Professional Documents
Culture Documents
1
Independent versus Dependent Demand
• Independent Demand
– Not related to demand for other assemblies or
products, instead from outside sources
– Generally forecasted demand
• Dependent Demand
– Generally related to production of an end
product (as defined on the MPS)
– Can be calculated instead of forecasted
2
Links To Other MPC Functions
3
Sample Bill of Materials
4
Sample Bill of Materials
5
Breaking Down the BOM into More
Detail – the Multilevel Bill
Multiple Bill
6
Single – level Bill
Example problem
7
Solve the problem!
Using the following product tree, construct the
appropriate single-level trees. How many Cs
are needed to make 50 Xs and 100 Ys?
8
Indented BOM – Use Indentation to
Show Parent-Component Relationships
9
Solve the problem!
Given the following parents and components,
construct a product tree. Figures in parentheses
show the quantities per item. How many Gs are
needed to make one A?
10
Sample Planning BOM
Pegging Report
11
Major Uses for Bills of Material
12
Exploding and Offsetting
Lead time (LT)
Exploding and
Offsetting
13
Example problem
14
Solve the problem!
Using the following product tree,
determine the planned order receipts and
planned order releases if 200 As are to be
produced in week 5. All lead times are 1
week except for component E, which has
a lead time of 2 weeks.
15
Gross requirements are the total quantity of a product or service
needed to meet customer demand. Understanding and calculating
‘gross requirements’ are essential for ensuring that your business has
the necessary inventory on hand to meet customer demand.
Example Problem
16
Solve the problem!
Given the following parents and components,
construct a product tree. Figures in parentheses
show the quantities per item. How many Gs are
needed to make one A?
Releasing Orders
17
Example
Schedule
receipts
18
Example Problem
19
Solve the problem!
Complete the following table. Lead time for the
part is 2 weeks, and the order quantity is 50.
What action should be taken?
20
Low-Level Coding and Netting
21
Netting and exploding first-level parts
22
Solve the problem 1!
Given the following product
tree, explode, offset, and
determine the gross and net
requirements. All lead times
are 1 week, and the quantities
required are shown in
parentheses. The master
production schedule calls for
100 As to be available in
week 5. There are 20 Bs
available. All other on-hand
balances = 0.
23
Solve the problem 3!
Given the following partial
product tree, explode, offset,
and determine the gross and
net requirements for
components H, I, J, and K.
There are other components,
but they are not connected to
this problem. The quantities
required are shown in
parentheses. The master
production schedule calls for
the completion of 60 Hs in
week 3 and 80 in week 5.
There is a scheduled receipt of
120 Is in week 2. There are
400 Js and 400 Ks available.
All lot sizes are lot-for-lot.
24
25
Using the Material Requirements Plan
Material Planner
Three types of orders:
- Planned orders
- Released orders
- Firm planned orders
26
Managing the Material Requirements Plan
Example problem
27
Example Problem
Example Problem
28
Some Key Terms
• Lead time – span of time for a process
• Exploding – process of multiplying requirements
by usage to get BOM requirements
• Offsetting – Placing requirements in the proper
period based on lead time
• Planned orders – Orders planned during the
explosion, but not yet released for processing
• Low-level code – lowest level on which a part
resides on the Bill of Materials
29
Sample Material Requirements Plan
30
Points About the MRP Record
• Current time – beginning of first period (often
called time buckets)
• Items considered available at beginning of
period
• Quantity in Projected Available row considered
at end of period
• Current period often called action bucket – action
should be taken to avoid a future problem
31
Other Key Terms
• Firm Planned orders – Orders not yet released,
but “frozen” in quantity and time to reduce system
“nervousness”
• Exception messages – messages generated by the
computer signaling planner action needed
• Bottom-up replanning – actions to correct for
changed conditions made as low as possible in the
product structure
32
Problem 1!
MPS parent X has
planned order releases of
30 in weeks 2 and 4.
Given the following
product tree, complete
the MRP records for parts
Y and Z. Quantities
required are
shown in brackets..
33
Problem 2!
Given the following product
tree, explode, offset, and
determine the gross and net
requirements. The quantities
required are shown in
parentheses. The master
production schedule calls for
the completion of 100 As in
week 5. There is a scheduled
receipt of 100 Bs in week 1.
There are 200 Fs available. All
order quantities are
lot-for-lot.
Problem 3!
Given the following product tree, complete the
MRP records for parts X, Y, W, and Z. Note
that parts X and Y have specified order
quantities.
34
Problem 4!
Given the following product
tree, develop a material
requirements plan for the
components. Quantities per
are shown in parentheses. The
following worksheet shows
the present active orders, the
available balances, and the
lead times.
Problem 5!
Given the following product
tree, determine the low-level
codes and the gross and
net quantities for each part.
There is a requirement for 100
As in week 4 and 50 Bs
in week 5. There is a
scheduled receipt of 100 Cs in
week 2. Quantities required of
each are also shown.
35