You are on page 1of 106

0 Sandra.Camy Sandra.Camy Miguel.

Martins 2022-05-30 First Issue

INDEX ISSUED BY CHECKED BY RELEASED BY RELEASE DATE REVISION DETAILS

CLIENT CONSORTIUM SUPPLIER

SUPPLIER DOC. NO.:

PROJECT PROJECT NO.:

TP-204233P OKP059/ST1.
New Power Generation Units for Zelten Power Plant 130
TITLES MAIN SUPPLIER

Procedure

General

Solar Packages - Package Ancillaries Installation Guidelines MAIN SUPPLIER DOC. NO.:

4D391-149401

DOCUMENT NO.: FORMAT SCALE

000-EMI2200987-VD-PR A4 N/A

CLIENT DOCUMENT NO.: REVISION STATUS*

0 AP
TP-204233P-PP3-2-V40-0007 SHEET SHEETS

1 106
* PRO-DMS Internal Status: IE (1)
– In Edition; IP (2)
– In progress; CH (2)
– Checked; RF (1)
– Refused; AC (3)
– Approved with comments; NA (1)
– Not approved; AP (3)
– Approved; NR (3)
– Not reviewed; RC (3)
– Reviewed with comments; FC(3) – For

Construction; AB(3) – As built; OB – Obsolete; ED(3) – External Document.

PRO-DMS External Submission Status : AA –Awaiting for External Entity Approval; AE – Approved by External Entity; ACE – Approved with Comments by External Entity; REE – Refused by External Entity; CA – Comments attached by External Entity;

CNA – Without comments by External Entity; AFC - Approved for Construction; FCC - For Construction with Comments; RFC - Refused for Construction; DAE - Deemed Approved by External Entity;

(1) A new upload doesn’t change the document revision; (2) Ongoing approval workflow, not allowing the upload of files; (3) A new upload implies a new revision.

© PROMANEC No part of this document may be copied, photocopied, reproduced, transmitted or otherwise duplicated on any medium without the prior written consent of PROMANEC. The information contained in this document is proprietary and may

not be used for any purpose other than that for which it has been supplied by PROMANEC, nor may such information be disclosed to third parties without the prior written consent of, and upon such terms as may be stipulated by PROMANEC. This

document and all copies made thereof shall be returned on demand.


DRAWING TITLE

ANCILLARY INSTALLATION GUIDELINE

TURBOMACHINERY SYSTEMS PROVIDER

ENGINEERING

CUSTOMER

PROJECT NAME EQUIPMENT

TAURUS 70 ONSHORE GENERATOR SET


SIRTE – ZELTEN BROWNFIELD - GTG
LOCATION
ZELTEN BROWNFIELD
Revision: 0
Status: AP
Released: miguel.martins (2022-05-30)
Checked: Sandra.Camy (2022-05-30)

DRAWING NO. REVISION RELEASE DATE


APPROVED
PROJECT MANAGER

Huish, Shawn
4D391 – 149401 NC 14 March 2022
Issued: Sandra.Camy (2022-05-30)

PROJECT ENGINEER
"THIS COPYRIGHTED WORK AND THE INFORMATION HEREIN IS PROPRIETARY
TO CATERPILLAR INC., SOLAR TURBINES INCORPORATED, AND/OR
Rombaux, Jean-yves
SUBSIDIARIES OF EITHER. WITHOUT EXPRESS WRITTEN PERMISSION FROM
COMMISSIONING SPECIALIST CATERPILLAR INC. OR SOLAR TURBINES INCORPORATED. ANY COPYING,
DISCLOSURE, OR USE EXCEPT THAT FOR WHICH IT IS LOANED, IS PROHIBITED."

Wilson,Kenneth
Document No.: 000-EMI2200987-VD-PR

PROJECT SHORT NAME


SIRTE-G

Caterpillar: Confidential Green


4D391-149401

TABLE OF CONTENTS

Paragraph Page
1.0 SCOPE ..................................................................................................... 4
2.0 NOMENCLATURE .................................................................................... 4

3.0 GENERAL SAFETY.................................................................................. 4


4.0 GENERAL WARNINGS ............................................................................ 6
5.0 PRE-INSTALLATION GUIDELINES ......................................................... 8

6.0 LIFTING GUIDELINES ............................................................................. 9

7.0 FLANGE HARDWARE AND TIGHTENING TORQUE ............................. 10

8.0 EXHAUST EXPANSION JOINTS ............................................................. 11


9.0 INLET FLEXIBLE DUCTS ........................................................................ 11

10.0 SUPPORT STRUCTURE GUIDELINES ................................................... 11

10.1 ANCILLARY SUPPORT STRUCTURE INSTALLATION AND


VERIFICATION PROCEDURES ……………………………………….…….12

11.0 LIST OF REFERENCE MATERIALS ........................................................ 13


Revision: 0

12.0 INSTALLATION GUIDELINES ................................................................. 14


12.1 ISO VIEWS ........................................................................................... 15
Status: AP

12.2 TURBINE EXHAUST SYSTEM................................................................ 16


Released: miguel.martins (2022-05-30)

12.2.1 Bill of Material ......................................................... 17


12.2.2 Exploded views ....................................................... 18
12.2.3 Gaskets ................................................................... 19
12.2.4 Hardware and Torque Sequence ........................... 20
Checked: Sandra.Camy (2022-05-30)

12.2.5 Typical Torque Sequence for Round Ducting....... 21

12.2.6 Assembly Details………………………………………22


12.2.7 Final Inspection ...................................................... 28
Issued: Sandra.Camy (2022-05-30)

12.3 TURBINE AIR INLET SYSTEM ............................................................ 29


12.3.1 Bill of Material ......................................................... 30
12.3.2 Exploded views ....................................................... 31
Document No.: 000-EMI2200987-VD-PR

12.3.3 Sealant..................................................................... 32

2
Caterpillar: Confidential Green
4D391-149401

12.3.4 Hardware and Torque Sequence ........................... 33

12.3.5 Typical Torque Sequence for Square/


Rectangular Ducting ………………………………….34

12.3.6 Assembly Details .................................................... 35


12.3.7 Final Inspection………………………………………...54

12.4 ENCLOSURE VENTILATION SYSTEM……………………………………55


12.4.1 Bill of Material…………………………………………..56

12.4.2 Exploded views………………………………………...58


12.4.3 Sealant……………………………………….…………..60
12.4.4 Hardware and Torque Sequence……………………61

12.4.5 Typical Torque Sequence for Square/


Rectangular Ducting ………………………………….62
12.4.6 Enclosure Exhaust .. ………………………………….63
12.4.6.1 Assembly Details ...………………………………64
12.4.6.2 Final Inspection.....…………………….…………70
Revision: 0

12.4.7 Generator Exhaust.……………………………………71


12.4.7.1 Assembly Details…………………………………72
Status: AP

12.4.7.2 Final Inspection…………………………………...79


Released: miguel.martins (2022-05-30)

12.4.8 Driver Enclosure Exhaust.……………………………80


12.4.8.1 Assembly Details…………………………………81
12.4.8.2 Final Inspection…………………………………...92
12.4.9 Driven Enclosure Exhaust. …….……………………93
Checked: Sandra.Camy (2022-05-30)

12.4.9.1 Assembly Details…………………………………94


12.4.9.2 Final Inspection………………………………….105
Issued: Sandra.Camy (2022-05-30)
Document No.: 000-EMI2200987-VD-PR

3
Caterpillar: Confidential Green
4D391-149401

1.0 SCOPE

The intent of this document is to provide the Customer, as well as Solar’s Field Service Representatives
(FSR), a general assembly instruction guideline pertaining to Ancillary systems. Therefore, this document
outlines the installation guidelines only for project 4D391.

The Ancillary Installation Guideline (AIG) is intended to provide a detailed guideline for assembly of the
ancillary system, with the most relevant information all collected into one document. The Ancillary
Installation Guideline (AIG) references the supplier documents listed in Section 11 as the source of the
information. Please reference those materials for interface definition, additional operation and
maintenance information.

IMPORTANT: Read all instructions before starting the installation of the components. The sequence of
operations provided in this document is not intended to be used as a step by step instructions by the site
contractors. It is the responsibility of the contractor to meet the intent of these installation instructions
regardless of the assembly sequence used based on the integration with support structure, lifting
arrangements, access, proper support and general safety guidelines.

2.0 NOMENCLATURE

1. ES – Engineering Specification
2. FSR – Field Service Representative
3. MID – Mechanical Interface Drawing
4. PIL – Product Information Letter
5. TPIM – Turbomachinery Package Installation Guideline

3.0 GENERAL SAFETY


Revision: 0

Observe standard safety practices. Make sure all personnel who are not directly involved with the
installation are cleared from the area. Consult with lead site personnel if there are any issues or
questions.
Status: AP

Solar turbine-driven packages are designed for safe and reliable operation. The packages include
features which protect the equipment from damaging malfunctions and unsafe operation.
Released: miguel.martins (2022-05-30)

Personnel must become familiar with the following safety requirements and must always observe the
safety requirements. Maximum safety of personnel is of primary importance, followed by protection of
equipment from damage. Careful adherence to these safety requirements will minimize hazards or injury
to personnel and equipment.

Included are procedures for certain operating malfunctions and precautions for personnel working in
Checked: Sandra.Camy (2022-05-30)

special environments (such as in an explosive atmosphere, or where there are dangerous substances).

MANUAL SAFETY WARNINGS, CAUTIONS AND NOTES


Three types of safety notices are used in the manual to emphasize critical information:

WARNINGS, CAUTIONS, and NOTES.


Issued: Sandra.Camy (2022-05-30)

WARNINGS, CAUTIONS, and NOTES are explained in order of significance as follows:

⚠ WARNING
Document No.: 000-EMI2200987-VD-PR

A WARNING identifies procedures, practices, conditions, or precautions, which if not heeded,


could result in personal injury or loss of life.

4
Caterpillar: Confidential Green
4D391-149401

⚠ CAUTION

A CAUTION identifies precautions, which if not observed, could result in damage or destruction of
equipment.

NOTE

A NOTE highlights information necessary to understand or follow a procedure, practice,


condition, or description.

EQUIPMENT SAFETY LABELS


Safety labels attached to the equipment are described in this section.

Safety and warning labels are in categories as detailed in the following subsections.

