An integrated decision support system for building asset management based


on BIM and Work Breakdown Structure
Maha Al-Kasasbeh a, Osama Abudayyeh b, Hexu Liu b, *
a
Civil Engineering Department, Hashemite University, Zarqa, Jordan
b
Civil and Construction Engineering Department, Western Michigan University, Kalamazoo, MI, 49008, USA

A R T I C L E I N F O A B S T R A C T

Keywords: The asset management phase of a building constitutes approximately 60% of its total lifecycle costs. However,
Asset management significant unnecessary expenses occur in current asset management practices because of the separation of the
Building information modeling design and construction phases from operation and maintenance and the lack of an effective building asset
Database management system
management system covering all types of buildings with numerous components. Asset management decision-
WBS
Life cycle
making is inherently a process that requires the assimilation of a multitude of data, processes, and software
systems. Therefore, this paper proposes an integrated decision support system for building asset management
that addresses the systematization and coordination of lifecycle data. In this approach, a lifecycle work break­
down structure (WBS) for the asset management system is developed to provide a unified hierarchy to categorize
and organize building assets. It is then used to develop the WBS-based integrated building lifecycle asset man­
agement model through a relational database management system (DBMS). Since building information model­
ling (BIM) is a rich information-based platform with large volumes of asset data needed, it is integrated with the
WBS-based DBMS to achieve an effective integrated building asset management. A case study of an educational
building is presented and discussed in the paper to demonstrate how the proposed automated solution is used for
asset management. The research contributes to the body of knowledge by formalizing a WBS-based unified asset
inventory hierarchy and mapping BIM data to the proposed hierarchy for effective asset management.

1. Introduction management systems usually are used to assist industrial practitioners in


“1) the assessment of the current condition, 2) prediction of the future
Building asset management is a strategic and systematic process of deterioration, 3) selection of maintenance and repair strategies, 4) condition
operating, maintaining, upgrading, and expanding physical assets improvement after a repair, and 5) asset prioritization and fund allocation.”
effectively throughout their lifecycle [1]. Asset management helps to [6]. However, most building asset management systems use standard
achieve the required level of service while minimizing cost. Addition­ building classifications for categorizing and analyzing assets [7,8].
ally, it helps to reduce risk and ensure an effective enhancement of These standard systems were designed without taking into consideration
capital over an asset’s lifecycle [2]. Asset management is also beneficial asset management needs [9]. Besides, efficient building management
because it can lead to increased knowledge of the assets, better opera­ systems must give more attention to all phases of the building lifecycle.
tional decisions, improved emergency response, and greater ability to As such, a reliable database that includes historical as-built information
plan and pay for future repairs and replacements (EFCNMT, 2006). In is necessary for asset management functions, including maintenance,
fact, effective asset management is more than maintenance. The condition assessment, and performance prediction. The lack of building
importance of asset management cannot be neglected because buildings lifecycle integration creates significant inefficiencies in asset manage­
could suffer serious problems, such as deterioration, premature failures ment coordination [9–11].
and renewals, and possibly the need for replacement. Building Information Modeling (BIM) has been increasingly used for
Building asset management is a highly challenging task since there asset management functions. BIM is an information-rich model with
are many types of buildings with numerous components that have large volumes of asset data that are a prerequisite for an effective
different maintenance needs and requirements [3–5]. Asset operation and maintenance phase [12,13]. Nevertheless, several

* Corresponding author.
E-mail addresses: malkasasbeh@hu.edu.jo (M. Al-Kasasbeh), osama.abudayyeh@wmich.edu (O. Abudayyeh), hexu.liu@wmich.edu (H. Liu).

https://doi.org/10.1016/j.jobe.2020.101959
Received 25 April 2020; Received in revised form 30 October 2020; Accepted 30 October 2020
Available online 4 November 2020
2352-7102/© 2020 Elsevier Ltd. All rights reserved.

Please cite this article as: Maha Al-Kasasbeh, Journal of Building Engineering, https://doi.org/10.1016/j.jobe.2020.101959
M. Al-Kasasbeh et al. Journal of Building Engineering xxx (xxxx) xxx

