Professional Documents
Culture Documents
Management Accounting Formulas
Management Accounting Formulas
A FORMULAS
1. C.M – F.C
3. NET PROFIT 2. BUDGETED SALES × PROFIT %
3. M/S × C.M RATIO
4. BUDGETED SALES × CM RATIO × MARGIN OF SAFETY
RATIO
𝐓𝐎𝐓𝐀𝐋 𝐂𝐎𝐍𝐓𝐑𝐈𝐁𝐔𝐓𝐈𝐎𝐍
= × 100
𝑻𝑶𝑻𝑨𝑳 𝑺𝑨𝑳𝑬𝑺
OR
𝐂𝐎𝐍𝐓𝐑𝐈𝐁𝐔𝐓𝐈𝐎𝐍 𝐏𝐄𝐑 𝐔𝐍𝐈𝐓
= × 100
𝑺𝑨𝑳𝑬𝑺 𝑷𝑬𝑹 𝑼𝑵𝑰𝑻
4. CM RATIO / PROFIT OR
𝐒𝐀𝐋𝐄𝐒 – 𝐕𝐀𝐑𝐈𝐀𝐁𝐋𝐄 𝐂𝐎𝐒𝐓
VOLUME RATIO = × 100
𝑺𝑨𝑳𝑬𝑺
OR
∆ 𝐂𝐎𝐍𝐓𝐑𝐈𝐁𝐔𝐓𝐈𝐎𝐍/𝐏𝐓𝐎𝐅𝐈𝐓
=
∆ 𝑺𝑨𝑳𝑬𝑺
P a g e 1 | 19
SYED SHAHBAZ RAZA ZAIDI
M.A FORMULAS
QUANTITY:
𝐓𝐎𝐓𝐀𝐋 𝐅𝐈𝐗𝐄𝐃 𝐂𝐎𝐒𝐓
=
𝑪𝑶𝑵𝑻𝑹𝑰𝑩𝑼𝑻𝑰𝑶𝑵 𝑷𝑬𝑹 𝑼𝑵𝑰𝑻
OR
𝐕𝐀𝐋𝐔𝐄 𝐎𝐅 𝐁𝐑𝐄𝐀𝐊𝐄𝐕𝐄𝐍 𝐏𝐎𝐈𝐍𝐓
=
𝑺𝑨𝑳𝑬𝑺 𝑷𝑹𝑰𝑪𝑬 𝑷𝑬𝑹 𝑼𝑵𝑰𝑻
5. BREAKEVEN POINT OR
SALES VALUE:
𝐓𝐎𝐓𝐀𝐋 𝐅𝐈𝐗𝐄𝐃 𝐂𝐎𝐒𝐓
= × SALES PRICE PER UNIT
𝑪𝑶𝑵𝑻𝑹𝑰𝑩𝑼𝑻𝑰𝑶𝑵 𝑷𝑬𝑹 𝑼𝑵𝑰𝑻
OR
𝐓𝐎𝐓𝐀𝐋 𝐅𝐈𝐗𝐄𝐃 𝐂𝐎𝐒𝐓
=
𝑷𝑹𝑶𝑭𝑰𝑻 𝑽𝑶𝑳𝑼𝑴𝑬 /𝑪𝑴 𝑹𝑨𝑻𝑰𝑶
QUANTITY:
𝐓𝐎𝐓𝐀𝐋 𝐅.𝐂 + 𝐃𝐄𝐒𝐈𝐑𝐄𝐃 𝐏𝐑𝐎𝐅𝐈𝐓
=
𝑪𝑶𝑵𝑻𝑹𝑰𝑩𝑼𝑻𝑰𝑶𝑵 𝑷𝑬𝑹 𝑼𝑵𝑰𝑻
6. SALE FOR DESIRED
PROFIT
VALUE:
𝐓𝐎𝐓𝐀𝐋 𝐅.𝐂 + 𝐃𝐄𝐒𝐈𝐑𝐄𝐃 𝐏𝐑𝐎𝐅𝐈𝐓
=+
𝑪𝑶𝑵𝑻𝑹𝑰𝑩𝑼𝑻𝑰𝑶𝑵 𝑴𝑨𝑹𝑮𝑰𝑵 𝑹𝑨𝑻𝑰𝑶
OR
𝐓𝐎𝐓𝐀𝐋 𝐅.𝐂 + 𝐃𝐄𝐒𝐈𝐑𝐄𝐃 𝐏𝐑𝐎𝐅𝐈𝐓
= × SALES PRICE PER UNIT
𝑪𝑶𝑵𝑻𝑹𝑰𝑩𝑼𝑻𝑰𝑶𝑵 𝑷𝑬𝑹 𝑼𝑵𝑰𝑻
PERCENTAGE
𝑩𝑼𝑫𝑮𝑬𝑻𝑬𝑫 /𝑨𝒄𝒕𝒖𝒂𝒍 𝒔𝒂𝒍𝒆𝒔 − 𝒃𝒓𝒆𝒂𝒌𝒆𝒗𝒆𝒏 𝒑𝒐𝒊𝒏𝒕
= × 100
𝑩𝒖𝒅𝒈𝒆𝒕𝒆𝒅 / 𝑨𝒄𝒕𝒖𝒂𝒍 𝒔𝒂𝒍𝒆𝒔
QUANTITY:
P a g e 2 | 19
SYED SHAHBAZ RAZA ZAIDI
M.A FORMULAS
QUANTITY:
𝐓𝐎𝐓𝐀𝐋 𝐅𝐈𝐗𝐄𝐃 𝐂𝐎𝐒𝐓
=
𝑾𝑬𝑰𝑮𝑯𝑻𝑬𝑫 𝑪𝑶𝑵𝑻𝑰𝑩𝑼𝑻𝑰𝑶𝑵 𝑴𝑨𝑹𝑮𝑰𝑵 𝑷𝑬𝑹 𝑼𝑵𝑰𝑻
HI -LO METHOD
P a g e 3 | 19
SYED SHAHBAZ RAZA ZAIDI
M.A FORMULAS
COST PROFIT
OVER APPLIED LESS ADD
UNDER APPLIED ADD LESS
BEGINNING STOCK COGS PROFIT
P a g e 4 | 19
SYED SHAHBAZ RAZA ZAIDI
M.A FORMULAS
THROUGHPUT ACCOUNTING