Caution, Warning and Danger labels may be accompanied with a Prohibition symbol, as shown in the
following figure. The use of the prohibition symbol indicates a potentially hazardous situation or practice
which is not to be allowed.
Revision: 0

Caution and Warning labels may be accompanied with a Safety Alert symbol, as shown in the following
Status: AP

figure. The use of the Safety Alert symbol with Caution and Warning labels increases the severity of the
label.
Released: miguel.martins (2022-05-30)
Checked: Sandra.Camy (2022-05-30)

x Danger - On the package, label has a red border, with white lettering on black, as shown in the
following figure. In the print version, colors are not shown.
Issued: Sandra.Camy (2022-05-30)

Danger is the most severe safety label. The signal word Danger indicates a potentially hazardous
situation which, if not avoided, will result in death or serious injury. Danger labels identify the most
serious hazards.

x Warning - On the package, label has an orange border, with white lettering on black, as shown in
the following figure. In the print version, colors are not shown.
Document No.: 000-EMI2200987-VD-PR

5
Caterpillar: Confidential Green
4D391-149401

The signal word Warning indicates a potentially hazardous situation which, if not avoided, could
result in death or serious injury. Hazards identified with the signal word Warning present a lesser
degree of risk of injury than those identified by the signal word Danger.

x Caution - On the package, label has a yellow border, with white lettering on black, as shown in
the following figure. In the print version, colors are not shown.

The signal word Caution used with a safety alert symbol indicates a potentially hazardous
situation which, if not avoided, may result in minor or moderate injury.

The signal word Caution used without a safety alert symbol indicates a potentially hazardous
situation which, if not avoided, may result in property damage.

x Notice - On the package, label has a blue border with white lettering on black, as shown in the
following figure. In the print version, colors are not shown.

NOTICE

The signal word Notice indicates a statement of policy relating directly or indirectly to the safety of
personnel or protection of property. The statement of policy is on the Notice label. A circle around
Revision: 0

the statement requires mandatory action. The Notice signal word is not to be associated directly
with a hazard or hazardous situation, and may not be used in place of Danger, Warning or
Caution labels.
Status: AP
Released: miguel.martins (2022-05-30)

4.0 GENERAL WARNINGS

WARNING - This general guideline is intended to facilitate communication between the owner, installer,
and Solar. It is not intended to replace the owner or installer's best practices. Failure to consider whether
these general guidelines are applicable to the unique features of a project, or additions and/or
modifications that are not reviewed and approved by Solar, may cause serious malfunction, may allow
unsafe operation, or other unsafe condition, any of which could result in significant property damage,
Checked: Sandra.Camy (2022-05-30)

personnel injury, and/or loss of life.

Solar's inspection, or failure to inspect, the performance of obligations of customer or its contractors shall
not make Solar liable for such obligations of customer or its contractors.

WELDING WARNING – AT NO TIME IS THE FRAME, OR ANY PACKAGE COMPONENT, TO BE


Issued: Sandra.Camy (2022-05-30)

USED AS A GROUND FOR WELDING OR OTHER FACILITY PURPOSES. High current flows between
welding ground and the arc during arc welding. Precautions must be taken to ensure that this current
does not pass through close tolerance moving surfaces, or electronic systems. Welding ground should be
placed as close to the weld location as possible or on the component to be welded. Failure to observe
this warning could void warranty claims.

Prior to any welding procedures, ensure that the turbine package is not in operation and is grounded per
Document No.: 000-EMI2200987-VD-PR

ES 2648. Power must be removed from the package by opening the 120-volt DC circuit breakers prior to

6
Caterpillar: Confidential Green
4D391-149401

welding on or in the vicinity of a turbine package. Weld grounding must be in proximity to weld activities.
Power to the control system must be shut off.

FIRE HAZARD

WARNING: Smoking, open flame, or spark-producing devices (such as cigarette lighters) are NOT
allowed in the package vicinity AT ANY TIME.

WARNING: All welding should be done prior to the installation of filter/evaporative cooler media or after
removal of all media from filter house.

WARNING: Wear protective equipment (face shields, goggles) and observe fire precautions when
operating in filter system.

FALL HAZARD

WARNING: Always keep the floor clean and dry to avoid slippery. Use appropriate handrails, ladders and
cages wherever required to avoid fall hazards. Always use appropriate lifting points, lifting lugs, spreader
bars to avoid falling of components and causing injury to maintenance personnel.
Revision: 0

EYE/EAR DAMAGE HAZARD


Status: AP

WARNING: Always wear goggles to safeguard your eyes from any filter module component protrusion
while operating in filter system.
Released: miguel.martins (2022-05-30)

WARNING: Always wear ear plugs to safeguard your ears from air pulses while cleaning the filters.
Checked: Sandra.Camy (2022-05-30)
Issued: Sandra.Camy (2022-05-30)

WARNING: While replacing the filter, make sure to shut off the compressed air supply from the air
manifold and its interconnections.

SHOCK HAZARD

WARNING: Always observe necessary safeguard measures to avoid electric shock to personnel. Shut
Document No.: 000-EMI2200987-VD-PR

down the system before working on any electrical components. Do not place any objects into any moving

7
Caterpillar: Confidential Green
4D391-149401

or electrically energized components to avoid any injury hazards. Never wire around automatic shutdown
devices, or bypass software alarms and shutdowns. They prevent personnel injury and damage to the
equipment. Do not step on electrical conduit or junction boxes or use them as supports.

INLET SYSTEMS

WARNING:

1. Filtration media within the air filtration system and evaporative cooler media are combustible. Use
every precaution to ensure filter media is kept away from heat sources.

2. Do not smoke or weld near the air filter system or evaporative cooler.

EXHAUST SYSTEMS

WARNING:

1. Do not locate exhaust components on or near flammable surfaces.

CAUTIONS
The following cautions cover Solar turbine-driven packages. Failure to observe these cautions could
result in damage to or destruction of equipment. The order of listing does not indicate order of
importance. Each item is important to overall equipment safety. These cautions (and others which may be
applicable to a specific installation site) must be observed during all service and operation of the package.
Revision: 0

⚠ CAUTION
Status: AP

Prevent foreign matter (such as ice) from entering air inlet. Foreign objects in the air inlet will cause
Released: miguel.martins (2022-05-30)

severe damage.

Protect air inlet from entry of contaminants such as moisture, dust, sand, and oil mist.

Under severe environmental conditions, ensure that inlet air filtration system is free of restrictions that
could reduce inlet air pressure. Use snow covers, de-icers, and sand/dust filters to protect the inlet air
system.
Checked: Sandra.Camy (2022-05-30)

Verify that exhaust collector drains are not connected to common drain manifolds. Common drain
manifolds sometimes drain or vent flammable gases and/or fluids.

5.0 PRE-INSTALLATION GUIDELINES


Issued: Sandra.Camy (2022-05-30)

1. Prior to any installation efforts, check the equipment nameplate for, and verify component identity
against, those indicated on the Mechanical Interface Drawing (MID), Also check for weight and air
flow direction.
2. The clean air section of the filter and clean air plenum must be completely vacuum cleaned and
any loose foreign matter like bolts, nuts, washers, slags, weld splatters, etc., must be removed,
Document No.: 000-EMI2200987-VD-PR

as catastrophic destruction can result from ingestion of foreign particles.

8
Caterpillar: Confidential Green
4D391-149401

3. Perform pre-installation cleaning of all modules, assemblies and ductwork using the appropriate
cleaning method. A water wash is appropriate for an unlined metal duct but not appropriate for
intake silencer with an acoustic lining that will absorb water or chemical cleaners. Common
methods include: a water wash, soap and water wash, wet rag wipe down, vacuum,
cleaning/blowing with compressed air or other method as required.
4. The air inlet assembly must be mounted on a surface designed to provide adequate support for
the weight of the equipment. The foundation on which the inlet resides must be designed to
ensure long-term support and service accessibility.

5. All duct sections, silencers and other components must be examined internally for cleanliness
and damage immediately prior to installation. Already assembled duct components should also
be checked before bolting up mating components.

6. Ducting during assembly should be sealed/covered if long periods of time are expected between
assembly. Components should be examined for any shipping/handling damage and repaired prior
to installation.

Storage and Preservation:

These procedures are to be performed prior to the arrival of Solar’s Commissioning Personnel
and are the responsibility of the customer and their contractor.

1. Packages stored at site must be protected from the weather.

2. Place shipping crates on level ground elevated off grade before construction activities. If
applicable, necessary preservatives for storage were applied on packages and all external
openings were properly sealed in the factory. Refer to PIL097 for the preservation information.
Revision: 0

3. Store open shipping crates in a controlled environment, such as a warehouse or better, as


applicable to climatic conditions of the field.
Status: AP

4. If factory preserved equipment has been opened for inspection, these items should follow
Released: miguel.martins (2022-05-30)

preservation procedures as outlined in PIL097 if these items are not intended to be in use within
three months.

5. Upon arrival at site and/or Storage Facilities please identify shipped crates containing Hazardous
materials and equipment (corrosive, flammable, pressurized gases, etc), review their MSDS
(Material Safety Data Sheet) and segregate them from rest of equipment following their specific
storage needs.
Checked: Sandra.Camy (2022-05-30)

6.0 LIFTING GUIDELINES

1. Qualified (licensed) riggers must follow standard rigging procedures in making any lift.

2. Components are intended for lifting by minimum 45 degree bridal where spreader bar or lifting
Issued: Sandra.Camy (2022-05-30)

angle is not specified on component drawings. Spreader bars, if necessary, are supplied by
others.

3. Never stand under or near an object being lifted or around the path it will travel.

4. Never stand near an operating crane. If the crane operator does not plan the lift appropriately,
Document No.: 000-EMI2200987-VD-PR

the crane can tip over and/or lifting component can come loose and drop.

9
Caterpillar: Confidential Green
4D391-149401

5. All lifts must have adequate rigging gear that is designed to support the lift weight with enough
factor of safety. Solar’s design factor for ancillary component, dynamic factor of 1.5 shall be used
for all lifts per API RP 2A for onshore and offshore applications.

6. When lifting loose ship items, be aware of any specific unpacking or uncrating instructions to
avoid damage to equipment and injury to personnel. Unpacking equipment out of sequence or
improper orientation may not expose lifting features and could lead to equipment damage and/or
personnel injury. Riggers must use lifting provisions on the equipment, where provided. Unless
instructions state otherwise, riggers must be cautioned to not lift ancillary equipment as
assemblies. Lifting in such a way may impose stresses that can lead to equipment damage. For
component lift, use lifting lugs and spreader bars as recommended preventing damage due to
over stressing. Take care not to damage any parts during erection.

7. For ancillary components (which are provided by the supplier directly to the site other than Solar
lifting equipment), refer to the supplier’s lifting instructions

8. Any crates, boxes, containers, etc, dropped during lifting or off-loading operations, regardless
of distance of the fall, must be reported by the customer for Solar to determine the extent of
damage. Even if no external crate or unit damage is visible, equipment can suffer critical internal
damage due to shock that will only become apparent upon start-up of the unit. This internal
damage can have negative consequences causing lengthy delays.

