Professional Documents
Culture Documents
1007/s10749-020-01116-y
Power Technology and Engineering Vol. 53, No. 5, January, 2020
Organization of the construction of three hydroelectric power plants on the Grande de Santiago River is de-
scribed, namely the Aguamilpa, El Cajòn, and La Yesca, for supplying power to the states of Nayarit and
Jalisco.
Keywords: Aguamilpa; El Cajòn; La Yesca; San Rafael; Grande de Santiago River; organization of construc-
tion; HPP cascade; assembly; equipment; hydropower potential development; Comissiòn Federal de
Electricidad.
Three gorges are used in the mountainous Grande de surge tank, and extended tailrace tunnel (Fig. 2). These lay-
Santiago River valley for the construction of three large outs are a universal solution that the client traditionally used
HPPs in Mexico — Aquamilpa, El Cajòn, and La Yesca — both on the given hydropower complexes and in many other
intended mainly for supplying power to the large industrial projects with a mountainous relief of the locality. The design
metropolis Guadalajara and the states of Nayarit and Jalisco,
heads are also similar at all three plants of the cascade:
in the territories of which are located hydropower com-
plexes. 145.1, 156.5, and 163.3, respectively, as well as the power of
Aguamilipa hydropower complex. Construction of the
lower step of the cascade, the Aguamilipa HPP, began in
1990 and was completed in 1994. Nine years later, in January
2003, development of the hydropower resources of the river 5
continued with the construction of the following plants — El
Cajòn and construction of the La Vesca HPP began down- 4
3
stream in 2007. The bid documents on all three objects were
worked out by the project client, the Comissiòn Federal de
Elecricidad (CFE) exclusively engaged in the generation and
distribution of electricity and having long-term traditions in
hydropower construction based on the use of reliable and
time-verified technical solutions. 2
A distinctive characteristic of the HPP projects on the
Grande de Santiago River is that the three hydropower com- 11
1
plexes have the same composition of structures and similar 10
6
layout and structural solutions regarding the hydraulic engi-
9
neering part and hydropower equipment. All hydropower
complexes have tall (about 200 m) rockfill dams with rein- 8
forced concrete impervious membranes and bank flume
spillways with overflow dams equipped with radial gates
(Fig. 1). Also similar are the layouts of the hydropower 7
structures with an inclined bank water intake, individual
Fig. 1. Plan of the Aguamilpa hydropower complex: 1, dam; 2, up-
headrace tunnels, underground powerhouse, underground
stream cofferdam; 3, downstream cofferdam; 4, diversion tunnels;
1 JSC Lengidroproekt, St. Petersburg, Russia; e-mail: KozyrevAB@1hp.ru 5, spillway; 6, HPP intake; 7, headrace tunnels; 8, underground pow-
2 PJSC Power Machines, St. Petersburg, Russia. erhouse; 9, underground surge tank; 10, tailrace tunnel; 11, emer-
3 JSC VNIIG im. B. E. Vedeneeva, St. Petersburg, Russia. gency canal.
557
1570-145X/20/5305-0557 © 2020 Springer Science+Business Media, LLC
558 A. V. Kozyrev et al.
7
6
4
3
2 5
2
4 3
1
5
8
6 7
Fig. 4. San Rafael hydropower complex (1994 – 2013). stream of the Aguamilpa HPP, was constructed. The struc-
tures of the San Rafael hydropower complex included a
gravity-type concrete non-overflow dam constructed accord-
the assembly area. works on assembling the generator stator ing to the rolled concrete technology and a spillway with six
were carried out at the same time in a shaft. Upon completing radial gates. A constant discharge of water of about
these works, the generator rotor was lowered on October 29, 190 m3/sec was released into the lower pool of the San Rafa-
1993, the line of shafting was checked on December 24, el complex.
