Rivised Unit Rate For Jimma Zone 2015 E.

C Road s project

UNIT RATE ESTIMATIONS FOR RURAL ROAD PROJECT


DF 1
Region:-Oromia
Zone:-Jimma
Contract
Pay Item No Description Unit Quantity Unit Rate
Amount

SERIES 2000 Setting out & Site Clearance


Division 2100 Setting out the horizontal Alignment
21.01 Setting out the horizontal Alignment LM 3.47 `
DIVISION 2100 Total sum -
Division 22 SITE CLEARANCE -
22.01 Grass cutting and Bush Clearing [Light] M2 0.81 -
22.02 Bush Clearing [Heavy] M2 1.11 -
22.03 Tree cutting and stumps removal - -
a Thickness in diam [20-50cm] NO 39.88 -
b Thickness in diam >50cm NO 81.18 -
c thickness of diam>100cm NO 162.36 -
22.04 stone/Boulders removal - -
a Diam. [<100cm ] of out cropped M3 93.38 -
b Diam. >150cm m3 152.94 -
22.05 Stripping and Grubbing removal M2 2.99 -
DIVISION 2200 Total sum
SERIES 2000 Total Sum -
SERIES 3000 Earth Works
DIVISION
Establishment of vertical alignment
3100
31.01 Establishment of vertical alignment M 3.52 -
31.02 excavation to level and compaction -
soft Material (ordinary soil or hard soil) (cut-
a M3 59.17 -
fill)
b intermidiate material(soft& decomposed Rock)(cut-fill) m3 79.52 -

c Hard Rock (cut-fill) m3 239.63 -


31.03 constraction of embankment -
1 side borrow M3 -
production of side borrow fill, spreading
a M3 89.97 -
and compaction
borrow materials production , loading,
unloading, transporting, spreading, and
ll compaction using dump truck.Tractor, M3
Animal cart, lobour and loading from a
distance of -
a (0.4≤x≤5) Km m3 223.11 -
b (5<X≤0)Km m3 248.67 -
c (10<X≤5)Km m3 273.53 -
d (15<x≤20)Km m3 295.94 -
e m3 338.48
(20<x≤25)Km -
f m3 378.62
(25<x≤35)Km -
DIVISION 3100 Total sum -
DIVISION
CONSTRUCTION OF THE ROAD FORMATION
3200
Side drain excavation and throwing to the
centere of the road for use of camber
32.01
formation if suitable or/ and cart away
unsuitable/excess material at distance not
soft Material (ordinary soil or hard soil) (cut-
a m3 87.36
fill) -
intermidiate material(soft& decomposed
b m3 121.75 -
Rock)(cut-fill)
c Hard Rock (cut-fill) m3 278.59 -
Spreading and Compaction for Camber
32.02
formation -
spreading and thrown to the centere of the road
a m2 11.35 -
and Compaction for Camber formation
32.03 Miter Drain/Catch water drain -
a soft materia lirrespective of depth m3 87.36 -
b intermidiate material irrespective of dpth m3 121.75 -
DIVISION 3200 Total sum -

