Professional Documents
Culture Documents
0107
COAL ASSETS
AUSTRALIA
FATAL
HAZARD
PROTOCOLS
OPERATIONS AND PROJECTS
Δ
CONTENTS
Δ Δ7
Background Inadequate
energy isolation
Δ1
Strata failure Δ8
Working at
Δ2 height
Fire and explosion
Δ9
Δ3 Lifting and
Mobile equipment cranage
Δ4 Δ10
Inappropriate Confined space
emergency response and irrespirable
noxious atmosphere
Δ5
Inrush and outburst Δ11
Tyre and
Δ6 rim
Explosives management
and shotfiring
Δ12
Electrical safety
Δ
INTRODUCTION
Commitment to SafeCoal
We are absolutely committed to making
SafeCoal a reality and this can only be
achieved with the combined commitment
of every member of our team and other
relevant stakeholders.
SafeCoal can only be as effective as the
commitment we make to implementing
these protocols whilst continuing to be
vigilant regarding the health and safety of
ourselves and others.
Δ0
BACKGROUND
Background Scope
A review of our recent fatalities, These Protocols apply to Glencore Coal Assets
Australia (GCAA) managed activities, Operations,
high potential risk incidents (HPRIs) sites and facilities, including new acquisitions
and serious incidents identified the and exploration, through all phases of projects,
need for an intervention program to construction, demolition, operation to closure, and
eliminate fatalities and improve our where applicable, post closure activities.
health and safety performance. This These Protocols apply to employees, contractors
program is called SafeCoal and one of and visitors who may be involved in controlled
activities.
its main initiatives is to focus on fatal
hazards. Structure of the Protocols
As a result of these reviews, a number of fatal The structure of the Fatal Hazard Protocols
hazard protocols (Protocols) have been developed includes:
that establish minimum requirements for the man- 1 General Mandatory Requirements (Section 0).
agement of these hazards consistently across our These requirements are to be applied to each
business. These Protocols also provide a number of the Protocols.
of additional expectations (Further Considerations)
that Operations are to consider as part of their con- 2 Individual Fatal Hazard Protocols:
tinual improvement and good practice initiatives.
a) Intent – provides the intent of the protocol.
These Protocols have not been developed to b) Mandatory Requirements – are to be
replace or override local health and safety legis- applied by each Operation, unless it can
lation, or associated legislation and other external be clearly demonstrated and agreed that a
requirements. The content and intent of these particular risk does not exist.
Protocols is to provide minimum requirements.
c) Further Considerations – are to be
The development team reviewed the catastrophic, considered, and if not applied then a
significant, and major hazards that were identi- justification is to be provided.
fied in the various Operations’ Broad Brush Risk
Assessment (BBRAs), the HPRIs, Industry Safety Assurance
Alerts, and the health and safety legislation that Assurance activities are to be conducted as de-
currently exists across the relevant jurisdictions, as tailed in GCAA Standard HSEC – Assurance.
well as other relevant information, including good
industry practice. Operations should be undertaking their own assur-
ance and verification processes from time to time
Context to satisfy themselves that the protocols are being
implemented and maintained, and the require-
It should be acknowledged that these Protocols
ments are being met.
may not represent all of the fatal hazards that
may exist or be faced by our operations, but the A self-assessment tool is available for Operations
outcomes do focus attention on the hazards that to use to internally track and monitor compliance
have resulted in recent fatalities and high potential against these Protocols.
risk incidents.
Variation to the Protocols
The other hazards and associated risks are
being, or will be, addressed through existing risk Deviation from any of the mandatory requirements
management processes, in accordance with GCAA will require formal approval from the General
Standard FIN - Risk Management. Manager – Health, Safety and Training, and the
relevant Operational Director.
Δ0
BACKGROUND
Continued
Δ1
STRATA FAILURE
.·
--
.•
-
--
~-. ' ....
