REKAP PERHITUNGAN VOLUME

NOMOR DEMENSI
MATA URAIAN POSISI SAT. VOLUME KONTRAK PANJANG LEBAR LUASAN BJ VOLUME KETERANGAN
TEBAL
PEMB M1 M M2 T/M3 (M3)

DIVISI 5. PERKERASAN BERBUTIR DAN PERKERASAN BETON SEMEN


5.1.(2) Lapis Pondasi Aggregat Kelas B M3 1.368,00
JUMLAH 950,00 7,20 6.840,00 1.368,00

3
5.3.(1.a) Perkerasan Beton Semen (PPC) M 1.862,00
JUMLAH 950,00 7,00 6.650,00 1.862,00
0,45 Semen Ton 834,18
3
0,63 Split 1/2-2/3 M 1.163,75
0,42 Pasir M3 485,14
1
9,90 Besi Ø 32 M 1.881,00 Konversi 12,00 156,75 Btg
1
4,20 Besi Ø 16 M 798,00 Konversi 12,00 66,50 Btg
1
97,76 Besi Ø 12 M 18.574,40 Konversi 12,00 1.547,87 Btg

5.3.(3) Lapis Pondasi bawah Beton Kurus M3 675,00


JUMLAH 950,70 7,10 6.750,00 675,00
0,25 Semen Ton 166,73
0,62 Split 1/2-2/3 M3 263,41
0,54 Pasir M3 229,13

REKAP MATERIAL
1 Agg. Kelas B = 1.368,00 M3
2 Semen = 1.000,00 Ton
3 Split 1/2-2/3 = 1.427,00 M3
4 Pasir = 714,00 M3
5 Besi Ø 32 = 157,00 Btg @12m
6 Besi Ø 16 = 67,00 Btg @12m
7 Besi Ø 12 = 1.548,00 Btg @12m