2015 First quarter Jimma zone construction Authorithy Feb, 2022


Rivised Unit Rate For Jimma Zone 2015 E.C Road s project

UNIT RATE ESTIMATIONS FOR RURAL ROAD PROJECT


DF 1
Region:-Oromia

DIVISION
Excavation for minor drainage structure
3300
33.01 Excavation for drainage structure
soft Material (ordinary soil or hard soil) (cut-
a M3 87.36
fill) -
intermidiate material(soft& decomposed
b M3 121.75
Rock)(cut-fill) -
c Hard Rock (cut-fill) M3 278.59 -
Backfilling using excavated material
33.02 M3 166.23
including copaction (for a structure) -
Backfilling using selected Granular material
33.03 including compaction (using Dump
truck,tractor, LODER.DL from the distance -
a (0≤ x ≤5) Km M3 476.79 -
b (5< X ≤10)Km M3 525.44 -
c (10 <X ≤15)Km M3 551.31 -
d (15<x ≤20)Km M3 588.56 -
f (20<x ≤25)Km M3 625.82 -
e (25<x ≤35)Km M3 681.71 -
G-20 Capping layer with a minimum
4days socked CBR of 20% (using Dump
33.04
truck ,tractor ,LOADER.DL from the distan
-
a (0 ≤x ≤5) Km M3 264.08 -
b (5<X ≤10)Km M3 295.65 -
c (10<X ≤15)Km M3 322.28 -
d (15<x ≤20)Km M3 359.01 -
e (20<x ≤25)Km M3 390.38 -
f (25<x ≤35)Km M3 437.74 -
DIVISION 3300 Total sum
-
DIVISION
constraction of Dry Masonary
3400

Construction of dry masonry stone


Transported (using Dump truck, Tractor, DL
34.01
from distance of )

a (0 ≤x ≤5) Km M3 1,229.49 -
b (5<X ≤10)Km M3 1,302.96 -
c (10<X ≤15)Km M3 1,390.67 -
d (15<x ≤20)Km M3 1,614.71 -
e (20<x ≤25)Km M3 1,735.77 -
f (25<x ≤35)Km M3 1,971.70 -
DIVISION 3400 Total sum -
SERIES 3000 Total Sum -
series 4000 Culvert and Drainage Works
DIVISION
PIPE LAYING
41000
41.01 PIPE LAYING
Reinforced concrete pipe (c-25) production &
laying on class-B bedding

a Nominal diameter 750 mm LM 5,428.74 -


b Nominal diameter 910 mm LM 7,574.92 -
c Nominal diameter 1060 mm LM 9,353.21 -
d Nominal diameter 1220mm LM 13,618.13 -
DIVISION 4100 Total sum -

2015 First quarter Jimma zone construction Authorithy Feb, 2022


Rivised Unit Rate For Jimma Zone 2015 E.C Road s project

UNIT RATE ESTIMATIONS FOR RURAL ROAD PROJECT


DF 1
Region:-Oromia
DIVISION MASONRY FOR MINOR DRAINAGE
4200 STRUCTURES
Construction of cemented Mortared class ”B”
42.01 stone masonry (1:4). For stone source

a distance of (0,5] Km M3 3,450.77 -


b distance of (5,10] Km M3 3,571.83 -
c distance of (10,15] Km M3 3,692.88 -
d distance of (15,20] Km M3 3,815.45 -
e distance of (20,25] Km M3 3,936.89 -
f distance of (25,35] Km M3 4,119.04 -
g distance of (35,45] Km M3 4,361.92 -
h distance of (45,55] Km M3 4,373.95 -
i distance of (55,65] Km M3 5,002.23 -
Construction of cemented Mortared class ”c”
stone masonry (1:6). For walls, ford, head
42.02
and wing walls. Retaining wall
-
a distance of (0,5] Km M3 3,179.75 -
b distance of (5,10] Km M3 3,300.43 -
c distance of (10,15] Km M3 3,421.48 -
d distance of (15,20] Km M3 3,542.54 -
e distance of (20,25] Km M3 3,663.60 -
f distance of (25,35] Km M3 3,845.19 -
g distance of (35,45] Km M3 4,087.31 -
h distance of (45,55] Km M3 4,329.42 -
i distance of (55,65] Km M3 4,571.54 -
DIVISION 4200 Total sum -
DIVISION
Concrete for Minor Drainage StructureS
4300
Minor Drainage Structures (Inlet and outlet
43.01 M3 3,505.08 -
concrete Structures for culvert(c-20)
DIVISION 4300 Total sum -
DIVISION
construction Check Dams
4400
44.01 Check dams
Dry masonry production. Hauling. Loading.
a Unloading and placing

