Professional Documents
Culture Documents
Energy Department of
Serbian Energy Efficiency Agency
WIND FARM
FEASIBILITY STUDY
Index
Duration
Activity Speaker
(min)
Introduction Mrs. Paloma Berberana 10
Site Selection Mrs. Paloma Berberana 5
Measurement programme Mrs. Inés Arañó 15
Wind Farm Design Mrs. Inés Arañó 10
Network Connection and
Mrs. Inés Arañó
electrical system analysis 5
Technical issues Mr . Vladimir Edelinski 15
Environmental Analysis Mrs. Inés Arañó 5
Geotechnical Study Mrs. Inés Arañó 5
Legal Analysis Mr. Slobodan Ruzic 10
Economic & Financial
Analysis Mr. Jaime Prado 10
2
Ingeniería, Estudios y
Proyectos NIP,SA
3
Company presentation
Business Units The provided services are structured in 4 business units
¾ Bosnia i Herzegovina
•Feasibility study of wind potential for power generation in BiH
¾ Bosnia i Herzegovina
•Rehabilitation of hydro power plant in Mostar (3 x24 MW)
•Analysis of use of small-hydro power plants for electricity production in Srpska Republic.
NIPSA was the consultant selected for the preparation of tender documents
¾ Honduras
•Feasibility study of Mezapa and Jilamito hydro power plants
•Design, installation and commissioning of Nacaome hydro power plant (12,5 and 5MW)
6
Project Overview
7
Project background Project Overview
8
Objectives of the study Project Overview
9
Activities Project Overview
¾Site selection
Installation
Inspection
¾Measurement programme
Analysis after six months
Analysis after one year
¾Wind farm design
¾Technical issues
¾Environmental analysis
¾Geotechnical study
¾Legal analysis
11
Locations Site Selection
1. Vrsac
2. Veliko Gradiste
3. Titel
4. Sabac
5. Negotin
6. Vlasina
12
Aims Site Selection
13
Criteria Site Selection
Existence of access
Acquisition of permits
15
Trip Site Selection
16
Trip Site Selection
17
Trip Site Selection
18
Measurement Programme
19
Installation and inspection Measurement Programme
¾Inspection report
20
Installation and inspection Measurement Programme
NEGOTIN
VELIKO
GRADISTE
TITEL
21
Six months wind data analysis Measurement Programme
¾ Objectives:
¾ Conclusions:
¾ Objectives:
To analyze wind resource in the areas and carry out the feasibility
study for the implementation of a wind farm in one of the sites
24
One year wind data analysis Measurement Programme
0
AUG SEP OCT NOV DEC JAN FEB MAR APR MAY JUN JUL AUG
2007 2008
25
One year wind data analysis Measurement Programme
Titel
Veliko Gradiste
Negotin
26
Spatial extrapolation Measurement Programme
¾Power
¾Wind density
speed extrapolation
extrapolation
NEGOTIN
•WAsP model at 80 m.a.g.l.
•Wind rose at met mast
27
Wind Farm Design
28
Overview Wind Farm Design
¾ Followed steps:
29
Wind turbine selection Wind Farm Design
¾ Objective: to select a suitable wind turbine for the proposed wind farm
30
Wind turbine selection Wind Farm Design
¾ Wind turbines:
31
Wind farm rating Wind Farm Design
¾ Network capacity:
Present and future state of the transmission network
Maximum power amount to evacuate at each interconnection point
¾ Land availability:
Accuracy of the space extrapolation
Possibility of construction the wind farm
¾ Project economics:
Economy of scale in wind farms
32
Wind turbines distribution Wind Farm Design
¾ The wind farm layout has been designed taking into account the
following factors:
33
Possible energy losses Wind Farm Design
Availability 97 %
Electrical losses 98 %
Icing and blade degradation 99.5 %
Substation maintenance 99 %
High wind speed hysteresis 99.5 %
TOTAL 93.2 %
34
Popadija wind farm Wind Farm Design
¾ Total power 45 MW
35
Popadija wind farm Wind Farm Design
Turbine site X-location [m] Y-location [m] Elev. [m] Ht [m] U [m/s]
¾ Wake losses
39
Network Connection &
Electrical System Analysis
40
Activities Network connection analysis
¾ Data acquisition
¾ Modelling
¾ Load flows
¾ Short circuit
41
Conclusions Network analysis
42
Conclusions Network connection analysis
