You are on page 1of 41
CONTRACTOR’S PROPOSAL FOR LOC NINH 1 SOLAR POWER PLANT (200MWp) Engineering, procurement, construction, supply, Installation, testing & commissioning Dated: 24 May, 2020, ‘TABLE OF CONTENT 1, PROJECT DESCRIPTION.. 2, PV SYSTEM 24 PV Array System 22 PV module, 2.3 Inverter and box transformer 2406 Combiner Box. 2. Calculation ofthe optimal angie of photovolaie modules 26 PY aray layout 3. ELECTRICAL SYSTEM.. 3.1 Grounding and Lighning Protection. 8.2 Cable Laying Instalaton Method 23 Lighting Systems 54 Substation Communication system, 35 CCTV system... 4. CONTROLAPROTECTION SYSTEM.. 4. SCADA System, 4.2 Metecrological stations 5. CIVIL WORK. 5.1 General 7 5.2 Site Clearance & Freperation 5.3 Stuctxe 5.4 Architecture 55 Road 5. Water Supply and Orsinage and Sewage Treatment Syste, 6. FIRE ALARM ANO FIREFIGHTING SYSTEM... 7. ANNEXES sen |AINEX-I CODES AND SIANUARUS ANNEX.02 PERFORANCE TESTS. [ANNEX-08 INSPECTIONGS, TESTING AND COMMISSIONING [ANNEX.OM BILL OF GJANTITIES (EQUIPMENT AND MATERIALS) ANNEX0S BILL OF QUANTITIES (CIVIL WORKS). ANNEX-06 PVSYST SIMULATION CALCULATION, LOCI SOLAR OME ANT ao) 1. PROJECT DESCRIPTION Loc Nh 12.8 solar powerplants planned fo be bultin Loc Ni, Tinh Binh Phu, wth @ ‘esigned total installed capacty of $49.9984 Mp (DC). Thre are three PV ds, each with 2 capacty of 199.08 MW, 198.88 NAP and 149.8384 RAN, as doa in the follow tabla 4 ‘Table 11 Overview of nal capacty nunerot | Meet! | cir | AC inst Pan | Pvmoau | oy lat ag | cope | canmaty | None reaper | Sretaonants | | “tw — - Faupment oem | 454500 0 woos | sors | “oie pret teennn2 | ese 00 0 woos | ters teens | se0ae0 8 woores | was Toa | 12eseco ° ‘senstea | 51075 2. PV SYSTEM 2.4 PV Array System Solar system designed in Loc Nin 1 solar powerplant consists of 464,500 ploves (2440.Np Monocystaine soon ipece), such a the above table 1.11. In order to factate the connection, the projct provided with 20 sats &.2SMW PV power generation unis in oa Lec Ninh 4 solar power slant hove 30 photovaliae power generaton uns. Each unt is Cequioped with one 6:25 NWA Box transformer and two sets 3128 KW cantralze Inverters, and twenty-four 2-ivone DC bghining protectan combiner boxes, Each combiner box is comected to less than 22 photovoltaic module stings, and each photovtaic module sting is comectedin sates wih 3¢ photovoltaic modules. On the whole, each unt provides 262-254 sets PV arrays withthe 2x30 arrangement. Every furor treo 6.25 MW units connect fo the hey: bult 220 RY eop up cubtation for ono cu ofthe 3 HY eurenteatoton tne. Dip angle ofthe PV arrays 10:The PY aay system votage is 1800 Voc. 2.2 PV module ‘Atleast 440W¥p Menc-cytln scon PV mori is applied to the Project. According tothe Cfcioncy reduction rte fe the 30-year operation petod ofthe plant, the minimum power ‘generation rates of 82.52% and 82.5% stall be guaranteed ae the opeaton for 10 years ‘and 30 years. Table 22-1 ain Paramore of PY Module z ria LOCIVNH 1 SOLAR POWER PLANT 00H) =n im eam + | Tee tree ons scan 2 | eect prance 21 | Sania rowerauaa i) 0 22_ | oastsonertowerc Mo on 23. | Weaie eco OH we 24_|Peksovrvatine wee 25 [Peak poer cent 0) ‘0x7 20 | openctadvtge mor 27 | shots crt ‘0x7 28. | Tremevinan vtge fay 0 ‘eves 3 | treme pane 21 Rata oping topes tal 6) ra 32 | Temper coe eso cutee) soo 33. | fenpute coat operat vatge i aa 4 | Temperature coeficent ef peak power (SK) a3 “| tects “| Bmersin at em ‘ec 608585 42 | wean oa) od 43 | eearntrg mr aa “| ere ctorncon fincin box rer 78 [Fane mari ——- 5 [Ope condo 2a enperne iewermere Noa The parameters We above able ae only used nthe bidding scheme aie Hage, and the fal parameters vil be based on the purchased equipment parameters 2.3 Inverter and box tranaformer 234 tnvertar ‘Tho unit capacty snot ess than 625M, each unt has 2 sets atleast 3. 125MW centralized inverters, “Table 23-4 Man Paramtreof ols than 6:25 HW (29.1264) verter Oct + ScLAR POWER RANT ont) im con ro canon esrumepvoiege | teow | Rat oumarowr | — ata ‘i Pa iar eps evar 7 _voltageystarting vokage output power ee KW wperiateaeare® | arson | Masini odeteunos | arian Tinie ee | 7A | _Feledgoinge | SPE oie wer gary | Noverman | Gatvotnge ange | oie Nashaew DoF] em aa | Rewdgitegns | Sale Micra o6 hort aq meron | app caret wwanmagcepny | 2225 Moin Operating temperature ‘effclencylefficlencyin | 39.%96.7% | P* “ee 36-600 OTA ~eoow [canna | Reatseranet = — Ta coaenets | trowtar | po printonand ting | eavbrodutn arg Sig SEOANTGN 00 OY doo sp ag alana ROTOR "Note: The parameters in he above table are only used inthe bang scheme at his stage, ‘and the na parameters wile based on the purchased equipment parameters 2.3.2 Box transformer ()95kV Tanstormer ‘Te box transformer has one no less than 6250 kVA transformer, $510 65-0.6RV, ro ese than 6250 KYA transformer, double. spit winding ot-immersed transformer, copper core winding, opacity: >B25MVA Reted vole at HV site: 35kV Rated vatage at Vso: 063K {(heoordng tothe inverter tpt val) “Transformation rato: 5282 570 63.0 634 Connection group: Dyttytt ‘Stort-crout mpedancs: 6% (According to the IEC 60076 standard) (2)854V Ring Main Unit ‘Tha high-voltage si of tho transfocmer i csanscted toa group of metsl-enclosed SF6 Insulation ring network caoinet equipment (RMU) tough a medium-votage cable. This ‘equipment is equipped wth wo load switch cabinets and one vacuum cra breaker cabinet LOCUM 5 SOAR POWER PLANT (2004) ‘The veltage love i 35AV the current is 630A, and the shoc-oreultcurent fs 20KA (1s) Compliant with global safey and gid code, “The Contractor willkep the ttalinstaled capac ofthe Box transformer of hs project changed, Note: Considering the equipment upgrade and replacement of each invertor ‘manufacturer, there are two capacity specifications of 6.25MW and 6.8MW (2 sets 34M), The specific parameters need tobe determined according tothe equipment procurement; the contractor will determine the total capacity ofthe inverter No leas than 618.76. 