TCODE : /N/SMEP/2PEGUPDWN2

Variant : MLATP PROPAGAT (Propagation Variant)

Then put the Sales order and Item as below screen.


Then Execute. Below screen appears, here select the Line you want to work on and click on the Green
check.

Below screen appears. From here select the all lines you want to work on (Some times multiple orders )
then it turns yellow.

Once it is yellow like below screen select the option highlighted in red from below screen to do the Total
Propagation.
Propagation scheduling is done once you click it.

Then check the logs from below screen by selecting the highlighted column.
Next screen will show you the log. This is production and we have not done the propagation here so
right now here no logs generated. But Log can be seen here if it is done.

Now Sales order UPDATE has to be done by selecting the highlighted option from below screen.
Here select the first column check box and check the green check and save it.
Once this is done initial scheduling is done for Customer Service. Then they will put the shipping date or
ready date on the Sales Order.