You are on page 1of 36

The Government Policy

for the Development


of PPPs (Poland)
The Government Policy
for the Development of PPPs (Poland)
July 2017
Table of contents

Introduction . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3
1. Challenges to the development of PPPs . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 6
2. Objectives of the PPP Policy . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 14
3. Scope of this Policy . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 16
4. Key principles of implementing PPP projects . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 19
5. Actions, role and responsibility of individual institutions . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 24
6. Monitoring and evaluation of the PPP Policy . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 31

2 Table of contents
Introduction
Developing infrastructure and providing public and organisational solutions, higher standards
services that meet society’s expectations are of services or technical and technological solu-
key elements in the economic development of tions aimed at reducing the cost of providing
Poland and public-private partnerships (PPPs) public services. PPPs may also contribute to
are one tool that can be used to deliver them. more effective use of European Union (EU)
To ensure the effective development of PPPs funds, through the implementation of proj-
in Poland, the Polish Government will take ects that combine EU funds and private sector
a series of actions aimed at increasing the scale financing.
of infrastructure investment and, at the same
time, ensuring their optimisation and benefits An estimated PLN 1.5 trillion of capital invest-
for the public interest. Actions also need to be ment is needed before 2030 in order to
taken to support public authorities in preparing maintain the current pace of infrastructure
and implementing PPP projects. The need to development in Poland. Many key sectors of
develop the use of PPP is emphasised in the the economy have high investment needs. For
“Strategy for Responsible Development”. The example, the environment sector investment
Strategy identifies a need to involve private plan envisages the construction of 21,800 km
sector experience in managing and maintaining of sewage networks, [including 16,900 km
infrastructure and preparing and implementing after 2015], and the modernisation of 4,200
projects, as well as private sector capital, in km of the existing sewage network, [including
the delivery of public activities. The underlying 3,500 km after 2015]. In the railway sector, the
context is that society expects wider availability, reconstruction of 8,500 km of railway lines is
and an increasing quality, of services offered by planned. According to data available at the
the public sector. end of 2015, the construction of 0.5 million
housing units is needed in order to address the
PPPs offer an opportunity for the faster devel- existing deficit in the housing sector. Signifi-
opment of Poland, which must not be wasted. cant modernisation of inland waterways is also
PPPs are one way of providing and financing envisaged, costing between PLN 24.6 billion
high-quality public infrastructure. A private PLN and PLN 90.6 billion. In addition, more
partner, when investing in the provision of than PLN 200 billion is needed to implement
public services, may provide resources that the National Road Construction Programme
allow for the introduction of new management over the period 2014-2023.

Introduction 3
Public budgets, including the state budget, materials and project management methods)
are not sufficient to deliver projects in both which reduce operating costs. Another import-
economic infrastructure (e.g. transport, envi- ant benefit is the potential for improvement in
ronment, energy) and social infrastructure (e.g. the standard of services, incentivised through
health, education, culture, sports and tourism). a system of penalties, at an agreed level for
Sources of private financing are therefore the long-term duration of the contract, where
needed in order to deliver infrastructure invest- performance is measured against the delivery
ment and provide public services. of ongoing contractual requirements and not
merely on construction of the infrastructure.
At a regional level, projects that involve coop- Bearing in mind that the traditional way of pro-
eration between the private and public sectors curing public services entails risks for the public
may also have a positive impact on the develop- authority, a PPP makes it possible to transfer
ment of local enterprise and contribute to the some of these risks to the private partner on
creation of new jobs. From a macroeconomic the basis that it is better able to manage them.
perspective, the development of PPPs can It should, however, be stressed that transferring
contribute to the country’s economic develop- all of the risks to the private partner can distort
ment through an increase in the number and the concept of partnership, increase project
value of infrastructure investment . costs for the public authority and reduce private
sector interest in the project.
At a project level, PPP may bring measur-
able benefits to public authorities and service From a financial management perspective and
end-users, although it must be borne in mind by offering an alternative to the traditional
that this always depends on specific conditions approach of funding public sector activities,
and circumstances. First and foremost, a proper PPP may make it possible for a public author-
partnership may result in greater cost savings ity to proceed with infrastructure investment
in the provision of services in the long term. without significant involvement of public funds
Being responsible not only for the construc- at the construction or renovation stage. This
tion, but also for the design, maintenance may also allow for more efficient planning of
and management of infrastructure, incentivises expenditure and the implementation of more
the private partner to look for optimal solu- infrastructure investment and public services
tions (including the latest technologies and at the same time.

4 Introduction
PPPs can also provide much greater certainty a PPP formula. Such a project may still fail
of infrastructure projects being completed in due to being unaffordable or not achieving
accordance with agreed timetables and bud- value added of a PPP formula in terms of
gets than is the case with traditional public increased efficiency, shorter delivery times-
infrastructure projects. This is principally due cales or higher quality of services provided.
to the fact that the private sector takes an
integrated and systematic approach to proj- The Polish Government is interested in a rapid
ect preparation and delivery. Moreover, the increase in use PPPs for the construction of
private partner is remunerated only once the public infrastructure and provision of high
construction of the infrastructure is complete quality public services. Public authorities
and the services, that are required in order should give PPPs equal consideration as an
for it to be used, are provided in accordance alternative to traditional methods of carrying
with agreed quality standards. As international out public activities, although in doing so the
experience has shown, traditional procurement potential benefits that a PPP may bring to
often carries a higher risk that a project will a specific project and to the public interest
end up being more expensive, not delivered still need to be demonstrated.
on time or, in extreme situations, interrupted
or abandoned.

It should also be noted that the implementa-


tion of projects in the form of PPPs can also
bring significant benefits for private sector
entities: primarily being the stable sources of
income from long-term agreements with the
public sector that allow for better long-term
business planning.

