Professional Documents
Culture Documents
CASE STUDY
SOUTHERN
CROSS STATION
AUSTRALIA
WSP|PARSONS BRINCKERHOFF STATION
CAPABILITY
Railway stations are key nodal points for the sustainable transport of
passengers. As such they have an important social-economic and environmental
role to play.
A well-functioning station that can provide comfortable transport options for
passengers in an efficient way will encourage commuters and travellers to use this
comparatively environmentally friendly way of travelling.
Because of the facilities and the technology that a station has to include to function
safely and efficiently, a station by itself consumes large amounts of resources and
might have negative environmental and social impacts on the adjacent
environment.
TRANSFORMATION OF TRANSPORT HUBS –
SOUTHERN CROSS STATION
Opening Modernisation Redevelopment
2000’s
1960’s
1859
•The 1880s saw the first •In October 1960 work on •Southern Cross was
of several unrealised a new Spencer Street redeveloped by the Civic
plans station commenced Nexus consortium
•Opened as Spencer •The station building •Innovative design by
Street Station in 1859, largely replaced the Grimshaw Architects
•From 1888 to 1894 the 1880s iron shed •Construction began in
layout platforms was •A new 413-metre platform October 2002 and was
altered, with new country number 1 was built. completed in late 2006
platforms •A new double-track •The central features of
•The current coach viaduct was constructed the design include a
terminal location was the between Spencer Street wave-shaped roof, a new
site of a number of new and Flinders Street entrance and concourse
platforms built for station. on Collins Street
suburban services.
SOUTHERN CROSS STATION PROJECT GOALS
Urban regeneration for
Melbourne was a key focus of
Victoria’s Premier, Jeff Kennett,
who publicized several high
profile capital improvement
projects in the city, leading up
to a bid for the 2006
Concessionaire gains
revenue through retail leasing
SOUTHERN CROSS PPP CONCESSION
Civic Nexus
Consortium
1
Leighton Contractors
2 Concession
ABN Amro
3
Nicholas Grimshaw and
Partners
4
Honeywell
At the end of the lease, the contract can
Cost of Procurement: US$2.3m
be renegotiated and renewed. If either
Basis of Award: Best design at least party chooses not to renew the contract,
cost and lowest availability payment the station will be returned to the Victoria
for operations and maintenance with government in working order
consideration for valuation of
surrounding real estate
AVAILABILITY PAYMENT
30 Year Concession From Start of Operating Period
Availability Reviewed
Annual Annual
payment against
payment Paid Indexing
(Core quarterly
AUD$ 34 Quarterly of
Services passenger
million Payment
Payment) count
FINANCIAL STRUCTURE OF SOUTHERN CROSS
Equity Investor Equity Investor
Development Australia ABN AMRO
Fund Management Ltd
2 bonds of AUS$335m
AUS$167m D&C Contract
1 bond of US$73.9m
Commercial risk • Demand shortfall, price elasticity, network interface risk, collection
risk
Operations
Macro risk
development, interest rates, exchange rates, inflation
Bracket 1 Percentage)
4,00,00,000
3,50,00,000
3,00,00,000
2,50,00,000
2,00,00,000
1,50,00,000
1,00,00,000
50,00,000
The image cannot be display ed. Your computer may not hav e enough memory to open the image, or the image may hav e been corrupted. Restart y our computer, and then open the
file again. If the red x still appears, y ou may have to delete the image and then insert it again.
Year
Flinder Street Station
Southern Cross Station
Completion
Planned
Over Budget Payments to Developer
• $21 million for modifications and additional works to which the Department Of
Infrastructure agreed that the developer was entitled under the original contractual
terms
Payments to the
• $8.5 million to settle claims to which the concessionaire did not admit liability developer withheld
• $2.75 million to settle a site access claim after the 2006 Commonwealth Games
Descoping
• Rail modification and signalling upgrade works were removed from the project
• Department Of Infrastructure taking over responsibility for completion of the project
• The State received a credit (calculated by an independent reviewer) from the
concessionaire for the de-scoped works
DELAYS AND OVER BUDGET
The state required the redevelopment consortium to keep the station at full
operation capacity throughout the project
Poor pedestrian
access and tram
interchange at street
level
LEVERAGING THROUGH COMMERCIAL RETAIL
The performance of the commercial development is also inconsistent with
forecasts for both inside and outside spaces
• A more efficient complex and a subtle mix of retail facilities and public spaces could have been achieved.
• This may have been improved with greater involvement of expert retailers in the design and approval
processes
• The lessons learnt by the contractor in building the roof were not carried through to the adjacent
retail development.
• This has resulted in less favourable public opinion of the commercial development and detracted from
the impact of the overall station development
MORE RECENTLY
The need for comprehensive Due Diligence from the outset……
Major Awards
• RIBA International Award
• RIBA Lubetkin Prize
• Australian Institute of Architects
Victorian Architecture Medal
• Australian Institute of Architects
William Wardell Award for Public
Architecture
• Victorian Industry Capability
Network Industry Achievement
Award
APPLICATION IN INDIA - IDENTIFYING AND ATTRACTING
THE RIGHT SERVICE PROVIDERS MIX
• Formats varying from mono-brand stores to multi
Travel Retail brand stores Key Metrics
(eg. Large bazaar, Lifestyle, Vishal Mart…)
• Focus on diverse range of fast moving goods