Professional Documents
Culture Documents
• Safety Moment
• Overview of DSPT
• Projects to Date
• Methodology Comparison
• TMEP Sumas Case Study
• TMEP Challenges and Outcomes
• Discussion
2
Safety Moment
Working in Extreme Temperatures
3
Winterization of Equipment
Safety, training, enduring the elements & overcoming risks
4
What We Do
Superior tunnelling solutions
5
Microtunnelling
Equipment Fleet
6
Industries We Serve
Building the world beneath you
Energy:
• Oil and gas pipeline
Civil / Infrastructure:
• Sewer / sanitary installations (lined/unlined)
• Storm water networks (lined/unlined)
• Watermain / telemetry – insertion required
• Marine intake and out take
• Electrical installations
• Fuel pipelines
• Offshore Applications
7
Trenchless Technology Overview
Rehabilitation, New Installation and Assessment
Crossing Applications
• Environmentally Sensitive
Trenchless Technologies
Areas
• Railroads, Highways and Rehabilitation Installation Assessment
Roadways
• Rivers, Streams, Bogs, Bayous,
Lakes Pipe CIPP Close-Fit Pipe
Slip Lining Shotcrete
Bursting Lining Lining Eating
• Mountainous Areas
• Urban Areas
• USACE Regulated Zones: SSET CCTV NDT Man Entry
Rivers, Ship Channels,
Canals, Dams, Levees
• Water to Land Crossings: Sea Impact Micro- Water Pipe Pipe Auger
Outfalls , Lake Intakes, Shore Moling Tunneling Jetting Jacking Ramming
HDD
Boring
Approaches
• Areas of Contaminated Soils
Direct Steerable Pipe Thrusting
8
Direct Pipe® Installation
What we do
Herrenknecht | The Direct Pipe Method ® (DPI) combines the advantages of microtunnelling and HDD
technology. In one step only, a prefabricated pipeline can be installed and the required borehole excavated
at the same time. This allows speedy and highly economic installation of pipelines with lengths of more
than 1,500 meters.
American Society of Civil Engineers | Direct Steerable Pipe Thrusting (DSTP) is the common name for the
installation of a steel pipeline that is installed into a bore using a pipe thruster, steerable and typically
installed between shallow launch and reception portals along a designed bore path that includes curves.
VS.
9
Direct Pipe® Installation
Methodology
10
Direct Pipe® Installation
What we do
Pipe Thruster
Invented as Aid
Tool for HDD assist
One-pass pipeline
installation method
combining
Microtunnelling and
HDD techniques
11
Direct Pipe® Installation
Site layout
12
Direct Pipe® Installation
Site layout
13
Direct Pipe® Installation By Year
Methodology
17
Direct Pipe® Installation By Year
Methodology
18
Direct Pipe® Installation By Footage
Methodology
19
Direct Pipe® Installation
Methodology
20
Direct Pipe® Installation Length | Diameter
Methodology
21
HDD vs. MT. vs. DPI
What is historically considered..
28
HDD, Direct Pipe®, Microtunnel Comparison
CRITERIA HDD DIRECT PIPE MICROTUNNELING
Design Length Longer and Deeper Short and Shallow Short and Shallow
Maximum Length >17,000 feet (5,200m) >7,000 feet (2,100m) >7,000 feet (2,100m)
Depth of Cover Generally Greater Than 25 feet Can Be as Low as 3X Pipe Diameter Can Be as Low as 3X Pipe Diameter
Entry/Launch
Surface Entry Near Surface Launch Shaft Launch
Approach
Governed By Installation and Governed By Installation and
Min. Install Radii Generally Flat or Sloped
Operating Stresses Operating Stresses
29
HDD, Direct Pipe®, Microtunnel Continued
CRITERIA HDD DIRECT PIPE MICROTUNNELING
Hydrostatic Drilling Fluid Pressure Hydrostatic Lubricating Pressure and Hydrostatic Lubricating Pressure and
Annular Pressures
and Cutting Transport Pressure Slurry Over Pressure Slurry Over Pressure
Gravel, Cobbles and Can Negotiate Up To 1/3 Size Of The Can Negotiate Up To 1/3 Size Of The
High Risk Of Failure
Boulders Cutterhead Cutterhead
Clay Soils High Risk of Hydraulic Fracture Low Risk of Hydraulic Fracture Low Risk of Hydraulic Fracture
30
Annular Pressure Comparison
Direct Pipe vs. HDD
180 100
160
LEVEE
0
Annular Pressure, Psi
140
ELEVATION, FT
120 -100
40
-400
20
0 -500
0+00 5+00 10+00 15+00 20+00 25+00 30+00 35+00 40+00 45+00 50+00
Limit Pressures with FOS=2 Estimated Annular Pressure - HDD Estimated Annular Pressure - DP
31
Method of Construction Favorability
What we do
& Cobbles
32
Method of Construction Favorability
What we do
33
TransMountain Pipeline – Sumas River Crossing
Field operations, Direct Pipe Installation - DPI®
TransMountain
Client introduction
• Trans Mountain operates 1,150 km (715 mi) 24” pipeline through Alberta and British Columbia, supplying 300,000
barrels of oil per day.
