Professional Documents
Culture Documents
Global Maintenance and Reliability Indicators
Global Maintenance and Reliability Indicators
Reliability Indicators
2nd Edition
A publication of
2nd Edition
Copyright © 2009 by the European Federation of National Maintenance Societies vsw and the Society
of Maintenance & Reliability Professionals. All rights reserved. Reproduction or transmittal by the
individual holder, or outside the company for whom the holder of this document is employed, of any
part of this document by electronic or mechanical means, including photocopying, microfilming, re-
cording, or by any information storage and retrieval system without the express written consent of the
EFNMS and SMRP is prohibited.
Authors:
Jerry Kahn, Tom Svantesson, Dick Olver, Al Poling
3. Harmonisation Effort...............................................................................................................................8
The standard CEN EN 15341 “Maintenance Key Performance Indicators” released in March
2007, was designed and developed from September 2003 until February 2007 by CEN Technical
Committee 319 Working Group 6, set up by the major European experts of maintenance man-
agement, with the aim to achieve a system and an architecture of indicators able to become a
common basis to measure the maintenance performance in a shared and significant way at world-
wide level.
In fact the WG 6, moving from all the maintenance indicators available in the literature and in the
guidelines, procedures and experiences of many multinational industrial companies, selected three
groups of KPIs as follows:
The characteristics of Maintenance KPIs introduced in the standard are the following:
simple and synthetic
defined in a clear and unambiguous way
measurable on homogenous basis
linked on one or more factors
suitable in management maintenance process
I do believe that this 2nd edition of this Harmonised Indicator Document, revised after the Work-
shop of Euromaintenance 2008 Congress, and many careful studies and feedback carried out by
Working Group 6, will support this perspective, giving an up-to-date and proved common base in
the process to achieve only one worldwide set of standard to measure the Maintenance Key Per-
formance Indicators
The value for an organisation to use standardized indicators or metrics such as the indicators from
the standard EN 15341 or the SMRP metrics are:
SMRP has defined 70 Best Practice Metrics to measure maintenance and reliability performance.
The process started in 2004 and is ongoing. In 2000, EFNMS defined a set of indicators to meas-
ure maintenance performance. These indicators are now incorporated in the European standard
EN 15341 “Maintenance Key Performance Indicators” released in May 2007. The joint EFNMS-
SMRP harmonization effort, which commenced in 2006, has the objective of documenting the
similarities and the differences in the SMRP metrics and the EN 15341 standards. (Figure 1.1)
The result of the activity is this document. Information on the use and application of “Global
Maintenance and Reliability Indicators” can be found at: www.HarmonisedIndicators.org.
With increased globalization and with companies producing goods and supplying services on an
international scale, the need for a common understanding of the indicators to measure mainte-
nance and availability performance is paramount. There is no doubt that this activity will eventu-
ally be a part in a global standard guideline for maintenance indicators.
The further objective for the document is to give the scale to measure a maintenance or reliability
performance. It is outside the scope of this document to give any recommended values and
thresholds for the indicators.
The indicators or metrics are supported by a set of guidelines and examples of the calculation.
This provides maintenance professionals with an easy-to- use guide for understanding of the indi-
cators, and of the components included or excluded in the calculation of each indicator.
The target group for the Harmonised Indicators Document is comprised of: Maintenance manag-
ers, Asset managers, Plant managers, Operations managers, Reliability Engineers, Technical man-
agers, General Managers or in general any other personnel who are involved with benchmarking,
or maintenance and reliability performance measurement.
It was clear from the start that both groups should strive to work toward a common set of indica-
tors to best serve the needs of the international community. However, since both groups had been
developing indicators for some time, and these indicators were already being published, a diver-
gence had already occurred in, formulas, definitions and grouping factors. Both organizations
agreed to form a joint EFNMS-SMRP working group to resolve differences between the
EN:15341 indicators and those being developed by the SMRP Best Practices Committee.
An indicator is determined to be common if it has the same basic formula or could be universally
applied. For these common indicators, it was first determined whether any differences could be
eliminated without sacrificing the objective of the indicator. If differences could not be elimi-
nated, the differences are qualified or explained. This is the essence of the harmonisation process,
which is graphically depicted in Figure 3.1
It should be noted that the grouping of indicators is different. In EN:15341, the indicators are
grouped into economic, technical and organizational sets. The SMRP indicators are categorized in
accordance with the five pillars of the SMRP Maintenance and Reliability Body of Knowledge:
Business and Management, Manufacturing Process Reliability, Equipment Reliability, Organiza-
tion and Leadership and Work Management.
When an indicator is harmonised, a statement so stating is added to the SMRP metric description.
Furthermore, the SMRP metric is recommended by EFNMS for use as a guideline for calculating
the EN 15341 indicators.
The indicators were used in the first joint SMRP-EFNMS Benchmarking Workshop, which was
held at Euromaintenance 2008 in Brussels.
EN 15341 SMRP
Indicator No Indicator Ratio Metric No. Metric name
E1 Total Maintenance Cost x 100/ 1.5 Total Maintenance Cost per RAV
Assets Replacement Value
E3 Total Maintenance Cost/ 1.3 Maintenance Unit Cost
Quantity of output
E7 Average inventory value of mainte- 1.4 Stocked MRO Inventory Value As
nance materials x 100/ a Percent of RAV
Asset Replacement Value
E8 Total internal personnel cost spent in 5.5.5. Internal Maintenance Personnel
maintenance x 100/ Costs
Total Maintenance Cost Value
E10 Total contractor cost x 100/ 5.5.71 Contractor Cost
Total maintenance cost
E11 Total cost of maintenance materi- 5.5.38 Maintenance Material cost
als x 100/
Total maintenance cost
E12 Total cost of maintenance 5.5.31 Stores Inventory Turns
materials x 100/
Average inventory value of Mainte-
nance materials
Warehouse turnover
E13 Cost for indirect maintenance person- 5.5.4 Indirect Maintenance Personnel
nel x 100/ Cost
Total Maintenance Cost
E15 Corrective maintenance cost x 5.1.1 Corrective Maintenance Cost
100/
Total Maintenance Cost
E17 Condition based maintenance cost x 5.1.5 Condition Based Maintenance
100/ Cost
Total Maintenance Cost
E18 Preventive maintenance cost x 100/ 5.1.3 Preventive Maintenance Cost
Total Maintenance Cost
E20 Maintenance shutdown cost x 100/ 5.1.9 Maintenance Shutdown Cost
Total Maintenance Cost
E21 Cost of training for maintenance/ 4.2.1 Maintenance Training Cost
Number of maintenance personnel
T2 Achieved uptime during required time 2.2 Availability
x100/
Required time
T17 Total operating time x 100/ 3.5.1 MTBF
Number of failures
T18 Number of Systems Covered by Criti- 3.1 Systems Covered by Criticality
cality Analysis x 100/ Analysis
Total Number of Systems
EN 15341 SMRP
Indicator No Indicator Ratio Metric No. Metric name
T21 Total time to restore x 100/ 3.5.2 MTTR
Number of failures
O3 Number of indirect maintenance per- 5.5.3 Indirect to Direct Maintenance
sonnel x 100/ Personnel
Number of direct maintenance person-
nel
O8 Man-hours used for continuous im- 5.7.1 Continuous Improvement Hours
provement x 100/
Total maintenance personnel man-
hours
O10 Direct maintenance personnel on 5.5.6 Craft Workers on Shift Ratio
shift x 100/
Total direct maintenance personnel
O16 Corrective maintenance man 5.1.2 Corrective Maintenance Hours
hours x 100/
Total maintenance man hours
O17 Immediate Corrective maintenance 5.4.1 Reactive Work
man-hours x 100/
Total maintenance man-hours
O18 Preventive maintenance man 5.4.2 Proactive Work
hours x 100/
Total maintenance man hours
O19 Condition based maintenance man- 5.1.6 Condition Based Maintenance
hours x 100/ Hours
Total maintenance man-hours
O20 Predetermined maintenance man- 5.1.4 Preventive Maintenance Hours
hours x 100/
Total maintenance man-hours
O21 Overtime internal maintenance man 5.5.8 Overtime Maintenance Hours
hours x 100/
Total internal maintenance man hours
O22 Number of work orders performed 5.4.4 Schedule Compliance – Work
as scheduled x 100/ Orders
Total number of scheduled work or-
ders
O23 Number of maintenance internal per- 4.2.2. Maintenance Training hours
sonnel man-hours for training x 100/
Total internal maintenance man-hours
O26 Number of the spare parts supplied by 5.5.33 Stock outs
the warehouse as requested x 100/
Total number of spare parts required
by maintenance
The terms Identical, Similar and Same Performance are used to classify the similarities and differ-
ences between the SMRP metrics and the EN indicators. Each set of indicators/metrics is classi-
fied as:
IDENTICAL – the basis of the indicators are the same although there may be some differ-
ences in how they are presented which are detailed in the comments
SIMILAR – there are some differences in the indicators that are detailed in the comments.
