You are on page 1of 11

DOI 10.

1007/s10749-020-01116-y
Power Technology and Engineering Vol. 53, No. 5, January, 2020

DEVELOPMENT OF THE HYDROPOWER POTENTIAL


OF THE GRANDE DE SANTIAGO RIVER (MEXICO)

A. V. Kozyrev,1 A. V. Lashin,2 I. O. Uskov,2 and V. I. Uskov3

Translated from Gidrotekhnicheskoe Stroitel’stvo, No. 8, August 2019, pp. 30 – 41.

Organization of the construction of three hydroelectric power plants on the Grande de Santiago River is de-
scribed, namely the Aguamilpa, El Cajòn, and La Yesca, for supplying power to the states of Nayarit and
Jalisco.
Keywords: Aguamilpa; El Cajòn; La Yesca; San Rafael; Grande de Santiago River; organization of construc-
tion; HPP cascade; assembly; equipment; hydropower potential development; Comissiòn Federal de
Electricidad.

Three gorges are used in the mountainous Grande de surge tank, and extended tailrace tunnel (Fig. 2). These lay-
Santiago River valley for the construction of three large outs are a universal solution that the client traditionally used
HPPs in Mexico — Aquamilpa, El Cajòn, and La Yesca — both on the given hydropower complexes and in many other
intended mainly for supplying power to the large industrial projects with a mountainous relief of the locality. The design
metropolis Guadalajara and the states of Nayarit and Jalisco,
heads are also similar at all three plants of the cascade:
in the territories of which are located hydropower com-
plexes. 145.1, 156.5, and 163.3, respectively, as well as the power of
Aguamilipa hydropower complex. Construction of the
lower step of the cascade, the Aguamilipa HPP, began in
1990 and was completed in 1994. Nine years later, in January
2003, development of the hydropower resources of the river 5
continued with the construction of the following plants — El
Cajòn and construction of the La Vesca HPP began down- 4
3
stream in 2007. The bid documents on all three objects were
worked out by the project client, the Comissiòn Federal de
Elecricidad (CFE) exclusively engaged in the generation and
distribution of electricity and having long-term traditions in
hydropower construction based on the use of reliable and
time-verified technical solutions. 2
A distinctive characteristic of the HPP projects on the
Grande de Santiago River is that the three hydropower com- 11
1
plexes have the same composition of structures and similar 10
6
layout and structural solutions regarding the hydraulic engi-
9
neering part and hydropower equipment. All hydropower
complexes have tall (about 200 m) rockfill dams with rein- 8
forced concrete impervious membranes and bank flume
spillways with overflow dams equipped with radial gates
(Fig. 1). Also similar are the layouts of the hydropower 7
structures with an inclined bank water intake, individual
Fig. 1. Plan of the Aguamilpa hydropower complex: 1, dam; 2, up-
headrace tunnels, underground powerhouse, underground
stream cofferdam; 3, downstream cofferdam; 4, diversion tunnels;
1 JSC Lengidroproekt, St. Petersburg, Russia; e-mail: KozyrevAB@1hp.ru 5, spillway; 6, HPP intake; 7, headrace tunnels; 8, underground pow-
2 PJSC Power Machines, St. Petersburg, Russia. erhouse; 9, underground surge tank; 10, tailrace tunnel; 11, emer-
3 JSC VNIIG im. B. E. Vedeneeva, St. Petersburg, Russia. gency canal.

557
1570-145X/20/5305-0557 © 2020 Springer Science+Business Media, LLC
558 A. V. Kozyrev et al.

7
6
4
3
2 5

Fig. 2. El Cajòn HPP. Longitudinal profile along hydropower struc-


tures: 1, HPP intake; 2, headrace tunnel; 3, underground power-
house; 4, underground surge tank; 5, tailrace tunnel; 6, shaft of the
conductors; 7, transformer area.