1 (0 ≤x ≤5) Km M3 1,229.49 -
2 (5<X ≤10)Km M3 1,302.96 -
3 (10<X ≤15)Km M3 1,390.67 -
4 (15<x ≤20)Km M3 1,614.71 -
5 (20<x ≤25)Km M3 1,735.77 -
6 (25<x ≤35)Km M3 1,971.70 -
b cement mortared Masonry class(1:6) -
a distance of (0,5] Km M3 3,179.75 -
b distance of (5,10] Km M3 3,300.43 -
c distance of (10,15] Km M3 3,421.48 -
d distance of (15,20] Km M3 3,542.54 -
e distance of (20,25] Km M3 3,663.60 -
f distance of (25,35] Km M3 3,845.19 -
g distance of (35,45] Km M3 4,087.31 -
h distance of (45,55] Km M3 4,329.42 -
i distance of (55,65] Km M3 4,571.54 -

2015 First quarter Jimma zone construction Authorithy Feb, 2022


Rivised Unit Rate For Jimma Zone 2015 E.C Road s project

UNIT RATE ESTIMATIONS FOR RURAL ROAD PROJECT


DF 1
Region:-Oromia
DIVISION 4400 Total sum -
DIVISION
Stone pitching
4500
Method 1
Dry stone pitching(Method 1), production,
45.01
Hauling,Loading, Unloading, and placing
a (0 ≤x ≤5) Km M2 276.64 -
b (5<X ≤10)Km M2 293.17 -
c (10<X ≤15)Km M2 312.90 -
d (15<x ≤20)Km M2 363.31 -
e (20<x ≤25)Km M2 390.55 -
f (25<x ≤35)Km M2 443.63 -

Method 2
Grouted (with mortar) stone pitching production
45.02 . Hauling. Loading. Unloading. and placing

a (0 .4 ≤x ≤5) Km M2 529.96 -
b (5<X ≤10)Km M2 550.07 -
c (10<X ≤15)Km M2 570.25 -
d (15<x ≤20)Km M2 590.42 -
e (20<x ≤25)Km M2 610.60 -
f (25<x ≤35)Km M2 640.86 -
Wired and Grouted (with mortar) stone
pitching production . Hauling. Loading.
45.03
Unloading. and placing

a (0 ≤x ≤5) Km M2 241.74 -
b (5<X ≤10)Km M2 253.02 -
c (10<X ≤15)Km M2 264.29 -
d (15<x ≤20)Km M2 275.56 -
e (20<x ≤25)Km M2 286.84 -
f (25<x ≤35)Km M2 298.11 -
DIVISION 4500 Total sum -
DIVISION
GABIONS
4600
46.01 GABIONS
Gully using Check Dams [ Dry stone
M3
masonry]
Gully using Check Dams [ cemented stone
M3
masonry]
Trench Excavation for Gully and others for
M3
Soft Soil
Trench Excavation for Gully and others for
M3
Hard Soil
for gully using Ckeck dam [dry stone
a M3 881.27
masonry] -
DIVISION 4600 Total sum -
DIVISION
DRIFT AND VENTED CAUSEWAYS
4700
47.01 fords Drift [Reinforced concrete]

a concrete c-20 M3 7,582.43 -


b Reinforcement bar Kg 161.95 -
47.02 fords Drift [Stone pitching] M3 -
a (0 ≤x ≤5) Km M2 529.96 -
b (5<X ≤10)Km M2 550.07 -
c (10<X ≤15)Km M2 570.25 -
d (15<x ≤20)Km M2 590.42 -
e (20<x ≤25)Km M2 610.60 -
f (25<x ≤35)Km M2 640.86 -

