depth of water required by a crop during the crop is

in the field. E.g. If a crop requires 15 waterings at an intervals of 12 days, the

depth of water applied in every watering is 10 cm.

 = 15 x 10 = 150 cm = 1.5 m

Intensity of irrigation:

11
It is the percentage area of a crop in a particular season.

Outlet Factor: It is defined as duty at the outlet.

Factor affecting duty:

1. Method and system of irrigation

2. Mode of applying water to the crops

3. Method of cultivation

4. Type of crop

5. Base period of crop

6. Climatic condition of the area

7. Quality of water

8. Canal conditions

9. Character of soil and sub soil of the canal

10. Character of soil and sub soil of irrigation fields.

Relation between duty and delta:

D = Duty in hect/cumec

 = Total depth of water in m

B = Base period in days

If we take a field of area D hectares, the supply to the field, corresponding to the

water depth  (m) will be =  x D hect.m.

= D  104 m3 …(1)

12
Again for the same field of D hect, 1 cumec of water is required to flow during

the entire base period. Hence water supplied to this field is equal to:

= 1 x B x 24 x 60 x 60 ….(2)

Equating these two equation (1) and (2) we get the result

B x 24 x 60 x 60
 = 4
D x 10

 = 8.64
B
mts
D

B = days

D = hect/cumec

In F.P.S. system,

 = 1.985
B
mts Where D in acres/cusecs
D

 in feet

Problem-1: Find the  for a crop if the duty for a base period of 110 days is

(a) 80 acres/cusec

(b) 1400 hect/cusec

Solution:

 = 1.985 x
110
(a) = 2.73 feet
80

 = 8.64 x
110
(b) = 0.678 m
1400

Problem-2:

13
An irrigation canal has gross commanded area of 80,000 hects. Out of

which 85% is culturable irrigable. The intensity of irrigation for kharif season is

30% and for Rabi season is 60%. Find the discharge required at the head of

canal if the duty at its head is 800 hect/cumec for kharif and 1,700 hect/cumec

for rabi season.

Solution:

Culturable area = 0.85 x 80,000 = 68000 hect.

Area under kharif seasons = 0.3 x 68000 = 20400 hect.

Area under rabi season = 0.6 x 68000 = 40800 hect.

Water required at the head of canal to irrigate the land under kharif

20400
season =
800

= 25.5 cumec

Water required at the head of canal to irrigate the land under rabi season

40800
= = 24 cumec.
1700

Water required during the kharif season is more than water required during rabi

season. Hence the canal must be designed to carry a discharge of 25.5 cumec.

Problem-3:

The table below gives the necessary data about the crops, their duty and

the area under each crop, commanded by a canal taking off from a storage tank.

Taking a time factor to be 13/20, calculate the discharge required at the

head of the canal.

14
Crop Base period Area (hect.) Duty at the head of
(days) the canal
(hect/cumec)

1. Sugarcane 320 850 580

2. Overlap for 90 120 580


sugarcane in hot
weather

3. Wheat (Rabi) 120 600 1600

4. Bajri (Monsoon) 120 500 2000

5. Vegetables (hot 120 360 600


weather)

Solution: Discharge required for crops.

850
Discharge required for sugarcane = = 1.465 cumec
580

120
Discharge required for overlap sugarcane = = 0.206 cumec
580

600
Discharge required for wheat = = 0.375 cumec
1600

500
Discharge required for Bajra = = 0.25 cumec
2000

360
Discharge required for vegetable = = 0.6 cumec
600

Since the sugarcane has base period of 320 days it will requires water in rabi

monsoon and hot weather.

Discharge required in Rabi = 1.465 + 0.375 = 1.74 cumec

Discharge required in Monsoon = 1.465 + 0.25 = 1.715 cumec

Discharge required in hot weather = 1.465 + 0.206 + 0.6

15
= 2.271 cumec

Thus the max. demand of 2.271 cumec is in the hot weather. The time

factor is the ratio of the no. of days the canal has actually sun to the number of

days canal was supposed to run.

Here the time factor is = 13/20

Therefore, the full supply discharge at the head of canal will be

20
= 2.271 x = 3.4938 cumec
13

Taking an allowance of 20% for the peak demand, the design discharge

will be = 3.493 x 1.2 = 4.19 = 4.2 cumec.

Problem-4:

The base period, intensity of irrigation and duty of various crops under a

canal system are given in the table below. Find the reservoir capacity if the

canal losses are 20% and reservoir

Losses are 12%.

Solution:

Crop Base Duty at the Area =8.64


B Vol. =
period field under the D Ax
(days) hect/cumec crop hect hect.m.
(A)
Wheat 120 1800 4800 0.576 2764.8

Sugarcane 360 800 5600 3.888 21772.8

Cotton 200 1400 2400 1.234 2961.6

Rice 120 900 3200 1.152 3686.4

16
Vegetable 120 900 1400 1.152 1612.8
V = 32798.4 hect.m.

Considering 20% canal losses and 12% reservoir losses.

32798.4
Capacity of reservoir =  46588.64 hect.m.
0.8 Χ 0.88

Losses in canal irrigation in Uttar Pradesh are as below:

Sandy soil - 2090 to 50%

Sandy loams - 1590 to 25%

Fine sandy loams - 1090 to 20%

Heavy day loam - 5% to 15%

Problem-1: For a canal G.C.A. is 5000 hects. Out of which 20% area is

uncultuable The intensity of irrigation is 40% wheat and 20% for rice. Outlet

discharge factor for wheat and rice are 1850 and 1200 hect/cumec respectively.

Determine the discharge at the head of the canal neglecting all the losses.

Solution:

Culturable area = 80% of 5000

C.C.A. = 4000 hects.

Area under wheat crop = 40% of 4000

= 1600 hects.

Area under rice crop = 800 hects.

1600
Discharge required in the field for wheat = = 0.864 cumec
1850

17
800
Discharge required in the field for rice = = 0.666 cumec
1200

The design discharge for canal should be 0.864 cumec.

Problem-2: A village has 2000 hect. of C.C.A. out of which 20% area is under

the cultivation of perennial crop i.e. sugarcane and 50% area is under cultivation

of wheat whose duty at the head of outlet is 2000 hect./cumec. Duty of

sugarcane is 700 hects./cumec. If demand of water during kor period is

increased by 20% of the total demand, find out discharge for which village

water course has to be designed.

Solution-2:

Total C.C.A. = 2000 hect.

Area under sugarcane crop = 20% of 2000

= 400 hects.

Area under wheat crop = 50% of 2000

= 1000 hects.

Discharge required in the field for sugarcane

400
= = 0.571 cumec
700

Discharge required in the field for wheat crop

1000
= = 0.5 cumec
2000

... Total discharge = 0.871 + 0.5

= 0.871 cumec

18
Add 20% for kor period demand = 1.071 x 1.20 cumec

... Design discharge for canal = 1.285 cumec

Problem-3: The left branch canal carrying a discharge of 20 cumec has a

C.C.A. of 20,000 hects. The intensity of Rabi is 80% and the base period is 120

days. The right branch canal carrying a discharge of 8 cumec has a C.C.A. of

12,000 hects. The intensity of irrigatioin of Rabi crop is 50% and the base

period is 120 days. Compare the efficiencies of the two canal system.

Solution: Duty for left canal

Discharge area for left canal

= 80% x 20,000 = 16000 hects.

16 , 000
Duty for left canal = = 800 hects./cumec
20

For sight canal

Area = 20000 x 50%

= 6000 hects

6 , 000
Duty = = 750 hects/cumec
8

Since the duty of left canal is more so this canal will be more efficient.

Problem-4: Water course commands an irrigated area of 600 hects. The

intensity of irrigation of rice in this area is 60%. The transplantation of rice

crops takes 12 days and total depth of water required by crop is 50 cm on the

field during transplantation period. During the transplantation period, the useful

rain falling on the field is 10 cm. find the duty of irrigation water for the crop on

19
the field during transplantation period and also at the head of distributory.

Assuming losses of water to be 20% to the water course, calculate the discharge

required in the water course.

Solution:

Irrigated land, C.C.A. = 600 hects.

Area for rice crop = 60% x 600 = 360 hects.

 = 50 – 10 = 40 cm.

 = 8/64
B B
or D = 8.64
D 

12
D = 8.64 x = 259.20 hects./cumec
0 . 40

Area 360
Discharge = =  1.388 Cumec.
Duty 259.20

Add 20% for losses of water = 1.388 (1.20)

= 1.666 cumec

20
UNIT – II

CLASSIFICATION OF IRRIGATION

Broadly irrigation can be classified into two types:

(1) Natural irrigation

(2) Artificial irrigation

(1) Natural Irrigation:

Irrigation done by natural source is called as natural irrigation. The main

source of supply in this case is rainfall. Rainwater falls on the surface of the

earth and irrigates various fields. Thus helping in increasing the crop

production.

The supply of water in this case is not assured. Rainfall may or may not

occur at the desired time. It may occur when there is no need of water and

moreover its quantity may be insufficient for growing a particular crop. Hence

arrangements for artificial irrigation are essentially required for producing high

yielding crops.

(2) Artificial irrigation:

The process of supplying water artificially for the purpose of irrigating

the field is known as artificial irrigation. Artificial irrigation is further classified

into following sub-heads.

(a) Surface irrigation

(b) Sub-surface irrigation

21
(c) Sprinkler irrigation

(a) Surface irrigation: In this type of irrigation water is applied to the field

on the surface. They are further sub-divided into two heads:

(i) Lift irrigation

(ii) Flow irrigation

(i) Lift Irrigation:

The process of supplying water to the field for crop production by lifting

it from its source of supply is known as lift irrigation. The source of supply in

this case is the underground water reservoir. In this system the supply is assured

for all the months of the year depending upon the position ground water table

and type of lifting arrangement.

(ii) Flow Irrigation:

The process of irrigation in which water flows from its source to the field

under gravity is known as flow irrigation. It is also called as canal irrigation.

