You are on page 1of 11

Tunnelling and Underground Space Technology 71 (2018) 329–339

Contents lists available at ScienceDirect

Tunnelling and Underground Space Technology


journal homepage: www.elsevier.com/locate/tust

Comparative study of construction methods for deep excavations above MARK


shield tunnels

Ming-Guang Lia, Jin-Jian Chena, Jian-Hua Wanga, , Yan-Fei Zhub
a
State Key Laboratory of Ocean Engineering, Department of Civil Engineering, Shanghai Jiao Tong University, 800 Dongchuan Road, Shanghai, China
b
Shanghai Tunnel Engineering Co., Ltd., 118 Dalian Rd., Shanghai 200082, China

A R T I C L E I N F O A B S T R A C T

Keywords: Although an appropriate construction method contributes to minimizing the excavation-induced impact on
Deep excavation existing facilities, few studies have focused on the comparison and optimization of the construction methods for
Tunnels engineering projects in practice. In this paper, Three-dimensional (3D) numerical simulations are carried out to
Numerical simulation compare the construction methods for an excavation above shield tunnels through a case history, which has been
Construction method
constructed by a novel excavation method, referred to as divided alternate excavation method (DAEM). A 3D
Comparative analysis
numerical model is developed in the finite element (FE) software, ABAQUS 6.10, to simulate the practical
construction process of the DAEM, and the numerical results are analyzed in combination with the field data.
Comparative studies are performed by simulating the hypothetical construction schemes of two conventional
excavation methods that were proposed for the investigated case. Numerical results confirm the effectiveness of
the DAEM on controlling the excavation-induced underlying tunnel deformation. Extensive parametric studies of
the DAEM are performed for further investigation. Through the comparative studies and parametric studies,
suggestions are proposed for optimization of construction methods for deep excavations above shield tunnels.

1. Introduction remedial measures or countermeasures are adopted, including soil re-


inforcement within excavation area (Hu et al., 2003; Huang et al., 2006;
Shanghai has experienced unprecedented infrastructure construc- Chen et al., 2013) and stiffness enhancement of retaining structures
tion activities in the past decades. To relive the traffic pressure in this (Huang et al., 2013). Moreover, a rational excavation sequence also
congested urban area, many metro tunnels have been excavated in this helps to control the deformation of the existing tunnels efficiently by
period using earth pressure balanced (EPB) shield machines. following the time-space effect (Hu et al., 2003; Lu and Hanyga, 2005b;
Meanwhile, more and more highway tunnels are being constructed, Liu et al., 2011; Li et al., 2014). However, the effectiveness of these
which calls for deep excavations supported by retaining structures. remedial measures or countermeasures on the tunnel deformation
Deep excavations will cause potential large soil deformations inside and needs to be evaluated.
outside of the excavation pit, and will result in serious influence on Numerical method is a feasible tool and has been widely used to
adjacent existing shield tunnels (Chai et al., 2014; Son and Cording, evaluate the response of tunnels to adjacent deep excavations (Zhang
2005). If excessive stress and deformation are induced in the shield et al., 2013; Ng et al., 2013, 2015a, 2015b). Two dimensional (2D)
tunnels, cracks will be developed and these tunnels may be damaged numerical simulation is preferred because of its high computational
(Chang et al., 2001). Therefore, to minimize the adverse impact, it is of efficiency (Chen et al., 2011; Sharma et al., 2001). Using the 2D FEM,
particular importance to compare and optimize the schemes before Hu et al. (2003) predicted the vertical and horizontal displacements of
construction. two adjacent tunnels induced by the excavation. Dolezalova (2001)
Tunnel deformations resulted from an adjacent deep excavation are predicted the deformation and stress change in a tunnel induced by an
a common problem encountered by engineers (Cooper et al., 2002; Lu open excavation, and the computed results agreed well with the mon-
and Hanyga, 2005a; Tan et al., 2015; Chen et al., 2016; Li et al., itoring data. Zheng and Wei (2008) studied the response of existing
2017a,b; Zhang et al., 2017). Chang et al. (2001) reported a case history tunnels at three typical locations to the excavation, namely at the
in which a section of a tunnel was damaged as a result of an adjacent central line under the excavation bottom, directly under the base of the
excavation. To keep the existing tunnels from damaging, several diaphragm wall and outside of the diaphragm wall. Considering the


Corresponding author.
E-mail addresses: Lmg20066028@sjtu.edu.cn (M.-G. Li), chenjj29@sjtu.edu.cn (J.-J. Chen), wjh417@sjtu.edu.cn (J.-H. Wang), zyflisp@163.com (Y.-F. Zhu).

