1. Purpose
This procedure is devised to provide guidelines for safe

2. Scope
This procedure is applicable at locations of compression department in Compression
electrical.

3. Procedure:

 A trench of about 1.5 meters deep should be excavated. Width of Trench should
be as per number of cable being laid.
 Trench should be covered with a 10 cm thick layer of fine sand.
 The cable must be laid over the sand bed. The sand bed protects the cable from
the moisture from the ground.
 Then the laid cable must be covered with a layer of sand about 10 cm thick.
 When multiple cables are to be laid in the same trench, a horizontal or vertical
spacing of about 30 cm should be provided to reduce the effect of mutual
heating. Spacing between the cables also ensures a fault occurring on one cable
does not damage the adjacent cable.
 Separate trenches need to be used for power and control cables.
 After execution of above mentioned steps, the trench should be covered with
bricks and soil to protect the cable from mechanical injury.

4. Precautions:
Safety glasses must be worn at all times Safety gloves must be worn.
in work areas.

Appropriate protective footwear


must be worn.

5. References
It is derived from OEM Manual.

© SNGPL. All rights reserved.


Please don’t copy without authorization.
Sui Northern Gas Pipelines Limited DOC. # SNGPL- COMP-ELECT-01

Compression Department Issue: A w.e.f:

CABLE LAYING PROCEDURE Rev #00 28-03-2019

© SNGPL. All rights reserved.


Please don’t copy without authorization.

You might also like