SUMMARY PROGRESS INSULATION OF INSTALLATION ON SKID

Date : 16 August 2023


Subject : Summary Progress Insulation of Installation On Skid
Project : SLB MEG AREA 1 ( TRAIN-5 )

TOTAL TOTAL
PIPING INSULATION TOTAL TOTAL
A SERVICE TEST PACK NUMBER PROGRESS PROGRESS REMARK PLAN COMPLETED
INSULATION TYPE SPOOLS PROGRESS
LAST WEEK THIS WEEK

No. SKIDS

1 SKID-1 GL IP 01T5-1JN-GL-SK1-TP-001 28 0% 0% Not Realess yet 6 Days after Realess

Realess from
2 SKID-1 GL IP 01T5-1JN-GL-SK1-TP-002 9 50% 0% 50% 15 August 23
Painting

Realess from
3 SKID-1 DC IP 01T5-1JN-DC-SK1-TP-001 6 50% 0% 50% 15 August 23
Painting

Realess from
4 SKID-1 DC IP 01T5-1JN-DC-SK1-TP-002 5 50% 0% 50% 15 August 23
Painting

SKID-2 HM IH 11 80% 20% 100% Completed


5 01T5-3AB-HM-SK-2-TP-001
SKID-2 HM IP 1 0% 0% 0% Not Insulation

Realess from
6 SKID-2 HM IH 01T5-3AB-HM-SK-2-TP-002 13 60% 35% 95% 9 August 23
Painting

Realess from
7 SKID-2 HM IH 01T5-3AB-HM-SK-2-TP-003 36 55% 40% 95% 14 August 23
Painting

SKID-2 HM IH 9 80% 20% 100% Completed


8 01T5-3AB-HM-SK-2-TP-004
SKID-2 HM IP 1 0% 0% 0% Not Insulation

Realess from
9 SKID-2 HM IH 01T5-3AB-HM-SK-2-TP-005 15 60% 35% 95% 9 August 23
Painting

10 SKID-2 HM IP 01T5-1AB-HM-SK-2-TP-006 3 100% 0% 100% Completed 15 June 23

SKID-2 GL IH 17 0% 0% 0% Not Realess yet 10 Days after reales


11 01T5-1JN-GL-SK-2-TP-001
SKID-2 GL IP 4 0% 0% 0% Not Realess yet 6 Days after Realess

12 SKID-2 GL IH 01T5-1JN-GL-SK-2-TP-002 16 0% 0% 0% Not Realess yet 12 Days after Realess

13 SKID-2 GL IH 01T5-1JN-GL-SK-2-TP-003 2 0% 0% 0% Not Realess yet 6 Days after realess

14 SKID-2 GL IH 01T5-1JN-GL-SK-2-TP-004 2 0% 0% 0% Not Realess yet 6 Days after realess

15 SKID-2 GL IH 01T5-1JN-GL-SK-2-TP-005 5 0% 0% 0% Not Insulation

Realess from
16 SKID-2 GL IH 01T5-1JN-GL-SK-2-TP-006 16 60% 35% 95% 14 August 23
Painting

Realess from
17 SKID-2 VT IH 01T5-1JN-VT-SK-2-TP-001 2 70% 25% 95% 14 August 23
Painting

Realess from
18 SKID-3 WC IC 01T5-1NN-WC-SK-3-TP-001 4 0% 50% 50% 7 Days after Realess
Painting

Realess from
19 SKID-3 WC IC 01T5-1NN-WC-SK-3-TP-002 3 0% 50% 50% 7 Days after Realess
Painting

20 SKID-4 PG IH 01T5-1JN-PG-SK-4-TP-001 8 55% 35% 90% Completed 20 August 23

21 SKID-4 PG IP 01T5-1NN-PG-SK-4-TP-002 8 75% 25% 100% Completed 07 August 23

Realess from
SKID-4 GL IH 16 0% 50% 50% 7 days after realess
Painting
22 01T5-1JN-GL-SK-4-TP-001
Realess from
SKID-4 GL IP 8 0% 50% 50% 7 Days after raeless
Painting

Realess from
SKID-4 GL IH 10 60% 20% 80% 20 August 23
Painting
23 01T5-1JN-GL-SK-4-TP-002
Realess from
SKID-4 GL IP 9 0% 50% 50% 20 August 23
Painting

Realess from
24 SKID-4 GL IP 01T5-1JN-GL-SK-4-TP-003 10 30% 25% 55% 20 August 23
Painting

Realess from
SKID-4 GL IH 3 0% 10% 10% 7 Days after raeless
Painting
25 01T5-1JN-GL-SK-4-TP-004
SKID-4 GL IP 4 0% 0% 0% Not Realess yet 7 Days after raeless

26 SKID-4 GL IP 01T5-1JN-GL-SK-4-TP-005 1 0% 0% 0% Not Insulation

Realess from
27 SKID-4 HM IH 01T5-3AB-HM-SK-4-TP-001 2 65% 20% 85% 10 August 23
Painting

Realess from
28 SKID-4 HM IH 01T5-3AB-HM-SK-4-TP-002 2 65% 20% 85% 10 August 23
Painting

Page 1 of 2
Realess from
29 SKID-4 HM IH 01T5-3AB-HM-SK-4-TP-003 6 65% 20% 85% 15 August 23
Painting

Realess from
30 SKID-4 HM IP 01T5-1AB-HM-SK-4-TP-004 4 30% 20% 50% 15 August 23
Painting

Realess from
31 SKID-4 HM IH 01T5-3AB-HM-SK-4-TP-005 5 60% 25% 85% 11 August 23
Painting

Realess from
32 SKID-4 WC IC 01T5-1NN-WC-SK-4-TP-001 24 0% 55% 55% 16 August 23
Painting

Total Spool and Progress Installation Pipings ( % ) 328 32% 20% 51%

Note :

Prepared By, Checked By, Approved By,

PT.Arca Bimasakti PT.Wasco Engineering Indonesia PT.Wasco Engineering Indonesia