2.4 DG Combiner Box Its demandes 1°65 protocion class to satsy the need af eutlook insaation and usage as \wel as SPO protection frst power power supply system. Cable grand in-out terminal, ‘maximum PV array vitae 1500 Ve 22 inputs Fuse with hlder type, DC ckcit breaker, OC ‘SPO, satfpowered, cure! mentoring foreach string, PY vetage monitor and SPO fake ‘monitoring must be Indes in DC combiner box also 2. Calculation ofthe optimal angle of photovoltaic modules According to the feast study report, the annual average radiation at ste area i 1847.58 ‘env? and input the radiation int the PV system sofware fo simulate the radiation at ste ‘ares, When the optimal angle of the photovollc modules Is 10 degres, the loss on the Inained surface ofthe PY modula isthe smallest. The amount of radiation receved isthe largest The photovoltaic power generation dung the operaton ofthe photovolaie power station fs shown in the PVsyst siulation resus inthe Annex 08: PVSYST SIMULATION, CALCULATION. 26 PV array layout “The photovoltaic power pent is died info 3 plots, The PV fled area of Loc Ninh 1 projct ‘covers an area of about 29 hectares. In ord to avoid shadows, the pitch of the component ‘subaraysin each block (fent and back edges ofthe PY module array) is 5400 ~ 6000, 3. ELECTRICAL SYSTEM 3.4 Grounding and Lightning Protection Grounding and lightning design shall conform to the Intute of Electcal and Elbctroncs Enginors standard IEEE 60/2000 "Guide for Safety in Gri station Grounding “and IEC £2205"The bahtning protecioninemational standard LOC HIN SOLAR POWER ANT 20) 3.14 Grounding of the PY Aray for Lighting Protection ‘Grouncing and ightning design shall conform tothe insttte of Electical and Elecrones [Engineers standard IEEE 80/2000 "Guile for Safety in Grid station Grounding” and IEC 623057Tho ightring proton international standard’ or equivalent Photovotac (PV) lghining amesters ofthe installed solar pane! area (Photovoltaic: PV) witb designed and manufactured in accordance wih system features suchas: rik density, ‘rect Ightning power, elecscty voltage, scale ofthe system. = The stel bar of foundation pla aso wil be mainly taken as dee ighningprotactive earthing for PV aay of ie power station, = The S05 mm# gavanlzed fat steal shal be lad around the equipment as the ‘rounding gid forth transformer and inverter, andthe 2.6m-ong 050 steal tube with hot galvanzing shalbe lida the verical grcunding electrode. “The PY modula ram is connected to tha bracket through the pressure block, ‘The PY Combiner box davies are connected to the bracket grounding eystem network ‘trough a 50 mn? plastic copper wie. ‘The wesc and tzaneformer are connected to bracket grounding system network through 55 mn galvanized flat tee, The photovoltaic medues shal be conecad fo the bracket by passing blocks the Photovaltsic fed brackets shall be connected by 404 mm? galvanzad fat seal and is realy connected with the main grounding network. Lightning protection systom and fre extinguishing sytem in photovoltaic area should mat requirements of Vtnam EVN and IEEE 80-2000 standard The earthing resistance of PV arays not greater than 4 0. ~ Allightrng protector for Inete station, MDB station, Lightning protection of the PV fled shall be use Faraday type connected with soparate ground system from PV. The ‘earthing resistance isnot higher han 40 - Uhting protection tthe photovoae fo, Lightning proteton ofthe PY filed shall be ‘early steamer type connected wih separate ground system from PV. The earthing resistance isnot higher than 20. 3.2 Cable Laying Installation Method The photovoitalc mostule connection in the Fel! area uses OCTS0NV photovoltaic special ‘ables. The DC cable belweon the combiner box and tho contrakzed inverter use the ‘single-core 120mm aluminum core cable ts votage ove is 1.8(9KV. 38KY collector Ines sea combination of overtead wes and cables, of which the MV cable use the engle-core ‘70-300? sluinum core cable, ts votag levels 26(35)k ‘AC auxllary pover for other systems shall be supped from station sevice transformer sine LOCK) SOLAR ONES ANT oma) connected sirecty from 35¢V cotecton Ine or rom extemsl22kV tne of EVN, PV cables shal be aie in HOPE cont an OC cables shale la in doc burial made, ‘38k current colecton line cables shall be overhead type and the cables In transformer sation sal be laid trough cable lade. Fiber optic shal be installed overnead, Meanwhte, cables from S8KV RMU to 36KV colton line and communication cable shall be lis in HDPE underground cordit ard the cables in 20k substation shall be lid though cable trench or cable tubes in tet butal mode. 3.8 Lighting Systems The indoor and outdoor lighting system of220KV substation aque for substation, inverter station and other buldingsis expected to use indoor LED ohn coin, wall hanging or ater types. The projct shoul be complet Intemational standards. 3.4 Substation Communication system 13.441 SDH Synchronous Optical Transmitter The 220KV Substation project would had be equipped with 1 sel of SDH optical transmission Cequiprnent, 1+ configuration of main equipment such as optical interface boar, and 2 sats of scheduling data networ< equipment. The comesponding SDH optical interface board is ‘added tothe opposite power grid substation 3.42 Communication prtoco! for SCADAEMS “The SCADATEMS signals tough te gateway wil use the IECEO87O-5-106 ‘communication protool procedure 104), “The transmission channel for SCADNEMS signals of Loc Nin(t-3) solar powerplant uses the IECS0670-£-104 communication protocol procedure 104) fr transmission of 9 and 2. 3.43 Hotline IP Phone information channel ‘At Loc Ninh 1-28 solar powerplant, the IP phones connected by Ethernet channel rom the IP phone connected to Switch, Router, FE conection of SOH Optical Transmission Equipment to Ad and A2 3.5 CCTV systom Monitoring objects ofthe shotoveii ik COTY eystem shall inckide:Bnx transformer anc -rvetter- Photovoltaic fl video informaton is sent othe substation CTV system tough optical cables. “The 220KV substation CCTV system has reserved the communication socess interface forthe photovolta eld CTY system, Pe 4 Loci 1 SAR POWER ANT OHNE 4, CONTROL& PROTECTION SYSTEM 4.1 SCADASystem PV power generation's one performs realtime Information (neuding: boxy transformer, combiner box, inverter). Bay level can work independently in case of falure of elation level and network. The desig othe system folows SCADA and RELAY protocols with EVN, Monitoring system for? Fld shouldbe abo tobe meritored up t sting level (current, voltage, power and daily energy generator). The status and alarm of each signa shall be realme cisplay, System shall be clang atleast: Current deviation and alarm tunction (comparison between the string in each combiner box) Power output precestion according to EVN requement. ~ Geographical display to show PV aray area avaiable with fault deniiaton and tivated alarm information. Monitoring and contr system for PV and substation shal be separate system for both hardware and sowere, ‘The 220KV substation SCADA systom has reserved the communication acoessinertace forthe photovotae le SCADA system. 