The difference in the two sets of calculations is estimated to affect the result by less than
5%
SAME PERFORMANCE – measuring the same performance area but there are significant
differences in how the definitions and or calculations which are detailed in the comments
The one-to-one comparison of each harmonised indicator is presented in Table 4.2 below.
E3 1.3 Similar Note 1: The difference is that EN 15341 has a broader defini-
tion and includes depreciation of maintenance owned equip-
ment and facilities in "Total Maintenance Cost" " (office, work-
shop and warehouse)
E7 1.4 Similar Note 1: Both indicators exclude depreciation cost for strategic
parts
E8 5.5.5. Similar Note 1: The difference is that EN 15341 has a broader defini-
tion and includes depreciation of maintenance owned equip-
ment and facilities in "Total Maintenance Cost" " (office, work-
shop and warehouse)
E11 5.5.38 Similar Note 1: The difference is that EN 15341 has a broader defini-
tion and includes depreciation of maintenance owned equip-
ment and facilities in "Total Maintenance Cost" (office, work-
shop and warehouse)
E12 5.5.31 Identical Note 1. The EN 15341 indicator includes only the inventory
turns of spare parts in the calculation. The SMRP metric calcu-
lates the value of the spare parts + operating parts (MRO).
However the SMRP metric 5.5.31 offers the possibility to calcu-
late spare parts separately.
Note 4: Both EFNMS and SMRP include failure finding tasks for
hidden failures in CBM ref. IEC 60300-3-11
E18 5.1.3 Similar Note 1: The difference is that EN 15341 has a broader defini-
tion and includes depreciation of maintenance owned equip-
ment and facilities in "Total Maintenance Cost" " (office, work-
shop and warehouse)
E20 5.1.9 Similar Note 1: The difference is that EN 15341 has a broader defini-
tion and includes depreciation of maintenance owned equip-
ment and facilities in "Total Maintenance Cost" " (office, work-
shop and warehouse)
T17 3.5.1 Identical Note 1: SMRP uses the Reciprocal value MTBF as Failure rate.
EN/IEC standards uses MTTF for the calculation of a Failure
Rate.(1/MTTF)
Note 2: SMRP uses MTBF for Repairable items and MTTF for
non – repairable items. This differs from the EN/IEC definition.
T21 3.5.2 Identical Note 1: The difference is in the glossary EN 15341 refers to "R
Restore" while SMRP refers to "R Repair". IEC 15191 term
191-13-08 approves "restoration" as well as "repair" Conclu-
sion: The difference is academic
Note 2: Both the SMRP metric and the EN metric include ad-
ministrative and logistic delay in the calculation.
O17 5.4.1 Same perfor- Note 1: The difference is that metric 5.4.1 measures the labour
mance hours that breaks the maintenance schedule. Indicator O17
measures only the labour hours spent on equipment failure re-
quiring immediate action regardless of schedule or no sched-
ule. When comparing Metric 5.4.1 with O17, the metric 5.4.1
will be a higher value since it measures labour hours spent on
equipment failure + poor planning + rapid change of priorities.
O18 5.4.2 Same perfor- Note 1: Proactive maintenance contains the EN 13306 defini-
mance tion of Preventive Maintenance + the part of corrective mainte-
nance tasks originating from findings during predictive and pre-
ventive activities.
O19 5.1.6 Same perform- Note 1: EN 15341 defines Conditioned Maintenance (hours) as:
ance “Preventive maintenance which includes a combination of con-
dition monitoring and/or inspection and/or testing analysis and
the following maintenance actions”.
Note 3: Both EFNMS and SMRP include failure finding tasks for
hidden failures in CBM ref. IEC 60300-3-11.
O21 5.5.8 Similar Note 1: Both SMRP and EN15342 calculate only direct person-
nel.
O23 4.2.2. Same perfor- Note 1: The difference is in the calculation method. EN 15341
mance Indicator O23 expresses the result as a percentage. SMRP
Metric 4.2.2 metric calculates the result as hours per year per
maintenance employee.
O26 5.5.33 Identical Note 1: The difference is in the way the performance is calcu-
lated. EN 15341 measures the success rate, while SMRP
measures the "un-success rate".
The indicators and metrics have been used in the maintenance community served by both SMRP and
EFNMS, and they have been used as the platform for the Benchmarking workshops organised by the two
organisations. These Benchmarking workshops have been excellent forums for understanding and use of
the indicators, and have generated a series of questions and comments for the application of the indica-
tors/metrics in the given organisation. These questions and comments have been posted and will be contin-
ued at the website: www.HarmonisedIndicators.org
The Harmonised Indicator website also has information on upcoming conferences and workshops where
global indicators will be discussed.
The Society of Maintenance & Reliability Professionals has developed standard definitions for mainte-
nance and reliability metrics used in the industry. These metrics were created by SMRP’s Best Practices
Committee, using a rigorous development process that included an initial draft, project manager review
and edit, subcommittee review and edit, Web review (for public review and comment), validation (pilot
implementation and verification), full committee review and edit, and final editing and formatting prior to
publication.
The grouping of indicators is different. In EN:15341, the indicators are grouped into economic (E), techni-
cal(T) and organizational (O) sets. The SMRP indicators are categorized in accordance with the five pillars
of the SMRP Body of Knowledge:
The numbering system utilized for the SMRP metrics is in accordance with the SMRP Body of Knowledge
(e.g., metric 1.2 belongs to the Business and Management category, metric 5.1.1 belongs to the Work
Management Category.)
When an indicator is harmonized, a statement declaring this fact is included in the SMRP metric descrip-
tion. Furthermore, the SMRP metric is recommended for use by EFNMS as a guideline or supporting
document for the European indicator.
“This metric and its supporting definitions are similar or identical to the indicator E7 in
standard EN 15341. This document is recommended by the European Federation of
National Maintenance Societies (EFNMS) as a guideline for calculating the E7 indica-
tor”. Details are provided in the document “Global Maintenance and Reliability Indicators”. In-
formation can be found at www.harmonizedindicators.org
In the following section, the SMRP metric for each of the harmonized indicators listed in Table 4.1(except
for those “In Process”) is presented. Cost metrics are expressed in $, however €, CHF, £ or any other cur-
rency may be used as appropriate.
A. Definition
The metric is the amount of money spent maintaining assets, divided by the Replacement Asset Value (RAV)
of the assets being maintained, expressed as a percentage.
B. Objectives
This metric allows comparisons of the expenditures for maintenance with other plants of varying size and
value, as well as to benchmarks. The RAV is used in the denominator to normalize the measurement given
that plants vary in size and value.
