Professional Documents
Culture Documents
net/publication/4155568
CITATIONS READS
22 2,702
3 authors, including:
Some of the authors of this publication are also working on these related projects:
A Novel TVA-REPSO Technique in Solving Generators Sizing (Journal PRZEGLAD View project
All content following this page was uploaded by Abdullah Asuhaimi Mohd Zin on 21 July 2015.
unnecessary tripping. The use of rate of frequency change the security of the grid and to avoid the minimum
(dfidt) is proposed, which provides advantages as follows: allowable frequency being overcome.
One can begin to trip load blocks without waiting The main motivation in *LS scheme is to avoid the
until the frequency drops critically. pLLt(4L fr'eqiiiency deviating from its nominal value. Most rotating
Load shedding steps can trip simultaneously instead machine is designed for optimum performance at a specific
o f sequentially. frequency. Often, rotating machine cannot operate safely or
+ Improved response time. effectively at more than a few percent below rated frequency
Flexible, and can be tailored to different level of [SI. Continuous operation of steam turbines should be
imports restricted to frequencies above 48.5 Hz. Operation below 48.5
Reduced fiequency swing. Hz should be limited to very short periods of time.
Load shedding schemes can be grouped into three main The design of a load shedding scheme is essentially
categories: traditional, semi adaptive and adaptive [3]. The determining a workable between providing maximum system
traditional scheme is the most simple and used by most protection and interrupting a minimal amount of service.
utilities. It sheds a certain amount of load when the system Although there is no established rule for achieving such a
frequency falls below certain threshold. The semi-adaptive
balance, there are certain design decisions that must be'made
method measure the rate of change of frequency (KOCOF)
in order to successfully implement a load shedding scheme.
when the system frequency reaches certain threshold.
According to that value, different amount of load are shed. The design decisions, which is considered separately are as
The adaptive method used model obtained horn the complete foIlows [lo]:
generating unit, along with its governor.
Maximize the anticipated overload.
There are several methods of dynamic or adaptive UFLS Select the number of load shedding stages.
proposed and discussed in literature [4]-[8]. All approaches Determhe the amount of load to be shed at each
are based on the use of the generator swing equation. In [4]an stage.
adaptive methodology is given for the setting the under- Calculate the relay settings.
frequency relays, based on the initial rate of change of Select which loads should be shed at each stage.
frequency at the relay. In [6] a method using both frequency
and voltage changes is presented. In [7] an adaptive scheme v. TNB SYSTEM CASE STUDY
that u5es both frequency and rate of change of frequency
measurement to dynamically set under-fiequency relays is Tenaga Nasional Berhad's (TNB) UFLS schemes have
presented. been installed to disconnect Ioad with respect to falling
frequency in the event of a major loss of generation. The
W . W L S CONSIDERAT~ONS scheme is designed to disconnect load at predefined fiequency
stages so as to match the losses io generation.
Before a load shedding program can be developed, it is
necessary to evaluate several criteria as listed below [2]-[3]. A. Case1
The steam has priority over the electrical system: The After the system collapse of 29' September 1992, TNB
steam system must be able to recover or both will implemented a 4-stage load shedding scheme of 1579MW in
fait. July 1993 based on a credible generation loss of 15OOMW
Electrical load shedding coordinates with the steam [ 11]+The 4-stage scheme was revised again immediately after
system by shedding load as soon as possible. the August 3d 1996 system collapse when considerably more
Facilities which are essential from a safety standpoint than 1500MW of generation was lost, to a &stage 2700MW
are not shed. scheme (Table I).
Facilities which can be shed without disruption of
process operations are shed first.
I -z1 I LI
Facilities which are easier to restore to normal
operation are shed before those which are difficult to I Stage 1 2 3 4 5
restarts. Frequenc
The action has to be quick, so that the frequency drop 49.5 49.3 49.1 49 48,s
Y (Hz)
is halted before a situation of danger has occurred.
Unnecessary actions have to be avoided.