4.2 Meteorological stations The Loc Ninh 1 solar powerplant project is provided with 8 ses of metaoroogical stations for lonvronmental monitoring, and each metecrolescal station Is composed of wind speed sensor, wind erection sensor, 2 sels of pyranometr (horizontal and i at last, PY module temperature and ambient temperature measuring probe, control box and suppor, to measure parameters such as ambient temperature, wind speed, wind dreton andiradiation tnt, lis S485 communication interface can be comected to tho monitoring system of rK-connected supansion and cetrol device for eal-me recording of environmental data, 5. CIVIL WORK 5.1 General ‘According to TGVNZ7S7:1995, the Design wind speed Is considered to ba 24mis (average ‘ind speed at height of tOm within tOmin, ‘The lowest point of te PV modules about 0.8m above ground ‘tis preliminary ceterined thatthe photovoltaic suppor base adopts a PHC-300.A pipe plo, the photovoic cuppa adopts a stcel structure, and the main fame adopts 2968 LOCKS} SOLAR ROWER A ANT 20200) stool 65.2 Site Clearance & Preparation ‘The sie clearance and land leveling as wel as the ernoval and throw-away of roots wil be one by the Employer. Land leveling should moet he following roqurements -Backll ofthe site shoulé be wel graded sand, gravel or sol, the maximum $22 of backfl cannot be greater than 200 mm. Tha compaction coficiert shouldbe noes than 0.92, expansive soll nc and so with ‘roan matter content greater han 5% camo! be used a fling. “Tho slopo ofthe sito should not be greator than 234, “The Contractor is ony responsible for minor eveng 5.3 Structure 5.31 Fixed PV mounting structure and Foundation ‘The PY mounting stuctueare designed with consideration gwen fo dead load, ve load. The dead load includes weight of PY madule and dead weight of PV mounting structure: the Ive load includes wind load end rainwater load, with the design wind speed of 26 mls. PV mounting structure are of fixed type and made of C2358 stel, which mainly consist of main beam, purine, column, dlagonal, connecting bots and cther bots, Modules and purines, purines and main beams, nan beams and columns are botad. The columns are connected vit the foundation through foundation bots. The selection ofthe structure section shouldbe ‘determined a the construction deal stage according to the technology andthe construction schadhle According to prlimnay geological report and hydrological data ia the FS, the foundation of PV mounting structure wil use PH-300-A pipe pl, the dlameter of pos SOD mm. AL this stage, the lngth of PHC-200-A lef 3.0m with 2.0m underground. Final, the clamter an length ofthe PHC pipe plo should be detained according to ‘he detail geotechnical rept and the stat load test ofthe pile 6.2.2 Foundation of transformer and invertor ‘Cunezete box fou is evelyn fre Furnan of vansore a net 5.3.3 Fencing of PV Site Area Only one fence i st forth works inthe form oft Lavre-mesh simple fence, with height of 2.5 morsel wee moh, 5.3.4 Collector Line Works 35KY collector ines adopt wo laying methods: overhead and cable rect burial, Reinorcad concrete foundation for tre tower of overhead bre, The slope of cable trench shal be ‘excavated by 1:0; after excavation, tench bottom shall be cleaned and tampod, and # 4? LOCIUNH # SOLAR POWER PANT (amu) 100mm fe sand shal te paved above and below the postion for cable laying, and seqrogaton (rks or tin concrete plates orang tapes or her ype segregation) sha be setabove cates forprotecton.and meet he requrements of Vietnam EVN's standard 5.4 Architecture One Warehouse wit 8a of 1000 ser, “Main guard nouse 1 nos -Simall guard house 4 ros. -Natch tower 6m height 1908 Project banner 1 nos. 5.5 Road A he PV fled, the with ofthe main oad of he infernal road ofthe Loe Ninh 1 solar power plat ie 6.0 m, and the wlth of the branch rosd le 4.0 m, graded macadam pavement ie Adopted. The intemal readis designed asa combination of permanent and temporary works tomes the requirements & construction, equipment transportation ard maintenance ‘The access read conrectng withthe loca oad Is about 1.0 km i otal length and &.0 m In width, with graded grave pavement. ‘Te table must be cleared within the scope of foad land. The requrements are a= fotos (The rubbish, xgaric residues and surface humus sol, tur, erop roots and topsoll thin the cad land area sal be removed, and tho tops plantod shal be stacked ina esignated spol yard. After the site is cleaned up, it shouldbe relled before fling to rake the compactnes meet the specified requirement {2)To fil the embankment, the humus sail thin the range ofthe foundation ofthe roadbed shouldbe compltely excavated andthe pte hauls be filed and compacta; In addtion, the pits win the range ofthe roadbed shouldbe fled and compacted, 5.6 Wator Supply and Crainage and Sowage Treatment Systom 1) Water Source ‘The water used in te booster station comes from the underground, The 220kV substation project cil a deep wel inthe 20KV substation, 2) Wator Supply Systm ‘The domestic water supply system has used complete sets of equipment, and the {acities include deep wel, water tanks, water supply pumps. 