You are on page 1of 24

Geotech Geol Eng

https://doi.org/10.1007/s10706-020-01353-y (0123456789().,-volV)
( 01234567
89().,-volV)

ORIGINAL PAPER

Three-Dimensional Simulation of Interaction Between


Surface Buildings and Twin Tunnelling Regarding
the Surface Settlement
A. Mirhabibi . A. Soroush

Received: 5 February 2016 / Accepted: 11 May 2020


 Springer Nature Switzerland AG 2020

Abstract Tunneling-induced strain and stress distri- Keywords Twin tunnels  Tunnel–building
bution in a soil medium is completely three dimen- interaction  3D finite element modeling  Assessment
sional. However, the issue is usually modeled in two- of 2D elastic beam method
dimensions (2D) in order to lower the computational
costs. In this study, full three-dimensional (3D) finite
element (FE) analysis of twin tunnelling and surface
building are carried out to compare the results with 2D 1 Introduction
ones and to find out surface settlement behavior during
tunneling process considering the presence of a Tunneling-induced strain and stress distribution in a
building on the surface. Conducting 3D FE parametric soil medium is completely three dimensional (3D).
studies, a large database is created and the results are This issue is usually simulated by two dimensional
used to evaluate different aspects of 3D modeling. (2D) models due to computational limitations. In 2D
Based on the outcomes of this study, comparison simulations, common simplified plane strain condi-
between 2D and 3D modeling is conducted, the tions are assumed and the surface buildings are
situations in which 3D analysis could be substituted modeled by an elastic surface beams (Mirhabibi and
by 2D plane strain models and the cases in which 3D Soroush 2012). This simplifications would result in
modeling is necessary are defined. The effects of some limitations i.e. length, height and internal walls
different parameters on surface settlement trough are of building could not be realistically modeled in the
assessed and a modification design graph for predic- equivalent surface beam and also 3D effects of
tion of maximum 3D building settlement from 2D tunneling could not be simulated accurately.
green-field analysis is suggested. Augrade (1997), Liu (1997), Netzel and Kaalberg
(2000) and Bloodworth (2002) investigated the inter-
action between tunneling and masonry buildings by
conducting some 3D numerical simulations. The
buildings were simulated using a façade box and no-
A. Mirhabibi (&)
Islamic Azad University, Parand Branch, Parand, Iran tension model was utilized for the masonry walls. Dias
e-mail: a_mirhabibi@piau.ac.ir and Kastner (2002) and Jenck and Dias (2004)
investigated the effect of multistory framed structure
A. Soroush
on the tunnel-induced ground settlement. The build-
Department of Civil and Environmental Engineering,
Amirkabir University of Technology, Hafez Street, ings were modeled by elastic columns supporting
Tehran, Iran floors assuming elastic properties.

123
Geotech Geol Eng

Shin et al (2002) used a pseudo-three-dimensional of building wall position with respect to tunnel axis.
analysis of tunnel construction and the results were Son (2016) with conducting numerical analysis inves-
compared with 2D analyses and field data. They also tigated the structural response of buildings to tunnel-
modeled green field conditions (cases in which no ing in clay considereing different conditions of tunnel
building presents at the surface; denoted by GF). and structure. Houhou et al. (2016) studied the
In some 3D studies, the influence of surface interaction of tunnel and building with help of 3D
building on tunnel-building interaction has been numerical analysis and comparing the results with
simulated utilizing surface elastic beam theory which field data.
could be considered as an extension of surface beam As reviewed, using three-dimensional (3D) simu-
theory commonly used in 2D analyses (Franzius 2003; lations, the actual conditions could be restored and
Franzius and Potts 2005; Pickhaver 2006; Dimmock consequently more accurate results could be achieved.
and Mair 2008). However, in common practices, two-dimensional (2D)
Devriendt et al (2010) conducted a 3D analysis of models are usually utilized due to lower computational
interaction between demolition of an existing building costs. Therefore, it could be useful if 3D and 2D
and a shallow tunnel to evaluate the effect of analysis are compared and the differences between
excavation and reloading of a surface structure on these approaches be studied to have a more clear
the displacement of existing tunnel. The results of understanding of differences between these modeling
numerical models were compared with field data. approaches. In past studies a comprehensive compar-
Maleki et al. (2011) studied the effect of structural ison between 2D and 3D simulation is rarely found
characteristics of surface buildings on the tunnel- which is tried to be performed in this study.
building 3D model interaction in which the surface In this research, the effects of different mechanical
buildings were modeled with two methods; equivalent and geometrical parameters in tunnel-building inter-
beam and real geometry. Liu et al. (2012) conducted action are studied using full 3D finite element (FE)
parametric 3D analysis to study the interaction simulations and differences between 2D and 3D
between a surface building and enlargement of a modeling is evaluated.
metro station. The building was modeled by beam The main goal is to assess in which cases the 2D
elements and the building weight was applied to the models are accurate enough and in which conditions 3D
model. Losacco et al. (2014) introduced an approxi- models should be inevitably adopted despite the fact
mate procedure for the evaluation of the damage that they need great computational resources. Besides,
induced on existing buildings by the excavation of a this article seeks to find the answer to the question that
tunnel. They carried out a series of 3D numerical whether by increasing the length of building in the third
analyses of the excavation of an EPB tunnel; which direction, could 2D plane strain models to be a
include either the simplified or the fully detailed suitable alternative for 3D models or not?
structural model of a masonry building. Do et al. The outcomes of this study are expressed in both
(2014) performed 3D green field numerical investiga- qualitative (Sect. 3) and quantitative (Sect. 4). The
tion to evaluate the impact of a new tunnel construc- results of 2D analysis presented in this article are from
tion on an existing tunnel and influence of the lagged a previous study by Mirhabibi and Soroush (2012).
distance between the two tunnels. Chakeri et al (2014)
investigated the effects of different parameters on
point of inflexion value of surface settlement trough in 2 Numerical Modeling
3D green field situation. Fu et al (2014) analyzed a
case study on the response of the ground and a group of 2.1 Bases of Parametric Studies and the Studied
buildings to the construction of twin tunnel. Results of Parameters
field data proved an evident soil structure interaction.
Katebi et al (2015) investigated influence of soil, The results presented in this study is based on
tunnel and building properties on tunnel lining loads numerical modeling by ABAQUS software using field
conducting 2D & 3D models. Camos and Molins data of Shiraz metro line 1 twin tunnels and is a
(2015) studied interaction between building damage complementary work on previous studies of Mirhabibi
and tunneling-induced ground subsidence and effect and Soroush (2012, 2013).

