Transformer Details
Dimensions & Weight Details Height 4.87 Mtr
Gross weight
Spirit Level
D shackle
wire rope sling
Hydraulic jack
Hydra
Wooden Sleepers
Chain block
Unloading and shifting of Transformer will be done by certified machinery & skilled workers.
Unloading the transformer to the designated location with the help of certified heavy duty lifting
Hydraulic jack & wooden sleepers &U channel rail. first uplift to transformer on the trailer with the help
of heavy duty hydraulic jack and set the transformer on the U channel rail & wooden sleepers then Push
& pull the transformer with the skilled worker with help of jack or chain block and set on position a short
distance from trailer on the sleeper then very carefully unload on the wooden sleeper & take down
slowly & safely 10to20mm down on every step the sleeper till the position the transformer wheels
accurately on the U channel rails, release the transformer step by step slowly & carefully till the wheels
settle down properly on the U channel.
Push & pull the transformer with the skilled worker & help of winch machine or chain block or other
arrangement to its original installation location and lock the transformer wheels to ensure the
transformer should not move from its permanent place ensuring the transformer and safely lock the
with padlock in order to keep the equipment safe.