You are on page 1of 1

N

J M
A B C D E F G H E L N P Q R S T U
1020 1850 1200
9900 9900 3240 4000 2660 9900 9830 4500 2420 2580 7250 6600 3300 2200 2200 Notes:
1.All dimensions are in millimeters and levels
are in meters unless otherwise specified.
2.Drawing shall not be scaled, only written
dimensions to be followed.
8
PB3= 400 X 900 PB3= 400 X 900 PB3= 400 X 900 PB3= 400 X 900 PB7= 400 X 900 PB3= 400 X 900 PB3= 400 X 900 PB3= 400 X 900 PB3= 400 X 900'P PB3= 400 X 900
3.Any Error or Discrepancies in the
400

400

400

500

500
Drawings are to be brought to the notice.
170 380
PB3= 400 X 900

of the Architect/ Engineers.

PB3= 400 X 900


PB3= 400 X 900
B3= 400 X 900

300 400 4500 300 4550 500 4575 300 4695 380 4662 300 4513 500 4512 300 4663 380 7470 500 4000 775 6875 500 6150 500 4970 380
PB7= 400 X 900

PB2= 300 X 750

PB4= 500 X 900

PB4= 500 X 900

PB3= 400 X 900

PB4= 500 X 900


PB7= 400 X 900

PB9= 400 X 900


6900

PB7= 400 X 900


PB8= 400 X 900

4. This drawings shall not be used other than


6700

6700

6500

6500
the purpose marked/issued specified.
500 5. The drawings to be read with conjuction
with structural drawings.
7 PB3= 400 X 900 PB3= 400 X 900 PB3= 400 X 900 PB8= 400 X 900 PB7= 400 X 900 B5= 500 X 900 PB3= 400 X 900 PB3= 400 X 900 PB3= 400 X 900 PB7= 400 X 900

PB3= 400 X 900


6. All the drawings prepared by Design

500

500
400

400
PB7= 400 X 900

and structural consultants are as per

PB1= 230 X 600


PB2= 300 X 750
4250

PB3= 400 X 900


NBC norms and guidelines.

4310

4390
300 400 9350 500 9450 500 9475 500 9545 380500 7350 500 4275 500 6875 500 9570 380 LIFT
REMOVAL OF FORMWORK(SHUTTERING) :
100
6 Shuttering of any part of the structure shall not be
PB7= 400 X 900

PB3= 400 X 900

PB3= 400 X 900


2000

PB7= 400 X 900


PB3= 400 X 900
230

PB2= 300 X 750 PB2= 300 X 750 PB2= 300 X 750 PB2= 300 X 750 removed until the concrete attains 70% of the specified
230 1900

LIFT
LIFT

380

300
CUTOUT
CUTOUT PB1= 230 X 600
strength of concrete however the following minimum

PB2= 300 X 750

PB4= 500 X 900

PB3= 400 X 900

PB1= 230 X 600


5 period (after final pour ) shall be allowed before
removal of shuttering as per clause 11.3.1, is 456:2000
PB7= 400 X 900

4310

4310
3650

A. Vertical side of shuttering of columns,walls & beams


- 24 hours

300
PB7= 400 X 900 PB7= 400 X 900 PB8= 400 X 900 PB8= 400 X 900 PB8= 400 X 900 PB2= 300 X 750 PB2= 300 X 750 PB3= 400 X 900 PB3= 400 X 900 B. Bottom shuttering of slabs (keeping the props)
4

300
380

380

380

380
- 3 days
C. Bottom shuttering of beams (keeping the props)
2240 230 2000 230 2120

LIFT
PB3= 400 X 900

1950
LIFT CUTOUT - 7 day

230
PB3= 400 X 900

CUTOUT
B6= 300 X 750
PB8= 400 X 900

D. Props to slabs :

PB2= 300 X 750

0
PB5= 230 X 750

PB5= 230 X 750

PB4= 500 X 900

PB3= 400 X 900


PB3= 400 X 900

PB7= 400 X 900

75
100

PB3= 400 X 900


X
i .spanning upto 4.5 m - 7 days
6900

PB3= 400 X 900

300 500 4550 300 4550 500 2760 230 4000 230 2650 230 4513 300 4513 500 4512 300 4733 380 2650 230 4000 230 2810 500 4430

0
38
1950

6900
230
LIFT LIFT i i .spanning over 4.5 m - 14 days

6740

6=
STAIRCASE CUTOUT STAIRCASE

PB
CUTOUT CUTOUT E. Props to beams & arches :
i .spanning upto 6 m - 14 days

230
2240
i i.spanning over 6 m - 21 days
3 LAP JOINTS FOR REINFORCEMENT BARS :
380

