You are on page 1of 14

Article

Subcontractor Selection Process Through IIM Kozhikode Society & Management Review
9(2) 129–142, 2020
Vendor Bids: A Case of An Outsourcing © 2020 Indian Institute
of Management Kozhikode
Service in Construction Reprints and permissions:
in.sagepub.com/journals-permissions-india
DOI: 10.1177/2277975220942078
journals.sagepub.com/home/ksm

Shobha Ramalingam1

Abstract
Subcontractors handle a large portion of the work in construction projects. The ability of the general contractor to deliver
projects on time, within budget and with the expected level of quality are significantly dependent on the performance
of subcontractors. Thus, selecting the right subcontractor for the right task is a determining factor for project success.
Literature has identified several criteria for subcontractor selection that predominantly includes financial capacity, ability
to complete on time and reputation and quality of workmanship. However, as projects are becoming more global and
complex, ensuring selection and award through a fair and competitive formal process becomes imperative. Nevertheless,
an understanding of a formal process, backing the selection criteria, seems to be lacking; more so in the context of
engineering outsourcing services. Vendor bid analysis is one such service, wherein the general contractor packages the
bids received from several subcontractors to a team in a different country who evaluate and enable the general contractor
to select and award the subcontractors for project tasks. To this end, an exploratory case study was conducted in an
outsourcing firm in India that provide services to general contractors in the USA to understand the formal process
of subcontractor selection across organizational boundaries along with its inherent risks and challenges. Data was
collected through a participatory research approach, supplemented with participant observation and team interviews
which were analysed through inductive reasoning and cross-case comparison methods. The findings showed a formalized
5-phase process across the organizational interface that included assess, identify, evaluate, negotiate and optimize phases.
Further, delving into the evaluate, negotiate and optimize phases, the nuances in outsourced projects and the firms
strategy to overcome them were evident, such as selection criteria and negotiation strategy adopted in the case of
a single bidder with high pricing to mitigate probable bid-rigging practices or ensuring constant training to overcome
the challenges due to lack of trade and country specific know-how. In addition, through a reflective approach, the value
addition services provided to the general contractor aimed to optimize the process and improve project governance.
These findings are expected to provide practical implication for firms in similar business and act as a steppingstone to
conduct further robust research.

Keywords
Subcontractor selection, vendor bid analysis, outsourcing services, process management, construction projects

Introduction Subcontracting allows the main contractor to transfer a


portion of his responsibility and associated project risks
Subcontracting constitutes a major portion of construction to the subcontractor. In view of it, Hinze and Tracey (1994)
projects in the architecture engineering and construc- contend that the selection of a subcontractor becomes
tion industry. Hoban and Francis (2003) note that one of critical as the ability of the main contractor to deliver the
the prominent characteristics of a construction project is project within time and budget and with the expected level
the practice of subcontracting a portion of a project by the of quality depends primarily on the performance of the
General Contractor (GCs) as a part of the overall contract. subcontractor.

1
Associate Professor, School of Construction Management, and Head, CSCDM, National Institute of Construction Management and Research (NICMAR),
Pune, India.

Corresponding author:
Shobha Ramalingam, Associate Professor, School of Construction Management, and Head, CSCDM, National Institute of Construction Management and
Research (NICMAR), Pune, India.
E-mail: sramalingam@nicmar.ac.in
130 IIM Kozhikode Society & Management Review 9(2)

Prior studies demonstrate that selection of a subcontrac- painters, who specialize on specific trades, b) Specialist
tor, to identify a responsive and responsible bidder, is a subcontractors such as for tunnel boring or post-tensioning
multicriteria decision process. For example, studies by and pile foundation activities and c) Labour-only subcon-
Cooke and Williams (1998) and Shiau, Tsai, Wang, and tractors, who provide skilled and unskilled labour to the
Huang (2009) identified subcontractor’s reputation, finan- main contractor (Eccles, 1981; Smith, 1995). By subcon-
cial capacity, quality of workmanship and timely comple- tracting, the GC can tap on subcontractors’ specialization
tion as some of the key selection criterions. Similarly, Doloi and thereby transfer portion of his project responsibility and
(2009) identifies 43 sub-criteria for a robust selection. On the associated project risks to the subcontractor (Arditi &
the other hand, traditional approaches base the selection on Chotibhongs, 2005). While this is advantageous, it is also
the lowest tender quote received even though researchers risky as the overall performance of the contractor depends
argue that making lowest bid price as the only criterion on the performance of subcontractors. For instance,
for award may not be appropriate (CIB, 1997; CSIR, 2002; Thomas, Marosszeky, Karim, Davis, and McGeorge (2002)
Hartmann, Ling, & Tan, 2009; Lavelle, Hendry, & Steel, argue that ‘rectification costs’ in case of poor performance
2007). While the debate on the set of criteria is still on, yet by the subcontractor could be as high as 12 per cent of the
another school of thought opine that having a selection total project cost. Thus, selecting the right subcontractor
criterion alone may not suffice and while it is a ‘necessary’ essentially contributes to a project’s success.
condition, it may not be ‘sufficient’ to ensure a competitive Seminal work by Hinze and Tracey (1994) in the United
bidding process. For instance, Bowen, Akintoye, Pearl, States and Latham (1994) in the United Kingdom highlight
Edwards (2007) throw light on the fact that the selection of problems in contractor–subcontractor selection criteria
subcontractors is largely based on an ad hoc process due to process due to the predominance of the ‘lowest price win’
reasons such as limited time to conduct a formal process. philosophy. Subsequent studies in this domain show that
However, such ad hoc methods defeat the purpose of fair subcontractor selection process is a multi-criteria decision
competition and judicious evaluation. Thus, taking a para- process which is not solely dependent on the cost of esti-
digm shift, researchers including CIB (1997), Beil (2010), mate of project tasks. For instance, Cooke and Williams
Ulubeyli, Kazaz, and Arslon (2017) advocate the need for a (1998) and Okoroh and Torrance (1999) observe past expe-
formal procedure for subcontractor selection and proclaim rience, financial strength, management ability to liaise with
that subcontractor/vendor/supplier must be selected through the main contractor and quality of workmanship to be sig-
processes such as competition, negotiation, partnering or nificant criteria for selection. Other studies include famili-
joint venture. arity with lean principles (Maturana, Alarcon, Gazmuri, &
In perspective, with the onset of globalization, compa- Vrsalovic, 2007), contractor’s quality records (Gruneberg,
nies are becoming more international and competition Hughes, & Ancell, 2007) and subcontractor’s reputation,
fiercer. Multinational engineering firms and global contrac- quality and time performance (Shiau et al., 2009) as sig-
tors are adopting global sourcing strategies. With strict reg- nificant. Nevertheless, time and again, studies have also
ulatory environments and formal contracting laws backing reported ‘price’ to be the dominant factor. For instance,
the projects, a formal selection procedure for vendors and Lavelle et al. (2007) showed that price still remained the
subcontractors becomes imperative. Intuitively, it therefore single prime criterion for selection and suggested assessing
interests one to explore the process of subcontractor selec- the relative importance of criteria under different scenarios
tion in the global context in order to understand the set of such as between high and low value work packages. A
procedures that entails the selection process along with its study by Hartmann et al. (2009) further assessed the rela-
embedded challenges. The next section discusses in detail tive importance of four main criteria that include quality,
insights from the literature that pave way to understand the price, technical know-how and cooperation but concluded
theoretical gaps. that ‘price’ is by far the most important selection criterion.
A study by Ajayi, Ayanleye, Achi, and Johnson (2010) also
highlight the trade-offs the main contractor has to make in
Literature Review the decision-making process, such as based on availability
of equipment, geographic location and project dynamics.
In large scale infrastructure projects, around 80–90 per cent However, in the last decade researchers have identified
of the project are subcontracted. This is predominantly due multiple criteria. For instance, Doloi (2009) identified 43
to increased project complexity and uniqueness (Hinze & sub-criteria for the selection process that included both
Tracey, 1994; Scott, Levitt, & Orr., 2011). Subcontractors quantitative and qualitative factors. Similarly, El-Khalek,
perform specific tasks on a project and in general are of Aziz, and Morgan (2018) categorized 55 criteria under
three types: a) Trade subcontractors such as carpenters or seven categories to determine the significant factors for
Ramalingam 131