challenges have been identified in applying BIM for asset management, step for a successful building asset management system and should be
including the lack of technical alignment between BIM software tools developed in a thorough and detailed manner. Moreover, the classifi­
and asset management processes and functions, as well as data inter­ cation of assets would help categorize the entity information of similar
operability [14–18]. In particular, Talebi [16] stated that: “BIM software components on different projects in an identical way within a unified
tools presently are not applicable or ‘ready-packed’ to fit the asset manage­ system. Several research efforts have thus been dedicated to asset clas­
ment processes. In other words, the number of BIM tools supporting asset sification. For instance, Elhakeem [6] proposed a five-level building
management processes by far is fewer than tools supporting the design stage. hierarchy, including system, subsystem, component, type, and instance.
This issue causes ineffective administrative work routines and gives restricted Similarly, Grussing [8] suggested a hierarchy system based on the
support to the crew onsite. Lack of technology alignment also leads to a digital Uniformat element classification system. This hierarchy consists of three
divide between the design and other stages.” Furthermore, attempts to levels, namely, building systems, building components, and building
enriching 3D models with facilities data in current BIM platforms can be sections. The building sections level includes attributes that describe the
challenging as it creates a discrepancy between the standard built-in characteristics of components, such as material types and locations.
classification systems and the facility data structure such as asset man­ Apart from that, Eweda et al. [3] developed a six-level building hier­
agement inventory [19]. archy: 1) building level describing the building type; 2) space level; 3)
Therefore, the purpose of this paper is to develop an integrated de­ category level, which specifies the four main building disciplines rep­
cision support system for effective asset management using BIM and resented inside the space, i.e., architectural, mechanical, electrical, and
database management systems (DBMS). This system is developed based structural; 4) family level, including all the components in the same
on a comprehensive work breakdown structure (WBS) framework to category that have similar characteristics; 5) family type level, intended
facilitate the integration of all life cycle phases for building asset man­ to clarify different types of components; and 6) family instance level,
agement. The comprehensive WBS framework consists of eight levels, which includes components properties.
such as asset management system, building category, building major However, these previous attempts regarding building inventory
part, system, subsystem, floor, space function, and assets. It provides a systems were associated with some drawbacks. For instance, some assets
unified hierarchy to categorize and organize building assets. BIM model need to be defined in a detailed space, and failing to do so makes it
is also mapped to such a WBS framework so that the proposed system is challenging to assign maintenance responsibilities to department
capable of addressing the discrepancy between the standard built-in workers in a building. Furthermore, prior literature failed to include
classification systems of BIM and asset management. The research utilities as parts of a building or consider the whole life cycle of a
contributes to the body of knowledge by formalizing a WBS-based uni­ building while designing their proposed inventory. Also, not all types of
fied asset inventory hierarchy and mapping BIM data to the proposed buildings are included, such as educational buildings, which are the
hierarchy (i.e., addressing BIM-Asset Management interoperability) for main focus of this research. Additionally, the WBS was not standardized
effective asset management. to define the level of decomposition, which would minimize subjectivity
The remainder of this paper is organized as follows. In Section 2, the and the visible deficiency in the logical breakdown of building compo­
literature on building asset management is reviewed to clarify the point nents into an appropriate hierarchy. Finally, none of the assets inventory
of departure and demonstrate the rationale underlying this research. presented in the former literature demonstrates comprehensive entities
Subsequently, the research methodology is described in Section 3. Sec­ that include mostly all types of assets in any building type.
tion 4 presents the WBS-based lifecycle model for asset management. Standard building classification systems have comprehensive facets
The development of an integrated decision support system for building and could be employed as decomposition criteria. Even though this is a
asset management is described in Section 5 and Section 6. A case study promising idea, they still lack the specific requirements of asset man­
of an educational building is presented to validate the methodology and agement, such as asset location and asset attributes (e.g., condition and
verify the prototype system in Section 7. The final section concludes by deterioration rates) when dealing with building assets. This deficiency is
highlighting the research contribution of this paper. due to the priority that each standard classification system represents.
For example, the Uniformat standard classification system focuses on
2. Literature review functional components which are suitable for rough cost estimation
during the schematic design phase. Construction components and final
This section reviews the relevant work with respect to building asset work results would be the priority of the MasterFormat classification
management. To begin with, asset inventory management is first illus­ system, which is useful in organizing construction information such as
trated; then, how BIM has been used to support building asset man­ procurement, contracting requirements, a technical dividing of activities
agement is discussed. and work practices, and mainly in the organization of cost.

2.1. Asset inventory management 2.2. BIM-enabled asset management

Asset inventory is vital to proper asset management functions. It is a Another main challenge in applying asset management strategies to
critical task when specifying the scope and schedule of building repairs, buildings is the timely availability of quality asset information [20,21].
asset condition assessment, and deterioration prediction [8]. An accu­ Such a challenge partly comes from the fact that asset data is dispersed
rate and well-developed building inventory can provide a powerful tool in the project life cycle. For example, as-built data is generated during
to develop proactive maintenance and better operational decisions. the design and construction phases, whereas the condition assessment
Furthermore, it can provide a better ability to plan for future repairs and data is collected throughout the operation and maintenance phase of a
replacements. One challenge confronted by the facility management facility. Design and construction phases have large volumes of asset data
(FM) industry is that numerous types of assets must be analyzed and that are prerequisites for successful and effective building management
categorized. Such a challenge may present difficulties in the develop­ during the operation and maintenance phase [22,23]. They can provide
ment of a consistent management system for the different types of reliable information for lifecycle building assets performance pre­
building assets. The reason arises from the fact that each building type is dictions and decision-making. The separation of the design and con­
complex with unique characteristics and has numerous components struction data from the asset data collection process in the current
with different maintenance needs and requirements [7]. Also, buildings practice leads to many issues, including information loss or inaccurate
have vast amounts of components, which have different maintenance and incomplete asset data. The fragmentation ultimately contributes to
requirements [7]. delays in building management tasks and cost overruns, resulting in
As such, the listing and classification of the assets inventory is a vital wasted time and money on nonvalue-added tasks, such as searching and

2
M. Al-Kasasbeh et al. Journal of Building Engineering xxx (xxxx) xxx

parts, i.e., physical word, virtual world, and the connection between
these two worlds. Lu et al. [21] reported that plenty of research is
moving from BIM to digital twins for facility operation and mainte­
nance. However, digital twin applications in asset management are still
at its infancy stage, and most of the previous research related to digital
twin primarily focuses on either conceptual proposal or digital
modeling-based data analytics (e.g., 3D as-built modeling). Moreover,
digital twin applications in asset management currently still concentrate
on the building level rather than the organization level and rely on BIM
technology for practical implementation.