Finally, it should be stressed that the possibil-


ity of a PPP transaction being neutral in the
public authority’s balance sheet should not
be the sole or prime motivator for adopting

Introduction 5
1.  Challenges to the development of PPPs
PPP MARKET IN POLAND 2009 on concessions for construction works or
services (Dz. U. of 2015, item 113) (Concession
Before 2005, Poland had no statutory reg- Act), which was later repealed by the Act of 21
ulations dedicated to PPPs (apart from the October 2016 on concession for construction
concession procedure provided for in public works or services (Dz. U. item 1920). Since
procurement law). However, the PPP for- 2009, the number of tenders for selection of
mula was still used occasionally by applying the private partner and of contracts concluded
other legal regulations such as the Act of 20 has been growing steadily.
December 1996 on municipal economy (Dz.
U. (Journal of Laws) of 2016, item 573, as However this growth is still not satisfactory
amended) or the Act of 27 October 1994 on and the effectiveness of launched tender pro-
toll highways and the National Road Fund (Dz. cedures is still low: from 2009-2016 more than
U. of 2015, item 641 , as amended). 460 tenders for the selection of a private part-
ner or concessionaire were announced, but the
In 2005, the Act of 28 July 2005 on PPP number of contracts concluded was just over
(Dz. U. item 1420, as amended) came into 110. The rate of effectiveness was therefore
force in Poland. However, due to its excessive below 25%. Furthermore, even fewer projects
restrictions and the heavy regulatory burden raised the financing required for project deliv-
it imposed coupled with the long absence of ery after the PPP contracts had been signed.
necessary implementing regulations, no PPP Such a low percentage suggests either that
contract was concluded while that Act was in the offers were unattractive to the private
force. In addition, the market was not yet ready sector for some reason (e.g. inappropriate
to implement projects using such an approach. allocation of risks, private partner income
There was also insufficient funding available not sufficiently covering expenditure, poorly
for carrying out the analysis required before prepared projects), or that the private sector
a PPP contract is concluded and implemented lacked resources to deliver what the public
sector expected.
A new phase in Poland’s PPP market started in
2009 with the introduction of the new Act of In Poland, PPPs have been used predominantly
19 December 2008 on PPP (Dz. U. of 2015, item by local government authorities (including
696, as amended) and the Act of 9 January subordinated entities), who have initiated

6 Challenges to the development of PPPs


more than 90% of the PPP tenders initiated.
At the national (Government/State) level, only
one PPP contract is currently being delivered
in Poland (excluding highway projects that
are implemented pursuant to the Act of 27
October 1994 on toll highways and on the
National Road Fund). The private partners
for most smaller concession projects are local
small and medium-sized enterprises (SMEs).

SMEs, however, often struggle with not having


appropriate organisational capacity, partic-
ularly for implementing larger PPP projects.
They are often unable to acquire appropriate
financing for projects that financial institutions
consider more risky or to mobilise sufficient
funds themselves. Moreover, there is insuffi-
cient support from the public sector for SMEs
seeking to deliver PPPs.

Prior to the EU 2014-2020 financial frame-


work, the implementation of PPP projects
that combine EU funding and private sources
of financing (hybrid PPP projects) was not
well supported by the prevailing rules. There-
fore despite the wide availability of the EU
funds, few such projects were implemented
in Poland. However, the Regulation of the
European Parliament and of the Council (EU)
No 1303/2013 of 17 December 2013 laying
down common provisions on the European

Challenges to the development of PPPs 7


Regional Development Fund, the European The Polish PPP market is characterised by
Social Fund, the Cohesion Fund, the European a wide diversity of sectors. Since 2009, under
Agricultural Fund for Rural Development and the PPL and Concession Acts, most con-
the European Maritime and Fisheries Fund tracts have been signed in the sports and
and laying down general provisions on the recreational sector (approximately 20% of all
European Regional Development Fund, the contracts), broadband sector (approximately
European Social Fund, the Cohesion Fund and 15%), sewage and water sector (approximately
the European Maritime and Fisheries Fund 10%), energy efficiency (approximately 10%)
and repealing Council Regulation (EC) No and public utility buildings sector (approxi-
1083/2006 (OJ EU L 347, 20.12.2013, pp. 320- mately 10%). In addition, there are projects
469, as amended), together with the Act of 11 for the construction and maintenance of car
July 2014 on the principles of implementation parks, urban regeneration, transport, energy
of the cohesion policy programmes financed and hospital equipment. However, in terms
under the 2014-2020 financial framework (Dz. of the value of contracts, the largest share is
U. of 2016, item 217, as amended), finally intro- represented by the waste management sector,
duced a series of measures in this regard for mainly due to one project with a value of PLN
public authorities interested in implementing 925 million (this does not include highway
such projects. construction projects, given that these were
implemented before 2009).
To date, the majority of PPP contracts, by
number, have been signed using the proce- Approximately 20% of contracts have a value
dure specified in the Concession Act. This is of up to PLN 1 million and 57% have a value
due, inter alia, to the fact that this assumes of between PLN 1 million and 100 million.
that the majority of the economic risk of Only 13 concluded contracts have been for
a project transfers to the private party. How- projects with a value of more than PLN 100
ever, it should be noted that the value of million. It should be noted that, when deciding
such contracts is lower than the value of PPP to use a PPP, the public parties (mostly local
contracts which have been signed under the government authorities) have usually chosen
Act of 29 January 2004 – Public Procurement the concession model, as this has the least
Law (Dz. U. of 2015, item 2164, as amended) impact on its budget. The concession model
(PPL Act). was usually used for the lowest contract value

8 Challenges to the development of PPPs


projects. A key motivation for this is the desire some being carried out excessively or even
to transfer to the private partner not only the duplicated and others being carried out too
construction risk, but, primarily, the demand slowly or not at all. In addition support for
and financing risk. So far, public authorities public authorities in preparing, assessing the
have used PPPs based on availability payments validity of, and managing PPP contracts has
to a limited extent only. been insufficient.

