Professional Documents
Culture Documents
Session 5-7
The Master Schedule
INTRODUCTION
• Developing and managing the master schedule
• It is the next logical step in production planning
• Assumes that S&OP has properly planned resources
• Contains more detail than the S&OP
• The time horizon is typically shorter than S&OP
• S&OP is usually planned in terms of product families
• Master schedule represents final, sellable products
• the major interface between the production
system and the external customers
• Small firms or firms primarily offering a pure service,
don’t have a formal master schedule
Background and Links to The S&OP
• S&OP lines up the proper resources
• S&OP uses aggregate forecast data as demand
input
• S&OP serves a very important function in planning
for long range resource needs
• Usually no inputs from actual customer orders
• The planning isn’t typically done at the final product
level
• More planning is then needed to
Background and Links to The S&OP
1. Break down the aggregated plans into buildable
products
2. Serve as a plan that uses actual customer orders in
addition to forecast data
3. Serve as a source of information to develop
capacity and resource plans
4. Serve as a method to translate customer orders
into effectively timed production orders
5. Serve as an effective tool to plan inventory levels,
particularly at the finished goods level
Background and Links to The S&OP
• This planning activity is called the master schedule
• It starts with a detailed product forecast
• Develops a set of rules for the consumption of the
forecast
• Translates the actual and projected customer
orders into specific production orders
• The master schedule has more detail than S&OP
• The master schedule has a shorter time horizon
• The master schedule values should add up to the
values developed in the S&OP
S&OP Relationship to MPS
Product Group A July August September October November
Working Days/ 22 21 23 20 19
Month
Approved 22,000 21,000 23,000 20,000 19,000
Production Plan
from S&OP
MPS Week 40 41 42 43
Product A1 1,000 1,000 1,000 1,000
Product A2 500 1,000 1,500 2,000
Product A3 1,500 500 500 1,500
Product A4 2,000 2,500 2,000 500
Total 5,000 5,000 5,000 5,000
Master Scheduling
Input: The approved Sales and Operations Plan
Sales and
Operations Plan
Rough Cut
Master Schedule Capacity Planning
Master Production
Schedule
Output: The approved Master Production Schedule
Master Schedule Horizon
• The master schedule needs to have a planning
horizon equal to or longer than the cumulative lead
time of the product or service being planned
• First examine the bill of material (product structure)
• shows components used to assemble a product
• shows not only the relationships between all components
but also shows quantities needed for each component
• contains lead times for purchase or production of each
component or assembly
• cumulative lead time is the amount of time it takes to
make a product from start to finish
Example BOM
Single level
Bearing
Bearing
B C Level 1
D E F G Level 2
H Level 3
Master Schedule Horizon
• Going level by level, we can see the longest lead time
for each level:
level longest lead time
0 (end product) 2 weeks
1 4 weeks
2 5 weeks
3 7 weeks
Master Schedule Horizon
• The cumulative lead time of this product (A) is 18 weeks
(2+4+5+7)
• As an example, suppose we had no master schedule
• A customer ordered one of the products for delivery in
week 14
• We had no problem promising delivery, since the lead time
for making the end product A is only 2 weeks
• That will, in fact, be the case assuming adequate inventory
exists at the lower levels
• If we don’t have adequate inventory, follow what would
happen:
Master Schedule Horizon
• Since the customer wants the product in week 14 and it takes 2 weeks to build, we
would need to start the end product production in week 12
• Since the level 1 subassembly (C) takes 4 weeks to build and we need it to build the
end product starting in week 12, we will need to start the production for
subassembly C in week 8
• Since the level 2 subassembly (G) takes 5 weeks to build and we need to have it
completed by week 8 to use it for the level 1 component, we will need to start its
production in week 3
• Since the level 3 component (H, a purchased part) has a 7 week lead time and we
need it in week 3 to use it to build the level 2 subassembly (G), we will need it to
order it 7 weeks before week 3
Time Fences
1. The demand time fence
• The forecast data is ignored and only customer order quantities
are used to make master schedule computations
For example, if a demand time fence is set at week 2 for the
master schedule, the forecast data for weeks 1 and 2 are ignored
for calculation purposes, regardless of how they may or may not
agree with actual order data
• Schedule is considered “frozen”
• no changes to the schedule
• The demand time fence is the closest to the present time in the
schedule
Time Fences
2. The planning time fence
• Is set equal to or slightly larger than the cumulative
lead time for the product.
