ID Resource Name Type Material Label Initials Group Max. Units Std. Rate Ovt.

Group Max. Units Std. Rate Ovt. Rate Cost/Use Accrue At Base Calendar Code
1 SEMEN Material SAK SMN Rp52.000 Rp0 Start
2 PASIR Material M3 PSR Rp250.000 Rp0 Start
3 AIR Material M3 AIR Rp5.000 Rp0 Start
4 BESI Material KG BS Rp7.000 Rp0 Start
5 BATA Material PCS BT Rp1.500 Rp0 Start
6 CAT Material KG CT Rp10.000 Rp0 Start
7 TRIPLEK Material M3 TRPLK Rp30.000 Rp0 Start
8 KAYU KASO Material M KS Rp1.000.000 Rp0 Start
9 KUSEN PINTU Material SET KP Rp300.000 Rp0 Start
10 KUSEN JENDELA Material SET KJ Rp250.000 Rp0 Start
11 PINTU Material SET P Rp500.000 Rp0 Start
12 JENDELA Material SET J Rp300.000 Rp0 Start
13 RANGKA ATAP Material SET RA Rp5.000.000 Rp0 Start
14 GENTENG DAN TALANG Material PCS GDT Rp12.000 Rp0 Start
15 GYPSUM Material M2 G Rp12.000 Rp0 Start
16 KERAMIK Material PCS K Rp10.000 Rp0 Start
17 EPOXY LANTAI Material M2 EL Rp25.000 Rp0 Start
18 ELEVATED FLOOR Material M2 EF Rp125.000 Rp0 Start
19 COVER CABLE DUCT Material M2 CCD Rp125.000 Rp0 Start
20 KONDULT KABEL Material M KK Rp15.000 Rp0 Start
21 KABEL NYY Material M KN Rp23.000 Rp0 Start
22 POWER OUTLET Material PCS PO Rp18.000 Rp0 Start
23 POWER SWITCH Material PCS PS Rp15.000 Rp0 Start
24 STEEL SUPPORT Material SET SS Rp30.000.000 Rp0 End
25 LA EQUPMENT Material SET LE Rp100.000.000 Rp0 End
26 VT EQUIPMENT Material SET V Rp200.000.000 Rp0 End
27 DS EQUIPMENT Material SET D Rp300.000.000 Rp0 End
28 DSE EQUIPMENT Material SET D Rp350.000.000 Rp0 End
29 CT EQUIPMENT Material SET C Rp400.000.000 Rp0 End
30 CB EQUIPMENT Material SET C Rp500.000.000 Rp0 End
31 MARSHALING KIOSK Material SET M Rp17.000.000 Rp0 End
32 POWER CABLE Material M P Rp45.000 Rp0 End
33 CONTROL CABLE Material M C Rp33.000 Rp0 End
34 CONDUCTOR Material SET C Rp1.500.000 Rp0 End
35 RELAY CONTROL PANEL Material SET R Rp330.000.000 Rp0 End
36 TELECOMMUNICATION PANEL Material SET T Rp150.000.000 Rp0 End
37 DC POWER SYSTEM Material SET D Rp120.000.000 Rp0 End
38 HIMI AND SCADA Material SET H Rp200.000.000 Rp0 End
39 BATTERY SYSTEM Material SET B Rp130.000.000 Rp0 End
40 UPS Material SET U Rp140.000.000 Rp0 End
41 TRAFO 150/20 KV Material SET T Rp2.000.000.000 Rp0 End
42 TRAFO 20/0.4 KV Material SET T Rp400.000.000 Rp0 End
43 CUBICLE 20 KV Material SET C Rp100.000.000 Rp0 End
44 BURUH SIPIL Work B 100 Rp130.000/hr Rp15.000/hr Rp0 Prorated PROYEK PEMBANGKITAN
45 TUKANG SIPIL Work T 50 Rp200.000/hr Rp25.000/hr Rp0 Prorated PROYEK PEMBANGKITAN
46 BURUH EM Work B 50 Rp175.000/hr Rp25.000/hr Rp0 Prorated PROYEK PEMBANGKITAN
47 TUKANG EM Work T 20 Rp250.000/hr Rp35.000/hr Rp0 Prorated PROYEK PEMBANGKITAN
48 ENGINEER Work E 10 Rp725.000/hr Rp100.000/hr Rp0 Prorated PROYEK PEMBANGKITAN
49 SUBKON INSTALASI EQUIPMENT Work S 8 Rp1.250.000/hr Rp0/hr Rp0 Prorated PROYEK PEMBANGKITAN
50 SUBKON TEST EQUIPMENT Work S 5 Rp3.250.000/hr Rp0/hr Rp0 Prorated PROYEK PEMBANGKITAN
51 SUBKON COMMISIONING Work S 2 Rp7.250.000/hr Rp0/hr Rp0 Prorated PROYEK PEMBANGKITAN
52 BURUH SIPl Work B 1 Rp0/hr Rp0/hr Rp0 Prorated PROYEK PEMBANGKITAN

Page 1 PROJECT TUGAS BESAR