You are on page 1of 1

N

J M
A B C D E F G H E L N P Q R S T U
1020 1200
9900 9900 3240 4000 2660 9900 9830 1850 4500 2420 2580 7250 6600 3450
Notes:
86300
32050 1.All dimensions are in millimeters and levels
are in meters unless otherwise specified.
1150

2.Drawing shall not be scaled, only written


8 1050
B1 B1 B1 B1 B1 B1 B1 B1 B1 B1
dimensions to be followed.
3.Any Error or Discrepancies in the
P1 P1 P1 P1 P1 P1 P1 P1 P1 P1 P1
Drawings are to be brought to the notice.
of the Architect/ Engineers.
6900

SBC-320KN/M2 4. This drawings shall not be used other than


B1

B1

B1

B1

B1

B1

B1

B1

B1

B1

B1
the purpose marked/issued specified.
5. The drawings to be read with conjuction
7 P4

B1
P1

B1
P1

B1
P2

B1
P1

B1
P1

B1
P1

B1
P1

B1
P1

B1
P1
B1
P1

with structural drawings.


6. All the drawings prepared by Design
and structural consultants are as per
4250

B4

NBC norms and guidelines.


RAFT 650 THICK REMOVAL OF FORMWORK(SHUTTERING) :
6
B2

B2

B2

B2

B1

B1

B1

B1
27500

Shuttering of any part of the structure shall not be


S.W2
2000

1200X1800 BEAM removed until the concrete attains 70% of the specified
5 3000X1800 PEDESTAL
strength of concrete however the following minimum
period (after final pour ) shall be allowed before
removal of shuttering as per clause 11.3.1, is 456:2000
3650

B4

P1 A. Vertical side of shuttering of columns,walls & beams


- 24 hours
4 B2 B2 B2 B2 B2 B3 B3 B3 B1 B. Bottom shuttering of slabs (keeping the props)
- 3 days
P2 P2 P2 P2 P1 P1 C. Bottom shuttering of beams (keeping the props)
- 7 day
D. Props to slabs :

B1

B1
B4
6900

B1

B1
i .spanning upto 4.5 m - 7 days
B4

B4
B4

B4
B4

i i .spanning over 4.5 m - 14 days


E. Props to beams & arches :
P1
i .spanning upto 6 m - 14 days
B1 B1 B4 B4 B1
3 P2 B2
P4
B4 B4 B4
P1

i i.spanning over 6 m
LAP JOINTS FOR REINFORCEMENT BARS :
- 21 days
RAFT LINE
3290

1. At any cross section of the member,not more than


50% of the bars shall be lapped.
2 2. Laps shall be staggered with a minimum centre to
centre distance of 1.3 times lap length of the bar for
PCC LINE tension & compression members.
3. Development length (ld) shall be as per (sp:34-1999)
NF2 NF1 NF1 NF1 NF2 table below:
NF1 NF1 NF1
a) Development length for column bars - 40d
b) Development length for beam bars - 50d
4. Laps in columns shall be provided at mid height of
floor and not at slab level .
11105

5. Laps in beams and slabs shall be provided at the


point of contraflexure.
6. Welding of bars shall be done as a stitch weld for 5
3000 times diameter of bar and a gap of 5 times higher
2700
1500 diameter bar and again welding for another 5 times
1350
diameter of bar using arc welding and special
electrodes after obtaining prior written approval from
1350

the structural designer.


1

3000
2700

7. Detailing of rebars shall confirm to sp-34 & is 13920.


GENERAL NOTES:
NF2 1. Concrete grade shall be M35(design mix) confirming to
NF1 NF1 NF1 NF1 NF1 NF2 M-35 GRADE CONCRETE is 456:2000
2. Minimum cement content = 380 kg/m3.
3. Min.grade of reinforcement marked thus (y) shall be Fe
550D confirming to IS 1786-1985
LAYOUT COLUMNS-BEAM SLAB , RC WALLS & FOOTING 4. Clear cover for reinforcement
01 SCALE: NTS a) Column = 40mm d) Raft slab bottom = 75mm
b) R.C wall = 40mm e) Raft slab top = 50mm
c) Shear wall = 40mm
This drg. read in conjection with arch.drgs.
FOOTING SCHEDULE :
5. Raft & Columns are designed for Ground + Mezzanine +
FOOTING Four floor loads only.
SI. FOOTING REINFORCEMENT NO OF 6. SBC of the soil is taken as 320kN / sqm. @ 2.40m below
NO. NAME FOOTING SIZE X = LONGER DIRECTION FOOTING from N.G.L. as per soil report.
Y = SHORTER DIRECTION
7. Spacer bar - 25mm dia to be provided in between two
Y20 @ 125 C/C
01 NF1 2000 x 2000 BOTTOM - 14 layer of reinforcement at every 750mm c/c
BOTHWAYS
Y16 @ 150 C/C
8. Structural engineer responsibility is limited to design &
D = 750 TOP - BOTHWAYS issual of structural drawing only
9. Onus of construction lies with contractor/owner
10. For concreting water cement ratio should be (0.45) (for
1bag cement= max-25 lit of water only to be added.)
NOTES STRUCTURAL DESIGN QUALITY ASSURANCE
REVISIONS
Notice of no objection from Southern Railways Katpadi is being accorded for design principles based on the The drawing has been prepared based on actual site survey and other terms and conditions of the EPC Agreement. Responsibility of accuracy, correctness , This drawing including its design and detailing has been checked in accordance with the requirements of EPC Agreement and found
recommendations of the Architect/Lead Designer and proposal by the Contractor. However, the completeness, integrity and full compliance with byelaws, standards, statutory, regulations of relevant Codes & Manuals/ Rules and as per EPC Agreement suitable for the execution purpose. The overall responsibility of correctness of design,detailing and compliance with EPC agreement R.NO DATE DESCRIPTION
overall responsibility and design accuracy lies with the contractor (Engineering Projects (india) Pvt Ltd) provisions, rests with the Design Consultants and the Contractor without any financial implications. rests with the Structural Design Consultant and Contractor.
CLIENT: PROJECT: EPC Contractor: DESIGN CONSULTANT Authority Engineer (PMS) AXEN CN/MAS DY. CE CN/MAS CE CN/MAS
Drawing Title :
SOUTHERN RAILWAYS, REDEVELOPMENT OF ENGINEERING PROJECTS M/S VOYANTS SOLUTIONS PVT. LTD.
KATPADI. KATPADI JUNCTION (INDIA) LTD-CHENNAI Drawing Type :
Drawing No.: Scale: 1:100 Date: 12.12.23
Drawing Purpose: Sheet Size: A2 Rev. No: R0
AGM DESIGN DIRECTOR TEAM LEADER LEAD DESIGNER

You might also like