http://dx.doi.org/10.1016/j.tust.2017.09.014
Received 17 January 2017; Received in revised form 7 September 2017; Accepted 10 September 2017
Available online 15 September 2017
0886-7798/ © 2017 Elsevier Ltd. All rights reserved.
M.-G. Li et al. Tunnelling and Underground Space Technology 71 (2018) 329–339

asymmetric nature between the excavation and the adjacent tunnels, resistance piles are installed on the both sides of the tunnels. Dividing
three dimensional (3D) numerical simulations are needed to achieve walls are also constructed to divide the big excavation into small pits so
more accurate estimations. Through 3D simulations, Liu et al. (2011) that a single unloading volume and lateral earth pressure can be re-
analyzed various influence factors, such as the ground reinforcement duced (Wang et al., 2003; Chen et al., 2017; Li et al., 2017a,b). 24
depth, the excavation sequence and the skew angle between the new dividing walls are constructed before excavation with the spacing from
tunnel and the existing tunnels, on the deformation of underlying 6 to 8 m, as shown in Fig. 2. These small pits are grouped and the pits in
tunnels. More recently, Huang et al. (2013) studied parameters that a group are excavated simultaneously in each construction stages.
may affect the tunnel response, including the relative position of the Three level struts are designed to support the retaining walls in each
tunnel with respect to the excavation, tunnel diameter, excavation di- small pit, and soil above the third level strut is excavated in layers,
mensions, and tunnel protection measures. Until now, many numerical leaving the last layer of soil with a thickness of 3–4 m. The corre-
simulations have been carried out to simulate the excavation process sponding struts should be installed timely after each layer of soil is
and the structural response of the adjacent tunnels. However, only few excavated. In order to minimize the tunnel deformations, the last layer
focused on quantifying the effect of construction methods on the de- of soil is excavated in blocks. After the construction of base slabs is
formation of tunnels, although an appropriate construction method completed, the next construction stage can be carried out. The novel
plays an important role in practice (Ferrada and Serpell, 2014; Zhang construction method of DAEM was successfully applied in the project.
et al., 2016). Although the deformation of the underlying metro tunnels was con-
In this paper, 3D numerical simulations are performed to compare trolled within the allowable value, the efficiency of this construction
three construction methods through a case history of a deep excavation method needs to be evaluated.
located above metro tunnels. The effect of the construction method on
the excavation-induced underlying metro tunnel deformation is dis- 3. Numerical simulation
cussed and quantified. Moreover, extensive parametric studies are
conducted to optimize the novel construction method of DAEM. Numerical simulation is a feasible method to model the construction
process and capture the structural response of the metro tunnels to
2. Overview of the case adjacent excavations. In this section, the finite element (FE) software,
ABAQUS 6.10, is used to evaluate the deformation of the underlying
The investigated case was an excavation of a highway tunnel lo- metro tunnel due to soil unloading in the highway tunnel excavation
cated above an existing metro tunnel in Shanghai. The highway tunnel with the construction method of DAEM.
was constructed by the cut-and-cover method. The excavation of the
highway tunnel was 27.1 m in width and 11.5 m in depth, and the 3.1. Numerical model
crossing length over the metro tunnel is 150 m. The underlying metro
lines were composed of two shield tunnels, i.e. the inbound and the Considering the skew angle between the highway tunnel and ex-
outbound, which were excavated using earth pressure balanced (EPB) isting tunnels, it is necessary to model all existing tunnels in three-di-
shield machines. The internal diameter and the thickness of the lining mensional (3D) conditions. To eliminate the influence of boundary
structure of the tunnels were 6.2 m and 0.35 m, respectively. More conditions on numerical results, the dimensions of the model are set to
detailed information of the project was reported by Chen et al. (2015). 328 m in length, 150 m in width and 60 m in depth, as shown in Fig. 3.
Metro tunnels are the lifelines of a city and are sensitive to adjacent As for boundary conditions, the horizontal movements of nodes on the
constructions. To safeguard the safety of these lifelines, strict guidelines four side boundaries are restrained with vertical movement allowed. All
have been made for deep excavations adjacent to metro tunnels, e.g. the nodes at the bottom of the model are fixed.
construction-induced maximum vertical displacement of the tunnels The model consists of subsoil layers, retaining structures, struts,
must be controlled within 20 mm (SZ-08-2000 Shanghai Municipal slabs and tunnel linings. The soil mass is modeled by a total of 133,040
Engineering Authority, 2000). In this project, the clearance between the solid elements. The tunnel linings, slabs and retaining structures are
new highway tunnel and the existing tunnels’ crown was only 4 m, so modeled as shell elements, and the struts are simulated using beam
appropriate countermeasures were needed before and during con- elements. The structural model of the deep excavation and the under-
struction. Soil improvement is an efficient way to reduce the rebound of lying metro tunnels is presented in Fig. 4. 16,127 shell elements are
soil below the excavation surface (Wang et al., 2010). The deep soil used for modeling the tunnel linings, slabs and retaining structures. The
mixing (DSM) method was used in this project to improve the sur- struts are modeled by 1700 beam structural elements.
rounding soil (Chen et al., 2013) and the tunnels were uplifted with a
maximum value of 3.7 mm during the soil improvement process. 3.2. Input parameters
Therefore, the heave of the underlying metro tunnels caused by the
excavation must be controlled within 16.3 mm. The concrete structure units of both the shell elements and beam
To safeguard the metro tunnel, Chen et al. (2015) proposed a novel elements were modeled as an isotropic linear elastic material with a
construction method of a divided alternate excavation method (DAEM) Poisson’s ratio of 0.15. Considering stiffness reduction due to cracks in
for the project by following the time-space effect. Fig. 1 illustrates the the concrete, the stiffness of retaining walls, protecting walls, dividing
principle and concept of the DAEM by comparing to the slope excava- walls and struts is reduced by 20% (Lim et al., 2010) from the nominal
tion and the divided successive excavation. In the slope excavation as value with an input Young’s modulus of 24 GPa. To consider the in-
shown in Fig. 1(a), the influence of unloading and the unloading width fluence of joint on the stiffness, the effective rigidity ratios of the lining
is increased compared with a vertical-sided excavation method. This for circumferential and longitudinal direction are set to be 0.7 and 0.17
will increase the uplift of the underlying tunnels during a single ex- as suggested by Huang et al. (2013) and Chen et al. (2016). Thus the
cavation. In the divided successive excavation, the soil in the excava- input Young’s moduli in circumferential direction and longitudinal di-
tion is removed from one side to the other side in turn, so the con- rection for lining are 21 GPa and 5.1 GPa, respectively. For modeling
struction duration is long and the superimposed effect is significant as soil behavior in excavation, Hardening-Soil Model (HS) is now be-
shown in Fig. 1(b). To overcome the disadvantages of conventional coming prevalent among users of FEM analysis for its competence in
excavation methods and to better utilize the principle of the time-space considering stress history of soils. Nevertheless, it still has difficulties in
effect and stiffness of tunnel, the DAEM was proposed to decrease de- defining reasonable model parameters due to lack of laboratory and
formation of the metro tunnel and to shorten the construction time as field tests. A fairly simple model with credible physical parameters is
shown in Fig. 1(c). In this construction method, isolated piles and preferred (Liao et al., 2013; Ou et al., 2013; Hsieh et al., 2013). The

