Professional Documents
Culture Documents
Vir 0267C 15
Vir 0267C 15
Position and orientation of the optics and benches to deal with the
vertical wedges
VIR-0267B-15
Issue: 3
Date: December 8, 2015
Contents
1 Introduction and goal 1
2 The current mirror positions 2
3 A simple model 4
4 The mirror definitions for Zemax 4
4.1 The tilt of the arm cavities . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 4
4.2 The Beam splitter . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5
4.3 The West Input mirror . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5
4.4 The North Input mirror . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 6
4.5 The West Compensation plate . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 7
4.6 The North Compensation plate . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 7
4.7 The POP . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 8
4.8 PR and SR . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 9
5 Simulation results for the CITF 9
5.1 Beam positions and tilt at the CITF output . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 9
5.2 Center of mass of the CITF optics . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 10
5.3 Comparison OSD - INJ results . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 11
In the TDR, the calculation were made in 2D, the whole plane of the interferometer being implicitly tilted to take into
account the fact that the end mirrors are lower than the central optics. So for the first time, a full 3D simulations was done
and currently Zemax seems the only tool we have to handle this work.
The goal of this note is: first, to derive the new mirrors/benches positions and second, check that it is still possible
to extract the pickoff beams from the BS and CP AR surfaces. The first work will be done with Zemax with the mirror
positions defined in 3D in space and then we will propagate two beams from each input mirrors toward the injection and
detection.
The configuration tested here is called the reference solution: the BS is kept installed as it is, the POP is mounted such
as its thin part is up (so the wedge orientation is at the opposite of the BS ones) and the recombination of the beams on
the HR side of the beamsplitter happens at a height of -3 mm (instead of 0 mm presently). The reason of the 3 mm is due
to the global tilt of the arms. Indeed, the beam from the arm cavities is going upward toward the injection and detection
system, so in order to not arrive too high on those systems, it was decided to lower whole central CITF optics by 3 mm.
WE
Z
Y
WI
NI NE
BS
PRM
Table 1: Measured positions of the mirror center of mass. Height is quoted with respect to BS center, assumed to be zero.
Frame of reference for x and y: VRS, for z: ∆Z = ZV RS − ZBS . Below are the current mirror positions, not the one of
the reference solution (which will be given in table 2). The detailed table as provided by INF is shown in figure 17 (last
page).
Mirror coordinates Method
Mirror name X[m] Y[m] ∆Z[m]
BS 0.0015 0.0248 0 F0 (SAT suspension point)
WI −5.6033 0.0026 −0.0008 F0 (SAT suspension point)
NI −0.0026 5.7777 0.0024 F0 (SAT suspension point)
PR −0.0189 −6.0849 −0.0012 square flange center
SR 6.0422 0.0216 0.0031 DIMA center
NE 0.0129 3005.7877 −0.9020 square flange center
WE −3005.5847 0.0312 −2.2233 square flange center
IT −0.0336 −11.0015 −0.0048 F0 (SAT suspension point)
DT 10.9718 −0.0028 0.0046 F0 (SAT suspension point)
VIR-0267B-15
issue : 3
The reference solution date : December 8, 2015
page : 4 of 25
3 A simple model
Before going to the full Zemax simulation, a simple model could be derived to have some rough estimate of some very
relevant numbers. First we can calculate the tilt of the laser beam coming from the arms:
The West end mirror is around 2.2 m below the central interferometer. So the beam coming from the arm cavity will be
tilted by 2.2/3000 which is around -730 µrad. Similarly, with the North end mirror 0.9 m below the central interferometer,
the laser coming back from the north arm is tilted upward by -300 µrad.
Assuming the beamsplitter is at a height of 0, the West input mirror should be 6 × 730 × 10−6 lower than the BS (that
is -4.4 mm). For North input mirror, we found it is -1.8 mm. So the 2 input mirrors are always lower than the BS.
If we suppose the BS in the middle of the recycling cavities, the PR height will be determined by the beam tilt coming
from the North arm, whereas the SR height is derived by the beam coming from the West arm. So following, the previous
reasoning, we can expect PR and SR to be respectively 1.8 mm and 4.4 mm higher than BS. So that simple result high-
lights the fact that the whole plane of the interferometer is tilted.