123
Geotech Geol Eng

Shiraz metro line 1 has a length of 24.2 km while Consequently, only this configuration is considered
15 km length of this line is constructed by using two in this study (Fig. 2) and other cases (asymmetry
Tunnel Boring Machines (TBMs). Horizontal dis- building location at the surface) are not reviewed due
tances between centerlines of the tunnels range to the high computational costs.
between 13 and 17 m with varying depth up to 23 m. Besides, the length of building (in the third
Geologically, the surrounding ground mainly con- direction; L) is added to the set of parameters. The
sists of lean clay (CL) with alternating sandy clay and advantage of the chosen geometry (with regards to
silt layers. A geological cross section along the tunnel Fig. 2) is the symmetry of models along the center line
route is shown in Fig. 1. Mechanical properties of the allowing to model only half of the geometry, which
dominant soil (CL) and lining concrete, utilized in the will result in a significant reduction in computational
numerical simulations, are shown in Table 1; the soil cost.
deposit is assumed homogeneous and isotropic. The Table 2 presents the parameters and their values
Mohr–Coulomb elasto plastic model was employed to considered in this study. Full factorial combinations of
define behavior of the soil, and an elastic behavior was these values leads to 288 different cases. Among of
considered for the tunnels liner and building material. these cases, results of 125 models which have been
The effect of constitutive model on the results of this studied in this article (Table 3).
study is explored in Sects. 3, 4. Boundary conditions, element types, and mesh
Mirhabibi and Soroush (2012) studied the effects of density of the numerical models were selected based
seven parameters on the interaction between twin on several sensitivity analyses to make sure that they
tunnels and surface buildings in 2D analysis. These will not influence the results. The buildings model is
parameters were Tunnel depth (Z0), Center to center explained in detail by Mirhabibi and Soroush (2013).
distance of the twin tunnels (D0), Building width (B), The surrounding soil was discretized by 20-node brick
Building stiffness (EI), Edge to edge surface distance quadratic reduced integration element (C3D20R) and
between buildings, Building weight and geometric building was rigidly connected to the soil.
location of building on the surface relative to tunnels. Since the simulation procedure is the same as
Results of that study showed that locating the building described by Mirhabibi and Soroush (2013), the
at symmetry line of tunnels will have the most effects verification of the numerical model is the same and
on tunnel-building interaction, i.e. in this case, the consequently not presented here.
effects of other parameters are most evident.

Fig. 1 General layout of Shiraz metro line 1(SURO 2003)

123
Geotech Geol Eng

Table 1 Material Clayey soil (CL) Tunnel liner concrete


properties used in numerical
simulations Unit weight, c, (kN/m3) 17 24
Saturated unit weight, csat , (kN/m3) 20.7 –
Total cohesion, Cu, (kN/m2) 100 –
Effective cohesion, C, (kN/m2) 10 –
Total friction angle, /u , degree 0 –
Effective friction angle, /0 , degree 30 –
Young’s modulus, E, (MPa) 20 33,700
Poisson’s ratio, m 0.25 0.2

EI

Length
B
Z0
Pillar Width

D0

Fig. 2 Illustration of the studied geometry and the parameters reviewed (The model is symmetrical relative to the center line)

2.2 Modeling Steps (TBM Advance Simulation) urban areas and therefore different buildings exist on
the surface, which are influenced by tunnelling.
15 km of Shiraz metro line 1 is constructed by using Considering TBM working procedure, the tunnel
two TBMs each with a cutting-wheel diameter of construction and with presence of building is simu-
6.9 m and a shield with external diameter of 6.88 m. lated in different steps in numerical models. In the first
For lining of the tunnels, 30-cm-thick precast concrete step, geostatic stresses are employed and then, the
segments with a length of 140 cm are installed just building and its weight are switched on at the same
behind the shield. The tunnels pass through different time in the FE model. Afterward the tunnel

123
Geotech Geol Eng

Table 2 Factors and their values used in 3D-parametric studies


Parameter Description Values

Z0 (m) Tunnel’s center depth 13.5, 18.5, 23.5 (Based on Shiraz metro line 1 elevation)
D0 (m) Distance between centerlines of twin 15, 22, 29 (corresponding to pillar width of 1, 2 and 3 times of tunnel diameter;
tunnels 1D, 2D, 3D)
B (m) Building’s width 10, 20, 40, 80
EI Building’s bending stiffness Corresponding to 3, 5, 10 and 15storey concrete buildings
L (m) Building’s length in the third 20, 40
direction