Depending upon the supply in this canal it is further sub-divided into two:

(I) Perennial irrigation

(II) Non-perennial irrigation

22
(I) Perennial irrigation:

Irrigation in which water is available for all the twelve months of the year

is termed as perennial irrigation. In this case head work is constructed for

storing of water on the upstream side and diverting the same into the canal.

The canal is constructed for carrying water to the field for irrigation

purpose. In this case a canal head regulator is constructed at the take off point of

the canal. Canal head regulator is constructed for controlling the supply of water

in the canal. The gates of head regulator are closed when no water is needed for

irrigation purpose or when any repairing work is to be carried out on the

downstream side of the canal. The supply in the canal is assured through out the

year as water is always available on the upstream of the head work.

(II) Non-Perennial irrigation:

Irrigation in which water is not always available for all the month of the

year is known as non-perennial irrigation In this system no regulator is provided

at the take off point of the canal. When water in the river rises it enters into the

canal and is used on the down streamside of the canal for irrigation purpose.

The bed level of the canal is fixed at lowest water level (L.W.L.) of the river

which indicates that whenever the level of water in river rises above its L.W.L.,

the water will automatically enter into the canal.

(b) Sub-surface irrigation:

The sub-surface irrigation method consists of supplying water directly to

root zone of the crop. In this case water is carried in perforated pipes under the

23
ground at a depth of 30-60 cm. Water escapes from these pipes into the soil and

reaches the plant roots. The method is aimed at avoiding evaporation and

minimizing percolation or seepage loss.

It requires heavy initial investment and could justified only when water is

very expensive. In Israel, technique have been developed which can reduces

water consumption to as low as one third of surface irrigation method without

reduction in yield.

(c) Sprinkler irrigation:

The process of irrigation in which the water is supplied to the land

through a system of pipe network connected to fine spray nozzles is terms as

sprinkler irrigation. This type of irrigation is useful where

(1) The field can’t be prepared for surface method

(2) Slopes are excessive

(3) Soil is erosive

(4) Soil is excessively permeable

In this system, there is large initial investment in purchase of pumping and

sprinkling equipment. In case of sprinkler irrigation, the crops are irrigated in

the same manner as by rainfall. Sprinkler system requires water sources free of

suspended impurities which would other wise clog the sprinkler. The best

sources are tube wells and lakes. Screening devices are necessarily required for

removing the suspended impurities when water.

24
CANALS:

India is a tropical country as the rainfall is insufficient or comes at

unsuitable times, is also not distributed uniformly.

Under these circumstances, it becomes essential to supply water

artificially to the field for increasing the production of the crops. So canal are

constructed for artificial supply of water. A canal is an artificial channel

generally trapezoidal in shape, constructed on the ground, some times below the

ground and also above the ground to carry water to the fields either from the

river or from a reservoir. When a canal is used for irrigation purpose it is called

an irrigation canal. Irrigation canal must be provided with a sufficient head of

water so that it may flow under gravity over the surrounding area.

25
Importance of canals:

Irrigation canal play a very important role in the development of country.

The importance of construction of canals for irrigation purpose are given below:

(1) They carry fine silt particles in suspension which is a good soil for

improving the production of crops.

(2) These are used for providing facilities for drinking, bathing and

washing purposes in addition to irrigation.

(3) These are very helpful in increasing the revenue of the government

because the water supplied to the field for irrigation purpose is

charged.

(4) These are also helpful in increasing the employment.

(5) These are helpful in increasing the timber wealth of the county

because many trees are planted along the canal banks.

Classification of canals:

Canals can be classified in the following ways:

(A) According to nature of supply:

Depending upon the nature of supply canals are classified as:

(1) Permanent canal or perennial canal.

(2) Inundation canals or Non-perennial canal.

(1) Permanent canal: The canal in which water is available throughout the

year is called permanent canal. The supply in the canal is controlled by the head

26
regulator constructed. at the take off point. A barrage is constructed across the

river to raise water level on upstream side as water is available throughout the

year. Hence it is also called as perennial canal.

(2) Inundation canals: The canal in which water is not available throughout

the year is called as inundation canals. The supply of this canal is not assured

and farmers can’t depend over this supply. Water in this canal enters only when

there is rainfall or flood in the river. As water is not available throughout the

year such canals are also known as non-perennial canals.

(B) According to financial output:

Depending upon the financial output there are two types of canal:

(1) Productive canal

(2) Protective canal

(1) Productive canal: Canals which indicates at the time of design and

planning that the total income will exceed the annual maintenance charges are

called productive canals.

(2) Protective canals: The canal which are constructed in the interest of

public and without any income are called protective canal.

(C) According to discharge:

A network of an irrigation canal system consist of following canals:

(1) Main canal

(2) Branch canal

(3) Distributaries canal

27
(i) Major distributaries

(ii) Minor distributaries

(4) Water course or field channels

(1) Main canal: They generally take the water directly from the river. Such

canals carry heavier supplies and are not used for direct irrigation. Main canal

act as water carrier to feed the supplies of the branch canal and major

distributaries. They very first canal of a canal system is known as main canal.

Its discharge is always more than 50 cumecs.

(2) Branch canal:

A branch canal takes off from the main canal. The main canal is also

known as the parent canal for the branch canal. The section of branch canal is

less than that of the main canal. The water of this canal is also not used directly

for irrigation purpose. The branch canal is designed to carry discharge of over

5.5 cumec.

28
(3) Distributaries canal:

A small channel take channel taking off from the branch canal is called a

distributary. Its main function is to distribute water to the fields for irrigation

purposes. Water is distributed through the outlets provided in the bank of

distributary. Distributaries are further classified according to their discharge

carrying capacity.

(i) Major distributary

(ii) Minor distributary

(i) Major distributary: If the discharge in the channel is not less than 0.25

cumec and not more than 5.5 cumec than the channel is termed major

distributary. The section is smaller than branch canal. It distributes water to the

water courses for irrigation purpose.

(ii) Minor distributary: If the discharge in the channel is less than 0.25

cumec than it is termed as minor distributary. It is also called as minor. They

supply water to the water courses through outlets.

(4) Water course or field channel:

Water course are the small channels constructed by the farmers and thus

were not the properly of government. Now in the government modernization

scheme the water course are also constructed and maintained by the government

and now they have become the property of government. The supply of the

channel comes through the outlet provided in the bank of the distributary. The

length of the water courses should not be more than 3 km in order to minimize

29
the losses. The bank of the water courses should be stabilized by planting

suitable grass in case of earthen field channels.

SECTION OF CANAL

Section of canal: (1) fully in cutting (2) fully in embankment

Canal losses and their estimation:

Mainly there are two types of losses:

(1) Evaporation losses

(2) Seepage losses

(1) Evaporation losses:

The process by which water changes into vapour is termed as

vaporization and varies with the climatic conditions of the region and hence can

30
never be predicted. The rate of evaporation depends upon the exposed free

water surface, intensity of wind and temperature of the area. Losses due to

evaporation are expressed in cumec per million sqm. of exposed water surface.

Evaporation losses are on an average not more than 8% of the total losses.

(2) Seepage losses:

Seepage losses are significant in beginning because in the initial stage

water fills up the soil poses. After this, when equilibrium is reached such losses

are reduced. Seepage losses are expressed in cumec/million sq.m. of wetted

surface. The seepage losses depends upon the following factors:

(1) Position of sub-soil water table

(2) Porosity of soil

(3) Depth of water in canal – greater the depth greater will be loss.

(4) Velocity of water – seepage is less in case of higher velocity.

(5) Amount of silt carried in suspension – The loss decrease with increase

in the amount of silt carried in suspension.

Depending upon the position of water table, seepage losses from the canal occur

in two ways:

(1) Absorption

(2) Percolation

(1) Absorption: When the water table is considerably below the ground

level, the water which seeps through the poses is unable to join water table and

31
wets the sub soil locally farming a saturated bulb. Zone in between the saturated

zone and the zone of capillary remains unsaturated.

(2) Percolation: The loss of water due to percolation depends upon the

porosity of the soil. When the water table is close to the ground level, the

seepage water may establish a direct link between the canal section and water

table. So the soil mass in between two extreme flow lines becomes completely

saturated.

Estimation of losses: The losses in the canal are usually measured by simple

method known as inflow and outflow method. In this method a long reach of the

canal is selected. Discharge observations are taken at the beginning and end of

this reach for several days. The outlet or any off-taking channel should be

completely closed during observation period. Finally the average value of the

difference between the discharge entering the reach and leaving the reach gives

the loss occurring in the reach. The losses are expressed in the following ways:

(a) Cumec/million sq.m. of wetted area

(b) As the percentage of discharge of the channel.

In Punjab the following formula is used to estimate the losses.

dq = 1.9 Q1/6

Q = Discharge in cumec

dq = loss in cumec/million m2 of wetted/area

In Uttar Pradesh (U.P.) the following formula is used to determine the canal

losses.

32
dq = 4.8603 x 10-3 (B+D)2/3

B = bed width C = 0.7 for main & branch canal

D = depth of canal = 1.0 for other canals

LINING OF CANALS:

Lining is the covering of surface of canal by any imperious material to

eliminate seepage losses.

Advantages of lining:

(1) The lining of canals prevents seepage loss and hence additional area

can be irrigated by the water saved. The cost of irrigation is therefore

reduced.

(2) The lining of canal is an important anti-water logging measure as it

reduces seepage to the adjoining areas.

(3) The lining provides a smooth surface. The rugosity coefficient

therefore decreases. The resistance to flow also decreases and hence

the velocity of flow in the lined canal increases.

(4) The increased velocity reduces the evaporation losses.

(5) The increased velocity helps to provide a narrow cross – section for

lined canals.

(6) Higher velocity helps in providing a flatter hydraulic gradient or bed

slope. Thus better command can obtained.

(7) Higher velocity prevents sitting of channel.

(8) Lining makes the banks more stable.

33
(9) Lining reduces maintenance cost and possibility of breaching.

(10) Lining of canal prevents or reduces weed growth.

(11) Lining of canal increases available head for power generation as flatter

gradient can be provided.

Disadvantages of canal lining:

(1) Canal, lining requires a heavy initial investment.

