You are on page 1of 37

ALBRECHT Reinhold CASSET Sebastien

Internal comments
D 2012-01-13 FIN taken into account STURM Jochen

MODIFICATIONS /
REV. DATE AUTHOR CHECKED BY STATUS APPROVED BY
OBSERVATIONS

Olkiluoto 3 NPP
CONFIDENTIAL as defined under the Olkiluoto 3 Plant Contract

SIEMENS
Jochen STURM FSS 2012-01-23

CONSORTIUM : WORK PACKAGE

AREVA NP NI-4-7500
SIEMENS AG OL3 KKS
Project Code FIN005
-

TITLE:

Test Instruction
for pretest on the motorized valves with URSULA box
N
ECCN:

DOCUMENT KIND : DCC : CONFIDENTIALITY :

Commissioning Instruction EDC RESTRICTED


N
AL:

AREVA NP FSM FSS DC 0427


Name of the issuing company COMPANY CODE DOCUMENT NUMBER

The reproduction, transmission or use of this document or its contents is not permitted without express written authority. Offenders will be liable for damages. All rights,
including rights created by patent grant or registration of a utility model or design, are reserved.
Goods labeled with "AL not equal to N" are subject to European or German export authorization when being exported out of the EU. Goods labeled with "ECCN not
equal to N" are subject to US reexport authorization. Even without a label, or with label "AL:N" or "ECCN:N", authorization may be required due to the final whereabouts
and purpose for which the goods are to be used.
The original version of this document is stored in electronic form in the AREVA NP-EDM system. The current status of this document can be viewed only in the EDM
system.
2006.04 ANP 2268
Document type

Commissioning Instruction
Class Number of pages 37
RESTRICTED Number of appendices 3

Document Title

Test Instruction
for pretest on the motorized valves with URSULA box

Short Title

ALBRECHT CASSET Sebastien STURM Jochen


Reinhold Internal comments taken into
D 2012-01-13 FIN
account

CASSET Sebastien ALBRECHT STURM Jochen


Reinhold Internal comments taken into
C 2011-09-28 FIN
account

CASSET Sebastien ALBRECHT STURM Jochen


Reinhold Internal comments taken into
B 2011-09-05 FIN
CHALET Jerome account

ALBRECHT
A 2011-08-15 CASSET Sebastien ReinholdCHALET First issue FIN STURM Jochen
Jerome

Rev Date Author Checked by Modifications / Observations Status Approved by

Contract :
Project FIN005
FSS DC 0427
File code -
No EOTP:

Subdivision INTERNAL IDENTIFICATION NUMBER

This document is the property of AREVA NP.


It must not be used reproduced, transmitted or disclosed without the prior written permission of AREVA NP.
2006.04 ANP 0313
Project OL3 N° ° FSS DC 0427
Confidentiality:
RESTRICTED REV. D 3 / 29

REVISIONS

IND STATUS
PARAGRAPH SCOPE OF THE REVISION
REV DATE

A 2011-08-15 First issue

B Internal comments taken into account


CONFIDENTIAL as defined under the Olkiluoto 3 Plant Contract

2011-09-05

3 Modification of prerequisites

4.2 English mistake

7 Modification of tasks

7, 8.1 Completed by “I&C” or “Commissioning”

Abbreviation, 7 Add the qualification of the I&C personnal

8.3.1, 8.3.2, 8.3.3 New instructions

C 2011-09-28 Internal comments taken into account

2, 8.3.1, 8.3.2, 8.3.3,


Precision on the criteria
8.3.4, App. A

1.2, 8.2, App. A Add verification before test

1.3, 8.3.1, 8.3.2,


Precision on the methods of work
8.3.3
N
ECCN:
N
AL:
Project OL3 N° ° FSS DC 0427
Confidentiality:
RESTRICTED REV. D 4 / 29

IND STATUS
PARAGRAPH SCOPE OF THE REVISION
REV DATE

D 2012-01-13 Internal comments taken into account

SUMMARY Procedure is valid for AUMA actuators, only

ABBREVIATIONS AUMA
CONFIDENTIAL as defined under the Olkiluoto 3 Plant Contract

REFERENCES New documents added

1.3 deleted

2 Additional note after the table was deleted

3 Delete of sentence “PTW is ready to start test”

Additional information for AUMA actuators added

Replace “Safety analysis” versus “Risk assessment”