380

300

300
PB3= 400 X 900 PB3= 400 X 900 PB3= 400 X 900 PB3= 400 X 900 PB3= 400 X 900 PB3= 400 X 900 PB2= 300 X 750PB2= 300 X 750 PB2= 300 X 750 PB3= 400 X 900 PB3= 400 X 900 1. At any cross section of the member,not more than
50% of the bars shall be lapped.
2. Laps shall be staggered with a minimum centre to
centre distance of 1.3 times lap length of the bar for
tension & compression members.
3. Development length (ld) shall be as per (sp:34-1999)
table below:
a) Development length for column bars - 40d
b) Development length for beam bars - 50d
4. Laps in columns shall be provided at mid height of
LAYOUT OF PLINTH BEAM floor and not at slab level .
5. Laps in beams and slabs shall be provided at the
point of contraflexure.
6. Welding of bars shall be done as a stitch weld for 5
times diameter of bar and a gap of 5 times higher
diameter bar and again welding for another 5 times
diameter of bar using arc welding and special
Max of 0.25L1 (or) Ld Max of 0.25L1 (or) Ld Max of 0.25L2 (or) Ld electrodes after obtaining prior written approval from
the structural designer.
50 mm 50 mm 7. Detailing of rebars shall confirm to sp-34 & is 13920.
TOP
REINFORCEMENT GENERAL NOTES:
1. Concrete grade shall be M35(design mix) confirming to
is 456:2000
2. Minimum cement content = 380 kg/m3.
3. Min.grade of reinforcement marked thus (y) shall be Fe
550D confirming to IS 1786-1985
0.1L1 BOTTOM 0.15L1 0.15L2 4. Clear cover for reinforcement
REINFORCEMENT a) Column = 40mm d) Raft slab bottom = 75mm
Max of L1/4 HOOP SPACING > d/2 Max of L1/4 Max of L2 /4 HOOP SPACING > d/2 b) R.C wall = 40mm e) Raft slab top = 50mm
(or) 2d (or) 2d (or) 2d c) Shear wall = 40mm
L1 L2
This drg. read in conjection with arch.drgs.
END SUPPORT INTERMEDIATE 5. Raft & Columns are designed for Ground + Mezzanine +
RESTRAINED SUPPORT Four floor loads only.
6. SBC of the soil is taken as 320kN / sqm. @ 2.40m below
from N.G.L. as per soil report.
7. Spacer bar - 25mm dia to be provided in between two
layer of reinforcement at every 750mm c/c
8. Structural engineer responsibility is limited to design &
issual of structural drawing only
9. Onus of construction lies with contractor/owner
10. For concreting water cement ratio should be (0.45) (for
1bag cement= max-25 lit of water only to be added.)
NOTES STRUCTURAL DESIGN QUALITY ASSURANCE
REVISIONS
Notice of no objection from Southern Railways Katpadi is being accorded for design principles based on the The drawing has been prepared based on actual site survey and other terms and conditions of the EPC Agreement. Responsibility of accuracy, correctness , This drawing including its design and detailing has been checked in accordance with the requirements of EPC Agreement and found
recommendations of the Architect/Lead Designer and proposal by the Contractor. However, the completeness, integrity and full compliance with byelaws, standards, statutory, regulations of relevant Codes & Manuals/ Rules and as per EPC Agreement suitable for the execution purpose. The overall responsibility of correctness of design,detailing and compliance with EPC agreement R.NO DATE DESCRIPTION
overall responsibility and design accuracy lies with the contractor (Engineering Projects (india) Pvt Ltd) provisions, rests with the Design Consultants and the Contractor without any financial implications. rests with the Structural Design Consultant and Contractor.
CLIENT: PROJECT: EPC Contractor: DESIGN CONSULTANT Authority Engineer (PMS) AXEN CN/MAS DY. CE CN/MAS CE CN/MAS
Drawing Title :
SOUTHERN RAILWAYS, REDEVELOPMENT OF ENGINEERING PROJECTS M/S VOYANTS SOLUTIONS PVT. LTD.
KATPADI. KATPADI JUNCTION (INDIA) LTD-CHENNAI Drawing Type :
Drawing No.: Scale: 1:100 Date: 12.12.23
Drawing Purpose: Sheet Size: A2 Rev. No: R0
AGM DESIGN DIRECTOR TEAM LEADER LEAD DESIGNER

You might also like