(2) Lining being permanent it is difficult to shift the outlets very often.

(3) It is very difficult to repair the damaged lining.

DESIGN OF CANALS:

1. Kennedy’s Theory: Kennedy was an executive engineer in Punjab

Irrigation Department. He carried out most of his investigation on some of the

canal reaches of Upper Bari Doab canal (now in Pakistan). The sites selected by

him did not require and silt clearance for more than 30 years and thus suppose

to be flowing with non silting and non scouring velocity. Based upon his

observations he concluded that the silt supporting power of a canal is mainly

dependent upon the generation of eddies rising from the base to surface of

canal. These eddies are generated due to friction of the flow of water with the

canal surface. The eddies formed at the bed tries to move the sediment up while

the weight of the sediment tries to bring it down thus keeping the sediment in

suspension. He finally concluded that (1) The silt supporting power is

proportional to bed width of the canal. Kennedy also defined the critical

velocity (non-silting, non-scouring velocity) Vo in the canal as the mean

34
velocity which would just keep the canal free from silting and scouring. He

related critical velocity. Vo to the depth of flow by the following equation:

Vo = 0.55 D0.64

where Vo = Critical velocity in m/s and D = depth of canal in (m).

This formula was found true for upper Bari doab canal system only and

not for all the conditions. He latter realized this short coming and introduced a

factor (m) as critical velocity ratio (C.V.R.). The values of m depends upon the

type of soil. The modified form of Kennedy’s equation became as

Vo = 0.55 m D0.64

Where m = critical velocity ratio. The value of m generally varies from 0.7 to

1.3.

Note: In case the value of m is not given it can be assumed as 1.

V
m 
Vo

where,

V = Actual velocity of flow given by Kutter’s equation

Vo = Critical velocity given by Kennedy’s equation

V  C RS

where,

R = hydraulic mean depth

S = longitudinal slope of the canal

C = Chezy’s constant

35
1 0.00155
23  
N S
C 
0.00155 N
1  (23  )
S R

Where N = Roughness coefficient or rougisty const. The value of N

varies from 0.0225 to 0.03.

Central Board of Irrigation and power (CBIP) has recommended the

following values of N for various discharges.

Discharge N

Upto 140 cumec 0.015

140 – 280 cumec 0.0225

280 and above 0.03

The biggest short coming in the Kennedy’s theory was that it did not gave

any equation for the slope of the canal. The slope is decided as per the general

slope of the area. By giving different value to the slope, different sections of the

canal can be worked out for the same discharge and Kennedy’s theory did not

give any indication as which of these sections would suit best for a particular

discharge.

Another defect of the Kennedy’s theory was that it neglected the eddies

coming out from the sides stating that these eddies are purely horizontal and

they do not have any silt supporting power.

Design steps:

36
1. Data given Q, N, m, S – Assume a value of depth D and calculate Vo

using the equation.

Vo = 0.55 m D0.64

2. Assume trapezoidal section of the canal having side slope ½: 1

Area = BD +0.5 D2

Q
3. Calculate the area by using the equation A 
Vo

4. Find out bed width of the canal using area equation.

5. Calculate wetted perimeter of the canal

P  B  S D

A
6. Calculate hydraulic radius R 
P

7. Calculate V by Kutter’s equation

V  C  RS

1 0.00155
23  
N S
where C 
0.00155 N
1  (23  )
S R

8. If V and Vo are same then the assumed depth is correct and the design is

O.K. Otherwise choose another value of depth and repeat the entire

calculation till the value of V and Vo concides or we get the value of m =

1.

Problem-1: Design a canal for 40 cumec discharge by Kennedy’s theory. The

other data required is given as N = 0.00225, m = 1 and S = 16 cm per km.

37
Solution: Assume depth of the canal = 1.5 m.

D = 1.5 m

(1) Vo = 0.55 m D0.64

= 0.55 x 1 x (1.5)0.64

= 0.713 m/s

Q 40
(2) Area =   56 . 10 m
2

Vo 0 . 713

(3) Actual area = BD + 0.5 D2 = 56.1

B x 1.5 + 0.5 (1.5)2 = 56.1

B = 36.65 m

(4) P = B + 5 D = 36.65 + 5 x 1.5

= 40.386 m.

A 56.1
(5) R=   1.40
P 40.386

(6) V = C RS

1 0.00155
23  
N S
C 
0.00155 N
1  (23  )
S R

1 0.00155
23  
-4
0.0025 1.6 x 10
C   47 . 50
0.00155 0.0225
1  (23  )
-4
1.6 x 10 1.40

4
V  42.56 1.40 x 1.6 x 10  0.7118 m/s

38
Problem-2: Design a canal for 50 cumec discharge by Kennedy’s theory. The

other data required is given as N = 0.0225, meter and S = 16 cm per km.

Solution: Assume depth of the canal = 2m

(1) Vo = 0.55 m D0.64 = 0.55 (1) (2)0.64

= 0.857 m/s

Q 50
(2) A    58 . 337 m
2

Vo 0 . 857

(3) A = BD + 0.5 D2

58.337 = 2B + 0.5 x 4

B = 28.168

(4) Wetted parameter P = B+5 D = 32.64 m

A 58.33
R    1.787
P 32.64

(5) N = CRS

1 0.00155
23  
5
x 10
0.0025 16
C   49 . 76
0.00155 x 105 0.0225
1  (23  )
16 0.863

16
S 
1000 x 100

16
V  49.69 0.863 x
1000 x 100

V = 841 m/s

V 0.841
M    0.98
Vo 0.857

39
Hence reducing the depth of the canal.

Assume D = 1.8 m, Vo = 0.001 m/s Vo = 0.979

Next value of D = 1.75 m,

B = 35.475 m, Vo = 0.786 m/s V = 0.785 m/s OK

Problem-3: Design an irrigation channel to carry a discharge of 30 cumec.

Assume a value of N = 0.0225, and m = 1. The canal has a bed slope of 0.2 m

per km.

Solution-1: Assume D = 2m.

2. Vo = 0.55 m D0.64 = 0.55 (1) (2)0.64

= 0.857 m/s

Q 30
3. A    35 sq.m.
Vo 0.857

4. A = BD + 0.5 D2

35 = B x 2 + 0.5 x 4

B = 16.5 m

5. Wetted parameter P = B + 5 D = 16.5 + 5 x 2

= 20.97 m

A 35
R    1.67 m
P 20.97

V = C RS
0 .2 1
6. S  
1000 5000

40
1 0.00155
23  
0.0025 1/5000
C   48 . 97
0.00155 0.0225
1  (23  )
1/5000 1.67

V  C RS  48 . 97 1 . 67 x 1 / 5000  0 . 895 m / s

V 0 . 895
m    1 . 044
Vo 0 . 859

Second Trial: Though CVR is very near to one let us have a second trial to get

a more closer value.

Since Vo is less than V, let us increase the depth D slightly and vice

versa.

The %age increase in B should be approximately equal to double the %

difference in CVR.

(1.044  1)
 x 100  4.4%
1

Double m = 8.8 ~ 10%

Hence increase D by 10%

So now trial value of D = 2.2 m

1. D = 2.2 m

2. Vo = 0.55 m D0.64 = 0.55 (1) (2.2)0.64= 0.910 m/s

Q 30
3. A    32.931 m
2

Vo 0.910

4. A = BD + 0.5 D2

32-931 = 2.2 B + 0.5 x (2.2)2

B = 13.868 m

41
5. Wetted perimeter

P = B + 5 D = 13.868 + 5 (2.2)

P = 18.788 m

A 32 . 931
R    1 . 7527
P 18 . 988

6. V = CRS

1 0.00155 x 5000
23  
0.0025 1
C 
0.00155 x 5000 0.0225
1  (23  )
1 1.7527

C = 45.951

1.7527 x1
V  C RS  45.951  0.860
5000

V 0.860
m    0.945
Vo 0.910

Problem-4: Design an irrigation canal to carry a discharge of 28 cumec.

A
Assume N = 0.0225, m 21, and  7.6
D

Solution: Side slope = ½:1 Design by Kennedy’s theory.

Let the depth of the channel be D

Let width of B of the channel be 7.6D

Velocity in the channel

V = 0.55 m D0.64

Keeping m = 1, V = 0.55 D0.64

Area of channel section = BD + D2/2 (1/2:1)

42
= 7.6 D2 + D2/2 = 8.1 D2

Since Q = AV

28 = (8.1D)2 (0.55 D0.64) = 4.46 D2.64

28
  6.28
2.64
D
4.46

D = 2.01m, B = 15.3 m,

Hydraulic mean radius R = A/P

BD  D /2
2

R 
B 5D

2
8.1 D
R 
7.6D  2.23D

But D = 2.01 m,

R = 1.66m,

Vo = 0.55 (2.01)0.64 = 0.86 m/s

By applying Kutter’s formula

V  C RS

where,

1 0.00155
23  
N S
C 
0.00155 N
1  (23  )
S R

1 0.00155
23  
N S
RS  0.86
0.00155 N
1  (23  )
S R

43
1 0.00155
23  
0.0225 S
1.66  0.86
0.00155 0.0225
1  (23  )
S 1.66

or 67.4S3/2 – 0.885S + 0.00155S1/2 – 1.42x10-5 = 0

1
By trials and error S 
6250

1
Hence S  , B = 15.3 m, D = 2.01 m.
6250

Problem-5: Design an irrigation canal to carry a discharge of 14 cumec.

Assume N = 0.0225, m = 1 and B/D = 5.7

Solution: Given that B/D = 5.7

Cross-sectional area of canal = BD + 0.5D2

= D2 [B/D + 0.5]

A = D2 [5.7 + 0.5] = 6.2D2

Vo = 0.55 m D0.64

Vo = 0.55 D0.64

Q = AVo = 6.2 D2 x 0.55 D0.64


1
Q
D  [ ] 2.64
6.2 x 0.55

1
14
D  [ ] 2.64  1.71 m
6.2 x 0.55

B = 5.7 D = 9.74 m.