Information added when adjustment of limit switches


is authorized

Correction and additional information regarding


6
multimeter
N

7 Sentence “Inviting TVO/STUK for…” deleted


ECCN:

Replace “Safety analysis” versus “Risk assessment”;


additional link to dedicated documents regarding
N

‘Risk Assessment” before and after ECC


AL:

Update of qualification to adjust limit switch for


AUMA actuators

8.3 Several modifcations

Appendix A Chapter “INTRODUCTION” removed


Project OL3 N° ° FSS DC 0427
Confidentiality:
RESTRICTED REV. D 5 / 29

SUMMARY

The target of this test instruction is to make a pretest on motorized valves with the URSULA box
where AUMA actuators according to [1] and [2] are used. That allows to anticipate the setting of
switches and verification of the wiring of valves and the running time of the stroke.
This TI is an internal documentation, useful for the preparation of SCI52 NI [3].

KEY WORDS
CONFIDENTIAL as defined under the Olkiluoto 3 Plant Contract

OL3, test instruction, URSULA, limit switch, torque switch, valve, overrun.

ABBREVIATIONS
AUMA Company AUMA
CDS Commissioning Document Sheet
CI Commissioning Instruction
CIRVAR Variants for Command Termination and Check back Signal processing of
Actuators
CRR Commissioning Result Report
DSV Data Sheet Valve
EOMR End Of Manufacturing Report
EPT Electronic Position Transmitter
ESP Electrical Skilled Person
FG Functional Group
HW Hardware
I&C Instrumentation and Control
LS Limit Switch
MCR Main Control Room
PACS Priority and Actuation Control System
N

PAS Process Automation System


ECCN:

PI Panel Interface to SICS


PICS Process Information and Control System
N

PLC Programmable Logic Control


AL:

RRS Result Record Sheet


SAS Safety Automation System
SCI Standard Commissioning Instruction
SCP System Commissioning Program
SICS Safety Information and Control System
SWGR Switchgear
TI Test Instruction
TS Torque switch
TXP TELEPERM XP
TXS TELEPERM XS
Project OL3 N° ° FSS DC 0427
Confidentiality:
RESTRICTED REV. D 6 / 29

URSULA German: Universalsteuerung für Regel- und Stellantriebe mit Umschaltbarer


Laufrichtung und Absteuervariante
English: Universal Multi Control Unit for Control- and Regulatory actuators
with Reversible running direction and Control variants
CONFIDENTIAL as defined under the Olkiluoto 3 Plant Contract
N
ECCN:
N
AL:
Project OL3 N° ° FSS DC 0427
Confidentiality:
RESTRICTED REV. D 7 / 29

TABLE OF CONTENTS

0. REFERENCES 8

1. INTRODUCTION 9
1.1. Objectives 9
1.2. Methods 9
1.3. Definition 9
CONFIDENTIAL as defined under the Olkiluoto 3 Plant Contract

2. ACCEPTANCE CRITERIA 10

3. PREREQUISITES FOR TEST PERFORMANCE 10

4. SPECIAL PRECAUTIONS 11
4.1. Safety Requirements 11
4.2. Security of Equipment 11
4.3. Provisions 11

5. INITIAL STATUS 12

6. LIST OF INSTRUMENTATION AND SPECIAL TEST EQUIPMENT 13

7. ORGANIZATIONAL MEASURES 14

8. INSTRUCTIONS 16
8.1. Requirement 16
8.2. Test preparation 16
8.3. Test of valves with URSULA box 18
8.4. Restoration of test of valve 27
N

9. APPENDICES 28
ECCN:
N

LIST OF APPENDICES
AL:

Appendix A: RESULT RECORD SHEETS A1

Appendix B: summary of needs to prepare the test B1

Appendix C: Example of SCI52’s RSS to be used C1

LIST OF FIGURES

Figure 1: Example of SCI52’s RSS to be used 2


Project OL3 N° ° FSS DC 0427
Confidentiality:
RESTRICTED REV. D 8 / 29

0. REFERENCES

N°. Title Coding Rev. Date

[1] Operation and Maintenance Manuals – SAI valve AUMA-TVO3-DOK20-SAI B 2006-10-16