3. Research methodology

The objective of this research is to propose an integrated asset


management system for owner organization (i.e., university) who em­
braces a cluster of various types of building facilities. The proposed
system is intended to facilitate the integration of all building lifecycle
phases through a unified WBS hierarchy for effective asset management.
Fig. 1. Research methodology.
Toward this objective, a case study method is used in this research since
verifying as-built documentation during the asset management phase it studies contemporary phenomena in its natural context and is best
[19,22,24]. applied to address explanatory questions [31]. In the context of the
The lack of integration between these phases of the lifecycle of a presented research, a typical education building is chosen as a case study
building makes information flow more difficult and ineffective. In to answer how the proposed system achieves more effective asset
particular, existing building asset management systems typically wait to management. The selected building contains common components and
build until buildings have been constructed and operated. Integrating functional spaces such as various labs, classrooms, and offices and serves
building lifecycle phases would better facilitate information flow and as a representative example to verify and validate the proposed system.
improve the availability, reliability, and consistency of asset informa­ Fig. 1 presents the research methodology. As shown in the figure, it
tion, resulting in reduced time and cost in asset management [25]. In consists of three steps: 1) developing a lifecycle building asset man­
this regard, Terreno et al. [18] illustrated how to use BIM in both the agement model, 2) developing and implementing a lifecycle relational
design and construction phase of a project and beyond that, and sum­ database model for asset management, and 3) applying the developed
marized qualitative descriptions of the benefits of BIM from these in­ system in a typical educational building for demonstration.
terviews. This means that BIM should be employed in the asset
management phase of a constructed asset. Subsequently, Thabet and • Step 1: Developing a lifecycle building asset management model
Lucas [25] developed steps for converting the spreadsheet-based
methodology into a model-based approach allowing the asset manage­ In this research, a lifecycle building asset management model is first
ment department to directly link to a BIM system. developed by formalizing a unified WBS. The WBS is used as the un­
However, several challenges in adapting BIM for asset management derlying integrated lifecycle model for the asset management process. As
include the lack of interoperability of current systems and fragmentation described earlier, existing asset management is limited in several aspects
of existing information [26], as well as the lack of specific requirements such as 1) lack of coverage of utilities; 2) the inability to include all types
in BIM applications [21,27]. Bercerik-Gerber (2012) mentioned that of assets in any building type; 3) insufficient in locating building assets
even though BIM would improve productivity, support proactive deci­ inside various kinds of buildings accurately. To address these limita­
sion making, and reduce costs, the facility managers had to recognize tions, a comprehensive WBS is formalized based on an extensive liter­
the challenges that need to be overcome before fully realizing the vision ature review, industry practices, and standards. It provides a unified
of BIM for asset management. To link BIM data to asset management, hierarchy to categorize and organize various building facilities. The
there are some options, such as 1) the use of proprietary links between WBS is capable of managing the building lifecycle phases, ultimately
BIM software and asset management platforms such as EcoDomus, and ensuring that all data gathered from the design and construction phases
OnumaSystems, 2) the use of industry foundation classes (IFC) format, are effectively integrated with the asset management phase. The WBS
and 3) direct links through application programming interfaces [28]. On can unify information from various sources, such as as-built BIM from
the contrary, Teicholz [29] proposed data transfer strategies to integrate the design and construction stage and inspection data from the opera­
BIM with asset management using open data exchange specification, tion and management stage. Fig. 2 schematically illustrates the proposed
such as the Construction Operations Building Information Exchange WBS model that integrates all lifecycle phases and overcomes the data
(COBie). These efforts attempt to solve the interoperability issue of BIM blockage in the current practice.
and FM from the perspective of data schema and storage. However, they
did not fully address the problem related to information requirement, i. • Step 2: Developing and implementing a lifecycle relational database
e., what information should be exchanged between BIM and FM. model for asset management that is integrated with BIM
Recently, Jang and Collinge [30] identified fifteen key issues from the
perspective of a mechanical and electrical contractor. To address these Following this, a relational database is then developed based on the
issues, the most notable solution is to specify information requirements lifecycle building asset management model and is further integrated
from the start of a build. In this regard, the research presented in this with BIM. It is worth noting that BIM offers historical data (as-built in­
paper is to develop a more comprehensive asset inventory hierarchy, formation) for building asset management, as it is a rich information
which, on the other hand, specifies the facility information repository that hosts information required for asset management. In
requirements. other words, BIM provides a portion of asset information (e.g., status
It should be noted that digital twin was recently introduced as a facility data), whereas dynamic data in the formalized WBS hierarchy is
promising solution to advance asset management further. Essentially, stored in the relational database (e.g., the lowest level, asset attributes,
digital twin refers to a replica of the physical assets, consisting of three which is described in Section 4). The dynamic building condition data
could be updated continuously during the operation and management

3
M. Al-Kasasbeh et al. Journal of Building Engineering xxx (xxxx) xxx

Fig. 2. Proposed asset data flow.

Fig. 3. Unified WBS for integrated lifecycle building asset management model.

stage. items, including data entry forms and reports.