BARRIERS TO THE PPP MARKET Lack of optimal legal solutions


IN POLAND
No legal barriers to the development of PPP
Lack of a clear institutional structure projects in Poland have been identified per se.
and coordinated PPP development policy However, Polish legislation governing PPPs is
perceived as not fully clear and inconsistent.
So far, the development of PPPs at the national The existing regulations have a number of
level has been fragmented and uncoordinated. shortcomings e.g. with regard to the appro-
The lack of a clear vision for the use of PPPs in priate procedures for selecting the private
Poland has hindered individual public authori- partner, taxation, financing and contract man-
ties’ plans to use them. Despite the existence agement. Consequently, some PPP projects
of statutory regulations, no clear vision or have had no chance of success because of
unanimous support of the Government as fear on the part of the public sector of making
regards the use of PPPs to deliver infrastruc- formal errors.
ture projects and public services have been
stated. No database of PPP investment plans

In addition, the development of PPPs in Poland So far, Poland has had no reliable database of
by various authorities has been carried out PPP investments plans at sectoral or regional
without appropriate distinction of the various levels. There has been no structuring or stan-
functions: planning or political support, pro- dardisation of tools for identifying and sharing
gramming/monitoring or certification) quality investment plan databases with the market
assurance) Consequently, the activities of vari- and no foreign models in this area have been
ous authorities have lacked coordination, with used or adapted. As a result, the private sector

Challenges to the development of PPPs 9


and financial institutions have been unable to such standards would be desirable for the
prepare, competently and comprehensively, development of the PPP market in Poland.
for delivering and financing projects.
Gaps in the dissemination and examination
Few large projects of good practice for PPP projects

A significant feature of the Polish PPP market Due to the lack (or a small number) of pilot
to date has been the limited number of success- projects in some sectors in Poland, there is an
fully delivered large, in particular Government/ insufficient database with examples of good
State level, projects. To date, public authorities practice. This is particularly true of successful
have rather funded their largest investment Government/State level projects. Therefore
needs from their own resources, from Euro- there are no effective guidelines are available
pean Union funds or by using resources that on how to implement a project as a PPP in
they have themselves obtained from financing a given sector. There are also no effective
institutions. Therefore the opportunity and means for disseminating good practice and
benefits of PPP have been overlooked at this guidelines in areas such as PPP project assess-
level, sending a negative message to other ment, preparation, private partner selection
public authorities faced with the need to and implementation.
provide appropriate public infrastructure and
public services. Limited knowledge of PPP and the principles
of PPP implementation
No standardisation of legal models
or documentation for PPP and concession A lack of knowledge and experience in pre-
contracts (standard documentation ready paring and implementing PPP projects leads
to use) to caution towards, or avoidance of, this more
demanding project delivery method. This is the
As only a small number of PPP contracts have case for public authorities implementing proj-
been signed so far in Poland, common con- ects, the institutions that control the activity
tractual standards have yet to be developed. of those authorities, the private sector and
However, it should be recognised that, due to financing institutions.
the costs involved in preparing PPP projects,

10 Challenges to the development of PPPs


Lack of dedicated project teams and Difficulties in preparing PPP projects and lack
experience in implementing PPP projects of diligent project preparation
in the public sector
The public party often neglects to carry out
The public party often fails to account for the the appropriate level of analysis required
fact that the preparation of a PPP project, and before implementing a PPP project or fails to
the private partner selection process, can be draw appropriate conclusions from such anal-
time consuming and expensive. The public ysis. In many cases, there is no verification of
authority therefore does not either appoint the rationale for using a PPP for a particular
an external organisation to carry out the nec- project in terms of assessing the benefits of
essary tasks, or designate a team of people a PPP compared with the traditional method
from within its existing structure with the of project implementation. The reasons for
proper competencies, capabilities and time this are, inter alia, that the public authorities
available to be involved in the PPP project. do not have the funding needed to meet the
The lack of, or inappropriate, organisation of costs of legal, technical and financial analysis
the project team (for example, regarding the during the project preparation stage or they
team’s competencies, decision-making capacity do not understand the requirements of project
or excessive burdening with other obligations), preparation in the first place. This problem
reduces the project’s chances of success. In arises particularly on smaller projects, where
such situations not only is the project prepa- the cost of such analysis can be dispropor-
ration phase prolonged but the length of the tionately high in relation to the value of the
private partner selection process is signifi- intended project.
cantly extended. This often affects the private
sector’s perception of and level of interest in Often the problem is not only the lack of, or
the project, not to mention the overall cost inadequate, PPP project preparation but also
of the project. It should also be emphasised the lack of key tender documents at the start
that project teams play an important role not of the tendering procedure. This can lead to
only during the project preparation and private changes in the scope or design of the project
partner selection stages, but also during the during the private partner selection process
project implementation and contract manage- which in turn can result in a prolonged tender-
ment stages. ing procedure, rising costs and sometimes the

Challenges to the development of PPPs 11


withdrawal of private entities from participat- of private entities in public sector activities.
ing. In this situation the public authority also This can be due to policy makers and stake-
loses credibility. holders not having sufficient understanding
of PPP principles or information about the
When the main motivation of public author- particular method for implementing the given
ities for implementing PPP projects is to project. The public authority often consults
avoid increasing the level of public debt, and provides information about the expected
inappropriate PPP models are often chosen. approach to project delivery too late or not
For example, there might be an attempt to at all, or does so only to a limited extent. As
transfer the demand risk to the private part- a result, due to a lack of information, the public
ner even though there is no possibility of this resorts to legal and political measures aimed at
leading to a commercially successful project. stopping the project, making its implementa-
Failure to adapt the delivery model to the tion difficult and discouraging private partners
requirements of the market can lead to a lack from becoming involved.
of private sector interest in the PPP and, ulti-
mately, the project not going ahead. Problems with project financing