Operation and Maintenance Manuals – SAN AUMA-TVO3-DOK20-SAN
[2] A 2005-11-15
valve
SCI: Commissioning of the control section of the NL-G/2007/en/1004
CONFIDENTIAL as defined under the Olkiluoto 3 Plant Contract

[3] switchgear feeders, motors, actuators and H 2011-04-23


control valves (SCI52 NI)
[4] Actuator Control Concept DR2.4.07 E 2010-12-08
Installation Instruction for AUMA SAI actuator 5298 INS 012
[5] D 2010-08-09
type
[6] Definition of the Valve Specification PEEO-G/2010/en/1003 C 2011-05-03
PI 20.06: HSE Method Statement / Risk FSM DC 0110
[7] A 2011-07-04
Assessment for commissioning
[8] KKS – Catalogue of valves FSF DC 0512 D 2011-08-04
Technical Data Sheet – AUMA – worm AUMA-TVO3-DOK5-GSI
[9] B 2007-12-07
gearboxes
SI 13.12 Site Instruction Management of Risk FSH DC 0024
[10] and Risk Change in plant areas and rooms A 2011-09-21
before and after ECC
[11] KKS-Catalogue of valves FSF DC 0512 D 2011-04-18
N
ECCN:
N
AL:
Project OL3 N° ° FSS DC 0427
Confidentiality:
RESTRICTED REV. D 9 / 29

1. INTRODUCTION

1.1. Objectives
The test objective is to make a pretest to anticipate the motorized valves and dampers
commissioning with AUMA actuators before the SCI 52 NI [3].
The test verifies correct implementation and completeness of:
• Direction of rotation
• Adjustment of limit switches
CONFIDENTIAL as defined under the Olkiluoto 3 Plant Contract

• Torque setting
• Running time
• Remote indication (if used)

1.2. Methods
Before the test, the RRS must be prepared according to the parameters of the valve (KKS,
CIVAR etc). The coherence of these parameters must be checked with appropriated
documents.
For each valve tested, the URSULA box is directly connected to the valve. This tool replace the
power supply, the main control room and the I&C.
The URSULA box is used to adjust the limit switches and to verify the movement.
This procedure includes four tests:
- Actuator with command termination on torque switch (TS) in both directions
- Actuator with command termination on limit switch (LS) in both direction
- Actuator with command termination on torque switch (TS) in closed position and
command termination on limit switch (LS) n open position
- Set up the remote position (if used)
N

Note: According to the valve’s CIRVAR only one of three first tests is used
ECCN:

For each valve the command termination is taken into account (CIRVAR in [4] and “CMD term.
VAR” on RRS)
N
AL:

1.3. Definition
Overrun: Distance traveled after engine shutdown due to time delay of the PLC length of signal
path and inertia of masses in movement.
Project OL3 N° ° FSS DC 0427
Confidentiality:
RESTRICTED REV. D 10 / 29

2. ACCEPTANCE CRITERIA

Kind Measured parameter / Acceptance criteria


(O/S)
Characteristic Checked

- In accordance with the Data


Direction of rotation
Sheet Valve
- In accordance with the Data
Adjustment of limit switch
CONFIDENTIAL as defined under the Olkiluoto 3 Plant Contract

Sheet Valve
- In accordance with the Data
Torque settings (label)
Sheet Valve
- Running time In accordance with the Data
Sheet Valve
- Remote indication (if used) In accordance with the Data
Sheet Valve

3. PREREQUISITES FOR TEST PERFORMANCE

Following prerequisites must be fulfilled prior to starting

• The body of the valve is clean


• The pressure test is done
• The insulation test is done on the actuator winding (certificate)
• The URSULA box is not connected to the valve
• It has to take into account the initial status of the system (with or without fluid) and the
working conditions for safe operation (consider of blocking fro process isolation)
• Risk assessment is ready to start the test ([7] and [10]).
N

• Temporary power supply is ready to start the test. Every features of power supply are
ECCN:

take into account (400 Vac / 63 A)


• Every manipulate part of valve must be accessible, else ensure a safe access (e. g.
scaffolding)
N
AL:

• The RRS of the tested valve has to be ready (expected values known)
• For dedicated types of valve, the closing and opening movements have to be carried out
under fluid conditions. Refer to the Data Sheet Valve
• AUMA actuator according to [1] and [2] is used
• Adjustment of limit switches for AUMA actuator is possible as long as it is authorized by
the installation instructions. By the document KKS-Catalogue of valve [11] the link to the
installation instruction for each valve is available (Batch2-ID).
Project OL3 N° ° FSS DC 0427
Confidentiality:
RESTRICTED REV. D 11 / 29

4. SPECIAL PRECAUTIONS

4.1. Safety Requirements

# Requirement

Electrical Clearance
1
Test Personnel shall be able to identify the location of main power.
Electrical Protection/Shock
a. 24VDC and 48VDC are present inside the URSULA box and personnel
CONFIDENTIAL as defined under the Olkiluoto 3 Plant Contract

2 shall exercise caution.


b. High voltage (400 V) is present in the URSULA box and personnel should
have the correct habilitation.
Mechanical
Mechanical part in motion, the personnel shall exercise caution (spindle)
3
Note: Handwheel is automatically disengaged when the actuator starts up.
Handwheel doesn’t rotate when the motor is running

4.2. Security of Equipment


# Requirement
Some types of valve have to be manipulated in fluid. Refer to the Data Sheet
1
Valve

2 Valves shall be operate by/with a qualified technical personnel

Operating the change-over lever while the motor is running can lead to
3
increased wear at the change-over mechanism (see [2] § 6)
N

4.3. Provisions
ECCN:

# Requirement
N

1 For each valve, prepare the test with their “Data Valve Sheet”
AL:
Project OL3 N° ° FSS DC 0427
Confidentiality:
RESTRICTED REV. D 12 / 29

5. INITIAL STATUS

KKS Description State

Available
- Valve For the relevant valves, the pipes are filled in
water
CONFIDENTIAL as defined under the Olkiluoto 3 Plant Contract
N
ECCN:
N
AL:
Project OL3 N° ° FSS DC 0427
Confidentiality:
RESTRICTED REV. D 13 / 29

6. LIST OF INSTRUMENTATION AND SPECIAL TEST EQUIPMENT

Quantity Type Range Accuracy

1 URSULA box (with its cable) - -


1 Cable for power supply 30m / 400 Vac / 63 A -
1 Tool box (screw driver …) - -
1 Multi-meter 0-600 V (AC/DC) 0.1 % of MR
CONFIDENTIAL as defined under the Olkiluoto 3 Plant Contract

1 Lamp - -
- Grease (white Vaseline) Non acidic
N
ECCN:
N
AL:
Project OL3 N° ° FSS DC 0427
Confidentiality:
RESTRICTED REV. D 14 / 29

7. ORGANIZATIONAL MEASURES

These operations are done under erection activities because ECCs are not signed.
The responsibilities of the operation (during the preparation, during the test, after the test) are
shared between the I&C commissioning team and the system commissioning team:
• The I&C commissioning team is in charge of:
- Preparing the SCI52 RRS of the valve (validity of the criteria)
- Preparing all the needs for the test (URSULA box, power supply cables to be
requested to the Intervention group, tools …)
CONFIDENTIAL as defined under the Olkiluoto 3 Plant Contract

- The validation of the results


The I&C commissioning team is responsible to support the System Commissioning
engineer

• The Commissioning system team is in charge of:


- Checking that the SCI52 RRS for the valve tested is available and completed with
the expected values
- Checking that the valve can be tested without fluid
- Preparing the test environment, accessibilities, scaffolding etc. (contact intervention
group).
- Check the availability of the EOMR for the valve to be tested
- Preparing the risk assessment with the support of the FG safety office ([7] and [10])
and organizing on spot the appropriate measures.
The commissioning system team is responsible of the test

Note: Find a summary in Appendix B concerning data, features, document of valves useful for
the preparation of the test and during the test
N
ECCN:
N
AL:
Project OL3 N° ° FSS DC 0427
Confidentiality:
RESTRICTED REV. D 15 / 29