subcontractor selection including time, cost, reputation, subcontractor selection process in an international project.
financial and risk capability. Apart from identifying the cri- For instance, in the first stage, shortlisting comprised of
teria, the evaluation process was also developed further. 10 criteria that included past performance, experience and
For instance, Marzouk, El Kherbawy, and Khalifa (2013) financial strength. The second stage, negotiation included
conducted a statistical analysis to identify significant crite- seven criteria such as knowledge of project, ability to solve
ria from several influencing factors previously identified in problems and reliability. Finally, the third stage, selection
the literature including cost, quality, technical capability, included seven criteria such as price, labour, payment plan
management capability, health and safety, reputation and and equipment. Thus, both a formal process and criteria for
time. Thus, it can be inferred that advances in subcontrac- selection in each phase was significantly highlighted.
tor selection methodologies has made a shift from the sin- In perspective, several countries impose a cap on the
gle criterion of price only to multiple performance criteria project cost that allow for either informal or formal bidding
using robust evaluation techniques. practices. For instance, according to the public contract
Further, though several performance based criteria code 10504.5 stipulated by the State of California in the
along with framework and approaches exist for subcon- USA (UCOP, 2015), competitive bidding practices for
tractor selection, literature also highlights the fact that the construction services allow informal bidding up to $300K.
main contractor tends to select subcontractors by neglect- Projects over $300K require the GCs to select qualified
ing the key criteria of performance and rather chooses to subcontractors and for contracts over $640K, GCs must
adopt unfair, ad hoc and biased selection practices (Bowen follow a formal bidding process. It is therefore evident that
et al., 2007). As informed by Mbachu and Nkado (2007), the selection criteria per se, though collectively exhaustive,
perhaps this explains the poor performance scenario on may not be independent and mutually exclusive. Adding
construction projects globally. However, with the onset of further, selection criteria, though a ‘necessary’ condition,
globalization, companies are becoming more international may not be ‘sufficient’ to ensure selection of a responsive
and competition fiercer. With strict regulatory environ- and responsible bidder through a fair and competitive
ments and formal contracting laws backing the projects, a bidding process. This insight brings in a paradigm shift in
formal selection procedure becomes imperative. A review our focus and triggers our interest to look at the formal
of literature in the international context demonstrates the selection procedures that back the subcontractor selection
procedural steps followed in the selection process. For criteria, more so in international projects.
instance, studies by Kakabadse and Kakabadse (2005) and One of the lucrative business model in the international
Beil (2010) discuss the supplier selection process in inter- context for construction projects is the global sourcing
national projects and in outsourcing strategies. These stud- strategies, namely ‘outsourcing’ and ‘offshoring’ services,
ies emphasize the need for a formalized selection process. that provide global and multinational engineering firms the
For instance, Beil’s (2010) study recommends adopting needed advantage to concentrate on delivering their core
a 5-stage formal procedure comprising of: identifying competencies while contracting out non-core project tasks
suppliers, soliciting information from suppliers, setting such as structure detailing works and development of
contract terms, negotiating with suppliers and evaluating Good-for-Construction drawings. Other benefits include
suppliers for a robust selection. Similarly, CIB (1997) availability of a global talent pool, round the clock work
advocates the need for a formal laid-down procedure ena- execution and price optimization on project tasks (Lewin
bled through strategies such as competition, negotiation, & Peeters, 2006). In the recent past, several construction
partnering and joint ventures. They further posit that the contractor firms have also adopted the strategy of outsourc-
principles of good selection practice must include: a) clear ing to contract with third party service providers, either
procedures that ensure fair and transparent competition within (domestic outsourcing) or outside the country (off-
among all subcontractors, b) a systematic tendering shore outsourcing) for services such as cost estimation and
process to identify and shortlist the number of qualified quantity take-off, developing simulated models, third-party
candidates and c) negotiations and final assessment prior design checking and so on (Lane, Maznevski, Mendenhall,
to awarding of the contract. Observing the caveats, CIB McNett, 2004). Apart from the stated benefits, yet another
(1997) also informs that the entire selection process is major reason for the popularity of this strategy among the
time consuming and require expertise to align with the GCs in the US construction industry is that approximately
formal contract of the project, probably a prime reason that 80 per cent of the firms have fewer than 10 employees (CIB,
deters main contractors from systematically adopting a 1997). On the other hand, ‘offshoring’, the practice of sub-
formal selection procedure for the award of subcontracts. contracting a part of the project task to their own subsidiary
Interestingly, Ulubeyli et al. (2017) took a step further in another country, is more predominant with multinational
to conceptualize the selection criteria with the phases of engineering firms (Messner, Chen, & Joseph, 2007).
132 IIM Kozhikode Society & Management Review 9(2)