Vo = 0.55 (1.71)0.64 = 0.775 m/s

44
9.74 x 1.71  0.5 (1.71)
2

R   1.335 m
9.74  5 (1.71)

By Kutter’s equation

V = CRS

1 0.00155
23  
N S
V  RS
0.00155 N
1  (23  )
S R

1 0.00155
23  
0.0225 S
0.775 
0.00155 0.0225
1  (23  )
S 1.335

 0.00155 0.0225   1 0.00155 


0.775 1  (23  )    23    1.335S
 S 1.335   0.0225 S 

1  0.448 
0.775 5  1/2
 (3.018  0.00155
1/2
x 10 )/S 67.44 S S
1.335

5
(2.024 x 10 )  1/2
  67.44  0.00155
1/2
0.9712 S S
S

67.44 S3/2 – 0.9712 S + 0.00155 S1/2 – 2.024 x 10-5 = 0

S3/2 – 0.0144 S + 2.298 x 10-5 S1/2 – 3 x 10-7 = 0

1
Assume S 
1000

1 1 5 1 7
 0.0144 )  2.278 x 10  3 x 10  0
3/2 3/2
( ) ( ( )
1000 1000 1000

Not satisfied

1
Assume S 
5000

45
3/2 1/2
 1   1  5  1  7
   0.0144    2.298 x 10    3 x 10 = 0 satisfied
 5000   5000   5000 

1
... S 
5000

LACFY’S REGIME THEORY

According to Lacey the dimension i.e. width, depth and slope of a regime

channel to carry a given discharge and a given silt charge are all fixed by nature.

Regime Channel: A channel will be in regime if it flows in incoherent

unlimited alluvium of the same character as that transported and the silt-grade

and silt charge all are constant.

A channel is said to be in regime when the following conditions are

satisfied.

(1) The discharge of the channel is constant.

(2) Silt grade and silt charge are constant.

(3) Channel is flowing in unlimited in coherent alluvium of the same

character as that transported.

(4) The channel has freedom to form its own section.

If all the above four conditions are satisfied then the channel is said to be in true

regime.

Incoherent alluvium: It is a soil composed of loose granular graded material

which can be scoured off with the same ease with which it is deposited.

1. Initial Regime:

46
If a channel is excavated with some deflective slope and somewhat

narrow section, it is free immediately, to throw down the incoherent silt on the

bed thereby increasing its bed slope and generating the increased velocity to

achieve a non-silting initial regime. The conditions of initial regime are

applicable to all those channels which have a considerable lateral restraint. Thus

a channel in initial regime attains a working stability and it neither silts nor

scour. It can be said that Kennedy’s theory is rough initial regime theory.

2. Final Regime: A channel which has formed its shape and slope in its own silt

finally is said to be in final regime. If the silt content or discharge is altered then

some changes occur till the final regime is obtained. To attain the final regime,

the channel forms its section first before the final slope. A channel can attain

final regime only if there is no lateral restraint. Natural silt transporting channel

have a tendency to assume a semi elliptical section. The coarser the silt, the

flatter is the semi-ellipse i.e. greater the width of water surface. If the silt is fine,

the section tends to a semi circular shape.

If a channel is designed with a section too small for a given discharge and

it is kept steeper than required, scour will occur till final regime is obtained. On

the other hand if the section is too large for the discharge and slope is kept

flatter then required, silting will occur till final regime is obtained.

47
Permanent Regime: When a channel is protected on the bed and side with

some kind of protecting material, the channel section can’t be scoured off and

so there is no possibility of change of section or longitudinal slope. The channel

is then said to be in permanent regime. Regime theory is not applicable to such

channels.

LACEY’S EQUATIONS:

1. Perimeter discharge relation (P-Q relation)

P  4.75 Q

2. Velocity discharge relation (V-Q-f, relation)


1/6
 Qf 
2

V   
 140 

Where f = silt factor given by

f = 1.76 mr

Where mr = mean particle diameter of silt in mm.

3. Regime slope equation (S-Q-f relation)


5/3
f
S  1/6
3340 Q

4. Regime scour depth equation (R-q-f relation)


1/3
q 
2

R  1.35  
 
 f 

48
Q 
q = Discharge per unit width  
 B 

Steps to be followed in the design of canal:

(By Lacey’s method)

(1) Given discharge Q and the silt factor f, calculate the regime velocity by

the relation
1/6
 Qf 
2

V   
 140 

(2) Knowing the velocity, determine the area of cross section of the canal by

continuity equation.

Q
A 
V

(3) Determine the wetted perimeter of the canal by the relation

P  4.75 Q

(4) Knowing A and P, determine B and D by assuming the side slope of the

canal as 1/2:1

A = BD + 0.5D2

P = B + D5

Solution of these two simultaneous equations gives the value of B and D.

(5) In order two check the numerical work, calculate R from two independent

relations.

BD  0.5D
2

R 
B  D 5

49
Both the values of R should be same. If not, check the numerical work of steps

1 to 4.

(6) Determine the bed slope of the canal by the relation


5/3
f
S  1/6
3340 Q

Problem-1: Using Lacey’s equation design an irrigation canal for the following

data.

Discharge Q = 20 cumec, Silt factor = 1.00 and side slope = 1/2:1.

Solution:

1. Given Q = 20 cumec, f = 1.00


1/6
 Qf 
2

V   
 140 

1/6
 20 x (1) 
2

  
 140 

V = 0.723 m/s

Q 20
2. A  
V 0.723

A = 27.66 m2

3. P  4.75 Q

 4.75 20  21.24 m

P = 21.24 m

4. 27.66 = BD + 0.5D2 …….. (1)

50
21.24 + B + D5 …….. (2)

From equation (2) B = 21.24 - 5D sub in equation (1) then we have,

27.66 = (21.24 - 5D) D + 0.5 D2

D2 – 12.234 D + 15.93 = 0

12.23   4 x 15.93
2
(12.23) 12.23  9.26
D    1.48 m,  10.75
2 2

B = 21.24 - 5 (1.48) = 17.93 m,

5/3 5/3
f (1) 1
5. S  1/6
 1/6

3340 Q 3340 (20) 5503

BD  0.5 D
2
A
Check: R  
P B 5D

17.93 x 1.48  0.5 (1.48)


2

R   1.30 φ m,
17.93  5 (1.48)

2
5 V 5
R    1.306
2
x (0.723) m
2 f 2

Since both the values of R are same, design of given canal is correct.

For Q = 40 cumec, Side slope = 1/2:1, f = 1

D = 1.83 m R = 1.64

B = 25.95 m S = 1/6177

Balancing Depth:

51
If the section of canal is in partial cutting and partial filling and the

amount of cut and file is equal, then the canal section is said to be economical.

For a given cross-section, there is always only one depth for which the cutting

and filling will be equal. This depth is known as balancing depth.

Let h = vertical height of top of bank from bed of canal.

B = bed width of channel

t = top width of canal bank

n:1 = side slope of canal in cutting

z:1 = side slope of bank in filling

y = full supply depth of the channel.

... Area of the cut = BD + nD2

Area of the fill = 2 [(h-D)t + z(h-D)2]

equating the area of cut and fill

(BD+nD2) = 2 [(h-D)t + z(h-D)2]

BD + nD2 = 2[ht-Dt + z(h2+D2-2h.D)]

BD + nD2 = 2ht - 2Dt + 2zh2 + 2zD2 - 4 zh.D

nD2 – 2zD2 + BD + 2Dt + 4zhD - 2ht – 2zh2 = 0

(n-2z)D2 + (B+2t + 4zh)D - 2h (t+zh) = 0

or (27-n)D2 - (B + 2t + 4zh) D + 2h (t + zh) = 0

A canal is usually constructed with a side slope of 1:1 in cutting and a

slope of 1.5:1 in filling. Therefore, putting Z = 1.5 and n = 1 in the above

equation, we get,

52
2 D2 - (B + 2t + 6h)D +h (2t + 3h) = 0

or D2 - (B/2 + t + 3h)D + h(t + 3/2h) = 0

53
UNIT – III

Head Works: A hydraulic structure which supplies and regulates the supply of

water to the canal is known as head work. Head works are of two types:

(1) Storage head work

(2) Diversion head work

Storage head work involves the construction of a dam to store the excess water

during monsoon and to supply the same during dry periods. A diversion head

work diverts the river water into the canal. A diversion head work serves the

following purposes.

(1) It raises the water level in the river so that commanded area can be

increased.

(2) It regulars the intake of water into the canal.

(3) It controls the silt entry into the canal.

(4) It reduces fluctuations in the level of supply in the river.

54
(5) It stores water for balancing the demand and supply over small

periods.

PARTS OF A DIVERSION HEAD WORKS:

(1) Weir / Barrage

(2) Divide wall

(3) Fish ladder

(4) Log channel

55
(5) Pocket or approach channel

(6) Scouring sluices

(7) Silt prevention devices

(8) Canal head regulator

(9) River training works (Marginal bund and guide bank)

(10) Piers and abutments

(11) Protection works

1. Weir

The weir is a solid obstruction across the river to raise the water level and

divert the water into the canal. Weirs are of various type.

56
(1) Vertical drop weir.

(2) Masonry or concrete slope weir

(3) Dry stone slope weir

(4) Parabolic weir

TYPICAL SECTION OF A BARRAGE

(1) Barrage:

The function of a barrage is similar to that of a weir, but the heading up

of water is affected by the gates alone. No solid obstruction is put across the

river. The crest level of the barrage is kept at a low level. During the floods, the

gates are raised to clear off the high flood level enabling the high flood to pass

down stream. When the flood recedes, the gates are lowered and the flow is

obstructed, thus raising the water level to the upstream of the barrage. Due to

this there is less silting and better control over the levels.

However, barrages are much more costlier than weirs. Due to this region

reason barrages are usually not constructed as a separate project but they are

combined with the bridge project so as to make it economical.

57
(3) Divide Wall: A divide wall is constructed across the barrage close to

the head regulator to separate the under sluices from main barrage

bays (passage between to pier). It isolates the pocket from the main

flow and creates a still pool water in front of canal H.R. thereby

minimizing the silt entry into the canal.