the turbogenerator units. Three 320-MW turbogenerator


units are installed at the Aguamilpa HPP and two 375-MW
units at the El Cajòn and La Vesca HPPs. The synchronous
rotational speed 150 rpm, rated generator voltage 17 kW
(13.8 kW at the Aguamilpa HPP), and electric current fre-
quency 60 Hz are the same at all HPPs. This made it possible
to use similar designs of the radial-axial hydraulic turbines Fig. 3. Aguamilpa HPP. Assembly of turbogenerator units.
with support of the bearing on the turbine cover with a 5.3-m
runner diameter (5.2 m at the Aguamilpa HPP) and umbrella
hydraulic generators with indirect air cooling. There are also crease. The water soon drowned the cofferdam completely.
distinctive features. In particular, the turbines of the El Cajòn Fortunately, by this time the dam was dumped to higher ele-
and La Vesca HPPs are equipped with built-in ring gates to vations, which permitted avoiding overflowing it with the
prevent slot cavitation between the wicket gate blades during development of a serious technogenic accident. In its turn,
stopping of the turbogenerator units, which is not provided the presence of the emergency canal made it possible to keep
for on the turbines of the Aguamilpa HPP. the upstream cofferdam from destruction, which was ex-
Bidding on the Aguamilpa HPP was organized with sep- tremely important since construction works at the foot of the
aration into two parts: construction and electromechanical. dam were still not completed.
The construction contractor was the company Ingenieros The electromechanical part of the project was realized by
Civiles Asociados (ICA), a Mexican firm engaged in realiz- the SEVST consortium consisting of the companies Siemens
ing large infrastructure projects on a nationwide scale: con- AG (Germany); Énergomashéksport (USSR), which subse-
struction of highways, bridges, airports, subway, and quently was a part of the Russian company OJSC Power Ma-
hydropower plants. The basic project, put up for competition, chines; Voest Alpine MCE (Austria); Grupo Siemens SA de
contained such technical solutions which during construction CV (Mexico); and Techint SA de CV (Mexico). The respon-
made it possible to achieve a high rate of conducting the sibility of each participant was determined by consortial
works and to maximally approach the time of putting the agreement:
turbogenerator units into operation in order to receive an in- — Siemens: excitation system, automatic relay equip-
come from the sale of the electricity being generated by the ment, monitoring system, 400-kW power cables, conductors,
HPP. These tasks were fulfilled by the contractor by using bridge cranes;
modern construction technology, machines, mechanisms, — Énergomashéksport: hydraulic turbines (Turoatom
and materials. Research and Production Association), hydraulic generators
The planned pace of construction was disrupted by a de- (JSC Élektrosila), power transfomers (JSC Zaporozhtrans-
structive flood which occurred on January 16 – 20, 1992 as a formator);
consequence of a powerful rain front. The inflowing dis- — Voest Alpine MCE: gates and hoisting mechanisms
charge at this time increased to 10,800 m3/sec, which con- for the HPP intake, draft tube and spillway decks, turbine
siderably exceeded the design capacity of the diversion tun- speed regulators;
nels. After the river water level rapidly approached the eleva- — Techint: storage and assembly of equipment.
tion of the upstream cofferdam crest, it was decided to open Assembly works on the first turbine began at the end of
the emergency canal made in a rocky cut into a cofferdam 1992 with the installation of linings and embedded parts
bypass. The water flowed along the emergency canal and (Fig. 3). Hydraulic tests of the scroll case were conducted on
within a hour filled the pocket between the cofferdam and in- January 30, 1993, and the runner was lowered into the tur-
completely constructed earth dam. The water level before bine pit on August 12, 1993. Simultaneously, works were
and after the cofferdam evened out and continued to in- carried out on assembling the generator rotor on a stand in
Development of the Hydropower Potential of the Grande De Santiago River (Mexico) 559

2
4 3
1

5
8

6 7

Fig. 5. C. H. San Rafael. Plan of hydropower complex: 1, dam;


2, upstream cofferdam; 3, downstream cofferdam; 4, diversion ca-
nal; 5, spillway; 6, HPP intake; 7, powerhouse; 8, tailrace canal.

