Professional Documents
Culture Documents
Mumbai Metro
Versova – Andheri – Ghatkopar Corridor
2
Introduction
• Concessioning Authority –
Mumbai Metro Region
Development Authority
(MMRDA)
• Concessionaire – Mumbai
Metro One Private Limited
(MMOPL)
• Project Name – Mumbai Metro
(First Corridor)
• Project Brief – Elevated MRTS corridor from Versova – Andheri – Ghatkopar
• Project Capacity – 11km,12 Stations & a car depot at DN Nagar
• Project Cost – Rs 2,356 Crore
• Type of PPP (Variant of PPP model adopted for implementation of the project) – Build-
Own-Operate-Transfer (BOOT)
• Project Status – Operation and Maintenance Stage
• Concession Duration – 35 Year (including 5 years construction period)
3
Timeline
Project
1st Conceptualization Feasibility Study approved by GoM Invitation of Bids
1997 1997-2000 Aug-2004 Aug-2004
4
Demand Analysis
Scenario of Public Transport
• 11 million people travel daily by Public Transport (share of PT more than 90%)
• Many areas in city and suburbs are not served by rail system
• Suburban rail traffic increased by 6 times while the capacity increased by only 2.3 times
• 4500 passengers travel per train against the carrying capacity of 1750 resulting in unbearable
overcrowding
Feasibility Report
• A detailed feasibility study was carried out under the Indo-German Technical Co-operation by
entrusting the consultancy work to TEWET in association with DE-Consult & TCS, during 1997-
2000.
• As per the report, Andheri to Ghatkopar MRTS as potentially bankable and economically viable
• Will reduce 90 min travel time to 21 min.
MRTS will grow to 6 lakhs commute per day
5
Process - 2 Stage Bidding
6
SPV
7
Scope of Project
8
Grant
9
Advertising Grant
10
Condition Precedent
11
Performance Security
12
Risk Assessment
14
Risk Assessment Steps
Risk analysis involves three main steps
1) Identification of risk:
This is the first step in risk analysis. In order to tackle or mitigate
the impact of any future adversity, it is important to first identify
that risk. There are many types of risks in a construction project.
Some of them are political risk, market risk, economical risk,
contractual risk, environmental risk, technical risk etc. Once
identified, steps can then be taken to mitigate the impact.
2) Assessment of risk:
This step involves analyzing the impact of all the risk. It helps to
identify more severe and important risks.
3) Allotment of risk:
After the first two steps, risk are then allotted to respective
parties which can tackle a particular risk.
15
Agenda
PPP Projects are complex projects that require effective
attention to risk and their mitigation.
Risks are inherently related to returns and the
service/expertise which yields those returns
– This gives a good perspective on who is best placed to bear
the risk
– Objectives of the government in taking up a ppp project is
essential to decide who bears a particular risk
• Some General Principles in Risk Management
– Thoroughness in identification of risks
– Lessons from similar projects
– Should be borne by party best placed to bear it
– Quantification of financial impact to the extent possible
– Thoroughness of documentation
16
Risk Management
Governance
Description: Financial management for projects needs to be
separated from overall accounting system
Risk Level: Medium
Responsibility: MMRDA
Mitigation Measures: A financial management assessment was
carried out, which indicates that the MMRDA has an accounting
system that allows for the proper recording of project financial
transactions in accordance with international principles generally
accepted in India, and has sufficient financial management capacity
to administer the project.
ADB = Asian Development Bank, DMRC = Delhi Metro Rail Corporation, MMRDA
= Mumbai Metropolitan Region Development Authority.
17
Risk Management
Governance
Description: The executing agency is unfamiliar with ADB
procurement process
Risk Level: Low
Responsibility: MMRDA and ADB
Mitigation Measures: Procurement is governed through various
laws and decrees, consistent with internationally accepted
principles and practices to ensure transparency, safeguard the
integrity of the procurement process.
Goods and consulting services will be procured in line with the
relevant ADB guidelines, with prior review by ADB at key steps in
the procurement process.
ADB = Asian Development Bank, DMRC = Delhi Metro Rail Corporation, MMRDA
= Mumbai Metropolitan Region Development Authority.