For the performance of the test the following number of workers is needed:
• 1 technician with the URSULA box knowledge performing orders on the box.
• 1 I&C Commissioning Engineer / technician with valve knowledge to adjust limit switch
(with the qualification SFS 6002, AUMA certificate and ESP).
• 1 System Commissioning Engineer / technician from the FG owner of the valve
Note : When the I&C Engineers / technician and System Engineers / technicians shall be
qualified to use the URSULA box, the team in charge of the test valve will be reduce to 2
persons (I&C Engineer/technician and System Commissioning Engineer/technician)
CONFIDENTIAL as defined under the Olkiluoto 3 Plant Contract
N
ECCN:
N
AL:
Project OL3 N° ° FSS DC 0427
Confidentiality:
RESTRICTED REV. D 16 / 29

8. INSTRUCTIONS

8.1. Requirement

# Requirement

1. Verify all test personnel have completed the signature log

2. Verify all test equipment has been recorded in result record sheet
CONFIDENTIAL as defined under the Olkiluoto 3 Plant Contract

3. Verify all prerequisites are completed and recorded

4. Test incidents shall be identified, disposed and reported

The I&C commissioning engineer is in charge to take appropriate measures in


5. case of findings. He determines on the acceptable test suspension and suitable
troubleshooting processes
Verify all steps are appropriately initialed/signed and dated. I&C manager has to
6. approve each RRS

7. Collect the result of erection tests (insulation test, cleaning, pressure test)
According to the CIRVAR of the valve, use the test associated ( to 8.3.1 or 8.3.2
8. or 8.3.3)
Attention: CIRVAR is very important to prepare the URSULA box
According to the EPT used, use the § 8.3.4.1 for “Poti” or § 8.3.4.2 for “4-20
9. mA”

8.2. Test preparation


N

Step # Step Description


ECCN:

In office
Prepare the RRS according to the data sheet valve (KKS in each pages,
N

1
in/out fluid, CIRVAR and EPT)
AL:

Check the coherence of parameters (e.g. stroke time, CIRVAR) between the
2
SCI52’s RRS and DSV the Technical Data Sheet (see [9])
3 In case of discrepancies, report to the System Commissioning Engineer

On site
Conduct a Pre-job Brief
4
(including information about the special precautions (see §4)
5 Ensure that the valve is accessible

6 The URSULA box is energized


Project OL3 N° ° FSS DC 0427
Confidentiality:
RESTRICTED REV. D 17 / 29

Step # Step Description

7 Take into account the risk assessment ([7] and [10])


Before to start the test, control the parameters on the valve’s steel plate:
- KKS of actuator (has to be the same of KKS of valve)
- KKS of valve (has to be the same of KKS of valve)
8
- Type of actuator and speed (e.g. SAN07.1-32)
- Type of gearbox (e.g. GSI80.3)
CONFIDENTIAL as defined under the Olkiluoto 3 Plant Contract

And fill out the RRS


Compare these parameters with the parameters expected in the Data Sheet
9
Valve
10 In case of findings record them on RRS
N
ECCN:
N
AL:
Project OL3 N° ° FSS DC 0427
Confidentiality:
RESTRICTED REV. D 18 / 29

8.3. Test of valves with URSULA box


The single test steps are in detail specified in Appendix A: Result Record Sheet (RRS). The
general description is listed below.

8.3.1. Actuator termination command TS (both direction): CIRVAR 01x [4]


With this kind of configuration, the LS is set that it is activated before the TS.
If TS is activated before LS the system will considerate a failure.
CONFIDENTIAL as defined under the Olkiluoto 3 Plant Contract

Step # Step Description

1 Open the switch compartment and the connection compartment


Before the first movement, check and note the position of the valve. At the end of the test, the
2 valve must be placed into this position

3 Connect the URSULA box

Setup of the URSULA box (Default setting)

In the URSULA box, choose the menu “Default setting” and for each features (Control variant,
4 Actuator protection and EPT type) choose the correct parameter (found in DSV)
Control Variant: Choose the type of valve, CIRVAR 01x
5 Note: With this information, URSULA stops the valve properly according to the command
termination and avoid to destroy the valve
Actuator Protection: Choose “Yes”
6
URSULA box can detect whether an actuator protection is present
EPT type: Choose the type of EPT (“Poti” or “4-20 mA”)
7 Be careful, it’s possible to destroy the “Poti” if you choose “4-20 mA”. “Poti” works with 1V
and “4-20 mA” works with 24 V
Basic test (Switch test)

8 Turn handwheel until valve is in intermediate position


N
ECCN:

In the switch compartment, check the setup of the torque switch, note on RRS (criteria) and
9 compare it with the data in the DSV. If the values do not match, report but don’t setup the
torque by yourself!
In the switch compartment, activate manually limit switch and torque switch :
N

- Limit switch open


AL:

- Limit switch close


10 - Torque switch open
- Torque switch close
and check the signal on the URSULA box
Setup end position CLOSED in “Tip mode” (inching mode)
With the URSULA box, perform CLOSE command in inching mode.
11 Check correct direction of control action (criteria) and activate torque close contact during
closing but before travel limit is reached
12 Check that valve stopped due to activation of the torque switch

13 In manual, turn handwheel clockwise until valve is closed


Project OL3 N° ° FSS DC 0427
Confidentiality:
RESTRICTED REV. D 19 / 29

Step # Step Description


Upon reaching the final position, turn back the handwheel by approximately ½ of turn.
14 Take into account the clearance of the handwheel
Check the limit switch close (change of state) and fill out the RRS (criteria). If it doesn’t match
15 continue in step 16, else continue in step 19

16 Adjust the limit switch close according to [1] § 9 or [2] § 9 and add a note in RRS

17 In manual, open the valve in the intermediate position


CONFIDENTIAL as defined under the Olkiluoto 3 Plant Contract

18 In manual, close the valve and check on the URSULA box the change of state of the LS

Setup end position OPEN in “Tip mode” (inching mode)


With the URSULA box, perform OPEN command in inching mode
Check correct direction of control action (criteria) and activate torque open contact during
19 opening but before travel limit is reached (travel limit can be check with the graduate on the
valve)
20 Check that valve stopped due to activation of the torque switch

21 In manual, turn handwheel counterclockwise until valve is open

Upon reaching the final position, turn back the handwheel by approximately ½ of turn.
22 Take into account of the clearance of the handwheel
Check the limit switch open (change of state) and fill out the RRS (criteria). If it doesn’t match
23
continue in step 24, else continue in step 27

24 Adjust the limit switch open according to [1] § 9 or [2] § 9 and add a note in RRS

25 In manual, close the valve in the intermediate position

26 In manual, open the valve and check on the URSULA box the change of state of the LS

Checking of setting in automatic mode


N

With the URSULA box, perform CLOSE command and check correct command termination
27 by the corresponding switch (LS first and TS second). If the TS is activated before LS, correct
ECCN:

the setting of the LS according to step 16 to 18


With the URSULA box, perform OPEN command and check correct command termination by
28 the corresponding switch (LS first and TS second). If the TS is activated before LS, correct
N

the setting of the LS according to step 24 to 26


AL:

Setup the remote indication

29 This is an option, if used see 8.3.4 (remote position indication)

Checking of running time in automatic mode

The valve is fully open


30
With the URSULA box, perform CLOSE command

31 Compare the measuring result of URSULA box with the required running time (referenced in
the “data sheet valve”)
The valve is fully closed
32
With the URSULA box, perform OPEN command
Project OL3 N° ° FSS DC 0427
Confidentiality:
RESTRICTED REV. D 20 / 29

Step # Step Description

33 Compare the measuring result of URSULA box with the required running time (referenced in
the “data sheet valve”)
34 Fill out the RRS (criteria) and sign

35 Restoration of the state of the valve according to 8.4


CONFIDENTIAL as defined under the Olkiluoto 3 Plant Contract
N
ECCN:
N
AL:
Project OL3 N° ° FSS DC 0427
Confidentiality:
RESTRICTED REV. D 21 / 29

8.3.2. Actuator termination command on LS (both direction): CIRVAR 02x [4]


With this kind of configuration, the LS is set that the TS is never activated.
TS is used only as a “Protective Overlay”

Step # Step Description

1 Open the switch compartment and the connection compartment


CONFIDENTIAL as defined under the Olkiluoto 3 Plant Contract

Before the first movement, check and note the position of the valve. At the end of the test, the
2 valve must be placed into this position

3 Connect the URSULA box

Setup of the URSULA box (Default setting)