9. If the paint is damaged during lifting, touch up is required to avoid rusting

10. Unless specifically noted on supplier lifting instructions, shipping rods, turnbuckles, or other
yellow painted components shall never directly be used as a lifting device.
Revision: 0

7.0 FLANGE HARDWARE AND TIGHTENING TORQUE


Status: AP

1. Refer to ES 9-54 for fastener installation and torque values.


Released: miguel.martins (2022-05-30)

2. Anti-seize to be installed on all flange hardware.


3. Attaching hardware kits (plus 10% extra) are included for all flanges in Solar’s scope. Hardware
for downstream connections in third party supplier scope are included in supplier shipment.
Hardware is not supplied for foundation or support steel interface.
Checked: Sandra.Camy (2022-05-30)

4. For exhaust flange bolted connections refer section 12.2.4. and for inlet flange bolted connections
refer section 12.3.4 and for vent flange bolted connection refer section 12.4.4

5. Snug tight is defined as the tightness that exists when the plies of the joint are in firm contact.
Snug tightening shall progress systematically until all bolts are simultaneously snug tight and the
connection is fully compacted. In some cases, proper tensioning of the bolt may require more
than a single cycle of systematic tightening to produce a uniform snug tight condition.
Issued: Sandra.Camy (2022-05-30)

6. Thread engagement per ANSI / ASME B18.2.6. The bolt length used shall be such that the end of
the bolt extends beyond or is at least flush with the outer face of the nut when properly installed.
The installation is not acceptable if the end of the bolt is shorter than the outer face of the nut.
Document No.: 000-EMI2200987-VD-PR

10
Caterpillar: Confidential Green
4D391-149401

8.0 EXHAUST EXPANSION JOINTS

1. The expansion joint (if supplied) will not support the weight of ducting or other components. The
expansion joint is designed to absorb thermal growth of the exhaust system.

2. Expansion bellows have 1-1/2” axial compression, ½” axial extension, ¼” lateral movement.
Bellows are not to be used for installation offsets.

3. During installation, ensure that there are no cold lateral or torsional movements transferred into
the flexible element.

4. Flange bolt holes shall line up without external forces applied and bolts shall be inserted by hand
without hammering.

5. Expansion joint is shipped with shipping braces holding the joint at its nominal installed length.

6. Do not remove the shipping braces/turnbuckles until installation of the entire exhaust system is
complete. Reference MID Note 11.0 for the allowable displacements of the expansion joint for
thermal growth.

7. A Solar FSR must be present to observe the removal of shipping braces/turnbuckles.

8. Do not install insulation blanket over fabric section of the expansion joint as it causes damage
due to overheating.

9. For fixed and sliding support of exhaust ducting, refer PIL 273.
Revision: 0
Status: AP

9.0 INLET FLEXIBLE DUCTS

1. Flexible ducting must be installed to accommodate the movement between different sections of
Released: miguel.martins (2022-05-30)

the inlet system.

2. Flexible ducting should be assembled using installed length.

3. Inlet Flexible ducts can have ½” offset in one direction either extension or compression or lateral
movement unless otherwise specified on component drawing.
Checked: Sandra.Camy (2022-05-30)

4. Do not remove the shipping braces/turnbuckles until installation of the entire inlet system is
complete.

10.0 SUPPORT STRUCTURE GUIDELINES

1. Structure for ducts and auxiliary devices should be self-supporting unless otherwise noted.
Issued: Sandra.Camy (2022-05-30)

2. Ensure the ancillary mounting structure does not impose any pre-loads on the turbomachinery, as
this can restrain the equipment, and can, in some cases, drive increased vibration levels.
Document No.: 000-EMI2200987-VD-PR

11
Caterpillar: Confidential Green
4D391-149401

10.1 Ancillary Support Structure Installation and Verification Procedures:

These procedures are to be performed prior to the arrival of Solar’s Commissioning Personnel and are
the responsibility of the customer and their contractor.

1. For enclosed projects, ensure that the enclosure structure is not supporting any equipment weight
beyond what is called for on the MID.

2. Verify that the ancillary support structure is supporting the equipment as shown on the MID.
Ensure that any facility-related equipment is either self-supporting, or that provisions are made on
the MID for the supporting points of the equipment. All structures should be designed in
accordance to API 616, Section 5.5.6.4 and account for the following:

a) Weight of components supported, as shown on the MID

b) Environmental loads, including but not limited to: wind forces, seismic forces, and motion due
to offshore conditions

c) Thermal growth

d) System stiffness

3. Ensure the layout of ancillary structure and ducting is performed according to the MID. Confirm
that the installation has made provision for operation and maintenance access.

4. Verify that support structure mounts are seated on appropriate foundation supports or mounted to
appropriate structure in the facility. Ensure pad loads on structure supports have been considered
and checked by end user.
Revision: 0

5. Review that all bolted structures have been assembled so the load is uniformly distributed among
its entire surface. In the case of attaching straight bars to angled bars or any other non-flat
Status: AP

structure make sure necessary compensating angled washers or hardware is used.


Released: miguel.martins (2022-05-30)

6. For all structural connections (beam to beam, column to beam, cross bracing), the hole diameter
shall be 1/16” greater than the bolt diameter.

7. For mounting duct feet to the supporting beam, the hole diameter shall be 1/8” greater than the
bolt diameter.

8. Recommended minimum bolts per ASTM F3125 for all structure connection and mounting bolts.
Checked: Sandra.Camy (2022-05-30)

9. Heavy hex structural bolt dimensions shall meet the requirements of the ANSI / ASME B18.2.6.
The bolt length used shall be such that the end of the bolt extends beyond or is at least flush with
the outer face of the nut when properly installed. The installation is not acceptable if the end of
the bolt is shorter than the outer face of the nut.

10. For fixed mounting pads, tighten all bolted connections using the AISC turn-of-nut method
Issued: Sandra.Camy (2022-05-30)

whereby the nut shall be rotated an additional 1/2 to 2/3 turn beyond the snug tight condition, or
equivalent torque value. Tack weld nut or permanently deform the threads to create a mechanical
lock.

Note: If hardware has a galvanized or other form of finish. Finish must be removed in the area
first, where tack weld is being applied.
Document No.: 000-EMI2200987-VD-PR

12
Caterpillar: Confidential Green
4D391-149401

11. For exhaust non-fixed (sliding) mounting pads, tighten nuts to snug tight condition, then back off
1/4 turn. The washer should be able to move. Tack weld nut or permanently deform the threads
to create a mechanical lock. Use only hardware provided

12. Slide Plates are required between the structural steel and component support pad for exhaust
systems. One 300 series stainless steel, typically 1/4" thick, slide plate per pad is required. The
component mounting pads should have slots and large enough support area for the pad and slide
plate including the thermal expansion. The slide plates to be secured enough to the support steel
in such a way that it should not slide out.

13. No pre-load is allowed on all flexible joints. Check all flexible joints on installed ducting and
ensure that install length of the flexible joints is in tolerance range (+/- ¼” for bellows and +/- 1/2”
for a flex duct). If the upstream and downstream of the ducts are not aligned properly than the
allowable tolerances are reduced by the amount of misalignment.
14. Use care when setting the exhaust components in place on the support steel slide plates. Ensure
the components are located properly in relationship to the turbine and stack centerlines and are
level, plumb and square with the mating support steel. Shimming may be necessary when setting
the components if the support feet do not contact the slide plates on the support steel. Shims
(supplied by others) to be 300 series stainless steel. Shims must be permanently attached either
by bolting or welding to the support steel. Do not weld a shim or slide pad directly to a component
mounting pad. Shims should be oversized relative to the support steel pads and fully engaged.

11.0 LIST OF REFERENCE MATERIALS:

Solar Drawing: MID 4D391-149725, Rev C


Revision: 0

ES Documents:
Status: AP

1. ES 9-54 - Fastener installation and torque values

TPIM Documents: TPIM 1000 (For GS)


Released: miguel.martins (2022-05-30)

PIL Documents: PIL 273, PIL 097


Checked: Sandra.Camy (2022-05-30)
Issued: Sandra.Camy (2022-05-30)
Document No.: 000-EMI2200987-VD-PR

13
Caterpillar: Confidential Green
Document No.: 000-EMI2200987-VD-PR Issued: Sandra.Camy (2022-05-30) Checked: Sandra.Camy (2022-05-30) Released: miguel.martins (2022-05-30) Status: AP Revision: 0

4D391-149401

12.0: INSTALLATION GUIDELINES

14

Caterpillar: Confidential Green


Document No.: 000-EMI2200987-VD-PR Issued: Sandra.Camy (2022-05-30) Checked: Sandra.Camy (2022-05-30) Released: miguel.martins (2022-05-30) Status: AP Revision: 0

4D391-149401

12.1: ISO VIEWS


4D391- SIRTE OIL COMPANY:

ISO VIEW 1 ISO VIEW 2


(FORWARD RIGHT) (AFT LEFT)

15

Caterpillar: Confidential Green


Document No.: 000-EMI2200987-VD-PR Issued: Sandra.Camy (2022-05-30) Checked: Sandra.Camy (2022-05-30) Released: miguel.martins (2022-05-30) Status: AP Revision: 0

TURBINE EXHAUST SYSTEM


4D391-149401

12.2:TURBINE EXHAUST SYSTEM

16
Caterpillar: Confidential Green
Document No.: 000-EMI2200987-VD-PR Issued: Sandra.Camy (2022-05-30) Checked: Sandra.Camy (2022-05-30) Released: miguel.martins (2022-05-30) Status: AP Revision: 0

TURBINE EXHAUST SYSTEM


4D391-149401

12.2.1: Bill of material

BOM as in MID:

Note: Find Number in the above table refers to the find number as in MID (4D391-149725 Rev C)

17
Caterpillar: Confidential Green
Document No.: 000-EMI2200987-VD-PR Issued: Sandra.Camy (2022-05-30) Checked: Sandra.Camy (2022-05-30) Released: miguel.martins (2022-05-30) Status: AP Revision: 0

TURBINE EXHAUST SYSTEM


4D391-149401

12.2.2: Exploded view

27 10

25 11 23
33

Number outside the bubble means “Refer to respective


page” in this document for more details about the
component and hardware.
Number inside the balloon refers to Find number as in
MID drawing (4D391-149725 Rev C)
Note: Balloon for hardware is not called out in exploded view. Refer to the respective pages for hardware detail.

18
Caterpillar: Confidential Green
Document No.: 000-EMI2200987-VD-PR Issued: Sandra.Camy (2022-05-30) Checked: Sandra.Camy (2022-05-30) Released: miguel.martins (2022-05-30) Status: AP Revision: 0

TURBINE EXHAUST SYSTEM


4D391-149401

12.2.3: Gaskets

1. High temperature gasket shall be installed between flanges. Gasket material comes as a part of hardware kit.

2. Gasket thickness and type may vary for different flange cross-sections. The compressed thickness of gasket shall be
0.25” for round duct.