(3) Fish Ladder: Fish ladders are generally provided to enable the fish to

proceed the head waters of the river in order to search their food.

(4) Pocket or approach channel: Pocket is a still pool of water in front of

the off taking canal. The purpose of the pocket is to minimize the silt entry into

58
the canal. Due to the less disturbance in pocket, mist of the silt is thrown off on

the bed and relatively clear water enters the canal.

(5) LOG Channel: This is a fast flowing channel adjacent to the divide wall

or fish ladder and is used to allow the passage of wooden log and dead bodies

during floods.

(6) Scouring Sluices: (or under sluices) These are the controlled opening in

weir or barrage. The purpose of under sluices is to scour the silt deposit in

pocket in front of the head regulator. It lowers the H.F.L. by passing heavy

discharges when required.

(7) Silt Prevention Devices: For the prevention of silt entry into the canal,

silt excluders and kings varies are used.

Silt Excluder

59
It is constructed on the river bed in front of the head regulator in the pocket. It

consists of tunnels of different length covering the full length of the head

regulator and discharging into first two bays of under sluices. The bottom layers

of sediment laden water are adverted through the tunnels back into the river by

putting a diaphragm at a suitable height without disturbing the sediment

distribution. The example of silt excluder can be cited at lower Chenab canal at

Khanki head works.

60
King’ Vanes

61
These silt varies are vertical diaphragm walls parallel to each other, starting in

line with the current and terminating at an angle with it. They are of low height

so as to divert bottom layers of water loaded with sediment away from the head

regulator.

(8) Canal head regulator:

A head regulator is a structure constructed at the head of a canal taking

off from a reservoir behind a weir or a dam. A head regulator serves the

following functions.

(1) Regulates the supply of water in the canal

(2) Controls the entry of silt in the canal

It consists of steel gates separated by piers. The regulation is done by means of

gates. The head regulator is normally aligned between 90 o to 127o to the axis of

the weir. For min sediment entry into the canal, the angle should be kept

between 105o-110o and the crest of the head regulator should be kept about 1 m

higher than the crest of under sluices.

(a) River training works:

Following are the river training works generally provided on canal head

works:

(1) Marginal Bund

(2) Guide Banks

(3) Spurs and Groynes

62
Marginal bunds are provided to protect the land and property against

submersion during high flood while rest of the structures are meant to confine

the river in its own course.

(10) Inverted Filters:

It is a layer of graded material and it prevents water mixed with soil to

come up on the down stream side of the barrage. It is known as inverted filter

because the process is reversed in direction as compared to filter.

63
(11) Pile lines

Pile lines are sheet obstruction provided at the beginning and end of

impervious floor in order to increase the stability and to keep the exit gradient

within permissible limit. In addition to these two pile lines there may be a third

or fourth pile lines known as intermediate pile serving as additional safety

measure.

(12) Impervious floor:

It is a concrete floor or sometimes a R.C.C. floor. Thickness of floor

varies according to the pressure of water. The floor is designed to counter

balance the effect of uplift pressure of water which acts below the impervious

floor in upward direction.

Difference between Barrage Barrage Weir


and Weir SL
(a) Low set crest High set crest
(b) Ponding is done by means of Ponding is done against the
gates raised crest or partly against
crest and partly by shutters
(c) Gated over entire length Shutters in part length
(d) Gates are of greater height Shutters are of smaller height, 2
m
(e) Gates are raised clear off the Shutters are dropped to pass
high floods to pass floods floods
(f) Perfect control on river flow No control of river in low
floods
(g) Gates convenient to operate Operation of shutters is slow,
involve labour and time
(h) High floods can be passed with Excessive afflux in high floods
minimum afflux
(i) Less silting upstream due to low Raised crest causes silting
set crest upstream
(j) Longer construction period Shorter construction period
(k) Silt removal is done through No means for silt disposal
under sluices
(l) Road and/or rail bridge can be Not possible to provide road-
constructed at low cost rail bridge
(m) Costly structure Relatively cheaper structure

64
RIVER TRAINING WORKS

River training works covers all those engineering works which are

constructed on a river so as to guide and confine the flow to the river channel.

Stabilizing and training the river along a certain alignment with a suitable water

way is therefore, the first and foremost aim of river training. The river training

works may serve the following objectives.

(1) To prevent the river from changing its course and to avoid out

flanking of structures like bridges, weirs, aqueduct etc.

(2) To prevent flooding of surrounding area by providing a safe passage

for the flood waters without over topping the banks.

(3) To protect the river banks by deflecting the river away from the

attacked banks.

(4) To provide minimum water depth required for navigation.

Types of river training works:

(1) Marginal embankment or levers.

(2) Guide banks

(3) Groynes or spurs

(4) Artificial cut offs

(5) Pitching of river banks

(6) Pitched islands

65
(1) Marginal embankment or levers:

Marginal embankments or levees are generally earthen embankments,

running parallel to the river at some suitable distance from it. They may be

constructed on both sides of the river or on one side for some suitable river

length where the river is passing through towns or cities. These embankment

wall, retain the flood water and prevents it from spreading into the nearby lands

and towns.

The alignment of levees should follow the normal meandering pattern of

the river. The levees are many times pitched on the upstream side (water side)

launching apron may also be provided if the bank is close to the main river

channel.

(2) Guide banks:

If an engineering structure such as a weir, barrage or bridge is

constructed, the river width is reduced and trained to dispose off the flood water

safely. It is well known that alluvial rivers have a tendency to shift their courses,

so if a structure such as a bridge is constructed across the existing river width

the other day, the river may shift, and there may not be any river water below

66
the existing bridge and the river will be found flowing away from it,

necessitating the construction of another structure. Hence a structure such as a

weir, barrage or bridge is constructed in a smaller width of the river and the

river water is trained to flow almost axially through this path without flanking

its structure.

The river is normally trained for this purpose with the help of a pair of

guide banks. The guide banks are generally provided in pairs. Usually they are

symmetrical and parallel. The guide banks usually consist of two heavily, built

embankments in the river in the shape of a bell mouth.

67
NORMAL GROYNE

68
(3) Groynes or Spurs:

Groynes are the embankment type structure constructed transverse to the

river flow extending from the bank into the river. That is why they may also be

called transverse dykes. They are constructed in order to protect the bank form

which they are extended by deflecting the current away from the bank. As the

water is unable to take a sharp curve, the bank gets protected for a certain

distance up-stream and down stream of the groyne. However, the nose of the

groyne is subjected to tremendous action of water and has to be heavily

protected by pitching etc.

The groynes may be built either perpendicular to the bank line or they

may be inclined upstream or down stream as shown in the figure. A groyne

pointing upstream has the property of repelling the flow away from it, and scour

holes caused by formation of vertical eddies are developed away from the bank.

Such groynes are called repelling groyne. On the other hand, a groyne pointing

down stream has the property of attracting the flow towards it and is called

attracting groyne. In an attracting groyne, scour holes are developed nearer the

bank as compared to those in repelling groyne. Since an attracting groyne brings

69
water current as well as scour holes nearer the bank, makes it more susceptible

to damage. They are not generally used. The groynes are therefore aligned

either perpendicular to bank or pointing upstream.

70
(5) Artificial cut offs:

A meandering river has a tendency to attain its original straight flow by

means of a cut off. A cut off channel may develop itself or may be induced

artificially. When the meander goes on increasing, it may damage some

valuable property or land, and then the river course may be straightened by

inducing an artificial cut off. The newly developed course will be far away from

the establishment or properties which would have been affected other wise. For

inducing an artificial cut off, only a pilot channel is require to be excavated in

case of rivers having easily errodible beds. The flood water will gradually

enlarge the pilot channel to the required cross section and will abandon the old

curved channel.

71
Types of groynes: Based upon the material of construction, the groynes may be

divided into two types, namely:

1. Impermeable groynes

2. Permeable groynes

Impermeable groynes: We also called as solid groynes or embankment

groynes. These groynes may be rock fill embankments or earthen embankments

protected with stone pitching or concrete blocks etc. These groynes are called

impermeable groynes because they do not allow any significant flow through

them. Their design is the same as that for the guide bank with an apron.

Commonly adopted dimension of the groyne embankment are

Free board – 1m, Top width = 3m, Side slopes = 2:1

Head (nose) = square and having slope of 5:1

Permeable groynes: Permeable groynes permit restricted flow through them.

These groynes are more or less temporary structures liable to be damaged by

floating debris. The common materials used as permeable groynes are:

(a) Trees used as groynes called ‘Tree spurs’.

(b) Timber stakes or wooden piles called Balli spurs

(c) Stone filled in balli crates

(d) Stone filled in wire crates

72
Balli spurs are being successfully used now-a-days on many rivers in

plains and are becoming very popular. In such spurs, saal ballies are driven

vertically into the river bed projecting from the bank to be protected, at suitable

spacing of about 1 m in two rows in zigzag manner. The top level of ballies is

kept at about 15 cm above the dry weather flow of the river. The ballies are

connected at top by cross ballies and longitudinally by longitudinal ballies as

shown in Fig.

BALLI SPUR

Balli spurs promote silting near the bank thus avoids the erosion of bank.

Balli spurs constructed on Yamuna river near Khizrabad village in Delhi are

successfully working.

73
T-shaped groynes: Denhey’s T-shaped groyne is a special typeof groyne

developed in India. It is an ordinary groyne provided with an extra cross groyne

at the head giving it a T-shape. The cross groyne protects the main groyne on

the sameprinciple as the main groyne saves the bank. These groynes are usually

spaced at 800 m apart.

Hockey shaped groyne: These groynes are shaped like a hockey stick at their

lower end. These groynes are attracting type groyne and hence are not useful for

bank protection.

74
75
CROSS DRAINAGE WORKS

During the course of flow of a canal, it has to cross natural stream and

rivers. Since both the canal and the natural stream has to go their way without

any hindrance some permanent work has to be constructed, to ensure the

passage of canal and natural streams across each other. These works are known

as cross drainage works.