330
M.-G. Li et al. Tunnelling and Underground Space Technology 71 (2018) 329–339

Fig. 1. Principle and concept of the DAEM.

Fig. 2. Layout of the supporting system of the DAEM.

331
M.-G. Li et al. Tunnelling and Underground Space Technology 71 (2018) 329–339

Fig. 3. Geometry and mesh of whole model.

subsoil in the construction field is mainly soft soil comprising Qua- 3.3. Simulation process
ternary alluvial and marine deposits. In general, the soil surrounding
the metro tunnels and near the excavation surface is very soft silty clay. According to the implementation of the DAEM in the project, the
In this paper, Modified Cam-Clay Model is adopted as the constitutive excavation procedure is divided into four stages. By following principle
relationship for subsoil in the numerical analyses (Roscoe and Burland, of the time-space effect and taking advantages of the tunnel stiffness
1968). (Chen et al., 2015), the pits numbered 5, 11, 18, 20, 22, 24 and 25 are
The related parameters for Modified Cam-Clay Model are listed in excavated in the first stage and followed by the excavation of pits
Table 1, in which λ, κ and M can be obtained using Eqs. (1)–(3), re- numbered 1, 2, 3, 7, 13, 15 and 23. In the third stage, pits 6, 8, 10, 17
spectively. and 19 are excavated and the others are excavated in the final stage.
The numerical simulation procedure is consistent with the practical
Cc excavation procedure to ensure the comparability of the numerical re-
λ=
ln10 (1) sults and the field data.

Cs 3.4. Analysis of the numerical results


κ=
ln10 (2)
The main concern of the project was the deformation of the un-
derlying metro tunnels. As mentioned before, the maximum heave of
sinφ′
M= the tunnels during excavation must be controlled within 16.3 mm
3−sinφ′ (3)
owing to the heave during soil improvement prior to excavation. To
ensure the safety of the running metro tunnels, a comprehensive long-
where Cc and Cs are the compression index and rebound index respec-
term monitoring program was carried out throughout the excavation
tively. φ′ is effective friction angle of triaxial test. Poisson’s ratio (ν) can
process. Fig. 6 presents a comparison of the vertical displacements of
be set equal to 0.3.
the metro tunnels between the numerical results and the field data at
To minimize the unloading effect, soil in the pit and around the
the completion of excavation. On the whole, the heave profiles of the
excavation area is improved by the triple-shaft deep soil mixing (DSM)
tunnels recorded from the FE model follow similar patterns to those
method. Fig. 5 shows the range of the improved soil. The maximum
recorded from the field. The FE model slightly underestimates the
depth of the improved soil above the tunnel is 13.8 m. The improved
movements of the tunnels outside the excavation area. This might be
soil in the excavation range from 9.0 m below the ground surface (BGS)
due to the following reasons: (i) it is difficult to simulate the excavation
to 26.0 m BGS. The maximum depth of the improved soil outside the
process realistically since the management is easily influenced by many
excavation is 26.0 m BGS. The improved soil is assumed as elastic
factors in practice; (ii) the soil properties are significantly complex and
material, and its elasticity modulus is 240 MPa according to the em-
at present no constitutive model can model the soil behavior realisti-
pirical laboratory test results.
cally. Despite this, the predicted maximum heaves and the locations of

Fig. 4. Structural model of DAEM.

332
M.-G. Li et al. Tunnelling and Underground Space Technology 71 (2018) 329–339

Table 1
Engineering properties of the soil layers.

