Professional Documents
Culture Documents
APD Guideline 2024
APD Guideline 2024
1. AutoCAD
2. Google Earth
3. Excel
APD PACKAGE
1. Basic Map
2. Home Pass
3. Bizz Pass
4. Distance
5. Drop Wire
6. Hub Box
7. Sub Box
8. End Box
9. Hub/sub/endbox ID
10. Precon (5m, 50m, 80m, 100m, 150m, 200m,
250, 300m)
11. Pole ID
12. Sling Wire
13. Uncovered Homepass
DROP WIRES
⚫ Grouping 16 home pass first for every Sub/End box. If not possible, we can cover < 16 ⚫ Put the drop wire on the middle node
home pass. of the house number
⚫ Sub/endbox can cover home pass < 120m as long as there are poles in between
DROP WIRES
⚫ Last pole can only cover home pass < 35m
Sub/endbox ID format:
FXXXXXD02S01A04
FXXXXXD01S02D01
S0X → Nomor Splitter
POLE ID
⚫ Continue to Add the pole ID (XXA)
Start from the Hub to the first subbox
PRECON CABLE & LINK BUDGED
Precon Cable Lists: Add 10m tolerance when adding the precon cable.
- Precon 5m Example: 41m FAT distance use precon 80m
- Precon 50m
- Precon 80m Note: If Need cable more than 300m, can be combine
- Precon 100m with add closure
- Precon 150m Case: cable span 430m then need propose Precon 450m
- Precon 200m Solution: Propose Precon 200 + Precon 250
- Precon 250m
- Precon 300m
PRECON CABLE & LINK BUDGED
Subbox/Endbox
Homepass
Homepass + Bizzpass
APD Case
Lebar jalan > 8 m, gunakan 2 pole terpisah untuk cover setiap sisi HP
Pada Google street view garisnya berwarna kuning
APD Case
Lebar jalan > 8 m, gunakan 2 pole terpisah untuk cover setiap sisi HP
Pada Google street view garisnya berwarna kuning
APD FORMAT
Latihan APD
Kerjakan APD package untuk contoh basemap berikut:
Homepass: ± 99 HP
Maksimal: 1 FDT
Thank you. Bring digital to every person, home and
organization for a fully connected,
intelligent world.