3) Photovoltaic module cleaning system ‘There is no clearing equiment in the PV power station. The frefahting system piping atvork can be usad se PV madul lasing zs Loc np 1 SOLA owe ANT pom) 4) Drainage Systom in Substation aes For the drainage system inthe operation management area, 2 indepandont facies are proved forthe air drainage and domestic sewage discharge, 2) Rainwater Drainage Rainwater drainage inudes the cainage of oo rarwatr rainwater inthe sto area and In cable trenches. Rainwater on the bulng root Is cllectod by rainwater hopper, then drcted trough rainwater ser pipe, fraly dscharged trough the ground rainwater eich. Through the raiewater inlet andthe rainwater pipe bred outdoor, ramatr Inthe ste area is cotected and discharged outs, “Through pipsne, rarwater in the cable tench is drained to the rainwater drainage ‘system inside the substation, b) Domestic sonage sischargo “Tho domestic sewage systom consists of sewage pipes, sewage Inspection wes, and septic tanks (efectve volume is about 2m"). The domestic sewage at each water point is colbctd int the sepictrk through the sewage pipeline, and after the saptc tanks seed, iis regualy cleared by spacial vehicles '5) Drainage system cf photovottac plant “The drainage dich of photovoliae plant areas mally arranged along the road, fofowing ‘allonal method and local sandarés with rtum paris of 20 years Drainage systom shallbe concrete orstne lng. 6. FIRE ALARM AND FIREFIGHTING SYSTEM. In the project, fre hydrants wil be sot up next to the main roads in the photovoltaic power Plant area. At the same tie, fe-fghting systems ere equipped with fe-ghting pipes and fre pumps, each set of photo-wllaic power unit transformer and inverter reom is equipped With 2 sot of COs fre extinguishers firefighting deve, The fkefgting piping network can be used as PV module cleaning, 7. ANNEXES ANNEX-01 CODES AND STANDARDS ‘The project wil conform tothe applcable requiem ofthe latest exon of the fotbwing standards orto recognized equat aT LOCOS SOLAR POWER A ANT ota) feces tli silicon terrestrial photovoltaic (PV) modules £0 60068 ireuetaltesing - Par 1: General and guidance = a Tao Coe BRO ROTO an at of power convorar for Use h phatovotale power aye FEC621002 | part2: Particular requirements for inverters otoraai (PV) systoms = Requirements fo tstng, fc enas-+ camentstion and maintenance — Pat: Grid comected ystems — Documentation, commissioning tests and inspection kaw 2ar2o0arait [Becrity ofthe National Assembly (14/2/2004) aw 2arzo eran a PUTS ane aaEMTETNG a Humbe OARS OTHE fect aw of the National Assembly (20/112012) | rToN-18-21-2006| [ectrc Equipment Norm freculatons ans hachncal standards Thetntegated contol system, protection sytem -onfigration, protecting technical spectficaton for ines and [rok vansformer station of EVN forms and decres| ent processes, which relate to ovthoad power Vanamissin| jreiar ang te regulation on GSibutedeletetyaystom Tesued ISITE-BCT _ by the Minty of industry and Trade (MOIT) (1111/2015) ruler arng projec development and model power purchase fivzotzrrr-8cT _byreaments applied to solar power projects (12/08/2017) jeceane Tet procedure of sanding proventon FEEE 1647 Fornecconnecton test of dibuted Enagy soca JEEECOZ01S [aot Satay HAC Sutton Grande vw carer ba opal oi aoc, esa RT tone esd he miso ast and Tada arorreact fistos rear Peon is aoa oT aol aa SSSR kozovwrrccr_[eosta0. a euterents and phe coo equtenerts for HV eupent tia Jcen0se fans votes Jecetnee Senay atone wastomers FECECOSO __[Sees)rtenaonal eocrlecical vcabiay (Sees Insulation coordination zx Loci SoxAPoWeR ANT omit) feceoo7e Seis) Power transformers | Series) Palwnylciorda muted cabs oated volagos up fc e027 andincluding 450/750 lec coos ndictrs of neue cables lec ease )ietesna Equipment and'SCADA jecenass Sores) Electical relays jecoazer Sees) Elects cables —Galeulaton ofthe curent rath lec eases Low-votage ebcicalinstatations EO 60528 ted nicke-cacmium prismatic rechargeable shoe coll Jeabal measuring Waneducor Tr convening a Slocieal weal ants to analogue or digtal slgnsle mon teat matode formulating and shosihing ator of fea ocr cables and optical cables fEC 60808 |Bhor-circuit currents in three-phase a.c, systems EC 60047 ‘Serios) Low votage switchgear and contol gear | ‘Saree Shor creut coments in de aulary metalation comes PSs wate [EC61096-1 Poworinstatatons excoeding 1 KV ac. Pat 1: Commen los jEC 62040 {Series} Uninterruptible Powe System Tgn-wlage sitchgear and contol gear = Part 200; AC [EC62271.200 fetatenclosed switchgear and contro gar fr rated vatoges ove 1 kV ane p to ai including 62 KV |ece2s05 [Series Protection against lining [Fre fatting Trcvw zoza.1996 Pe Brveniion and proctor Balk and srucures — sgn requirements righting system ~Ganeral requirement for Gaughs, fewer onan ten [FOvN 5738:2001 Fire warning system — Design requirements [FEW 7435-7 Fre pretection potable and wheeled fre extinguishers [Pv inaataton Fodralntalatons of buldings Part 7-772. Requroments for JEc90364-7 712 kpecsa installation or ocatons- Solar photovaale (PV) power ols fec.e2548 Photovotac (PV) arays— Desion requirements Cui 1 SOLAR POWER AN zou EceaTIe srmcaia corosion tasting of photovolae (PV) modules [Ponnecors To BG applica i PS Safety requirements and Ec 62a62:2014 11506212008 [onnectos for PV aysiem fresaoes [Balance eystom of PV je 6an26 ond lors of ulated cables esis on elie and apical Tre cables undor We condons = Jec603s2-1-2 Part 1.2: Testor vaca fame propagation for a single insuate| ro cable «Procedure for 1 RW pre-mivad ame Frvs0s1e eo cates tr patra syst Jecewor bata cxrosintesng of phatovotao PW romies JEcc1720 __ Preowtae PV mds qalfeaton is (EVN 27S7-1005 _[ondsand lets Deskn standard oa Wasa Biking Cae Nr Pyar & Cave Daa for .200ex0 __feonsucion aidnce for determination of ae Copan of We wind Jose unser Tovi 2737:1008 gh of stucures for eainquake relsancos: Pant General ON 8-201 amperage Ign of sutures for earthquake reatancos: Pa [mst 2201 ne ing sas ond prc secs TOWN 55752072 fel eructires —Osegn standard “uw oananoxa” PUP Sander Test eto n situ Tor pits under at pressive lad Asce7-10 mn design loads for buldings and other structures 5 EN 1900, 2002 ass of Stuctural Design |Eurocede 1 Aone on sirucures — Part 1 General actions lbenstes, ser-weigt moosed ads tr bukangs "| IEwoccde 1- Actions on sruciures — Part 3: General actions (OxD 2291909, 5 ads [Eurocedo 1: Aatons on srucures — Part 1 General aeons fi991-7.42005 [Wired actions EN ‘urocede 3 — Desig of steel ruclures — Part -71 General 995-1-1:2008 ‘and ules for busing fsen urocede f Acions on erucures — Par T-7 General ules ae [962-1-1:2003 fue for bulsings LOC MI SOLAR POWER ANT 200 sen fses-t22008 Treen 3 — Design of Seal srucuTes — Pan TE Goward Jes — Structural redeson 51070085: 2007Eoeado 3 Des of stoeetuctures Part & Ping BS EN 14199:2005 ution of special