Fig. 4. San Rafael hydropower complex (1994 – 2013). stream of the Aguamilpa HPP, was constructed. The struc-
tures of the San Rafael hydropower complex included a
gravity-type concrete non-overflow dam constructed accord-
the assembly area. works on assembling the generator stator ing to the rolled concrete technology and a spillway with six
were carried out at the same time in a shaft. Upon completing radial gates. A constant discharge of water of about
these works, the generator rotor was lowered on October 29, 190 m3/sec was released into the lower pool of the San Rafa-
1993, the line of shafting was checked on December 24, el complex.
1993, and then final assembly of the unit took place. After An area for constructing the HPP was provided for in the
this, startup and adjusting tests were conducted: idling opera- abutment to the right bank of the San Rafael complex, but the
tion of the unit, high-voltage tests of the stator winding, etc. plant itself was not constructed at first. The San Rafael com-
plex was put into operation in such a form in July 1994
Synchronization of the first unit with the network was per-
(Fig. 4) and operated 19 years. Only in 2013 did construc-
formed on March 18, 1994. The second unit was assembled
tion of the HPP begin by the Acciona company under condi-
analogously and started on May 28, 1994 and the third was
tions of an EPC contract. The HPP is equipped with three
put into operation on June 9, 1994. Andritz 8-MW vertical Kaplan turbines. Construction of the
It was planned to operate the Aguamilpa HPP 6 h/day in HPP took 3 years and was completed on February 3, 2016
a peak regime with a discharge of 750 m3/sec, which would (Figs. 5 – 7).
lead to pronounced daily fluctuations of the lower pool water El Cajòn hydropower complex. The 1994 completion
level. To stabilize the level regime of the river, a counter- of the construction of the hydropower complex consisting of
regulator, the San Rafael hydropower complex, 17 km down- the Aguamipla HPP and San Rafael counter-regulator cre-

Fig. 6. San Rafael HPP. View from lower pool.


560 A. V. Kozyrev et al.

main hydropower equipment at the El Cajòn HPP were simi-


lar to the parameters of the equipment for the Aguamilpa
HPP, this permitted enlisting the same suppliers: OJSC Tur-
boatom (Kharkov, Ukraine) for the turbines and PM/Élek-
trosila branch (St. Petersburg, Russia) for the generators.
Such a decision was justified from an economic and techni-
cal viewpoint as it made it possible to optimize the projects
with consideration of the experience in assembling and oper-
ating equipment at the preceding HPP of the cascade.
Various manufacturers and companies were enlisted for
supplying auxiliary electromechanical equipment and tech-
nological systems:
— gates, hoisting cranes, and hydraulic drives with in-
stallation and commissioning management — Ukraine
plants: Novaya Kakhovka Ukrgidromekh Plant, Zuevskii
Fig. 7. San Rafael HPP. Machine hall. Electromechanical Plant, Novokramatorsk Machine-Build-
ing Plant;
— speed regulators and ring gate control systems —
ated favorable conditions for developing a local irrigation Voith Siemens (Austria);
system as well as served as a powerful momentum for further — generator excitation system — PM/Élektrosila
development of the hydropower resources of the Grande de branch (Russia); SF 6 gas-insulated switchgear (GIS) — VA
Santiago River, particularly the construction of the next step Tech (Great Britain).
of the cascade, the El Cajòn HPP. Supplied from Brazil:
Unlike the bids on the Aguamipla HPP, competition for — the main step-up transformers — ABB;
the El Cajòn HPP was conducted as a single lot, without sep- — automated technological process control system —
aration into construction and electromechanical parts. The Siemens;
client wanted to deal with a single responsible juridical per- — generator voltage conductors — Alstom;
son in the form of a consortium uniting representatives of — conductors for plant’s own needs system — Power
financial groups, construction companies, and equipment Bus;
suppliers. The competition was held in February 2003. In it — small turbogenerator unit for the plant’s own needs
participated three consortiums, having presented their — WEG/Altona.
own technical and commercial proposal (TCP): ICA — According to the contract with PM, the Brazilian firm
ADISA — La Peninsular — OJSC Power Machines (PM), Energ Power was the general designer of the electromechani-
US$748 million; General Electric — Camargo Correa — cal part of the project and chief collector of complete sets of
Andrade Gutierrez, US$812 million; and Aristos — Con- auxiliary equipment and technological systems of the HPP.
structora Cota — Tradeco — Nacional — Torres Mexicanas. This circumstance is explained by the presence of a large
The last consortium was disqualified because of infringe- quantity of equipment of Brazilian manufacturers known
ments made in the technical part of the TCP. The consor- to Energy Power from joint projects in Brazil. The mechani-
tiums confirmed participation in the competition by bank cal and crane equipment were designed by the special design
guarantees in the form of pledged sums, which were returned and technological bureau Zaporozhstal’ (Zaporozh’e,
after the end of bids. In the spring of 2003, victory was Ukraine).
awarded to the consortium, which subsequently was called The El Cajòn HPP was a complex turnkey project for
Constructora Internacional de Infrastructura (CIISA), where PM. The main complexity consisted in monitoring and tech-
the construction firm ICA was the director and the company nical coordination of tens of contracts with various suppliers
PM was the equipment supplier. This consortium had the of equipment and services as well as in interaction with de-
lowest cost of generation of electricity in the TCP competi- signers of the construction part. This was achieved by the
tion — 0.74 peso/(kW · h). The main competitors of PM in joint efforts of specialists at PM’s head office in St. Peters-
the competitions were world giants of power machine build- burg, design departments of plants, specialists of PM repre-
ing General Electric and Siemens, which offered their ser- sentatives in Mexico City, and PM groups at the HPP.
vices to the other consortiums. A detailed schedule for conducting the construction and
The contract obligations of PM included the design, assembly work was worked out by the CIISA consortium on
manufacture, and delivery of hydropower, electrical, me- the basis of the following critical events regulated by the bid:
chanical, and hoisting-transporting equipment, assembly, — transfer of water discharges in the river to the diver-
startup and adjustment works, conduction of all types of sion tunnels — November 30, 2003;
tests, putting the HPP into commercial operation, and guar- — completion of the construction of the upstream
antee servicing for two years. Since the parameters of the cofferdam — July 1, 2004;
Development of the Hydropower Potential of the Grande De Santiago River (Mexico) 561