2015 First quarter Jimma zone construction Authorithy Feb, 2022


Rivised Unit Rate For Jimma Zone 2015 E.C Road s project

UNIT RATE ESTIMATIONS FOR RURAL ROAD PROJECT


DF 1
Region:-Oromia
Ford drift [cemented mortared masonry
47.03 M3
(1:4)] -
a distance of (0,5] Km M3 3,450.77 -
b distance of (5,10] Km M3 3,571.83 -
c distance of (10,15] Km M3 3,692.88 -
d distance of (15,20] Km M3 3,815.45 -
e distance of (20,25] Km M3 3,936.89 -
f distance of (25,35] Km M3 4,119.04 -
g distance of (35,45] Km M3 4,361.92 -
h distance of (45,55] Km M3 4,373.95 -
i distance of (55,65] Km M3 5,002.23 -
Causeway Ford
Causeway Ford [reinforced concrete (C-25)
47.04 including pipe laying / class B bedding

a Nominal diameter 750 mm Lm 1,468.02 -


b Nominal diameter 910 mm Lm 2,259.70 -
c Nominal diameter 1060 mm Lm 3,123.32 -
d Nominal diameter 1220mm Lm 3,125.18 -
DIVISION 4700 Total sum -
SERIES 4000 Total Sum -
CONSTRUCTION OF EMBANKMENT
SERIES 5000 GRAVELLING AND STABILIZATION

DIVISION
Placing Gravelling materials
5100
Gravel materials production,
loading,unloading, spreading and
51.01 M3
compacting wich is transported (using DT,
Loader, Tractor ,DL, etc from
a (0 ≤x ≤5) Km M3 263.77 -
b (5<X ≤10)Km M3 301.03 -
c (10<X ≤15)Km M3 327.28 -
d (15<x ≤20)Km M3 334.01 -
e (20<x ≤25)Km M3 401.79 -
f (25<x ≤ 35)Km M3 457.68 -
g (35<x ≤45)Km M3 532.20 -
h (45 <x ≤ 55)Km M3 606.71 -
i (55<x ≤ 65)Km M3 681.23 -
j (65<x ≤ 75)Km M3 755.74 -
DIVISION 5100 Total sum -
DIVISION
Mechanica stabilization
5200
Mechanical Modification Extra over
52.01
unstabilized layers ) -

a By adding a Soil binder


-

b By mixing materials from different sources M3


-
52.02 Chemical stabilizing agent -
a using local lime materials M3 92.66 -
DIVISION 5200 Total sum -
SERIES 5000 Total Sum -
SERIES 6000 HAND PACKED PAVING

DIVISION Dry Hand Packed Stone Paving and


6100 Mortared Hand Packed Stone paving

2015 First quarter Jimma zone construction Authorithy Feb, 2022


Rivised Unit Rate For Jimma Zone 2015 E.C Road s project

UNIT RATE ESTIMATIONS FOR RURAL ROAD PROJECT


DF 1
Region:-Oromia

Placing/finishing dry Hand packed stone


Paving [ size of 150mm,200mm or 225mm ]
61.01 M2
Transported using DT, Loader,Tractor .DL
etc. from

a (0 ≤x ≤5) Km M2 57.58 -
b (5<X ≤10)Km M2 69.29 -
c (10<X ≤15)Km M2 80.99 -
d (15<x ≤20)Km M2 92.70 -
e (20<x ≤25)Km M2 104.41 -
f (25<x ≤ 35)Km M2 116.12 -
Placing/finshing of Mortared (1:6)hand
Packed Stone Paving [Size of
61.02
150mm,200mm or 225mm] Transported
using DT, Loader,Tractor .DL etc. from
a (0 ≤x ≤5) Km M2 120.81
-

b (5<X ≤10)Km M2 132.52


-
c (10<X ≤15)Km M2 144.22
-

d (15<x ≤20)Km M2 155.94


-
e (20<x ≤25)Km M2 167.64 -

f (25<x ≤ 35)Km M2 179.35


-
DIVISION 6100 Total sum
-
DIVISION 6200 Stone Setts and cobble Stone paving
Stone sett paving (dressed stone and
62.01 cobble stone paving)

Cobble stone paving (15cm*15cm*15cm)