-.,. ~•~ --
~-
."t I I
I I I ;:
I I I I
Δ1
STRATA FAILURE
Continued
Δ2
FIRE AND EXPLOSION
Δ2
FIRE AND EXPLOSION
Continued
Δ2
FIRE AND EXPLOSION
Continued
Δ2
FIRE AND EXPLOSION
Continued
Δ3
MOBILE EQUIPMENT
e) The maximum speeds at which the m) The safe refuelling of the mobile plant
mobile plant and equipment may and equipment.
operate. n) Interaction of mobile plant and
f) Steps to be taken by the operators equipment with fixed structures,
of the mobile plant and equipment to including overhead power lines,
demonstrate that the mobile plant and buildings, elevated structures, or bins.
equipment is safe for use, including o) Specific operational procedures
brake testing, pre-shift inspection and involving certain items of mobile plant
defect reporting. and equipment, e.g. haul trucks queuing
g) Measures to be taken when people at a loader, continuous miners and
are transported in the mobile plant or shuttle cars, etc.
equipment, including the segregation p) Road demarcation and signage.
of people from loads, the provision q) The establishment of designated parking
of seating, the wearing of seat belts, areas, to enable light vehicles to be
and the use of other operator restraint parked in a location, and/or, position that
devices. Where seat belts or other is separated from, and is clearly visible
restraint devices are installed they are
to be used.
Δ3
MOBILE EQUIPMENT
Continued
Δ3
MOBILE EQUIPMENT
Continued
Δ3
MOBILE EQUIPMENT
Continued
Δ4
INAPPROPRIATE
EMERGENCY RESPONSE
Intent clearly signposted), and appropriate
transport and response vehicles.
The intent of this Protocol is to e) Effective and robust communication
eliminate or minimise potential devices and procedures for initial
fatalities, injuries and incidents arising notification of personnel of an
from risks related with inappropriate emergency situation, and for ongoing
response to an emergency situation. two-way communication during
emergency situations.
Mandatory Requirements f) Safe evacuation from all workplaces or
4.1 General other occupied spaces.
4.1.1 A risk assessment is to be conducted and g) Control of site access and restricting
documented to identify potential emergency re-entry to the affected areas.
situations. h) Clearly defined procedures for the
4.1.2 An Emergency Response Management reporting of emergencies, and/or for
Plan is to be developed, implemented and initiating an emergency response.
maintained. As a minimum, it is to include: i) Duty cards that clearly identify
a) Response(s) to, and containment of, each of the responsible person’s
identified emergency situations. duties, functions, and reporting
relationships,refer to GCAA HSEC –
b) Processes to minimise further injury, Incident Management Manual - Part 2
damage, or loss to rescuers or others. – Duty Cards and Task Cards.
c) Emergency response procedures, j) Communication with and involvement of
including first aid, medical treatment, fire external emergency agencies.
fighting, and rescue.
k) Preparation for safe resumption of
d) Provision of adequate emergency normal operations.
equipment, including escape and rescue
apparatus (readily accessible and l) Notification of internal and external
stakeholders.
Δ4
INAPPROPRIATE
EMERGENCY RESPONSE
Continued
Δ5
INRUSH AND OUTBURST
Δ5
INRUSH AND OUTBURST
Continued
Δ6
EXPLOSIVES AND
SHOTFIRING
Intent g) Design of blasts to minimise the risk of
fly rock to persons and/or damage to
The intent of this Protocol is to structures and property.
eliminate or minimise potential h) Quality controls for drilling, loading,
fatalities, injuries and incidents that stemming, and tie-up.
arise from risk associated with the i) Risk controls for drilling, loading,
use of explosives, detonators and stemming, and tie-up.
shotfiring equipment. j) Procedures for barricading and
Mandatory Requirements signposting loaded shots to prevent
unauthorised entry and/or to prevent
6.1 General inadvertent access by person(s), plant,
6.1.1 A risk assessment is to be conducted and and equipment.
documented to identify the hazards and to k) Procedures for loading of explosives
assess the risks associated with the stor- into hot or reactive ground, e.g.
age, issuing, transport, handling, loading, spontaneous combustion areas.
and use of explosives, detonators, and
related equipment. l) Establishment of exclusion zones and
procedures for pre-blast inspection,
6.1.2 An Explosives and Shotfiring Management clearance, and sentry placement, for
Plan is to be developed, implemented and
the safety of person(s), plant, and
maintained. As a minimum, it is to include:
equipment during blasting.
a) Only purchasing explosives and m) Assignment of responsibility for clearing
detonators, and provide shotfiring the shot area to the shotfirer or other
equipment, that is of an approved type, responsible person.