18
Risk Management
Others
Description: The executing agency is inexperienced in implementing
metro projects
Risk Level: Low
Responsibility: MMRDA
Mitigation Measures: The MMRDA has been assisted by the DMRC
in the implementation of Line 2A. All equipment, including the
rolling stock, is being procured by the DMRC. The DMRC has a
sound reputation and track record in executing metro systems in
Delhi and in assisting with startups in other major cities in India.
ADB = Asian Development Bank, DMRC = Delhi Metro Rail Corporation, MMRDA
= Mumbai Metropolitan Region Development Authority.
19
Risk Management
Others
Description: Ridership projections are not realized owing to external
factors such as inadequate feeder systems
Responsibility: MMRDA
ADB = Asian Development Bank, DMRC = Delhi Metro Rail Corporation, MMRDA
= Mumbai Metropolitan Region Development Authority.
20
Risk Management
Others
Description: Delays in construction of tracks due to unpredictable
engineering problems may subsequently delay the commissioning
of rolling stock and signaling, train control, and telecommunications
systems.
ADB = Asian Development Bank, DMRC = Delhi Metro Rail Corporation, MMRDA
= Mumbai Metropolitan Region Development Authority.
21
Risk Management
Others
Description: Delays in approval of operational and organizational
plans due to prolonged government processes.
Responsibility: MMRDA
ADB = Asian Development Bank, DMRC = Delhi Metro Rail Corporation, MMRDA
= Mumbai Metropolitan Region Development Authority.
22
Risk Mitigation Overview
23
Risk Allocation
24
Finances Risk
Finance of Mumbai Metro
Total Project Cost ₹ 2356 Crores
Viability Gap Funding (VGF) ₹ 650 Crores
₹ 470 by GoI (20% of project)+ ₹ 180 by GoM (7.5% of project)
25
Financial Risk
Financial Risk of a Metro project mainly depends on three
components-Project Cost, Liquidity and Cash Flow.
26
Financial Risk: Project Cost
Project Cost Overrun
Estimated cost of Project- Rs. 2356 Crores
Actual cost of Project- Rs. 4300 Crores
There was an escalation of 82% in the project cost
Risk Mitigation-
Due to increase in project cost, MMOPL decided to increase the fare
and asked CM to increase the fare and got approval
Slabs Fare as per DPR Revised fare
(2004) 2013
A 9 10
B 11 20
C 13 30
D 40
27
Material Risk
• To mitigate such a risk the MMRDA should first be aware about the purchasing of
the materials, the dealers of the material should be approved by ISO certification.
Also, they should provide the quality certificate for each materials, like ballast,
sleepers, rails etc.
• Again, the department should have multiple options i.e., multiple number of
dealers of the materials. So that if one fails due to deliver the required material on
time, other could deliver that item on site on time, to avoid risk associated with
delay.
Abnormal Increase in
material prices compared
Availability of material
to
the original bid amount
28
Material Risk
• Mitigation Process
Availability of material
Responsibility of MMOPL for material
procurement and liable to pay penalty
for delay.
Delay in supply
29
Site Risk
• The risk associated with the land acquisition can be mitigated with the project
starting only after all the required land is procured and handed over by the
government.
• Sending pre notice to the landowner for the acquisition, so that acquisition
process can easily be done.
• For proper site investigation, the Daily Project Report (DPR) system should be
installed properly, and the format of DPR should contain site photographs, daily
material consumption, daily manpower used, and amount of work done etc.
30
Site Risk
• Mitigation Process
Land use and
Planning metro path on min. private
acquisition/resettlement and
lands at pre-fixed rates
rehabilitation risk
31
Site Risk
• Cost Estimate
13% of the
total
estimated
budget.
32
Site Safety Risk
• And the measures to mitigate such a risk is also very common like wearing safety
equipment like helmets, hand glows, boots, goggles etc. most of the government
enterprises and private firms do not follow such a measures, which they should be aware
of.
• Apart from this, many acts are there for the welfare of labors for example
– The Workmen’s compensation act, 1923
– The Employees Compensation act, 1923
– The Trade Unions Act, 1926
– The Payment of Wages Act, 1936
– The Employers Liability Act, 1938 and many more.