It is also the case that a lack of awareness on The majority of projects in Poland encounter
the part of the public party as to the cost of problems in obtaining financing. Financing
of inappropriate risk allocation on a project institutions usually become involved in a proj-
(and particularly in transferring more risk to ect at too late a stage, when there is either
the private partner than is appropriate) can no or very limited opportunity to influence the
have a significant impact on the effectiveness shape of the PPP contract. This can lead to
of the PPP project and lead to its cancellation. situations where financing is refused because
the arrangements that have already been
Insufficient information for the public agreed between the public and private parties
are unacceptable to the financial institutions.
Another significant problem often faced by
public authorities is stakeholder resistance to On the other hand, financial institutions some-
a given infrastructure project and, particularly times show no interest in being involved in
in the case of PPP projects, to the involvement a project at an early stage, discouraged from

12 Challenges to the development of PPPs


doing so by the relatively low percentage of
tender announcements that result in signed
PPP contracts.

There is also insufficient knowledge on the


part of both parties to the PPP contract as
regards possible project financing structures,
sources of financing and security. There is also
no system of guarantees for loans taken for
implementing PPP projects and “non-banking”
sources of financing in Poland are rarely used.

Challenges to the development of PPPs 13


2.  Objectives of the PPP Policy
One of the Government’s objectives, stated in In addition to the above, the Policy should
its “Strategy for Responsible Development”, contribute to:
is to encourage businesses and financial insti-
tutions to become involved in, and allocate yy a better quality of services and public
their financial resources to, new investment infrastructure,
projects in order to further economic devel-
opment and improve the quality of public yy reducing the up-front investment burden
services. on public budgets through the provision
of private financing,
PPPs are one of the tools for implementing
the “Strategy for Responsible Development”, yy increasing the effectivness of using of
particularly as part of the area – Capital for existing public assets,
development, but only where the benefits of
PPP outweigh the traditional approach to pro- yy implementing innovative solutions in con-
viding infrastructure and public services. More struction, maintenance and public service
use of PPPs may lead to a sustained increase delivery,
in the rate and quality of public investment in
the long term. yy establishing clear principles for using the
PPP formula,
The purpose of this Government Policy for the
Development of PPPs (the Policy) is to increase yy increasing public sector awareness of PPP
the scale and effectiveness of infrastructure as an alternative method for providing
projects using PPP on the assumption that infrastructure and high-quality public ser-
a PPP formula is selected for delivering public vices,
tasks and services where it maximises the eco-
nomic and social benefits. yy establishing the principle, in particular for
large Government/State level projects, that
PPP is one of the options to be considered
when choosing the method for delivering
infrastructure investment projects,

14 Objectives of the PPP Policy


yy increasing the number of eco-
nomically feasible infrastructure
investment projects (using tradi-
tional and PPP formula) funded from
the state budget,

yy supporting the local government


sector in implementing PPP projects.

Objectives of the PPP Policy 15


3.  Scope of this Policy
The Policy sets out key principles for imple- For the purposes of the Policy, it is assumed
menting PPP projects, as well as the actions that PPP can be applied to all infrastructure
and responsibilities of the relevant institutions and public services that public authorities
for developing the use of PPPs. are obliged to provide by law or statute. In
particular, this includes economic and social
The Policy covers cooperation between public infrastructure as well as infrastructure belong-
and private entities, within the meaning of the ing to public administrations and universities.
Act of 19 December 2008 on PPP (the PPL Act)
and the Act of 21 October 2016 on concession PPP Models
for construction works or services. A private
partner is selected in accordance with the pro- The Policy applies to various forms of cooper-
cedure determined by the PPL Act or the Act on ation between the public and private sectors.
concession for construction works or services. One form of this cooperation takes the form of
a contractual relationship between the public
The object of a PPP is the provision and main- and private parties (a so-called “Contractual
tenance of infrastructure, or the management PPP”). In turn, depending on the mechanism
of infrastructure combined with the provision used to remunerate the private partner, a dis-
of services, for a defined period. PPPs are tinction can be made between:
comprehensive in nature, involving the design,
finance, construction (or renovation), mainte- yy A concession contract for the construction
nance and management of infrastructure or works or services, where the private part-
involving only the provision of services and ner is remunerated directly by consumers
management of infrastructure entrusted to of the services/users of the infrastructure,
the private partner. possibly with additional payments from the
public authority. Under a concession for
PPP is not a method of privatisation; at the construction works or services the contract-
end of the contract, all of the PPP assets are ing authority (the public party) entrusts
transferred (returned) to the public authority, the concessionaire (the private party) with
unless the contract provides otherwise. In PPP, carrying out construction works and sub-
the public authority is responsible to the public sequently managing them, or providing
for the quality of services provided. services, in return for the right to payment