Accordingly, the relational model composes of historical, static, and
dynamic databases. This step involves the following tasks: 1) developing • Step 3: This step develops an educational building case study to
the data acquisition module, which includes designing the required asset demonstrate how the proposed integrated system is used for asset
inspection and analysis forms for the dynamic database along with the management
data entry forms for populating the static and historical databases; 2)
developing the data storage module, which includes creating the data­ In specific, an education building is chosen as a case study, i.e., the
base tables from the relational data model and database schema; 3) College of Engineering and Applied Sciences (CEAS) building at Western
creating the data processing module, which includes integrating BIM Michigan University (WMU). It is selected because this building is a
with DBMS for extracting historical as-built asset information from BIM typical multiple-story building for both teaching and research, which
models as well as developing the asset management reports; and 4) consists of various functional spaces such as teaching labs, research labs,
developing the web-based user interface, which involves two menu classrooms, offices, study lounges, and so forth. All asset information is

4
M. Al-Kasasbeh et al. Journal of Building Engineering xxx (xxxx) xxx

Fig. 4. Building asset database schema.

5
M. Al-Kasasbeh et al. Journal of Building Engineering xxx (xxxx) xxx

Fig. 5. Data entry form: a) dynamic inspection, b) analysis data, c) historical data.

6
M. Al-Kasasbeh et al. Journal of Building Engineering xxx (xxxx) xxx

Fig. 6. Proposed asset database storage module design.

Fig. 7. The ETL technique data flow diagram.

collected and stored in the developed database. Asset reporting is used to and site work. Level four is building systems, including structural,
demonstrate how the developed system effectively and efficiently pro­ architectural, mechanical, electrical, and conveyance systems.
vides desired information for condition assessment and facilitates deci­ Level five refers to such building subsystems as openings, finishes,
sion making in asset management. The proposed methodology is and furnishing under the architectural system, and sanitary sewage,
described in detail in the following sections. storm drainage, fire suppression, plumbing, and HVAC (heating, venti­
lating, and air conditioning) under the mechanical system. Level six is
4. WBS-BASED lifecycle model for asset management the floors of buildings. Level seven is space functions, including class­
room, laboratories, mechanical room, and so forth. The last level is as­
Effective asset data management requires the development of an sets, such as drainage piping and windows. It is worth noting that this
integrated data model so that information can flow smoothly during the framework is designed to have the flexibility to create asset accounts at
lifecycle. This research utilizes a WBS to develop the building inventory any level on the WBS hierarchy depending on the required details and
system in consideration of the project life cycle. A WBS is regarded as available resources. At the asset account level, the system must cover all
one of the essential tools for defining and structuring project work [32]. activities, information, and processes that result in the achievement of
Additionally, most organizations use WBS to break down a project into effective building management throughout the building life cycle [9].
manageable work packages that have well-defined scopes [33]. A WBS
breaks down the project deliverables into smaller units and organizes 4.1. Coding system
the project team’s work into manageable components. It, as a hierar­
chical structure, categorizes and organizes project work. Each An identification system is developed to support the WBS frame­
descending level in the hierarchy represents increasingly detailed work. work. It is designed to provide an easy mechanism for coding each task
This hierarchy and breakdown are essential within building asset man­ so that tasks are uniquely numbered and correctly summarized. In
agement, allowing projects to be subdivided into deliverables. The WBS addition, the work can easily be identified and tracked over time. The
is typically designed through a top-down approach. The upper levels of proposed coding scheme can identify all the processes and tasks of a
the WBS are broken into logical groupings of work; each subsequent building project. In a WBS, every level entity has a unique assigned
level is further broken down until the work has reached a manageable number; level 1 is designated by 1.0, all other levels are subordinate to
size. It subdivides work into manageable units that include all the pro­ this level. Level 2 is designated by 1. X (e.g., 1.1, 1.2, 1.3). Level 3 is
cedures required to obtain the objectives. designated by 1.X.X (e.g., 1.1.1, 1.1.2,1.1.3). This sequence continues
Fig. 3 shows the proposed lifecycle WBS for the building asset progressively until the asset task level is assigned for all work required
management model, integrating the design and construction data with for the entire project. The proposed WBS has eight levels. Each
the operation and maintenance phases. The unified WBS framework is component at the last level should have a code that contains eight digits.
proposed to track and manage all of a facility’s lifecycle phases, hence Since the tasks are properly subordinated, the project tasks can be
facilitating data flow throughout the lifecycle of a building. This WBS automatically numbered.
framework consists of eight levels, with the top-level being the asset
management system. Level two of this hierarchy is building categories
5. A lifecycle relational database model for asset management
such as education buildings and healthcare facilities. Level three covers
the major building components, such as substructure, superstructure,
The development of an integrated building asset data management

7
M. Al-Kasasbeh et al. Journal of Building Engineering xxx (xxxx) xxx

Fig. 8. The web interface of integrated lifecycle asset management.

Fig. 9. Asset account inspection form.

Fig. 10. Asset account prediction form.

system requires designing a corresponding database schema that rep­ 5.1. Historical database
resents the various lifecycle phases of the building assets. Fig. 4 presents
the building asset database schema. The relational database schema The historical database contains the tables that hold historical as-
discussed in this section was created using an entity-relationship con­ built information generated from the design and construction phases
ceptual data model. Relations are expressed using the following format and potentially stored in BIM models. As shown in Fig. 4, these tables in
with the primary keys underlined: Relation-name (i.e., attribute 1, this database include 1) Building (Building ID, Building description,
attribute 2, …., attribute n). The integrated lifecycle building asset Building address, Building area, Building year built, Categories ID); and
management relational model consists of three primary databases: his­ 2) Asset account definitions (Asset account ID, Building ID, Asset ac­
torical, static, and dynamic. The following subsections discuss these count description, Criticality value, Installation or placed date, Design
databases. life, Replacement value).