A significant part of a contractor’s work that is out- selection is a process by which firms primarily identify,
sourced is project cost estimation, which is principally evaluate, negotiate and contract vendors/subcontractors/
through vendor bid analysis technique. PMBOK® (2013) suppliers. However, in the global context, such as in an out-
states it as a structured formal process initiated by the GC sourcing strategy, there is limited literature that informs of
to systematically select and award the project to vendors the formal procedure for the selection process. A compre-
or subcontractors. This technique allows the GC to esti- hensive understanding on the various phases that entail the
mate the project cost by comparing the bids submitted process and the sequence of activities in it is still lacking.
by multiple qualified vendors/subcontractors. However, Motivated by these insights, this study tries to understand
the parameters of cost estimation that are crucial and deter- the vendor selection process in an outsourcing context and to
mine competitive vendor selection include accuracy, confi- this end explores the following two research questions:
dentiality, credibility, precision, reliability, risk detailing,
uniformity, validity and verification. PMBOK® (2013, a) What are the various phases and activities involved
p. 207) also observes that ‘when projects are awarded to a in the subcontractor selection process in an out-
vendor under competitive processes, additional cost esti- sourcing strategy?
mating work may be required of the project team to exam- b) What are the challenges in the process and how does
ine the price of individual deliverables and to derive a cost the outsourcing team optimize and add value to the
that supports the final total project cost’. While such tech- process?
niques aim at ensuring a fair and competitive bidding
process, a highly debated topic in the literature with respect
to the contractor and subcontractor selection process is Research Methodology
the unethical bidding practices such as underbidding, bid
cutting and shopping, bid rigging and overbilling (Azhar, The study required investigating on the life cycle of a
Selph, & Maqsood, 2011; Olusegun, Benson, Esther, & project across organizational and national boundaries. Due
Michael, 2011). For example, in a recent study in the to the exploratory nature of the study, participatory research
Middle East, Shah and Alotaibi (2017) demonstrate that approach was adopted. Participatory research is based on the
top three contractor-related factors leading to unethical principles of participation and self-inquiry and is viewed as
bidding practices were withdrawal of an offer in exchange an alternative to the conventional qualitative social research
of money, bid shopping (such as divulging one’s bid to that allows for rich data collection, a prerequisite for explor-
other competitors prior to award, in order to secure a low atory studies (Eisenhardt, 1991). The fundamental principle
bid) and bid rigging (wherein, competitors conspire to of this approach is that it is research with rather than on
allow one another to secure contracts at raised prices). people (Heron & Reason, 1997; Reason & Bradbury, 2008;
Cognizant of this fact, measures are laid down by various Reason & Heron, 1986). It is also synonymously associated
regulatory authorities to curtail such practices. For instance, with ‘action research’ and termed as ‘participatory action
the National Code of Practice has laid down nine key moral research’. However, researchers like Bell et al. (2004) con-
standards for fair bidding that include tenderers should not tend that while there are several points of convergence in the
take part in any type of collusive practice and ought to be two methods, such as ‘orientation to inquiry’, there are also
prepared to prove their probity. However, in essence, these certain distinctive features. For instance, in a participatory
are some of the challenges and known risks that the con- research, the emphasis is on ‘collaborative research’ activi-
tractors must be aware of to ensure a fair bidding. ties rather than on ‘action’. Hence, while reflection is conse-
Reflecting on the above, it is evident that frameworks quential in action-based research, it may not be in the case
and criterions exist for robust subcontractor selection. of participatory research and the outcome of a participative
However, the lack of a formalized selection process and research may lead to new insights and broadens perspec-
adoption of ad hoc and biased procedures defeats the pur- tives, such as on processes or every day practices (Lewin,
pose of a fair and free-market competition. Thus, the focus 1946; Kindon, Pain, & Kesby, 2007).
of this study is primarily to understand the subcontractor Data was collected through participatory research
selection process and the formalized process sequence approach wherein a research student was stationed in an
in it rather than on identifying criteria for subcontractor outsourcing firm in India for a period of two months, from
selection. While Beil (2010) proposed a 5-stage selection April to June 2018. The outsourcing firm contracted work
process (identify supplier, solicit information, set contract primarily from engineering or contractor firms in the USA
terms, negotiate, evaluate/award), Ulubeyli et al. (2017) to execute tasks such as building information modelling
identified three stages (shortlisting, negotiation and selec- and conditioning, predictive data analysis, project cost esti-
tion). Instinctively, it can therefore be inferred that vendor mation and quantity take-off, bid support service such as
Ramalingam 133

production tracking and document control for projects. Two On-Scree-Take-off (OST) software. Further tasks included,
projects were selected for the study, namely Project Hill and developing document control for specifications and adden-
Project Crest (pseudo names to maintain confidentiality), dums and preparing a summary bid sheet with the scope of
which were ongoing during the researcher’s stationed period. work and quantities identified.
Both were renovation projects of a school building, each This bid sheet was then dispatched to the GC, who
of which was budgeted at a cost of 15 to 20 million USD. based on the identified scope and quantity of work in the
These two projects were packaged by a GC from the USA. project, invited tenders from subcontractors or vendors by
The work was contracted to prepare the bid package and floating a Request for Proposal (RFP) or Request for Quote
provide support in the vendor (subcontractor) selection pro- (RFQ). This phase was primarily executed by the GC.
cess. The researcher was part of a team of 3–5 people, who However, it was critical to identify a minimum number of
executed the tasks on the two projects. Data primarily col- viable and potential subcontractors to drive competition
lected through participant involvement was further sup- and reduce disruption risks. On receipt of the bids, the
ported through observations and semi-structured interviews. GC would package them back to the outsourcing firm to
The interviews were open-ended in nature and were con- analyse and evaluate the offers.
ducted post the completion of the project task with the team Received bids were evaluated to compare the pricing
members. Data was analysed using inductive reasoning strategy of the subcontractors for the given scope of work.
technique and compared across the two cases to enable This task resulted in the preparation of a bid book. The
rationalization of the data (Yin, 2003). The results and the bid book was a comprehensive document that informed
findings are discussed in the following section. about the number of subcontractors/vendors competing for
each task of the project, the bid amount and the percentage
of cost involved (to the total cost of the project) for the bid
Case Findings packages.
The bid book was then dispatched to the GC with infor-
This section is divided into four parts. Process flow Sequence mation on the major scope of work in a project and the
and Project Phases identifies the flow sequence of the pro- bidders proposed cost estimates along with a list of short-
cess across the organizational interface. Remaining subsec- listed subcontractors with selection criteria and negotiation
tions focus on each of the sequence phases in depth. Vendor strategy. Based on the negotiation between the two parties,
Selection Criteria and Negotiation Strategy discusses the the subcontractors re-submitted a bid, which was then re-
vendor selection criteria, Process Challenges and Coping evaluated at the outsourcing unit. Thus, the entire process
Methods identifies the challenges faced in the process and was repeated between the client and the outsourcing team
the coping mechanisms adopted and Improving Project till the final selection and awarding of the contract to the
Governance discusses the team’s initiatives to improve vendors/subcontractors for the specified tasks of the project.
project governance. The role of the outsourcing firm would either culminate
post the selection and awarding of the subcontractor or
based on the contract between the GC and the outsourcing
Process flow Sequence and Project Phases firm, both parties would monitor and manage the vendors
till the completion of the scope of the work. In this study,
A work order was foremost contracted between the client while the outsourcing firm was not involved in the vendor
(the GC) and the outsourcing firm for a defined work pack- management process, they undertook activities to optimize
age with specified deliverables. The sequence of workflow the selection process, improve project governance and pro-
and the activities involved in the work package were as vide value-added services to the client. Figure 1 illustrates
follows: the set of tasks involved at the offshore and onshore unit
Project drawings and specifications were received from and the sequence of the workflow across the boundaries.
the GC as a pdf file that included architectural, civil, struc- In particular in this study, the received work package
tural, landscape, mechanical, electrical and plumbing details. included 250–300 drawings for each of the two projects.
The tasks for the team in the outsourcing firm was primarily Figure 2 shows a sample of the drawing received in the
to assess the scope and estimate quantities. This included work package and the estimation and quantity take-off
reviewing the design, organizing the drawings using done using the OST software, wherein, each element was
Bluebeam software, formatting the drawings with company colour-coded and the quantity estimated.
custom sequence orders, developing document control for Further, during the review process, the teams in the
drawings and creating a ‘bookmark’. Quantity take-off was outsourcing firm interacted virtually with the client team
then carried out for each element of the building using over e-mail and telephone for analysis and clarification
134 IIM Kozhikode Society & Management Review 9(2)