Types of cross drainage works:

(1) The aqueduct

(2) The Siphon aqueduct

(3) The super passage

(4) The siphon super passage

(5) Level crossing

76
1. AQUEDUCT: The aqueduct is type of cross drainage work in which

canal water is taken across the natural stream by allowing it to flow over the

stream in masonry flumed channel constructed and supported over the natural

stream like an ordinary bridge. The difference being that while a bridge carries a

road way or a railway, the aqueduct carries a canal. The conditions for the

construction of an aqueduct are that the margins between bed of the canal and

the highest flood level in the drainage should be such as to allow sufficient

77
margin for free board. Aqueducts are generally constructed at places where

canal is situated at levels higher than natural drainage.

2. SIPHON AQUEDUCT:

Siphon aqueduct is similar to an aqueduct with a difference that the

drainage instead of simply passing under the canal has to be lowered to form a

siphon. This becomes necessary where the canal runs over the drainage, but the

margin is not sufficient for the free passage of canal water over the drainage

water. In a siphon aqueduct the water of the drainage is depressed before entry

into the barrels provided under the canal. It flows past the barrels and comes up

on the other side due to its own head. Some head is of course lost in friction

while the water flows under the canal.

78
3. SUPER PASSAGE:

Super passage is a cross drainage work where drainage water flows over

the canal in an artificial trough constructed for it. Super passage is generally

found in the head reaches (initial reach) of a canal, when the canal is in deep

cutting. The discharge of a canal is known while the maximum discharge of a

drain has to be estimated. When the super passage is proposed the discharge

should be estimated very accurately. This is necessary because of the danger of

79
failure of the work, in case of he discharge of drainage exceeds the designed

value.

Another difficulty in the construction of a super passage is the necessity

to construct heavy river training works, so that the flow of the drainage is

always ensured over the crossing. The necessary condition for the construction

of super passage is that the bed level of drainage should be at a level higher than

the full supply level of the canal to allow sufficient margins for the free board.

80
4. SIPHON SUPER PASSAGE:

This is a structure constructed where the canal water is siphoned under

the drainage. This work is constructed where the drainage although flowing at a

level higher than canal, has a small margin, not sufficient to allow for the free

passage of drainage water over the canal. In this case, a passage is constructed

under and across the drainage at a level below the normal level of the canal. The

canal water is depressed and allowed to flow through the depressed passage. It

comes up on the other side after crossing with some loss of head due to friction.

5. LEVEL CROSSING:

When the canal and the drainage crosses each other, situated almost at the

same level, the cross drainage work that may be constructed is level crossing. In

level crossing both the channels cross each other such that water of one channel

mixes with that of the other. To check the downward flow of water, in both the

channel regulating gates or weir with falling shutters are provided on the

81
drainage, just below the crossing and a regulator is constructed across the canal,

also just below the crossing.

The working of the level crossing assumes that while one channel is

running full, the other one not working. This condition is actually fulfilled,

because during rains, when the drainage carries full discharge no water is

required in the canal. Similarly during winter or summer when full water is

required in the canal, the drainage may not be carrying full water. When the

canal runs, the gates of the regulator on the canal are fully opened but the gates

of the drainage are opened only to pass the discharge equivalent to the discharge

of the drainage in coming at the level crossing to pass through the same way

when the drainage is carrying full water and the canal is not running, the gates

of the regulator on the canal are closed.

82
UNIT – IV

DAM

DAM:

A dam may be defined as an obstruction built across a stream or a river.

At the back of this barrier, water is collected forming a pool. The side on which

water gets collected is called u/s side and other side of the barrier is called d/s

side. The lake of water which is formed at u/s is called a reservoir.

Purpose of a dam: The water stored in the reservoir can be used for irrigation,

water supply, hydropower generation, recreation (entertainment) or for any

other use depending upon the purpose for which the dam has been designed and

constructed.

FACTOR GOVERNING THE SELECTION OF A DAM SITE:

1. Suitable foundation: Solid rock foundation such as granite and gneis

have a high bearing power. They offer high resistance to erosion and

percolation. Almost every kinds of dam can be built on such. Foundation

consisting of coarse sand and gravels are unable to bear the weight of

high concrete gravity dams but are suitable for earthen and rock fill dams.

Silt and fine sand foundation suggest the adoption of earthen dams. A

rock fill dam on such a foundation is not suitable, due to excessive

seepage and settlement problem, clay foundations are unsuitable for

gravity dam and rock fill dam. However, earthen dam may be provided

on clay foundation after special treatment.

83
2. Economy: For economy, the length of a dam should be as small as

possible and for a given height it should store maximum amount of water.

The river valley at the dam site should be narrow, but should open out

upstream to provide a large basin for a reservoir.

3. Topography: The general bed level of the dam site should preferably be

higher than that of river basin. This will reduce the height of dam and will

facilitate drainage problem.

4. Spillway: A suitable site for the spillway should be available in the near

vicinity. If the spillway is to be combined with the dam, the width of the

gorge or canyon should be sufficient enough to accommodate it.

5. Material: Material required for the construction should be easily

available locally or in vicinity so that cost of transportation is reduced.

6. Reservoir: The reservoir basin should be reasonably water tight. The

stored water should not escape on through its side walls & bed.

7. Land and Property: The value of land property submerged by the

proposed dam should be as low as possible.

8. Transportation: The dam site should be easily accessible so that it may

be connected to important cities by rails and roads etc.

9. Colony: Site for establishing a healthy living environment should be

available in the near vicinity.

CLASSIFICATION OF DAMS:

(A) Classification according to their use

84
(1) Storage dam

(2) Diversion dam

(3) Detention dam

1. Storage dam:

This is most common type of dam constructed across a river to store the

water behind it during the rainy seasons and to supply the same when required.

Usually such schemes are multiple purpose schemes i.e. for irrigation, electric

power generation, water supply, flood control and recreation. A storage dam

may be constructed of concrete, rock fill etc. The example of such dam is

Bhakra and Nangal Dam in Punjab and Rihand Dam in U.P. Tehri Dam in

Uttrakhand.

2. Diversion Dam:

Diversion dams are constructed across the river to raise the level of water

at u/s side and divert it into a canal. The height of such dams are small and

hence temporary storage is created. Weirs and barrages are the example of such

dams. Examples of weirs can be seen at Khanki head work and Bhimgoda head

work. Example of barrages can be sited at Narora and Okhla.

3. Detention dam:

These are constructed to store the water during flood and to release it

later on the safe rate. Some times no outlet provided in the dam. Water, is

allowed to stand and percolate in the ground thereby elevating ground water

85
table to facilitate left irrigation. Such type of dam is some times called water

spreading dam or check dam.

(1) Non-over flow dam:

Non-over flow dam is one in which water is not allowed to over top the

dam. The height of dam is fixed such that it is higher than maximum expected

flood level. It may be constructed of concrete, earth masonry earth and rock fill

etc. Examples Idduki dam in Kerala does not have any over flow portion.

(2) Over flow dam: Over flow dam is one in which excess water is allowed

to flow over the crest of the dam. The d/s portion of the dam is made up of rigid

material to resist the erosive action of flowing water. Over flow dams are

commonly known as spillway. Usually the two types of dams are combined in a

river valley project i.e. some port of the main dam is made as over flow dam

(spillway).

(e) Classification according to material:

(1) Rigid dam

(2) Non-rigid dam

(1) RIGID DAM: Rigid dams are those which are constructed of rigid

material such as masonry, concrete, steel and timber. Rigid dam may further be

classified as:

(i) Masonry, concrete or gravity dam

(ii) Arch dam

(iii) Buttress dam

86
(iv) Steel dam

(1) Gravity Dam: Gravity dam is one in which the destabilizing forces, such

as water pressure wave pressure, silt pressure, uplift pressure etc are resisted by

87
the weight of the dam. A gravity dam may be constructed of masonry or

concrete. Masonry is used only for low height dams, while concrete gravity dam

may be of considerable height as Bhakra dam. Gravity dams are the most strong

and stable for the places of heavy rainfall. Its maintenance cost is negligible

however initial cost is high. Also it required sound rocks for its foundation.

(ii) Arch Dam: An arch dam is curved in plan. The major part of its water

bed is carried horizontally to the abutments by arch action. The remaining part

of the load is transferred to the foundation by cantilever action. The weight of

the dam is not utilized to resist the external forces. Hence the section of arch

dam adopted is lesser as compared to gravity dam. The problem of uplift

88
pressure is minimized due to small base width. Hoover dam of U.S.A. (222 m

high) is an example of this type of dam. An arch dam may be of constant radius

type, variable radius type and constant angle type.

DECK TYPE BUTTRESS DAM

89
MULTIPLE ARCH TYPE BUTTRESS DAM

(11) BUTTRESS DAMS: It consist of “number of buttresses or piers which

divides the total span of the dam into a number of spans. To retain the water

90
between the buttresses, horizontal arches or flat deck slabs is constructed. In the

former case, it is known as multiple arch buttress dam, in latter case it is known

as deck type buttresses dam. It is less massive than gravity dam, hence can be

constructed on a weak foundation. Also the problem of uplift pressure is

reduced to a great extent. Amount of concrete used in buttress dam is about 1/2

to 1/3 of the concrete used in gravity dam of the same height. Financial

economy may not be achieved due to high cost of reinforcements and from

work. However, material economy is still there.

2. NON-RIGID DAMS: Non-rigid dams can be classified as:

(i) Earth dam

(ii) Earth and rock fill dam

(i) Earth dam:

91
Earth dams are oldest type of dam used to store the water. In earlier

days earth dams were constructed of low heights. But owing to the

92
development of the knowledge of soil mechanics and advancement of

construction technology, the highest dam in world today are earth

dams. For example Roguni Russia (335 m), Nusek Russia (300 m) and

Tehri dam (260 m in India) are the earth dams.

Earth dams can be adopted on any type of foundation. They can be

constructed with locally available material. They require relatively unskilled

labour and are generally cheaper than other types. Future increment of height is

easier in this case.

(ii) Earth and Rock Fill Dam:

Earth and rocks fill dam are water impounding structure composed of

fragmental material. These material are made up of discrete particles which

have space or voids between them. They derive their strength from position,

93
internal friction and mutual attraction of the particles. Unlike materials when are

rigidly cemented together, they form a somewhat flexible structure, which can

deform slightly to conform to the deflection of the foundation without failure.

