Professional Documents
Culture Documents
Florian Fink / Thomas Hensler, OMICRON, Austria / Frank Trillenberg, NRM Netzdienste, Germany / Jörg Köppel,
ABB, Germany
The double busbar substation Kruppstraße has ten 2.2 Communication to the Test Devices
active bays, where one ABB REB500 field unit is For the communication between the test devices, the
installed each. Into each field unit a CMC test devices binary input/output extension device and the
injects one current triple and records the binary controlling PC, an Ethernet network was built up in
signals for trip, annunciation busbar trip and the substation. The application software can control
annunciation breaker failure. Because the CMC test all 6 CMC test devices using this network, replay the
devices are capable to output two current triples, for calculated transient current signals on the
some cases one test device was used to inject into two corresponding test devices and record all binary
neighbouring field units. signals.
ABB REB500
fild units
CMCs
PTP-Transparent
Switch
ISIO200
CMGPS588
ABB REB500 PTP GMC
central unit
Laptop with
RelaySimTest analog- and binary signals
Ethernet connections
For the time synchronization of the CMC test devices 2.3 Overview of the Equipment Used
a GPS-receiver CMGPS 588 was used, which provides
a precise time synchronization using IEEE 1588 PTP In total the following equipment was used:
(Precision Time Protocol) over the existing Ethernet • 6 OMICRON CMC test devices
connections. The CMGPS 588 device operates as an • 1 binary input/output extension device
IEEE 1588 grandmaster clock, which forwards the OMICRON ISIO 200
time information to all CMC test devices over the • 1 switch Hirschmann Mach 1040
network. For the Precision Time Protocol the IEEE • 1 GPS-receiver OMICRON CMGPS 588
1588 power profile was used, which requires a PTP-
• about 300 m Ethernet cable (including 5 Ethernet
transparent switch, so that the required time
cable reels),
precision (± 100 ns) can be guaranteed between all
• More than 100 measurement leads, many with
switch ports.
length of 6 and 10 m
• A huge number of power cables and extension
socket outlets
3 Wiring Check
Next the check of the wiring had to be done. Therefore
unsymmetrical currents were injected into one or two
bays using only one test device. This should show,
that the currents are measured correctly on the
individual field units and that the corresponding
binary signals can be recorded by the CMCs.
For other fault types this non-selectivity could not be relatively short time, without the need to change the
observed. In the beginning this false behaviour could test setup. The network calculation within the
not be interpreted. After analysis of the fault software provides all the test quantities and using a
recordings from the central unit of the protection it complete setup with various test devices almost all
was obvious, that there was a wiring error in the substations can be tested.
Holmgreen-circuit within the coupling field. The
It could be shown, that smaller deviations, such as the
terminals of the ground currents were connected
wiring error described above, could not be found by a
wrong, so that the single-phase-to-ground fault
classical parameter test. If it is necessary to inject
currents over the coupling were interpreted wrong,
currents at three locations simultaneously, classical
which resulted in the false behaviour described
parameters tests are at its limits. For the utility NRM
above.
this was the first time to test a busbar protection in
detail in the field. For the future it will be considered
8 Advantages of a Simulation- to apply this approach for every new commissioning.
Based Test in Addition to a
Parameter Test Literature
The setting parameters of a protection relay are [1] Ziegler, G.: Numerical Differential Protection –
important and relevant for the function of a Principles and Applications, Publicis Publishing,
protection system. To verify that these values, 2nd Edition, 2012
calculated from the network calculation, work [2] ABB: Distributed busbar protection REB500 -
correctly within the protection relay and are set Operation Manual, 9th Edition (valid for software
correctly, is the main task of a classical parameter test version V7.60), ABB, 2011
during commissioning. In a complex protection
system, as within a busbar protection, these para-
meters are linked with a high number of logical
functions, which
makes the overall test
of the whole system
considerably more
difficult. Therefore
complex tables have to
be made, where all the
fault cases which have
to be tested are
described and where
all the values to inject
are calculated indi-
vidually.
This process can take
up to a whole week for
a bigger substation
and due to the
numerous rewirings
necessary and the
manual calculation of
the test quantities this
is a huge effort and
very prone to errors.
RelaySimTest offers
the possibility to
automate this test. The
effort to setup the test
is quite high (see
Figure 3: Scheme of
the test setup), but if it
is done correctly once,
a complete system test
Figure 10: Simulation of an Inside Fault with RelaySimTest
can be conducted in a