Then a second useful number is the lateral shift in transmission from the beamsplitter. For a beamsplitter of thickness
t = 65.5 mm, refractive index n = 1.45 and with a beam incident at 45◦ , the lateral shift ∆y of the laser beam in
transmission is given by [?]: s
1 − sin2 θ
∆y = t sin θ 1 −
n2 − sin2 θ
That gives us ∆y = 20.4 mm. The simple calculations presented here will explain most of the results in the next section,
where the exact shape and positions of the mirrors will be implemented.
Z
Y
WI
WE
X
BS
Z
Y
The red dot coordinates and the front face tilts are given by:
Coordinates [mm] Tilt [deg] Tilt [mrad]
Surface name X Y Z θx θy θz θx θy θz
BS front -20.5 0 -3 0 0 45 0 0 785
BS is 65.5 mm thick has a vertical wedge of 380 µrad (0.022◦ ) with the thin part down. In the simulation, the wedge
was added to the AR side.
WI
Figure 4: Zoom on the West input mirror
WI is 200 mm thick has no wedge but two curved surfaces of radius 1420 m (meniscus lens). The X coordinate is
given from the tower position, the Y from the TDR whereas the Z coordinates is given by the desired recombination height
on the beamsplitter.
NI
Figure 5: Zoom on the West input mirror
The red dot coordinates and the front face tilts are given by:
VIR-0267B-15
issue : 3
The reference solution date : December 8, 2015
page : 7 of 25
NI is 200 mm thick has no wedge but two curved surfaces of radius 1420 m (meniscus lens).The X coordinate is given
from the TDR, the Y from the tower position whereas the Z coordinates is given by the desired recombination height on
the beamsplitter.
CP W
Figure 6: Zoom on the West CP
The red dot coordinates and the front face tilts are given by:
Coordinates [mm] Tilt [deg] Tilt [mrad]
Surface name X Y Z θx θy θz θx θy θz
CP W front -5303.3 0.00 -7.4 0 -0.0209 0.0372 0 -0.364 0.650
15). In DET format, it is Tx = 375 µrad (rotation of the CP around its horizontal axis) and Ty −650 µrad (rotation of the
CP around its vertical axis). To be noted the change of sign with the CP W in the vertical tilt.
The 2 values, could be translated in the Virgo Reference System as an extra tilt of θx = 375 µrad and θz = −650 µrad.
This plate has also small wedge (< 20 µrad) which is included in the simulation, the thin part is down as it is now
installed. The coordinates for the CP front surface are given knowing the separation from the IM and the CP which is of
200 mm (from AR IM surface to CP first surface).
CP N
Figure 7: Zoom on the North CP
The red dot coordinates and the front face tilts are given by:
Coordinates [mm] Tilt [deg] Tilt [mrad]
Surface name X Y Z θx θy θz θx θy θz
CP N front 0 5477.7 -4.9 0.0044 0 -0.0372 0.076 0 -0.65
POP
Z
Y
The red dot coordinates and the front face tilts are given by:
VIR-0267B-15
issue : 3
The reference solution date : December 8, 2015
page : 9 of 25
POP is 35 mm thick has a vertical wedge of 1000 µrad (0.057◦ ) with the thin part up (at the opposite of BS). A slight
tilt along the horizontal plane of the POP is implemented in order to arrive at the right height on the first optic of the SPRB
telescope, the detailed explanation is given in section 6.3.
4.8 PR and SR
For the simulations done at LMA, PR and SR are not included in the simulation because their positions are results of the
simulation itself. For the expected positions of PR and SR, we took the actual position of the tower along the beam axis
(along Y for PR and along X for SR) to set that particular coordinate. The transverse coordinates are derived from the
simulations and are reported in the next section.
In the Zemax simulation, a screen (i.e. a position detector) is inserted at the position of PR (HR side), located
(−95 mm) along the y axis with respect to the POP front face, (PR Y = -6035 mm). Similarly, the SR screen is positioned
at the coordinate X = 5994 mm.
The beam (B5), the reflection to the BS AR side from the beam coming from the North arm, on SR has for coordinates
and tilt:
Coordinates [mm] Tilt [deg] Tilt [mrad]
X Y Z θx θy θz θx θy θz
SR beam 5994 72.1 -3.2 0 -0.001 0 0 -0.015 0
VIR-0267B-15
issue : 3
The reference solution date : December 8, 2015
page : 10 of 25
The B5 beam is going slightly downward with a tilt of −15 µrad as seen from BS toward the detection.
1. with Zemax, we can get the transverse (perpendicular to the laser beam so also including the beam height) positions
of the optics. That what is explained in the previous section.