8
M. Al-Kasasbeh et al. Journal of Building Engineering xxx (xxxx) xxx

Fig. 11. Asset account maintenance form.

Fig. 12. Developed WBS for WMU’s CEAS building.

5.2. Static database 5.3. Dynamic database

The static database holds tables that define the components and The dynamic database includes the tables that store and process asset
processes in the asset management system. These tables consist of 1) condition assessment and prediction information over time. These tables
Facilities categories (Categories ID, Categories description); 2) Inspec­ contain 1) Asset account inspection (Asset account ID, Inspection date,
tion method (Inspection method ID, Inspection method description); 3) Condition value, Inspection method ID, Employee ID, Condition rating
Condition rating (Condition rating ID, Condition rating description, ID, Time on service); 2) Asset account remaining life prediction (Asset
Rating, Action required); 4) Criticality rating (Criticality rating ID, account ID, Prediction date, Employee ID, Remaining service life); and
Criticality rating description, Rating); 5) Risk rating (Risk rating ID, 3) Asset account maintenance (ID, Asset account ID, Maintenance
Asset account ID, Rating description, Risk value, Condition value, Crit­ Description, Rehabilitation cost, Maintenance date).
icality value); and 6) Employee (Employee ID, Name, Employee expe­
rience, Employee address). 6. An integrated BIM-DBMS asset management system

The design of the BIM-DBMS asset management system includes the

9
M. Al-Kasasbeh et al. Journal of Building Engineering xxx (xxxx) xxx

Fig. 13. Facility categories table in the static storage module.

6.2. Data storage module

The data storage module achieves the lifecycle data integration by


using BIM and DBMS. Fig. 6 schematically illustrates the proposed
module. Specifically, as-build data and static data were obtained from
BIM and collected from the design and construction phases. Such data
was saved into historical and static databases. On the contrary, dynamic
data can be obtained from the asset management phase using inspection
Fig. 14. Inspection methods table in the static storage module. and analysis forms. It should be noted that the complete data storage
module is an implementation of the DBMS schema discussed earlier and
design of data acquisition, data storage, and data processing modules shown in Fig. 4.
along with the user interface. Each module is described in the following
sub-sections.
6.3. Data processing module
6.1. Data acquisition module
To facilitate the extraction of as-built data from the design and
The data acquisition module is developed to facilitate the data entry construction phases to the asset management decision support system,
for populating the three databases. It consists of several forms, as shown an ETL-based automated technique was developed. Fig. 7 schematically
in Fig. 5. Specifically, each static table in the static database has a data illustrates how this technique has been carried out by performing the
entry form. For the static database, the information can be obtained three operations: 1) Extracting the as-built data from BIM models using
directly from the user or extracted from the static or historical databases. flat comma-separated values files; 2) Transforming the extracted data to
The inspection and analysis data acquisition forms have been designed a staging area for re-formatting to fit the relational database schema;
to populate the dynamic database. In the inspection data entry form, and 3) Loading the data into the historical database tables.
information regarding the condition of assets includes current condition,
inspection date, and other relevant static and historical data, as shown in 6.3.1. Asset reporting
Fig. 5a. Four database views were designed and developed to process the
The analysis data entry form is used for the prediction of asset asset data and produce reports. Each view produces an asset manage­
remaining life and is based on user data as well as data from the static ment report that is used for decision making. The four reports that have
and historical databases (see Fig. 5b). For the historical database, the been developed are:
information can be obtained from the design and construction phases,
which is extracted from the BIM model. To populate the tables in this • Asset account status report: This report is useful when the status of a
database, entry forms, as well as automated extraction and populating particular asset is needed by the asset manager. In this report, the
scripts, were developed. Fig. 5c shows the data entry form for the his­ asset account condition behavior can be identified for a specified
torical database, which includes the asset account definition tables. It given time interval. Determining the condition behavior later also
should be noted that this form is directly invoked by the Extract, helps in prediction analysis for this asset,
Transform, and Load (ETL) interface to populate the relevant database • Asset accounts condition assessment report: This report includes
tables and is not directly accessible by users. condition information about all existing asset accounts for a given
date range. It facilitates making decisions regarding maintenance
needs and helps with fund allocation,

10
M. Al-Kasasbeh et al. Journal of Building Engineering xxx (xxxx) xxx

Fig. 15. Condition rating table in the static storage module.

6.4.2. Reports
Four user report options exist under the report menu item: 1) Asset
account status report form, 2) Building asset accounts condition
assessment report form, 3) Building asset accounts condition prediction
report form, and 4) Building asset accounts risk assessment report form.
Examples of these reports are discussed in the case study section.

7. Case study

The CEAS building at WMU is used as a case study in this research to


Fig. 16. Criticality rating table in the static storage module.
demonstrate how to use the proposed automated WBS-based asset
management framework and decision support system. The CEAS was
• Asset account remaining service life report. This report presents the built in 2003 with a total space of 323,000 square feet on two floors that
prediction of the remaining life for all existing assets. It can be
helpful for future planning of fund allocation as well as taking pro­
active maintenance actions,
• Asset account risk assessment report. This report shows the risk value
for all existing assets for a given date range. It is used when the
criticality is important for the decision since the risk value is a
function of both condition value and the criticality. Examples of
these reports are provided with the case study section.

6.4. Graphic user interface

A web-based user interface has been developed for this system to


provide access from any computer connected to the internet using a
standard browser. The interface includes two menu items (see Fig. 8),
including 1) Data entry forms and 2) Reports.