No. Soil layer name H (m) w (%) γ (kN/m3) e c (kPa) φ λ κ M

1 Filled soil 1.8 18.0 2.0


3 Silty clay 7.2 34.7 18.2 1.13 12 22.0 0.081 0.007 0.86
4 Very soft silty clay 8.0 48.6 16.9 1.37 14 11.5 0.142 0.012 0.43
5-1 Clay 7.0 34.2 18.2 0.98 17 19.0 0.060 0.005 0.73
6 Hard clay 6.0 22.5 19.9 0.68 49 17.0 0.035 0.003 0.65
7-1 Sandy clay 5.0 29.9 18.7 0.84 3 33.0 0.024 0.002 1.33
7-2 Fine sand > 10 27 19 0.76 0 34.5 0.019 0.002 1.40

Note: H = Average thickness, w = water content, γ = unit weight, e = void ratio, c, φ = cohesion and friction angle of direct shear test, λ and κ are the slopes of the compression line
and the swelling-recompression line, respectively, M is the stress ratio at the critical state.

Fig. 5. Range of the improved soil.

Fig. 6. Comparison between numerical prediction and mea-


sured results.

Fig. 7. Conventional excavation methods for pit above


shield tunnels.

the maximum heave are in good agreement with the field data, which are reasonable and can be used for comparative studies of the con-
provide an evidence for further study. It should be noted that the aim of struction methods for this deep excavation above shield tunnels.
this paper is to perform the comparison and optimization of construc-
tion methods for deep excavation above shield tunnels rather than to
4. Comparative studies of construction methods
evaluate the numerical method. Therefore, it can be tentatively con-
cluded that the input soil parameters used in the numerical simulation
The time-space effect in deep excavations indicates that the

333
M.-G. Li et al. Tunnelling and Underground Space Technology 71 (2018) 329–339

Table 2 the PIEM, PPEM and DAEM, respectively. Moreover, the maximum
Comparison between previous projects and this project (Chen et al., 2015). tunnel heave in each project and related key factors that influence the
response of the tunnel are also listed in this table. It can be seen from
Projects He (m) Hf (m) L (m) δ (mm) Excavation
method the table that the values of the excavation depth, clearance and the span
length vary in each case and the effectiveness of construction methods
Yanggao Rd. 7.4 7 33 13 PIEM on controlling the tunnel deformation is unclear. In order to carry out
Undercrossing
the comparative study of these construction methods, this section pre-
Subsided square at 5.0 3 38 8
Nanjing Rd. sents two hypothetical construction schemes for this deep excavation
Metro air shaft at Huaihai 9.1 7.3 50 6.5 with PIEM and PPEM, respectively. Numerical models are developed to
Rd. simulate the hypothetical construction schemes, and the tunnels’ re-
Dongfang Rd. 6.5 3 18 17 PPEM sponses caused by the three construction methods are comparatively
Undercrossing
analyzed.
Agile square 4.9 3.6 120 8.5
Xin Jinqiao square 5.0 4 38 9.8
EWRTC (this project) 11.5 4 150 14.8 DAEM
4.1. Hypothetical schemes of conventional construction methods
Note: He: excavation depth, Hf = clearance between excavation base and the tunnel
crown, L = span length, δ = tunnel heave. In the hypothetical construction scheme of PIEM, soil around the
metro tunnels is improved to reduce the deformation of both the sup-
different excavation methods will result in different responses of the porting structures in the excavation and the metro tunnels. Dividing
underlying tunnels. Other than the DAEM, there are two conventional piles and resistance piles are installed at both sides of each tunnel to
construction methods that consider the time-space effect and are also divide the whole excavation into five small pits, as shown in Fig. 8. Soil
available for deep excavation above metro tunnels. The conventional around the tunnels, i.e. in zones D1, D3 and D5, is first removed in
construction methods are the parallel isolation excavation method layers and in blocks, leaving soil in zone D2 and D4 to resist the tunnel
(PIEM) and perpendicular partitioned excavation method (PPEM), deformation during the construction. After the construction of the base
which were proposed by Lu (2002) and Li et al. (2006), respectively. slab in these three zones is completed, soil is backfilled on the base slab
Fig. 7 delineates features of the PIEM and the PPEM. In the PIEM, di- to reduce the unloading. The remaining pits above the tunnels, i.e.
viding walls are installed on both sides of each tunnel and divide the zones D2 and D4, are excavated simultaneously. Since soil unloading
whole excavation into several small pits, as shown in Fig. 7(a). Soil in above metro tunnels has a serious impact, a layer of soil in zones D2 and
zone A1 and zone A3 are excavated simultaneously in layer and in D4 is removed first. Then the remaining soil is divided into seven
block, leaving zone A2 to resist the tunnel heave. After construction in segments based on the width of the zones D2 and D4 and these strips
zone A1 and zone A3 is finished, zone A2 is excavated in strips (Lu, are excavated alternately from the middle to the sides. After the com-
2002). In the PPEM, dividing walls should not be constructed since the pletion of each excavated block, the shaped steels inside the protecting
longitudinal retaining walls are close to the tunnel structure. To reduce walls at both sides of the tunnel are pulled out and then the base slab is
the tunnel heave, the overlying excavation is constructed in strips, and constructed immediately. To prevent further uplift of the tunnels, the
each strip is perpendicular to the axis of the tunnel, as shown in base slabs should be backfilled when their strength reaches a certain
Fig. 7(b). These small strips are so small that the principles of “time- value. Then the excavation of the next block can be carried out. After
space effect” and “tunnel stiffness” are better utilized (Li et al., 2006). the construction of all the base slabs is completed, the inner wall and
Table 2 lists several projects in practice, which were constructed by the roof are constructed in turn.
In the hypothetical construction scheme of PPEM, resistance piles

Fig. 8. Parallel Isolation Excavation Method (PIEM) for the


case history.