Throughput is the money generated from sales minus the cost of the materials used in
making the items sold.
All costs other than materials are seen as fixed in the short term.
Inventory is valued at material cost only.
Bottleneck resource or binding constraint – an activity which has a lower capacity than
preceding or subsequent activities, thereby limiting throughput.
P a g e 5 | 19
SYED SHAHBAZ RAZA ZAIDI
M.A FORMULAS
INVENTORY MANAGEMENT
2. ANNUAL DEMAND: = NORMAL USE PER DAY × WORKING DAYS PER YEAR
𝐀𝐍𝐍𝐔𝐀𝐋 𝐃𝐄𝐌𝐀𝐍𝐃
3. OPTIMUM NO. OF ORDERS: = 𝐄𝐎𝐐
6. SAFETY STOCK (MAXIMUM USE PER DAY – NORMAL USE PER DAY) × LEAD
TIME
WITH SAFTEY STOCK
(DEMAND FOR MATERIAL ITEM PER DAY/ WEEK × LEADTIME
7. REORDER POINT/ LEVEL IN DAYS/ WEEK) + SAFETY STOCK
𝐄𝐎𝐐 𝐨𝐫 𝐎𝐐
8. AVERAGE INVENTORY + SAFETY STOCK
𝟐
10. ABSOLUTE MAXIMUM INVENTORY RE-ORDER LEVEL + ORDERING QUANTITY - [MINIMUM USAGE
× MINIMUM LEAD TIME]
11. MINIMUM INVENTORY (SAFETY RE-ORDER LEVEL - [NORMAL USAGE × NORMAL LEAD TIME]
STOCK)
P a g e 6 | 19
SYED SHAHBAZ RAZA ZAIDI
M.A FORMULAS
𝐓𝐎𝐓𝐀𝐋 𝐋𝐈𝐀𝐁𝐈𝐋𝐈𝐓𝐈𝐄𝐒
5. DEBT RATIO × 100
𝐓𝐎𝐓𝐀𝐋 𝐀𝐒𝐒𝐄𝐓𝐒
𝐓𝐎𝐓𝐀𝐋 𝐄𝐐𝐔𝐈𝐓𝐈𝐄𝐒
6. EQUITY RATIO × 100
𝐓𝐎𝐓𝐀𝐋 𝐀𝐒𝐒𝐄𝐓𝐒
TIMES
𝑪𝑶𝑵𝑺𝑼𝑴𝑷𝑻𝑰𝑶𝑵
𝑨𝑽𝑬𝑹𝑨𝑮𝑬 𝑹𝑨𝑾 𝑴𝑨𝑻𝑬𝑹𝑰𝑨𝑳
P a g e 7 | 19
SYED SHAHBAZ RAZA ZAIDI
M.A FORMULAS
TIMES
𝑪𝑶𝑺𝑻 𝑶𝑭 𝑷𝑹𝑶𝑫𝑼𝑪𝑻𝑰𝑶𝑵
𝑨𝑽𝑬𝑹𝑨𝑮𝑬 𝑾𝑰𝑷
TIMES
𝑪𝑶𝑺𝑻 𝑶𝑭 𝑮𝑶𝑶𝑫𝑺 𝑺𝑶𝑳𝑫
𝑨𝑽𝑬𝑹𝑨𝑮𝑬 𝑭. 𝑮
DAYS
= TIMES × 365
OR
𝑨𝑽𝑬𝑹𝑨𝑮𝑬 𝑭.𝑮
× 365
𝑪𝑶𝑺𝑻 𝑶𝑭 𝑮𝑶𝑶𝑫𝑺 𝑺𝑶𝑳𝑫
TIMES
𝑪𝑹𝑬𝑫𝑰𝑻 𝑺𝑨𝑳𝑬𝑺
𝑨𝑽𝑬𝑹𝑨𝑮𝑬 𝑫𝑬𝑩𝑻𝑶𝑹𝑺
P a g e 8 | 19