I using DT, Loader, Tractor, DL, etc, from

a (0 ≤x ≤5) Km M2 56.24
-

b (5<X ≤10)Km M2 61.70


-

c (10<X ≤15)Km M2 67.17


-

d (15<x ≤20)Km M2 72.64


-

e (20<x ≤25)Km M2 78.10


-

f (25<x ≤ 35)Km M2 83.56


-
Dressed stone paving (10cm*20cm*30cm)
II using DT, Loader, Tractor, DL, etc, from -

a (0 ≤x ≤5) Km M2 41.15
-

b (5<X ≤10)Km M2 44.80


-

c (10<X ≤15)Km M2 48.44


-

d (15<x ≤20)Km M2 52.07


-

e (20<x ≤25)Km M2 55.72


-

f (25<x ≤ 35)Km M2 59.36


-
DIVISION 6200 Total sum -

DIVISION 6300 Non-reinforced Concrete pavement

2015 First quarter Jimma zone construction Authorithy Feb, 2022


Rivised Unit Rate For Jimma Zone 2015 E.C Road s project

UNIT RATE ESTIMATIONS FOR RURAL ROAD PROJECT


DF 1
Region:-Oromia

63.01 Non-reinforced Concrete paving

Mass concrete production and cast in-situ


I Excluding Formwork

a Grade C-30 M3 9,327.65

b Grade C-25 M3 8,265.65


-

c Grade C-20 M3 7,582.43


-

II construction of formwork
-

a Formwork M2 318.34
-
DIVISION 6300 Total sum -
SERIES 6000 Total Sum -

SERIES 7000 STRUCTURES

DIVISION 7100 STRUCTURES

I Excavation for slab culvert(bridge) ≤ 10m

Excavation for foundation in soft


a material (ordinary soil or hard soil) M3 112.28
less than 1.50m -
Excavation for foundation in soft
b material (ordinary soil or hard soil) M3 108.71
grater than 1.50m to any depth -
Excavation for foundation in intermidiate
c material( soft &Decomposed rock) to any M3 121.75
-
depth
Excavation for foundation in hard rock
d M3 327.20 -
material to any depth
II Backfill for slab culvert(bridge) ≤ 10m M3
-
Backfilling using material from excavation
a M3 166.23
including compaction -
Backfilling using selected Granular material
b M3
including compaction

1 (0 ≤x ≤5) Km M3 493.54
-

2 (5<X ≤10)Km M3 514.05


-

3 (10<X ≤15)Km M3 556.95


-

4 (15<x ≤20)Km M3 588.56


-

5 (20<x ≤25)Km M3 625.82


-

6 (25<x ≤ 35)Km M3 681.71


-
III CONCRETE

Mass concrete production and


71.01
placing excluding form work

a Grade C-20 M3 7,582.43 -

b Grade C-25 M3 8,265.65 -

c Grade C-30 M3 9,327.65 -

Reinforcement bar ( supply, bending, cutting


71.02 Kg -
and fixing)
161.95
IV construction of formwork -
a formwork m2 318.34 -
DIVISION 7100 Total sum -
DIVISION 7200 construction of masonry

2015 First quarter Jimma zone construction Authorithy Feb, 2022


Rivised Unit Rate For Jimma Zone 2015 E.C Road s project

UNIT RATE ESTIMATIONS FOR RURAL ROAD PROJECT


DF 1
Region:-Oromia

72.01 Dry stone Massonry Walls

1 (0 ≤x ≤5) Km M3 1,229.49
-

2 (5<X ≤10)Km M3 1,302.96


-

3 (10<X ≤15)Km M3 1,390.67


-

4 (15<x ≤20)Km M3 1,614.71


-

5 (20<x ≤25)Km M3 1,735.77


-

6 (25<x ≤ 35)Km M3 1,971.70


-
Cemented –mortared (1:4) stone
72.02 masonry
walls -

a distance of (0,5] Km M3 3,450.77


-

b distance of (5,10] Km M3 3,571.83


-

c distance of (10,15] Km M3 3,692.88


-

d distance of (15,20] Km M3 3,815.45


-

e distance of (20,25] Km M3 3,936.89


-

f distance of (25,35] Km M3 4,119.04


-

g distance of (35,45] Km M3 4,361.92


-

h distance of (45,55] Km M3 4,373.95


-

i distance of (55,65] Km M3 5,002.23


-
Cemented –mortared (1:6) stone
72.03 masonry
-
walls
a distance of (0,5] Km M3 3,179.75
-