Figure 1. Process Flow Sequence

on the project. The following vignette from one of the laundry equipment are different in specifications and draw-
respondents during an interview elucidates the Request for ings. The responses from the client were primarily over
Information (RFI) raised: mail were: a) It is on sheet no. XXX. b) Wait for addendum
1. c) It is in addendum 1. Please refer to it. d) Go as per the
In case some component is mentioned in the drawings but the specifications.
description of that component is not given in specification
As discussed, a bid sheet was generated and dispatched to
or insufficient data is provided, then we enquire about it to
the architect/engineers of the client to get the relevant data. the client (the GC) to inform about the scope of the work,
On-screen take-off sheet is done accordingly and made avail- various tasks and the quantities involved in the project. It
able for rectifications, if necessary. required four weeks for the team to prepare the bid sheet
based on which the client initiated the bidding process and
Some of the clarifications made included: a) Are metal invited tenders from local subcontractors and vendors. The
lockers present in the project? b) There is a door marked on received bids were subsequently packaged back to the team
sheet no. XXX but no description is given for that. c) In the in India for evaluation of the bids and preparation of a bid
specifications, two types of canopies are described but, in book for each project. Preparation of a bid book required a
the drawing, only one type is mentioned. d) Dimensions of duration of 10 days.

Figure 2. Quantity Take-off Using OST Software, Project Crest


Ramalingam 135

Probing further, the next three subsections provide a Scope of work with larger bid amount and minimal
detailed understanding on the Evaluate, Negotiate and competitors was of significant concern to the GC as shown
Optimize phases to unearth critical aspects of the process. in red in Figures 4(a) and 4(b). The pricing strategy by
the vendors/ subcontractor had to be examined critically.
In certain instances, only one bid was received for tasks
Vendor Selection Criteria and Negotiation Strategy with a larger scope of work, leading to no competition and
with a possibility of higher pricing strategy put forth by the
This subsection focuses on the activities in the Evaluate
vendor. For example, in the case of Project Crest, it was
and Negotiate phases to understand the bidder selection
observed that electrical works accounted for 11.99 per cent
criteria, the negotiations that take place with respect to the
of total project cost and the bid amount quoted was
bid amount and the nuances involved. When multiple bid-
$1,140,000.00, highest tender amount (see Figure 4(a)).
ders submitted their bid, the bidder with the bid amount
A similar scenario was observed for plumbing works
closest to the actual price estimated by the outsourcing
with 9.92 per cent of total cost and an amount of
team was shortlisted and communicated to the GC. Figure
$1,574,000.00 in Project Hill (see Figure 4(b)). Only one
3 shows a sample of the bid list created. The highlighted
quotation was received for those tasks. On being informed
rows in green were the selected bids in each category. For
instance, for concrete, 11 bids were received. The vendor by the outsourcing team, the GC subsequently sought more
with a bid amount of $1,694,847.00 was shortlisted. quotations for this work package from other bidders and, in
Revised bids had to be received when a bidder was found the process, anticipating a stiff competition, the first bidder
to have included only a limited scope in the estimate or had also revised his quotation and resubmitted his bid, presum-
submitted an incomplete bid. Such practices ensured accu- ably by reducing his profit margin, as informed by one of the
racy in the cost estimate and functioned as a warning signal team members in the firm. This process consequently led to
to the main contractor. optimizing project costs and helped to take account of the
As informed by the respondents, the negotiation strategy bid value for future projects.
was with respect to number of bidders and the bid amount. Figure 5 shows various bidder scenarios. Figure 5(a)
Figures 4(a) and 4(b) shows a sample of the bid package for shows a 0 to 2 bidder scenario, wherein wherein, there
projects Crest and Hill respectively, that include information were instances when no bids were received for tasks such
on the bid amount, percentage of the bid amount to total cost as foundation, metal stair nosing, rough carpentry and
of the project and the number of subcontractors / vendors re-roofing. Figure 5(b) shows instances of single bidder for
competing for the various project tasks. tasks such as glazing, fire alarm, electrical and laboratory