33
Site Safety Risk
• Mitigation Process
Surveillance by sub-contracted
Theft & Anti-social Elements
security services.
34
Site Safety Risk
• Risk Analysis
35
Site Safety Risk
36
Design Risk + Technical Risk
• As the major time required for the completion in railway project is Design and
survey phase, Perfect design is must necessary, as millions of kg of load is going
to transfer on that way. So, MMRDA spent more time for preparation of design
and survey reports.
• Here in this case, TEWET with DE-Consult & TCS, who is preparing the feasibility
reports of this project took 3 years to complete whole reports.
• So, it can be mitigated by ensuring good design report and vetted by owner and
consultant before the project commences. And also, by hiring experience
surveyors and designers or giving proper training to the fresher employee under
the guidance of experts such a risk can be mitigated.
• Also, by providing Defect liability clause in contract it can be done.
37
Design Risk + Technical Risk
• MMOPL must submit all the drawings and the schedule of the project to
MMRDA. These would be reviewed by MMRDA and scrutinized by the
Independent Engineer. MMRDA would not be responsible for any delays
caused due to the drawings of the project.
• The technology risk would vest with the both the private operator/
governments as the project would be executed in conformance with the
Specification and Standards specified in the Schedules of the
Agreement.
38
Legal Risk
• So, it can be mitigated by ensuring good design report and vetted by
owner and consultant before the project commences. And also, by hiring
experience surveyors and designers or giving proper training to the
fresher employee under the guidance of experts such a risk can be
mitigated.
• Also, by providing Defect liability clause in contract it can be done.
• MMOPL must submit all the drawings and the schedule of the project to
MMRDA. These would be reviewed by MMRDA and scrutinized by the
Independent Engineer. MMRDA would not be responsible for any delays
caused due to the drawings of the project.
Disputes among
Ambiguity of Difficulty to get
the parties of Change in Law
work legislations permits
contract
39
Legal Risk
• Mitigation Process
MMOPL must apply for all the
Difficulty to get permits permits/approvals required & bear
the risk of delays
40
External Risk
• Major dependence on one client - So, it is found that private consultancies who
work for such a government body should establish their office on every site
locations to overcome such an unnecessary cost and comfort.
• New stakeholders emerge and request changes - Unsupportive stakeholders
& loggerhead between shareholders are the major source of such a risks. Which
can be mitigated by working closely with the major stake holders and by knowing
their aspirations.
New stakeholders
Laws and local standards
emerge and request Public objections
change
changes
Major dependence on
Tax change Reputation Risk
one client
41
Organizational Risk
• Again, in this case such a kind of risk happens in private consultancies, the
subcontracted items and other design reports like GADs, Hydrological reports
etc. could not reach on time to the head office or respective site locations, which
aims to delay in getting permits and delay in execution of work as well.
• So, to overcome such a risk the private consultancies should manage proper
transportation systems. Also, the materials stored on site should be protected
well against rain, wind and other unnecessary things like thief, wasting etc.
Failure to disclose
Bankruptcy changes and resulting
extra work
42
Organizational Risk
• Mitigation Process
43
Management Risk
Poor site
Management of
Project manager's Resource management and
Contracts & Joint
technical capability management supervision by the
Ventures
contractor
Poor
Lack of leadership
communication Changes in
Improper planning quality of project
between involved management ways
manager
Parties
44
Management Risk
• Mitigation Process
45
Contractual Risk
• The contractual Liability types of risk found very serious effect on project.
• If in case for private consultancy firm failed to carry any work, so breach of
contract happens, to complete such an incomplete work, MMRDA must float
tender again, and after all the tedious procedure of tendering some another
consultancy firm will take the responsibility to complete the remaining work, which
causes lots of miss interpretation and tedious work.
• To mitigate such a risk the MMRDA should be strictly aware of breaching of
contract initially in tendering process.
46
Contractual Risk
• Mitigation Process
Only lenders are protected. MMRDA
takes over the assets and is liable to
Private Operator Event of Default
pay 90% of the debt due less
insurance claims.
MMRDA takes over the assets and is
liable to pay 110% of adjusted equity
MMRDA Event of Default
and 100% of debt due. Lenders are
covered.