334
M.-G. Li et al. Tunnelling and Underground Space Technology 71 (2018) 329–339

Fig. 9. Perpendicular Partitioned Excavation Method


(PPEM) for the case history.

Fig. 10. Structural model of PIEM.

Fig. 11. Structural model of PPEM.

are installed at both sides of each tunnel and the soil around the tunnels transverse direction of the pit. After construction of each strip is com-
is also improved to resist the tunnel heaves during excavation. The pleted and the base slab is reloaded, excavation of the next strip can be
excavation process is illustrated in Fig. 9. The first layer of soil is re- carried out. When the construction of all the base slabs is completed,
moved as a whole. Then the excavation proceeds longitudinally from the inner walls and the roofs are constructed in sequence.
one side to the other with slope excavation. During excavation, the
struts should be installed timely. Since the crossing length over metro 4.2. Numerical simulation of conventional construction methods
tunnels is 150 m, the pit is excavated in 41 small strips with the width
about 3 m, as shown in Fig. 9. Since the width of the excavation is 27 m, Based on the hypothetical construction scheme of PIEM, a related
each small strip should be divided into several blocks along the numerical model is built in the FE software. The geometry of the soil

335
M.-G. Li et al. Tunnelling and Underground Space Technology 71 (2018) 329–339

Fig. 12. Comparison of base heaves using different construction schemes: (a) DAEM, (b) PIEM, (c) PPEM.

model of PIEM is the same as that of DAEM, while their supporting schemes. It can be seen that the maximum base heave of all the schemes
systems are different, as shown in Fig. 10. In the model of PIEM, a total are located right above the existing tunnels. In the PIEM construction
of 142,186 solid elements are used for the subsoil mass. 11,300 shell scheme, the base heave is noticeable larger than the other construction
elements are used for tunnel linings, slabs and retaining walls, dividing schemes with a maximum heave of 27.0 mm. The base heaves of the
piles and resistance piles. The struts are modeled by 1299 beam ele- DAEM and PPEM are well controlled with the maximum heave values
ments. Both the constitutive model and input parameters of soil and of 16.9 mm and 21.1 mm respectively. In DAEM and PPEM construction
structure element used in this model are the same as those in the model schemes, the whole excavation is divided into dozens of small parts.
with construction scheme of the DAEM. After the excavation of each part is finished, the bottom slab is con-
The numerical model for the construction scheme of PPEM is built structed and the base of this part is reloaded. Thus the soil rebound can
in ABAQUS 6.10 with same geometry as those in previous models. The be restrained and the heaves of the underlying tunnels are reduced
layout of the retaining structures and the tunnels is shown in Fig. 11. A consequently.
total of 162,601 solid elements are used for the soil mass, and 13,190 Fig. 13 illustrates a comparison of the structural responses of the
shell elements are used for tunnel linings, slabs, retaining walls and metro tunnels to the deep excavation constructed by DAEM, PIEM, and
resistance piles. The struts are modeled by 992 beam elements. Both the PPEM. Although the uplifted metro tunnels have similar profiles, the
constitutive model and parameters are the same as those in the nu- tunnel heaves caused by excavation using different construction
merical models with the construction scheme of DAEM and PIEM. methods are different in magnitude. The maximum heave caused by the
excavation with DAEM is noticeably smaller than that caused by the
excavation with PIEM and PPEM, which confirms the ability of the
4.3. Results and analysis
DAEM in controlling the deformation of the metro tunnels located
under excavations.
Fig. 12 shows a comparison of the vertical displacement contours at
To further understand the process of excavation-induced uplift of
the completion of the excavation between different construction

336
M.-G. Li et al. Tunnelling and Underground Space Technology 71 (2018) 329–339

Fig. 13. Comparison of tunnel heaves using different con-


struction schemes.