¾Power system losses increase in winter peak regime, i.e. power system
losses decrease in summer light regime, but are negligible after the wind
farm connection to transmission network
¾Security criterion N–1 is fulfilled after the wind farm connection, and level of
short circuits at neighbouring substations is increased for less than 10 %
comparing to the case when the wind farm is not connected
44
Environmental Analysis
45
Potential effects and impacts Environmental analysis
¾Effects on fauna
¾Effects on vegetation
¾Effects on soil
¾Effects on water
¾Effects on landscape
46
Conclusions Environmental analysis
¾The study area does not belong to any of protected areas as national
parks, landscape parks, nature reserves…
47
Next steps Environmental analysis
¾ Pre-construction studies
¾ Avoidance measures
¾ Mitigation measures
¾ Compensatory measures
¾ Decommissioning plan
48
Geotechnical Study
49
Conclusions Geotechnical study
¾Material from excavation is not suitable for building the culmination on the
top of the fill and it is necessary to obtain it in quarry. Any of them are suitable
to build the core of the fill
50
Pictures Geotechnical study
51
Legal Analysis
52
EU Regulation on Renewable
Legal Analysis
Generated Electricity
¾ Investment support
¾The Treaty came into force on July 1, 2006, and includes a 10-years period
56
Proposals Legal analysis
¾Legal framework
1. Develop an institutional and legal framework comprehensive, stable,
transparent and reliable on renewable energy – in progress.
2. The regulation must include a precise definition of the RES and define goals.
3. Feed in tariffs should be adopted as the most appropriate supporting scheme
for Serbia
4. Simplify existing procedures for issuing energy permits, construction permits
and licensing for generation:
• Avoid concession procedure for small hydro energy facilities and simplify
requests for energy permit issuing.
• Define precise instructions to Public Utilities responsible for water
management regarding ownership issues.
• Define precise instructions regarding spatial & city planning to
responsible municipality entities.
• Producers should apply for generation licenses in the Energy Agency,
without any accreditation from the Government or other bodies. 57
Proposals Legal analysis
58
Proposals Legal analysis
¾ Environmental protection
Integrate renewable energy issues into non-energy sector policies and cross
sector issues: environmental, R&D, planning, etc
59
Economic & Financial Analysis
Income estimation Economic & Financial Analysis
-Equivalent Hours-
Base Scenario
Selling Price
2,505 h/year
45 MW 10,147 k€/year
61
O&M Expenses Economic & Financial Analysis
M&A Staff
1500
Electric Installation
k€
Insurances
1000 Land lease
1522
Energy consumption
1184
500 Roads, buildings & gardens
1% 4% 4% 1% 2% Cost of turbines
2% Civil Works
5% Electric Installation
Engineering
Substation
Transmission Line
81% Development Costs
61875 k€ Others
1375 €/kW
63
Financial Structure Economic & Financial Analysis
54432
50% of Debt service
40000
61875 17,7%
30000
20000
10000
11698
0
* Financial construction costs and Loan fee
64
Equity %
Internal return rate (IRR) Economic & Financial Analysis
k€
Equity
140000
Acc. Free Cash Flow
120000
100000 IRR (25): 18.2%
80000
60000
11,698
40000
20000
0
0 2 4 6 78 10 12 14 16 18 20 22 24 Years
Pay back
65
Sensitivity analysis Economic & Financial Analysis
1800
1600
1400
1200
1000
€/kW
800
600
400
200
0
86
88
90
92
94
96
98
00
02
04
06
08
10
19
19
19
19
19
19
19
20
20
20
20
20
20
Year
-Scenarios-
67
Sensitivity analysis Economic & Financial Analysis
-Sensitivity Analysis-
30%
28.00%
1325 €/kW
25.70%
25% 1375 €/kW
24.20%
23.60% 1425 €/kW
22.20%
1475 €/kW
21.80% 20.30% 20.60%
20%
IRR
18.20%
18.00%
16.20% 16.20%
15% 14.60%
14.70% 13.20%
10%
5%
10 9.5 9 8.5
Selling price Cent. €/kWh 68
Conclusion Economic & Financial Analysis
69
THANK YOU!
70