47
Environmental Risk
48
Environmental Risk: Aarey Forest
• Metro Car shed area was
proposed on Aarey colony on a
plot of 1 acres.
49
Environmental Risk: Aarey Forest
• Environmental groups Vanashakti and
Aarey Conservation Group (ACG) filed
a petition with the National Green
Tribunal (NGT) in January 2015
requesting that the Aarey Colony be
protected as a no-development zone
• On 16 April 2019, the Supreme Court
rejected a petition filed the Aarey
Conservation Group, a non-government organisation, seeking an
alternative site to construct the depot.
• On 5th October 2019, people protested against cutting of trees at night
at Aarey forest, then Supreme court issues stay order on cutting of
trees.
• In March 2021, it was decided that the Metro shed car will be shifted
to Kanjumarg.
This delayed the opening of project by atleast 2 years
50
Operational Risks
51
Construction Risk
Major construction risks of a metro project are-
52
Construction Risk
Source: Vishwas H S, G D Gidwani, 2017, Hazards Identification and Risk Assessment in Metro
Railway Line Construction Project at Hyderabad
53
Construction Risk
Source: Vishwas H S, G D Gidwani, 2017, Hazards Identification and Risk Assessment in Metro
Railway Line Construction Project at Hyderabad
54
Risk Matrix
Source: Vishwas H S, G D Gidwani, 2017, Hazards Identification and Risk Assessment in Metro
Railway Line Construction Project at Hyderabad
The risk matrix shows the combination of impact and probability that in turn yield a risk
priority. In construction risks with high impact and high probability are design errors and
omissions, construction cost overruns and scheduling errors, contractor delays, and these
risks require further analysis, including quantification, and aggressive risk management.
55
Human Resource Risk
• Here, such a risks again happens majorly with private consultancies, due
to some trained employees working on such big projects leaves the jobs,
so the companies must hire some other new employees and must train
them first, which consumes too much time which indirectly effects the
project delay.
• MMOPL is the operating partner, hence it bears this risk.
• MMOPL must plan and manage its human resources according to the
demands and needs of the project.
Manpower Risks -
Inadequate succession Inability to attract quality
Specialized manpower
planning personnel
leaving the jobs
56
Assessing Value for Money
• A VfM analysis for the project has not been undertaken in the Feasibility Study.
– The only other comparable is the Delhi Metro where the (DMRC), is a public sector organization,
has been very successful in managing project timelines and costs.
– There is no precedent of similar institution in rail based public transport in Maharashtra.
– Neither can data on other public works contract be adapted for the Mumbai Metro One project.
– Therefore, a quantitative analysis to assess VfM was not practical for this project.
• But a qualitative assessment of what has been achieved by the private operator
based on publicly available information and discussions with officials working on
the project was attempted.
– Reduction in financial burden on the state budget – VGF was reduced from ₹1250 Cr to ₹650 Cr.
Compensation for shifting of public utilities add ₹50-60 Cr. Taxes in return are estimated to be
₹300 Cr.
Hence, net spending = ₹400 Cr. Return after 35-year assets worth = ₹ 2300 Cr
– Substantial Risk Transfer – The private sector has undertaken substantial project risks, such as
financing, construction, operations and traffic/ revenue risks. Traffic risk, which is one of the
major risks of a user fee-based model, is completely vested with the private operator with no
clauses that provide for any compensation by the state government if the rider ship of the metro is
low.
57
Key Learnings
• Assessing bid process is crucial – The process of bid for choosing the
successful bidder took more than 2 years. This led to a lesser number of
bidders to bid for the project. The concession agreement was based on
the model concession agreement. These delays resulted in only one
bidder finally submitting a bid for the project.
• Delays in approval can derail the project – There was a delay in
obtaining approvals for the over bridge that passed over the railway line
from the railway authorities. Project gets delayed from scheduled
deadline because a railway was exploring the feasibility of another
project invading the path of the metro line. It is recommended that
authorities be cognizant of all other upcoming infrastructure projects that
have the potential to affect operations of the planned project while
bidding out such projects and resolve the same prior to the appointment
of a developer.
58
Key Learnings
59
Key Learnings
61
Thank You
62
62