construction is modeled in a number of steps simulat- excavation face at the final step. The sum of these
ing the tunnel pass through the building. numbers is 100 m. Figure 5 illustrates the components
In each step, the cutter head excavates the ground in of third dimension of 3D numerical models. Reduction
1.4 m length while the face pressure is applied to the of this length might cause the boundary implications
excavated face in order to balance the earth pressure on the results or inability to fully model the tunnelling
(Fig. 3). Behind the cutter head, a shield with a length procedure. Conversely, increasing the third dimension
of 9.1 m exists which restricts the deformation of will result in excessive computational costs.
excavated surface to the shield position. Behind the Figure 6 presents the adequacy of model length in
shield, pressurized grout is injected into the annular third direction. As illustrated, by progress of tun-
gap between the segmental lining and the excavated nelling from the front of model (number of steps in the
ground surface. As the grout hardens, the pressure Fig. 6 indicates the number of excavation steps and
diminishes and solid grout plus lining start to interact consequently the tunnel construction progress), the
with the surrounding soil. This procedure is modeled results of surface settlements have converged at the
according to Shiraz metro line 1 characteristics as front and also at the end of the 3D model which proves
shown schematically in Fig. 3. Figure 4 shows a that there is no boundary effect on the results and the
sample image of ABAQUS model. In the model, boundaries are far enough to allow the steady state.
tunnel construction begins by enough distance from
building (Fig. 5), passes beneath the building and goes 2.4 Modeling of Surface Buildings
enough distance beyond the building. Therefore, all
effects of tunneling process on the surface building Mirhabibi and Soroush (2013) showed that in order to
could be evaluated. get the most reliable results, especially for longitudi-
nal profile of settlement, it is better to model the
2.3 Assessment of Adequacy of the Third building as realistically as possible i.e. simulation of
Dimension in the Numerical Model the building by structural components accompanied
by exterior walls and partition-walls distributed in
In 3-dimensional models it is essential to consider an typical distances close to reality. Figure 7 presents the
appropriate dimension for longitudinal length of the typical floor plans of this type of building modeling for
model to prevent the effects of boundaries on the various widths of buildings considered in this study.
results. Regarding the geometrical specifications of
this study, the distance of front boundary and the 2.5 Computation Resources
building is considered to be 20 m i.e. around three
times the tunnel diameter. Moreover, about 14 m (two As discussed, considering the symmetry of models,
times the tunnel diameter) is considered for the only half of each model was simulated to reduce the
distance between the end of the longest building (with computational costs. The number of elements in the
40 m length) and the hardened grout. One diameter models varied between 17,500 and 30,000. Due to the
distance is also considered between rear boundary and huge number of elements and large number of

123
123
Table 3 Cases analyzed in 3D-parametric studies; marked by ‘‘•’’
Depth 3 Storey 5 Storey 10 Storey 15 Storey
and
pillar B = 10 B = 20 B = 40 B = 80 B = 10 B = 20 B = 40 B = 80 B = 10 B = 20 B = 40 B = 80 B = 10 B = 20 B = 40 B = 80
width
of
tunnels

Length = 20 m 13.5-1D • • • • • • • • • • • • • • •
13.5-2D • • • • • • • • • • • • • • •
13.5-3D • • • • • • • • • • • • • • •
18.5-1D • • • • •
18.5-2D • • • • • • • • • • • • • • •
18.5-3D • • • • •
23.5-1D • • • • •
23.5-2D • • • • •
23.5-3D • • • • •
Length = 40 m 13.5-1D • • • • • • •
13.5-2D • • • • • • •
13.5-3D • • •
18.5-1D • • •
18.5-2D • • • • • • •
18.5-3D • • •
23.5-1D • • •
23.5-2D • • •
23.5-3D • • •
Note: The term of ‘‘13.5-1D’’ refers to the case in which the tunnel’s depth is 13.5 m and pillar width of tunnels is one times of tunnel diameter (1D) i.e. distance between centerlines
of tunnels is 15 m. All other terms in the table could be defined accordingly with reference to Table 2
Geotech Geol Eng
Geotech Geol Eng

Fig. 3 Schematic procedure of twin TBM’s running at Shiraz metro line 1

Fig. 4 Sample image of TBM simulation in numerical models

modeling steps (60 steps in each case), the normal Amirkabir University of Technology (AUT) has a
computers were not capable of simulating the models. power of 34,000 billion operations per second. Using
Consequently, Amirkabir university super-computer this super-computer, the average running time was
was utilized to run the models. Super-computer of between 15 and 20 h with a huge volume of data.

123
Geotech Geol Eng

Fig. 5 Components of the third dimension of 3D models

Fig. 6 Illustration of changes settlement profile in the longitudinal direction while tunnels go forward (excavation face is shown for
each step)

123
Geotech Geol Eng

B=10m B=80m

B=20m B=40m

Fig. 7 Typical floor plans used in the analyses for various assumed building’s widths

3 Qualitative Assessment of Influence simulations to assess tunnelling effects on the surface


of Parameters buildings may not be conservative.

Conducting parametric studies (Table 3); the results 3.1 Tunnels Depth (Z0)
are presented in this section in a qualitative manner in
which the trends and not the values are reviewed. In As illustrated in Fig. 8, increase of tunnels’ depth
the next section, the results will be analyzed with a leads to decrease of tunnelling effects on building
quantitative approach. settlement. It is evident by comparing the settlement
Outcomes of this study indicated that, generally the troughs’ change as the tunnel depth increases from
effects of different parameters on surface settlement 13.5 to 18.5 m and from 18.5 to 23.5 m. However, the
trough in 3D analysis are the same as two-dimensional order of settlement values in all depths is the same and
ones. However, predicted settlement by three-dimen- consequently the tunnel depth is not a major parameter
sional models is higher than two-dimensional plane in tunnel-building interaction.
strain ones and as a result, relying on 2D plane strain Besides, comparison of 3D and 2D analyses’ results
reveals that three-dimensional modeling predicts

123
Geotech Geol Eng

Fig. 8 Changes of cross Distance from Symmetry Line (m)


sectional settlement trough 2
due to changes of tunnels Building
depth 0
0 20 40 60 80 100 120
-2

Selement (mm)
Depth23.5 - 3D Modelling
-4
Depth23.5 - 2D Modelling
Depth13.5 - 3D Modelling
-6 Depth13.5 - 2D Modelling
Depth18.5 - 3D Modelling
-8 Depth18.5 - 2D Modelling

-10

-12
(a) 3-storey building , Length=20m, B=80m, D0=15m

Distance from Symmetry Line (m)

(b)10-storey building , Length=20m, B=80m, D0=29m

higher surface settlement than two-dimensional ones is shown in the green-field cases (the case in which no
and also, the settlement troughs of 2D analysis are building is present at the surface; GF) in Fig. 9.
more rigid (have less curvature) than 3D ones. The results of 3D analyses showed that by increas-
Consequently, differential settlements predicted by ing the central distance of tunnels, the curvature of
3D analyses are more than that of 2D ones. settlement trough decreases and its shape gets more
rigid. This behavior is not seen in the 2D analysis.
3.2 Center to Center Distance of Tunnels (D0) Figure 9 presents the results of changing D0
parameter for two different cases. The settlement
As discussed by Mirhabibi and Soroush (2012), the amounts of 3D models are evidently higher than 2D
center to center distance of tunnels (or sheer distance ones and also have more curvature and flexibility.
between tunnels; Pillar width) affects the surface
settlement trough significantly, the influence of which