geotechnical workemicopies EEE St 691-2001 EEE Gunde er Tansmison Structure Foundation Dewan and resing Loctun + soxae pon Ns (ci) ANNEX.02 PERFORMANCE TESTS 1. Purpos 1) This Schedule sets forth the basis for the dotormination of the Performance Acceptance Tet (PAT) incidngscoeptance eftera, 2) The objective of et perfomance tess fs 10 prove thal the Project ie capable of ‘generating enorny as expected 2. Contractor's Responsbiliies 1) Perform al checks, calraton, measurements for all measuring equipment involved thetest 2) Clean and maintain all pyranometers as required by the local environmental condtons; daly leaning fs required during PAT. 3) Acquire data, perfom caleiatlons and present resus 4) Maintain an accurate record ofa plant vents, fa ‘er montoring system inclting he start ad endl of each event 5) Provide ful access to the Project's sto, al maintenance records, actuty logs, colected data and real-time data from SCADA tothe Over: £8) Notify the Owner onthe Intended stat date ofeach test period at last 5 busine ‘days porto commance the each test prio, 2. Detaled Technical Report 1) Upon completion of each test, the Contractor wil provide to the Owner a detailed {echnical report, the "Perfsmance Test Repot’,indcating thatthe Project, as designed, constructed and commissioned, has generated the requted energy in order to moet the performance citer descized below 2) The Perormance Test Report wil provide evidence that al tests have boon satsfaconly completes ard wil present the test preparation, dala source, calculation and results ofthe test Calcutn worksheet in Excel format and allnecessary PVayst fas wil be prowded together wih Perlman Test Report fr review, 3) The report wil also provide detsis of any noted defclency and corecive action cared ou ding the tox periods. 4) The Owner wil view the Performance Test Report and provise writen comments to the Contractor, it any, within 10 business days, which the Contractor will asonaby aderess 4. Performance Tests 1) PAT Period “The PAT Perod wil commence ona dat ater al the following acties have Bean fly complete: ‘Al commissioning ant slar-up actives have been successfuly completed and all 1 dowmtime fram equipment LOCH 1 SOLAR PONER ANT oma) deficiencies potently affecting energy generaton performance have been fly resolved; ‘The Projects synctrerized to the Local Ut ie: [Al modules forthe project have been installed onthe stuctore a exposed to sunlight {or atleast 15 days; ‘A visual inspection ofthe modules has been conducted to make sure that they ae in a reasonable sate of teaniness and in particular fee from constructon residues (2, mud, cust); Solar metering equipment has boon completely installed and calbvated: ‘Al pyranometers we been calibrated and cleaned as par manufacturers recommendatons; All temperature senso’s have been Instaled and calibrated; and ‘The SCADA system fly operational and Owner has access to all operational data, 2) The PAT Period wi consist of at least 7 days nthe aggregate where al th follwing conditions are met for ach day ‘Te global horizontal radiance is an average of 400 Wim? fr each how for at least hours pe day, “eal dally radiation onthe horizontal planes atleast 2k, ‘Any equipment outage or curtaiment that resis in a lass of energy exceed tothe gr ‘or oss the necessary performance data during dayight hous shorter than 15 minutes per day in tho aggregate ‘The PAT Period wil te extended by one day for any day on wich al the conditions above ae not met 3) Method of Measurement Data collection by the SCADA system will commence at 12:00AM and end at 11'53PM ‘on each test day, averaged on a 5 minute Interval ‘The average value of each meteorological and electrical measurement relevent 1 the perfomance test wil be recorded as 8 time stamped fle andthe historical series ofa data points wil be avatable as a single, comma-separated values fle (CSV), the "Measurement Data’. Relevant data shal include Plane of Array (POA) and Global Horizontal (GH!) radiance, ambient teperture, and onary fecorded a the revere meter, No ata points receded during the Test Period and compiled in the ofignal Measurement Data fe wal be remaved o filed with other data at anytime, No uncertainties or conection factors wil be apliod tothe Measurement Data 4) Data Analysis ‘All measured data mist be from the Measurement Data fle, adequate quality checks shall be cad out to ersure that measurement data satisies the Test Period contions radiance is measure by the horizontal (SHI pyranometers fr tracker systems, and by vyt Loci» soxar Pow LAN oct) lao of aay (POA) pyranameters for eed tt systems ‘Where moce than one meteorological stations instated a a Project the aritametic mean forthe recorded parameter wil bo used Fer PAT, the olling datapoints aa be excluded from the Data Analysis (but not rm the Measurement Data fe _—The global havizontl radiance is below 100 Win? _—The S-minute average iralance ders by mare than 10% fom the average radiance forthe hour centered abou: that 5-minute petiod, 5) Cateulation ‘The Performance Ratio calculation formula is Productioneneray Expected energy Performance Ratio (PR) Tai SEE cent Oreo) ‘Aer the Data Anaya, the recorded data for actual meteorological conditions during the “Test Parod wl be inputints the Tost PVsyst Model ‘The expected eneray generation forthe Test Period (expressed in Kh) as calculated by ‘ho Tost PYeyst Modo, willbe called E>. “The actual energy production forth project over the samo paiod (expratsod in KWh) vill be read from the projects revenue meter, and wil be called Eueren. Aur enegy consumption forthe substzion isnot to bo included win Eyer=. Al other ausllary energy consumed inthe project shal be included (inverters, trackers, vansformers et) 6) PAT Remedy and Retest ‘The Contactor has the follwing options the project does not pass PAT, ori the Contractor elects o terminate the PAT before the completion ofthe Test Pri “The Contractor may al the Contractor's sole discretion and cost, eae! fo remedy any home It believes caused the Project fo fall the PAT and subsequently repeat tho PAT in econ wih his Schedule. For ean, such test wil run fr the same duration and wil be subject tothe same consiions as sel forth in this Schedule, It the Contractor eleds not to remedy, ori the Project does not pass the PAT for Contractor's reasons after tree (8) altompts to remedy and retest, the PAT wil be considered felled and the perfomance liquidated damages shall apply. However, the Project does not pass tho PAT forthe Employer or EVNS reasons, the Contractor shall no longer be lable for Loc hui 7 SOLAR POWER RANT 2040) the performance guarante thereat The Contracor wil have maximum 20 days for remedy and retest stating from end of PAT Peto Loc Wnt # SOLAR FONE PLANT aH) ‘ANNEX-03 INSPECTIONGS, TESTING AND COMMISSIONING. 