2. Optocad simulations have been done to check the longitudinal lengths in the recycling cavities, that is particularly
important to ensure the proper resonance of the sidebands. The results of the desired optimal mirror positions are
shown in the table 2. It is planned to also derive the optical path directly in Zemax in a near future for cross-
checking.
Table 2: Calculation of the positions of the mirror center of mass from the Zemax and Optocad simulations.
Coordinates
Mirror name X[mm] Y[mm] Z[mm]
BS 2.7 23.2 −3
WI −5599.9 0 −7.4
NI 0 5774 −4.9
PR −19.4 −6084.9 0.0
SR 6044.0 20.3 2.6
Comparing the results from the Zemax and Optocad simulations (table 2) and the actual tower positions from the
beginning (table 1), one can derive the required mirror shift which are shown in the table 4.
Table 4: Difference between desired mirror positions from Zemax and Optocad and the actual tower positions (Zemax/Op-
tocad results - actual tower positions). The numbers indicated by how much the suspension has to be shifted to reach the
optimal position. The blue numbers are derived from Optocad.
Coordinates
Mirror name ∆X[mm] ∆Y[mm] ∆Z[mm]
BS 1.2 −1.6 −3
WI 3.4 −2.6 −6.6
NI 2.6 −3.7 −7.3
PR −0.5 0 1.2
SR 1.8 −1.3 −0.5
VIR-0267B-15
issue : 3
The reference solution date : December 8, 2015
page : 11 of 25
1. The main adjustment to be done is along the z direction, that is expected since the reference plane is now 3 mm
lower and for the first time, the mirror positions have been derived in 3D, so taking into account the beam tilt due
to the arm cavities, the input mirrors have to be lower than the BS.
2. The adjustment to be made for PR and SR are reasonable, with less than 2 mm for the 3 coordinates.
Table 5: Meniscus lens optical center position in the Virgo reference system.
Coordinates [mm] Tilt [deg] Tilt [mrad]
X Y Z θx θy θz θx θy θz
ML front -19.2 -10656 0.4 -0.004 0 0 -0.07 0 0
Note that the meniscus lens (ML) should be tilted around θx by −0.004◦4 meaning that the whole bench and conse-
quently the beam should be tilted around θx by this amount.
According to what we have measured and extrapolated from the measurements, the meniscus lens center coordinates
are: XM L = (−16.8 ± 0.5) mm and ZM L = (−2.0 ± 0.5) mm
Indeed, starting from Injection tower filter 0 coordinates in the VRS measured by INF group [?], we get xIT F 0 =-33.6
mm. Since we know that the meniscus lens axis is shifted by 14 mm towards East respect to SIB1 bench center and that
SIB1 was moved by 4.2 mm towards East5 . xM L = −33.6 + 14 + 4.2 = −15.4 mm.
The vertical position of the meniscus lens center was estimated using a Leica level6 .Thus, the displacement of the Menis-
cus lens and consequently of the SIB1 bench is given in table 6.
In conclusion, horizontally, we have to move SIB1 bench, IMC end mirror by 3.8 mm westward. This should not be
a problem for what concerns the suspension according to SAT [?]. For SIB1, in order to re-center the bench blocking
3 Virgo Logbook entry #32372
4 Here one can notice, one difference from the OSD value which is found to be −0.003◦
5 Virgo Logbook entry #32426
6 Virgo Logbook entry #32334
VIR-0267B-15
issue : 3
The reference solution date : December 8, 2015
page : 12 of 25
Table 6: Meniscus lens optical center position difference respect the meniscus lens current estimated position.
∆X [mm] ∆Z [mm]
Difference respect to ML -3.8 2.4
estimated optical center
system we will have to move the bench blocking system and to move the ground coils supports. This operation will
require a re-opening of IB tower and might take one day. A top view of one ground coil magnet system of SIB1 south side
is depicted on figure 9. There should be a clearance of approximately 9.5 mm between the coil and the magnet support
since we have to move the bench by only 3.8 mm towards west it should be ok.
9.5 mm
Figure 9: top view of the South ground coils. As one can see on the figure the distance between the coil and the magnet
support (attached to SIB1) is of the order of 9.5 mm.
VIR-0267B-15
issue : 3
The reference solution date : December 8, 2015
page : 13 of 25
For the IMC end mirror, when the suspension point will have been moved by 3.8 mm an inspection inside MC tower
is required in order to check that there is no interference of the payload/marionette with all the safety structures installed
in MC tower around the payload.