C. Formula
Maintenance Cost per RAV (%) = [Total Maintenance Cost ($) × 100] ÷ Replacement Asset Value ($)
D. Component Definitions
F. Sample Calculation
If Total Maintenance Cost is $3,000,000 annually and the Replacement Asset Value for the assets is
$100,000,000, then the Maintenance Cost as a Percent of Replacement Asset Value would be:
Maintenance Cost As a Percent of RAV = [Total Maintenance Cost ($) × 100] ÷ Replacement Asset Value
G. Harmonisation
Note 1: The difference is that EN 15341 has a broader definition and includes depreciation of maintenance
owned equipment and facilities in "Total Maintenance Cost" (office, workshop and warehouse)
Note 2: The SMRP term “Replacement Asset Value” = the EN 15341 term “Asset Replacement Value”
A. Definition
The metric is the measure of the total maintenance cost required for an asset or facility to generate a unit of
production.
B. Objectives
To quantify the total maintenance cost to produce a standard unit of production over a specified time period
(e.g. monthly, quarterly, annually, etc.). This metric provides a period over period trend of maintenance cost
per unit produced. This measure can be applied to a specific asset, a group of assets within a facility, across an
entire facility or across multiple facilities.
C. Formula
D. Component Definitions
E. Qualifications
1. Time Basis: Annually, if a shorter interval is used, it should include a weighted portion of planned outages or
turnarounds.
2. To be used by: Maintenance, Operations, Finance or other functions to evaluate and benchmark mainte-
nance cost for production units within a plant, across multiple plants or against the industry.
3. To obtain data necessary for this measure, Total Maintenance Cost includes all costs associated with
maintaining the capacity to produce over a specified time period.
4. Standardized units are industry typical measures that enable valid comparisons across similar businesses.
These are the gross standard units (disregarding any first pass quality losses) and must be the same for
comparison purposes.
F. Sample Calculation
The total maintenance cost for the year was $2,585,000. The total output from the manufacturing site in that
same year was 12,227,500 kg.
G. Harmonisation
Note 1: The difference is that EN 15341 has a broader definition and includes depreciation of maintenance
owned equipment and facilities in "Total Maintenance Cost" (office, workshop and warehouse)
Note 2: The EN 15341 definition: “Production and service quantity” expanding the definition to more than
a physical product. The SMRP component definition is “… any other standard unit of measures”. This
makes the two component definitions identical.
A. Definition
The metric is the value of maintenance, repair and operating materials (MRO) and spare parts stocked on site
to support maintenance, divided by the Replacement Asset Value (RAV) of the assets being maintained at the
plant, expressed as a percentage.
B. Objectives
This metric enables comparisons of the value of stocked maintenance inventory on site with other plants of
varying size and value, as well as to benchmarks. The RAV is used in the denominator to normalize the
measurement given that different plants vary in size and value.
C. Formula
Stocked MRO Inventory Value per RAV (%) = [Stocked MRO Value ($) × 100] ÷ Replacement Asset Value
($)
D. Component definitions
Stocked MRO Inventory Value Current book value of maintenance, repair and
operating materials held in stock at the plant site
(including consignment and vendor managed in-
ventory). Include the value of MRO materials in
all storage locations including remote stores loca-
tions whether or not the material is included in
inventory asset accounts or an allocated portion
of pooled spares. (Try to estimate the value of
“unofficial” stores in the plant even if they are
not under the control of the storeroom and even if
they are not “on the books”). Include the esti-
mated value for stocked material that may be in
stock at zero-value because of various CMMS
and/or accounting idiosyncrasies, etc. DO NOT
include raw material, finished goods or related
inventories. The monetary cost of an individual
storeroom item can be calculated as:
N
∑ (Quantity on Hand × Individual Item Cost)i
E. Qualifications
F. Sample Calculation
If Stocked MRO Inventory Value is $3,000,000, and the Replacement Asset Value (RAV) is $100,000,000,
then the Stocked MRO Inventory Value as a Percent of RAV would be:
Stocked MRO Inventory Value per RAV (%) = [Stocked MRO Value ($) × 100] ÷ Replacement Asset Value
($)
Stocked MRO Inventory Value per RAV (%) = ($3,000,000 × 100) ÷ $100,000,000
G. Harmonisation
Note 2: SMRP metrics include operating materials. The EN 15341 definition only includes maintenance
materials. This can give a higher value compared to the EN15341 indicator.
A. Definition:
Internal Maintenance Personnel Cost is the total burdened cost incurred for plant employees for the
period expressed as a percentage of the total maintenance cost for the period.
B. Objectives:
This metric enables management to monitor the contribution of internal maintenance labour costs to to-
tal maintenance costs. This value can then be compared to industry benchmarks and analyzed for cost
reduction opportunities.
C. Formula:
Internal Maintenance Personnel Cost (%) = Internal Maintenance Personnel Cost x 100
Total Maintenance Cost
D. Component Definitions
Internal Maintenance Personnel Cost Internal Maintenance Personnel cost would include
all burdened internal maintenance labour costs, both
straight time and overtime. (Internal maintenance
personnel are plant employees only, not contractors.)
Include maintenance labour costs for normal operat-
ing times as well as outages/shutdowns/turnarounds.
Include labour for capital expenditures directly re-
lated to end-of-life machinery replacement (this is
necessary so that excessive replacement – vs. proper
maintenance – is not masked). Include the cost for
staff overhead support (supervisors, planners, manag-
ers, storeroom personnel, etc.) Include the cost for
maintenance work done by operators. Do not include
labour used for capital expenditures for plant expan-
sions or improvements. Do not include contractor
labour cost. Do not include janitorial cost.
Total Maintenance Cost Expenditures for maintenance labour (including
maintenance performed by operators, e.g., TPM),
materials, contractors, services, and resources. In-
clude all maintenance expenses for outages / shut-
downs / turnarounds as well as normal operating
times. Include capital expenditures directly related to
end-of-life machinery replacement (this is necessary
so that excessive replacement versus proper mainte-
nance is not masked). Do not include capital expen-
ditures for plant expansions or improvements.
F. Example Calculation:
Following are the categories of maintenance costs used last year at the site:
G. Harmonisation
Note 1: The difference is that EN 15341 has a broader definition and includes depreciation of maintenance
owned equipment and facilities in "Total Maintenance Cost" (office, workshop and warehouse)
Note 2: Both EN 15341 E8 and the SMRP metric 5.5.5 include internal Maintenance Personnel costs. In-
ternal Maintenance Personnel cost includes blue collar, managerial, support, and supervision personnel.
A. Definition
Contractor Cost is the percentage of contractor costs of the total maintenance costs used to maintain
assets.
B. Objectives
This metric allows one to determine whether the permanent maintenance workforce is appropriately
sized and staffed for the maintenance workload. Top performers typically use some complement of
contractors for specialty crafts and/or skills, for peak or abnormal workloads (such as out-
ages/turnarounds/shutdowns) and for specialty tools/resources (e.g., cranes, vibration measurements,
etc.).
C. Formula
1. Time Basis: Should be measured annually, but can be measured monthly as well.
2. Typically used by corporate managers, plant managers, maintenance managers, human
resources managers, vice presidents to compare different sites.
3. Cannot rely on this metric alone for contractor cost assessment (i.e., the labour por-
tions may have to be considered separately.)
F. Example Calculation
If annual Contractor Maintenance Cost is $2,600,000, and annual Total Maintenance Cost is
$10,000,000, then the percent Contractor Cost would be:
G. Harmonisation
Note 1: The difference is that EN 15341 has a broader definition and includes depreciation of maintenance
owned equipment and facilities in "Total Maintenance Cost" (office, workshop and warehouse)
A. Definition
Maintenance Material Cost is the total cost incurred for materials needed to repair and maintain plant
and facility assets for the period expressed as a percentage of the total maintenance cost for the pe-
riod.
B. Objectives
This metric enables management to monitor the contribution of maintenance material costs to total
maintenance costs. This value can then be compared to industry benchmarks and analyzed for cost
reduction opportunities.