Figure 3. Selection Criteria of Bid Amount


136 IIM Kozhikode Society & Management Review 9(2)

Figure 4(a). Bid Package, Project Crest


Figure 4(b). Bid Package Sample, Project Hill

equipment installation and Figure 5(c) shows instances of ‘Accuracy’ in estimate and ‘document control’ were two
3–5 bidders for tasks such as door frame, drywall, plumbing major ingredients for successfully executing the work
and mechanical respectively. packaged by the client as informed by one of the respond-
In such situations, it was crucial to inform the client and ents. However, the team faced three major challenges:
receive more bids wherever there was only one bidder (or Foremost was the lack of knowledge on different trades
no bidder) in order to ensure a fair competition, ethical bid- that led to inaccurate estimates by the outsourcing team,
ding and project cost optimization. This entire exercise was which in turn led to providing the client with inappropriate
therefore iterative till the final selection of subcontractors selection criteria. This also often led to rework. Respondents
and vendors for the project tasks. from the outsourcing firm informed that re-work in projects
had often led to 20 per cent or more increase in total project
costs and eventually resulted in loss of goodwill. To over-
Process Challenges and Coping Methods come this challenge, the outsourcing team insisted bidders
quantify the scope and bid quotation as per the work break-
This subsection focuses on the activities in the Evaluate down structure of the respective trades. Further, to diffuse
and Negotiate phases to understand the process challenges. this knowledge, the team members were constantly provided

Figure 5(a). 0–2 Bidder Scenario Figure 5(b). Single Bidder Figure 5(c). 3–5 Bidders
Ramalingam 137

Figure 6. Combined Vendor–Cost Comparison Across Projects for Major Activities

with in-house training on country-specific trade activities cost component in most of the projects. They included con-
and estimation techniques. crete works, masonry works, structural steel combo, roof-
Second, the bidders would submit a lumpsum quote for ing system, glass and glazing, drywall and ACT, plumbing,
the tasks instead of a detailed item rate quote. This would mechanical, electrical works and site utilities. An in-depth
lead to ambiguity in the scope of work and result in a analysis allowed the team to arrive at a standardized unit
discrepancy in the bid amount. In certain instances, the rate for each of the above activities. This in turn helped
bidders would refuse to re-submit the bid as an item rate to educate GCs on market rate per unit of quantity and
quotation even if it was insisted. Such quotations were standardize the bid practices. Figure 6 shows the combined
risky, and an accurate estimate and selection criteria were vendor–cost analysis across projects that led to identify the
challenging. rate per unit of a quantity.
Third, the selection criterion was more often based on Such value-added initiatives by the team led to minimiz-
the lowest bidder. However, certain vendors/subcontractors ing of variation and disparity among the contractors of vari-
would quote for multiple tasks in the project. While the bid
ous projects and thereby improved project governance. Yet
analysis helped to identify the quantum of work for which
another initiative for improving project governance included
the vendor submitted a bid, it was difficult to assess the
providing bid tracking features as an add-on to enable the
capability of the subcontractor to perform multiple tasks.
GC to compare and analyse the bids according to inclusion
It was therefore required to assess the vendor’s current
or exclusion of the work scope during project execution as
workload and other parameters including reputation and
against the contracted work package and sum. This service
past experience by the GC. However, due to time constraint,
this was not always possible and it caused a discrepancy in aided the GC to monitor and manage vendors with ease, in
judicious selection, leading to poor project performance case the outsourcing team was not involved post selection of
post bid award. the subcontractors, until project completion.

Improving Project Governance Discussion


This section focuses on the activities in the Optimize phase This study explores the subcontractor selection process in
to understand the team’s effort to optimize the process. an outsourcing strategy. Foremost, the study identifies five
Through a process of self-inquiry and as an effort towards phases and the activities involved in each phase of the
improving project governance that could enhance the abil- process flow sequence (see Figure 1). The identified five
ity of the GC to select vendors/subcontractors for future phases and the flow sequence is as follows:
works with little variation in pricing strategy, the teams
developed several value-addition processes. One such ini- Assess à Identify à Evaluate à Negotiate à Optimize
tiative was to compare the major activities in a project that
contributed to a larger scope of the work with higher cost Based on insights from practice theory put forth by Barley
component across all projects in order to identify the opti- and Kunda (2001) and Feldman and Orlikowski (2011), the
mum cost of execution and economize on project costs. phases in the life cycle of an outsourcing project from the
Ten major activities were thus identified that had a higher time when work is contracted with an outsourcing unit and
138 IIM Kozhikode Society & Management Review 9(2)

packaged for execution till task completion and handover In this study, the outsourcing team did not manage the ven-
to the client are coined as verbs. This framework further dor portfolio post vendor selection and bid award. However,
identifies the activities involved in each of these phases reflecting on the sequence of tasks performed and to add
(see Figure 1), which is a significant contribution of this value to the services provided, the outsourcing team took the
study. Comparing and contrasting the five phases in this initiative of comparing a total of 10 bid books developed
study with the procedural steps put forth by Beil (2010), a during the same period to establish the vendor selection cri-
distinction was evident in the outsourcing context. For teria and arrive at a standard unit rate for every quantity, an
instance, the outsourcing team evaluated the received bids important information that would standardize the bid rates
in Stage 3, compared and verified the quantities estimated across projects and aid clients in a judicious vendor selection
by the vendor and assessed its accuracy to the defined process. Such initiatives aimed to optimize the process and
scope. Based on the assessment, bidders were shortlisted, maintain a long-standing relationship with the clients and
and the GC was informed for further evaluation and improve project governance. ‘Optimize’ was thus an opera-
negotiation. It is therefore proposed that in Stage 3, the tional responsibility which continued till the termination
process sequence would be the Evaluate phase. However, of the contract. Deloitte (2013) argue that this phase could
post negotiation, re-assessment and re-evaluation would ensure that the vendor execution was optimally managed
take place, prior to final selection and award of the contract. and continually improved through constant feedback in the
Additionally, it was observed that in the Assess phase, the operation and by also looking ‘inward’ into the process and
outsourcing team assessed the project scope, estimated the organization. The benefits would then include continual
quantities and informed the client (the GC) of various improvement of the agreed governance model, long-term
subcontracting tasks based on which the client floated a planning and impact assessment for effective contractual
notice inviting tender (RFP) to solicit information from the obligation.
vendors in the form of quotations. This was an activity in Third, in this study, the Negotiation phase culminates
the Identify phase and therefore not earmarked separately into a ‘contract’ unlike the study by Beil (2010) wherein
from solicit information phase as proposed by Beil (2010). ‘negotiation’ and ‘contract’ are two distinct phases. The
Further, setting contract terms was not carried out by the negotiation strategy explored in this study was with respect
outsourcing team on the two projects and therefore it is not to the selection criteria, bid amount and the number of
considered as a separate work practice in this study. competing subcontractors. Further, Beil (2010) argue that
Second, through this framework, a comprehensive under- the negotiation processes in practice may combine take-it-
standing can be drawn on the pre-selection, the Assess phase or-leave-it offering, competitive tendering and bargaining.
and post-award, the Optimize phase, in the process sequence. This aspect was evident in this study. The negotiations
These activities are not evident or significantly informed were in fact a trade-off between various dimensions such
in the existing literature. For instance, the GC foremost as price and time. For instance, high price and shorter task
dispatched the project scope as a bundle of drawings to the duration vs low price and longer duration. As Beil (2010)
outsourcing firm. The team in the outsourcing unit had to informs, the challenge lies in constructing the trade-off for
subsequently review, organize, assess the scope of work and a ‘win-win’ strategy to both parties. When the bids were
prepare a bid sheet, based on which the GC would float a negotiated, vendors were inclined to revise and re-submit
tender or RFP. This Assess phase was quite critical to iden- the bids, which had to be re-evaluated and. if necessary,
tify all necessary tasks for which the GC would invite bids re-negotiated, till final selection and award of the contract.
and subcontracts. Proper understanding of the project scope, Thus, the entire process was iterative in nature, more spe-
good knowledge of the local regulations and by-laws of cifically in the evaluation and negotiation phases between
the country where the project was being commissioned the vendors, the GC and the outsourcing team.
and sound technical know-how to accurately - estimate were Fourth, multiple bids for a particular task ensured fair
critical parameters at this phase for the outsourcing team. competition and pricing strategy. Hence, to induce competi-
This also meant that the outsourcing unit had to develop tion and avoid overpriced bid estimates, especially in cases
technical and managerial competencies to handle contrac- where there were less than three bidders, the GC would
tual technicalities and legal know-how in the global context invite further tenders. During such instances, it was interest-
(Leonardi & Bailey, 2008; Mahalingam & Levitt, 2007). ing to note that the initial bidder would revise his quotation
Subsequently, in the Optimize phase, if vendor management anticipating a stiff competition. In essence, such negotiation
was part of the contract of the outsourcing firm, then transi- strategies curtail malpractices such as ‘bid rigging’ (Porter
tioning the contracted scope of work and resources to the & Zona, 1993). The Competition Act 2002 (Competition
vendor/subcontractor for execution and monitoring the task Commission of India, 2000) has laid provisions related to
completion comprised the vendor management portfolio. ‘bid rigging’ and connote that subcontracting arrangements
Ramalingam 139