Vertically, if we lower the ITF plane by 3 mm, SIB1 bench should be raised by only a few mm. The EIB height should be
ok (currently a laser beam located 100 mm from the optical table is at z=0mm in the VRS). No IMC end mirror vertical
displacement is required.
For what concerns aspects related to the planning, we give hereafter a list of tasks and an estimation of the time required
to modify the position of INJ benches to cope with the new ITF optical configuration. The main actions which have to be
done in the next months are listed below:
• Move SIB1 bench up by 2.4 mm.
• Move SIB1 bench westward by 3.8 mm.
• Check ground coils centering and re-center it and the blocking system (IB tower opening required).
• Move IMC end mirror westward by 3.8 mm.
• Check IMC payload and marionette safety structures (MC tower opening required).
• Input beam should be realigned to account for the bench displacement. SIB1 global realignment using on-board
actuators has to be foreseen.
Overall, we have to foresee 2 to 3 weeks of activity to make all this work and recover a proper functioning of INJ
subsystem.
• As written in section 4.9, the dark fringe beam (B1) reaching the SR mirror and propagating towards the suspended
detection bench SDB1 is tilted vertically by 961 µrad, instead of the expected vertical tilt of (739 µrad) in the case
of a BS horizontal wedge. Given this tilt angle of 961 µrad, the dark fringe beam reaches the first component of the
SDB1 bench, i.e. the telescope meniscus lens, at an altitude Z = 7.1 mm in the VRS.
• With a BS horizontal wedge the B1 beam transmitted by the BS was tilted horizontally by 300 µrad (with respect to
the west arm axis) due to the crossing of the BS wedge. This horizontal tilt induced an horizontal shift of 3.2 mm of
the beam position at the entrance of the SDB1 bench. With the BS vertical wedge, the B1 beam is no longer tilted
in the horizontal plane, which implies that the beam position on the SDB1 bench changes by +3.2 mm along the Y
axis.
The impact of the B1 beam position at the entrance of the detection bench is discussed in the two sub-sections that follow.
Moreover, in order to compensate for the vertical tilt (961 µrad) of the B1 beam reaching the SDB1 bench, the tele-
scope meniscus lens will be shifted up in the vertical plane by 3.5 mm with respect to its current nominal position (ie
center of the lens at 100 mm from the bench floor). It has been checked with two independent simulations (Zemax,
Optocad) [?] that such a vertical shift of the meniscus lens allows to obtain in transmission of the lens a beam which
propagates horizontally (ie parallel to the bench surface) and at 100 mm from the bench floor. This is also the case for
VIR-0267B-15
issue : 3
The reference solution date : December 8, 2015
page : 14 of 25
beams at different wavelengthes than the YAG (790 nm for the Hartmann beam, 532 nm for the auxiliary laser). Indeed
it was checked with the Zemax simulation that the effect on the beams position and tilt of the different refractive index
of the meniscus lens at those wavelengths is well negligible. The Zemax simulation has also been used to check that the
vertical shift of the meniscus lens has a negligible impact on the theoretical mode matching with the OMC which remains
above 99.9%. Furthermore the needed shift (ie 3.5 mm) is half the available range of the picomotor (±6.3 mm) allowing
to adjust the vertical position of the meniscus lens mount.
As a consequence of the compensation of the vertical tilt of the incident beam by a vertical translation of the menis-
cus lens, the B1 beam will be miscentered by 3.5 mm with respect to the center of the lens. Given the lens diameter of
150 mm and the beam size (w = 22 mm), this miscentering is acceptable. It has also been checked with a Zemax simu-
lation [?] that in this configuration the B5 beam will be miscentered by 13 mm with respect to the center of the meniscus
lens, which is also OK for a negligible clipping on the edges of the optic mount.
Table 7: Expected position of the center of the SDB1 bench in the Virgo reference system, for the reference solution. The
Z position refers to the altitude of a point located at 100 mm above the bench floor, that is to say the expected altitude of
the beam.
Coordinates [m] Tilt [deg]
X Y Z θx θy θz
Center of SDB1 bench 10.9718 -0.0005 0.0071 0 0 0
Table 8: Expected position of the dark fringe telescope meniscus lens optical center in the Virgo reference system, for the
reference solution.