C. Formula
Maintenance Material Cost The value of all maintenance, repair, and operat-
ing material (MRO) used during the period. This
includes both stocked MRO inventory usage and
outside purchased materials, including cost to
repair a spare. Do not include material used for
capital expenditures for plant expansions or im-
provements. Do not include contractor labour
cost.
Total Maintenance Cost Expenditures for maintenance labour (including
maintenance performed by operators, e.g., TPM),
materials, contractors, services, and resources.
Include all maintenance expenses for outages /
shutdowns / turnarounds as well as normal oper-
ating times. Include capital expenditures directly
related to end-of-life machinery replacement (this
is necessary so that excessive replacement versus
proper maintenance is not masked). Do not in-
clude capital expenditures for plant expansions or
improvements.
F. Example Calculation
Following are the categories of maintenance costs used last year at the site:
G. Harmonisation
Note 1: The difference is that EN 15341 has a broader definition and includes depreciation of maintenance
owned equipment and facilities in "Total Maintenance Cost" (office, workshop and warehouse)
Note 2: It is assumed that operating materials (“O” component in MRO) is only for maintenance purposes
A. Definition
The metric is a measure of how quickly inventory is flowing through the storeroom inventory system
B. Objectives
C. Formula
D. Component Definitions
Value of Stock on Hand The current dollar value of the stock in inventory.
E. Qualifications
A given storeroom has current values and purchases over the previous twelve months as follows:
Total storeroom inventory value is $7,241,296
Total of all storeroom purchases during this period is $15,836,351
Total spare parts inventory value is $3,456,789
Total of all spare parts purchases during the period is $5,123,456
Total operating supplies inventory is $1,567,890
Total of all operating supplies purchases during the period is $9,345,678
G. Harmonisation
Note 1. The EN 15341 indicator includes only he inventory turns of spare parts in the calculation.
The SMRP metric calculates the value of the spare parts + operating parts (MRO). However the
SMRP 5.5.31 offers the possibility to calculate spare parts separately.
Note 2: If SMRP 5.5.31 calculation is applied only to the spare parts in stock excluding operating
parts, then the metrics are similar
A. Definition
Corrective Maintenance Cost is the percentage of total maintenance cost that is used to restore equipment to a
functional state after a failure or when failure is imminent. (See Figure 5.2 – Maintenance Work Types, which
is section 5.27)
B. Objectives
This metric quantifies the financial impact of work done on corrective maintenance tasks. Trending corrective
maintenance costs can provide feedback to evaluate the effectiveness of proactive activities.
C. Formula
Corrective Maintenance Cost (%) = (Corrective Maintenance Cost ( ×100) ÷ Total Maintenance Cost
D. Component Definitions
Corrective Maintenance Cost Labour, material, services, and/or contractor cost for
work done to restore the function of an asset after
failure or when failure is imminent.
E. Qualifications
F. Sample Calculation
The total maintenance cost for the month was $1,287,345. The total cost of all corrective work orders was
$817,010.
Corrective Maintenance Cost (%) = (Corrective Maintenance Cost ×100) ÷ Total Maintenance Cost
G. Harmonisation
Note 1: The difference is that EN 15341 has a broader definition and includes depreciation of maintenance
owned equipment and facilities in "Total Maintenance Cost" " (office, workshop and warehouse)
Note 2: The SMRP component definition for Corrective Maintenance “is the hours/cost to restore equip-
ment to a functional state after a failure or when a failure is imminent”. This is similar to the EN 13306
definition “. Maintenance carried out after fault recognition and intended to put an item into a state in
which it can perform a required function”
Note 4: SMRP includes part of the work identified during Condition Based Maintenance (CBM), and Pre-
ventive maintenance (PM) in the Corrective Maintenance definition.
In the EN definition for Condition Based Maintenance any work identified during CBM activities is in-
cluded in CBM indicators
A. Definition
Condition Based Maintenance Costs (shown as a percentage) is maintenance costs that are used to
measure, trend, and compare equipment conditions with known standards to detect, analyze, and cor-
rect problems before they cause functional failures. (See Figure 5.2 – Maintenance Work Types ion
Section 5.27)
B. Objectives
The objective is to track cost of condition based (predictive) maintenance tasks. Trending the percent-
age of condition based maintenance costs can provide feedback to evaluate the effectiveness of proac-
tive activities when compared to percentage of cost trends of all maintenance work types.
C. Formula
Condition Based Maintenance Costs (%) = Condition Based Maintenance Costs X 100
Total Maintenance Costs
D. Component Definitions
Condition Based Maintenance Costs Labour, material and services cost by company
personnel or contractors for work performed as
condition based maintenance. Includes operator
costs if all operator maintenance costs are in-
cluded in Total Maintenance Costs.
Condition Based Maintenance (PdM) Condition Based Maintenance (CBM) is an
equipment maintenance strategy based on meas-
uring the condition of equipment in order to as-
sess whether it will fail during some future pe-
riod, and then taking appropriate action to avoid
the consequences of that failure. The condition of
the equipment could be measured using condition
monitoring, statistical process control, equipment
performance, or through the use of human senses.
The term Condition Based Maintenance (CBM),
On-Condition Maintenance and Predictive Main-
tenance (PdM) can be used interchangeably.
E. Qualifications
F. Sample Calculation
The total maintenance cost for the month was $193,400. The total cost of predictive work orders
for company maintenance personnel was $17,100, contractor cost for predictive work totalled
$9,300, operator work orders for equipment monitoring totalled $4898 and operator preventive
work orders totalled $7947.
Condition Based Maintenance Costs (%) = Condition Based Maintenance Costs X 100
Total Maintenance Costs
= 16.18 %
EN 15341 Indicator E17 and SMRP Metric 5.1.5 have the Same Performance.
Note 1: The difference is that EN 15341 has a broader definition and includes depreciation of maintenance
owned equipment and facilities in "Total Maintenance Cost" " (office, workshop and warehouse)
Note 2: EN 15341 defines Conditioned Maintenance (cost) as: “Preventive maintenance which includes a
combination of condition monitoring and/or inspection and/or testing analysis and the following mainte-
nance actions.
SMRP counts the “condition monitoring and/or inspection and/or testing analysis” and does not include the
ensuing activities (i.e., work performed as corrective maintenance) as CBM
Conclusion: Calculating the indicator based on the SMRP metric 5.1.5 definition will give a lover number
that by the EN 15341 definition since the ensuing actions are excluded” from the SMRP definition of CBM
Note 4: Both EFNMS and SMRP include failure finding tasks for hidden failures in CBM ref. IEC 60300-
3-11
Note 5: EN 15341 and SMRP includes operator CBM hours in the calculation
A. Definition
Preventive Maintenance Cost (shown as a percentage) is the maintenance cost that is used to perform
fixed interval maintenance tasks, regardless of the equipment condition at the time. (See Figure
5.2 – Maintenance Work Types in section 5.27)
B. Objectives
The objective is to quantify the financial impact of work done as preventive maintenance tasks.
Trending the percentage of preventive maintenance costs can provide feedback to evaluate the effec-
tiveness of proactive activities when compared to percentage of cost trends of all maintenance work
types.
C. Formula
D. Component Definitions
F. Sample Calculation
The total maintenance cost for the month was $567,345. The total cost of preventive work orders
for company personnel was $227, 563, contractor purchase order amount for preventive work to-
talled $23,587, operator work orders for equipment monitoring totalled $4,600 and operator pre-
ventive work orders totalled $7,300.
= 45.55%
G. Harmonisation
Note 1: The difference is that EN 15341 has a broader definition and includes depreciation of maintenance
owned equipment and facilities in "Total Maintenance Cost" (office, workshop and warehouse)
Note 3: Minor tasks not included in the procedure detected during Preventive/Predetermined maintenance
are included in Preventive/Predetermined activities.
Please look at the Q/A section at the harmonised website for further discussions of the subject.