are often part of a bid rigging scheme wherein competitors reliability of documentation, which eventually would help in
who agree not to bid or to submit a losing bid collude to keep reducing rework due to wrong assessment of the bid package
and estimate.
the bid amount at a predetermined level, thereby stifling
fair market competition. In such instances, the rigged price
Apart from training to overcome the issues due to lack of
could be higher than the competitive bidding price. This was
knowledge of specific trades, the team also proposed to the
explicitly evident in the two projects explored as explained
GC to request for a detailed breakup of the vendors’ esti-
in subsection Vendor Selection Criteria and Negotiation
mate according to the work breakdown structure of their
Strategy. Bid rigging is an illegal and fraudulent practice, a
respective trades in the RFP. These insights address the
criminal offense that can be investigated in the Court of Law.
Bid rigging practice have some sort of monetary benefit for second research question in this study.
the bidders. For instance, a low bidder may agree to with- Finally, it was noted that when bidders bid for multiple
draw their bid in favour of the next low bidder in exchange tasks, it was a challenge to assess their current workload
of a lucrative subcontract in the next project or so. OECD and capacity to execute multiple tasks in the project.
(Organization for Economic Cooperation and Development) Decisions had to be taken for sole-award contracting vs
countries that support free-market economy have estab- multiple-award contracting based on selection criteria such
lished stringent laws to curtail this practice and suggest as timely completion, reputation, financial capability, qual-
designing the tender process to maximize participation ity of work and the price. On this aspect, Beil (2010) argue
(OECD, 2013). Researchers like Foremny and Dorabialski that there could be many other considerations for such
(2018) say that one practical way to prevent collusion is decisions. For instance, to avoid monopoly and continued
to expand the list of potential bidders by inviting a wider presence in future projects, multi-award contracting could
group of qualified subcontractors or suppliers to participate, be favoured. Alternatively, sole-award contracting would
as was also evident in this study. Further to ensure this prac- be beneficial when it is unduly costly or risky to deal with
tice, they suggest that effective competition can be enhanced multiple suppliers (subcontractors).
if a sufficient number of credible bidders are able to respond In short, it was significantly evident that both a formal
to the invitation to tender and have an incentive to compete procedure and selection criteria complemented each other in
for the contract. the process. Selection criteria or a formal procedure alone
Fifth, the process challenges evident in this study were did not suffice for a robust selection. Further, as noted in the
quite interesting and relate to earlier studies that reflect literature, ‘accuracy’ in estimation and ‘document control’
these aspects significantly in the literature such as due to were critical governing principles.
cultural and institutional differences across national bound-
aries; lack of local knowledge (Mahalingam & Levitt, 2007;
Scott et al, 2011); interpretation issues in construction Conclusion
drawings; communication challenges due to technology-
mediated interaction and complexity in projects (Leonardi This study aimed to explore the bidding procedure in the
& Bailey, 2008; Iorio, Peschiera, Taylor, & Korpela, 2011) subcontractor selection process through an outsourcing
augmented with the need to ensure ‘accuracy’ and ‘reliabil- strategy in construction. Two projects were selected in an
ity’ in cost estimation (PMBOK®, 2013). Providing con- outsourcing firm in India that contracted with a GC in the
stant ‘training’ on local work practices and construction USA to support subcontractor selection process using
methods was one of the coping mechanisms adopted by the vendor bid analysis technique. A participatory research
firm in this study as is also explicitly informed in the litera- approach to the study ensured rich insights on the formal
ture. The outsourcing team depended heavily on the GC as procedure adopted. A process flow chart was developed
a ‘knowledge broker’ for clarifications and understanding. that illustrated the sequence of workflow through five
However, the team also informed that they looked at the phases across the organizational interface. They include
possibility of accessing additional information through a) Assess, b) Identify, c) Evaluate, d) Negotiate and e)
advanced technology instead of heavy reliance on the GC as Optimize. An understanding of the activities in each phase
is evident from the vignette below: and the process sequence addresses the first research ques-
tion and is a major contribution for improved theoretical
From our experiences, and assessing our performance and understanding.
challenges, we can say that it can be improved by better col-
Second, it was evident that a formalized procedure was
laboration and coordination using the latest technologies to
access additional information instead of singularly depend- necessary, which would complement the subcontractor
ing on only one source of information, the client, and also to selection criteria in the evaluation and negotiation phases
improve understanding the scope, accuracy in estimates and of the process. Thus, while vendor bid analysis is by itself
140 IIM Kozhikode Society & Management Review 9(2)