Coordinates [m] Tilt [deg]
Surface name X Y Z θx θy θz
ML front 10.6168 0.0203 0.0106 0 0 0
6.2.2 Impact of the horizontal shift of the B1 position at the bench input
By comparing the Y coordinate of the center of the meniscus lens given in table 8, and the Y coordinate of the B1 beam
reaching the SR mirror in section 4.9, one can notice a difference of 4.3 mm (20.3 mm-16 mm). This value is compatible
(with an error of about 1 mm) with the expected 3.2 mm miscentering on the meniscus lens due to having the BS wedge
becoming vertical. This implies that the beam will arrive on the meniscus lens with a horizontal miscentering by 4.2 mm,
with respect to the meniscus lens center as it was installed assuming a BS horizontal wedge. To deal with this, two actions
will be performed:
• The SDB1 bench will be translated by 2.3 mm along the Y axis, thus reducing the residual horizontal beam mis-
centering down to 2 mm with respect to the meniscus lens. The SDB1 bench translation will be performed by
displacing the suspension axis of the bench. The requested translation (2.3 mm) is compatible with the tuning
range of the suspension axis [?]. It must be underlined that a translation of the SDB1 bench will result in a similar
horizontal shift of the bench output beams which propagate towards the SDB2 bench. Therefore the translation
of the bench by 2.3 mm towards the Y axis, combined to the vertical translation by 2.5 mm (section 6.2.1), will
induce a √
miscentering of the beams passing through the mini-links between the SDB1 tower and SDB2 mini-towers
equal to 2.32 + 2.52 = 3.4 mm. Such miscentering remains lower than the foreseen margin for the mechanical
positioning of the mini-links (order of 5 mm) and is therefore acceptable.
VIR-0267B-15
issue : 3
The reference solution date : December 8, 2015
page : 15 of 25
• The residual miscentering of 2 mm with respect to the meniscus lens center will be compensated by a translation
(by 2 mm) of the meniscus lens along the Y axis. This translation can be applied with a picomotor already foreseen
to correct the beam miscentering. A Zemax simulation [?] was performed to check that a horizontal miscentering
of the beam by 3.2 mm (larger than the one foreseen) can be compensated by translating the meniscus lens by the
same amount. In the simulation the meniscus lens was also shifted vertically to compensate the beam vertical tilt
angle as mentioned in 6.2.1. The simulation shows that the horizontal translation of the meniscus lens allows to
recover a good matching and a good alignment with the OMC (above 99.8%) under the assumption of a 3.2 mm
miscentering. Moreover it has also been checked with the Zemax simulation that the horizontal translation of the
meniscus lens has a low impact on the position and tilt of the Hartmann beam (at 790 nm) and auxiliary beam (at
532 nm): indeed after 664 mm of propagation after the dark fringe telescope, the YAG beam and the Hartmann
beam are only separated by 0.2 mm (0.55 mm between the 532 nm and the 1064 nm beams) for a translation of the
lens of 3.2 mm (in reality the needed translation will be only 2 mm, and thus the beam separation even smaller).
This type of deviation between the YAG beam and the other wavelengthts should not require any correction on the
bench.
The actions described above correspond to the reference solution to deal with the horizontal shift of the dark fringe beam.
It must be underlined that alternative solutions exist, if for instance, the optical distortions induced by the dark fringe tele-
scope when the meniscus lens is translated turns out to be more significant than expected. In this case a possible solution
would be to correct the beam horizontal shift entirely by a translation of the bench. Backup solutions are discussed in
section A in case the needed translation to be applied on the SDB1 bench turns out to be larger than expected.
The expected position of the center of the SDB1 bench in the VRS coordinates is shown in Table 7. The bench coor-
dinates have been deduced from the coordinates of the center of the detection tower derived from the SAT suspension
point (cf. Table 1). The bench and the detection tower are expected to be at the same X coordinate, while the bench will
be shifted by +2.3 mm along the Y axis and by +2.5 mm along the Z axis with respect to the tower center. The expected
position of the meniscus lens, after applying the vertical translation to compensate the tilt of the incident beam and the
horizontal translation to compensate the residual horizontal miscentering of the beam is shown in table 8.
(with opposite sign) in the vertical plane. An Optocad simulation [?] of the pick-off telescope (simulating the optical path
projected in a vertical plane) has confirmed these results.
POP
B4
19 mm
7.3 mrad
Z=0
470 µrad
Z From BS
Y
X
Figure 10: Tuning of the B4 beam altitude with a POP tilt angle.