SYED SHAHBAZ RAZA ZAIDI
M.A FORMULAS
TIMES
𝑪𝑹𝑬𝑫𝑰𝑻 𝑷𝑼𝑹𝑪𝑯𝑨𝑺𝑬𝑺
𝑨𝑽𝑬𝑹𝑨𝑮𝑬 𝑪𝑹𝑬𝑫𝑰𝑻𝑶𝑹𝑺
1) VOLUME
2) INFLATION
3) DAYS/ TIMES
𝑵𝑬𝑾 𝑫𝑨𝒀𝑺
𝑶𝑳𝑫 𝑫𝑨𝒀𝑺
𝑶𝑳𝑫 𝑻𝑰𝑴𝑬
𝑵𝑬𝑾 𝑻𝑰𝑴𝑬
20. CHANGES Change in Volume impact on followings
P a g e 9 | 19
SYED SHAHBAZ RAZA ZAIDI
M.A FORMULAS
TRADE CREDIT
“The act of obtaining funds by delaying payments to supplier (give-up
early discounts)”
P a g e 10 | 19
SYED SHAHBAZ RAZA ZAIDI
M.A FORMULAS
FV = PV (1 + 𝒓)𝒏
1. FUTURE VALUE PV = present value
(Compounding) FV = future value
r = cost of capital or interest rate
n = number of years/ periods
2. PRESENT VALUE 𝐅𝐕
PV =
(Discounting) (𝟏 + 𝒓)𝒏
𝟏 − (𝟏 + 𝒓)−𝒏
PV = P
𝒓
𝟏 − (𝟏 + 𝒓)−𝒏+𝟏
PV = P +1
𝒓
P a g e 11 | 19
SYED SHAHBAZ RAZA ZAIDI
M.A FORMULAS
Average investment
8. EFFECTIVE RATE 𝟏 +𝒓 𝒎
=( ) -1
𝒎
𝑷
IRR = A + × (B-A) %
9. INTERNAL RATE OF 𝑷−𝑵
RETURN (IRR) Where
A is the (lower) rate of return
B is the (higher) rate of return
IRR is the rate at which our
P is the NPV at A
project NPV is zero N is the NPV at B
OR
Discounted cash out flow =
Discounted cash inflow
𝑰𝑵𝑰𝑻𝑰𝑨𝑳 𝑰𝑵𝑽𝑬𝑺𝑻𝑴𝑬𝑵𝑻
10. IRR OF ANNUITY 𝑨𝑵𝑵𝑼𝑨𝑳 𝑪𝑨𝑺𝑯 𝑭𝑳𝑶𝑾 𝑨𝑭𝑻𝑬𝑹 𝑻𝑨𝑿
P a g e 12 | 19
SYED SHAHBAZ RAZA ZAIDI
M.A FORMULAS
𝑷𝑽 𝑶𝑭 𝑪𝑨𝑺𝑯 𝑰𝑵𝑭𝑳𝑶𝑾𝑺
11. PROFITTABILITY
=
𝑷𝑽 𝑶𝑭 𝑪𝑨𝑺𝑯 𝑶𝑼𝑻𝑭𝑳𝑶𝑾𝑺
INDEX OR
𝑵𝑷𝑽
=
𝑷𝑽 𝑶𝑭 𝑪𝑨𝑺𝑯 𝑶𝑼𝑻𝑭𝑳𝑶𝑾𝑺
17. CAPITAL
ALLOWANCE 𝐂𝐎𝐒𝐓 – 𝐑𝐄𝐒𝐈𝐃𝐔𝐀𝐋 𝐕𝐀𝐋𝐔𝐄
(DEPRECIATION 𝑳𝑰𝑭𝑬
P a g e 13 | 19
SYED SHAHBAZ RAZA ZAIDI
M.A FORMULAS
1. DEPRICIATION
18. TAX SAVE(SHIELD) 2. LOSS ON DISPOSAL