123
Geotech Geol Eng

Fig. 9 Assessment of center Distance from Symmetry Line (m)


to center distances (Pillar
width) of twin tunnels 0
0 20 40 60 80 100 120

-4

Selement (mm)
D0=15 (pillar width=1D) / 3D Modelling
-8
D0=15 (pillar width=1D) / GF
D0=15 (pillar width=1D) / 2D Modelling
D0=22 (pillar width=1D) / 3D Modelling
-12 D0=22 (pillar width=1D) / GF
D0=22 (pillar width=1D) / 2D Modelling
D0=29 (pillar width=1D) / 3D Modelling
D0=29 (pillar width=1D) / GF
-16 D0=29 (pillar width=1D) / 2D Modelling

-20

(a) 3-Storey building, Z0=13.5m ،B=80m ،Length=20m

Distance from Symmetry Line (m)

0
0 20 40 60 80 100 120

-4
Selement (mm)

D0=15 (pillar width=1D) / 3D Modelling


-8 D0=15 (pillar width=1D) / GF
D0=15 (pillar width=1D) / 2D Modelling
D0=22 (pillar width=1D) / 3D Modelling
-12 D0=22 (pillar width=1D) / GF
D0=22 (pillar width=1D) / 2D Modelling
D0=29 (pillar width=1D) / 3D Modelling
D0=29 (pillar width=1D) / GF
-16 D0=29 (pillar width=1D) / 2D Modelling

-20

(b) 3-Storey building, Z0=18.5m ،B=80m ،Length=20m

3.3 Building Width (B) As the building width increases (i.e. the building
stiffness decreases relative to the surrounding ground)
Similar to 2D analysis (Mirhabibi and Soroush 2012), other parameters start to show their effects. Figure 10
the building width is the most effective parameter in illustrates the effect of building width (B) on surface
tunnel-building interaction issue. For small values of settlement trough.
building width, the relative stiffness of building Comparing 2D and 3D analysis results displays
compared to the surrounding ground is too high and identical behavior regarding the general increase of
consequently the settlement trough has a very small settlement and its curvature in three-dimensional
curvature. In this situation, other geometrical and analysis.
mechanical properties of building and tunnels do not
come into effect.

123
Geotech Geol Eng

Fig. 10 Assessment of Distance from Symmetry Line (m)


building width effect 2

0
0 10 20 30 40 50 60 70 80 90 100
-2

-4 B=10 / 3D Modelling
B=20 / 3D Modelling

Selement (mm)
-6
B=40 / 3D Modelling

-8 B=80 / 3D Modelling
GF
-10 B=10 / 2D Modelling
B=20 / 2D Modelling
-12
B=40 / 2D Modelling
-14 B=80 / 2D Modelling

-16

-18

-20

(a)3-Storey building, Z0=13.5m ،D0=15m ،Length=20m

Distance from Symmetry Line (m)


2

0
0 20 40 60 80 100
-2

-4 B=10 / 3D Modelling
Selement (mm)

B=20 / 3D Modelling
-6
B=80 / 3D Modelling

-8 GF
B=10 / 2D Modelling
-10 B=20 / 2D Modelling
B=80 / 2D Modelling
-12

-14

-16

-18

(b) 5-Storey building, Z0=18.5m ،D0=22m ،Length=20m

3.4 Building Stiffness (EI) consequently the higher number of stories results in
higher stiffness.
Stiffness of building especially in combination with As illustrated in Fig. 11, increase of building
building width is one of the major controlling factors stiffness will result in less settlement trough curvature
of tunnelling-induced building settlement. The (more rigid settlement trough). Therefore, for building
method of applying building stiffness in 2D models with higher stiffness, differential settlement would
is described by Mirhabibi and Soroush (2012). In 3D have lesser concerns.
models, building stiffness is directly simulated by FE Again, 3D analysis leads to larger settlement with
model i.e. the real shape of building is modeled and higher curvature and consequently more differential
settlement compared to 2D models.

123
Geotech Geol Eng

Fig. 11 Assessment of Distance from Symmetry Line (m)


building stiffness effect on 2
tunnelling induced surface
settlement trough (the more 0
building storey would result 0 20 40 60 80 100
in more stiffness)
-2
D0=15 / 3storey

Selement (mm)
D0=15 / 10storey
-4
D0=22 / 3storey
D0=22 / 10storey
-6 D0=29 / 3storey
D0=29 / 10storey

-8

-10

-12

(a) Z0=18.5m, B=80m, Length=20m

Distance from Symmetry Line (m)


2

0 20 40 60 80 100
-2

-6
Selement (mm)

B=10 / 3storey
-10
B=10 / 10storey
B=80 / 3storey
-14 B=80 / 10storey

-18

-22

-26

(b) Z0=13.5m, D0=15m, Length=20m

3.5 Building Weight 2013). The more the beam’s stiffness, the less would
be the surface settlement.
The results presented in the previous sections showed The second factor is the building weight. As
that the amounts of surface settlements predicted by indicated by Mirhabibi and Soroush (2012), for each
3D analysis are higher than that of 2D ones. The building storey, 10kN/m2 linear force is applied to the
reason for this could be explored in two factors. The surface beam in the 2D plane strain models. The
first factor is the difference between bending stiffness outcomes of the 2D parametric studies showed that
in 2D and 3D analysis. In 2D models, the building is just about 6% increase in settlement is produced by
simulated by an elastic plane strain beam which over consideration of these loads. However, based on the
predicts the bending stiffness (Mirhabibi and Soroush engineering judgment, more settlement is anticipated
by applying weight loads especially for high-rise