1. Functional Testing 44, Seriatizing Provide Project drawings that include PV sting wing, combiner box elctreal principe te, electrical system single tne et; ‘Record al combines boxes serial numbers and indeate zone locations within Project Record al Inverters sor umbers and indleate zone locations within Projet Record al medium vllage transformer serial numbers, and inverter serial number(s) to.which each is comected Record a Neteontogical Weather Stations serial numbers and Indicate zone locations within Projet 1.2. PV Stings Open Citclt Voltage Test (Voc) ‘Measurement of Vac of each and every string is required to ensure that al stings have the same nunber of Nodules connected anc correct poany. This is intended to ‘check the correct instalation ac wel a the balanced performance of tho arrays, This “Toss notintanded as a measure of Module or aay perfomance, “Test wil be in accordance with Standard: IEC 62446 Grd Connected Photovoale ‘Systems. Minimum Requirements for Systom Oocumentation, Commisioning Tocts and Inspection. + Open the Combiner box DG disconnect and remove all string fuses in the ‘combiner box ‘+ Measure the open circu voitge ofeach sting onthe we side of he fuso holier. 4+ Aflr massuremant and recording of each sting Voe, replace the fuses back to the 1..PV String Cables Perform sting cable related electra! tests including ensuring proper connactity of strings on each combiner box according te sting tables, 44, AC MY Cables -Elocrcal Tests ‘Conduct insulation resistance test performed individual on each conducts, with al ‘other conductors and shields grounded, Ensure all AC MV cable tested for isolation OCI 5 SOLAR ROWER ANT oN) resistance before commissioning the inverter and utity Interconnection, Where _appleabe performance a shill-conthuiy test on each pawor cable, 1.5. Metering Systom — Electrical Tests [Ensue correct messurement and indation by applying voltage or curent to each ‘analog input; corect operation and setting of each auxary inpuoutput festure (vechanical relay, gta and analog); and conf measurements ad indications aro consistent with loads present afer intl system energization. 416. Grounding & Lightning Protection Very thatthe groanding end ghining protection system is compliant vith design ravings. The grounding system shall comply with eloctical system code 2s Intorprotod by tho EVN requirements 2, Inspection 24. General Visual and Mechanical inspections Ingpect the visual and mechanical sttbutes of each ofthe folowing components ‘nctuing the nameplate deta consistency with drawings and speciation, physical ‘and mectanical condition, the unit clearness, certificate, the anchorage, elgnment, rcunng and cla ances per manufectixing an instalation eqtsemerts 2.2. PV Module Visual Inspections PV panels to be ssualy inspected and recorded upon receipt, prior to and post instalation onthe aay racking, Pre and post installa inspection Procedure should document the flowing ~ Contractor shal viualy inspect the mesile packaging upon receipt. Any damage shall be documented by the Contractor, Contractor shall nat be required to unpack andlor incviually hspect each module. At such time if any damage is discovered Contractor shall immeditaly nati Clot. Cnt and Contactor wl work together to ‘etemin the source of the damage and responsi. ~Visualy inspect each module to determine th presence er absence of anomalies or defects. Optical magnifcaton isnot required. Visual inspection 1 not intended to replace the Factory Acceptance Quality Measures, but is intended to improve the ‘overall quality ofthe netalation. Such anomalies or defects should nctuc, but are not ites to Loc nni 1 SOLA ROMER BAN (024 ++ Shipping Damage (document damaged packaging prior o unpacking and damage to modules ater unpacking) + Insalaon Darger 1 Broken, cracked, etched, scratched, wrinkled, oF tm extemal surfaces, ++ Broken, cracked or fully electrical iterconnections. +A photovtaic 28 touching another cal r the module frame. ++ Missing, peeling, or éamaged metal layers on cell surfaces, and any ational snomalies or defects specieg by the user — Record the results ofthe visual nspecton so that any changes that occur dung subsequent testing can be ented. 2.3. Marking and Labeting ‘The marking onal of the wees and cables used in the solar farm shall be in compliance with ‘he local letra stardard, Al electrical equipment used in he Projet shal be labeled th safoy signage, 24. Racking Array and Module Mounting Inspections {Visual inspection of Mechanical insta ion ~ Inspect PY rack assomblies and wire tray assembles to ensure there ae no loose serens oF attach, Inspect PV meduleintatation to ensure modules are installed wth unform spac. ~ Inspect all PV modules and clamps ane ensure they are fastened to racking system 8 per module man facturer and racking manufactrer instalation specieations Ensure no loose sews and stachments, spacing is per the module manufactuos (uideines and unfarm spacing and al fastened components. (iVisual inspecticn of Electical instalation ~ Visually inspect any plug and recoptacle connectors between the PV modules to censure they are fly engaged an fee fom unde stress; = Visually inspect the aay fo ensure module and rack to rack grounding has been inetaled ~ Check to see that al wing is neat and wall supported Loc + SOLAR ROWER ANT nat) 2.5. Combiner Box ~ Electrical Inspections ‘The constuctor n addtion to General Visual and Mechanical Inepection Requirements, inspect cabnety (visual, mechanical ae electrical), tightness of pole rmounteg hardware, al ground bonds, electrical comedtions, contnuty from box conectors to posive fuse blocks and negative terminals; 26, Box ranstormer andinverter ~ Visual, Mechanical and