• Currently constructing an expansion, which is 980 km (610 mi) of 36” product line along the existing Right of Way.
35
Project Information
Overview
The original plan was to complete the replacement when the new expansion 36" line was to be installed, delays in the
construction of the 36" required the client to find an alternate solution
Options:
• HDD
• Micro Tunnel
• Direct Pipe
36
Project Information
Overview
Crew Size:
• Our typical DPI crew consists of 11 field personnel and 4-5 onsite management during internal installation
• We ramp up to 26-28 during tunnelling, we split the same crew into night shift for tunnelling 10 and 10 per shift, plus
onsite management
Duration:
• Started tunnelling the 42” June 29th and Finished July 04
• Started Pulling the 42” back July 14, Finished July 15th (27 hours)
Thrust Loads:
• Theoretical thrust load was 105T, final thrust was 75T
• Pullback of the 42” started at 130T and steadily dropped, after only a couple metres we were at 85T
37
Project Information
Continued
38
Site Layout
39
Technical Challenges
1: Pipe size
40
Technical Challenges
2: Construction of all internals prior to use
41
Technical Challenges
3: Construction of all externals prior to use
42
Technical Challenges
4: Foundation/Anchoring Design
• Sumas River crossing was situated on the old Sumas Prairie Lake bed
and had no significant soil strength from surface to 80 metres (262
feet) of depths. Blow counts from 0-18 per 300mm (12 inches) were
encountered at the entry pit where the foundation and Thruster unit
were setup. This caused the need to combine 36" x 18 metre helical
piles and driven sheet piles in order to generate the resistance needed
to hold the thruster in place.
• Combined thruster and clamp weight over 63,800 kgs (142,000 lbs) o
pump off.
43
Technical Challenges
5: Insertion of 24" product pipe into 42"
casing
44
Technical Challenges
6: Removal of the 42" casing
• In order to remove the 42" casing, we needed to fill the void between the
outside of the 24" line and the inside of the 42" casing, as well as allow for the
volume that the 42" casing wall thickness once the casing was removed to
maintain the integrity of the dikes on each side of the river.
• The DPI finish, to the casing pull had 10 days between the two, we advanced the
casing twice during this 10 day period to determine how the annular fluid was
holding up and to note the increase in forces required to move the 42" casing
compared to the final thrust forces of the tunnelling phase.
• Anchoring the 24" pipe. Due to the introduction of the slurry based void filling
material the forces imposed between the 24" pipe and the 42" casing were
higher than when inserting the 24" pipe dry. Drag of the 24" when dry, and
buoyant uplift forces when filled.
• A cleaning pig was attached to the back of the 24" product pipe in order to
ensure all of the void filling material was forced out of the open end thereby
filling the void as we removed the 42" casing.
45
Technical Challenges
7: Extreme Heat
46
Direct Pipe® Outlook
• Direct Pipe Installations are becoming more accepted by clients in Canada, and worldwide.
• Educating clients of the benefits of this trenchless installation method will help expand it into new markets.
47
Go néirí an bóthar leat.
Good luck on your journey.
Research in Underground Risk
Source: Canadian Journal of Civil Engineering
• Studied the risks involved in the Horizontal Directional Drilling (HDD) and the
Open Cut (OC) excavation.
• Utilized the Total Risk Index Model (TRI) to calculate the risk value for
underground urban utility projects,
Ma et al. (2010) | China University of Geosciences
• Developed a model to quantify the risk of Maxi HDD projects
• Comprehensive Evaluation Method (FCEM) and Analytical Hierarchy
Process (AHP).
Gierczak (2014) | Clemson
• Focused on developing a model used for evaluating the safety risk of Mini,
Mid, Maxi HDD projects
• Fuzzy Fault Tree Analysis (FFTA) for risk assessment methodology mode.
Moganti (2016) | Clemson
• Developed a hierarchical safety risk assessment framework for
investigating the safety risks of HDD projects.
49
Risk and Design Considerations
Source: Ariaratnam (2007)
• Safety
• Soil Conditions
• Obstructions
• Site Access
• Project Details
• Client Specifications
• Existing Utilities
• Environmental Impact
• Restoration
• Project Specifications
• Costs
• Weather
• Traffic
50
Risk and Design Considerations
Top 5 Risks on Critical Crossings
51
Risk and Design Considerations
Additional Parameters to Consider
52
Direct, Indirect, and Social Costs of Underground Construction
Source: Ariaratnam (2007)
53
Method of Construction Selection
What we do
• Soil conditions
• Pipe material
• Pipe diameter
• Length
• Depth of cover
• Accuracy
• Marine requirements
• Fluid requirements
• Number of crossings
• Site constraints
55
Trenchless Installation Methodology Risk Assessment
56
Trenchless Installation Methodology Risk Comparison
57
Trenchless Installation Methodology Cost Comparison
Risk vs. Reward
58
Trenchless Installation Methodology Cost Comparison
Risk vs. Reward
59