(i.e. permitted by a statutory body for
use in a surface or underground mine) n) Requirement that no shot may be fired
and manufactured to a recognised until the clearance is confirmed by the
quality standard. mining supervisor.
b) A Site Security Plan to prevent o) Procedures for managing misfires
unauthorised access to, or use of, and for the recovery and disposal of
explosives and detonators that are undetonated explosives.
transported to and stored on site. p) Establishment of the competency and
c) Storage of explosives and detonators authorisation requirements for persons
in a safe and secure location, and in a involved in explosives handling and
licensed or approved magazine, with shotfiring, including those specified in
separate storage for explosives and relevant legislative requirements.
detonators. q) Identification of training needs and
d) An inventory system that records the competency requirements of relevant
delivery, issue and return of stock employees and contractors in relation
movements. Only authorised person(s) to explosives and shotfiring, and the
are to issue or receive explosives and provision of adequate training and
detonators. assessment to verify competency.
e) Provision of vehicles or other methods
to transport explosives and detonators
safely on site. Only authorised person(s)
are permitted to travel in the vehicle with
explosives.
f) Appointment of a suitably qualified
person to design blasts.
Δ6
EXPLOSIVES AND SHOTFIRING
Continued
Notes:
Application of this Protocol is to be read with
the General Mandatory Requirements outlined
in Section 0 (Background) of this Fatal Hazards
Protocols Document.
Δ7
INADEQUATE
ENERGY ISOLATION
Intent c) Site requirements for:
►►Individual isolations.
The intent of this Protocol is to
eliminate or minimise potential ►►Group isolations - involves the use of
Permits (refer to GCAA Permit HSEC
fatalities, injuries and incidents arising – Group Isolation).
from risks associated with inadequate
►►High Voltage isolations - involves the
isolation of energy sources. use of Permits, (refer to GCAA Permit
Mandatory Requirements HSEC – High Voltage Access Permit),
except where risk assessment allows
7.1 General otherwise for non-overhead switching
7.1.1 A risk assessment is to be conducted and e.g. longwall electric dump trucks.
documented to identify the hazards and d) Use of locks in preference to danger and
assess the risks associated with interaction permit tags.
with energy sources (electricity, pressure,
temperature stored energy (e.g. springs or e) Use of tags where locks cannot be used.
suspended loads like conveyor takeups) Tags are to be limited to the following
etc.). types:
7.1.2 An Energy Isolation Procedure and Permit ►►Personal danger tags.
System is to be developed, implemented ►►Permit danger tags.
and maintained for relevant energy sourc-
es. As a minimum, it is to include: ►►Out of service tags.
a) The 12-step process for isolations, refer ►►Commissioning tags.
to figure 7-1 below. ►►Information tags.
b) Particular emphasis is to be placed on:
f) Provision of adequate numbers of
►►Identification and dissipation of isolation points on plant and equipment,
relevant energy sources. and in determining locations,
►►Isolating and securing. give consideration to practicality,
accessibility and clear identification.
►►Verification of the isolation, i.e. test
for dead. g) Isolation devices are to be (wherever
possible) lockable and clearly labelled to
identify the equipment that has or is to
be isolated, and to identify whether the
isolation switch or power switch is in the
‘on’ or ‘off’ position.
Figure 7-1 – 12-step isolation process h) For plant and equipment containing
energy sources that cannot currently be
locked out, a risk-based and prioritised
isolate & place tags, locks action plan should be developed to
secure or permits
advise address positive isolation requirements.
relevant verify isolation
parties (test for dead) i) Any person working on high voltage
identify commence
equipment (greater than 1200 volts AC
energy work or 1500 volts ripple free DC) that cannot
sources
be isolated with basic isolation, and
check
complete
work operation cannot verify a break in the electrical
conductors, is to have a permit in place
restore
check energy that incorporates a second competent
work
clear remove tags, electrical isolation verifier; (refer to
area locks or permits
Δ7
INADEQUATE
ENERGY ISOLATION
Continued
Δ8
WORKING AT HEIGHT
Δ8
WORKING AT HEIGHT
Continued
p) Lanyards are to include a shock the user before use, and destroyed
absorber device when being used in following a fall or where inspection has
a fall arrest system, unless it can be shown evidence of excessive wear or
demonstrated that a force of 6kN won’t mechanical malfunction.
be experienced by the harness attached t) Consideration of the means of rescue
point during the fall. of persons who have fallen and are
q) Lanyard anchorage points on apparatus suspended. The appropriate rescue
should be above the head of the worker, equipment and competent employees/
and where practical are to be no lower contractors are to be readily available.
than shoulder height. Where it is u) Factoring in the prevailing environmental
impractical to do so (e.g. on a flat roof), conditions, e.g. wind and rain, that could
a risk assessment is to be conducted have an impact on a person’s ability to
and documented, and alternate work at height safely, and re-inspection
anchorage points selected. and recertification of scaffolding
r) Anchorage points and anchorage following any windy or rainy conditions.
systems are to be signed, tested, 8.1.3 Identification of training needs and compe-
and approved by a competent person tency requirements of relevant employees
to verify that they are capable of and contractors in relation to working at
withstanding a breaking force of 15kN, height.