3. The Gasket may need to be cut to size for each flange connection.

4. Allow gasket to overlap at the ends and ensure gasket makes a complete seal of the flange.

5. Use adhesive to temporarily attach the gasket onto the flange.

6. Gasket shall not be twisted, rolled, or deformed.

7. Ensure gasket material is not protruding into the internal duct gas path.

19
Caterpillar: Confidential Green
Document No.: 000-EMI2200987-VD-PR Issued: Sandra.Camy (2022-05-30) Checked: Sandra.Camy (2022-05-30) Released: miguel.martins (2022-05-30) Status: AP Revision: 0

TURBINE EXHAUST SYSTEM


4D391-149401

12.2.4: Hardware and Torque Sequence

1. Flange to flange bolted connections can be tensioned using the AISC turn-of-nut method whereby the nut shall be
rotated an additional 1/2 to 2/3 turn beyond the snug tight condition, or equivalent torque value. Thread engagement
per ANSI / ASME B18.2.6. The bolt length used shall be such that the end of the bolt extends beyond or is at least
flush with the outer face of the nut when properly installed. The installation is not acceptable if the end of the bolt is
shorter than the outer face of the nut.

2. For fixed support points, tighten all bolted connections using the AISC turn-of-nut method whereby the nut shall be
rotated an additional 1/2 to 2/3 turn beyond the snug tight condition. Tack weld nut or permanently deform the threads
to create a mechanical lock.

3. For non-fixed (sliding) support points, tighten nuts to snug tight condition, then back off 1/4 turn. The washer should
be able to move. Tack weld nut or permanently deform the threads to create a mechanical lock.

4. Hardware is 316 SST, grade B8M per ASTM A193. Details are included within the kit bill of material shown on
subsequent sheets.

5. Thread engagement per ANSI / ASME B18.2.6. The bolt length used shall be such that the end of the bolt extends
beyond or is at least flush with the outer face of the nut when properly installed. The installation is not acceptable if
the end of the bolt is shorter than the outer face of the nut.

6. If one or more screws, bolts or nuts of a series are tightened, as in a series of bolts around a flange or a half shell, the
entire series must be tightened equally to prevent distortion, damage or leakage. See below figure for torque
sequences for bolt pattern.

20
Caterpillar: Confidential Green
Document No.: 000-EMI2200987-VD-PR Issued: Sandra.Camy (2022-05-30) Checked: Sandra.Camy (2022-05-30) Released: miguel.martins (2022-05-30) Status: AP Revision: 0

TURBINE EXHAUST SYSTEM


4D391-149401

12.2.5: Typical Torque Sequence for Round Ducting

Note: The above torque sequence remains the same irrespective of the number of holes in the ducting.

21
Caterpillar: Confidential Green
Document No.: 000-EMI2200987-VD-PR Issued: Sandra.Camy (2022-05-30) Checked: Sandra.Camy (2022-05-30) Released: miguel.martins (2022-05-30) Status: AP Revision: 0

TURBINE EXHAUST SYSTEM


4D391-149401

12.2.6: Assembly Details


x Detail 1: Assemble exhaust bellows onto the exhaust collector

x Detail 2: Assemble exhaust silencer onto the exhaust bellows

x Detail 3: Assemble exhaust rainstack onto the exhaust silencer

****Assembly details above shall not be considered as installation order. Order of installation may vary based on
integration with support structure, lifting arrangements, access, proper support and general safety guidelines. It is
recommended that the component installation start at the turbine connection and continue outward. ****

Note:

1. Ensure exhaust silencer is installed, aligned, levelled, and anchored to foundation prior to installing expansion bellow
and rainstack.

2. Foundation anchor bolts for the exhaust silencer are supplied by others.

22
Caterpillar: Confidential Green
Document No.: 000-EMI2200987-VD-PR Issued: Sandra.Camy (2022-05-30) Checked: Sandra.Camy (2022-05-30) Released: miguel.martins (2022-05-30) Status: AP Revision: 0

TURBINE EXHAUST SYSTEM


4D391-149401

Detail 1:
x Assemble exhaust bellows onto the exhaust collector
x Do not remove the shipping braces/turnbuckles until installation of the
entire system is complete
.

Note: Bellows exhaust cannot bear load and temporary supports shall be erected prior to installing the silencer exhaust

23
Caterpillar: Confidential Green
Document No.: 000-EMI2200987-VD-PR Issued: Sandra.Camy (2022-05-30) Checked: Sandra.Camy (2022-05-30) Released: miguel.martins (2022-05-30) Status: AP Revision: 0

TURBINE EXHAUST SYSTEM


4D391-149401

Air Flow Direction:

x Expansion bellows should be assembled as per air flow direction symbol and installed length as mentioned in
Solar print 2043338-300 Rev N/C

Air flow Direction Installed Length

24
Caterpillar: Confidential Green
Document No.: 000-EMI2200987-VD-PR Issued: Sandra.Camy (2022-05-30) Checked: Sandra.Camy (2022-05-30) Released: miguel.martins (2022-05-30) Status: AP Revision: 0

TURBINE EXHAUST SYSTEM


4D391-149401

Detail 2:
x Assemble exhaust silencer onto the exhaust bellows

25
Caterpillar: Confidential Green
Document No.: 000-EMI2200987-VD-PR Issued: Sandra.Camy (2022-05-30) Checked: Sandra.Camy (2022-05-30) Released: miguel.martins (2022-05-30) Status: AP Revision: 0

TURBINE EXHAUST SYSTEM


4D391-149401

Thermal expansion of silencer exhaust:


x Important: Check orientation as shown
x Arrows indicate the direction of thermal expansion.

THERMAL EXPANSION IN AXIAL


DIRECTION

26
Caterpillar: Confidential Green
Document No.: 000-EMI2200987-VD-PR Issued: Sandra.Camy (2022-05-30) Checked: Sandra.Camy (2022-05-30) Released: miguel.martins (2022-05-30) Status: AP Revision: 0

TURBINE EXHAUST SYSTEM


4D391-149401

Detail 3:
x Assemble exhaust rainstack onto the exhaust silencer

27
Caterpillar: Confidential Green
Document No.: 000-EMI2200987-VD-PR Issued: Sandra.Camy (2022-05-30) Checked: Sandra.Camy (2022-05-30) Released: miguel.martins (2022-05-30) Status: AP Revision: 0

TURBINE EXHAUST SYSTEM


4D391-149401

12.2.7 Final Inspection

x Verify all blocking, shipping braces, tools and other equipment used in the erection of the system have been removed from the
internal areas of the system

x Ensure that all components have been cleaned inside the air passages

x Ensure that all transportation tags and labels have been removed

x Ensure that all parts and surface finish were not damaged during installation

x Make sure that the Air flow direction indicated on ducts has been followed

x Verify gaskets are installed correctly without any damage and the material is not in the internal duct gas path

x Ensure that all earth/ground wires are installed for earthing of equipment and bonding between mechanical parts

x Complete systems must be completely installed, cleaned, inspected, etc.,

x Verify that all drains have been properly connected or plumbed

x Verify the four (4) vents that are 90 deg apart at the silencer base are open and unobstructed.

x Verify any external blankets have been installed per the installation instructions (If supplied)

x Perform a random sampling of flange bolts to confirm they are properly tightened. If multiple bolts are found to be loose on a flange
connection, it is recommended to retighten all flange connection nuts

x Verify all sliding supports hardware is installed correctly as per sec 12.2.4

28
Caterpillar: Confidential Green
Document No.: 000-EMI2200987-VD-PR Issued: Sandra.Camy (2022-05-30) Checked: Sandra.Camy (2022-05-30) Released: miguel.martins (2022-05-30) Status: AP Revision: 0

TURBINE AIR INLET SYSTEM


4D391-149401

12.3: TURBINE AIR INLET SYSTEM

29
Caterpillar: Confidential Green
Document No.: 000-EMI2200987-VD-PR Issued: Sandra.Camy (2022-05-30) Checked: Sandra.Camy (2022-05-30) Released: miguel.martins (2022-05-30) Status: AP Revision: 0

TURBINE AIR INLET SYSTEM


4D391-149401

12.3.1: Bill of material

BOM as in MID:

Note: Find Number in the above table refers to the find number as in MID (4D391-149725, Rev C)

30
Caterpillar: Confidential Green
Document No.: 000-EMI2200987-VD-PR Issued: Sandra.Camy (2022-05-30) Checked: Sandra.Camy (2022-05-30) Released: miguel.martins (2022-05-30) Status: AP Revision: 0

TURBINE AIR INLET SYSTEM


4D391-149401

12.3.2: Exploded Views


71 40
7 6
43
5
39
2 45
3
37 1 47
31 6
42
64
4 8
36
30 44
3
46 31
48

Number outside the bubble means “Refer to respective page” in 32


this document for more details about the component and hardware
53
Number inside the balloon refers to Find number as in
4D391-149725, Rev C

Note: Balloon for hardware is not called out in exploded view. Refer respective pages for hardware details

31
Caterpillar: Confidential Green
Document No.: 000-EMI2200987-VD-PR Issued: Sandra.Camy (2022-05-30) Checked: Sandra.Camy (2022-05-30) Released: miguel.martins (2022-05-30) Status: AP Revision: 0

TURBINE AIR INLET SYSTEM


4D391-149401

12.3.3: Sealant

Prior to the lift of ducting and silencers between the air filter and the turbine enclosure, apply ¼-inch bead of sealant
(supplied in the Flange Hardware kits) to the upstream duct interface flanges that will mate to their adjoining downstream
assemblies. The sealant must be applied in a figure 8 pattern around all mounting holes as shown below.

Note: Inlet systems use Sikaflex-221 for flange-to-flange sealant. Refer to Solar P/N 1057827 if additional quantity is
Needed

32
Caterpillar: Confidential Green
Document No.: 000-EMI2200987-VD-PR Issued: Sandra.Camy (2022-05-30) Checked: Sandra.Camy (2022-05-30) Released: miguel.martins (2022-05-30) Status: AP Revision: 0

TURBINE AIR INLET SYSTEM


4D391-149401

12.3.4: Hardware and Torque Sequence

1. Unless otherwise indicated on the assembly drawing, bolts should be tightened to the snug-tight condition after all
components are in place and correctly positioned.

2. For fixed support points, tighten all bolted connections using the AISC turn-of-nut method whereby the nut shall be
rotated an additional 1/2 to 2/3 turn beyond the snug tight condition. Tack weld nut or permanently deform the
threads to create a mechanical lock.

3. For non-fixed (sliding) support points, tighten nuts to snug tight condition, then back off 1/4 turn. The washer should
be able to move. Tack weld nut or permanently deform the threads to create a mechanical lock.

4. Hardware is 316 SST, grade B8M per ASTM A193. Details are included within the kit bill of material shown
on subsequent sheets.

5. Thread engagement per ANSI / ASME B18.2.6. The bolt length used shall be such that the end of the bolt extends
beyond or is at least flush with the outer face of the nut when properly installed. The installation is not acceptable if
the end of the bolt is shorter than the outer face of the nut.

6. If one or more screws, bolts or nuts of a series are tightened, as in a series of bolts around a flange or a half shell,
all that series must be tightened equally to prevent distortion, damage or leakage. See below figure for torque
sequences for bolt pattern.