Lens L2
Doublet
Folding mirror
M2
Figure 12: Top view of the SDB1 bench. The purple circle indicates the position of the SDB1 B5 M1 mirror where the
two beams B1 and B5 are separated. The red and yellow lines indicate the foreseen optical paths for B1 and B5 when the
BS wedge was supposed to be horizontal.
B5
mirror mount
B5
support
21 mm
B1
100 mm
BENCH FLOOR
Figure 13: Scheme of the B5 beam extraction with a one-inch folding mirror. The beams are drawn with a diameter equal
to 6w. The folding mirror is rotated by 45◦ with respect to the incident beams (and hence the oval shape of the mirror).
VIR-0267B-15
issue : 3
The reference solution date : December 8, 2015
page : 19 of 25
B5
B1
Figure 14: Projection of the B1, B5 and secondary beams coming from the CP reflections in a plane perpendicular to the
propagation of the B1 beam and located 575 mm after the dark fringe telescope, as predicted by the DarkF simulation.
(about 21 mm) under this assumption. Similarly a simulation was run assuming no horizontal shift of the incident beam
and lead to the same results concerning the B1/B5 separation. One can conclude that the separation between B1 and B5 at
the telescope output is rather independent from the selected strategy for dealing with the vertical tilt of the B1 beam and
its horizontal shift.
By combining an Optocad simulation (to estimate the separating distance between B4 and the CP beams) and a geo-
metrical calculation (to extract the right position between the beams in 3D) [?], one obtains after the pick-off telescope,
on the SPRB bench, the distribution of beams shown in Figure 15. The beams B4, B6, B9, B6p and B9p are reflected
on the surface of the POP which points towards the BS, while the beams B4’, B6’, B9’, B6p’, B9p’ are reflected on the
surface of the POP pointing towards PR. With the thicker edge of the POP down, the B4’, B6’, B9’, B6p’, B9p’ beams
are obtained from the B4, B6, B9, B6p, B9p beams by a vertical down translation of 32.8 mm. As shown in Figure 15,
with this choice of wedge orientation, and CP tilts, all the beams are well separated, which makes possible the extraction
of the B6 and B9 beams.
The positions of the CP beams and the B4 beam after the pick-off telescope have also been checked with a DarkF
simulation. The predicted beam positions are shown in Figure 16. By comparing this figure with Figure 15, one can
notice an opposite sign on the relative altitude of the beams B4’, B6’, B9’, B6p’, B9p’ with respect to the beams B4,
7 The front surface of the CP is defined as the surface pointing towards the arm cavities, while the back surface is defined as the surface pointing
towards PR. B6 refers to the beam from the West CP and B9 from the North.
VIR-0267B-15
issue : 3
The reference solution date : December 8, 2015
page : 20 of 25
B6, B9, B6p, B9p: this is due to the fact that an opposite orientation have been chosen for the POP wedge in the DarkF
simulation. Another difference between the two simulations comes from the fact that multiple reflections on the CP have
been included in DarkF, which is why more beams are visible in Figure 16. Beyond these differences, the two figures are
very similar, which confirms that the positions of the CP beams with respect to B4 are well understood.
B9p B6p
B4
B6 B9 32.8 mm
B9p’ B6p’
B4’
B6’ B9’
Figure 15: Expected positions of the B4 beam and the beams coming from the reflections on the CP (B6, B9, B6p, B9p),
in a plane perpendicular to the direction of propagation of B4 and located 280 mm after the pick-off telescope. The beams
are drawn with a diameter corresponding to 8w. B4, B6, B9, B6p, B9p refer to the beams reflected on the main surface
of the POP (ie the one with the higher reflectivity), while B4’, B6’, B9’, B6p’, B9p’ refer to the beams reflected on the
second surface of the POP.
B4’
B9p’ B6p’
B6’ B9’
B9p B6p
B6 B9
B4
Figure 16: Projection of the B4 and secondary beams coming from the CP reflections in a plane perpendicular to the
propagation of the B4 beam and located 251.3 mm after the pick-off telescope, as predicted by the DarkF simulation.
The prime beams are inverted compared to figure 15 because the POP wedge for the DarkF simulations was in opposite
direction.
• The bench should be rised by 2.5 mm as explained in section 6.2. A translation along the Y axis of the bench by
2.3 mm is also foreseen as explained in section 6.2.2.