Table 3 less. In construction schemes of PPEM and DAEM, the unloading vo-
Tunnel heaves caused by each construction stage. lume of soil in the first stage is almost the same as those in the second
stage. However, the magnitude of excavation-induced underlying
Construction method PIEM PPEM DAEM
tunnel heave in the first construction stage is larger than that in the
Construction stage Stage1 Stage2 Stage1 Stage2 Stage1 Stage2 second construction stage. Note that the maximum rebounds of the
underlying tunnels, with construction schemes of PIEM, PPEM and
Maximum heave (mm) 7.3 22.5 18.8 19.5 9.6 14.9
DAEM, are 22.5 mm, 19.5 mm and 14.9 mm, respectively. Since the
maximum tunnel heave must be controlled within 16.3 mm, only the
underlying metro tunnels, each construction scheme is divided into two DAEM construction scheme can be used in this project.
stages. In PIEM construction scheme, the first construction stage in-
cludes excavation of zones D1, D3 and D5 and excavation of the re- 5. Parametric studies of DAEM
maining zones is the second construction stage. In PPEM construction
scheme, excavation of the first strip to the 21th strip is the first con- 5.1. Effect of each small pit on tunnel heave
struction stage and excavation of the remaining strips is the second
construction stage. For DAEM construction scheme, excavation of the In DAEM, dividing walls are constructed to divide the excavation
odd-numbered pits is the first construction stage and excavation of the into twenty-five small pits and each pit can be excavated in-
even-numbered pits is the second construction stage. Table 3 lists the dependently. In this section, twenty-five 3D numerical simulations are
maximum tunnel heaves after each construction stage of the three conducted to study the impact of each small pit on the tunnels. Fig. 14
construction schemes. Results of PIEM construction scheme reveal that illustrates the maximum heave of the inbound and outbound caused by
the excavation right above the tunnels (D2 and D4) causes larger tunnel excavation of each independent pit. It can be seen from this figure that
heaves than the removing of soil around the tunnels (D1, D3 and D5), the responses of the inbound and outbound to excavations are similar.
even though the unload volume of soil right above the tunnels is much Despite the same unloading volume, the excavation right above the
tunnels causes the greatest influence on the tunnels and it decreases

Fig. 14. Tunnel heave caused by excavation of each in-


dependent small pit.

337
M.-G. Li et al. Tunnelling and Underground Space Technology 71 (2018) 329–339

Table 4 increased gradually with the increase of the distance between the
Tunnel heaves with different dividing wall intervals. tunnels and the small pits. Fourth, simultaneous excavation of alternate
small pits is suggested because it can save construction duration sig-
Wall intervals 6m 12 m 18 m 24 m
Tunnel heaves (mm) Inbound 14.9 15.5 16.0 16.2 nificantly. As more and more metro lines have built in the cities, ex-
Outbound 14.6 15.6 15.8 16.0 cavations adjacent to tunnels will be frequently encountered by en-
gineers in practice and the clearance between the excavation and the
tunnels will become smaller. To minimize the excavation-induced
nonlinearly with the increase of distance between the small pits and the tunnel deformation, additional construction measures are needed in the
tunnels. Therefore, the excavation scheme of the small pit right above DAEM.
the tunnels should be improved for further optimization of the DAEM.
7. Conclusions and suggestions
5.2. Effect of excavation procedure
This paper presents a numerical study on excavation-induced de-
To further reduce the excavation-induced tunnel heave, the con- formation of underlying metro tunnels. 3D numerical simulations are
struction scheme needs to be optimized. Four excavation schemes are conducted to model three construction methods for a case history of a
designed with different grouping and excavation sequence. In this first deep excavation located above metro tunnels. Moreover, parametrical
excavation scheme, these twenty-five small pits are excavated si- studies are carried out to analyze the key factors of DAEM on the ex-
multaneously. In the second excavation scheme, these twenty-five small cavation-induced structural deformation of underlying metro tunnels.
pits are divided into two groups, i.e. the odd-numbered pits in the first Based on the numerical analyses, following conclusions can be drawn.
group and the even-numbered pits in the second group, and the two
groups are excavated successively. In the third excavation scheme, the (1) Comparative analyses indicate that tunnel deformation due to
small pits are divided into four groups with the pits numbered 1, 5, 9, above unloading is closely related to the excavation methods. The
13, 17, 21, 25 in the group one, the pits numbered 2, 6, 10, 14, 18, 22 in maximum vertical displacements of the metro tunnels caused by
group two, the pits numbered 3, 7, 11, 15, 19, 23 in group three and the construction schemes of PIEM, PPEM and DAEM are 22.5 mm,
pits numbered 4, 8, 12, 16, 20, 24 in group four, respectively. In this 19.5 mm and 14.9 mm, respectively. Comparing to the PIEM and
excavation scheme, the small pits are excavated in turn from group one PPEM, the DAEM shows a better efficiency in controlling the tunnel
to group four. In the fourth excavation scheme, the small pits are deformation by following the time-space effect and taking the ad-
grouped as in the third excavation scheme and the four groups are vantage of the tunnel stiffness.
excavated in order of group one, group three, group two and group (2) Parametric studies reveal that unloading right above the tunnels
four. causes greatest influence on the tunnel deformations and the in-
The maximum tunnel heave caused by excavations using different fluence decreases nonlinearly with the increase of distance between
excavation procedures are 15.8 mm, 15.0 mm, 14.7 mm and 13.9 mm the pits and the tunnels. The deformation of the underlying tunnels
respectively. It indicates that all the four excavation schemes can be can be well controlled if the small pits are divided into several
adopted to control the tunnel deformation with allowable value and the groups with these groups excavated alternately. The maximum
construction risk is the lowest using the fourth excavation scheme, in tunnel heaves increase slightly with the increase of the dividing
which the small pits are divided into four groups with these groups wall interval.
excavated alternately. (3) Based on the numerical analysis, suggestions can be proposed for
similar projects in the future. The DEAM has priority over the PIEM
5.3. Effect of dividing wall interval and the PPEM regardless of the construction cost. The interval of
dividing walls right above the tunnels should be as small as possible
In the DAEM construction scheme, dividing walls are constructed to so that a single unloading volume can be reduced. To save con-
resist the tunnel deformation. In order to thoroughly understand the struction cost, the interval of the other dividing walls can be in-
effect of the dividing walls, four simulations are conducted with di- creased gradually with the increase of the distance between the
viding wall intervals of 6 m, 12 m, 18 m and 24 m, respectively. Table 4 tunnels and the small pits. Simultaneous excavation of alternate
lists the numerical results of the maximum metro tunnel heaves at the small pits is suggested because it can save construction duration
completion of excavation. As expected, the magnitude of the maximum significantly.
tunnel heaves increases with the increase of the dividing wall interval.
However, the effect of the wall interval on the tunnel heave is insig- Acknowledgements
nificant. This might be attributed to the fact that all the investigated
intervals were within the ranges of spatial effect. The financial support from the National Natural Science Foundation
of China (NSFC Grant No. 41602283, 41372282, 41330633) is grate-
6. Suggestions for optimization of the construction method fully acknowledged.