(single person anchor) or 21kN (two
8.1.4 Provision of adequate training and assess-
person anchor).
ment to verify competency.
s) Fall arrest equipment is to be tested
and certified for use, inspected by
Δ8
WORKING AT HEIGHT
Continued
8.2 Use of ladders above two (2) metres: 8.3 Further Considerations
8.2.1 A person may ascend or descend a ladder 8.3.1 Where applicable to the Operation, or a
without fall protection, provided they are risk is identified, consider the use of the
able to use both hands and legs, maintain following equipment or processes:
three points of contact, they continue to
face the ladder, and only take one rung at a) Using mobile elevated work platforms
a time. for undertaking maintenance activities
on large equipment, including workshop
8.2.2 Extension ladders are to be tied off or and field maintenance activities.
footed, with an angle of one (1) in four (4)
maintained and at least one metre of the b) Installing fixed access platforms on
ladder is to extend above the access or installations and large mobile plant and
work area. equipment where routine maintenance
activities require personnel to work at
8.2.3 If a person is to work from a ladder, fall height.
restraint or arrest devices are to be used,
unless three points of contact can be c) Installing stairways for vehicle access
maintained and the task does not involve in place of ladders for large mobile plant
overreaching. and equipment.
d) Engineering the design of plant and
equipment to eliminate the need for
working at height during maintenance
and construction. For example, lighting
towers or fixed lighting that lower the
lights to the ground.
e) Installing controls or modifying the
existing controls on mobile elevated
work platforms so that the control
functions remain the same regardless of
the orientation of the basket.
f) Using non-corrosive materials in areas
where a corrosive environment exists,
for example, wash plants.
Notes:
Application of this Protocol is to be read with
the General Mandatory Requirements outlined
in Section 0 (Background) of this Fatal Hazards
Protocols Document.
Δ8
WORKING AT HEIGHT
Continued
Δ9
LIFTING AND CRANAGE
Δ9
LIFTING AND CRANAGE
Continued
Δ9
LIFTING AND CRANAGE
Continued
Notes:
Application of this Protocol is to be read with
the General Mandatory Requirements outlined
in Section 0 (Background) of this Fatal Hazards
Protocols Document.
Δ9
LIFTING AND CRANAGE
Continued
Δ10
CONFINED SPACE AND
IRRESPIRABLE
NOXIOUS ATMOSPHERES
Intent ►►The provision and use of safety
harnesses with life lines attached (for
The intent of this Protocol is to recovery of persons in the event of
eliminate or minimise potential rescue).
fatalities, injuries and incidents ►►Access to the permit at the job
arising from risks associated with location.
personnel entering or working in a ►►Sign-in and sign-out of persons who
confined space or a workplace where enter the confined space.
irrespirable or noxious atmosphere ►►Nomination and identification of
may exist. competent stand-by persons, who are
to be present at the entry point for the
Confined Space duration of the work.
10.1 Mandatory Requirements ►►Defined communication methods
10.1.1 A risk assessment is to be conducted and to be used between the stand-by
documented to identify the hazards and person(s) and personnel within the
assess the risks associated with confined confined space.
space entry. ►►Identification of the appropriate
10.1.2 A Confined Space Procedure and Permit specification for the equipment to be
System is to be developed, implemented taken into or used within the confined
and maintained (refer to GCAA Permit space.
HSEC – Confined Space Entry Permit). As ►►Barricading and sign-posting
a minimum, it is to include: requirements.
a) Identification and signposting of ►►An area/task specific Rescue
confined spaces that exist within the Management Plan and provision
operation. and accessibility of suitable rescue
equipment and competent personnel.
b) A Confined Space Register.
c) A documented pre-entry risk e) Requirement that atmospheric
assessment, atmospheric testing and monitoring equipment is to be of an
clearly defined conditions of entry. approved type, listed on a register,
and be inspected, tested, calibrated
d) Conditions of entry are to include: and stored in accordance with the
►►Isolation of energy sources. manufacturer’s specifications.