33
Caterpillar: Confidential Green
Document No.: 000-EMI2200987-VD-PR Issued: Sandra.Camy (2022-05-30) Checked: Sandra.Camy (2022-05-30) Released: miguel.martins (2022-05-30) Status: AP Revision: 0

TURBINE AIR INLET SYSTEM


4D391-149401

12.3.5: Typical Torque Sequence for Square/Rectangular Ducting

Note: The above torque sequence remains the same irrespective of the number of holes in the ducting.

34
Caterpillar: Confidential Green
Document No.: 000-EMI2200987-VD-PR Issued: Sandra.Camy (2022-05-30) Checked: Sandra.Camy (2022-05-30) Released: miguel.martins (2022-05-30) Status: AP Revision: 0

TURBINE AIR INLET SYSTEM


4D391-149401

12.3.6: Assembly Details


x Detail 1: Assemble inlet donasonic silencer inlet onto the enclosure roof
x Detail 2: Assemble inlet flex duct onto the inlet donasonic silencer
x Detail 3: Assemble inlet elbow duct onto the inlet straight duct at ground level
x Detail 4: Assemble straight duct along with elbow duct on to the flex duct
x Detail 5: Assemble inlet duct onto the inlet elbow duct
x Detail 6: Assemble heat exchanger onto the inlet duct
x Detail 7: Assemble inlet straight duct onto the heat exchanger
x Detail 8: Assemble inlet straight duct onto the inlet straight duct
x Detail 9: Assemble inlet straight duct onto the inlet straight duct
x Detail 10: Assemble inlet straight duct onto the inlet straight duct
x Detail 11: Assemble inlet duct onto the inlet straight duct
x Detail 12: Assemble inlet flex duct onto the inlet duct
x Detail 13: Assemble leg kit with inlet air filter
x Detail 14: Assemble inlet air filter onto the duct inlet flex

****Assembly details above shall not be considered as installation order. Order of installation may vary based on
integration with support structure, lifting arrangements, access, proper support and general safety guidelines. It is
recommended that the component installation start at the turbine connection and continue outward. ****

Note:
1. Ensure support structure installation is aligned and level, and all mating components are aligned prior
to installing flexible elements.
2. Support structure by others and must be erected before any ducts can be installed. Ensure cleanliness
of all duct work prior to installation.

35
Caterpillar: Confidential Green
Document No.: 000-EMI2200987-VD-PR Issued: Sandra.Camy (2022-05-30) Checked: Sandra.Camy (2022-05-30) Released: miguel.martins (2022-05-30) Status: AP Revision: 0

TURBINE AIR INLET SYSTEM


4D391-149401

Detail 1:
x Assemble inlet donasonic silencer inlet onto the enclosure roof
x Check orientation using flow direction arrow stamped on the exterior of the silencer

Flow direction

36
Caterpillar: Confidential Green
Document No.: 000-EMI2200987-VD-PR Issued: Sandra.Camy (2022-05-30) Checked: Sandra.Camy (2022-05-30) Released: miguel.martins (2022-05-30) Status: AP Revision: 0

TURBINE AIR INLET SYSTEM


4D391-149401

Detail 2:
x Assemble inlet flex duct onto the inlet donasonic silencer
x Do not remove the shipping braces/turnbuckles until installation of the
entire system is complete

Note: Flex duct cannot bear load and the support structure shall be erected prior to installing the inlet duct

37
Caterpillar: Confidential Green
Document No.: 000-EMI2200987-VD-PR Issued: Sandra.Camy (2022-05-30) Checked: Sandra.Camy (2022-05-30) Released: miguel.martins (2022-05-30) Status: AP Revision: 0

TURBINE AIR INLET SYSTEM


4D391-149401

Air Flow Direction of Inlet Flexible Duct (Solar Drawing 1828120-100 REV 0):
x Inlet expansion joint can be assembled in any direction as it is symmetric
x Installed length should be as mentioned in below screen shot

Installed length

Note: Inlet Flexible ducts can have ½” offset in one direction either extension or compression or lateral movement unless otherwise
specified on component drawing.

38
Caterpillar: Confidential Green
Document No.: 000-EMI2200987-VD-PR Issued: Sandra.Camy (2022-05-30) Checked: Sandra.Camy (2022-05-30) Released: miguel.martins (2022-05-30) Status: AP Revision: 0

TURBINE AIR INLET SYSTEM


4D391-149401

Detail 3:
x Assemble inlet elbow duct onto the inlet straight duct at ground level

39
Caterpillar: Confidential Green
Document No.: 000-EMI2200987-VD-PR Issued: Sandra.Camy (2022-05-30) Checked: Sandra.Camy (2022-05-30) Released: miguel.martins (2022-05-30) Status: AP Revision: 0

TURBINE AIR INLET SYSTEM


4D391-149401

Detail 4:
x Assemble straight duct along with elbow duct on to the flex duct

Hardware and Support


structure by others

Note: Support structure steelwork supporting the elbow duct shall be installed prior to installing the other duct. Elbow duct shall be
placed on support structure upon initial installation by means of support feature

40
Caterpillar: Confidential Green
Document No.: 000-EMI2200987-VD-PR Issued: Sandra.Camy (2022-05-30) Checked: Sandra.Camy (2022-05-30) Released: miguel.martins (2022-05-30) Status: AP Revision: 0

TURBINE AIR INLET SYSTEM


4D391-149401

Detail 5:
x Assemble inlet duct onto the inlet elbow duct
x Access door should be faced as shown

Access Door

41
Caterpillar: Confidential Green
Document No.: 000-EMI2200987-VD-PR Issued: Sandra.Camy (2022-05-30) Checked: Sandra.Camy (2022-05-30) Released: miguel.martins (2022-05-30) Status: AP Revision: 0

TURBINE AIR INLET SYSTEM


4D391-149401

Detail 6:
x Assemble heat exchanger onto the inlet duct

Heat exchanger inlet and


outlet ports should be
facing in this direction

Hardware and Support


structure by others

Note: Support structure steelwork supporting the heat exchanger shall be installed prior to installing the other duct. heat exchanger
shall be placed on support structure upon initial installation by means of support feature
Interconnect tubing for the heat exchanger is provided by others and must be supported by the support structure. The heat exchanger
piping connections cannot bear any external loads.

42
Caterpillar: Confidential Green
Document No.: 000-EMI2200987-VD-PR Issued: Sandra.Camy (2022-05-30) Checked: Sandra.Camy (2022-05-30) Released: miguel.martins (2022-05-30) Status: AP Revision: 0

TURBINE AIR INLET SYSTEM


4D391-149401

Detail 7:
x Assemble inlet straight duct onto the heat exchanger

Hardware and Support


structure by others

Note: Support structure steelwork supporting the inlet straight shall be installed prior to installing the other duct. Inlet straight shall be
placed on support structure upon initial installation by means of support feature

43
Caterpillar: Confidential Green
Document No.: 000-EMI2200987-VD-PR Issued: Sandra.Camy (2022-05-30) Checked: Sandra.Camy (2022-05-30) Released: miguel.martins (2022-05-30) Status: AP Revision: 0

TURBINE AIR INLET SYSTEM


4D391-149401

Detail 8:
x Assemble inlet straight duct onto the inlet straight duct

44
Caterpillar: Confidential Green
Document No.: 000-EMI2200987-VD-PR Issued: Sandra.Camy (2022-05-30) Checked: Sandra.Camy (2022-05-30) Released: miguel.martins (2022-05-30) Status: AP Revision: 0

TURBINE AIR INLET SYSTEM


4D391-149401

Detail 9:
x Assemble inlet straight duct onto the inlet straight duct

Hardware and Support


structure by others

Note: Support structure steelwork supporting the inlet straight duct shall be installed prior to installing the other duct. Inlet straight duct
shall be placed on support structure upon initial installation by means of support feature

45
Caterpillar: Confidential Green
Document No.: 000-EMI2200987-VD-PR Issued: Sandra.Camy (2022-05-30) Checked: Sandra.Camy (2022-05-30) Released: miguel.martins (2022-05-30) Status: AP Revision: 0

TURBINE AIR INLET SYSTEM


4D391-149401

Detail 10:
x Assemble inlet straight duct onto the inlet straight duct

46
Caterpillar: Confidential Green
Document No.: 000-EMI2200987-VD-PR Issued: Sandra.Camy (2022-05-30) Checked: Sandra.Camy (2022-05-30) Released: miguel.martins (2022-05-30) Status: AP Revision: 0

TURBINE AIR INLET SYSTEM


4D391-149401

Detail 11:
x Assemble inlet duct onto the inlet straight duct
x Access door should be faced as shown

Access Door

Hardware and Support


structure by others

Note: Support structure steelwork supporting the inlet straight duct shall be installed prior to installing the other duct. Inlet straight duct
shall be placed on support structure upon initial installation by means of support feature

47
Caterpillar: Confidential Green
Document No.: 000-EMI2200987-VD-PR Issued: Sandra.Camy (2022-05-30) Checked: Sandra.Camy (2022-05-30) Released: miguel.martins (2022-05-30) Status: AP Revision: 0

TURBINE AIR INLET SYSTEM


4D391-149401

Detail 12:
x Assemble inlet flex duct onto the inlet duct
x Do not remove the shipping braces/turnbuckles until installation of the
entire system is complete

Note: Flex duct cannot bear load and the support structure shall be erected prior to installing the inlet duct

48
Caterpillar: Confidential Green
Document No.: 000-EMI2200987-VD-PR Issued: Sandra.Camy (2022-05-30) Checked: Sandra.Camy (2022-05-30) Released: miguel.martins (2022-05-30) Status: AP Revision: 0

TURBINE AIR INLET SYSTEM


4D391-149401

Air Flow Direction of Inlet Flexible Duct (Solar Drawing 1828120-100 REV 0):
x Inlet expansion joint can be assembled in any direction as it is symmetric
x Installed length should be as mentioned in below screen shot

Installed length

Note: Inlet Flexible ducts can have ½” offset in one direction either extension or compression or lateral movement unless otherwise
specified on component drawing.