16 Scope of this Policy


from consumers/users or in return for this the most appropriate procedure to use for
right together with additional payment selecting the private partner.
from the public authority. A key character-
istic of a concession contract is this method Co-operation in the form of a PPP can also
by which the private partner is remuner- be established through the creation of a spe-
ated. In the case of a concession, this is cial-purpose vehicle by public entity and private
mainly through charges paid by consumers/ partner, a so-called “Institutional PPP”, and the
users, while in the other case (described remuneration for that vehicle can take similar
below), the private partner is primarily forms to those used for a contractual PPP.
remunerated through availability payments
from the public authority (potentially sup- Size of projects
plemented with charges paid directly by
consumers/users). The Policy applies to both small and large
projects. The high costs of preparing a PPP
yy A PPP contract concluded pursuant to project may, however, exceed the benefits
the PPL Act envisages the private partner arising from the PPP project. In particular,
being remunerated mainly by the public this can be the case on smaller projects that
authority, (through a so-called “availability are based on availability payments. The use
payment”), which in some cases may be of PPPs for small projects should be properly
supplemented by charges paid directly by verified in advance by the public authorities
consumers/users for the services provided. implementing them. It is also recommended
The availability payment is a regular pay- that smaller projects with common or simi-
ment made in return for the private partner lar features are either combined into larger
making the infrastructure available, and groups or delivered as programmes to reduce
managing and maintaining it. The infra- their individual preparation costs and increase
structure is usually built (or renovated) the effectiveness of their implementation.
and financed by the private partner. There
are various procedures that can be used to
procure a PPP contract under the PPL Act,
but the unique nature and complexity of
a PPP usually makes competitive dialogue

Scope of this Policy 17


Sectors practice, PPP contracts are usually concluded
for a period of between 10 and 30 years. The
The Policy applies to all public services sec- duration of the contract should not, however,
tors. PPPs may be used, in particular, in be shorter than the period needed for the
sectors such as: environmental protection private partner’s payback.
(water and wastewater management, waste
management), transport (road, rail, urban, Parties to the contract
stations, logistics centres, ports), education
(e.g., schools, kindergartens, nurseries, uni- The Policy applies to projects involving a public
versities, scientific research institutes), urban authority that is obliged to provide public
infrastructure (e.g., regeneration, parking services pursuant to relevant regulations and
lots, housing), culture, sports, tourism and a private entity that pursues an economic activ-
recreation, healthcare (infrastructure, equip- ity that is independent of and not controlled
ment), administrative and public civic buildings by the public entity. Public entities include all
(e.g. courts, city halls, ministerial buildings, public sector authorities, the Government/
museums, police headquarters, fire brigade State sector, local government authorities,
facilities), telecommunications and IT infra- universities and other public sector entities.
structure (e.g. broadband networks), energy
efficiency (e.g. thermal insulation of buildings,
modernisation of heating systems), and more.

Duration of the contract

The Policy applies to contracts of various


durations. Each contract requires an individ-
ual assessment of its duration having regard
to any relevant legal regulations. However,
cooperation between the public and private
parties in a PPP should, as a rule, be long-term,
as only then will it be possible to realise the
benefits expected from a PPP arrangement. In

18 Scope of this Policy


4.  Key principles of implementing PPP projects
Protecting the public interest can be a cheaper form of delivering a public
investment project than traditional public
When deciding to deliver an infrastructure procurement, generating savings throughout
project, including deciding on the use of its life.
a PPP formula, the public authority should
ensure that the project does not conflict with Proper structuring of the process – project
the general public interest. Therefore, when implementation stages
preparing the project, it is important to verify
that it aligns with actual social needs and to Before implementing an infrastructure proj-
determine the material and non-material ben- ect, regardless of the approach selected, the
efits its implementation will bring to society. public authority should carefully define the
From the very early stages of identifying the scope of the project, including the extent and
project need and defining the objectives and timetable of actions that need to be taken.
scope of the PPP project, care must be taken Public authorities implementing PPP projects
to document and justify the actions taken and should use the support of their own experts
decisions made, for the purpose of subsequent or external consultants to ensure that the
evaluation and potential review. scope and method of delivering their invest-
ment plans are appropriate and accurately
Appropriate strategy for project specified. After specifying the scope of the
implementation project, it is recommended that the public
authority verify whether the implementation
When embarking on an investment in public of the project will be more effective using
infrastructure or public services, in addition to a traditional model or the PPP model and to
confirming the appropriateness and legitimacy verify the financial feasibility of the project.
of the underlying project itself, the public At this stage, it is also necessary to identify
authority should verify the possibility and the proper allocation of risk and the proposed
benefits of using a PPP formula compared to project financing model as well as the key pro-
other methods of project delivery. This is the visions of the proposed PPP agreement. Such
case in particular for large investment projects, analysis should be supported by market tests
including Government/State infrastructure that demonstrate the potential for involving
projects. Over the project lifecycle a PPP a private entity, the optimal mechanism for

Key principles of implementing PPP projects 19


its remuneration and the allocation of the conclusions. Such an assessment may also be
responsibilities between the public and private based on qualitative indicators of efficiency.
partner. The scope of analysis should seek to
determine the structure of the project so that, A PPP should be used where, on the basis
while the public interest as a priority, the proj- of forecast financial inputs, the PPP delivers
ect has the potential to attract interest from greater benefits (e.g. increased efficiency,
private entities and to receive financing. The increased innovation of solutions, etc.)
next step should be to carry out the private when compared to the traditional model of
partner selection procedure and to commit implementing infrastructure projects. When
the budget required or to disregard the PPP estimating these benefits on the basis of
approach. For these tasks, the public entity value for money analyses, it is important to
should use its own specialised PPP teams or compare the same cost items, level of services
external consultants (in particular, legal and and period for providing the services and to
financial as well as technical advisers). include costs arising from the acceptance of
risks by the public and private entities as well
Assessment of the effectiveness – value for as other, non-financial, benefits.
money
Focus on services rather than on the
The public authority should structure the proj- infrastructure
ect in such a way so as to obtain the maximum
economic and social benefits from its imple- In preparing a PPP project, the public authori-
mentation. The benefits should be calculated ty’s focus should be on the quality and volume
for the entire project lifecycle, taking into of services that the project will deliver. The
account the costs of design and construction, objective of a PPP is not limited to the devel-
current provision of services, costs of main- opment of specific infrastructure, or to be
tenance and modernisation, and payment at used simply as a tool for avoiding of financ-
the end of the project. These activities should ing the infrastructure by the public sector.
reflect both the financial and social discount Thus the output of a PPP contract should be
rate. Such analyses should be made on a basis expressed in terms of the services provided
of reliable data, as the adoption of rigid, as a result of the infrastructure that is to be
unverified assumptions may lead to wrong made available.

