Blocking (double layer

3/4" plywood 2'x8')


10
5 Curtain Wall 1" smooth conduit for data cables,
Scoring Monitors
(extend downward after NOT corrugated orange tube.
3 11 bowling installation)
12
8' Suggested
4
Initially 7'-6" 10' Suggested Pin Sight Line Touchscreen
1 above slab
9'-1" 1'-8"
depression
2 11'-1" Pinsetter Machine
Ball Return Home Bowling Alley Sales & Installation
22" Finished
Opening
Foul Line www.FusionBowling.com
1'-8"
17" 6 7 8 9 17"

5'-3" Aisle 8'-1"


18' (End of slab depression to face of curtain wall)
60' Regulation size bowling lane (from center of head pin to foul line)
71' (Rear face of curtain wall to front of slab depression)
15'-8" Approach
(foul line to front of slab depression) (904) 701-2695
89' (Entire slab depression)

Side Section Preferred Partner

GENERAL NOTES:
This drawing depicts a typical scenario, and will change based
on unique circumstances at each job site. Contact Fusion
Bowling early for free design and planning help. The first site
1" Embedded Conduits 25' 9' 7' visit occurs during the electrical rough-in stage. Equipment
5'-3" Aisle 11'-1" Pinsetter Machine 1'-8" Line (for home-run power from bowling
Pin Sight lead time is approximately six months.
subpanel to under-lane equipment)
17" Gutter

2'-10"
Narrow Capping Consider adding (by others)

Foul Line
4
Scoring Monitors
11'-6" Slab depression

11'-6" Slab depression


Curtain Wall (opening spans - Closet for lane machine and maintenance supplies
Lane 2 (above) Touchscreen
3 5 11'-6" across bowling lanes)
Ball Return
- Mop sink for lane machine refilling/draining
Gutter - Built-in shelving or cubbie holes for shoes and balls

5'-10"
11 7
6 Return Capping 10 9
12 Gutter 8 - UV lighting to make bowling lanes fluoresce ("glow")
1'-8"

Foul Line
2 Regulation size bowling lane 8' Suggested
Lane 1 Ceiling Blocking
(60' from center of head pin to foul line) Installation Timing

2'-10"
1 (double layer 3/4"
Narrow Capping
Gutter
plywood 2'x8') Bowling installation occurs after:
17"
- HVAC is maintaining 72º.
Pin Sight Phoenix LT4 Lane Machine 15'-8" Approach (foul line to
Line Side aisles suggested, not required needs storage closet or cabinet. front of slab depression)
- Permanent power meter is activated.
56"L, 36"H, 14"D, 250 lbs on casters. - Ceiling finishes & light fixtures are completed.
13
Bowling installation occurs before:
18' (End of slab depression to face of curtain wall) 71' (Rear face of curtain wall to front of slab depression) - Flooring.
89' (Entire slab depression)
Fusion Bowling is an out-of-town contractor. Electrician must
Plan have materials and be ready to work when bowling installation
begins.

Customer must provide empty 30-yard³ dumpster.

Blocking (double layer


3/4" plywood 2' W, 8' L)

Lane 1 Lane 2
Electrical Notes
Monitor Monitor # Device Description Breaker Current Voltage

1 Subpanel Mounted in bowling mechanical room, and dedicated to bowling circuits only — — —
2 Surge suppressor Provided by Fusion Bowling. Connect to subpanel. 15A — 230V**
Builder adds this 3 3-Phase converter* Provided by Fusion Bowling. Wall-mount near pinsetters. 60A 45A 230V
portion of curtain wall Initially
after bowling installation. 7'-6" above 4 Safety switch* Provided by Fusion Bowling. 3-pole 15A fusible disconnect for phase converter — — 230V
slab 5 Pinsetter machine Single flex cord from ceiling per pair of pinsetter machines —† 12A 230V**
22" depression Bumpers Duplex receptacle under return capping
6 15A 3A 115V
Finished
7 Foul detector Duplex receptacle under return capping 15A 1A 115V
17"
8 Capping lights Duplex receptacle under return capping 15A 1A 115V
9 Ball return Junction box under trap door in approach 15A 6A 115V
2'-10" 5'-10" 2'-10" 1" Embedded Conduits
(for home-run power from 10 Scoring monitors Duplex receptacle in ceiling
11'-6" Slab Depression 15A 8A 115V
bowling subpanel to
under-lane equipment)
11 Scoring electronics Quad receptacle on rear face of curtain wall DATE/REVISION: 12/27/2022
12 Internet jack Hard-wired ethernet jack on rear face of curtain wall — — —

Front Section 13 Lane oil machine Dedicated 5-20R wall receptacle near foul line
*Not needed if building has 3-phase power. **208V if building has 3-phase power.
20A
†15A if building has 3-phase power.
15A 115V
2-Lane Bowling Alley