1993, and then final assembly of the unit took place. After An area for constructing the HPP was provided for in the
this, startup and adjusting tests were conducted: idling opera- abutment to the right bank of the San Rafael complex, but the
tion of the unit, high-voltage tests of the stator winding, etc. plant itself was not constructed at first. The San Rafael com-
plex was put into operation in such a form in July 1994
Synchronization of the first unit with the network was per-
(Fig. 4) and operated 19 years. Only in 2013 did construc-
formed on March 18, 1994. The second unit was assembled
tion of the HPP begin by the Acciona company under condi-
analogously and started on May 28, 1994 and the third was
tions of an EPC contract. The HPP is equipped with three
put into operation on June 9, 1994. Andritz 8-MW vertical Kaplan turbines. Construction of the
It was planned to operate the Aguamilpa HPP 6 h/day in HPP took 3 years and was completed on February 3, 2016
a peak regime with a discharge of 750 m3/sec, which would (Figs. 5 – 7).
lead to pronounced daily fluctuations of the lower pool water El Cajòn hydropower complex. The 1994 completion
level. To stabilize the level regime of the river, a counter- of the construction of the hydropower complex consisting of
regulator, the San Rafael hydropower complex, 17 km down- the Aguamipla HPP and San Rafael counter-regulator cre-
3
6 10
8
7
9
5
Fig. 11. El Cajòn HPP. Assembly of turbine stator. Fig. 13. El Cajòn HPP. Installation of the turbine cover with ring
gate.
The installation of two stop gate-emergency gates with brated in the deep-water experimental basin of the Krylov
rods, individual hydraulic drives and installation and com- Central Research Institute (TsNII, St. Petersburg, Russia).
missioning management, stop log, and gantry crane for ser- Works on the HPP were carried out in the presence of repre-
vicing it were provided for on the HPP intake. Assembly sentatives of the client, RM, and turbine manufacturer. The
works began on April 27, 2006 and continued until Decem- generator was tested by specialists of the Élektrosila plant.
ber 2006. During the tests the efficiency values claimed and guaranteed
in the TCP were confirmed.
Six radial gates with individual hydraulic drives and in-
stallation and commissioning management, stop logs, and a It should be noted that upon completion of construction,
gantry crane for servicing them were installed in the bays of objects of the industrial facilities, storages and temporary
the spillway dam (Fig. 15). Assembly works began on Octo- communications of various types, residential settlement, ad-
ber 14, 2005 and were completed on November 9, 2006 with ministrative and household buildings, and temporary access
test lifts of the gates and check releases of water into the roads and bridges were dismantled. In accordance with the
lower pool of the complex. requirements of the bid, complete rehabilitation and planting
The first unit was put into commercial operation on Feb- trees and shrubs of the territory of the construction site of the
ruary 27, 2007. Thus, works on assembling the first turbo- hydropower complex were carried out and those roads,
generator unit took about 25 months. Simultaneously, assem- bridges, and other infrastructure objects which were intended
bly works were carried out on the second unit, which contin- for permanent operation were reconstructed and updated.
ued for 27 months and were completed with commissioning La Vesca hydropower complex. In 2006 a competition
on May 30, 2007 (Fig. 16). The fact of commissioning the was announced for collaboration of ICA with PM on the con-
units was confirmed by the act of temporary acceptance after struction of the El Cajòn HPP, it was decided to form a new
200-h operation under load. From that moment responsibility consortium Constructora de Proyectos Hidroeléctricos
for operating the plant passed from the consortium to the cli- (CPH) for participating in the competition for the La Vesca
ent with technical support of specialists of the consortium. HPP. The following consortiums participated in the bids:
Special courses were organized to train the client’s operating CPH (ICA — La Peninsular — PM), US$908 million;
personnel by specialists of PM and suppliers. Gusta — Synohidro, US$1249 million; Techint — Impre-
In the fall of 2007 full-scale tests were conducted to con- gilo — V A Tech. The last consortium was disqualified be-
firm the correspondence of the actual efficiency of the unit to cause of infringements made in the technical part of the TCP.