20 Key principles of implementing PPP projects


A focus by the public authority on services yy form the basis of the partnership and the
therefore encourages actions that are better provisions of the PPP contract that govern it.
adapted to underlying needs, better use of
the assets (either existing or developed) Using private sector knowledge, innovation
within the scope of the project, maximum and skills
effectiveness of the solutions adopted, and
innovation. As early as during the design The private partner should be selected on
phase of the project, and not just during the basis of its knowledge and experience.
the operational stage when the services are Therefore, the assessment of criteria such as
being delivered, the private partner will be the knowledge and innovation of the private
focused on selecting the best ways to provide sector, and the quality and creativity of pro-
the services. posed solutions, are of particular importance
in the selection procedure.
Responsible allocation of risk
Guaranteeing transparency and
Risk analysis and risk management must always competitiveness
feature in the process for implementing PPP
projects, as these: Transparency and competitiveness should be
yy allow allocation of each risk to the party maintained during the private partner selec-
which is able to manage it best, tion process, i.e. using an open, transparent,
yy influence the total cost of the project as competitive tendering procedure. In practice,
well as play an important role in assessing this is achieved by selection in accordance with
the validity of using a PPP formula at vari- relevant Polish law. Special attention must be
ous stages of the project preparation and paid to avoiding misuse or excessive use of
implementation, limitations on transparency in the procedure
yy allow determination of how the PPP impacts (protection of trade secrets, confidentiality in
public debt and public deficit, the competitive dialogue). In addition, every
yy influence the ability to obtain financing for effort should be made to ensure that the
the project, actions of the project team and decisions of the
yy influence the private sector’s appetite for public authority are understood by potential
delivering the PPP project, private partners and the general public.

Key principles of implementing PPP projects 21


Guaranteeing proper management within the limitations of the law, and its objec-
of the PPP contract tives can be achieved while accommodating
economic or social changes.
PPP contracts, and shareholders’ agreements
in case of the institutional PPPs, are long-term Communication with the public, users and
in nature and require active management. other stakeholders
In order to ensure effective management of
a contract throughout the project lifecycle, it is Effective communication, inter alia, creates
necessary to determine the nature and quality market interest and reduces stakeholder
of the services required and to define precisely opposition to a project. Open dialogue with
the associated performance indicators. stakeholders and careful consideration of
their opinions and comments at an early
The public authority should be aware that stage increases the chances of successful proj-
even though it is outsourcing certain ser- ect delivery. This process of dialogue should
vices to a private partner or an institutional involve policy makers, financial institutions,
PPP, it retains ultimate legal responsibility potential private partners and future users/
for providing these services. It is therefore consumer. Effective communication is also
recommended that, during the project prepa- facilitated by creating PPP strategies as part
ration stage, the expected quality of services, of general investment strategies, at both the
the indicators to be used to measure their Governmental/State level and local level.
quality as well as the frequency and form of
measurement, are defined and indicated in Involvement of financing institutions
the tendering documents and PPP contract.
Input from interested financial institutions and
It is necessary to identify dedicated units/ banks should be sought at an early stage of
teams responsible for implementing the tasks project preparation and can be done within the
related to contract management and use of framework of market consultation or by way
the project assets. of individual interviews. This can reduce the
risk of the public and private parties reaching
It is also advisable that the PPP contract is agreements which later cannot be accepted by
designed to be flexible so that it can adapt, financial institutions and results in their refusal

22 Key principles of implementing PPP projects


to finance the project. An additional benefit of
this activity is the opportunity it provides for
the public authority to familiarise itself with
all aspects of the project, including possible
financing structures, sources of financing and
any available guarantee instruments.

Project teams

The public authority’s staff will influence the


success of a PPP project. A stable project
team with appropriate competencies, time
and personnel resources, and that is dedicated
to the task, facilitates the preparation and
implementation of the PPP project as well
as its management at the operational stage.
It allows the public entity to keep control of
the project and to manage it in a responsible
manner. It also allows for effective coopera-
tion with consultants and the private partner,
allows experience and knowledge gained to be
used in the subsequent phases of delivering
the PPP project, and increases the chances of
further projects being successfully delivered
using this approach.

Key principles of implementing PPP projects 23


5. Actions, role and responsibility
of individual institutions
Establishing Government/State level structures policy and the objective of providing public
and systems for managing and implementing services,
the Policy is critical for the development of yy coordination – ensuring consistency in
PPP. This will provide consistency and coordi- PPP-related activities across the Govern-
nation of activities and clear responsibility for ment/state administration,
the effectiveness of the Policy and will avoid yy monitoring – identifying the number
duplication of activities. and structures, as well as outcomes, of
implemented PPP projects (e.g. their effec-
Central PPP coordination and management unit tiveness, meeting of objectives set at the
assessment phase, fiscal implications),
The Minister in charge of regional develop- yy analytical – assessing the impact of legal
ment will serve in a central organisational role and institutional regulations on PPP imple-
(PPP Unit), responsible for the use of PPPs in mentation processes and on the efficiency
Poland and for coordinating the activities of and effectiveness of implemented projects
other government institutions in this regard. in meeting their objectives, as well as
A dedicated department will act as the centre assessing transparent and proper applica-
of knowledge on PPPs and will cooperate tion of the regulations,
with other PPP units within the ministries, yy legislative – preparing the necessary amend-
other public entities, bodies and teams at the ments to legal and institutional regulations
Government/State level involved in PPP (e.g. and processing their implementation,
Team for PPP, PPP Platform) and entities in the yy educational – organising training courses,
non-government sector (foundations, associa- workshops and other initiatives aimed at
tions) involved in PPP activities. Its key tasks improving the knowledge and awareness
as a central coordination and management of the public and private sector represen-
unit will include: tatives of PPPs,
yy implementation – in particular the develop- yy support – providing substantive support
ment of a methodology for implementing to public authorities to prepare and imple-
the Policy and the use of PPP in order to ment PPP projects as well as developing
pursue the Government’s socio-economic