6.4.1. Data entry forms


This component includes dynamic, static, and historical database
entry options. Dynamic database option has three data entry forms,
including asset account inspection, asset account prediction, and asset
account maintenance forms. Fig. 9 presents an asset account inspection
form. Fig. 10 presents the asset account prediction form, and Fig. 11
shows the asset account maintenance form. It is worth noting that some
of the fields are populated automatically from the static database, while
other fields are entered by the user. For example, once the user enters an
ID, the asset account description is filled with information from the
database automatically. The static database option has six forms that
facilitate populating the tables in the static database. The historical
database option facilitates populating the historical database using the
ETL technique and the automated scripts that are developed for
extracting as-built data.
Fig. 18. Risk rating table in the static storage module.

Fig. 17. Employee table in the static storage module.

11
M. Al-Kasasbeh et al. Journal of Building Engineering xxx (xxxx) xxx

Fig. 19. a. WMU’s buildings table in the historical BIM database. b. CEAS building’s asset account definition table in the historical BIM database.

are dedicated to teaching and research. It includes seven computer − Finishes in the east wing of the first floor for bathroom F205. This
teaching labs, 75 research and teaching laboratories, and several class­ includes ceiling, flooring, and wall finishes.
rooms, offices, study lounges, and breakout rooms. The building also has − Stair for space function A102. The base level for this stair is the
a penthouse that houses all its mechanical and electrical systems. The first floor, and the top-level is the second floor.
layout of the building is divided into two 600-foot wings (east and west) • Asset account defined at asset level (level 8):
that are joined by a central glass hub. In addition to the entire engi­ − Celling for faculty office G262 in east wing of first floor.
neering complex, there are two attached parking garages and a − Electrical power generator for electrical room F001 in east wing of
basement. basement.
A WBS asset management inventory of CEAS has been developed for − Wood single-flush door size: 36′′ × 84′′ for room E− 241 in the east
the automated asset management system. The portion of the WBS is wing of the second floor.
shown in Fig. 12, which illustrates the CEAS substructure and super­
structure. From this figure, the first level is the entire asset management
system, followed by the educational building type as the second level. 7.1. DBMS tables and data entry
The third level is the building components, which include substructure
and superstructure. The fourth level is the system level and consists of 7.1.1. Static database tables
the CEAS architectural, electrical, mechanical, structural, and conveyor For the static database storage module that has been identified in
systems. The fifth level is the subsystems, including finishes and open­ DBMS, each table has fixed data (static), as shown in Figs. 13–18. These
ings for the architectural system; HVAC for the mechanical system; figures present the data entry for facility categories table, inspection
lighting and power for the electrical system; and walls and stairs for the method, condition rating table, criticality rating table, employee table,
structural system. The sixth level is the floors and includes the CEAS and risk rating table, respectively.
first, second, and penthouse levels for the superstructure, and the
basement under the substructure. The seventh level is the space function 7.1.2. Historical database tables
and includes such spaces as faculty and administrative offices, stair area The historical (as-built) database has been extracted from BIM
and bathrooms on the first floor, classroom on the second floor, elec­ models. This database includes the building table and asset account
trical rooms in the basement, and mechanical room in the penthouse. definition table, as shown in Fig. 19a and b. Fig. 19a presents historical
The eighth level includes such assets as ceilings for faculty and admin­ information regarding the CEAS building included in this database (of
istrative offices, electrical power generator for electrical rooms, and which CEAS is one). Fig. 20b depicts a historical database for the
wood single-flush door size: 36′′ × 84′′ for classroom E− 241. selected asset accounts for CEAS. For populating the dynamic database,
As mentioned before, the proposed WBS framework has flexible asset inspection, and analysis information for these asset accounts have been
accounts at different levels of detail. In this case study, the asset ac­ collected. The inspection data covers the period from 2015 to 2018, the
counts are marked with an asterisk, as shown in Fig. 12. As demon­ prediction information covers the period from 2014 to 2018, and the
strated in this figure, the asset account level represents the depth of the maintenance database table year from 2015 to 2018. Examples of these
asset management breakdown for each subdivision. The following are databases are shown in Fig. 20a, b, and c, respectively.
examples of asset accounts defined at different WBS levels along with
their descriptions: 7.2. Asset management reporting

• Asset account defined at the floor level (level 6): The following reports are examples from the CEAS asset manage­
− West and east wings of first floor doors for classrooms, halls, ment decision support system:
faculty, and administrative office.
− Structural system in west and east wings for basement floor, • Asset Account Status Report (see Fig. 21): This report presents an
which includes beams, columns, walls, slabs, and stairs. example of the status of a specific asset over a specified period of
• Asset account defined at the subsystem level (level 5): time. For example, Fig. 21 is the Celling for Faculty Office G262 in East
− Lighting system for all building floors (first floor, second floor, Wing of First Floor asset account report and shows that the ceiling of
and penthouse). this room was in good condition (Rated as 2) in 2015 and began to
• Asset account defined at the space function level (level 7): deteriorate in 2016 and 2017 with ratings of 3 and 4, respectively. In
− Mechanical equipment in west wing of penthouse for mechanical 2018, this asset reached a rating of 5 that requires a total
room A-3001. replacement.