►►Establishment and maintenance f) Requirement that atmospheric
of oxygen levels required for the monitoring equipment can only be used
duration of the task. by personnel who have been trained,
►►Identification of contaminants, assessed as competent, and authorised.
temperature extremes, g) Identification of training needs and
concentrations of flammable competency requirements of relevant
substances, and any other hazards employees and contractors in relation
that may be harmful. to Confined Space, and the provision
►►Continuous atmospheric monitoring of adequate training and assessment to
of the space for the duration of the verify competency.
task.
►►Establishment of ventilation
requirements, i.e. natural or forced.
►►Identification of the need for use of
self contained breathing apparatus.
Δ10
CONFINED SPACE AND
IRRESPIRABLE
NOXIOUS ATMOSPHERES
Continued
Δ11
TYRE AND RIM
MANAGEMENT
Intent tyres and rim assemblies identified in
FHP 11.1.2e.
The intent of this Protocol is to g) Selection of tools and equipment to be
eliminate fatalities, injuries, and fit for purpose. This includes condition
incidents when working with or near checks and calibration before use of any
tyres, rims, and wheel assemblies. tool used to control pressure or torque
settings.
Mandatory Requirements h) Tyres and wheel assemblies with no
11.1 General recorded maintenance history, or no
11.1.1 The Operation is to complete a document- documented pre-work inspection,
ed risk assessment to identify all hazards to be deflated to zero pressure, and
associated with managing tyres, rims and confirmed, before releasing tension on
wheel assemblies. This includes assessing the rim or wheel assembly fastenings.
the risks and implementing the controls. i) The deflation of all tyres to zero
11.1.2 The Operation is to develop, implement, pressure, and confirmation, before
and maintain a Tyre, Rim, and Wheel releasing tension on the rim fastenings,
Management Plan based on the risk when there is no formal procedure
assessment. As a minimum, the Tyre, Rim, available. A risk assessment, identifying
and Wheel Management Plan is to include specific safe handling pressures, is to
specific requirements for: support all formal procedures for the
a) All identified risks when procuring, removal and handling of wheels and
storing, lifting, fitting, removing, testing, rim fastenings at any handling pressure
repairing, maintaining, and changing greater than zero.
tyres and wheel assemblies where the j) All split rim (divided rim) assemblies to
rim diameter is 24 inch (61 centimetre) deflate the tyre to zero pressure, and
or greater. confirm, before removal.
b) All identified risks when managing k) All dual wheel assemblies to deflate
tyres and wheel assemblies where the both tyres to the specified safe handling
rim diameter is less than 24 inch (61 pressure, and confirm, before releasing
centimetre). tension on the rim fastenings (refer to
c) Task specific procedures to address FHP 11.1.2i).
tyre and wheel deflation, disassembly, l) A process to demarcate a restricted
assembly and inflation risks. For work area when changing tyres and
multi-piece and split rim (divided rim) wheels, to protect other personnel not
assemblies, this includes quality checks directly involved.
at hold points for safety critical steps. m) Formal procedures (or reference to) for
d) A documented maintenance regime for managing ‘no-go zones’ when deflating,
the periodic testing and inspection of removing, installing, and inflating tyres.
tyres, rims, and wheel assemblies. No person is to stand in the direct line of
e) Rim base identification with a unique fire during tyre inflation.
number for maintenance tracking of n) Restraint of wheel assemblies with a
all rims with a diameter of 24 inch (61 rim diameter of less than 24 inch (61
centimetre) or greater, and for rims centimetre) during inflation.
with a diameter of less that 24 inch (61 o) Continuous monitoring of tyres and
centimetre) identified for tracking in the wheel assemblies during inflation and
risk assessment. deflation, from outside the no-go zone,
f) Use of a tyre and rim-base register to and in a safe, remote location (refer to
record the history and maintenance of FHP 11.1.2m).
Δ11
TYRE AND RIM
MANAGEMENT
Continued
Δ12
ELECTRICAL SAFETY
~
415 VOLTS
>"11.U•"lll•l
Δ12
ELECTRICAL SAFETY
Continued
GLOSSARY
Δ GLOSSARY
Continued
surface and where there is a risk of a methane gas Work Basket – A work basket is an attachment
explosion. (Within such a zone all equipment is to that is attached to a piece of equipment, i.e. a
be either flame-proof or intrinsically safe). crane.