Hence such type of dams are adaptable to any kind of foundation.

To prevent the seepage through the body of the dam a clay core is placed

between u/s and d/s shell. This clay core continues as a cut off below the dam. It

may extent upto the impermeable strata or near to it.

Causes of failure of gravity dam:

Following are the modes failure of a gravity dam:

1. Over turning

2. Sliding

3. Compression or crushing

4. Tension

(1) Over Turning:

The over turning of the dam section can takes place when the resultant

face at any section cuts the base of the dam down stream of the toe. In this case

the resultant moment at the toe becomes clockwise and has a tendency to

overturn the dam. On the other hand if the resultant cuts the base within the

body of the dam, there will be no overturning.

94
For stability requirement, the dam must be safe against overturning. The

factor of safety against over turning is defined as the ratio of stabilizing moment

to the over turning moments.

F.O.S. (Factor of safety) 


 (stabilizi ng moment)

 over turning moment

and it should not be < 1.5

(2) SLIDING:

A dam will fail in sliding at its base or at any other level, if the horizontal

forces causing sliding are more than the resistance available to it at that level.

The resistance against sliding may be due to friction alone or due to friction and

shear strength of the joint. If the shear strength is not taken into account the

factor of safety is known as factor of safety against sliding. The factor of safety

against sliding may be defined as ratio of actual coefficient of static friction ()

on the horizontal joint to the sliding friction. The sliding factor is the minimum

coefficient of friction required to prevent sliding.

μ
F.O.S. against sliding 
tan 

It should be greater than 1.

(3) COMPRESSION OR CRUSHING: The maximum compressive stress

occurs at the toe of the dam and hence for safety this should not be greater than

the allowable compressive stress to prevent the material of dam from crushing.

95
(4) TENSION: For stability of dam no tension should be permitted at any

joint of the dam under any circumstance. For moderately high dam, for no

tension to develop, the eccentricity should be less than b/6 where b is the base

width of the dam. In other words the resultants should lie within the middle

third of the base. However in case of extra high dams, 230 to 260 m small

tension within the permissible, limit is generally permitted for comparatively

small periods of loading such as heavy flood or earthquake.

TUBE WELLS

A water well is a hole or shaft usually vertical, excavated in the earth for

bringing ground water to the surface. Well can be mainly divided into two

classes:

(1) Dug wells or open wells

(2) Bored wells or tube wells

An open well is comparatively of bigger diameter and is suitable for discharge

upto 0.005 cumecs. A tube well is a long pipe sunk into the ground with a

strainer which allows water to pass through but prevents sand from coming in.

Types of tube wells:

The tube wells may be of three types:

(1) Strainer well

(2) Cavity well

(3) Slotted well

96
(1) Strainer type tube well: The strainer well is the most common and

widely used well. In this type of well, a strainer which is a special type

of wire mesh is wrapped round the main pipe of the well. The main

pipe contains bigger holes or slots then the opening of the strainer.

The total area of the opening of the tube is kept equal to the openings

of the strainer so that the velocity of flow does not change. The

strainer well may draw water either from an unconfined aquifer of

unlimited extent or from one or more confined aquifer layers. The

strainers are provided only in that length of the pipe where it crosses

the aquifer. The pipe in the aquifer portion is kept perforated. In the

rest of the portion plain or blind pipe as provided. The well is

generally plugged at bottom.

97
(2) Cavity type tube well: This is a special type of tube well in which water

is not drawn from the strainer, but it is drawn through the bottom of the well,

where a cavity informed. The tube well pipe penetrates a strong clay layer

which acts as a roof. The essential condition for a cavity well to function

efficiently is to have confined aquifer of good specific yield and the aquifer

should have strong impervious material above it. In the initial stage of pumping

with help of a centrifugal pump or an airlift pump, fine sand comes with water

and consequently a hollow cavity is formed.

As the special surface area of cavity increases outwards the radial

velocity decreases and the sand particles stop entering the well. At this stage, an

equilibrium cavity formation is established and clean water continues to enter

the well.

98
(3) Slotted type tube wells:

A slotted well is adopted when sufficient depth of water bearing stratum

is not available even upto a depth of 75 to 100 m so that strainer type tube well

can’t be used and suitable strong roof is not available so that a cavity well may

be formed. In such circumstances a slotted well is used and is made to penetrate

to some depth in the water bearing strata. A slotted tube well consist of a slotted

tube penetrating the confined aquifer. The size of the slots may be 25 mm x 3

mm at 10-12 mm spacing. In order to prevent the fine particles entering into the

pipe, it is shrouded with a mixture of gravel and coarse sand.

First of all a casing pipe of 36 cm diameter is lowered and soil is

excavated out. The water bearing strata is penetrated by a depth of about 5 m

length. The perforated pipes some times known as education pipe of 15 cm

diameter is then lowered, the slotted portion being only 5 m long and the rest of

99
the length being of plain pipe. Gravel is then poured from the top upto about 3

to 4 m higher than the perforation level. The casing pipe is then withdrawn and

the well is developed with the help of compressed air pumped into the education

pipe. By developing the well with the help of compressed air the sand

surrounding the gravel filter is freed of finer particles, and the chances of

getting the filter choked are reduced.

STRATA CHART Silt 0

The strata chart shows for a particular silt upto a Coarse 16

depth of 300 to 400 feets all the varieties of soil sand and

available with their thickness and depth at which gravels 68

they are encountered. The composite length of the Clay


80
strainer and in fact even type of tube well is decided Medium

on the basis of this chart. Strata charts are prepared sand


102
on the basis of information supplied by the bores. Clay
106
While, the boring is in progress, borer collects Sand
120
samples of soil in a big wooden box having many Coarse

small compartments specially mode for this purpose. sand and

The borer uses each small compartment for a gravels


141
different layer. Based on these samples, the strata
(feets)
chart is prepared.

100
ADVANTAGES AND DISADVANTAGES OF WELL IRRIGATION

OVER CANAL IRRIGATION:

Advantages:

(1) The well is under the direct control of the owner. Hence wells may be

sunk and equipped as required.

(2) Isolated area can be irrigated by a well.

(3) Supply from a well can be maintained fairly constant.

(4) Since the well is generally centrally located, the loss in transit is very

much reduced. The duty of water in well irrigation is generally higher.

(5) Volumetric assessment is possible.

(6) Well irrigation is helpful in lowering the sub soil water level and in

draining off irrigated land which might become water logged.

In canal irrigation, chances of water logging are much more than in

well irrigation.

(7) Unless drought continues for several years, well irrigation does not

fail in drought seasons, while, a canal may fail.

(8) With the help of well irrigation more than one crop in a year can be

grown.

(9) The well water which is warmer in cold weather and cooler in hot

weather is more agreeable the crops.

(10) Cost of construction of well is low.

101
Disadvantages:

(1) Due to mechanical defects in the pump or due to interruption in

electric supply, water may not be available to the crops in right time.

(2) Since water has to be lifted from the well the working expenses are

very high in comparison to the canal irrigation.

(3) Well irrigation is clear and free from silt. Clear water does not have

the manuring value which silted canal water provides.

(4) Tube well strainer is subjected to progressive deterioration due to

mechanical and chemical action. Thus replacements are necessary

after frequent interval of time.

(5) The maintenance of mechanical and electrical machinery also requires

great care and more funds.

102
UNIT – V

CANAL FALL

Canal Fall:

A fall is an irrigation structure constructed across a canal to lower down

its water level and to destroy the surplus energy liberated from the falling water

which may other wise scour the bed and bank of the canal.

The slope of natural ground is always steeper than the design bed slope of

the canal based on silt theories. If an irrigation canal taking off from its head is

in cutting, it will soon meet the condition when it will be entirely in

embankment. If the canal is in embankment, the cost of construction and

maintenance is very high also the seepage losses are considerable. To avoid this

problem, falls are introduced at appropriate places. Arrangements are made to

dissipate the energy of falling water.

103
Types of fall:

(1) OGEE FALL: This fall has gradual and concave curves, with an aim to

provide a smooth transition and to reduce disturbance and impact.

104
(2) RAPID FALL:

These falls consist of a glacis sloping at one vertical to 10-20 horizontal.

The long glacis assured the formation of hydraulic jump. Hence the fall works

satisfactorily. However, the cost of construction is high.

105
(3) STEP FALL:

The total amount of drop is divided into 3 to 4 steps in this type of fall.

106
(4) NOTCH FALL:

These falls were designed for high discharges. The fall consist of one or

more trapezoidal notches in a high crested wall. As the channel approached the

fall, there was neither draw down nor heading up of water. The trapezoidal fall

was very successful and was adopted in India for many years.

(5) GLACIS TYPE FALL:

107
MONTAGUE FALL

The glacis type fall may either be straight glacis fall or parabolic glacis

fall. The parabolic glacis fall is also known as Montague fall.

108
(6) VERTICAL DROP FALL:

In the vertical drop fall, nappe of water impinges into the water cushion

below. The Sarda type fall is a type of vertical drop fall. In this type of fall, the

high velocity jet enters the deep pool of water in the cistern and the dissipation

of energy is affected by turbulent diffusion.

109
(7) SARDA TYPE FALL:

This type of fall was designed and developed for Sarda canal system in

U.P. This fall has been constructed for drops varying from 0.9 to 1.8 m. In

earlier designs, the cistern was not depressed below the down stream floor and

the down stream wings were not flared. This resulted in erosion of banks to the

down stream of work. Later some recommendations were made for the design.

DESIGN OF SARDA TYPE FALL:

The complete design of the fall consist of the design of the following

component parts:

(1) Crest (crest)

(2) Cistern

110
(3) Impervious floor

(4) Down stream protection

(5) Design of u/s approach

(1) DESIGN OF CREST:

(i) Length of crest:

The length of crest is kept equal to the bed width of the canal and no

fluming is done in this type of fall. Some times however, the length of crest is

kept equal to the bed width of canal plus the water depth to take into account the

increase in discharge at a future date.