3
6 10
8

7
9
5

Fig. 8. El Cajòn HPP. Plan of hydropower complex: 1, dam; 2, up-


stream cofferdam; 3, downstream cofferdam; 4, diversion tunnels; Fig. 9. El Cajòn HPP. Dam and inlet portals of tailrace tunnels.
5, spillway; 6, HPP intake; 7, headrace tunnels; 8, underground HPP
powerhouse; 9, underground surge tank; 10, tailrace tunnel.

— completion of assembly and tests of gates on the HPP


intake and spillway dam before the forthcoming shutdown of
the diversion tunnels — June 30, 2006;
— shutdown of the diversion tunnels and start of filling
the reservoir — July 1, 2006.
On the critical path of construction were works on con-
structing two 900-m long 14 × 14-m diversion tunnels, erec-
tion of temporary cofferdams, and dumping the dam with
about 11 million m3 of fill (Fig. 8).
Works on constructing the underground machine hall and
surge tank as well as on driving numerous tunnels and verti-
cal shafts of various purposes were carried out on the right
bank of the river irrespective of the dam fill in the channel
part. Travel from the left to the right bank was provided for
along the crests of the cofferdams. A temporary steelwork Fig. 10. El Cajòn HPP. HPP dam and intake.
bridge was assembled for getting to the right bank and start
working on the underground structures without waiting for
dumping the cofferdams to be completed. 400 tons. By that time, construction works on the under-
For conducting the assembly works, the specialized com- ground excavation for the powerhouse and its roof and walls
pany Duero Ingenieria (Mexico) was contracted, which had were completed. The crane, turbine, and generator equip-
at its disposal the necessary hoisting mechanisms, work- ment were manufactured and delivered to the storages of the
shops, vehicle fleet and facilities, outdoor and covered construction site. Assembly works on the first turbine began
storages, assembly devices, and other equipment for effec- on February 8, 2005 with the installation of the draft tube el-
tive conduction of assembly works. Together with the trade bow liner. By that time the assembly cranes were still not
union, Duero Ingenieria selected skilled workers and engi- erected; therefore, the temporary 10-ton capacity construc-
neering staff, having provided them with safe working con- tion bridge crane and wheel-mounted crane were used. The
ditions as well as comfortable living and rest conditions. turbine stator (Fig. 11) was assembled by a standard bridge
Assembly of the equipment was under the control of a group crane on June 8, 2006. Hydraulic tests of the scroll case were
of field inspection and chief assembly specialists of the sup- carried out after assembly was completed. During concret-
plier plant. On the initiative of CM, the Mexican team of as- ing, the scroll case was filled with water and was under the
semblers was reinforced by Russian specialists of the com- rated pressure in accordance with the requirement of the bid
pany JSC Spetsgidroénergomontazh (SGÉM). documents. The runner (Fig. 12) was lowered into the tur-
At the start of 2005, the construction contractor trans- bine pit on April 19, 2006, and the turbine cover along with
ferred to PM a field of operations for assembling two ma- the hydraulic cylinders of the ring gate was installed on June
chine hall bridge cranes each with a lifting capacity of 12, 2006 (Fig. 13).
562 A. V. Kozyrev et al.