Electical Inspections ~The constructor ensures ll transformers (ew-vatage step-up to intermediate, secondary step-up to gid and grounding) have been tested atthe factory and ‘ocumentes prose arvng al projet ste per appicabiestandars. ~The constructor inspect the folowing adtional tems operation of alarm, carta, and trip excite fom tempertue indeatrs,coxect liquid level i tank (ol level) and temperature, de-evergized tap-changer poston & lef as spectied, no signs of ‘overheating with primary and secondary connections, bushings and nsultors are ‘Goan, check ol love and temperature, sot transformer taps to rated voltage, 3s _snscifed, cil lake and excessive rusting, coxrect ype. In sition to General Visual and Mechanical Inspecton requirements, inspect the folowing adational tems: al ground cables cornectod and torqued, all empty holos have been plugged, and ensure weather and rodent prof 27. Cleult Breakers ~ Visual and Mechanical Inspections In action to General Vaual and Mechanical Inspection requirements, inspect the folowing addtional tems: ckeut breaker size & (ype comesponds to. drawings, ‘coordinator study, and aderess for microprocessr-communicaton packages, correct 28, Relays ~ Visual and Mechanical Inspections. In adtion to Genel Visual ané Mechanical Inspecton requirements, inspect the folowing sdtional tems; modeVstyelseal number, fmarelsotwere revision, and ‘ated control volag recordad, very oporation of lightening diodes, displays, & targets, passwords for all access levels recorded, font panel clean and foreign ‘material removed tem case, an relay sen scoorcance wih coordination study 2. Lightning Arrests -Visual and Mechanical Inspections In addon to General Visual and Mechanical Inspection requirements, inspect the folowing edaional ts: ground lead on each device i indvidualy attached to a ‘round bus or grourd electrode and elcticaly connected and recorded, applicable, x & LOC NHS SOLAR POWER A ANT Zoo) 2.40, UPS~Visual ane Mechanica Inspections | dation to Genera! Visual and Mechanica Inspecton requrements, inspect the coating fans, ‘241, Cables - Visual end Mechanical Inapections In addition to General Visual and Mechanical Inspecton requemeonts, Inspect the follwing addtional tems: cable data comparison wit dravings and specications, compression-appie connectors for earest cable match & bndentation, coroct Identification & arrangements and cable jacket insulation and conto, 3. Commissioning 34. SCADA System ‘AISCADA systems used in the project shal be tested and accepted as fotos: ~ Contin compliance vith the Litys SCADA recuirements ~ Very communication with each Inverter ~ Conti measurement eadngs from inverters per specication ~ Conf status reacings fom auliary equipments per spectcation ~ Communication Ramos log-in, tp access) tested ~ Connection tothe Usity, if applicable, needs to be tested ~ Alvatables measured by the SCADA system have to be validated, not ony readings ‘rom the inverters eadings from the recomibiner boxes and from the weather stato, forexampi, sive have tobe checked ~ Acabinels are dan of dust and debi, ~ Alvluesesplaye on screens ae valid and scale correct. ‘3.2. Communication System Cconfm compliance wi the U's Canto an Telecemmunication equrements ty testing requirements are successtuly completed ~ Ethernet equipmentinstales ~ Network programming competed ~ PRC Equipment Verification Loca 1 SOLAR ROMER AV (200) ~ Confirm reviewed stings applied to relay Functional tats ofthe SCADA, commands from both the Human Machine Interfaces and trough the web intrace £33. Protection and Contre! Equipment ‘The constructor Al Protection & Contol EqupmentiSystoms shal be tested and ‘documented in the Contractor's Final Functonal Test Report and shall be in accordance to appabe standards, ~ Perform insuationsesitance tests fom each ckeut to the grounded frame in accordance with Manufacturers published data ~ Apply voltage or curent toa analog inputs and very correct registration of he relay rete unetion. Chock functional operation of each element used inthe protacion scheme, ~ Conf the Functinal Operation a flows: 1+ Under Votage Relay 4+ Instantaneous Overeurent Relay Time Overcuret + Overvetage Reay + Directional Ovecurent Relay 4 Frequency Relay + Contr! Verifcaton 34, Power Factor Contro System ‘A Power Qualty miler shal be Instaled wih adequate settings. Volage or current ‘hall be applied as appropiate to each analog input. Aor inital system energization, ‘cont that the monauroments and Inoatlons are consistent wh loads presen Ensure thatthe PLE and network equpmest are installed and programmed, Verify PLC and inverter communication, Very control, setting and timings according to loading (feity producer). Ensure that the Power Factor Cent! system meets the EWNs quirements '35.Contro Verfiea erty the operation of al active digit! Inputs, oxtput contact, infemel ogi funtion Used in the poecion scheme, and te reseting of a minimax recorders, L 4 4 oon 1 so.Ane POWER ANT oni) communication sts, faut counters; events sequence recorder, and event recorders, 3.6, Testing of Interconnection «The systems Grd interconnection and protections systems shal be tested and accepted in accordance with the EVN's requirements, ancew Pa wscomien | et ‘ahvxed Fa TORTS HOT asanapecenieo| any ‘oost'nvseseaecn| MONE) ayy ore 10091 +020} gow asl yay aupreishioouoy! “dNngrre mee snptiston asso anoe “diygrie sno sed ences 1woudnbe peu amionoia) LP neu -ejoweied oaveasoneg “80 Pa 181 uoWdinbe BunooujBue Arewd ouN0e13 I e1eeL 9 yo Ssancud sup BuUNp WoREZHELY BOIS 810A Sk RUNS (S1vRISLVW GNY LN3WdIND’) S3LLUNWND JO 7118 ¥O-XENNY GEE LIVEN ES BAGS THIN GOT ce | spls0e usps] yas p909| ed wubadamsaneW | P0560) nisoezowseien ‘osseous eoiono Soa 99 sBHIN Une | FT rsa » | soysovossanay | ©Eb sauzrarsuonacenen | gg we | wn TUN] emma} ze ‘ero pmuisoor3 | ey | wy suuperezi| —aneonal ret >.e1e htt opin, ponsiogeoeren Tonorerse piso eonioa mea] Ey i nee srt recs ave ot | | ana se natty) "Spon | v1 sovendu ye nica | Jere ar Pi mung seed papeuo marae) vy smoueredeomoea | RO | wn | wontons cow | ay (TART TENET APTOS TARGET ped oxo au, sunuuunnysopneueg, meen iesrovon Ud aoatoa uenuysoer eoegustll] vex saa iwskowen ecu dog iy wenn ser ‘buoy Busecay ‘nvSEOWebeH0N, ou vosswsuesl | 964 peaUano 58 "yes 950 buy ‘uno Bupioooy tunuunry sopr@ueg, INISEOW ENON, we ox j0 aby ‘ua Bupioooy uunuunry sejnpue9, RISEOW BEAN, go oun 0 3644 ‘or Bupiocoy AISEOW eEEHOA a poigolez suport} yoo1e 2990800] 2, 2.05+.0'e0ue! snjeoduo), YMSIOAASAHMN | ASE J0, 960 yse/sz0¥. 