24 Actions, role and responsibility of individual institutions


guidelines, standards and reference docu- Activities to support the further
ments to support the development of PPP, development of public-private partnership in
yy evaluation – at the request of public enti- Poland
ties, evaluating the validity and quality of
the preparation of PPP projects, The Policy identifies a series of activities, to
yy information – maintaining a platform of be implemented within a period of not more
cooperation and information exchange than two years (except for long-term activi-
amongst, inter alia, public entities, ties), needed in order to ensure the proper
representatives of business, banks, non-gov- development and use of PPPs in Poland:
ernmental organisations and international
institutions, in order to support of the 1. proposing the necessary legal amend-
development of the PPP market in Poland. ments (arising from a comprehensive
review of the PPP legal environment)
The roles of Government/State units, that are needed to eliminate inconsis-
local government units and other public tencies and improve the development of
institutions in relation to PPP PPP in Poland, and preparing and carrying
out the legislative processes required to
It is recommended that individual ministries implement those amendments. The new
and central Government bodies consider regulations should be stable (to avoid
establishing, within the framework of their exposing the relevant parties to the risk
existing structures, units to take responsibility of legal uncertainty or frequent amend-
for PPP development activities in their sector ments). They should also take into account
or region and for cooperation with the central the interests of both the public and private
unit. Other public institutions, such as self-gov- party and provide the protection for each
ernment units at different levels, universities, party.
etc. are also advised to consider the creation – responsibility: Minister in charge of
of similar units. regional development;

Actions, role and responsibility of individual institutions 25


2. developing and monitoring a PPP proj- – responsible: Minister in charge of re-
ect pipeline (a database of investment gional development in cooperation with
plans). The market’s need to know about all public contracting authorities;
future projects should be met through
a public database of PPP project plans. This 4. carrying out educational and informa-
database will identify projects that are at tion dissemination activities including
the pre-contract stage (at least in the ini- the development and implementation
tial preparation stage but before contract of a communication strategy to improve
signature) which have the potential to be knowledge about the benefits of PPP and
developed as PPPs. increase society’s acceptance and support for
– responsibility: Minister in charge of re- implementing infrastructure projects using
gional development in cooperation with this approach. The Government will carry out
all public contracting authorities; a wide range of training activities for both
the private and public sector, at basic and
3. keeping a database of signed PPP advanced levels, to prepare staff in public
projects and monitoring their imple- authorities for implementing PPP projects.
mentation and impact. In order to assess These activities will include regional training
the impact of PPP projects, ascertain the and specialised training as well as specialist
benefits of using a PPP formula and eval- workshops. Training will be aimed at the
uate the effectiveness of actions taken employees of public institutions at local,
within the framework of the Policy, a com- regional and central levels, as well as regula-
prehensive public database of PPP projects tory bodies (Central Anti-Corruption Office,
(for which contracts have been signed) regional accounting chambers, tax offices, tax
will be created. This database will serve inspection offices, public prosecutor’s offices,
as a basis for carrying out various types Supreme Audit Office). Study visits will also
of routine analyses, inter alia, to specify be carried out, with the aim of disseminating
further courses of action for developing good practice in implementing PPP projects
PPP or to evaluate the costs of risk, and in Poland. It is important to strengthen the
to use as the basis for analysing the value potential of public authorities by raising mana-
for money of PPP projects. gerial competence and improving knowledge
about PPP as a tool for implementing public

26 Actions, role and responsibility of individual institutions


infrastructure projects. In parallel, informa- and tendering stages, when obtaining
tion activities are needed in order to build financing and at contract signature and
a positive attitude towards PPPs, primarily its execution. It is necessary for the Gov-
by promoting knowledge about the potential ernment to provide advisory support for
benefits of using PPPs. The objective of these selected PPP projects. As part of this sup-
activities is also to present PPPs as a reliable, port, actions should be taken to provide
transparent, alternative method of providing substantive advisory services (financed by
necessary infrastructure and public services, the Ministry of Economic Development) on
without leading to privatisation. a larger scale than before.
– responsible: Minister in charge of re- – responsible: Minister in charge of re-
gional development; gional development;

5. developing and wide dissemination of


guidelines, recommendations, good
practice relating to, for example, project
preparation (including value for money
assessment), carrying out the tendering
procedure, standard contract clauses for
various sectors, monitoring PPP projects,
methodology for calculating the discount
rate, return of assets to the public sector,
management of PPP contracts and con-
tract changes. The use of such documents
will be mandatory for projects receiving
Government advisory support, but other-
wise can be used and applied voluntarily.
– responsible: Minister in charge of re-
gional development;

