Professional Documents
Culture Documents
Master Scheduling
1
Information Needed to Develop an
MPS
• Production Plan data
• Forecasts
• Actual customer orders
• Inventory levels
• Capacity constraints
2
Relationship to Production Plan
(Cont.)
3
Example - MPS
4
Problem: The Wicked Witch Whisk Company manufactures a line
of broomsticks. The most popular is the 36-inch model, and the
sales department has prepared a forecast for 6 weeks. The opening
inventory is 30. As master scheduler, you must prepare an MPS.
The brooms are manufactured in lots of 100.
5
Objectives and Steps for the MPS
• Objectives –
– Maintain good customer service
– Make effective use of resources
– Maintain effective levels of inventory
• Accomplished by:
– Develop a preliminary MPS
– Check MPS against capacity and resources
– Reconcile any differences
Preliminary MPS
An example:
- The product is made to stock,
- an inventory is kept,
- the product is made in lots of 100,
- and the expected opening inventory is 80 units.
6
Problem : The Amalgamated Mailbox Company manufactures
a family of two mailboxes. The production plan and the MPS
are developed on a quarterly basis. The forecast for the product
group follows. The opening inventory is 270 units, and the
company wants to reduce this to 150 units at the end of the year.
Develop a level production plan.
Production plan
7
Problem : (Cont.)
The forecast sales for each of the mailboxes in the family also follow.
Develop an MPS for each item, bearing in mind that production is to be
leveled as in the production plan. For each mailbox, the lot size is 220.
8
Example Resource Bill
9
10
Problem 1: The Acme Widget Company makes widgets in
two models, and the bottleneck operation is in work center
10. Following is the resource bill (in hours per part).
Problem 1 (Cont.)
a. Using the resource bill and the master production
schedule, calculate the number of hours required in work
center 10 for each of the 5 weeks. Use the following table
to record the required capacity on the work center.
11
Resolution of Differences
overtime,
extra workers,
routing through other work centers,
subcontracting
revise the master production schedule
12
Example MPS Environments
13
Engineer-to-order
- a form of make-to-order (MTO) products.
- the product is designed before manufacturing,
- based on the customer’s very special
needs.
14
MPS Planning Horizon
EXAMPLE –
Cumulative Planning Horizon
• For this product – Minimum Planning Horizon 12 weeks
15
Production planning, MPS, and Sales
Delivery Promises
• MPS is a plan for what production can and
will do
• Sales delivery promises can be made from
– “Consumption” of forecasts – Projected
available balance
– Available to Promise calculations
• MPS values for a given time period left after actual
customer orders are subtracted.
16
The MPS and delivery time
ATP - Example
17
ATP - Example
ATP - Example
Can the master planner accept an order for another 20 for delivery
in week 3?
18
ATP - Example
Example problem
19
Solve the Problem 1!
Calculate the available to promise using the
following data. There are 90 units on hand.
20
Solve the Problem 3!
Given the following data, can an order for 20 for delivery
in week 4 be accepted? Calculate the ATP using the
following table. On hand = 50 units.
PAB = prior period PAB or on-hand balance + MPS - greater of customer orders or forecast
21
Solve the Problem 1!
Given the following data, calculate the projected available
balance and the planned MPS receipts. The lot size is 200.
The demand time fence is 2 weeks.
22
Solve the Problem 2!
Given the following data, calculate the projected available
balance and the planned MPS receipts. The lot size is 100.
The demand time fence is 2 weeks..
Using the Amalgamated Nut Cracker, Inc., example, we now combine the two
calculations into one record. The demand time fence is at the end of 3 weeks.
23
MPS - ATP – PAB
Example
24
Time Fences
25
Time Fences
• Points in the planning horizon to define the
flexibility allowed in the MPS
– Frozen Zone (closest to current date)
• Capacity and materials committed to customer orders, forecast
generally ignored
• Senior management approval for changes
– Slushy Zone
• Less commitment of materials and capacity
• Tradeoffs negotiated between marketing and manufacturing
– Liquid Zone – All changes allowed within limits of the
Production Plan
26
Error Management
27
Solve the Problem!
a. Given the following master schedule, fill in the projected available
and available to promise rows:
b. A customer wants an order of 100 in period 4. What can you tell him?
c. The customer from part (b) cancels his request, but then says he
wants 120 in period 5. What do you tell him now?
d. Sales has requested that you add an MPS of 200 in period 9 to cover
their needs for a sales promotion. What do you tell them and why?
e. What action (if any) should be taken in period 11? Why is it okay to
take the action?
28