Fig. 11. El Cajòn HPP. Assembly of turbine stator. Fig. 13. El Cajòn HPP. Installation of the turbine cover with ring
gate.

Fig. 12. El Cajòn HPP. Turbogenerator pit.


Fig. 14. El Cajòn HPP. Assembly of generator rotor.

At the same time, works were carried out in the shaft of


the turbogenerator unit on assembling the generator stator. and on assembling a bridge crane for servicing the gates.
The generator rotor was lowered into the pit on September 1, These works began on April 23, 2005 and were completed on
2006 (Fig. 14). On October 20, 2006 the line of shafting was November 9, 2006.
checked, and then final assembly of the unit was accom-
At the same time, works were performed also on other
plished. After this, startup and adjustment tests were carried
structures of the hydropower complex. On the ground sur-
out: idling operation of the unit and high-voltage tests of the
face above the powerhouse was constructed an electrical
stator winding. The unit was synchronized with the network
substation on which were carried out the installation of six
on February 15, 2007.
17/400-kV single-phase step-up transformers, assembly of
Simultaneously, the auxiliary technological systems of
the powerhouse were assembled and adjusted: water cooling, the 400-kV gas-insulated switchgear, as well as other electri-
fire extinguishing (gas and water), drainage of the power- cal equipment: circuit breakers, switches, overvoltage limit-
house and dewatering system of the turbine blading, ventila- ers, etc. These works began in May 2006 and were com-
tion and air conditioning, industrial water supply, com- pleted in February 2007. The 17-kV generator voltage con-
pressed air, communication, lighting, grounding, direct and ductors transmitting electricity from the generators to the
alternating current, etc. The turbine draft tubes were re- transformers were located in two vertical 6-m diameter,
moved into the underground surge tank. Works were carried 120-m deep shafts and were assembled along with other sub-
out there on installing stop logs for closing off the draft tubes station equipment.
Development of the Hydropower Potential of the Grande De Santiago River (Mexico) 563

Fig. 16. El Cajòn HPP. Machine hall of underground powerhouse.


Fig. 15. El Cajòn HPP. Construction of spillway.