3. INCREASE IN EXPENSES
VARIANCE ANALYSIS
MATERIAL VARIANCE
2.1. MATERIAL MIX = (ACTUAL USING STD. MIX – ACTUAL KG) × STD. COST
VARIANCE
ACTUAL USING STD. MIX = ACTUAL INPUT/ STD OUTPUT × SPECIFIC STD. INPUT
P a g e 14 | 19
SYED SHAHBAZ RAZA ZAIDI
M.A FORMULAS
LABOR VARIANCE
2.1. LABOUR MIX = (ACTUAL USING STD. MIX – ACTUAL HOURS) × STANDARD RATE PER
VARIANCE HOUR
ACTUAL USING STD. MIX = ACTUAL INPUT/ STD OUTPUT × SPECIFIC STD. INPUT
2.2. LABOUR YIELD = (OUTPUT SHOULD BE – ACTUAL OUTPUT) × STANDARD OUTPUT COST
VARIANCE
OUTPUT SHOULD BE = ACTUAL INPUT/ STD. INPUT × STD. OUTPUT
3. IDLE TIME = (ACTUAL HOURS – PAID FOR HOURS) × STANDARD RATE PER HOUR
VARIANCE
1. TOTAL VARIABLE FOH = (STD. V.FOH FOR ACTUAL OUTPUT – ACTUAL V.FOH)
VARIANCE
P a g e 15 | 19
SYED SHAHBAZ RAZA ZAIDI
M.A FORMULAS
2. SPENDING VARIANCE = (STD. V.FOH FOR ACTUAL HOURS WORKED - ACTUAL V.FOH)
3.2. CAPACITY
VARIANCE = (ACTUAL HOURS – ESTIMATED HOURS) × RATE
SALES VARIANCE
P a g e 16 | 19
SYED SHAHBAZ RAZA ZAIDI
M.A FORMULAS
1. SALES PRICE = (STD. SELLING PRICE – ACTUAL SELLING PRICE) × ACTUAL NO. OF UNITS
VARIANCE SOLD
4. SALES VOLUME PROFIT = (ACTUAL UNITS SOLD - BUDGETED SALE UNITS) × STANDARD
VARIANCE PROFIT PER UNIT
PLANNING VARIANCE
P a g e 17 | 19
SYED SHAHBAZ RAZA ZAIDI
M.A FORMULAS
OPERATIONAL VARIANCE
Sales values recorded at actual amounts. No accounts are kept for sales variances
P a g e 19 | 19
SYED SHAHBAZ RAZA ZAIDI