Professional Documents
Culture Documents
Introduction . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3
1. Challenges to the development of PPPs . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 6
2. Objectives of the PPP Policy . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 14
3. Scope of this Policy . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 16
4. Key principles of implementing PPP projects . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 19
5. Actions, role and responsibility of individual institutions . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 24
6. Monitoring and evaluation of the PPP Policy . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 31
2 Table of contents
Introduction
Developing infrastructure and providing public and organisational solutions, higher standards
services that meet society’s expectations are of services or technical and technological solu-
key elements in the economic development of tions aimed at reducing the cost of providing
Poland and public-private partnerships (PPPs) public services. PPPs may also contribute to
are one tool that can be used to deliver them. more effective use of European Union (EU)
To ensure the effective development of PPPs funds, through the implementation of proj-
in Poland, the Polish Government will take ects that combine EU funds and private sector
a series of actions aimed at increasing the scale financing.
of infrastructure investment and, at the same
time, ensuring their optimisation and benefits An estimated PLN 1.5 trillion of capital invest-
for the public interest. Actions also need to be ment is needed before 2030 in order to
taken to support public authorities in preparing maintain the current pace of infrastructure
and implementing PPP projects. The need to development in Poland. Many key sectors of
develop the use of PPP is emphasised in the the economy have high investment needs. For
“Strategy for Responsible Development”. The example, the environment sector investment
Strategy identifies a need to involve private plan envisages the construction of 21,800 km
sector experience in managing and maintaining of sewage networks, [including 16,900 km
infrastructure and preparing and implementing after 2015], and the modernisation of 4,200
projects, as well as private sector capital, in km of the existing sewage network, [including
the delivery of public activities. The underlying 3,500 km after 2015]. In the railway sector, the
context is that society expects wider availability, reconstruction of 8,500 km of railway lines is
and an increasing quality, of services offered by planned. According to data available at the
the public sector. end of 2015, the construction of 0.5 million
housing units is needed in order to address the
PPPs offer an opportunity for the faster devel- existing deficit in the housing sector. Signifi-
opment of Poland, which must not be wasted. cant modernisation of inland waterways is also
PPPs are one way of providing and financing envisaged, costing between PLN 24.6 billion
high-quality public infrastructure. A private PLN and PLN 90.6 billion. In addition, more
partner, when investing in the provision of than PLN 200 billion is needed to implement
public services, may provide resources that the National Road Construction Programme
allow for the introduction of new management over the period 2014-2023.
Introduction 3
Public budgets, including the state budget, materials and project management methods)
are not sufficient to deliver projects in both which reduce operating costs. Another import-
economic infrastructure (e.g. transport, envi- ant benefit is the potential for improvement in
ronment, energy) and social infrastructure (e.g. the standard of services, incentivised through
health, education, culture, sports and tourism). a system of penalties, at an agreed level for
Sources of private financing are therefore the long-term duration of the contract, where
needed in order to deliver infrastructure invest- performance is measured against the delivery
ment and provide public services. of ongoing contractual requirements and not
merely on construction of the infrastructure.
At a regional level, projects that involve coop- Bearing in mind that the traditional way of pro-
eration between the private and public sectors curing public services entails risks for the public
may also have a positive impact on the develop- authority, a PPP makes it possible to transfer
ment of local enterprise and contribute to the some of these risks to the private partner on
creation of new jobs. From a macroeconomic the basis that it is better able to manage them.
perspective, the development of PPPs can It should, however, be stressed that transferring
contribute to the country’s economic develop- all of the risks to the private partner can distort
ment through an increase in the number and the concept of partnership, increase project
value of infrastructure investment . costs for the public authority and reduce private
sector interest in the project.
At a project level, PPP may bring measur-
able benefits to public authorities and service From a financial management perspective and
end-users, although it must be borne in mind by offering an alternative to the traditional
that this always depends on specific conditions approach of funding public sector activities,
and circumstances. First and foremost, a proper PPP may make it possible for a public author-
partnership may result in greater cost savings ity to proceed with infrastructure investment
in the provision of services in the long term. without significant involvement of public funds
Being responsible not only for the construc- at the construction or renovation stage. This
tion, but also for the design, maintenance may also allow for more efficient planning of
and management of infrastructure, incentivises expenditure and the implementation of more
the private partner to look for optimal solu- infrastructure investment and public services
tions (including the latest technologies and at the same time.
4 Introduction
PPPs can also provide much greater certainty a PPP formula. Such a project may still fail
of infrastructure projects being completed in due to being unaffordable or not achieving
accordance with agreed timetables and bud- value added of a PPP formula in terms of
gets than is the case with traditional public increased efficiency, shorter delivery times-
infrastructure projects. This is principally due cales or higher quality of services provided.
to the fact that the private sector takes an
integrated and systematic approach to proj- The Polish Government is interested in a rapid
ect preparation and delivery. Moreover, the increase in use PPPs for the construction of
private partner is remunerated only once the public infrastructure and provision of high
construction of the infrastructure is complete quality public services. Public authorities
and the services, that are required in order should give PPPs equal consideration as an
for it to be used, are provided in accordance alternative to traditional methods of carrying
with agreed quality standards. As international out public activities, although in doing so the
experience has shown, traditional procurement potential benefits that a PPP may bring to
often carries a higher risk that a project will a specific project and to the public interest
end up being more expensive, not delivered still need to be demonstrated.
on time or, in extreme situations, interrupted
or abandoned.