123
Geotech Geol Eng

buildings which apply much more load on the surface. where the ration of building length to its width is more
This idea was previously suggested by Bloodworth than 2, could we use plane strain approximation or
(2002) who stated that the weight factor is more not?
effective in three-dimension models rather than 2D In order to answer this question, four different
models. widths of buildings were analyzed; 10 m, 20 m, 40 m
Therefore, in order to evaluate the effect of building and 80 m while two values were considered for the
weight factor on the surface settlement, nine cases of length; 20 m and 40 m. Thus, the ratio of building
this study were analyzed again but without weight. length to its width was in the range of 0.25 to 4.
Table 4 introduces the different cases analyzed in both Figure 13 presents the schematic numerical model
conditions of weighted and weightless. with illustration of buildings. Also, Table 3 introduces
Figure 12 presents the results of 3D analyses (with the cases in which the length of building is considered
and without weight load) versus 2D models. As 40 m and outcomes are compared with 20 m long
illustrated in this figure, application of weight would ones.
have a considerable effect on the increase of surface Comparison of the results of cases shows that
settlement. On the other hand, exclusion of weight increase of building length does not have any major
load from the 3D analysis, leads to results which are influence on the behavior of tunnelling-induced sur-
more close to the 2D ones. Hence it may be concluded face settlement of building. However, increase of
that a 2D model can be assumed as an approximation building length in some cases leads to small increase
of a 3D model which excludes the weight of building of surface settlement which could be the result of
from the simulation. Also, it is obvious that the augmentation of building weight due to larger area of
geometric shape of the settlement curve is approxi- the building (As described earlier, in this study 10 kN/
mately independent of the building weight. m2 is applied for each building storey. So, increase of
building length will increase the area of each building
3.6 Longitudinal Length of Building (L) storey).
Therefore, it could be concluded that the three-
The possibility of complete modeling of building is dimensional behavior of tunnelling-induced surface
one of the major advantages of 3D models. In two settlement of buildings could not be simulated with 2D
dimensional plane strain models, the length of build- plane strain approximation even for buildings with
ing along the tunnel route i.e. the third length which is length to width ratio equal to four.
actually limited to a few meters, is considered to be In the following, the qualitative effect of increase of
infinite which results in errors in comparison with building length is described more accurately.
reality. However, in engineering practices, the 3D real
• Increasing the number of building stories will
cases are approximated by 2D plane strain simulations
results in more noticeable effect of increase of
whenever the ratio of the length of structure to its
building length i.e. tunnelling-induced settlement
width, gets more than a certain amount. The ratio of
of a 40 m-long building will be more than a 20 m-
length to width of surface buildings that allows 2D
long one. (Figs. 14 and 15). By increasing the
approximation instead of 3D modeling was studied in
building width (augmentation of building weight),
this research. It is obvious that in the cases where the
a larger increase in surface settlement is obtained.
ratio of building length to its width is less than 2, the
• Enlargement of building width (B) will cause a
plane strain behavior definitely could not be consid-
small increase in surface settlement due to the
ered. But, the question is that whether for the cases

Table 4 Different cases 5 Storey building 10 Storey building


studied to evaluate the
effect of building weight on B = 10 B = 20 B = 40 B = 80 B = 10 B = 20 B = 40 B = 80
the surface settlement
Z0 = 13.5, D0 = 15 • • •
Z0 = 13.5, D0 = 22 • • •
Z0 = 18.5, D0 = 22 • • •

123
Geotech Geol Eng

Fig. 12 Assessment of Distance from Symmetry Line (m)


effects of building’s weight 2
on building’s settlement 0
trough 0 10 20 30 40 50 60 70 80 90 100
-2

-4 Z0=13.5 / D0=15 / B=10 / 5storey

Selement (mm)
Z0=13.5 / D0=15 / B=10 / 5storey / Weightless
-6
2D Modelling
-8

-10
-16
-12 0 2 4 6 8 10

-14 -18

-16
-20
-18

-20 -22

-22

(a) 5-storey building, B=10m ،Z0=13.5m ،D0=15m

Distance from Symmetry Line (m)


2

0
0 10 20 30 40 50 60 70 80 90 100
Selement (mm)

-2
Z0=13.5 / D0=22 / B=80 / 5storey
Z0=13.5 / D0=22 / B=80 / 5storey / Weightless
-4 2D Modelling

-6

-8

-10

(b) 5-Storey building, B=80m ،Z0=13.5m ،D0=22m

Distance from Symmetry Line (m)


2

0
0 10 20 30 40 50 60 70 80 90 100
-2
Selement (mm)

-4
Z0=13.5 / D0=22 / B=80 / 10storey

-6 Z0=13.5 / D0=22 / B=80 / 10storey / Weightless


2D Modelling
-8

-10

-12

-14

-16

(c)10-Storey building, B=80m ،Z0=13.5m ،D0=22m

123
Geotech Geol Eng

2-diameter, the surface settlement will have small


increase with enlargement of building length. But,
with more central distance of tunnels, no special
changes are observed. Generally, these changes
could be ignored for engineering cases. A sample
of this behavior is presented in the Fig. 18.

4 Quantitative Assessment of 3D Analysis Results

4.1 Comparison of 3D Models with 2D Models

The results presented at the preceding sections show


that in many cases the results of 3D models have major
differences with the 2D ones. However, in some cases
the difference is not considerable and could be
neglected for engineering purposes. Considering the
fact that the cost of 3D modeling is much more than
2D ones, it could be very beneficial if the cases in
which the differences are negligible, and therefore
3-dimentional modeling is not necessary, could be
identified.
The available data base of this study would help to
define the criteria for the cases in which 2D analysis
could be used instead of 3D ones. If we accept the 20%
difference between 2D and 3D model’s results as the
higher boundary for neglecting 3D modeling, the
Fig. 13 Presentation of location of building at the numerical
following criteria should be all met as the prerequisite
models with length of 20 m, 40 m of neglecting 3D modeling and sufficing to 2D
interaction included simulation:
increase of building length. In other words, when
• Small building width (less than 20 m).
the length of a 40 m-wide building is enlarged, a
• Small number of building stories (less than 5
small increase in surface settlement is observed
stories).
compared with the case of a 20 m-wide building.
• Length of building larger than its width (L [ B)
This small augmentation in settlement may be due
to the increase of building weight. Figure 16 Also, when the tunnels get closer, neglecting 3D
illustrates this issue. simulation is more reliable.
• Augmentation of twin tunnels’ depth (Z0) will For the cases where the building length is less than
reduce the increasing effect of enlargement of its width (L \ B) and the number of stories is more
building length. Figure 17 shows some samples for than 5, the surface settlement predicted by 3D
the issue. As shown, the increase of building length simulations is significantly higher than 2D models
is higher when the tunnels are located at the depth and therefore 3D simulation is required.
of 13.5 m compared to the ones located at depth of For the cases between these two ranges, the
18.5 m. decision whether or not to use 3D simulation will be
• Widening the central distance of tunnels (D0) does upon engineering judgment.
not have any major influence on the effects of Besides, there are many cases in which the differ-
building length. It means that by increase of ence between results of 3D simulations and 2D green-
tunnels central distance from 1-diameter to field ones is less than 20%. In these cases, even 2D