49
Caterpillar: Confidential Green
Document No.: 000-EMI2200987-VD-PR Issued: Sandra.Camy (2022-05-30) Checked: Sandra.Camy (2022-05-30) Released: miguel.martins (2022-05-30) Status: AP Revision: 0

TURBINE AIR INLET SYSTEM


4D391-149401

Detail 13:
x Assemble leg kit
x Assemble leg kit with inlet air filter
x Then assemble filter system onto the ducts

50
Caterpillar: Confidential Green
Document No.: 000-EMI2200987-VD-PR Issued: Sandra.Camy (2022-05-30) Checked: Sandra.Camy (2022-05-30) Released: miguel.martins (2022-05-30) Status: AP Revision: 0
Document No.: 000-EMI2200987-VD-PR Issued: Sandra.Camy (2022-05-30) Checked: Sandra.Camy (2022-05-30) Released: miguel.martins (2022-05-30) Status: AP Revision: 0
Document No.: 000-EMI2200987-VD-PR Issued: Sandra.Camy (2022-05-30) Checked: Sandra.Camy (2022-05-30) Released: miguel.martins (2022-05-30) Status: AP Revision: 0

TURBINE AIR INLET SYSTEM


4D391-149401

Detail 14:
x Assemble inlet air filter onto the duct inlet flex

53
Caterpillar: Confidential Green
Document No.: 000-EMI2200987-VD-PR Issued: Sandra.Camy (2022-05-30) Checked: Sandra.Camy (2022-05-30) Released: miguel.martins (2022-05-30) Status: AP Revision: 0

TURBINE AIR INLET SYSTEM


4D391-149401

12.3.7: FINAL INSPECTION

Verify all blocking, shipping braces, tools and other equipment used in the erection of the system have been removed from the
internal areas of the system

Ensure that all components have been cleaned inside the air passages

Ensure that all transportation tags and labels have been removed

Ensure that all parts and surface finish were not damaged during installation

Make sure that the Air flow direction indicated on ducts has been followed

Ensure that all earth/ground wires are installed for earthing of equipment and bonding between mechanical parts

Complete systems must be completely installed, cleaned, inspected, etc., with filters installed

Check the seal of the filter elements against filter banks

Check the air tightness of the clean air side. One person should enter the clean air side by access hatch and check for any light
coming through. If there is enough light for this, one other person can shine flashlight from the outside. All gaps need to be filled
with sealing compound

Verify that access doors, if used during the erection of the system have been replaced and securely tightened

Verify that all drains have been properly connected or plumbed

Perform a random sampling of flange bolts to confirm they are properly tightened. If multiple bolts are found to be loose on a flange
connection, it is recommended to retighten all flange connection nuts

54
Caterpillar: Confidential Green
Document No.: 000-EMI2200987-VD-PR Issued: Sandra.Camy (2022-05-30) Checked: Sandra.Camy (2022-05-30) Released: miguel.martins (2022-05-30) Status: AP Revision: 0

ENCLOURE VENTILATION SYSTEM


4D391-149401

12.4: ENCLOSURE VENTILATION SYSTEM

55
Caterpillar: Confidential Green
Document No.: 000-EMI2200987-VD-PR Issued: Sandra.Camy (2022-05-30) Checked: Sandra.Camy (2022-05-30) Released: miguel.martins (2022-05-30) Status: AP Revision: 0

ENCLOURE VENTILATION SYSTEM


4D391-149401

12.4.1: Bill of material

BOM as in MID:

Note: Find Number in the above table refers to the find number as in MID (4D391-149725, Rev C)

56
Caterpillar: Confidential Green
Document No.: 000-EMI2200987-VD-PR Issued: Sandra.Camy (2022-05-30) Checked: Sandra.Camy (2022-05-30) Released: miguel.martins (2022-05-30) Status: AP Revision: 0

ENCLOURE VENTILATION SYSTEM


4D601-149401

ISO view:

ISO VIEW 1 ISO VIEW 2


(FORWARD RIGHT) (AFT LEFT)

57

Caterpillar: Confidential Green


Document No.: 000-EMI2200987-VD-PR Issued: Sandra.Camy (2022-05-30) Checked: Sandra.Camy (2022-05-30) Released: miguel.martins (2022-05-30) Status: AP Revision: 0

ENCLOURE VENTILATION SYSTEM


4D391-149401

12.4.2: Exploded Views


67
15 77
18
68
18 78
13

15
76

21
13 75
69 17
65
Generator-Exhaust 17
Enclosure-Exhaust
73
Number outside the bubble means “Refer to respective
page” in this document for more details about the
component and hardware.
Number inside the balloon refers to Find number as in
MID 4D391-149725, Rev C

Note: Balloon for hardware is not called out in exploded view. Refer respective pages for hardware details

Caterpillar: Confidential Green 58


Document No.: 000-EMI2200987-VD-PR Issued: Sandra.Camy (2022-05-30) Checked: Sandra.Camy (2022-05-30) Released: miguel.martins (2022-05-30) Status: AP Revision: 0

ENCLOURE VENTILATION SYSTEM


4D391-149401

91
22
89
88 19 104
14 103 22
87 13
102
86 12
19
16 13 101
85 90 14
100
9
84 99 12
20 16
98
9
97
20

17
82

17
Driver Enclosure Air Inlet 95 Driven Enclosure Air Inlet

Caterpillar: Confidential Green 59


Document No.: 000-EMI2200987-VD-PR Issued: Sandra.Camy (2022-05-30) Checked: Sandra.Camy (2022-05-30) Released: miguel.martins (2022-05-30) Status: AP Revision: 0

ENCLOURE VENTILATION SYSTEM


4D391-149401

12.4.3: Sealant

Prior to the lift of ducting and silencers between the air filter and the turbine enclosure, apply ¼-inch bead of sealant
(supplied in the Flange Hardware kits) to the upstream duct interface flanges that will mate to their adjoining downstream
assemblies. The sealant must be applied in a figure 8 pattern around all mounting holes as shown below.

Note: Ventilation systems use Sikaflex-221 for flange-to-flange sealant. Refer to Solar P/N 1057827 if additional quantity
is needed.

Caterpillar: Confidential Green 60


Document No.: 000-EMI2200987-VD-PR Issued: Sandra.Camy (2022-05-30) Checked: Sandra.Camy (2022-05-30) Released: miguel.martins (2022-05-30) Status: AP Revision: 0

ENCLOURE VENTILATION SYSTEM


4D391-149401

12.4.4: Hardware and Torque Sequence

1. Flange to flange bolted connections can be tensioned using the AISC turn-of-nut method whereby the nut shall be
rotated an additional 1/2 to 2/3 turn beyond the snug tight condition, or equivalent torque value. Thread
engagement per ANSI / ASME B18.2.6. The bolt length used shall be such that the end of the bolt extends
beyond or is at least flush with the outer face of the nut when properly installed.

2. For fixed support points, tighten all bolted connections using the AISC turn-of-nut method whereby the nut shall
be rotated an additional 1/2 to 2/3 turn beyond the snug tight condition, or equivalent torque value.

3. For non-fixed (sliding) support points, tighten nuts to snug tight condition, then back off 1/4 turn. The washer
should be able to move. Tack weld nut or permanently deform the threads to create a mechanical lock.

4. Hardware is 316 SST, grade B8M per ASTM A193. Details are included within the kit bill of material shown on
subsequent sheets

5. Thread engagement per ANSI / ASME B18.2.6. The bolt length used shall be such that the end of the bolt
extends beyond or is at least flush with the outer face of the nut when properly installed. The installation is not
acceptable if the end of the bolt is shorter than the outer face of the nut.

6. If one or more screws, bolts or nuts of a series are tightened, as in a series of bolts around a flange or a half shell,
all that series must be tightened equally to prevent distortion, damage or leakage. See below figure for torque
sequences for bolt pattern.

Caterpillar: Confidential Green 61


Document No.: 000-EMI2200987-VD-PR Issued: Sandra.Camy (2022-05-30) Checked: Sandra.Camy (2022-05-30) Released: miguel.martins (2022-05-30) Status: AP Revision: 0

ENCLOURE VENTILATION SYSTEM


4D391-149401

12.4.5: Typical Torque Sequence for Square/Rectangular and Round Ducting

Note: The above torque sequence remains the same irrespective of the number of holes in the ducting.

Caterpillar: Confidential Green 62


Document No.: 000-EMI2200987-VD-PR Issued: Sandra.Camy (2022-05-30) Checked: Sandra.Camy (2022-05-30) Released: miguel.martins (2022-05-30) Status: AP Revision: 0

ENCLOURE VENTILATION SYSTEM


4D391-149401

12.4.6: ENCLOSURE-EXHAUST

Caterpillar: Confidential Green 63


Document No.: 000-EMI2200987-VD-PR Issued: Sandra.Camy (2022-05-30) Checked: Sandra.Camy (2022-05-30) Released: miguel.martins (2022-05-30) Status: AP Revision: 0

ENCLOURE VENTILATION SYSTEM


4D391-149401

12.4.6.1: Assembly Details

x Detail 1: Assemble pneumatic damper onto the enclosure roof

x Detail 2: Assemble elbow silencer onto the pneumatic damper

x Detail 3: Assemble duct louver vent onto the elbow silencer

x Detail 4: Assemble screen vent onto the duct louver vent

****Assembly details above shall not be considered as installation order. Order of installation may vary based on
integration with support structure, lifting arrangements, access, proper support and general safety guidelines. It is
recommended that the component installation start at the turbine connection and continue outward.****

Note:

1. Ensure support structure installation is aligned and level, and all mating components are aligned prior to installing
flexible elements.

2. Support structure by others and must be erected before any ducts can be installed.

Caterpillar: Confidential Green 64


Document No.: 000-EMI2200987-VD-PR Issued: Sandra.Camy (2022-05-30) Checked: Sandra.Camy (2022-05-30) Released: miguel.martins (2022-05-30) Status: AP Revision: 0

ENCLOURE VENTILATION SYSTEM


4D391-149401

Detail 1:
x Assemble pneumatic damper onto the enclosure roof
x Ensure the correct damper orientation while assembling onto the enclosure

Pneumatic arrangement
should face in this direction

Caterpillar: Confidential Green 65


Document No.: 000-EMI2200987-VD-PR Issued: Sandra.Camy (2022-05-30) Checked: Sandra.Camy (2022-05-30) Released: miguel.martins (2022-05-30) Status: AP Revision: 0

ENCLOURE VENTILATION SYSTEM


4D391-149401

Isolation damper fire connection system:


x The isolation damper and fire suppression system should be internally connected by joining flexible hose assembly
In to the union damper
Top View
Left Side View

Caterpillar: Confidential Green 66


Document No.: 000-EMI2200987-VD-PR Issued: Sandra.Camy (2022-05-30) Checked: Sandra.Camy (2022-05-30) Released: miguel.martins (2022-05-30) Status: AP Revision: 0

ENCLOURE VENTILATION SYSTEM


4D391-149401

Detail 2:
x Assemble elbow silencer onto the pneumatic damper

Caterpillar: Confidential Green 67


Document No.: 000-EMI2200987-VD-PR Issued: Sandra.Camy (2022-05-30) Checked: Sandra.Camy (2022-05-30) Released: miguel.martins (2022-05-30) Status: AP Revision: 0

ENCLOURE VENTILATION SYSTEM


4D391-149401

Detail 3:
x Assemble duct louver vent onto the elbow silencer

Caterpillar: Confidential Green 68


Document No.: 000-EMI2200987-VD-PR Issued: Sandra.Camy (2022-05-30) Checked: Sandra.Camy (2022-05-30) Released: miguel.martins (2022-05-30) Status: AP Revision: 0

ENCLOURE VENTILATION SYSTEM


4D391-149401

Detail 4:
x Assemble vent straight duct onto the elbow silencer

Caterpillar: Confidential Green 69


Document No.: 000-EMI2200987-VD-PR Issued: Sandra.Camy (2022-05-30) Checked: Sandra.Camy (2022-05-30) Released: miguel.martins (2022-05-30) Status: AP Revision: 0

ENCLOURE VENTILATION SYSTEM


4D391-149401

12.4.6.2 FINAL INSPECTION

x Verify all blocking, shipping braces, tools and other equipment used in the erection of the system have been removed
from the internal areas of the system.

x Ensure that all components have been cleaned inside the air passages.

x Ensure that all transportation tags and labels have been removed.

x Ensure that all parts and surface finish were not damaged during installation.

x Make sure that the Air flow direction indicated on ducts has been followed.

x Ensure that all earth/ground wires are installed for earthing of equipment and bonding between mechanical parts.

x Complete systems must be completely installed, cleaned, inspected, etc.,

x Verify that all drains have been properly connected or plumbed.

x Verify that access doors, if used during the erection of the system have been replaced and securely tightened.

x Perform a random sampling of flange bolts to confirm they are properly tightened. If multiple bolts are found to be
loose on a flange connection, its is recommended to retighten all flange connection nuts.