the value which was claimed in the TCP. The firm Kharkov- According to the results of examining the TCPs, the competi-
TurboInzhiniring (Kharkov, Ukraine) with the participation tion’s organizer decided to annul the bids because the bid
of JSC TsKIG research and production association (St. Pe- participants exceeded the budget cost of the project —
tersburg, Russia) was enlisted to test the turbine. Used for US$836 million.
these works were 57 hydrometer flowmeters installed on a The following consortiums participated in repeated bids
support frame inside the headrace tunnel near the entry into in 2007: CPH (ICA — La Peninsula — PM). US$ 768 mil-
the scroll casing. The readings from each flowmeter were lion; Techint — Impregilo — VA Tech, US$ 856 million;
used to determine the velocity of the flow and then the dis- Carso — Voith Siemens, US$811 million. Making a decision
charge of water through the turbine and efficiency were cal- about awarding the contract, the client took into account that
culated. Before and after the tests, the flowmeters were cali- the presence of construction equipment and skilled labor
564 A. V. Kozyrev et al.
5
3
4
10
9
8
2 6
7
Fig. 18. La Vesca HPP. Hauling the turbine runner.
Fig. 17. La Vesca HPP. Plan of hydropower complex: 1, dam; 2, up-
stream cofferdam; 3, downstream cofferdam; 4, diversion tunnels;
5, spillway; 6, HPP intake; 7, headrace tunnels; 8, power house;
9, underground surge tank; 10, tailrace tunnel. — main step-up transformers, automatic control system,
GIS, and other electrical equipment — Siemens.
The firm Hydroproject de Mexico (Mexico) was selected
force, having been freed up at the El Cajòn HPP, would be a as the general designer of the electromechanical part of the
strong impulse for starting the construction of the La Vesca CM project. Specialists of this company coordinated the
HPP located near the preceding site. Participation of PM in work of numerous subcontractor organizations, monitored
the consortium made it possible to use analogous hydro- fulfillment of the work schedule, coordinated the designs of
power equipment of the same supplier that equipped the the equipment with the designs of the construction part, etc.
downstream plants of the cascade with turbines and genera- All assembly works were accomplished by the Duero Inge-
tors. As a result, the client awarded the winner in the compe- nieria company assisted by SGÉM specialists and under the
tition to the CPH consortium, which showed in its TPC the supervision of head engineers of the suppliers.
lowest cost of electricity generation — 0.80 pesos/(kW · h). Having positive working experience on the construction
A subcontract form of participation of PM in the CPH con- of the El Cajòn HPP, the participants of the CPH consortium
sortium was accepted during internal negotiations and mu- looked at the new contract with great enthusiasm, consider-
tual agreement. Construction of the La Vesca HPP began in ing it a copy of the preceding one. Actually, there was much
October 2007. in common in the layout and designs of the structures of the
The contract obligations of PM, as also for the El Cajòn two hydropower complexes. The La Vesca HPP had an anal-
HPP, included design, manufacture, delivery of the entire ogous rockfill dam 200 m tall with an impervious reinforced
volume of technological equipment, assembly and startup concrete membrane, bank flume spillway, maximum capac-
and adjustment, conduction of guarantee tests, putting the ity 15,100 m3/sec, and two 14 × 14-m diversion tunnels
HPP units into commercial operation on January 2 and April (Fig. 17) The water from the intake to the unit of the under-
2, 2012 with guarantee two-year servicing. The suppliers ground powerhouse was delivered by two tunnels with an in-
of the main hydropower equipment were JSC Turboatom side diameter of 7.7 m and a maximum discharge of
(Ukraine) and PM/Élektrosila (Russia), as also on the down- 250 m3/sec through each tunnel. A substation with step-up
stream plants of the cascade; the suppliers of the auxiliary transformers and GIS was located in an outdoor area.