Although the DAEM contributes to controlling the excavation-in- References


duced deformation of the underlying shield tunnels, the construction
cost of the DAEM might be higher than those of the PIEM and PPEM ABAQUS [Computer software]. ABAQUS user manual, ABAQUS.
because of the installation of the dividing walls. To balance the cost and Chai, J.C., Shen, S.L., Ding, W.Q., Zhu, H.H., Carter, J., 2014. Numerical investigation of
the failure of a building in Shanghai, China. Comput. Geotech. 55, 482–493.
effect, some recommendations for deep excavations above shield tun- Chang, C.T., Sun, C.W., Duann, S.W., Hwang, R.N., 2001. Response of a Taipei Rapid
nels can be proposed based on the numerical studies and construction Transit System (TRTS) tunnel to adjacent excavation. Tunn. Undergr. Space Technol.
experience in practice. First, regardless of the construction cost, the 16 (3), 151–158.
Chen, J.J., Wang, J.H., Xiang, G.W., Wen, S.L., Du, Y., 2011. Numerical study on the
DEAM has priority over the PIEM and the PPEM. Second, the interval of movement of existing tunnel due to deep excavation in Shanghai. Geotech. Eng. J.
dividing walls right above the tunnels should be as small as possible so SEAGS & AGSSEA 40 (3), 30–40.
that a single unloading volume can be reduced. However, according to Chen, J.J., Zhang, L.Y., Zhang, J.F., Zhu, Y.F., Wang, J.H., 2013. Field tests, modification,
and application of deep soil mixing method in soft clay. J. Geotech. Geoenviron. Eng.
previous construction experiences, the interval should not be less than 139 (1), 24–34.
6 m considering the operability of the equipment in construction. Third, Chen, J.J., Zhu, Y.F., Li, M.G., Wen, S.L., 2015. Novel excavation and construction
to save construction cost, the interval of the other dividing walls can be method of an underground highway tunnel above operating metro tunnels. J. Aerosp.