Caterpillar: Confidential Green 70


Document No.: 000-EMI2200987-VD-PR Issued: Sandra.Camy (2022-05-30) Checked: Sandra.Camy (2022-05-30) Released: miguel.martins (2022-05-30) Status: AP Revision: 0

ENCLOURE VENTILATION SYSTEM


4D391-149401

12.4.7: GENERATOR-EXHAUST

Caterpillar: Confidential Green 71


Document No.: 000-EMI2200987-VD-PR Issued: Sandra.Camy (2022-05-30) Checked: Sandra.Camy (2022-05-30) Released: miguel.martins (2022-05-30) Status: AP Revision: 0

ENCLOURE VENTILATION SYSTEM


4D391-149401

12.4.7.1: Assembly Details


x Detail 1: Assemble pneumatic damper onto the enclosure roof

x Detail 2: Assemble manual damper onto the pneumatic damper

x Detail 3: Assemble elbow silencer onto the manual damper

x Detail 4: Assemble duct louver vent onto the elbow silencer

x Detail 5: Assemble screen vent onto the duct louver vent

****Assembly details above shall not be considered as installation order. Order of installation may vary based on
integration with support structure, lifting arrangements, access, proper support and general safety guidelines. It is
recommended that the component installation start at the turbine connection and continue outward.****

Note:
1. Ensure support structure installation is aligned and level, and all mating components are aligned prior to installing
flexible elements.

2. Support structure by others and must be erected before any ducts can be installed.

Caterpillar: Confidential Green 72


Document No.: 000-EMI2200987-VD-PR Issued: Sandra.Camy (2022-05-30) Checked: Sandra.Camy (2022-05-30) Released: miguel.martins (2022-05-30) Status: AP Revision: 0

ENCLOURE VENTILATION SYSTEM


4D391-149401

Detail 1:
x Assemble pneumatic damper onto the enclosure roof
x Ensure the correct damper orientation while assembling onto the enclosure

Pneumatic arrangement
should face in this direction

Caterpillar: Confidential Green 73


Document No.: 000-EMI2200987-VD-PR Issued: Sandra.Camy (2022-05-30) Checked: Sandra.Camy (2022-05-30) Released: miguel.martins (2022-05-30) Status: AP Revision: 0

ENCLOURE VENTILATION SYSTEM


4D391-149401

Isolation damper fire connection system:


x The isolation damper and fire suppression system should be internally connected by joining flexible hose assembly
In to the union damper
Top View
Left Side View

Caterpillar: Confidential Green 74


Document No.: 000-EMI2200987-VD-PR Issued: Sandra.Camy (2022-05-30) Checked: Sandra.Camy (2022-05-30) Released: miguel.martins (2022-05-30) Status: AP Revision: 0

ENCLOURE VENTILATION SYSTEM


4D391-149401

Detail 2:
x Assemble manual damper onto the pneumatic damper

Caterpillar: Confidential Green 75


Document No.: 000-EMI2200987-VD-PR Issued: Sandra.Camy (2022-05-30) Checked: Sandra.Camy (2022-05-30) Released: miguel.martins (2022-05-30) Status: AP Revision: 0

ENCLOURE VENTILATION SYSTEM


4D391-149401

Detail 3:
x Assemble elbow silencer onto the manual damper

Caterpillar: Confidential Green 76


Document No.: 000-EMI2200987-VD-PR Issued: Sandra.Camy (2022-05-30) Checked: Sandra.Camy (2022-05-30) Released: miguel.martins (2022-05-30) Status: AP Revision: 0

ENCLOURE VENTILATION SYSTEM


4D391-149401

Detail 4:
x Assemble duct louver vent onto the elbow silencer

Caterpillar: Confidential Green 77


Document No.: 000-EMI2200987-VD-PR Issued: Sandra.Camy (2022-05-30) Checked: Sandra.Camy (2022-05-30) Released: miguel.martins (2022-05-30) Status: AP Revision: 0

ENCLOURE VENTILATION SYSTEM


4D391-149401

Detail 5:
x Assemble screen vent onto the duct louver vent

Caterpillar: Confidential Green 78


Document No.: 000-EMI2200987-VD-PR Issued: Sandra.Camy (2022-05-30) Checked: Sandra.Camy (2022-05-30) Released: miguel.martins (2022-05-30) Status: AP Revision: 0

ENCLOURE VENTILATION SYSTEM


4D391-149401

12.4.7.2 FINAL INSPECTION

x Verify all blocking, shipping braces, tools and other equipment used in the erection of the system have been removed
from the internal areas of the system.

x Ensure that all components have been cleaned inside the air passages.

x Ensure that all transportation tags and labels have been removed.

x Ensure that all parts and surface finish were not damaged during installation.

x Make sure that the Air flow direction indicated on ducts has been followed.

x Ensure that all earth/ground wires are installed for earthing of equipment and bonding between mechanical parts.

x Complete systems must be completely installed, cleaned, inspected, etc.,

x Verify that all drains have been properly connected or plumbed.

x Verify that access doors, if used during the erection of the system have been replaced and securely tightened.

x Perform a random sampling of flange bolts to confirm they are properly tightened. If multiple bolts are found to be
loose on a flange connection, its is recommended to retighten all flange connection nuts.

Caterpillar: Confidential Green 79


Document No.: 000-EMI2200987-VD-PR Issued: Sandra.Camy (2022-05-30) Checked: Sandra.Camy (2022-05-30) Released: miguel.martins (2022-05-30) Status: AP Revision: 0

ENCLOURE VENTILATION SYSTEM


4D391-149401

12.4.8: DRIVER ENCLOSURE AIR INLET

Caterpillar: Confidential Green 80


Document No.: 000-EMI2200987-VD-PR Issued: Sandra.Camy (2022-05-30) Checked: Sandra.Camy (2022-05-30) Released: miguel.martins (2022-05-30) Status: AP Revision: 0

ENCLOURE VENTILATION SYSTEM


4D391-149401

12.4.8.1: Assembly Details

x Detail 1: Assemble pneumatic damper onto the enclosure roof


x Detail 2: Assemble elbow silencer onto the pneumatic damper
x Detail 3: Assemble fan vent onto the elbow silencer
x Detail 4: Assemble vent duct onto the fan vent
x Detail 5: Assemble vent straight duct onto the vent duct
x Detail 6: Assemble vent silencer onto the vent straight duct
x Detail 7: Assemble filter with switch wired onto the vent silencer
x Detail 8: Assemble vent screen onto the filter with switch wired
x Detail 9: Assemble weather louver straight duct onto the vent screen

****Assembly details above shall not be considered as installation order. Order of installation may vary based on
integration with support structure, lifting arrangements, access, proper support and general safety guidelines. It is
recommended that the component installation start at the turbine connection and continue outward.****

Note:

1.Ensure support structure installation is aligned and level, and all mating components are aligned prior to installing
flexible elements.

2.Support structure by others and must be erected before any ducts can be installed.

Caterpillar: Confidential Green 81


Document No.: 000-EMI2200987-VD-PR Issued: Sandra.Camy (2022-05-30) Checked: Sandra.Camy (2022-05-30) Released: miguel.martins (2022-05-30) Status: AP Revision: 0

ENCLOURE VENTILATION SYSTEM


4D391-149401

Detail 1:
x Assemble pneumatic damper onto the enclosure roof
x Ensure the correct damper orientation while assembling onto the enclosure

Pneumatic arrangement
should face in this direction

Caterpillar: Confidential Green 82


Document No.: 000-EMI2200987-VD-PR Issued: Sandra.Camy (2022-05-30) Checked: Sandra.Camy (2022-05-30) Released: miguel.martins (2022-05-30) Status: AP Revision: 0

ENCLOURE VENTILATION SYSTEM


4D391-149401

Isolation damper fire connection system:


x The isolation damper and fire suppression system should be internally connected by joining flexible hose assembly
In to the union damper
Top View
Left Side View

Caterpillar: Confidential Green 83


Document No.: 000-EMI2200987-VD-PR Issued: Sandra.Camy (2022-05-30) Checked: Sandra.Camy (2022-05-30) Released: miguel.martins (2022-05-30) Status: AP Revision: 0

ENCLOURE VENTILATION SYSTEM


4D391-149401

Detail 2:
x Assemble elbow silencer onto the pneumatic damper

Caterpillar: Confidential Green 84


Document No.: 000-EMI2200987-VD-PR Issued: Sandra.Camy (2022-05-30) Checked: Sandra.Camy (2022-05-30) Released: miguel.martins (2022-05-30) Status: AP Revision: 0

ENCLOURE VENTILATION SYSTEM


4D391-149401

Detail 3:
x Assemble fan vent onto the elbow silencer

Hardware and Support


structure by others

Note: Support structure steelwork supporting the fan vent shall be installed prior to installing the other duct. Fan vent shall be placed on
support structure upon initial installation by means of support feature

Caterpillar: Confidential Green 85


Document No.: 000-EMI2200987-VD-PR Issued: Sandra.Camy (2022-05-30) Checked: Sandra.Camy (2022-05-30) Released: miguel.martins (2022-05-30) Status: AP Revision: 0

ENCLOURE VENTILATION SYSTEM


4D391-149401

Detail 4:
x Assemble vent duct onto the fan vent

ISO VIEW 2
(AFT LEFT)

Caterpillar: Confidential Green 86


Document No.: 000-EMI2200987-VD-PR Issued: Sandra.Camy (2022-05-30) Checked: Sandra.Camy (2022-05-30) Released: miguel.martins (2022-05-30) Status: AP Revision: 0

ENCLOURE VENTILATION SYSTEM


4D391-149401

Detail 5:
x Assemble vent straight duct onto the vent duct

ISO VIEW 2
(AFT LEFT)
Hardware and Support
structure by others

Note: Support structure steelwork supporting the vent straight shall be installed prior to installing the other duct. Vent straight shall be
placed on support structure upon initial installation by means of support feature