The protection system has to be liable and redundant, Load
300 400 600 600 800 2700
as a malfunction of it would surely lead to a major (MY
failure of the whole system,
I72
It was decided to have an independent review of this 6- TNB system is intcrcoiii~cclctlto Singaporc I'UII systcm via
stage scheme to determine whether any improvement could be 230 kV tic lines. Tlic Iwatl i d gciicratioti a1 Singapore I'Uf3 is
discovered. The static review of the 6-stage scheme was done assumed to bc balancc at 4000MW. Sincc ~ h frcqucncy
c dccay
using the formula given by Western Council Coordinating rate is the function of pcrccnlagc ovcrload in thc
Council (WSCC) [12]. As a rule of thumb to minimize over interconnected systcm, having thc Singaporc PUB conncctcd
shedding, it is always better to have more stages with smaller would reducc the pcrccntagc ovcrload and hcncc rcducc thc
load at each stage. Moreover, tripping a big block of load at frequency decay rate. Fig. 2 shows 1hc cffcct of tripping and
one time will give a large impact to an already weakened not tripping the tic linc to Singaporc PUB in G-slayc schcmc.
system. A new 11-stage scheme was recommended as shown The rate of frequency dccay incrcase from 1.2 l i d s to 2.3
in Table 11. The new 11-stage scheme was designed to Hds'when the linc is tripped.
minimize the changes t o the 4-stage scheme, It shed the same
amount of load in the same frequency range as in the 6-stage
scheme.
T-WWdbdlilppnlS~PUOT.aA~+J
-
Tarl Ladh t t C W MW. (imam h ZlOUMW
IIlr
TABLE II
RECOMMENDED 11-STAGE UFLS SCHEME
Stage 1 1 1 2 1 3 1 4 1 5 1 6
Frea (Hzl 1
I
49.5 4 49.4 I 49.3 49.2 1 49.1 1 49.0 df/di-- 1.2 tWm
I 1
. %
VIII. REFERENCES
J. F. Fuller, E. F. Fuchs, and K. J. Roesler, "Influence of harmonics on
power distribution system protection," IEEE Trans. Power Dclivev, vol.
3,pp, 549-557, Apr. 1988.
G.S.Grewal, J. W.Konowalec, and M. Hakim. "Optimization of a load
shedding scheme," Industry Applications Magazine, IEEE. Vol. 4 NO.4.
pp. 25 -30, JUly-Aug. 1998.
B. Delfino, S. Massucco, A. Morini, P. Scalera and F. Silvcstm.
"lmplemeniation and Comparison of Different Under Frequcncy Load-
Shedding Schemes," Power Engineering Society Summer Meefing.2001,
Vol. 1, pp. 307-3 12.
P. M. Anderson and M. Mirheydar, "An adaptive method for setting
underfrequency load shedding relays," I€€€ Trans. Power Sysf., 1992,
Vol. 7, NO.2. pp. 647-655.
J. G. Thompson and B. Fox, "Adaptive load shedding for isolatcd power
system," IEE Proc.- Gener. Trunsm. Dwtrib , Vol. 141, No. 5 , pp. 491-
496. Sep 1994.
D. Prasetijo, W. R. Lachs, and U. Susanto, "A new load shedding
scheme for Limiting under-frequency", IEEE Truons. Power Sysl., Vol. 9,
NO.3, pp. 1371-1378, Aug. 1994.
V. N. Chuvyvhin, N. S. Gurov, S. S . Venkala. and R. E. Brown, "An
adaptive approach to load shedding and spinning reserve control during
underfrequency conditions," IEEE Trans. Power Sysl., Vol. 11, No. 4,
pp. I805-lSl0,1996.
S. J. Huang and C. C. Humg. "An adaptive load shedding mclbod with
time-based design for isolated power syslems." Electr. Power Enerby
S,~t..Vol.22,NO.1, pp. 51-58,2000.
E.A. Urden, "Load Shedding and Frequency Relaying. " Applied
Protective Relaying, Westinghouse Electric Corporation. pp. 21 .I-21 .I 6,
1997
[IO] H. E. Lokay and V. Burtnyk, "Applicalions of Underrrcqucncy Rclays
for Automatic Load Shedding, " IEE Transactions, Vol. 78, pp.776-782,
1968.
[ 11] Zainoren Shukri and J. T. Vijayan, "Dynamic Simulations Optimizc
Application of an Underfrequency Load Shedding Schemc, " Prcscnlcd
at The 24h Annual Westem Protective Relaying Confcrence:1997.
[ 121 "Underfrequency Load Shedding Guide," Preparcd by Weslcm System
Co-ordinating Council, 1994.
IX. BIOGRAPHIES