123
Geotech Geol Eng

Fig. 14 Assessment of Distance from Symmetry Line (m)


2
surface settlement changes
for a 3-Storey building with 0
Z0 = 13.5 m, D0 = 15 m 0 20 40 60 80
and B = 10 m -2

-4

Selement (mm)
-6

-8 L=20
L=40
-10

-12

-14

-16

-18

-20

(a) Cross sectional settlement trough

Distance in Longitudinal direcon (m)


0
0 20 40 60 80 100
-5
Selement (mm)

-10
L=20
L=40
-15 Building (L=20m)

-20
Building (L=40m)
-25

(b) Longitudinal settlement profile at the surface symmetry axis of tunnels

green-field model could be utilized instead of 3D as an elastic surface beam and therefore, highly over
model. The criteria that should be met to allow such a predicts the bending stiffness of building and results in
substitution are as presented in Table 5: less surface settlement while in three dimensional
Regarding the above criteria, with the decrease of simulations, the building and its interaction with the
building width, the ratio of BL increases and the building tunnels and the surrounding soil are simulated more
should have less bending stiffness (fewer stories) to realistically.
avoid 3D simulations. On the contrary, when the It should be noted that the above conclusions and
building width increases, BL decreases and 3D models the criteria for neglecting 3D simulation are about the
could be conveniently neglected even for taller maximum building settlement of the buildings that are
buildings. located at symmetry line of tunnels. In this case, the
According to these criteria, the cases where 3D maximum building settlement would happen at the
models could be substituted with 2D green-filed middle of the building. However, as described earlier,
models are more frequent than the ones where 3D comparison with previous results (Mirhabibi and
simulations could be replaced by 2D interaction Soroush 2012) shows that the same recommendations
models. may be applicable for the other cases where buildings
This is mainly due to the modeling approach in 2D are located on the surface with every given geometry.
plane strain simulations where the building is modeled

123
Geotech Geol Eng

Fig. 15 Assessment of Distance from Symmetry Line (m)


surface settlement changes 2
for a 10-Storey building
with Z0 = 23.5 m, 0
D0 = 22 m and B = 80 m 0 20 40 60 80 100 120

-2

Selement (mm)
-4

L=20
-6
L=40

-8

-10

-12

-14

(a) Cross sectional settlement trough

Distance in Longitudinal direcon (m)


0
0 20 40 60 80 100
-2
Selement (mm)

-4
-6
-8
L=20
-10
L=40
-12
-14
-16

(b) Longitudinal settlement profile at the surface symmetry axis of tunnels

4.2 Regression Analysis of Three-Dimensional analysis was employed to find a reliable correlation
Models Results (Incorporation of Analyses between geometrical and mechanical parameters of
Results into a Design Graph) building and tunnels and the ratio of maximum
building settlement to the corresponding green-field
In the previous sections, interaction between twin- value (SR). The method, definitions and parameters
tunneling and a building located at the symmetry axis are the same as described by Mirhabibi and Soroush
of tunnels on the surface was studied by full 3D (2012) where just one new parameter is added to the
numerical modeling. Based on the outcomes of these independent variables; ‘‘L’’; length of building at the
analyses the difference between 2D and 3D numerical third direction which could be merely defined in 3D
simulations was examined. Also, the effects of differ- models.
ent factors and parameters on the tunneling-induced The same approach employed by Mirhabibi and
surface settlement of building were investigated using Soroush (2012) is used here to find the best correlation
the numerical results. Using the available database, the between SR parameter and relative bending stiffness,
authors tried to incorporate the results of analyses into q .
design. So, they looked to find out a design correlation When the length of building is added to the
between green-filed settlement and full 3D settlement independent variables, the definition of relative stiff-
of building induced by twin tunnelling. As described ness parameter should be revised. As described by
in details by Mirhabibi and Soroush (2012) regression Mirhabibi and Soroush (2012), the q parameter needs

123
Geotech Geol Eng

Fig. 16 Assessment of Distance from Symmetry Line (m)


surface settlement changes 2
due to enlargement of
0
building width for a 0 20 40 60 80 100
3-Storey building with -2
Z0 = 13.5 m, D0 = 15 m
-4

Selement (mm)
-6 B=10 / L=20
B=40 / L=20
-8
B=80 / L=20
-10 B=10 / L=40
B=40 / L=40
-12 B=80 / L=40

-14

-16

-18

-20

(a) Cross sectional settlement trough

Distance in Longitudinal direcon


0
0 20 40 60 80 100

-4
Selement (m)

-8

-12 B=10 / L=20


B=40 / L=20
B=80 / L=20
-16 B=10 / L=40
B=40 / L=40
B=80 / L=40
-20

(b) Longitudinal settlement profile at the surface symmetry axis of tunnels

to be dimensionless and eventuate to best fitness to the factors in the tunnel-building interaction. Increase of
data. Examining different combinations of parameters building stiffness and central axes of tunnels would
and regression basics, the following equation was used enhance the stiffness of building relative to the twin
as the best definition for relative stiffness parameter: tunnels, while increase of tunnels’ depth and building
  width will reduce the relative stiffness.
 EID30 L
q ¼ ; Definition of relative parameter The best fit equation to the numerical results
Es Z02 B5 achieved from regression analysis has a linear form
in 3D simulations; as follows:
ð1Þ Y ¼ a þ bX þ e ð2Þ