A. Definition
Maintenance Shutdown Cost are the total costs incurred in association with a planned maintenance
shutdown expressed as a percentage of the total maintenance cost for the period in which the shut-
down(s) occurred.
B. Objectives
This metric enables management to track the contribution of planned maintenance shutdown costs to to-
tal maintenance costs. This value can then be compared to industry benchmarks and analyzed for cost
reduction opportunities.
C. Formula
Total Maintenance Shutdown Cost Total costs incurred to prepare and execute all planned
maintenance shutdown or outage activities. Include all
staff costs incurred for planning and management of the
maintenance activities performed during the shutdown.
Include all costs for temporary facilities and rental
equipment directly tied to maintenance activities per-
formed during the shutdown. Include operator costs, if
operators work on maintenance activities during the
shutdown. Do not include costs associated with capital
project expansions or improvements that are performed
during the shutdown. Total Maintenance Shutdown
Costs are determined and reported for a specific time
period, e.g. monthly, quarterly, annually.
Total Maintenance Cost Total expenditures for maintenance labour (including
maintenance performed by operators, e.g., TPM), mate-
rials, contractors, services, and resources. Include all
maintenance expenses for out-
ages/shutdowns/turnarounds as well as normal operating
times. Include capital expenditures directly related to
end-of-life machinery replacement (this is necessary so
that excessive replacement versus proper maintenance is
not masked). Do not include capital expenditures for
plant expansions or improvements. Maintenance costs
are for activities on work orders. (i.e., tied to work or-
ders)
F. Example Calculation:
Following are the categories of costs incurred for the annual maintenance shutdown at the site:
G. Harmonisation
Note 1: The difference is that EN 15341 has a broader definition and includes depreciation of maintenance
owned equipment and facilities in "Total Maintenance Cost" (office, workshop and warehouse)
Note 2: The SMRP metric includes the planning and preparation cost for a shutdown. Planning and prepa-
ration costs are expected to be less than 5% of the shutdown cost. EN 13541 defines the cost as: “Cost of
maintenance performed during shutdowns”. This excludes the planning and preparation costs.
.
A. Definition
Maintenance training costs are the dollar expenditures for the formal training that maintenance per-
sonnel receive annually. It is expressed as costs per employee.
B. Objectives
This metric is designed to measure how much formal training is being provided to improve the skills
of the maintenance personnel.
C. Formula
Training Costs per Employee = Total Training Costs / Number of Maintenance Employees.
Can also be expressed as a percentage of the total labour costs worked by a maintenance department
D. Component Definitions
F. Sample Calculation:
Training Costs (travel expenses, stationary, registration fees, instructor fees, etc.)
$ 0 Safety (completed in house)
$ 6,500 Laser alignment
$ 7,000 Hydraulic systems
$ 6,500 Circuit analysis
$ 6,000 Job planning
$ 1,600 Team building
$ 0 Math skill (completed in house)
$ 3,000 Annual SMRP Conference (registration costs, travel, etc.)
$ 4,800 Storeroom management
$35,400 = Classroom training for the year
Training Costs per Employee = Total Training Costs / Number of Maintenance Employees =
Looking at training costs as a percent of the total costs, the maintenance department total costs for the year
was 42,240 man-hours at a cost of $1,162,000
% Training Costs = Annual Training Costs / Total Department Costs Worked * 100%
Looking at the training costs just for the electrical craft, the 4 electricians received the following training:
Labour
$1,200 Safety
$1,550 Circuit analysis
$ 775 Team building
$3,525 = Total labour for the year
$11,625 = Grand Total
G. Harmonisation
Note 1: The SMRP term: “Maintenance Employees” is similar to EN 15341 “Direct + Indirect personnel”
Note 2: SMRP includes participation in conventions, seminars and workshops under the umbrella of SMRP
Body of Knowledge in “Training hours”
Note 4: The result of the indicator E21 is unit of value/person. Metric 4.2.1 offers the possibility to calcu-
late the result as a percentage.
A. Definition
Mean Time Between Failures (MTBF) is the average length of operating time between failures for an asset or
component. MTBF is used primarily for repairable assets and components of similar type. A related term,
Mean Time to Failure (MTTF) is used primarily for non-repairable assets and components, e.g. light bulbs and
rocket engines. Both terms are a measure of asset reliability and are also known as Mean Life. MTBF is the
reciprocal of Failure Rate (λ) at constant failure rates.
B. Objectives
This metric is used to assess the reliability of a repairable asset or component. Reliability is usually expressed
as the probability that an asset or component will perform its intended function without failure for a specified
period of time under specified conditions.
C. Formula
D. Component Definitions
E. Qualifications
Assume an asset had 10 failures in 1000 hours of operation, as indicated in the diagram below,
Failures
1 2 3 4 5 6 7 8 9 10
100 152 192 297 433 485 689 757 823 951
1000
Hours
G. Harmonisation
Note 1: SMRP uses the reciprocal value MTBF as failure rate. EN/IEC uses MTTF for the calculation of a
failure rate (1/MTTF).
Note 2: SMRP uses MTBF for repairable items and MTTR for non-repairable items. This differs from the
EN/IEC definition.
A. Definition:
The metric Systems Covered by Criticality Analysis is the ratio of the number of systems in a fa-
cility for which a criticality analysis has been performed divided by the total number of systems in
the facility, expressed as a percentage.
B. Objectives:
The purpose of a systems criticality analysis is to identify those systems which pose the most seri-
ous consequences or adverse effects if they fail. This will direct maintenance resources and im-
provement initiatives can be focused on these failure modes
The objective of the metric is to show progress towards applying criticality analyses to all critical
systems.
C. Formula:
Systems Covered by Criticality Analysis (%) = [Number of Systems for which a criticality analysis
has been performed ÷Total Number of Systems] X 100
D. Component Definitions:
Criticality Analysis A quantitative analysis of events and faults and the ranking
of these in order of the seriousness of the combination of
the seriousness of their consequences and frequency of oc-
currence.
Critical System A system that is vital to continued operations, will signifi-
cantly impact production, or have inherent risks to person-
nel safety or the environment if failed
1. Time Basis: Calculate at the start of a maintenance improvement initiative and track in
accordance with the initiative reporting schedule. Track annually thereafter.
2. Used by: Corporate management, plant managers and reliability engineers.
3. The assets which are included in each system should be as defined by the management of
that facility or organization. The term “system” must be related and transferred to the facil-
ity’s technology (i.e., assets, functional locations)
4. The type of criticality analysis can range from use of a simple criticality table to a formal
Failure Modes and Effects Criticality Analysis (FMECA).
5. Considerations for criticality analysis include, for example, safety, environment, produc-
tion, product quality, and cost.
6. The analysis must be formally documented and assessments must be risk-based.
7. Criticality analysis should be performed on all new systems prior to installation and com-
missioning.
8. Before performing a criticality analysis, all systems must be ranked/assessed to identify
critical systems, and separate these from non – critical systems (see Figure 1)
9. The goal should be to have all critical systems covered by a criticality analysis
10. All non-critical systems should have their failure impacts on the process reviewed periodi-
cally to determine if the original criticality assessment was accurate
F. Sample Calculation:
The XYZ Company has started a new maintenance improvement initiative at its ABC plant. The plant Re-
liability Engineer determined that during the last improvement program five years ago, criticality analyses
were performed on 337 of the facility’s 1,427 assets (hereafter termed systems).
Systems Covered by Criticality Analysis (%) = [Number of Systems for which a criticality analysis has
been performed /Total Number of Systems] X 100
This provides the starting point for tracking improvement in this metric, and provides a benchmark to a
concurrent improvement initiative being conducted at plant DEF.
G. Harmonisation
A. Definition
Mean Time to Repair or Replace (MTTR) is the average time needed to restore an asset to its full opera-
tional capabilities after a failure. MTTR is a measure of asset maintainability, usually expressed as the
probability that a machine can be restored to its specified operable condition within a specified interval of
time, regardless of whether an asset is repaired or replaced.