a structured technique to systematically evaluate and select time and support during data collection and analysis and for
vendors/subcontractors (PMBOK®, 2013), nonetheless, it sharing information on two of their projects for academic and
research purpose.
required to be backed by two factors: a) a robust formal
procedure wherein ‘accuracy’ of information, ‘document
Declaration of Conflicting Interests
control’, ‘reliability’ and ‘verification’, all of these param-
The author declared no potential conflicts of interest with respect
eters are critical and b) subcontractor selection criteria for
to the research, authorship and/or publication of this article.
judicious evaluation and negotiation in order to identify
responsive and responsible bidder. Funding
Third, the nuances involved in the process and the mana-
The author received no financial support for the research,
gerial implications to overcome the same were evident by authorship, and/or publication of this article.
delving deeper into evaluate, negotiate and optimize phases
of the process flow sequence, which addressed the second ORCID iD
research question. For example, during instances of a single Shobha Ramalingam https://orcid.org/0000-0003-4026-5866
bidder or less than three bidders with high pricing, the GC
was informed to invite more bids. In such situations, single References
bidders were also found to revise and resubmit their bids. Arditi, D., & Chotibhongs, R. (2005). Issues in subcontracting
Such selection criteria and negotiation strategy ensured practice. ASCE Journal of Construction Engineering and
curtailing the probability of unethical practices. Further, Management, 131(8), 866–876.
providing in-house training on trade-specific activities Ajayi, O.M., Ayanleye, A., Achi, F., & Johnson, O. (2010)
Criteria for selection of subcontractors and suppliers in a
or country-specific construction practices or requesting a
building project in Lagos state, Nigeria, Proceedings 5th Built
breakup of the submitted estimate based on bidders trade Environment Conference, Durban, South Africa.
specific work breakdown structure, were some of the mech- Azhar S., Selph J., & Maqsood T. (2011). Unethical business prac-
anisms adopted to overcome interpretation issues and to tices and corruption in international construction: A survey
ensure reliability and accuracy of the bid estimate for judi- of American contractors working overseas. In K. Haugbølle,
cious selection of a responsive and responsible bidder. S. C. Gottlieb, K. E. Kähkönen, O. J. Klakegg, G. A. Lindahl,
This study suffers from certain practical limitations. For & K. Widén (Eds.). 6th Nordic conference on construction
economics and organisation: Shaping the construction/society
instance, the subcontractor selection criteria that can back
nexus. (Vol. 3, Construction in society, pp. 457–468). Denmark:
the formal process, such as during the evaluation and nego- Danish Building Research Institute, Aalborg University, .
tiation stages, were not explored. It was apparent in this Barley, S.R., & Kunda, G. (2001). Bringing work back in.
study that the teams in the outsourcing unit primarily based Organization Science, 12(1), 76–95.
their evaluation on the pricing strategy of the bidders and Bell, J., Cheney, G., Hoots, C., Kohrman, E., Schubert, J., Stidham,
had limited knowledge on the bidder’s pre-qualification as L., & Traynor, S. (2004). Comparative similarities and
differences between action research, participative research,
well as selection criteria, which predominantly influenced
and participatory action research. Retrieved from http://www.
vendor selection. It would therefore be more holistic to iden- arlecchino.org/ildottore/mwsd/group2final-comparison.pdf
tify the selection criteria that are critical in the various stages Beil, D. R (2010) Supplier selection. In J. J. Cochran (Ed.). Wiley
of the process. Taking forward, future studies could also encyclopedia of operation research and management science
explore the correlation between vendors’ pre-qualification (pp. 1–13). New York: John Wiley & Sons.
and selection criteria along with the stages of construction to Bowen, P., Akintoye, A., Pearl, R., & Edwards, P.J. (2007)
Ethical behaviour in the South African construction industry.
make the framework more robust, especially in the context
Construction Management and Economics, 25(6), 631–48.
of engineering outsourcing services. In perspective, though Construction Industry Board, Working Group 3 (CIB). (1997).
the findings cannot be generalized due to a single firm analy- Code of practice for the selection of subcontractors. London:
sis, it is believed that the developed process flow chart with Thomas Telford.
an understanding about its challenges can benefit practition- Cooke, B., & Williams, P. (1998). Construction planning,
ers in similar settings to eliminate or minimize contractor’s programming and control. UK: Macmillan Press Ltd.
Competition Commission of India. (2002). Competition Act,
risk for improved project performance and delivery in the
2000: Provisions relating to bid rigging (Advocacy Series 3).
construction industry. Retrieved from www.cci.gov.in
CSIR (2002) Status of the construction industry in South Africa.
Acknowledgement Council for Scientific and Industrial Research, Building
I would like to acknowledge the contribution of Mr. Vishu and Construction Technology. Retrieved from www.csir.
Goyal, former post graduate student in Advance Construction co.za/websource/ptl0002/docs/boutek/akani/2002/jul/01.
Management at NICMAR, Pune for being part of the study and html
instrumental in collecting data and compiling the results. I am Deloitte. (2013). The outsourcing handbook: A guide to outsourc-
profoundly thankful to the team in the outsourcing firm for their ing, London: Deloitte MCS Limited.
Ramalingam 141