The installation of two stop gate-emergency gates with brated in the deep-water experimental basin of the Krylov
rods, individual hydraulic drives and installation and com- Central Research Institute (TsNII, St. Petersburg, Russia).
missioning management, stop log, and gantry crane for ser- Works on the HPP were carried out in the presence of repre-
vicing it were provided for on the HPP intake. Assembly sentatives of the client, RM, and turbine manufacturer. The
works began on April 27, 2006 and continued until Decem- generator was tested by specialists of the Élektrosila plant.
ber 2006. During the tests the efficiency values claimed and guaranteed
in the TCP were confirmed.
Six radial gates with individual hydraulic drives and in-
stallation and commissioning management, stop logs, and a It should be noted that upon completion of construction,
gantry crane for servicing them were installed in the bays of objects of the industrial facilities, storages and temporary
the spillway dam (Fig. 15). Assembly works began on Octo- communications of various types, residential settlement, ad-
ber 14, 2005 and were completed on November 9, 2006 with ministrative and household buildings, and temporary access
test lifts of the gates and check releases of water into the roads and bridges were dismantled. In accordance with the
lower pool of the complex. requirements of the bid, complete rehabilitation and planting
The first unit was put into commercial operation on Feb- trees and shrubs of the territory of the construction site of the
ruary 27, 2007. Thus, works on assembling the first turbo- hydropower complex were carried out and those roads,
generator unit took about 25 months. Simultaneously, assem- bridges, and other infrastructure objects which were intended
bly works were carried out on the second unit, which contin- for permanent operation were reconstructed and updated.
ued for 27 months and were completed with commissioning La Vesca hydropower complex. In 2006 a competition
on May 30, 2007 (Fig. 16). The fact of commissioning the was announced for collaboration of ICA with PM on the con-
units was confirmed by the act of temporary acceptance after struction of the El Cajòn HPP, it was decided to form a new
200-h operation under load. From that moment responsibility consortium Constructora de Proyectos Hidroeléctricos
for operating the plant passed from the consortium to the cli- (CPH) for participating in the competition for the La Vesca
ent with technical support of specialists of the consortium. HPP. The following consortiums participated in the bids:
Special courses were organized to train the client’s operating CPH (ICA — La Peninsular — PM), US$908 million;
personnel by specialists of PM and suppliers. Gusta — Synohidro, US$1249 million; Techint — Impre-
In the fall of 2007 full-scale tests were conducted to con- gilo — V A Tech. The last consortium was disqualified be-
firm the correspondence of the actual efficiency of the unit to cause of infringements made in the technical part of the TCP.
the value which was claimed in the TCP. The firm Kharkov- According to the results of examining the TCPs, the competi-
TurboInzhiniring (Kharkov, Ukraine) with the participation tion’s organizer decided to annul the bids because the bid
of JSC TsKIG research and production association (St. Pe- participants exceeded the budget cost of the project —
tersburg, Russia) was enlisted to test the turbine. Used for US$836 million.
these works were 57 hydrometer flowmeters installed on a The following consortiums participated in repeated bids
support frame inside the headrace tunnel near the entry into in 2007: CPH (ICA — La Peninsula — PM). US$ 768 mil-
the scroll casing. The readings from each flowmeter were lion; Techint — Impregilo — VA Tech, US$ 856 million;
used to determine the velocity of the flow and then the dis- Carso — Voith Siemens, US$811 million. Making a decision
charge of water through the turbine and efficiency were cal- about awarding the contract, the client took into account that
culated. Before and after the tests, the flowmeters were cali- the presence of construction equipment and skilled labor
564 A. V. Kozyrev et al.