equipment were changed. It is necessary to note that supply- However, the natural conditions of the La Vesca HPP site
ing the El Cajòn HPP with complete sets of Brazilian-made were considerably more complex. The steep walls of the can-
auxiliary equipment caused difficulties for the client related yon created problems for organizing industrial facility and
to the complexity of its servicing. For this reason, require- residential settlement sites, as well as substantially hindered
ments on purchasing equipment on the local market were the construction of temporary roads. On some stretches the
brought up in the bid. To meet this requirement, companies longitudinal incline of the roads exceeded 20%, and the
having representation in Mexico were enlisted to supply aux- ground cover was constantly destroyed and deformed by the
iliary equipment to the La Vesca HPP, namely: heavy-load trucks. The transport company Transportes Telle-
— speed regulators, ring gate control system, small ria, having the necessary experience, specialized equipment,
turbogenerator unit for own needs — Andritz; and skilled personnel, was contracted to haul oversize loads
— hydraulic drives and installation and commissioning under complex conditions of the mountainous locale
management — Rexroth; (Figs. 18 and 19). In particular, to overcome the most hazard-
Development of the Hydropower Potential of the Grande De Santiago River (Mexico) 565
Fig. 19. La Vesca HPP. Transporting a sector of the generator stator. Fig. 21. La Vesca HPP. Construction of vertical shafts of support
cutoff.
Fig. 20. La Vesca HPP. Inlet portal of diversion tunnels with rein-
forced-concrete galleries.
Fig. 22. La Vesca HPP. Dam. View from upstream pool.
amount of the budget cost of the project; therefore, the prob- CONCLUSIONS
lem of exceeding the limits and allocation of additional fi-
nancing was solved at the National Congress of Mexico. 1. The project of constructing a cascade of four HPPs
During this period, the rate of construction decreased sub- with a total capacity of 2484 MW and average long-term
stantially; works were carried out mainly on the dam. As a electricity generation of 4721 million (kW · h) was realized
result, it was decided to prolong construction according to an from 1990 to 2013 on the Grande de Santiago River (Mex-
updated schedule. ico).
The units of the La Vesca HPP were put into industrial 2. The system of reservoirs with a river flow dam-regu-
operation on October 29 and November 30, 2012. The total lator that formed on the river created favorable conditions for
construction time instead of 4 years and 7 months specified the development of an irrigation system having great agricul-
by the bid was 5 years and 2 months. Construction of the tural significance.
HPP structures was completed with a substantial budget 3. Construction confirmed the organizational and techni-
overrun. cal possibility of supplying equipment and performing the
In November – December 2013, full-scale tests of the entire complex of construction and assembly “turnkey”
turbine were conducted to confirm the efficiency values de- works in a brief calendar time.
clared in the TCP. According to the competition conditions, 4. Success of the construction was due to the joint ef-
the tests should be conducted by the thermodynamic method, forts of the client and contractor.
for which the Norwegian company Sweco, having the neces- The client’s responsibilities were:
sary measuring equipment and work experience, was hired. — working out detailed bid documents, preparing and
Support frames on which were located perforated tubes for conducting bids;
intake of water from various points of the cross section were — examination of the TCP of competitors and awarding
installed inside the tailrace tunnel and draft tube or conduc- the contract to the victor;
ing the tests. The water entered a measuring vessel in which — strict monitoring of the quality and time of perform-
it was mixed and its temperature measured. Furthermore, the ing construction works, manufacture, delivery, and assembly
water pressure before and after the turbine and the energy of of equipment;
the water flow and turbine efficiency were calculated. The — training of operating personnel.
guaranteed efficiency values were confirmed during the The responsibilities of the contractor were:
tests. — enlistment of investments for financing construction;
The completion of the construction of the La Vesca HPP — development of design documents;
was a significant event both for the client and for the consor- — enlistment of qualified personnel to realize the de-
tium. Complex technical problems that occurred during con- signs;
struction were able to be solved by all participants involved — organization of the construction and assembly of
in the project. In 2013 the authoritative Mexican construction equipment with the use of modern innovative technolo-
journal Obras awarded the La Vesca HPP the honorary title gies, machines, and mechanisms providing a high labor
“Construction of the Year” as the largest hydropower con- productivity;
struction project of the highest social significance, and the — effective management of administrative resources
PM company received from the client a “Reliable Supplier” and technical problems regarding coordination of the works
certificate. of organizations involved in the project.