Doloi, H. (2009) Analysis of pre-qualification criteria in contractor implicit knowledge explicit in task-based offshoring. MIS
selection and their impacts on project success. Construction Quarterly, 32(2), 411–436.
Management and Economics. 27(12), 1245–1263. Lewin, K. (1946). Action research and minority problems.
Eccles, R. (1981). Bureaucratic versus craft administration: The Journal of Social Issues, 2(4), 34–46.
relationships of market structure to the construction firm. Lewin, A.Y., & Peeters, C. (2006). Offshoring work: Business
Administrative Science Quarterly, 26(3), 449–469. hype or the onset of fundamental transformation? Long
Eisenhardt, K. M. (1991). Better stories and better constructs: Range Planning, 39(3), 221–239.
The case for rigor and comparative logic. Academy of Mahalingam, A., & Levitt, R.E. (2007). Institutional theory as a
Management Review, 16(3), 620–627. framework for analyzing conflict on global projects. ASCE
El-khalek, H.A., Aziz, R.F., & Morgan, E.S. (2018) Identification of Journal of Construction Engineering and Management,
construction subcontractor prequalification evaluation criteria 133(7), 517–528.
and their impact on project success. https://doi.org/10.1016/j. Marzouk, M.M., El Kherbawy, A.A., & Khalifa, M. (2013)
aej.2018.11.010 Factors influencing subcontractors’ selection in construction
Feldman, M.S., & Orlikowski, W.J. (2011). Theorizing practice projects. Housing and Building National Research Center
and practicing theory. Organization Science, 22(5), 1240– (HBRC) Journal, 9, 150–158.
1253. Maturana, S., Alarcon, L.F., Gazmuri, P., & Vrsalovic, M. (2007).
Foremny, A., & Dorabialski, W. (2018). Review of collusion and On-site subcontractor evaluation method based on lean
bid rigging detection methods in the construction industry. In principles and partnering practices. Journal of Management
M. J. Skibniewski & M. Hajdu (Eds.). Proceedings of the cre- in Engineering, 23(2), 67–74.
ative construction conference (pp. 946–953). DOI 10.3311/ Mbachu, J.I.C., & Nkado, R.N. (2007). Factors constraining
CCC2018-123 successful building projects implementation in South Africa.
Gruneberg, S., Hughes, W., & Ancell, D. (2007) Risk under
Construction Management and Economics, 2(1), 39–54.
performance-based contracting in the UK construction sector.
Messner, J., Chen, C., & Joseph, G. (2007). Effective use of the
Construction Management and Economics, 25(7), 691–9.
global engineering workforce (Research Report 211(11)).
Hartmann, A., Ling, F., & Tan, J. (2009). Relative important of
Austin, TX: The Construction Industry Institute.
subcontractor selection criteria: evidence from Singapore.
OECD. (2013). Investigations and the use of screens to detect
ASCE Journal of Construction Engineering and Management,
cartels, ex-officio cartel. Organisation for Economic Co-
135(9), 826–832.
operation and Development, Retrieved from http://www.
Heron, J., & Reason, P. (1997). A participatory inquiry paradigm.
oecd.org/daf/competition/exofficio-cartel-investigation-
Qualitative Inquiry, 3(3), 274–294.
2013.pdf
Hinze, J., & Tracey, A. (1994). The contractor–subcontractor
Okoroh, M. I., & Torrance, V. B. (1999). A model for subcontractor
relationship: The subcontractors’ views. Journal of Construc-
selection in refurbishment projects. Construction Management
tion Engineering and Management, 120(2), 274–287.
and Economics, 17(3), 315–327.
Hoban, A.M., & Francis, V.E. (2003). Improving contractor/
Olusegun, A., Benson, O., Esther, A., & Michael, A. (2011),
subcontractor relationships through innovative contracting.
Corruption in the construction industry of Nigeria: Causes
In B.O. Uwakwe, & I.A. Minkharah (Eds.). Construction
innovation and global challenges (pp. 771–778). Cincinnati, and solutions. Journal of Emerging Trends in Economics and
OH: CRC Press. Management Sciences, 2(3), 156–159.
Iorio. J, Peschiera, G., Taylor, J.E., & Korpela, L. (2011) Factors PMBOK®. (2013). A guide to project management body of
impacting usage patterns of collaborative tools designed to knowledge (PMBOK®; 5th Ed.). Pennsylvania, PA: Project
support global virtual design project networks. Journal of Management Institute, Inc.
Information Technology in Construction, 16, 209–230. Porter, R.H., & Zona, J.D. (1993). Detection of bid rigging in
Kakabadse, A., & Kakabadse, N. (2005). Outsourcing: Current procurement auctions. Journal of Politics and Economics
and future trends. Thunderbird International Business 101, 518–538.
Review, 47(2) 183–204. Reason, P., & Heron, J. (1986). Research with people: The
Kindon, S.L., Pain, R., & Kesby, M. (Eds.). (2007). Participatory paradigm of co-operation experiential enquiry. Person-
action research approaches and methods: Connecting people, Centred Review, 1(4), 456–476.
participation and places. UK: Routledge. Reason, P., & Bradbury, H. (2008). Concluding reflections:
Lane, H.W., Maznevski, M.L., Mendenhall, M. E., & McNett, J. Whither action research. In P. Reason & H. Brandbury (Eds.).
(2004). The Blackwell book of global management: A guide Action research, participative inquiry and practice (2nd ed.,
to managing complexity. Blackwell Publishing. pp. 695–707). Los Angeles, CA: SAGE.
Latham, M. (1994) Constructing the team: Joint review of pro- Shah, R.K., & Alotaibi, M. (2017). A study of unethical practices
curement and contractual arrangements in the UK construc- in the construction industries and potential preventive
tion industry: Final report by Sir Michael Latham. London: measures. Journal of Advanced College of Engineering and
H.M.S.O. Management, 3, 55–77.
Lavelle, D., Hendry, J., & Steel, G. (2007). The selection of Shiau, Y., Tsai, T., Wang, W., & Huang, M. (2009). Use question-
subcontractors: Is price the major factor? In D. Boyd (Ed.). naire and AHP techniques to develop subcontractor selection
Proceedings of the 23rd Annual ARCOM Conference system. Construction Management and Economics, 33(2),
(pp. 65–73). UK: Association of Researchers in Construction 1–6.
Management. Scott, W.R., Levitt, R.E., & Orr, R.J. (Eds.) (2011). Global
Leonardi, P.M., & Bailey, D.E. (2008). Transformational projects: Institutional and political challenges. Cambridge:
technologies and the creation of new work practices: Making Cambridge University Press.
142 IIM Kozhikode Society & Management Review 9(2)

Smith, A.J. (1995). Estimating, tendering and bidding for California, Office of the President, Facilities manual, State of
construction: Theory and practice. Basingstoke: Macmillan. California.
Thomas, R., Marosszeky, M., Karim, K., Davis, S., & McGeorge, Ulubeyli, S., Kazaz, A., & Arslon, V. (2017). Decision criteria for
D. (2002). The importance of project cultures in achieving subcontractor selection in international projects. Proceedings of
quality outcomes in construction. In C.T. Formoso & G. Bal- the International Conference on Civil and Environmental Engi-
lard (Eds.). Proceedings of 10th conference of the International neering. Cappadocia, Nevsehir, Turkey, May 8–10, 2652–2665.
Group for Lean Construction (pp. 101–13). Retrieved from Retrieved from http://dx.doi.org/10.17100/nevbiltek.321055
http://iglc.net/Papers/Conference/12 Yin, R.K. (2003). Case study research design and methods
UCOP. (2015). Changes to informal competitive bidding, Public (3rd Ed., Applied Social Research Method Series 5). Sage
Contract Code 10504.5, Construction Services, University of Publications.

You might also like