(ii) Shape of the crest and discharge formula:

Two types of crest are used as shown in figure. The rectangular crest is

used for discharges upto 14 cumecs and the trapezoidal crest is used for

discharge over 14 cumecs.

(A) For the rectangular crest:

(a) Top width of the crest is given by:

BTOP = 0.55 d (in m)

(b) Base width is given by:

H  d
B base

ρ

111
For masonry crest,  may be taken as 2 (two)

(c) Discharge through the crest is given by:


1/6
 H 
Q  1.835 LH
3/2




…… (1)
 BT 

Q = Discharge (cumecs)

L = Length of crest (m)

H = Height of water on u/s side above the crest level (m)

BT = Width of the crest (m)

(B) For trapezoidal crest:

(a) Top width of the crest is given by

B TOP  0.55 H  d

(b) u/s batter (slope) = 1:3

D/S batter (slope) = 1:8

Thus the base width is determined by the batter.

(c) The discharge through the crest is given by:


1/6
H 
Q  1.99 LH
3/2
  …… (2)
 B 

(iii) Crest level: From equation (1) and (2) the value of H is calculated.

Therefore, R.L. of crest = u/s F.S.L. – H

Height of crest above u/s bed level (h) = D-H

112
Brick pitching is laid on a slope of 10:1 for 2 to 4 m length u/s of the

crest, and drain holes are provided in the crest at this level to drain out the u/s

bed during the closure of the canal.

(2) DESIGN OF CISTERN:

The length depression of the cisterns are given by the following equation:

l c  5 (E.H
1/2
L
)

1
and x  (E.H L
)
2/3

where lc = length for cistern

(3) DESIGN OF IMPERVIOUS FLOOR:

Total length of impervious floor is determined either by Bligh’s theory or

by Khosla’s theory. The maximum seepage head occurs when there is water on

the upstream side upto the top of crest and there is no flow to the d/s side. From

the figure the maximum seepage head = d. Out of the total impervious floor

length, a minimum length (ld) to be provided to the D/S of the crest is given by

the following expression.

l d  2 (D_  1.2)  H L
(m)

The balance of the impervious floor length may be provided under and upstream

of the crest. The thickness of the impervious floor, is determined by Khosla’s

theory. However a minimum thickness of 0.3 m to 0.4 m is provided for the

floor to the upstream of the crest and for floor to the d/s of the crest, the actual

thickness depends upon the uplift pressure subject to a minimum of 0.3 m to 0.4

113
m for small falls and 1 to 1.5 m for large fall is always provided to the d/s of the

impervious floor.

(4) D/S PROJECTION: The d/s protection consists of:

(i) Bed protection (ii) Side protection (iii) D/S wings

(i) BED PROTECTION: The bed protection consist of brick pitching about

20 cm thick resting on 10 cm ballast. The table below give the length of

pitching and the no. of cut offs to be provided.

Head over crest Total length of Remarks Cut offs


(m) pitching on D/S
(m) Number Depth
(m)

Up to 0.3 3.0 1 0.3


Horizontal upto the ends of
masonry wings and then

0.4 to 0.45 3.0 + 2 HL 1 0.3


sloping at 1 in 10

0.45 to 0.60 4.5 + 2 HL 1 0.45


0.60 to 0.75 6.0 + 2 HL 1 0.60
0.75 to 0.90 9.0 + 2 HL 1 0.70
0.90 to 1.05 13.5 + 2 HL 2 0.90
1.05 to 1.20 18.0 + 2 HL 2 1.05
1.20 to 1.50 22.5 + 2 HL 3 1.35
(ii) SIDE PROJECTION: Side pitching consisting of one brick on edge

provided after the warped wings. The side pitching is curtailed at an angle of

450 from the end pitching in plan. Generally the warping of masonry wings is

done from vertical to slope of 1:1. Hence the side pitching is warped from a

slope of 1:1 to 1.5:1. The pitching is supported on a toe wall 1½ brick thick and

of depth equal to half of depth of water at d/s.

114
(ii) DOWN STREAM WINGS: the d/s wings are kept vertical for a length of 5

to 8 times HLE, from the crest and are then warped to a slope of 1:1. The wings

follow a circular arc, tangential at starting point of warp in plan. These walls are

designed as earth retaining structure.

(5) DESIGN OF u/s APPROACH:

For discharges upto 14 cumecs the u/s wings may be splayed straight at

an angle of 45o. For greater discharges the wings are kept segmental with radius

equal to 5 to 6 times H, subtending an angle of 60 o at the centre and then carried

straight into the berm upto 1 m.

BLIGH’S CREEP THEORY:

The design of impervious floor depends upon the seepage of water in the

pervious soil on which the apron is built. Bligh assumed that the seepage occurs

along the surface of contact of the impervious floor with the pervious

foundation. He gave the same weightage to horizontal and vertical contacts.

In other words, he neglected the effect of sheet pile or a cut off in

reducing the seepage. He assumed that the slope of hydraulic gradient line is

constant throughout the length of apron. According to Bligh, total creep length

for the given figure is

L = 2d1 + l + 2d2

If H is the head loss, the head loss per unit length of creep ‘c’ would be

115
H H
C  
L 2d 1
 l  2d 2

He called the loss of head per unit length of creep as percolation coefficient.

The reciprocal of this i.e. L/H, He called coefficient of creep. He assigned the

values of creep coefficient from 5 to 18 depending upon the size of bed

material. Length of creep for a safe hydraulic gradient is given by

L = CH

Design problem no. 1:

Design a Sarda type fall for the following data:

U/S
(i) Full supply discharge :  40 cumecs.
d/s

U/S 218.30 m
(ii) Full supply level (F.S.L.) : 
d/s 216.80 m

U/S 1 .8 m
(iii) Full supply depth : 
d/s 1.8 m

U/S 2 6 .0 m
(iv) Bed width : 
d/s 2 6 .0 m

U/S 216 . 50 m
(v) Bed level : 
d/s 215.00 m

(v) Drop : 1.5

Design floor on Bligh’s theory taking coefficients of creep = 8.

116
Solution-1: (1) Calculation of H and d:

Refer to main figure:

Since the discharge is more than 14 cumecs trapezoidal crest will be

adopted.

Discharge through a trapezoidal crest is given by:


1/6
H 
Q  1.99 LH
3/2
 
 B 

Given:

L = width of canal = 26 m

Q = 40 cumecs

B = 0.55H+d

But H+d = D + drop in bed level …. (1)

H+d = 1.8 + 1.5 = 3.3 m

... B = 0.55 3.3 = 0.999 ~ 1.00 m

Therefore, Q will be:


1/6
 H 
Q  1.99 x 26 x H
3/2
 
 1.00 

3 1 1/6

1
40  1.99 x 26 x H 2 6
 
1

H = 0.8569 ~ 0.86 m

Substituting the value of H in equation no. (1)

Then we have

d = 1.8 + 1.5 – 0.86

117
d = 2.44 m

Height of crest above bed = D-H

u/s TEL = 1.8 – 0.86 = 0.94 m

(2) Design of crest:

Since the discharge is more than 14 cumecs, trapezoidal crest will

be adopted

velocity of approach va = ?

Assume side slope of the canal as 1:1

x-section area of canal = BD + D2

A = (26+1.8) 1.8 = 50.04 m2

Therefore, velocity of approach can be calculated as

Q 40 cumecs
Va   2
 0.799 ~ 0.8 m/s
A 50.04 m

2 2
V (0.8)
Velocity head    0.032 m
2g 2x9.81

Hence R.L of u/s TEL = u/s F.S.L. + Velocity head

= 218.30 + 0.032 m

= 218.332 m

R.L. of crest = u/s F.S.L. – H

= 218.30 – 0.86 = 217.44 m

118
Value of E = u/s TEL – R.L. of crest

= 218.332 – 217.440 = 0.892 m.

(3) Design of cistern:

Depth of cistern is given as:

1
x 
2/3
[E.H L
]
4

1
x 
2/3
[0.892 x 1.5]
4

HL = Amount of fall = 1.5 m (given)

x = 0.303 m

Length of cistern lc = 5 (EHL)1/2 = 5(0.892 x 1.5)1/2

= 5.78 m.

Keep the length of cistern =6 m

RL of bed of cistern = RL of d/s bed –x

=215.00 – 0.303 = 214.697 m

Keep the RL of cistern at RL 214.7 m

Therefore revised value of x = 215.00 – 214.7 = 0.30 m

4. Design of Impervious floor

Seepage head Hs = d = 2.44 m, Bligh’s coefficient = 8

... Length of impervious floor = CHs =8x2.44

Or creep length = 19.5 m

Provide u/s cut off d1 = 1.0 m and d/s cut off d2 =1.6 m

119
(Assume the depth of cut off from 1 – 3m, greater value in d/s and lesser

value in u/s)

The vertical creep length = 2(1+1.6) = 5.2 m

... Length of horizontal floor = 19.5 – 5.2 =14.3 m

Provide 15 m length of impervious floor.

Minimum length of impervious floor to the d/s of toe of the crest wall

Ld = 2(D+1.2) + HL

= 2(1.8+1.2) + 1.5 =7.5 m

Provide Ld = 8 m. The balance of the floor length i.e. 15-8 = 7 m is to be

provided under and u/s of the crest.

5. Design of d/s wings

Keep the d/s wings vertical for a length of

6HLE = 6(0.892x1.5) = 7 m

Then the wings may be warped to 1:1 slope, at splay of 1 in 3.

6. Downstream Pitching

(a) Bed Pitching:

From the given table length of bed pitching for H = 0.86 m is equal to

(9+2x1.5) = 12 m. This may be provided horizontal upto the end of masonry

wingsand then sloping at 1 in 10.

(b) Side Pitching:

Side Protection consisting of 0.2m thick brick on edge is to be

provided. This pitching has to be warped to a slope of 1.5:1 and to

120
be curtailed at an angle of 450 from the end of bed pitching in plan.

Support the side pitching on a toe wall 0.4 m thick and 1 m deep.

121

You might also like