B. Objectives
The objective of this metric is to assess maintainability, including the effectiveness of plans and proce-
dures.
C. Formula
MTTR = total repair or replacement time (hours) ÷ number of repair or replacement events
D. Component Definitions
Repair /Replacement Event The act of restoring the function of an asset after
failure or imminent failure by repairing or replac-
ing the asset.
E. Qualifications
Assume an asset had 10 failures in 1000 hours of operation and repair times were 2, 6, 10, 6, 5, 10, 1, 2, 5
and 3 hours as shown in the diagram below.
FAILURES
1 2 3 4 5 6 7 8 9 10
Repair Time 2 6 10 6 5 10 1 2 5 3
100 152 192 297 433 485 689 757 823 951
1000
Hours
MTTR = total repair or replacement time (hours) ÷ number of repair or replacement events
MTTR = (2+6+10+6+5+10+1+2+5+3) ÷ 10
MTTR = 50 hours ÷ 10
G. Harmonisation
Note 1: The difference is in the glossary EN 15341 refers to "R Restore" while SMRP refers to "R Re-
pair". IEC 15191 term 191-13-08 approves "restoration" as well as "repair" Conclusion: The difference is
academic
Note 2: Both the SMRP metric and the EN metric include administrative and logistic delay in the calcula-
tion.
This definition is similar to the definition used in many ISO/IEC EN standards: “Termination of the ability
to perform a required function”
A. Definition:
Continuous Improvement Hours is the percentage of internal maintenance labour hours that is used
to improve the current performance to an increased level. Continuous Improvement Hours are used
to improve the performance for, but not limited to safety, quality, and environment, availability, out-
put and cost.
B. Objectives:
The objective of the metric is to quantify and track the internal labour hours used to improve the de-
velopment of the maintenance performance and the overall performance (e.g. safety, output cost and
environmental) of the operation/company.
C. Formula:
Continuous improvement hours =: Internal labour hours used for continuous improvement X 100
Total internal maintenance personnel labour hours
D. Component Definitions
Internal labour hours The internal direct and indirect labour hours used on improvement processes
used for continuous intended to improve the current level of availability, reliability, maintain-
improvement ability, quality, safety, environment and costs.
Examples are hours used for systematic critical analysis, identification of
improvements, participation in projects and their preparations, as instructor
for training and education internally and externally, or, finally, for safety,
quality or environmental audit or schemes. Do not include labour hours for
capital expenditures for plant expansions or improvements
F. Sample Calculation:
The internal maintenance labour used during January 2007 was 1000 hours, which was made up of
labour, support and management hours (both direct and indirect).
The monthly report from the CMMS for January 2007 showed:
Mechanics and supervisor hours used for a safety fish bone analysis on Pump # 117 12 hours
Contractor man hours used for a safety fish bone analysis on Pump # 117 10 hours
(Note: Contractor hours are external and excluded from the metric calculation)
Electrical hours used in a task force to improve the quality on line AA 28 hours
Hours used for an improvement of the lifetime on Fan #1017 24 hours
Hours used for a project proposal to debottlenecking of line BB,
leading to a potential improved output on 15 % 6 hours
Hours used as instructor in training of a new method for pump alignment
of internal staff 9 hours
Hours used to participate in an expansion capital project on dryer # 2 25 hours
(Note: Capital man hours are excluded from the metric calculation)
G. Harmonisation
A. Definition
The metric is the ratio of the number of maintenance craft workers on shift to the total number of maintenance
craft workers.
B. Objectives
This metric is an indirect measurement of equipment reliability since frequent unexpected failures require
craft workers on shift to expedite repairs. Trending the number of craft workers on shift can also help
identify maintenance issues on the off shifts and can be used to benchmark with other companies or be-
tween departments within the same plant.
C. Formula
Craft Worker on Shift Ratio = Total Number of Maintenance Craft Workers on Shift ÷ Total Number of
Maintenance Craft Workers
D. Component Definitions
Maintenance Craft The worker responsible for executing maintenance work orders (e.g. electri-
Worker cian, mechanic, PM/PdM technician, etc.).
On Shift Maintenance craft workers who rotate with or are assigned work hours
aligned with a production shift are considered “on shift.” Maintenance craft
workers on shift typically work on emergency work and are not identified
with the main group of maintenance craft workers that work day shift.
E. Qualifications
A given maintenance department has 24 mechanics with 3 on shift, 8 Electricians with 2 on shift and 4 in-
strumentation technicians with 1 on shift.
Craft Worker on Shift Ratio = Total Number of Maintenance Craft Workers on Shift ÷ Total Number of
Maintenance Craft Workers
F. Harmonisation
Note 1: "On call" craft workers are excluded from the calculation for both metrics/indicators
Note 2: SMRP Metric calculates the formula as a ratio. EN 15341 indicator calculate the formula as per-
centage.
Note 3: The term “Maintenance Craft worker” is similar to EN 15341: “Direct maintenance personnel”
A. Definition
Corrective Maintenance Hours is the percentage of total maintenance labour hours that is used to restore
equipment to a functional state after a failure or when failure is imminent. (See Figure 5.2 – Maintenance
Work Types in Section 5.27)
B. Objectives
This metric quantifies the labour resource impact of work done on corrective maintenance tasks. Trending
corrective maintenance hours can provide feedback to evaluate the effectiveness of proactive activities.
C. Formula
Corrective Maintenance Hours (%) = (Corrective Maintenance Labour Hours × 100) ÷ Total Maintenance
Labour Hours
D. Component Definitions
Corrective Mainte- The worker responsible for executing maintenance work orders (e.g. electri-
nance Labour Hours cian, mechanic, PM/PdM technician, etc.).
Total Maintenance Total maintenance labour is expressed in hours and includes all maintenance
Labour Hours labour hours for normal operating times as well as outages, shutdowns and
turnarounds. If operator hours spent on maintenance activities are captured,
they should be included in the numerator and denominator of all applicable
metrics. Include labour hours for capital expenditures directly related to end-
of-life machinery replacement so that excessive replacement versus proper
maintenance is not masked. Do not include labour hours used for capital
expansions or improvements.
E. Qualifications
The total internal maintenance labour used during the month was 2400 hours of straight time and 384 hours
of overtime. Maintenance done by contractors consumed another 480 hours. Corrective maintenance la-
bour during the month was 1832 hours.
Corrective Maintenance Hours (%) = (Corrective Maintenance Hours × 100) ÷ Total Maintenance Labour
Hours
F. Harmonisation
Note 1: The SMRP component definition for Corrective Maintenance “is the hours/cost to restore equip-
ment to a functional state after a failure or when a failure is imminent”. This is similar to the EN 13306
definition “. Maintenance carried out after fault recognition and intended to put an item into a state in
which it can perform a required function”
Note 2: SMRP includes part of work identified during Condition Based Maintenance (CBM) and Preven-
tive Maintenance (PM) in the Corrective Maintenance definition. In the EN definition for Condition Based
Maintenance any work identified during CBM activities is included in the CBM indicators
A. Definition
Reactive work is maintenance work that breaks into the weekly schedule.
B . Objectives
This metric is used to measure and monitor the amount of work that is performed outside of the weekly
schedule.
C . Formula
Reactive Work (%) = [Work that breaks into the weekly schedule (hrs) ÷ Total Maintenance Labour Hours] ×
100
D . Component Definition s
Total Maintenance Total maintenance labour is expressed in hours and includes all maintenance
Labour Hours labour hours for normal operating times as well as outages, shutdowns and
turnarounds. If operator hours spent on maintenance activities are captured,
they should be included in the numerator and denominator of all applicable
metrics. Include labour hours for capital expenditures directly related to end-
of-life machinery replacement so that excessive replacement versus proper
maintenance is not masked. Do not include labour hours used for capital
expansions or improvements.