Hot Work - Hot work is any welding, thermal or oxy Monitoring Program – Agreed program to
cutting, frictional cutting and grinding, heating or regularly monitor and measure the effectiveness
other fire or spark producing operation. of specific aspects of controls, procedures and
management plans.
Inrush – Relates to the sudden flow of water or
other substance which could result in drowning, Operational Areas – Any areas where production
asphyxiation, entrapment or physical impact. activities are undertaken.
Potential inrush hazards need to be identified
considering: Operations Engineering Management Plan –
Formal process for management of engineering
►► The potential sources of inrush including practices, in particular as it relates to design,
current, disused or abandoned mine work- install, commission, use, maintenance and decom-
ings, along the same seam or across strata, missioning.
surface water bodies, backfill operations, highly
permeable aquifers, bore-holes, faults or other Outburst – Outburst is the sudden and violent
geological weaknesses. ejection of coal, gas and rock from a coal face and
surrounding strata in an underground coal mine.
►► The potential for the accumulation of water, gas
or other materials that could liquefy or flow into PAT – Proximity Awareness Technology.
other workings or locations. PDT – Proximity Detection Technology.
►► The magnitude of all potential sources and Positive Communication – Includes the active
maximum flow rates. communication between both mobile equipment
►► The Maximum Probable Consequence operators and confirmed responses.
scenarios for each potential source, espe- Permit System – Formal system required for
cially including the accuracy of plans of other specific tasks or activities, ie. working in confined
workings, variation in rock properties, geological space, whereby a permit has to be issued to an
weaknesses or similar unknowns. operator prior to commencing work.
►► The potential sources of inundation (slower flow Procedure – Documented process detailing the
of water) including extreme weather, overflow requirements for conducting an activity or task.
or failure of levies and dam structures, failure
or blocking of flow channels (either regular, Rigger/Dogger – A Rigger is a person that spe-
overflow, or emergency), which have potential cialises in the lifting or moving of extremely large
to accumulate/accelerate and escalate to an or heavy objects, and a Dogger is a person who
inrush event. directs the operation of a crane.
Issue Specific Risk Assessment – Risk assess- Rim – Part of a wheel assembly, mounted to a
ment which identifies and assesses the risk related vehicle using cleats and studs or nuts.
to a specific topic, i.e. strata, which is normally
identified as a risk in the Baseline Risk Assess- Rim Assembly – The assembly of wheel compo-
ment or BBRA. nents, not including a tyre. A rim assembly typically
comprise a rim base, flanges, bead seat band and
Dragline Bucket Jewellery – Miscellaneous items lock ring.
used to attach the dragline bucket to the hoist
ropes. Rim Base – The part of the rim assembly on which
the tyre is mounted and supported.
Management Plan - Formal process for man-
agement of a particular activity, task or are of the Safe Handling Pressure - The nominal pressure,
business which articulates management activities determined by risk assessment, for handling wheel
and roles and responsibilities. assemblies during dismounting, mounting, storage
and transport.
SAT – Safety Adherence Technology.
Δ GLOSSARY
Continued
Δ REFERENCES
References:
The following references can be a useful source of additional information in relation to the issues ad-
dressed in these Protocols:
Related Documents
Title
Risk Management (GCAA Finance Standard)
Documents and Records (GCAA HSEC Standard)
Leadership, Culture, and Accountability (GCAA HSEC Standard)
Training (GCAA HSEC Standard)
Change (GCAA HSEC Standard)
Assurance (GCAA HSEC Standard)
Incident Management Manual - Part 1 (GCAA HSEC Manual)
Incident Management Manual - Part 2 (GCAA HSEC Manual)
Work Authorisation and Permit System (GCAA HSEC Protocol)
Hot Work (surface) Permit (GCAA HSEC Permit)
Confined Space Entry Permit (GCAA HSEC Permit)
Complex Lift Permit (GCAA HSEC Permit)
Work at Height Permit (GCAA HSEC Permit)
High Voltage Access Permit (GCAA HSEC Permit)
Group Isolation Permit (GCAA HSEC Permit)
Tyres and Rims (GCAA Engineering Guideline)
Reference Information
Reference Title
ACARP Australian coal industry’s research program.
MiRMgate Industry recognised databases, including records of industry related
incidents, hazards, causation factors, and recommended preventative
measures.
Δ DOCUMENT HISTORY
Intentionally blank
COAL ASSETS
AUSTRALIA
GCAA-625378177-13287
www.glencore.com.au