12
M. Al-Kasasbeh et al. Journal of Building Engineering xxx (xxxx) xxx

Fig. 20. a. CEAS building’s asset account inspection table. b. CEAS building’s asset account remaining life prediction table. c. CEAS building’s asset account
maintenance table.

13
M. Al-Kasasbeh et al. Journal of Building Engineering xxx (xxxx) xxx

facilitated a wide range of functionalities, including the accurate


acquisition, storage, processing, and reporting of asset information
promptly. It has also increased operational efficiency by aiding in the
planning, execution, and coordination of maintenance operations.
It is worth noting that the integrated decision support system for
building asset management was developed using BIM and DBMS. The
integration between BIM and DBMS was achieved by the ETL technique
in the form of flat comma-separated values files. The WBS-based
framework is generic for all kinds of university buildings and lays a
foundation for managing and organizing buildings for effective building
asset management. However, the information extracted from BIM
(which is described in Section 5.1) could be exchanged through COBie
format. That is, the identified information could be transferred from BIM
to the integrated decision support system for building asset management
using COBie. In such a case, the extracted data in the format of COBie
need to be saved to the staging area and then re-formatted to fit the
Fig. 21. An example of an asset account status report.
relational database schema.
The integrated approach in this paper addresses the challenges dis­
• Building Asset Accounts Condition Assessment Report (see Fig. 22): cussed in the literature by creating one unified model that can be used
This report presents condition ratings during March 2018 for all throughout the lifecycle of a building. It results in more sustainable,
CEAS asset accounts. This report indicates that some asset accounts efficient, and well-managed buildings, as well as in eliminating the
(i.e., celling for faculty office G262 in the east wing of the first floor) costly and time-consuming efforts caused by the separation of the life­
need to be replaced. In contrast, others (i.e., lighting system for all cycle processes. The proposed framework provides an inventory system
building floors (first floor, ground floor, and penthouse)) do not need that covers all types of buildings along with their lifecycle information.
any maintenance. For example, the framework provides an accurate location for each asset
• Building Assets Account Remaining Service Life Report (see Fig. 23): in a building, hence facilitating maintenance work assignments and
This report presents the prediction of the remaining service life for all allowing information integration between the various phases of the
CEAS asset accounts from the year 2016–2018. From this report, the lifecycle. It also allows for creating flexible asset accounts that can be
asset manager must conclude that the Celling for Faculty Office G262 defined at any WBS level, depending on the desired details and the
in East Wing of First Floor asset account is a priority. availability of resources.
• Building Asset Accounts Risk Assessment Report (see Fig. 24): In this
report, all the risk values for the CEAS asset accounts in 2018 have Author statement
been presented. This report shows that the asset accounts, including
lighting system for all building floors (first floor, ground floor, and Maha Al-Kasasbeh: Methodology, Software, Investigation, Writing-
penthouse), stair for space function A102, and mechanical equip­ Original draft preparation.
ment in the west wing of the penthouse for mechanical room A-3001, Osama Abudayyeh: Methodology, Writing- Reviewing and Editing,
have more risk value so it should be the focus of the asset manager. Supervision.
Hexu Liu: Methodology, Validation, Writing- Reviewing and Edit­
8. Discussions and conclusions ing, Project administration, Supervision.

Building asset management is an integrated data-driven decision- Declaration of competing interest


making process that is needed for proactively maintaining and ensuring
the long-term sustainability of building assets. This research contributes The authors declare that they have no known competing financial
a building asset management system that was developed using a unified interests or personal relationships that could have appeared to influence
WBS hierarchy as the sole model for managing all university buildings the work reported in this paper.
during all phases of the building lifecycle. An integrated decision sup­
port system for building asset management using BIM and DBMS was
then developed. This included developing data acquisition, data storage,
and data processing modules. The proposed decision support system

Fig. 22. An example of a building asset accounts condition assessment report.

14
M. Al-Kasasbeh et al. Journal of Building Engineering xxx (xxxx) xxx

Fig. 23. An example of building asset accounts remaining service life report.

Fig. 24. An example of building asset account risk assessment report.

References [8] M.N. Grussing, Life-cycle asset management methodologies for buildings,
J. Infrastruct. Syst. 20 (1) (2014), 04013007-1-04013007-8.
[9] R Maha Alkasisbeh, O. Abudayyeh, Development of work breakdown structure
[1] M.A. Akofio-Sowah, R. Boadi, A. Amekudzi, M. Meyer, Managing ancillary
inventory framework for building assets, in: Conference of Construction Research
transportation assets: the state of the practice, J. Infrastruct. Syst. 20 (1) (2014),
Congress 2018, 2018.
04013010.
[10] J.D. Goedert, P. Meadati, Integrating construction process documentation into
[2] S.W.A. Shah, M.N. Mahmood, N. Das, Strategic asset management framework for
building information modeling, J. Construct. Eng. Manag. 134 (7) (2008) 509–516.
the improvement of large scale PV power plants in Australia, in: 2016 Australasian
[11] K. Farghaly, F.H. Abanda, C. Vidalakis, G. Wood, Taxonomy for BIM and asset
Universities Power Engineering Conference (AUPEC), IEEE, 2016, pp. 1–5.
management semantic interoperability, J. Manag. Eng. 34 (4) (2018), 04018012,
[3] A. Eweda, T. Zayed, S. Alkass, Space-based condition assessment model for
https://doi.org/10.1061/(asce)me.1943-5479.0000610.
buildings: case study of educational buildings, J. Perform. Constr. Facil. 29 (1)
[12] S. Lee, J. Yu, D. Jeong, BIM acceptance model in construction organizations,
(2015), 04014032 (1)-04014032(12).
J. Manag. Eng. (2015), 04014048, https://doi.org/10.1061/(ASCE)ME.1943-
[4] T. Hegazy, W. Gad, Dynamic system for prioritizing and accelerating inspections to
5479.0000252.
support capital renewal of buildings, J. Comput. Civ. Eng. 29 (5) (2015),
[13] X. Yin, H. Liu, Y. Chen, Y. Wang, M. Al-Hussein, A BIM-based framework for
04014058-1-04014058-8.
operation and maintenance of utility tunnels, Tunn. Undergr. Space Technol. 97
[5] R Maha Alkasisbeh, O. Abudayyeh, Building Asset Management System: A
(2020) 103252.
Performance Evaluation Approach, Institute of Industrial and Systems Engineers,
[14] H. Yan, P. Damian, Benefits and barriers of building information modeling, in: 12th
2018, 2018.
International Conference on Computing in Civil and Building Engineering, Beijing,
[6] A. Elhakeem, T. Hegazy, Building asset management with deficiency tracking and
2008.
integrated life cycle optimisation, Struct. Infrastruct. Eng. 8 (8) (2012) 729–738.
[7] S.S. Ahluwalia, A Framework for Efficient Condition Assessment of the Building
Infrastructure, Ph.D. thesis, University of Waterloo, Waterloo, ON, Canada, 2008.