All of the parameters used in q Eq. 1 have the same where
definition as described by Mirhabibi and Soroush
(2012) and the Length is the longitudinal dimension of SR
Y ¼ P ; X ¼ Lnðq Þ; e ¼ estimation error
the building. B
Regarding the elements of relative stiffness param-
Table 6 and Fig. 19 illustrate the summary results
eter, it is obvious that the building width, and the
of the regression model.
central distance of tunnels axes are the most important

123
Geotech Geol Eng

Fig. 17 Assessment of Distance from Symmetry Line (m)


surface settlement changes 2
due to enlargement of twin
tunnels depth for a 3-Storey 0
building with D0 = 15 m 0 20 40 60 80 100
and B = 80 m
-2

Selement (mm)
Z0=13.5 / L=20
-4
Z0=23.5 / L=20
Z0=13.5 / L=40
-6 Z0=23.5 / L=40

-8

-10

-12
(a) Cross sectional settlement trough

Distance in Longitudinal direcon (m)


0
0 20 40 60 80 100

-4
Selement (mm)

-8

-12 Z0=13.5 / L=20


Z0=23.5 / L=20
Z0=13.5 / L=40
Z0=23.5 / L=40
-16

(b) Longitudinal settlement profile at the surface symmetry axis of tunnels

Figure 19 presents the design graph assigned to the 4.3 Effect of Constitutive Model
numerical data resulted from regression model.
In order to use this equation for predicting the As described before, the Mohr–Coulomb elastic-
maximum settlement of building induced by tunnel- perfectly plastic model is utilized in this study. It
ing, the relative stiffness parameter should be calcu- should be noted that the main purpose of this research
lated according to the Eq. 1. Using Fig. 19 or Table 6, is not predicting the values of tunneling-induced
the modification factor (SR) could be derived. Apply- surface settlements but rather exploring the trends and
ing the SR factor into the green-field settlement would comparing the effect of full 3D modeling on the
result in prediction of maximum tunneling-induced results. Therefore, the ratios (and not the absolute
building settlement. This procedure could be very values) of surface settlements in 2D and 3D and green-
useful for preliminary design stages. If more accurate fields conditions are compared with each other.
results are needed, 3D simulations should be Consequently, it could be assumed that the effect of
conducted. constitutive model on the results may be neglected.
In order to evaluate the effect of constitutive
models on the results, three cases were analyzed with
three different behavior models; Mohr–Coulomb,
Drucker-Prager and Cap-model.

123
Geotech Geol Eng

Fig. 18 Assessment of Distance from Symmetry Line (m)


surface settlement changes 0
0 20 40 60 80 100
due to enlargement of twin
tunnels central distance for 3
& 5-Storey buildings with -2

Z0 = 13.5 m and B = 80 m
-4 D0=15 / L=20

Selement (mm)
D0=22 / L=20
D0=29 / L=20
-6 D0=15 / L=40
D0=22 / L=40
D0=29 / L=40
-8

-10

-12

(a) Cross sectional settlement trough for a 3-storey building

Distance from Symmetry Line (m)


0
0 20 40 60 80 100

-2

-4 D0=15 / L=20
Selement (mm)

D0=22 / L=20
D0=29 / L=20
-6 D0=15 / L=40
D0=22 / L=40
D0=29 / L=40
-8

-10

-12

(b) Cross sectional settlement trough for a 5-storey building

Table 5 The Criteria for Building width (m) Ratio of building length to its width (L=B) Number of building stories
substituting 2D green-field
simulations instead of 3D 10 L=B  2 Less than or equal to 5
models
20 L=B ¼ 1 Less than or equal to 5
40 L=B ¼ 0:5 ; 1 Less than or equal to 5
80 L=B\1 Less than or equal to 10

The studied cases are: • Coupled model with the above condition plus
3-storey building with width of 10 m
• Green-field condition for tunnels running at
Z0 = 13.5 m and D0 = 15 m The results are presented in Fig. 20. As illustrated,
• Coupled model with the above condition plus despite the difference between magnitudes of surface
3-storey building with width of 10 m. settlements in various models, the trends and the ratio

123
Geotech Geol Eng

Table 6 The results of the best fit regression model applied to dimensional plane strain models which are commonly
the results of 3D simulations of twin-tunneling beneath the used in engineering practices and results of accurate
building located at symmetry axis of tunnels
three-dimensional models. The authors also explored
Variable Coefficient t-statistic Prob. the situations in which rather simplified 2D simulation
could be adopted with enough accuracy and they
Intercept -3.148791 -82.02079 0.0000
described the cases in which 3D models have to be
X 0.197719 23.92024 0.0000
adopted to achieve precise results. Also, the effect of
R-squared = 0.867 constitutive models on the results was investigated.
F-statistic = 572.2 Moreover, based on the results of numerical analyses,
Prob (F-statistic) = 0.000 a design graph was proposed to be used in preliminary
Mean absolute percentage error = 9.3 design stages of engineering practices.
Using Shiraz metro line 1 data and ABAQUS code,
132 three-dimensional numerical models were ana-
lyzed and the outcomes were used to assess the effects
of settlements values could be assumed similar of different geometrical and mechanical parameters on
irrespective of behavior models for practical purposes. the interaction issue. The rather simplified assump-
tions of this study (homogenous and isotropic soil and
concrete, classical Mohr–Coulomb failure criteria for
5 Conclusion the soil and elastic concrete, and short-term undrained
analysis) are mostly based on the common design
In this research, numerical full 3D modeling of twin- practice.
tunnel and building interaction were conducted and Below, the findings of this study are summarized:
the results were compared with 2D analysis. The main
goal of this article was to study the effect of different 1. Generally, the predicted settlements by 3D models
geometrical and mechanical parameters on the tun- are larger than the 2D plane strain ones. Conse-
neling induced settlements of surface buildings and to quently, relying on the results of 2D models results
study the differences between the results of two-

Ln( r *)
0
-10 -8 -6 -4 -2 0 2 4 6 8 10

-1
Ln(SR/∑B)

-2

-3

-4

One building Located at symmetry line of tunnels

-5

-6

Fig. 19 Design graph for predicting of maximum building settlement where building is located at symmetry axis of tunnels