9810" eyeuily sejowresed e2uewopog wn wondioseq owen “on we OE INE MOT IOS TFT ‘aide eRUENED ‘vojoeixd BUN sues reauien | Ju yop fare ey PSA crore | ee ce 4 | sus yor feaeseH pemUeVED | a9 SRN | ey r $305 FS eH PORE SaaS on | 1 [amarosienmwrremeeo| aeoehomen| FFE Supuncig | ¥b oge sore owns sojoursed ooue us ” 7 wwondus a oN S nat joued ‘wn dosed wen | en ‘RDEV OT TOS T NOT FST_DoyeE Tanod Sera SrniAe SS Ime ‘eid GOV, £2 (WO8-GAT 611200 ‘openve “ZHOrE=ndO “slno-penb) ogi © iso} | HOW, woREN same cevoncto sy} uowdnbe Buyeauibue Arepucsss jea1noeIa z-¥ O1GEL EE TE SOT TOS TN TOT x LOCKE) SOLAR POWER RANT oun) ANNEX-05 BILL OF GUANTITIES (CIVIL WORKS) ee CEE Se em a — «| fon = =. 7 [Berens Soleiaaeie a 13 everer a ae — a a a a eT aaa ——— =a on olan a =f ——— 142 | cable tutes) a =e so “ee oa alarms Sea vce appa, | pp 17 Sour acto of PV Fat ea Simpeenca PV ft wo in| 80 [mnie oce 1 | Fudaton tahnrgrod Earth vers wearin m | am oath ers beektlg m | a80 Lear corrects m | wo Fourdsin cont G0 m | ao Gitar [as co [Risepmaeaanst com oa 110 | bawage cro ae won| 0a 1. [ sos oat tte im [10 1:2 [onto acne in| ae 119 [Bang Pv ste 187 | Warehouse [too | Sefeer Fae ‘182 [man quattone es [ tote tonr fame 1138 | nat guru mo [4 [Setar 1184 | Wath ovr vee [tame OCI 1 SOLAR POnER FANT 2a) ANNEX-06 PVSYST SIMULATION CALCULATION 4x PVSYST v6.75) 910420] Pace 15 Grid-Connected System: Simulation parameters. Project: LoeNinht Geographical site Lectin ccouey Vietnam Suan atte 1160" Longiude 10848" & Tire tne ns LegalTine Tine zone UTe7 Alte 8D ‘Abed 020 Mateo dat: Lectin Hetaonrm 72 (1001-2010), Sate100%-Syrhate ‘Simulation variant: New simulation varlant ‘Sinton dato 30420 19410 Simulation forthe 40th year of operation Simulation parameters Syste type United sheds Collctor Pane Orientation me aims Sheds contguration Ne. otsbeds 5 nines sheds ‘shade spacing 580" Colledor wists 00m Inactive band Tep 0027 Bator 02m ‘Shing tnt sre LUmtprotla ange 26°” Groundoov.Reto{@CR) 87.8% Models used ‘Transposon Paez Dine Pete, Metener Horizon Free Horton Near Shadings tual snscngs of shads BV Bray Characteristics PV module Siero Medal LRA-T2NPH AON now ‘Cictom paramos dofiniton Manuiocrr Long Soar ‘wanserot PV maces Ineetos So modes Impure 15180 stings Tolsmonber of PV modes Np mosules 454500" _UnitNem Power 40> ‘ray bal power Nomial(STC) 198880 KiYp ALoperstng cond, 180484 Kp (40°C) ‘ay operating enacts (0° C) ‘Umpp 2 Timp 1280078 ‘otto edule on SH et Inverter Model EP126HAUDAO2 "Cision parameters coiton anuactrer Shorg contact ‘opera Volage BIOI800V UntNom, Power 3125 kc ax power 928°C) 3894 SE love pa eet verare 60 une Tot Poe 187500 kWlac ‘Promento 407 PV Ara loss factors ‘ray Soling Losses oss Fracton 10% ‘Thema Loss factor Uc (cons) 280 Win K ‘vind) 0.0 Wnt Kms Weg Oi Loss Global erayres, 0073 mOAm Los Fracton 1.0% at STC Sete Dito toes Vet Oop O7 oes Frcton 0.1% STC LUD ntcod Depradaton le Fraeton 10% Mose ally toes ls Facton 0.7% Mose Wismateh Losses oe Fracfon 0S at MPP Suing Meta oss le Fracion 0.10% ode erage dagen ar20 10 Lows foctor 04 Sioa Mmalc du To degadaon pS depunson 04 Klyear Vine RMS deport 0.4 Soar Bx pvsyst vers aioaz0 | Page28 Grid-Connected System: Simulation parameters | Ineldonce oct (AMY: User dened AW rele ‘system oss factors [AC los, anata econ ‘ora votage 20H ees: 240000 mn? 200m Lose Frasfon 0.1 Yat STC ster uanfomer Iron a (24H cannaaon) 167020 W lec Frcaon 0.1% at STC Recbvfndscie losses 203mOhm Loss Facton 10% at STC naval of 5ystm 36 ays, 3 pre Tine rcion 1.0% eet needs Unis tod ai) ‘uae oss cmlat ane) 30000". tom Power tesh, 0.0 KA PVSYST V85| aioaz0 | Page 3 Grid: Connected Syetom: Main recults Project: LocNinht ‘Simulation variant: Now simulation variant ‘Simulation for theft year of operation Main eyetom paramatr= ‘Syst pa Untied sheds PV Fad Oretaton ‘Shots depstion tt 1 xiputh Pv meses Model LR&TOHPH-ANON-now "Prom 440\%p Pv rey Ne ofmadtiea 454500 Pom tea! 199900 kw Ione ‘Model EP125HKUD02 "Prom 125k ae Irv pack No ofunts. 60.0 Prom toa! 187500 KW 9c Users eed rst ad (oi) ain simulation resus | Systm Producten Produced Energy S105K3 MWhiyear Specie prod. 1553 KNAW New smatin vation PvsyST vers iso420] Page as Grid-Connected Syetem: Loss diagram Project Lochinht ‘Simulation variant: New simulation variant ‘Sinulatin forthe 10th year of operation Main system parameters System type United sheds PV Fd Oretaon ‘Stats eosion tt 1 inuth Pv modes Model UR472HPH-AtON-neN "Prom 440 Wp Pv ray Ne.otmedies 454500, Pom ot! 129960 Kp vere ‘Model EPI25HAUDO2 |” Prom S125KW ac rte pock No.of units 600 Pom 3! 187500 KW 9c Users ods one dh) ose gr ore te whole ee ‘ta neem ca plane wr Sarg arn ee at caren gota ‘anger oer ‘ay oni ney (ST fe) ‘eae epadeon oy) Pe dito tn tyne Logins aettin SIT ST cite ey Sa ‘evar Lee ce epeton te) ‘Sat Lone vr ina age ‘Sere volgen ‘stan, oe) ‘Stara nay ected i PVSYST v6.75 taoaz0| Pages Grid-Connected System: P50 - P80 evaluation Projeot : LooNinht ‘Simulation variant: New simulation variant ‘Simulation forthe 10th your of operation Main system paramotrs ‘ipo Unlimited sheds PY Fit Omntaton ‘Shade pection at 1 imu Pv mado Model LR&-T2HPHA¢ON-naw Poo 440 Np Pv roy Neofmiies. 454500 Pom tal 198060 kw lover Model EP21254AUD02 "Prom Saeki ae Inver pack N,ofunts 600 Prom ol 187500 KW se Users eds Untinios ea () Evaluation of the Production probaly forcast ‘The probably dstbuton fe system produconfrcast or dfoontyearsis mainly dependoré on th moto deta sod forthe sult, and depands onthe olor choices Moto dal source etoorerm 72 (100-2010), Set=100% Melo a ed Monty eerogen Stic Mulla erage ‘Spectid Devaton ‘tmsto change 00 Yeartojearvatily Varies 25% ‘Tho probably dtibton varices depending on smo oytom paramos uncealnes Species Deaton PV male redeinghparamelere 1.0% Inver ofieny ncaraniy 05 % Soling and misnacn ureeransoe 10% Dogadaion montanty 10% (loa! varity tao + sytem) Variance 3.1% (qusdate sun) pool roductnprobsbilly Variaiey 987240 Ps Hoe MWh oo 2anzeo twWh Pos Zaeei6 mn Probability detribution

You might also like