15
M. Al-Kasasbeh et al. Journal of Building Engineering xxx (xxxx) xxx

[15] F. Mehmet, Benefits of Building Information Modeling for Construction Managers [25] W. Thabet, J. Lucas, Asset data handover for a large educational institution: case-
and BIM Based Scheduling, M.S. thesis, Worcester Polytechnic Institute, study approach, J. Construct. Eng. Manag. 143 (11) (2017), 05017017.
Massachusetts, 2011. [26] C. Talamo, M. Bonanomi, Methodological experimentation: proposal of a datasheet
[16] S. Talebi, Exploring advantages and challenges of adaptation and implementation template for FM activities in the BIM environment, in: Knowledge Management
of BIM in project life cycle, in: 2nd BIM International Conference on Challenges to and Information Tools for Building Maintenance and Facility Management,
Overcome, BIM Forum Portugal, 2014. Springer International Publishing, Switzerland, 2015.
[17] A. Ghosh, A.D. Chasey, M. Mergenschroer, Building information modeling for [27] H.B. Cavka, S. Staub-French, E.A. Poirier, Developing owner information
facilities management: current practices and future prospects, Build. Inf. Model. requirements for BIM-enabled project delivery and asset management, Autom.
(2015) 223–253, https://doi.org/10.1061/9780784413982.ch09. ConStruct. 83 (2017) 169–183.
[18] S. Terreno, C. Anumba, E. Gannon, C. Dubler, The benefits of BIM integration with [28] P. Parsanezhad, J. Dimyadi, Effective facility management and operations via a
facilities management: a preliminary case study, Comput. Civil Eng. (2015), BIM-based integrated information system, in: CIB Facilities Management (CFM)
10.1061-9780784479247.084. 2014 Conference, 21-23 May, 2014, Copenhagen, Denmark, 2014.
[19] Jaehyun Park, Hubo Cai, WBS-based dynamic multi-dimensional BIM database for [29] P. Teicholz, BIM for Facility Managers, Wiley, Hoboken, NJ, 2013.
total construction as-built documentation, Autom. ConStruct. 77 (2017) 15–23, [30] R. Jang, W. Collinge, Improving BIM asset and facilities management processes: a
2017. Mechanical and Electrical (M&E) contractor perspective, J. Build. Eng. (2020)
[20] P. Brous, P. Herder, M. Janssen, Governing asset management data infrastructures, 101540.
95, Procedia Comput. Sci. 9 (1) (2016) 303–310. Available: ISSN 1877-0509. [31] P. Runeson, M. Höst, Guidelines for conducting and reporting case study research
[21] H. Liu, O. Abudayyeh, W. Liou, BIM-based smart facility management: a review of in software engineering, Empir. Software Eng. 14 (2) (2009) 131.
present research status, challenges, and future needs, in: 2020 Construction [32] H. Liu, M. Lu, M. Al-Hussein, BIM-based integrated framework for detailed cost
Research Congress, Tempt, Arizona, USA, 2020. March 8-10. estimation and schedule planning of construction projects, in: ISARC. Proceedings
[22] Tuyen Le, H. David Jeong, Interlinking lifecycle data spaces to support decision of the International Symposium on Automation and Robotics in Construction, vol.
making in highway asset management, Autom. ConStruct. 64 (2016) 54–64, 2016. 31, IAARC Publications, 2014, p. 1.
[23] C. Yuan, T. McClure, P. Dunston, H. Cai, Leveraging construction inspection and [33] Y.M. Ibrahim, A. Kaka, G. Aouad, M. Kagioglou, Framework for a generic work
documentation for asset inventory and lifecycle asset management, J. Inf. Technol. breakdown structure for building projects, Construct. Innovat. 9 (4) (2009)
Construct. 21 (2016) 72–85, 2016. 388–405.
[24] C. Yuan, T. McClure, P. Dunston, H. Cai, Life-cycle approach to collecting,
managing, and sharing, J. Construct. Eng. Manag. 143 (6) (2017), 04017001.

16