Introduction 5
1. Challenges to the development of PPPs
PPP MARKET IN POLAND 2009 on concessions for construction works or
services (Dz. U. of 2015, item 113) (Concession
Before 2005, Poland had no statutory reg- Act), which was later repealed by the Act of 21
ulations dedicated to PPPs (apart from the October 2016 on concession for construction
concession procedure provided for in public works or services (Dz. U. item 1920). Since
procurement law). However, the PPP for- 2009, the number of tenders for selection of
mula was still used occasionally by applying the private partner and of contracts concluded
other legal regulations such as the Act of 20 has been growing steadily.
December 1996 on municipal economy (Dz.
U. (Journal of Laws) of 2016, item 573, as However this growth is still not satisfactory
amended) or the Act of 27 October 1994 on and the effectiveness of launched tender pro-
toll highways and the National Road Fund (Dz. cedures is still low: from 2009-2016 more than
U. of 2015, item 641 , as amended). 460 tenders for the selection of a private part-
ner or concessionaire were announced, but the
In 2005, the Act of 28 July 2005 on PPP number of contracts concluded was just over
(Dz. U. item 1420, as amended) came into 110. The rate of effectiveness was therefore
force in Poland. However, due to its excessive below 25%. Furthermore, even fewer projects
restrictions and the heavy regulatory burden raised the financing required for project deliv-
it imposed coupled with the long absence of ery after the PPP contracts had been signed.
necessary implementing regulations, no PPP Such a low percentage suggests either that
contract was concluded while that Act was in the offers were unattractive to the private
force. In addition, the market was not yet ready sector for some reason (e.g. inappropriate
to implement projects using such an approach. allocation of risks, private partner income
There was also insufficient funding available not sufficiently covering expenditure, poorly
for carrying out the analysis required before prepared projects), or that the private sector
a PPP contract is concluded and implemented lacked resources to deliver what the public
sector expected.
A new phase in Poland’s PPP market started in
2009 with the introduction of the new Act of In Poland, PPPs have been used predominantly
19 December 2008 on PPP (Dz. U. of 2015, item by local government authorities (including
696, as amended) and the Act of 9 January subordinated entities), who have initiated
In addition, the development of PPPs in Poland So far, Poland has had no reliable database of
by various authorities has been carried out PPP investments plans at sectoral or regional
without appropriate distinction of the various levels. There has been no structuring or stan-
functions: planning or political support, pro- dardisation of tools for identifying and sharing
gramming/monitoring or certification) quality investment plan databases with the market
assurance) Consequently, the activities of vari- and no foreign models in this area have been
ous authorities have lacked coordination, with used or adapted. As a result, the private sector
A significant feature of the Polish PPP market Due to the lack (or a small number) of pilot
to date has been the limited number of success- projects in some sectors in Poland, there is an
fully delivered large, in particular Government/ insufficient database with examples of good
State level, projects. To date, public authorities practice. This is particularly true of successful
have rather funded their largest investment Government/State level projects. Therefore
needs from their own resources, from Euro- there are no effective guidelines are available
pean Union funds or by using resources that on how to implement a project as a PPP in
they have themselves obtained from financing a given sector. There are also no effective
institutions. Therefore the opportunity and means for disseminating good practice and
benefits of PPP have been overlooked at this guidelines in areas such as PPP project assess-
level, sending a negative message to other ment, preparation, private partner selection
public authorities faced with the need to and implementation.
provide appropriate public infrastructure and
public services. Limited knowledge of PPP and the principles
of PPP implementation
No standardisation of legal models
or documentation for PPP and concession A lack of knowledge and experience in pre-
contracts (standard documentation ready paring and implementing PPP projects leads
to use) to caution towards, or avoidance of, this more
demanding project delivery method. This is the
As only a small number of PPP contracts have case for public authorities implementing proj-
been signed so far in Poland, common con- ects, the institutions that control the activity
tractual standards have yet to be developed. of those authorities, the private sector and
However, it should be recognised that, due to financing institutions.
the costs involved in preparing PPP projects,
It is also the case that a lack of awareness on The majority of projects in Poland encounter
the part of the public party as to the cost of problems in obtaining financing. Financing
of inappropriate risk allocation on a project institutions usually become involved in a proj-
(and particularly in transferring more risk to ect at too late a stage, when there is either
the private partner than is appropriate) can no or very limited opportunity to influence the
have a significant impact on the effectiveness shape of the PPP contract. This can lead to
of the PPP project and lead to its cancellation. situations where financing is refused because
the arrangements that have already been
Insufficient information for the public agreed between the public and private parties
are unacceptable to the financial institutions.
Another significant problem often faced by
public authorities is stakeholder resistance to On the other hand, financial institutions some-
a given infrastructure project and, particularly times show no interest in being involved in
in the case of PPP projects, to the involvement a project at an early stage, discouraged from
Project teams
Data source:
-
own data of the Ministry of Economic Development; “Public-private partnership in Poland. Experiences and prospects
for the future” – Sobieski Institute, 2016, PPP MARKET REPORT – Assessment of the current state and prospects
of the financial involvement of the private and public sectors in the development of public-private partnership in
Poland” – Ministry of the Economy, 2013; National Road Construction Programme for 2014-2023 (with a perspec-
tive to 2025); National Railway Programme by 2023; Resolution on the adoption of the “Assumptions for plans
to develop inland waterways in Poland for the years 2016-2020 with a perspective to 2030; “Mieszkanie plus”
programme; Update of the “National municipal wastewater treatment programme 2015”.
Notes
Ministry of Economic Development
Department for Public-Private Partnership
ISBN: 978-83-7610-640-3
Free copy
OF ECONOMIC