5
3
4

10
9
8

2 6
7
Fig. 18. La Vesca HPP. Hauling the turbine runner.
Fig. 17. La Vesca HPP. Plan of hydropower complex: 1, dam; 2, up-
stream cofferdam; 3, downstream cofferdam; 4, diversion tunnels;
5, spillway; 6, HPP intake; 7, headrace tunnels; 8, power house;
9, underground surge tank; 10, tailrace tunnel. — main step-up transformers, automatic control system,
GIS, and other electrical equipment — Siemens.
The firm Hydroproject de Mexico (Mexico) was selected
force, having been freed up at the El Cajòn HPP, would be a as the general designer of the electromechanical part of the
strong impulse for starting the construction of the La Vesca CM project. Specialists of this company coordinated the
HPP located near the preceding site. Participation of PM in work of numerous subcontractor organizations, monitored
the consortium made it possible to use analogous hydro- fulfillment of the work schedule, coordinated the designs of
power equipment of the same supplier that equipped the the equipment with the designs of the construction part, etc.
downstream plants of the cascade with turbines and genera- All assembly works were accomplished by the Duero Inge-
tors. As a result, the client awarded the winner in the compe- nieria company assisted by SGÉM specialists and under the
tition to the CPH consortium, which showed in its TPC the supervision of head engineers of the suppliers.
lowest cost of electricity generation — 0.80 pesos/(kW · h). Having positive working experience on the construction
A subcontract form of participation of PM in the CPH con- of the El Cajòn HPP, the participants of the CPH consortium
sortium was accepted during internal negotiations and mu- looked at the new contract with great enthusiasm, consider-
tual agreement. Construction of the La Vesca HPP began in ing it a copy of the preceding one. Actually, there was much
October 2007. in common in the layout and designs of the structures of the
The contract obligations of PM, as also for the El Cajòn two hydropower complexes. The La Vesca HPP had an anal-
HPP, included design, manufacture, delivery of the entire ogous rockfill dam 200 m tall with an impervious reinforced
volume of technological equipment, assembly and startup concrete membrane, bank flume spillway, maximum capac-
and adjustment, conduction of guarantee tests, putting the ity 15,100 m3/sec, and two 14 × 14-m diversion tunnels
HPP units into commercial operation on January 2 and April (Fig. 17) The water from the intake to the unit of the under-
2, 2012 with guarantee two-year servicing. The suppliers ground powerhouse was delivered by two tunnels with an in-
of the main hydropower equipment were JSC Turboatom side diameter of 7.7 m and a maximum discharge of
(Ukraine) and PM/Élektrosila (Russia), as also on the down- 250 m3/sec through each tunnel. A substation with step-up
stream plants of the cascade; the suppliers of the auxiliary transformers and GIS was located in an outdoor area.
equipment were changed. It is necessary to note that supply- However, the natural conditions of the La Vesca HPP site
ing the El Cajòn HPP with complete sets of Brazilian-made were considerably more complex. The steep walls of the can-
auxiliary equipment caused difficulties for the client related yon created problems for organizing industrial facility and
to the complexity of its servicing. For this reason, require- residential settlement sites, as well as substantially hindered
ments on purchasing equipment on the local market were the construction of temporary roads. On some stretches the
brought up in the bid. To meet this requirement, companies longitudinal incline of the roads exceeded 20%, and the
having representation in Mexico were enlisted to supply aux- ground cover was constantly destroyed and deformed by the
iliary equipment to the La Vesca HPP, namely: heavy-load trucks. The transport company Transportes Telle-
— speed regulators, ring gate control system, small ria, having the necessary experience, specialized equipment,
turbogenerator unit for own needs — Andritz; and skilled personnel, was contracted to haul oversize loads
— hydraulic drives and installation and commissioning under complex conditions of the mountainous locale
management — Rexroth; (Figs. 18 and 19). In particular, to overcome the most hazard-
Development of the Hydropower Potential of the Grande De Santiago River (Mexico) 565

Fig. 19. La Vesca HPP. Transporting a sector of the generator stator. Fig. 21. La Vesca HPP. Construction of vertical shafts of support
cutoff.

Fig. 20. La Vesca HPP. Inlet portal of diversion tunnels with rein-
forced-concrete galleries.
Fig. 22. La Vesca HPP. Dam. View from upstream pool.

ous stretches of the road when delivering transformers


concrete galleries each 70 m long were added on to them
weighing more than 100 tons each, a motor vehicle train con-
(Fig. 20). To stabilize the left-bank slope, a support cutoff
sisting of a tractor, trailer, and two heavy bulldozers, which
was made in the form of a series of concrete-filled vertical
moved with lowered blades, cutting like a knife into the road
cover for braking the train and keeping a speed at no more shafts about 60-m deep and 7 m in diameter (Fig. 21). Dur-
than 4 km/h, was used. ing construction of the spillway, the need for additional stabi-
lization of the slopes of the pit was revealed, which affected
Despite the high rate of conducting the construction
the abutment of the spillway to the earth dam. This led to the
works, lagging occurred by the end of 2009. This was ex-
need to shift the axis of the dam and to increase its profile
plained by the considerable volume of additional construc-
volume (Fig. 22). The design of the spillway was also
tion works, the need for which arose as a result of the real,
extremely complex engineering geological situation from changed, which was divided into three independent canals
that presented in the bid documents. An urgent revision of made at different levels (Fig. 23).
the basic design decision became necessary. In particular, on Considerable difficulties arose during construction of the
the left-bank slope was discovered a geological fault which HPP intake (Fig. 24). The absence of intact rock in this zone
threatened the stability of the rocky slope about 150 m high necessitated the construction of a foundation in the form of
above the inlet portals of the diversion tunnels. To secure the reinforced concrete piles. Technical difficulties were re-
slope, a massive 40-m high retaining structure was erected, vealed during construction of the underground structures. In
during the construction of which 400,000 m3 of concrete was particular, within the limits of the assembly site was found a
placed. To protect the inlet portals of the tunnels, reinforced tectonic fault, which necessitated transferring the site to the
566 A. V. Kozyrev et al.