• In our earlier example of product A with four
material levels, the planning time fence could be set
at the 18 week mark. Beyond the time fence (19
weeks and beyond), there is adequate time to react
to new orders, even if there will be a requirement to
order the purchased items in the bill of materials, so
the master production schedule values are very free
to be changed
MPS Time Zones
Quantity
Demand
Forecasted demand
Customer orders
Time
Frozen Flexibl Free
Future
e
time
Demand Planning
time fence time fence
Sources of Demand
• The master schedule is said to be a disaggregation
of the S&OP (breaking down S&OP product family
numbers into specific product numbers)
• The forecasting methods used for demand
forecasting are often different for the master
schedule when compared to the S&OP
• S&OP are long-range, often generated from
causal methods
• Master schedule are more often generated from
qualitative or time series methods
Basic Methodology
The master schedule uses demand (customer orders and
forecast) in its development
• It considers
• inventory plans
• labor plans
• plans for phasing in new products
• Now at a different level of detail
• meeting the customers needs for delivery as established in
the S&OP
• balancing the preliminary master schedule numbers against
available capacity
• establishing inventory levels according to the S&OP
Basic Methodology
Figure below shows a simple master schedule
• It should be noted that the entire planning tool is called a
master schedule, while the specific schedule production
quantities and times are called the master production schedule
(MPS)
• A sample master schedule
• On hand = 70
• Lot size = 80
Basic Methodology
Period 1 2 3 4 5 6 7 8 9 10
Demand 40 50 45 50 50 50 50 50 50 50
Projected available 30 60 15 45 75 25 55 5 35 65
MPS 80 80 80 80 80 80
MPS 60 60 60 60 60
Before proceeding to explain the ATP, let’s make sure about the other numbers in
the master schedule:
• The first 2 weeks are within the DTF. That implies the forecast is ignored for
these first 2 weeks, and the PAB is computed from the customer orders only
• Between the DTF and the PTF (12 weeks) we calculate the PAB from the
1. If the forecast number is larger, it implies there are still
potential customer orders that will be placed
2. If the customer order number is larger, it is obvious that
the forecast was too low, and we need to reflect what
the customers actually want
• The MPS was developed so that there would never be a
negative PAB. It is important to remember that a negative
PAB implies there is inadequate planned production to
meet the projected demand, a condition that most
companies prefer to avoid.
Period 1 2 3 4 5 6 7 8 9 10 11 12
Forecast 22 25 20 20 18 18 32 30 28 28 29 23
Customer orders 24 23 17 22 15 14 17 16 12 16 13 11
MPS 60 60 60 60
• One key issue should be noted in the example above. The ATP
logic is calculated only from customer orders, not from forecasts
at any time. The concept here is the calculation shows available
to promise to customers, not to forecasts.
Basic Definitions
• MRP. (Materials Requirements Planning). MRP is the basic
process of translating a production schedule for an end
product (MPS or Master Production Schedule) to a set of
requirements for all of the subassemblies and parts
needed to make that item.
• Main Advantage of MRP over JIT: MRP takes forecasts for end
product demand into account. In an environment in which
substantial variation of sales are anticipated (and can be
forecasted accurately), MRP has a substantial advantage.
Example
Basic Equation:
Net Req. = Gross req. - Scheduled Receipts - projected on hand
inventory
Basic Algorithm
1. Compute time-phased requirements
2. Determine Planned Order Release (LS)
3. Compute ending inventory
4. Proceed to next level (if any)
Explosion Calculus
Advantages:
1. Decreases Inventory Costs
2. Improves Production Efficiency
3. Reveals quality problems (see Figure 7-10)
Disadvantages:
1. May result in increased worker idle time
2. May result in decreased throughput rate
River/Inventory Analogy
Illustrating the Advantages of Just-in-
Time
Features of JIT Systems
(continued)
Kanban Information Flow System
Advantages:
1. Efficient tracking of lots
2. Inexpensive implementation of JIT
3. Achieves desired level of WIP
Disadvantages:
1. Slow to react to changes in demand
2. Ignores predicted demand patterns
Kanban Information System vs
Centralized Information System (MRP)
Features of JIT Systems
(continued)
JIT Purchasing System
Advantages:
1. Inventory reduction
2. Improved coordination
3. Better relationships with vendors
Disadvantages:
1. Decreased opportunity for multiple sourcing
2. Suppliers must react quickly
3. Potential for congestion
4. Suppliers must be reliable.
Comparison of MRP and JIT