Weekly Schedule The list of maintenance work to be done in the week. It is usually finalized
three to four days before the start of the work week.
E . Qualifications
The total hours worked in the month by the maintenance organization on all work types and priorities is
1000 hours. A total of 350 hours was worked on emergency and similar work that was not on the weekly
schedule.
Reactive Work (%) = [Work that breaks into the weekly schedule (hrs) ÷
Total Maintenance Labour Hours] × 100
G. Harmonisation
EN 15341 Indicator O17 and SMRP Metric 5.4.1 have the Same Performance
Note 1: The difference is that metric 5.4.1 measures the labour hours that breaks the maintenance schedule.
Indicator O17 measures only the labour hours spent on equipment failure requiring immediate action re-
gardless of schedule or no schedule. When comparing Metric 5.4.1 with O17, the metric 5.4.1 will be a
higher value since it measures labour hours spent on equipment failure + poor planning + rapid change of
priorities.
Depending on the application of the metric, one should be careful about making comparisons
A. Definition
Proactive work is maintenance work that is completed to avoid failures or to identify defects that could
lead to failures. It includes routine preventive and predictive maintenance activities and work tasks identi-
fied from them.
B. Objectives
This metric is used to measure and monitor the amount of work that is being done in order to prevent fail-
ures or to identify defects that could lead to failures.
C. Formula
Proactive Work (%) = [Work completed on preventive maintenance work orders, predictive maintenance
work orders, and corrective work identified from preventive and predictive work orders (hrs) ÷ Total Mainte-
nance Labour Hours] × 100
D. Component Definitions
F. Sample Calculation
The total actual hours worked in the month by the maintenance organization is 1000 hours. A total of 150
hours was worked on preventive maintenance, 100 hours was worked on predictive maintenance and 400
hours was worked on corrective maintenance from preventive and predictive maintenance work orders.
Proactive Work (%) = [Work completed on preventive maintenance work orders, predictive maintenance
work orders, and corrective work Identified from preventive and predictive work orders (hrs) ÷ Total
Maintenance Labour Hours] × 100
Proactive Work (%) = [(150 hours + 100 hours + 400 hours) ÷ 1000 hours] × 100
G. Harmonisation
EN 15341 Indicator O18 and SMRP Metric 5.4.2 have the Same Performance
Note 1: Proactive maintenance contains the EN 13306 definition of preventive maintenance + the part of
corrective maintenance tasks originating from findings during predictive and preventive activities
A. Definition
Condition Based Maintenance Hours (shown as a percentage) is maintenance labour hours that are
used to measure, trend, and compare equipment conditions with known standards to detect, analyze,
and correct problems before they cause functional failures. (See Figure 5.2 – Maintenance Work
Types in Section 5.27)
B. Objectives
The objective is to quantify the labour resource impact of work done as condition based (predictive)
maintenance tasks. Trending the percentage of condition based maintenance hours can provide feed-
back to evaluate the effectiveness of proactive activities when compared to the percentage of labour
hour trends of all maintenance work types.
C. Formula
Condition Based Maintenance Hours (%) = Condition Based Maintenance Hours X 100
Total Maintenance Labour Hours
D. Component Definitions
Condition Based Maintenance Hours Total craft hours, company or resident contractor
for condition based maintenance work per-
formed. Includes operator hours if all operator
maintenance hours are included in Total Mainte-
nance Labour Hours.
Condition Based Maintenance (PdM) PdM is an equipment maintenance strategy based
on measuring the condition of equipment in order
to assess whether it will fail during some future
period, and then taking appropriate action to
avoid the consequences of that failure. The con-
dition of the equipment could be measured using
condition monitoring, statistical process control,
equipment performance, or through the use of
human senses. The term Condition Based Main-
tenance, On-Condition Maintenance and Predic-
tive Maintenance can be used interchangeably.
E. Qualifications
F. Sample Calculation
The total maintenance labour hours for the month were 3753 hours of straight time (operator main-
tenance hours not included) and 47 hours of overtime. Oil samples drawn by a contract sampling
crew consumed 196 hours and the round based vibration readings by operators consumed another
24 hours. The total hours from Condition Based Maintenance work orders by the company mainte-
nance staff totalled 876 hours.
Condition Based Maintenance Hours (%) = Condition Based Maintenance Hours X 100
Total Maintenance Labour Hours
= 28.21 %
EN 15341 Indicator O19 and SMRP Metric 5.1.6 have the Same Performance
Note 1: EN 15341 defines Conditioned Maintenance (hours) as: “Preventive maintenance which includes a
combination of condition monitoring and/or inspection and/or testing analysis and the following mainte-
nance actions”. SMRP counts the “condition monitoring and/or inspection and/or testing analysis” and
does not include the ensuing activities (i.e., corrective maintenance) as CBM. Conclusion: Calculating the
indicator based on the SMRP metric 5.1.5 definition will give a lover number that by the EN 15341 defini-
tion since “..the ensuing actions are excluded” from the SMRP definition of CBM
Note 3: Both EFNMS and SMRP include failure finding tasks for hidden failures in CBM ref. IEC 60300-
3-11
Note 4: EN 15341 and SMRP includes operator CBM hours in the calculation
A. Definition
The percentage of Preventive Maintenance hours is maintenance labour that is used to perform fixed
interval maintenance tasks, regardless of the equipment condition at the time. (See Figure 5.2 –
Maintenance Work Types in Section 5.27).
B. Objectives
The objective is to quantify the labour resource impact of work done on preventive maintenance tasks.
Trending the percentage of preventive maintenance hours can provide feedback to evaluate the quantity
of proactive activities when compared to the percentage of labour hour trends of all maintenance work
types.
C. Formula
D. Component Definitions
F. Sample Calculations
The total maintenance hours for the month was 1800 hours of straight time (operator maintenance
hours not included) and 125 hours of overtime. A pump bi-annual overhaul done by resident con-
tractors consumed 48 hours and the monthly scheduled operator rounds of lubrication, filter
changes, burner cleanings and adjustments consumed another 150 hours. The total hours from pre-
ventive work orders by the company maintenance staff totalled 452 hours.
= 25.97 %
G. Harmonisation
Note 2: Minor tasks not included in the procedure detected during Preventive/Predetermined maintenance
are included in Preventive/Predetermined activities.
Please look at the Q/A section at the Harmonised Indicator website for further discussions
A. Definition
The metric is the number of overtime maintenance labour hours used to maintain assets, divided by the total
maintenance labour hours to maintain assets, expressed as a percentage.
B . Objectives
This metric is used to determine whether the permanent maintenance workforce is performing effectively and
appropriately staffed for the maintenance workload.
C . Formula
Overtime Maintenance Hours (%) = (Overtime Maintenance Labour Hours ÷ Total Maintenance Labour
Hours) × 100
F. Sample Calculation
In a given month overtime maintenance labour hours is 500 and the total maintenance labour hours is
10,000 for the same month, overtime maintenance hours would be:
Overtime Maintenance Hours (%) = (Overtime Maintenance Labour Hours ÷ Total Maintenance Labour
Hours) × 100
G. Harmonisation
Note 2 Permanent contractors on site are included in the calculation of SMRP metrics 5.5.8. EN 15341 ex-
cludes contractors
A. Definition
The metric is a measure of adherence to the weekly maintenance work schedule expressed as a percent of total
number of scheduled work orders.
B. Objectives
This metric measures compliance to the weekly maintenance schedule and reflects the effectiveness of the
work scheduling process.
C. Formula
Scheduled Compliance (%) = (Number of work orders performed as scheduled ÷ Total number of scheduled work orders)
× 100
D. Component Definitions
E. Qualifications
For a given week there were 135 work orders scheduled. At the end of the week 113 scheduled work orders
and 45 emergency work orders were completed.
Scheduled Compliance (%) = (Number of work orders performed as scheduled ÷ Total number of scheduled work orders)
× 100
Note: The emergency work orders do not count as they broke into the weekly schedule.