Caterpillar: Confidential Green 87


Document No.: 000-EMI2200987-VD-PR Issued: Sandra.Camy (2022-05-30) Checked: Sandra.Camy (2022-05-30) Released: miguel.martins (2022-05-30) Status: AP Revision: 0

ENCLOURE VENTILATION SYSTEM


4D391-149401

Detail 6:
x Assemble vent silencer onto the vent straight duct

ISO VIEW 2
(AFT LEFT) Hardware and Support
structure by others
Note: Support structure steelwork supporting the vent silencer shall be installed prior to installing the other duct. Vent straight shall be
placed on support structure upon initial installation by means of support feature

Caterpillar: Confidential Green 88


Document No.: 000-EMI2200987-VD-PR Issued: Sandra.Camy (2022-05-30) Checked: Sandra.Camy (2022-05-30) Released: miguel.martins (2022-05-30) Status: AP Revision: 0

ENCLOURE VENTILATION SYSTEM


4D391-149401

Detail 7:
x Assemble filter with switch wired onto the vent silencer

ISO VIEW 2
(AFT LEFT)

Caterpillar: Confidential Green 89


Document No.: 000-EMI2200987-VD-PR Issued: Sandra.Camy (2022-05-30) Checked: Sandra.Camy (2022-05-30) Released: miguel.martins (2022-05-30) Status: AP Revision: 0

ENCLOURE VENTILATION SYSTEM


4D391-149401

Detail 8:
x Assemble vent screen onto the filter with switch wired

ISO VIEW 2
(AFT LEFT)

Caterpillar: Confidential Green 90


Document No.: 000-EMI2200987-VD-PR Issued: Sandra.Camy (2022-05-30) Checked: Sandra.Camy (2022-05-30) Released: miguel.martins (2022-05-30) Status: AP Revision: 0

ENCLOURE VENTILATION SYSTEM


4D391-149401

Detail 9:
x Assemble weather louver straight duct onto the vent screen

ISO VIEW 2
(AFT LEFT)

Caterpillar: Confidential Green 91


Document No.: 000-EMI2200987-VD-PR Issued: Sandra.Camy (2022-05-30) Checked: Sandra.Camy (2022-05-30) Released: miguel.martins (2022-05-30) Status: AP Revision: 0

ENCLOURE VENTILATION SYSTEM


4D391-149401

12.4.8.2 FINAL INSPECTION

x Verify all blocking, shipping braces, tools and other equipment used in the erection of the system have been removed
from the internal areas of the system.

x Ensure that all components have been cleaned inside the air passages.

x Ensure that all transportation tags and labels have been removed.

x Ensure that all parts and surface finish were not damaged during installation.

x Make sure that the Air flow direction indicated on ducts has been followed.

x Ensure that all earth/ground wires are installed for earthing of equipment and bonding between mechanical parts.

x Complete systems must be completely installed, cleaned, inspected, etc.,

x Verify that all drains have been properly connected or plumbed.

x Verify that access doors, if used during the erection of the system have been replaced and securely tightened.

x Perform a random sampling of flange bolts to confirm they are properly tightened. If multiple bolts are found to be
loose on a flange connection, its is recommended to retighten all flange connection nuts.

Caterpillar: Confidential Green 92


Document No.: 000-EMI2200987-VD-PR Issued: Sandra.Camy (2022-05-30) Checked: Sandra.Camy (2022-05-30) Released: miguel.martins (2022-05-30) Status: AP Revision: 0

ENCLOURE VENTILATION SYSTEM


4D391-149401

12.4.9: DRIVEN ENCLOSURE AIR INLET

Caterpillar: Confidential Green 93


Document No.: 000-EMI2200987-VD-PR Issued: Sandra.Camy (2022-05-30) Checked: Sandra.Camy (2022-05-30) Released: miguel.martins (2022-05-30) Status: AP Revision: 0

ENCLOURE VENTILATION SYSTEM


4D391-149401

12.4.9.1: Assembly Details


x Detail 1: Assemble pneumatic damper onto the enclosure roof
x Detail 2: Assemble elbow silencer onto the pneumatic damper
x Detail 3: Assemble fan vent onto the elbow silencer
x Detail 4: Assemble vent duct onto the fan vent
x Detail 5: Assemble vent straight duct onto the vent duct
x Detail 6: Assemble vent silencer onto the vent straight duct
x Detail 7: Assemble filter with switch wired onto the vent silencer
x Detail 8: Assemble vent screen onto the filter with switch wired
x Detail 9: Assemble weather louver straight duct onto the vent screen

****Assembly details above shall not be considered as installation order. Order of installation may vary based on
integration with support structure, lifting arrangements, access, proper support and general safety guidelines. It is
recommended that the component installation start at the turbine connection and continue outward.****

Note:

1.Ensure support structure installation is aligned and level, and all mating components are aligned prior to installing
flexible elements.

2.Support structure by others and must be erected before any ducts can be installed.

Caterpillar: Confidential Green 94


Document No.: 000-EMI2200987-VD-PR Issued: Sandra.Camy (2022-05-30) Checked: Sandra.Camy (2022-05-30) Released: miguel.martins (2022-05-30) Status: AP Revision: 0

ENCLOURE VENTILATION SYSTEM


4D391-149401

Detail 1:
x Assemble pneumatic damper onto the enclosure roof
x Ensure the correct damper orientation while assembling onto the enclosure

Pneumatic arrangement
should face in this direction

Caterpillar: Confidential Green 95


Document No.: 000-EMI2200987-VD-PR Issued: Sandra.Camy (2022-05-30) Checked: Sandra.Camy (2022-05-30) Released: miguel.martins (2022-05-30) Status: AP Revision: 0

ENCLOURE VENTILATION SYSTEM


4D391-149401

Isolation damper fire connection system:


x The isolation damper and fire suppression system should be internally connected by joining flexible hose assembly
In to the union damper
Top View
Left Side View

Caterpillar: Confidential Green 96


Document No.: 000-EMI2200987-VD-PR Issued: Sandra.Camy (2022-05-30) Checked: Sandra.Camy (2022-05-30) Released: miguel.martins (2022-05-30) Status: AP Revision: 0

ENCLOURE VENTILATION SYSTEM


4D391-149401

Detail 2:
x Assemble elbow silencer onto the pneumatic damper

Caterpillar: Confidential Green 97


Document No.: 000-EMI2200987-VD-PR Issued: Sandra.Camy (2022-05-30) Checked: Sandra.Camy (2022-05-30) Released: miguel.martins (2022-05-30) Status: AP Revision: 0

ENCLOURE VENTILATION SYSTEM


4D391-149401

Detail 3:
x Assemble fan vent onto the elbow silencer

Hardware and Support


structure by others

Note: Support structure steelwork supporting the fan vent shall be installed prior to installing the other duct. Fan vent shall be placed on
support structure upon initial installation by means of support feature

Caterpillar: Confidential Green 98


Document No.: 000-EMI2200987-VD-PR Issued: Sandra.Camy (2022-05-30) Checked: Sandra.Camy (2022-05-30) Released: miguel.martins (2022-05-30) Status: AP Revision: 0

ENCLOURE VENTILATION SYSTEM


4D391-149401

Detail 4:
x Assemble vent duct onto the fan vent

ISO VIEW 2
(AFT LEFT)

Caterpillar: Confidential Green 99


Document No.: 000-EMI2200987-VD-PR Issued: Sandra.Camy (2022-05-30) Checked: Sandra.Camy (2022-05-30) Released: miguel.martins (2022-05-30) Status: AP Revision: 0

ENCLOURE VENTILATION SYSTEM


4D391-149401

Detail 5:
x Assemble vent straight duct onto the vent duct

Hardware and Support


structure by others
ISO VIEW 2
(AFT LEFT)

Note: Support structure steelwork supporting the vent straight shall be installed prior to installing the other duct. Vent straight shall be
placed on support structure upon initial installation by means of support feature

Caterpillar: Confidential Green 100


Document No.: 000-EMI2200987-VD-PR Issued: Sandra.Camy (2022-05-30) Checked: Sandra.Camy (2022-05-30) Released: miguel.martins (2022-05-30) Status: AP Revision: 0

ENCLOURE VENTILATION SYSTEM


4D391-149401

Detail 6:
x Assemble vent silencer onto the vent straight duct

Hardware and Support


structure by others

ISO VIEW 2
(AFT LEFT)

Note: Support structure steelwork supporting the vent silencer shall be installed prior to installing the other duct. Vent silencer shall be
placed on support structure upon initial installation by means of support feature

Caterpillar: Confidential Green 101


Document No.: 000-EMI2200987-VD-PR Issued: Sandra.Camy (2022-05-30) Checked: Sandra.Camy (2022-05-30) Released: miguel.martins (2022-05-30) Status: AP Revision: 0

ENCLOURE VENTILATION SYSTEM


4D391-149401

Detail 7:
x Assemble filter with switch wired onto the vent silencer

ISO VIEW 2
(AFT LEFT)

Caterpillar: Confidential Green 102


Document No.: 000-EMI2200987-VD-PR Issued: Sandra.Camy (2022-05-30) Checked: Sandra.Camy (2022-05-30) Released: miguel.martins (2022-05-30) Status: AP Revision: 0

ENCLOURE VENTILATION SYSTEM


4D391-149401

Detail 8:
x Assemble vent screen onto the filter with switch wired

ISO VIEW 2
(AFT LEFT)

Caterpillar: Confidential Green 103


Document No.: 000-EMI2200987-VD-PR Issued: Sandra.Camy (2022-05-30) Checked: Sandra.Camy (2022-05-30) Released: miguel.martins (2022-05-30) Status: AP Revision: 0

ENCLOURE VENTILATION SYSTEM


4D391-149401

Detail 9:
x Assemble weather louver straight duct onto the vent screen

ISO VIEW 2
(AFT LEFT)

Caterpillar: Confidential Green 104


Document No.: 000-EMI2200987-VD-PR Issued: Sandra.Camy (2022-05-30) Checked: Sandra.Camy (2022-05-30) Released: miguel.martins (2022-05-30) Status: AP Revision: 0

ENCLOURE VENTILATION SYSTEM


4D391-149401

12.4.9.2 FINAL INSPECTION

x Verify all blocking, shipping braces, tools and other equipment used in the erection of the system have been removed
from the internal areas of the system.

x Ensure that all components have been cleaned inside the air passages.

x Ensure that all transportation tags and labels have been removed.

x Ensure that all parts and surface finish were not damaged during installation.

x Make sure that the Air flow direction indicated on ducts has been followed.

x Ensure that all earth/ground wires are installed for earthing of equipment and bonding between mechanical parts.

x Complete systems must be completely installed, cleaned, inspected, etc.,

x Verify that all drains have been properly connected or plumbed.

x Verify that access doors, if used during the erection of the system have been replaced and securely tightened.

x Perform a random sampling of flange bolts to confirm they are properly tightened. If multiple bolts are found to be
loose on a flange connection, its is recommended to retighten all flange connection nuts.

Caterpillar: Confidential Green 105

You might also like