b distance of (5,10] Km M3 3,300.43


-

c distance of (10,15] Km M3 3,421.48


-

d distance of (15,20] Km M3 3,542.54


-

e distance of (20,25] Km M3 3,663.60


-

f distance of (25,35] Km M3 3,845.19


-

g distance of (35,45] Km M3 4,087.31


-

h distance of (45,55] Km M3 4,329.42


-

i distance of (55,65] Km M3 4,571.54


-
DIVISION 7200 Total sum -
DIVISION 7300 Bridge
Excavation for foundation in soft
73.01 material (ordinary soil or hard soil) m3 112.28
less than 1.50m -
Excavation for foundation in soft
73.02 material (ordinary soil or hard soil) m3 108.71
grater than 1.50m to any depth -
Excavation for foundation in intermidiate
73.03 m3 121.75
material( soft &Decomposed rock) to any depth
-
Excavation for foundation in hard rock
73.04 m3 327.20
material to any depth
-

2015 First quarter Jimma zone construction Authorithy Feb, 2022


Rivised Unit Rate For Jimma Zone 2015 E.C Road s project

UNIT RATE ESTIMATIONS FOR RURAL ROAD PROJECT


DF 1
Region:-Oromia
Backfilling using material from excavation
73.05 m3 166.23
including compaction
-
Backfilling using selected Granular material
73.06 M3 493.54
including compaction
-

73.07 Backfill with ston pitching / laying M3 347.05


-
mass concret production and cast in-situ
73.08
excluding formwork -
a C-20 m3 7,582.43 -
b C-25 m3 8,265.65 -
c C-30 m3 9,327.65 -
73.09 RC Bridge Railing and Posts Lm 2,801.75
-
73.1 Steel Pipe Bridge Railing and Posts Lm 414.00
-
Reinforcement bar of different diameter ( supply
73.11 Kg 161.95
, bending, cutting and fixing -
73.12 cemented mortar Stone Masonry(1:4)
-

a distance of (0,5] Km M3 3,450.77


-

b distance of (5,10] Km M3 3,571.83


-

c distance of (10,15] Km M3 3,692.88


-

d distance of (15,20] Km M3 3,815.45


-

e distance of (20,25] Km M3 3,936.89


-

f distance of (25,35] Km M3 4,119.04


-

g distance of (35,45] Km M3 4,361.92


-

h distance of (45,55] Km M3 4,373.95


-

i distance of (55,65] Km M3 5,002.23


-
BRIDGE BEARINGS ETC…..
73.13
(Elastomeric bearings) -
73.13(a) Type -1 NO 23,500.00
-
73.13(b) Type -2 NO 23,500.00
-
73.14 Drainage pipes and weep holes
-
73.14 Drainage pipes(20 cn internal Dia Pvc) m 106.58 -

73.15 Packed Riprap m3 521.24 -

73.16 Formwork i m2 636.68


-
DIVISION 7300 Total sum -
SERIES 7000 Total Sum -
SERIES 8000 ROAD FURNITURE
DIVISION 8100 `
81.01 Traffic Signs NO 2,428.79 -
81.02 Guide and KM Posts NO 1,731.74 -
81.02 Guard rails LM - -
DIVISION 8100 Total sum -
SERIES 8000 Total Sum -
TOTAL OF ALL SERIES -

2015 First quarter Jimma zone construction Authorithy Feb, 2022