338
M.-G. Li et al. Tunnelling and Underground Space Technology 71 (2018) 329–339

Eng. 28 (6), A4014003. Lu, J.F., Hanyga, A., 2005a. Wave field simulation for heterogeneous porous media with
Chen, R.P., Meng, F.F., Li, Z.C., Ye, Y.H., Ye, J.N., 2016. Investigation of response of singular memory drag force. J. Comput. Phys. 208 (2), 651–674.
metro tunnels due to adjacent large excavation and protective measures in soft soils. Lu, J.F., Hanyga, A., 2005b. Fundamental solution for a layered porous half space subject
Tunn. Undergr. Space Technol. 58, 224–235. to a vertical point force or a point fluid source. Comput. Mech. 35 (5), 376–391.
Chen, J.J., Li, M.G., Wang, J.H., 2017. Active Earth pressure against rigid retaining walls Ng, C.W., Shi, J.W., Hong, Y., 2013. Three-dimensional centrifuge modelling of basement
subjected to confined cohesionless soil. Int. J. Geomech. 17 (6). excavation effects on an existing tunnel in dry sand. Can. Geotech. J. 50, 874–888.
Cooper, M.L., Chapman, D.N., Rogers, C.D.F., Chan, A.H.C., 2002. Movements in the Ng, C.W.W., Shi, J.W., Masin, D., Sun, H.S., Lei, G.H., 2015a. Influence of sand density
Piccadilly Line tunnels due to the Heathrow Express construction. Geotechnique 52 and retaining wall stiffness on three-dimensional responses of tunnel to basement
(4), 243–257. excavation. Can. Geotech. J. 52 (11), 1811–1829.
Dolezalova, M., 2001. Tunnel complex unloaded by a deep excavation. Comput. Geotech. Ng, C.W.W., Sun, H.S., Lei, G.H., Shi, J.W., Masin, D., 2015b. Ability of three different soil
28, 469–493. constitutive models to predict a tunnel's response to basement excavation. Can.
Ferrada, X., Serpell, A., 2014. Selection of construction methods for construction projects: Geotech. J. 52 (11), 1685–1698.
a knowledge problem. J. Constr. Eng. Manage. 140 (4), B4014002. Ou, C.Y., Hsieh, P.G., Lin, Y.L., 2013. A parametric study of wall deflections in deep
Hsieh, P.G., Ou, C.Y., Lin, Y.L., 2013. Three-dimensional numerical analysis of deep ex- excavations with the installation of cross walls. Comput. Geotech. 50, 55–65.
cavations with cross walls. Acta Geotech. 8 (1), 33–48. Roscoe, K.H., Burland, J.B., 1968. On the generalized stress–strain behaviour of ‘wet’ clay.
Hu, Z.F., Yue, Z.Q., Zhou, J., Tham, L.G., 2003. Design and construction of a deep ex- In: Heyman, J., Leckie, F.A. (Eds.), Engineering Plasticity. Cambridge University
cavation in soft soils adjacent to the Shanghai Metro tunnels. Can. Geotech. J. 40 (5), Press, pp. 535–609.
933–948. Shanghai Municipal Engineering Authority, 2000. Specification for excavation in
Huang, A.J., Wang, D.Y., Wang, Z.X., 2006. Rebound effects of running tunnels under- Shanghai metro construction. SZ-08-2000, Shanghai, China (in Chinese).
neath an excavation. Tunn. Undergr. Space Technol. 21 (3), 399. Sharma, J.S., Hefny, A.M., Zhao, J., Chan, C.W., 2001. Effect of large excavation on de-
Huang, X., Schweiger, H.F., Huang, H.W., 2013. Influence of deep excavations on nearby formation of adjacent MRT tunnels. Tunn. Undergr. Space Technol. 16 (2), 93–98.
existing tunnels. Int. J. Geomech. 13 (2), 170–180. Son, M., Cording, E.J., 2005. Estimation of building damage due to excavation-induced
Li, Z.G., Liu, G.B., Zeng, Y., Wu, X.J., 2006. Control measures of tunnel displacement by ground movements. J. Geotech. Geoenviron. Eng. 131 (2), 162–177.
over-excavation unloading. Chin. J. Undergr. Space Eng. 2 (3), 430–433. Tan, Y., Li, X., Kang, Z.J., Liu, J.X., Zhu, Y.B., 2015. Zoned excavation of an oversized pit
Li, M.G., Chen, J.J., Xu, A.J., Xia, X.H., Wang, J.H., 2014. Case study of innovative top- close to an existing metro line in stiff clay: case study. J. Perform. Constr. Facil. 29
down construction method with channel-type excavation. J. Constr. Eng. Manage. (6), 04014158.
140 (5), 05014003. Wang, J.H., Zhou, X.L., Lu, J.F., 2003. Dynamic response of pile groups embedded in a
Li, M.G., Chen, J.J., Wang, J.H., 2017a. Arching effect on lateral pressure of confined poroelastic medium. Soil Dynam. Earthq. Eng. 23 (3), 53–60.
granular material: numerical and theoretical analysis. Granul. Matt. 19 (2), 20. Wang, J.H., Xu, Z.H., Wang, W.D., 2010. Wall and ground movements due to deep ex-
Li, M.G., Zhang, Z.J., Chen, J.J., Wang, J.H., Xu, A.J., 2017b. Zoned and staged con- cavations in shanghai soft soils. J. Geotech.Geoenviron. Eng. 136 (7), 985–994.
struction of an underground complex in Shanghai soft clay. Tunn. Undergr. Space Zhang, Z.G., Huang, M.S., Wang, W.D., 2013. Evaluation of deformation response for
Technol. 67, 187–200. adjacent tunnels due to soil unloading in excavation engineering. Tunn. Undergr.
Liao, S.M., Fan, Y.Y., Shi, Z.H., Shao, W., Kong, X.P., 2013. Optimization study on the Space Technol. 38, 244–253.
reconstruction and expansion of an underground rail transit center in Shanghai soft Zhang, L.M., Wu, X.G., Liu, H.T., 2016. Strategies to reduce ground settlement from
ground. Tunn. Undergr. Space Technol. 38, 435–446. shallow tunnel excavation: a case study in China. J. Constr. Eng. Manage. 142 (5),
Lim, A., Ou, C.Y., Hsieh, P.G., 2010. Evaluation of clay constitutive models for analysis of 04016001.
deep excavation under undrained conditions. J. Geoeng. 5 (1), 9–20. Zhang, Z.J., Li, M.G., Chen, J.J., Wang, J.H., Zeng, F.Y., 2017. Innovative construction
Liu, H.L., Li, P., Liu, J.Y., 2011. Numerical investigation of underlying tunnel heave method for oversized excavations with bipartition walls. J. Constr. Eng. Manage. 143
during a new tunnel construction. Tunn. Undergr. Space Technol. 26 (2), 276–283. (8), 04017056.
Lu, H.W., 2002. Design of foundation pit of protection segment of grade separation metro Zheng, G., Wei, S.W., 2008. Numerical analyses of influence of overlying pit excavation
under Yanggao Road in Century Avenue. Urban Roads Bridges Flood Control 2, 44–48 on existing tunnels. J Centr. South Univ. Technol. 15, 69–75.
(in Chinese).

339

You might also like