Fig. 23. La Vesca HPP. Dam and spillway canals.

Fig. 26. La Vesca HPP. Electrical substation.

Fig. 24. La Vesca HPP. HPP intake.


Fig. 27. La Vesca HPP. General view.

opposite side of the powerhouse with a corresponding elon-


gation of the transport tunnel. As a result of decompaction of
the rock mass, movements of the vertical walls of the surge
tank were discovered, which necessitated additional shoring
up the walls by reinforced-concrete braces (Fig. 25).
Despite the safety measures taken, the client feared a
landslide during filling of the reservoir and water invasion of
the left-bank slope. A bottom outlet equipped with two coni-
cal gates were constructed inside one of the diversion tunnels
for control during filling. This structure was not provided for
earlier in the design.
The aforementioned changes mainly submerged the con-
struction part of the project and to a lesser degree the electro-
mechanical part. Nevertheless, the question arose about the
impossibility of starting the units at the contract times and
well as about the insufficiency of the financial resources allo-
cated for construction. since according to the conditions of
the contract the engineering geological risks were applied to
the client, ICA turned to CFE with the request for additional
Fig. 25. La Vesca HPP. Surge tank with braces. construction financing. The client had funds only in the
Development of the Hydropower Potential of the Grande De Santiago River (Mexico) 567

amount of the budget cost of the project; therefore, the prob- CONCLUSIONS
lem of exceeding the limits and allocation of additional fi-
nancing was solved at the National Congress of Mexico. 1. The project of constructing a cascade of four HPPs
During this period, the rate of construction decreased sub- with a total capacity of 2484 MW and average long-term
stantially; works were carried out mainly on the dam. As a electricity generation of 4721 million (kW · h) was realized
result, it was decided to prolong construction according to an from 1990 to 2013 on the Grande de Santiago River (Mex-
updated schedule. ico).
The units of the La Vesca HPP were put into industrial 2. The system of reservoirs with a river flow dam-regu-
operation on October 29 and November 30, 2012. The total lator that formed on the river created favorable conditions for
construction time instead of 4 years and 7 months specified the development of an irrigation system having great agricul-
by the bid was 5 years and 2 months. Construction of the tural significance.
HPP structures was completed with a substantial budget 3. Construction confirmed the organizational and techni-
overrun. cal possibility of supplying equipment and performing the
In November – December 2013, full-scale tests of the entire complex of construction and assembly “turnkey”
turbine were conducted to confirm the efficiency values de- works in a brief calendar time.
clared in the TCP. According to the competition conditions, 4. Success of the construction was due to the joint ef-
the tests should be conducted by the thermodynamic method, forts of the client and contractor.
for which the Norwegian company Sweco, having the neces- The client’s responsibilities were:
sary measuring equipment and work experience, was hired. — working out detailed bid documents, preparing and
Support frames on which were located perforated tubes for conducting bids;
intake of water from various points of the cross section were — examination of the TCP of competitors and awarding
installed inside the tailrace tunnel and draft tube or conduc- the contract to the victor;
ing the tests. The water entered a measuring vessel in which — strict monitoring of the quality and time of perform-
it was mixed and its temperature measured. Furthermore, the ing construction works, manufacture, delivery, and assembly
water pressure before and after the turbine and the energy of of equipment;
the water flow and turbine efficiency were calculated. The — training of operating personnel.
guaranteed efficiency values were confirmed during the The responsibilities of the contractor were:
tests. — enlistment of investments for financing construction;
The completion of the construction of the La Vesca HPP — development of design documents;
was a significant event both for the client and for the consor- — enlistment of qualified personnel to realize the de-
tium. Complex technical problems that occurred during con- signs;
struction were able to be solved by all participants involved — organization of the construction and assembly of
in the project. In 2013 the authoritative Mexican construction equipment with the use of modern innovative technolo-
journal Obras awarded the La Vesca HPP the honorary title gies, machines, and mechanisms providing a high labor
“Construction of the Year” as the largest hydropower con- productivity;
struction project of the highest social significance, and the — effective management of administrative resources
PM company received from the client a “Reliable Supplier” and technical problems regarding coordination of the works
certificate. of organizations involved in the project.

You might also like