• Once the optical components of the bench have been reshuffled, an adjustment of the bench balancing will be
needed.
• The meniscus lens will be rised by 3.5 mm as explained in section 6.2, and translated along the Y axis by 2 mm as
explained in section 6.2.2. These steps should be performed only when the real ITF beam is available on the SDB1
bench.
Overall it might take about 2 months between the time when a decision is made to go ahead with the proposed solution
for tackling the BS vertical wedge and the time when the reshuffling of the SDB1 bench is completed.
2. change the path of pick-off beams originated by residual reflection off the wedged surfaces;
3. change the path of pick-off beams refracted through the wedged surface.
The wedge angles considered here are of the order of some ∼100 µrad. Effects like in 1 could change the peak of
light back-scattered from the wedged surface so that if the maximum was expected at a given direction, it is now changed
to a direction rotated by 90◦ around the optical axis. However, due to the inherently cylindrical symmetry of the baffle
system inside vacuum vessels, this rotation does not represent a problem.
The effects 2 and 3 deals with the pick off beams circulating in the power recycling cavity. However, due to their
small angular tilt compared to the length of the PRC, those beams are always superimposed with the main beam and so
the baffles have little interaction with the circulating pick off beams. As explained before the separation main beam - pick
off beams is done after the different telescopes.
If we take into account the tilt of the arm cavities, the heights of the core-optics in the central area will be adjusted.
This means, in turn, that also the main optical axis is tilted with respect to the axes of the central links and flanges where
baffles are installed. However, baffles are designed to cope with centering accuracy of the order of ∼ 10mm while the
foreseen tilt of the optical axis is equivalent to an off-axis of ∼ 5mm.
As a conclusion, the change of orientation of the BS-wedge and the tilt of the arm cavity axes have negligible impact
on the baffle system in the CITF, while the beam-dumps and diaphragms on the suspended benches have to be designed
in order to cope with the new beam paths.
10 Conclusion
In this document, the reference solution proposed to manage the vertical wedges has been detailed. Since the beamsplitter
was the first suspended mirror of all the CITF optics, it was decided to leave it with its current wedge orientation. As
recommended by PAY, the beamsplitter and input mirrors have been slightly shifted to be at their nominal TDR values.
Then the PR, POP and SR postions have been calculated in 3D using Zemax. The recommended mirror positions are all
within 3.5 mm in the horizontal plane from their current expected positions. The proposed change are relatively small
since the wedge orientation has little impact on the beam positions in the CITF (as a consequence of the small wedge
angles used).
The suspended benches on the injection and detection sides have also to be tuned in position and tilt to manage
the new laser beam positions and inclinations. The present study found that the changes are manageable and could be
implemented. The bench and IMC tuning to accommodate the new position may take around 3 weeks on the injection
side. Regarding the detection, the reshuffling and tuning of the suspended benches may take 2 months.
The main incertitude was for the destination of the pick off beams. That concerned in particular the beam reflected by
the AR side of the beamsplitter (B5) which is extracted after the dark fringe detection telescope and the two reflections
from the CPs sides which have to be well separated from other beams on the SPRB bench. It was shown that the extraction
of that beams are still possible thanks to a modifications of the CP tilt and a new arrangement of the benches.
So no show-stopper has been found which can prevent us implementing the reference solution. As a reminder, the
table 9 summarises where the mirrors (center of mass) should be located.
Table 9: The implementation of the reference solution required the mirror center of mass to be at the following positions:
Coordinates
Mirror name X[mm] Y[mm] Z[mm]
BS 2.7 23.2 −3
WI −5599.9 0 −7.4
NI 0 5774 −4.9
PR −19.4 −6084.9 0.0
SR 6044.0 20.3 2.6
VIR-0267B-15
issue : 3
The reference solution date : December 8, 2015
page : 23 of 25
3. Launch the simulation inside the local folder (with Python installed):
p y t h o n AdV Layout . py
page : 25 of 25
towers. The spread of these differences for any single tower with respect to the BS was within a couple of mm.
date : December 8, 2015
Instead, we reported the average difference between the same reference points at the level of the square flange for different
we do not have the same measurement, so it was not possible to compare the same reference points for all the towers.
value of zBS = 9.3979 refers to the height of the F0 prism measured by A. Paoli for the BS suspension. For some towers
Figure 17: Detailed table of the expected mirror positions as provided by INF. The positions were confirmed by SAT. The