6. providing comprehensive advisory ser-


vices to public bodies at the preparation

Actions, role and responsibility of individual institutions 27


7. certification (quality assurance/assess- – responsible: Minister in charge of re-
ment). In order to increase confidence in the gional development;
selection of the PPP formula, in particular
the assessment of the benefits of the PPP 8. developing and implementing an obliga-
project and the quality of analysis carried tory opinion on the formula to be used
out prior to project implementation, it will to implement large projects financed
be possible to verify by the central coor- from the Government/State budget.
dination and management unit (PPP Unit) In the case of large projects (i.e. over
the decision to implement an infrastructure PLN 300 million of investment from the
project as PPP, as well as the adequacy of Government/State budget) intended for
the PPP project preparation. Certification traditional procurement, it is necessary
will be fully voluntary on the part of the to also assess the use of PPP. The insti-
public authority implementing the project tution responsible for the project should
and will be provided to projects once they carry out an appropriate analysis and seek
have reached a suitably advanced. The a non-binding opinion of the designated
certification will focus mainly on assess- entity (e.g. Minister in charge of regional
ing the accuracy and completeness of the development) before making a decision on
pre-implementation analysis of the project, its approach to project delivery (a so-called
the legal and organisational model pro- “PPP test”). This opinion will confirm that
posed, the mechanism for remunerating implementing the project in question
the private entity as well as the proposed using the traditional approach is valid
distribution of risks in the PPP arrangement. only if doing so will bring greater bene-
Conclusions from the certification pro- fits throughout the project lifecycle than
cess will be used to determine whether the PPP formula. These opinions will not
it is appropriate to separate the project apply to projects co-financed from the EU
certification activities, as has been the funds or non-repayable international finan-
case in other European countries, from cial instruments (e.g. Connecting Europe
the central coordination unit and trans- Facility (CEF)), projects in the defence
fer these to a specialised public advisory sector, projects concerning supplies of
entity established specifically for this sensitive equipment, sensitive services and
purpose.

28 Actions, role and responsibility of individual institutions


construction works or projects that are investment projects (e.g. preferential
already in preparation. loans for public entities). This assessment
– responsible: Minister in charge of re- should take account of both the needs
gional development; and capacity of the state budget and the
benefits which may be brought about by
9. analysing and establishing a system of the increased level of investment.
warranties and guarantees for the public – responsible: Minister in charge of public
and private sectors – creating a special finance in cooperation with Minister in
fund for PPPs to allow for financing based charge of regional development, Bank
on preferential terms and interest rates. Gospodarstwa Krajowego (National
The fund should support commercial banks Economy Bank) and Polish Development
to lend to more risky projects without Fund;
requiring expensive security packages and
imposing excessively strict conditions. In 11. support for micro, small and medi-
addition, an assessment will be carried as um-sized enterprises through training
to the possibility of making available other courses on preparing for participation in
products to reduce the costs of financing tendering procedures and advice on the
PPP projects. However, such forms of sup- planning, negotiation and delivery stages
port must not distort competition in this of PPP projects.
regard and so careful analysis is required – responsible: Polish Agency for Enter-
of the options for establishing such a fund prise Development;
and the rules under which it will function.
– responsible: Minister in charge of public 12. taking into account the characteristics
finance in cooperation with the Bank of PPP projects and the Act on conces-
Gospodarstwa Krajowego (National sion for construction works or services
Economy Bank) and Polish Development as part of ongoing training programmes
Fund; on public procurement.
– responsible: President of the Public
10. assessing opportunities to develop Procurement Office in cooperation with
instruments to co-finance the public sec- Minister in charge of regional develop-
tor’s costs of preparing and implementing ment;

Actions, role and responsibility of individual institutions 29


13. developing and implementing sectoral/ and will attract wider interest in PPP
regional strategies for PPP develop- projects from private partners (optional
ment, as stand-alone documents or as activity).
a part of more extensive sectoral/regional – responsible: interested ministries, cen-
investment strategies, including the prepa- tral Government administration bodies
ration of sectoral/regional databases and local government units.
of investment plans. This approach will
facilitate the organisation of investment
priorities at the sectoral and local levels

30 Actions, role and responsibility of individual institutions


6. Monitoring and evaluation
of the PPP Policy
The implementation of the activities provided investment outlays in national economy in
for in this document, and their outcomes, the public sector to the level of 5%.
needs to be monitored and evaluated. This yy Increase in the number of tenders ini-
evaluation will cover the period from 1 January tiated by the Government/State sector
2017 until 31 December 2020. The evaluation to select the private partner – the imple-
results will be presented to the Council of mentation of the activities provided for in
Ministers by the Minister in charge of regional this document is expected to result in the
development. initiation of at least 10 such procedures.
yy Increase in the number of signed PPP
The principal indicators against which the contracts in relation to the number of
effectiveness of the Policy’s activities will be tender opportunities announced to 40%.
assessed by 2020 are:
yy Increase in the number of implemented The evaluation should lead to conclusions
PPP investment projects – conclusion of concerning the continuation/strengthening or
at least 100 new PPP contracts. alternation of the activities described in the
yy Increased share of the value of signed Policy and be used as a tool for designing any
PPP contracts, in terms of percentage of necessary changes to the Policy.

Data source:
-
own data of the Ministry of Economic Development; “Public-private partnership in Poland. Experiences and prospects
for the future” – Sobieski Institute, 2016, PPP MARKET REPORT – Assessment of the current state and prospects
of the financial involvement of the private and public sectors in the development of public-private partnership in
Poland” – Ministry of the Economy, 2013; National Road Construction Programme for 2014-2023 (with a perspec-
tive to 2025); National Railway Programme by 2023; Resolution on the adoption of the “Assumptions for plans
to develop inland waterways in Poland for the years 2016-2020 with a perspective to 2030; “Mieszkanie plus”
programme; Update of the “National municipal wastewater treatment programme 2015”.

Monitoring and evaluation of the PPP Policy 31


Notes

Notes
Ministry of Economic Development
Department for Public-Private Partnership

Pl. Trzech Krzyży 3/5


00-507 Warszawa
www.mr.gov.pl
www.ppp.gov.pl
ppp@mr.gov.pl

ISBN: 978-83-7610-640-3

Free copy

OF ECONOMIC

You might also like