G. Harmonisation
Note 1: Both metrics/indicators measures scheduled compliance - Not planned and scheduled performance.
Note 2: Metric 5.4.4 is calculated on a weekly basis. EN O22 is calculated on any given time frame - also
weekly.
A. Definition
The metric is the number of hours of formal training that maintenance personnel receive annually. It is
expressed as hours per employee.
B. Objectives
This metric measures the investment in training to improve the skills and abilities of maintenance personnel.
C. Formula
This metric can also be expressed as a percentage of the total number of hours worked by a maintenance
department.
D. Component Definitions
E. Qualifications
F. Sample Calculation
A given maintenance organization consists of a manager, maintenance engineer, planner, two foremen, ten
mechanics, four electricians and a storeroom clerk. Training hours during the year included
The maintenance department total hours for the year were 38,400 man hours.
Maintenance Training Hours (%) = (Training Hours ÷ Total Hours Worked) × 100
The total hours of electrician training for the year = 48 + 64 + 32 = 144 hours
EN 15341 Indicator O23 and SMRP Metric 4.2.2 have the same performance
Note 1: The difference is in the calculation method. EN 15341 Indicator O23 expresses the result as a per-
centage. SMRP Metric 4.2.2 metric calculates the result as hours per year per maintenance employees.
Note 2 Nominator is similar for both metrics including training hours for direct and indirect personnel.
EN 15341 O23 expresses the indicator as a percentage of "Total Maintenance personnel man hours”, which
includes contractor hours and excludes indirect personnel
SMRP Metric 4.2.2 expresses the result as a ratio per maintenance employee (excluding contractors and
including direct and indirect personnel)
Note 3.The SMRP term: “Maintenance Employees” is similar to EN 15341 “Direct + Indirect personnel”
Note 4: SMRP includes participation in conventions, seminars and workshops under the umbrella of SMRP
Body of Knowledge in “Training hours”. This difference is estimated to impact the calculation with less
than 5 %
A. Definition
The metric is a measure of the frequency that a customer goes to the storeroom inventory system and
cannot immediately obtain the part needed.
B. Objectives
The metric is used to maintain the appropriate balance in stocked inventory. Too much inventory in-
creases working capital unnecessarily. Too little inventory results in unnecessary delay and equip-
ment downtime that can negatively impact costs and profits. Stock Outs is a measure that can be
used to minimize the waste associated with excess inventory.
C. Formula
D. Component Definitions
Number of Inventory Requests with Stock An inventory request is considered a stock out if
Out the inventory item is normally stocked on site
and the inventory request is for a normal quantity
of the item, but the inventory on hand is insuffi-
cient to fill the request
Total Number of Inventory Requests The total of all requests for items listed as
stocked in the storeroom inventory system
E. Qualifications
A storeroom receives 1,234 stock requests in a given month. There were 30 requests in this same month
where there was insufficient inventory to fill the request. Analyses of these 30 requests found 4 that were
excessive orders beyond the normal request quantities; therefore these 4 requests did not meet the criterion
for stock outs. The remaining 26 requests were stock outs.
G. Harmonisation
Note 1: The difference is in the way the performance is calculated. EN 15341 measures the success rate,
while SMRP measures the "un-success rate"
Note 2:_The formula for the calculation of the metric 5.5.33 based on the O26 calculation is:
100 % - (Value from EN 15341, O26) = Result for SMRP 5.5.33 metric
The SMRP defined work types can be compared to those of standard EN 13306 in Figure 5.3
Scheduled, continious
Scheduled
or on request
These documents provide additional guidance and/or clarification on the use of particular SMRP Metrics
6.2 References
IEC 60300-3-11, 2nd Ed. Dependability management - Part 3-11: Application guide - Reliability
centred maintenance
ISO 14224 Petroleum and Gas industries – Collection and exchange of reliability and maintenance data for
equipment, Annex E
CEN – www.cen.org
EFNMS – www.efnms.org
SMRP - www.smrp.org
The European Federation of National Maintenance Societies, EFNMS is the European umbrella organisa-
tion for national maintenance societies in Europe. The organisation was founded in 1971. Today EFNMS
has 21 members and several candidates for membership.
The mission for EFNMS is to coordinate and represent the National Maintenance Societies supporting a
knowledge network and providing means to improve the know-how and direction of Maintenance in the
European Union. With the aim, by means of maintenance to raise the effectiveness and competitions of
Industry and infrastructure of Europe thereby providing social environmental and economical
In 1995, Working Group 7 (WG7) was formed and tasked with selecting a number of benchmark indicators
that were regarded as important when measuring maintenance performance. In 2002, they unveiled the set
of thirteen indicators listed in Table 1.
Members of Working Group 7 actively participated in the standardisation activities of the European Com-
mittee for Standardization Technical Committee 319 - Maintenance (CEN/TC 319). The technical commit-
tee’s efforts resulted in publication of 71 indicators in the European Standard EN:15341 “Maintenance Key
Performance Indicators” in March 2007.
The European Maintenance Benchmarking Committee (previously called WG 7) utilizes the indicators in
EN: 15341:2007 to conduct workshops through Europe and the Middle East, wherein nearly 200 partici-
pants in 18 workshops have been given the opportunity to calculate indicators on their company’s mainte-
nance and availability performance and to gain a deeper understanding in their use.
For more information about the EFNMS, please visit their website at www.efnms.org
The SMRP organization was formed and chartered in 1992 as a not-for-profit, 501(c) corporation. SMRP
promotes information exchange through a network of maintenance and reliability professionals, supports
maintenance and reliability as integral part of business and asset management, and seeks to be a voice that
advances innovative reliability practices.
The Society for Maintenance and Reliability Professionals (SMRP) is an independent, not-for-profit pro-
fessional society dedicated to instilling excellence in maintenance and reliability, in all types of manufac-
turing and service organizations, worldwide. The SMRP Best Practices Committee was chartered with
identifying and standardizing maintenance and reliability metrics (indicators) and terminology. This devel-
opment work commenced in 2004 and continues to the present day. The first set of approximately 30 indi-
cators, termed metrics, was presented in 2006. Currently, there are 70 metrics published or under develop-
ment. Published metrics can be purchased on the SMRP web site for a nominal fee.
The SMRP Best Practices Committee has also developed a workshop which utilizes the SMRP metrics.
For more information about the SMRP, please visit their website at www.smrp.org.
e-mail: rolver@agrium.com
Phone number: +1 (403) 255-7349
Mr. Kahn has over 30 years experience working for international tech-
nology-driven companies. He has worked in the fields of pulp & paper,
nuclear power engineering, non – destructive examination, simulation
and modeling, global research program development, strategic planning, cost engineering, customer ser-
vice engineering, marketing and industrial plant maintenance.
He is a Past President of the Georgia Society of Professional Engineers (GSPE), the USA delegate to the
Maintenance Committee (COPIMAN) of the Pan American Federation of Engineering Societies (UPADI),
and a Fellow Member of the National Society of Professional Engineers (NSPE). Mr. Kahn is also a mem-
ber of the Society for Maintenance & Reliability Professionals (SMRP), the American Institute of Chemi-
cal Engineers (AIChE), the American Society for Quality (ASQ), and the Standards Engineering Society
(SES), where he serves on the Standards Development Committee.
e-mail: jerry.kahn@siemens.com
Phone number: +1 (713) 504-4730
In his role as Technical Director with SMRP, Al works with the Body of Knowledge directorate commit-
tees: Benchmarking, Best Practices and Maintenance & Reliability Knowledge. Al’s primary objective is
to facilitate the completion of the respective committee deliverables and provide value to SMRP members
and to the maintenance and reliability industry at large.
e-mail: apoling@smrp.org
Phone: +1 (832) 295-3009
Web: www.smrp.org
e-mail: ts@tsmc.dk
Phone number: +45 (2483) 9817
www.tsmc.dk