123
Geotech Geol Eng

Fig. 20 Effect of constitutive model on the results

to assess the surface building stability during 7. Parametric studies on the ratio of building length
tunnel construction may not be conservative. to its width proved that the plane strain assumption
2. The settlement curves resulted from 3D simula- could not be applied to the building-tunneling
tions are more flexible compared to 2D plane interaction even for length to width ratios equal to
strain ones (they have more curvature). This 4. According to these studies, the three-dimen-
means that the plane strain assumption and sional behavior of building is different from the
modeling the building as equivalent elastic beam two-dimensional simulations even for large
leads to large value for bending stiffness of the lengths of building.
building. The higher the bending stiffness value of 8. In many cases, the difference between results of
the beam, the less would be the building settle- full 3D models and 2D model is less than 20%
ment. The settlement curves with higher curva- which could be neglected for engineering pur-
tures (which are the outcomes of 3D models) will poses. The criteria to indentify these situations
result in more differential settlements. where 3D simulation is not necessary were
3. The building weight in three dimensional models described.
produces higher settlements compared to two 9. Conducting regression analysis, a modification
dimensional simulations. factor was developed to be used in preliminary
4. The building width and its stiffness are the most design stages in order to predict the maximum
important parameters affecting the building sur- building surface settlement through the available
face settlement curve. Increase of building weight 2D green-filed results.
will increase the flexibility and curvature of
settlement curve while augmentation of building Acknowledgements The authors would like to thank the
stiffness will reduce this curvature. Amirkabir fast processing center for their cooperation in
5. Increase of tunnels’ depth will decrease the effect facilitating the access to the super-computer.
of tunneling on the building settlement.
6. Enlargement of longitudinal length of building,
increases the building weight, and as a result,
increases the surface settlement. The more the
building width, the bigger this influence would be.

123
Geotech Geol Eng

References Katebi H, Rezaei AH, Hajialilue-Bonab M, Tarifard A (2015)


Assessment the influence of ground stratification, tunnel
ABAQUS 6.8, User’s Documentation., Hibbitt, Karlsson and and surface buildings specifications on shield tunnel lining
Sorensen, Inc loads (by FEM). Tunn Undergr Sp Technol 49:67–78
Augrade CE (1997) Numerical modelling of tunnelling pro- Liu G (1997) Numerical modeling of damage to masonry
cesses for assessment of damage to buildings. Ph. D. The- buildings due to tunnelling. Ph.D. Thesis, Oxford Univ
sis, Oxford Univ Liu JF, Qi TY, Wu Z (2012) Analysis of ground movement due
Bloodworth AG, (2002) Three-dimensional analysis of tun- to metro station driven with enlarging shield tunnels under
nelling effects on structures to develop design methods. building and its parameter sensitivity analysis. Tunn
PhD thesis, Oxford Univ Undergr Space Technol 28:287–296
Camos C, Molins C (2015) 3D analytical prediction of building Losacco N, Burghignoli A, Callisto L (2014) Uncoupled eval-
damage due to ground subsidence produced by tunneling. uation of the structural damage induced by tunnelling.
Tunn Undergr Sp Technol 50:424–437 Geotechnique 64(8):646–656
Chakeri C, UnverOzcelik By (2014) A novel relationship for Maleki M, Sereshteh H, Mousivand M et al (2011) An equiva-
predicting the point of inflexion value in the surface set- lent beam model for the analysis of tunnel-building inter-
tlement curve. Tunn Undergr Sp Technol 43:266–275 action. Tunn Undergr Space Technol 26:524–533
Do N, Dias D, Oreste P et al (2014) Three-dimensional Mirhabibi A, Soroush A (2012) Effects of surface buildings on
numerical simulation of a mechanized twin tunnels in soft twin tunnelling-induced ground settlements. Tunn Undergr
ground. Tunn Undergr Sp Technol 42:40–51 Sp Technol 29:40–51
Dias D, Kastner R (2002) Tunnelling in soils-ground move- Mirhabibi A, Soroush A (2013) Effects of building three-di-
ments and damage to buildings. In: Proceedings of 2nd int. mensional modeling type on twin tunneling-induced
conf. soil structure interaction in urban civil engineering, ground settlement. Tunn Undergr Sp Technol 38:224–234
Zurich, pp 249–253 Netzel H, Kaalberg FJ (2000) Numerical damage risk assess-
Devriendt M, Doughty L, Morrison P et al (2010) Displacement ment studies on adjacent buildings in Amsterdam. In:
of tunnels from a basement excavation in London. Proc Inst Proceedings of Int. Conf. Geotechnical and Geological
Civ Eng Geotech Eng 163(GE3):131–145 Engineering. Melbourne
Franzius JN (2003) Behavior of building due to tunnel induced Pickhaver JA (2006) Numerical modeling of building response
settlement. Ph.D. Thesis, Univ. of London to tunnelling. Ph.D. Thesis. Oxford Univ
Franzius JN, Potts DM (2005) Influence of mesh geometry on Shin JH, Potts DM, Zaravkovic L (2002) Three-dimensional
three-dimensional finite element analysis of tunnel exca- modeling of NATM tunnelling in decomposed granite soil.
vation. ASCE Int J Geomech 5(3):256–266 Geotechnique 52(3):187–200
Fu J, Yang J, Zhang X et al (2014) Response of the ground and Shiraz Urban and Railway Organization-SURO (2003)
adjacent buildings due to tunnelling in completely weath- Geotechnical Investigation Report, Line 1
ered granitic soil. Tunn Undergr Sp Technol 43:377–388 Son M (2016) Response analysis of nearby structures to tun-
Houhou MN, Emeriault F, Vanoudheusden (2016) Three-di- neling-induced ground movements in clay soils. Tunn
mensional back-analysis of an instrumented shallow tunnel Undergr Sp Technol 56:90–104
excavated by a conventional method. É Geotech Geol Eng
34:1101 Publisher’s Note Springer Nature remains neutral with
Jenck O, Dias D (2004) 3D-finite difference analysis of the regard to jurisdictional claims in published maps and
interaction between concrete building and shallow tun- institutional affiliations.
nelling. Geotechnique 54(8):519–528

123

You might also like