In the URSULA box, choose the menu “Default setting” and for each features (Control variant,
4 Actuator protection and EPT type) choose the correct parameter (found in DSV)
Control Variant: Choose the type of valve, CIRVAR 02x
5 Note: With this information, URSULA stops the valve properly according to the command
termination and avoid to destroy the valve
Actuator Protection: Choose “Yes”
6
URSULA box can detect whether an actuator protection is present
EPT type: Choose the type of EPT (“Poti” or “4-20 mA”)
7 Be careful, it’s possible to destroy the “Poti” if you choose “4-20 mA”. “Poti” works with 1V
and “4-20 mA” works with 24 V
Basic test (Switch test)

8 Turn handwheel until valve is in intermediate position


In the switch compartment, check the setup of the torque switch, note on RRS (criteria) and
9 compare it with the data in the DSV. If the values do not match, report but don’t setup the
torque by yourself!
In the switch compartment, activate manually limit switch and torque switch :
- Limit switch open
N

- Limit switch close


10
ECCN:

- Torque switch open


- Torque switch close
and check the signal on the URSULA box
N

Setup end position CLOSED in “Tip mode” (inching mode)


AL:

With the URSULA box, perform CLOSE command in inching mode.


11 Check correct direction of control action (criteria) and activate torque close contact during
closing but before travel limit is reached
12 Check that drive stops and measure the overrun

13 In manual, turn handwheel clockwise until valve is closed


Upon reaching the final position, turn back the handwheel by the amount equal to the overrun
14 + approximately ½ of turn.
Take into account the clearance of the handwheel
Check the limit switch close (change of state) and fill out the RRS (criteria). If it doesn’t match
15 continue in step 16, else continue in step 19

16 Adjust the limit switch close according to according to [1] § 9 or [2] § 9 and add a note in RRS
Project OL3 N° ° FSS DC 0427
Confidentiality:
RESTRICTED REV. D 22 / 29

Step # Step Description

17 In manual, open the valve in the intermediate position

18 In manual, close the valve and check on the URSULA box the change of state of the LS

Setup end position OPEN in “Tip mode” (inching mode)


With the URSULA box, perform OPEN command in inching mode.
Check correct direction of control action (criteria) and activate torque open contact during
19
CONFIDENTIAL as defined under the Olkiluoto 3 Plant Contract

opening but before travel limit is reached (travel limit can be check with the graduate on the
valve)
20 Check that drive stops and measure the overrun

21 In manual, turn handwheel counterclockwise until valve is open


Upon reaching the final position, turn back the handwheel by the amount equal to the overrun
22 + approximately ½ of turn.
Take into account of the clearance of the handwheel
Check the limit switch open (change of state) and fill out the RRS (criteria). If it doesn’t match
23 continue in step 24, else continue in step 27

24 Adjust the limit switch open according to [1] § 9 or [2] § 9 and add a note in RRS

25 In manual, close the valve in the intermediate position

26 In manual, open the valve and check on the URSULA box the change of state of the LS

Checking of setting in automatic mode


With the URSULA box, perform CLOSE command and check correct command termination
27 by the corresponding switch (by the LS). If the TS is activated, correct the setting of the LS
according to step 16 to 18
With the URSULA box, perform OPEN command and check correct command termination by
28 the corresponding switch (by the LS). If the TS is activated, correct the setting of the LS
according to step 24 to 26
N

Setup the remote indication


ECCN:

29 This is an option, if used see 8.3.4 (remote position indication)


N

Checking of running time in automatic mode


AL:

The valve is fully open


30
With the URSULA box, perform CLOSE command

31 Compare the measuring result of URSULA box with the required running time (referenced in
the “data sheet valve”)
The valve is fully closed.
32
With the URSULA box, perform OPEN command

33 Compare the measuring result of URSULA box with the required running time (referenced in
the “data sheet valve”)
34 Fill out the RRS (criteria) and sign
Project OL3 N° ° FSS DC 0427
Confidentiality:
RESTRICTED REV. D 23 / 29

Step # Step Description

35 Restoration of the state of the valve according to 8.4


CONFIDENTIAL as defined under the Olkiluoto 3 Plant Contract
N
ECCN:
N
AL:
Project OL3 N° ° FSS DC 0427
Confidentiality:
RESTRICTED REV. D 24 / 29

8.3.3. Actuator termination command on TS for closed position and LS for opened
position: CIRVAR 03x

Step # Step Description

1 Open the switch compartment and the connection compartment

Before the first movement, check and note the position of the valve. At the end of the test, the
2 valve must be placed into this position
CONFIDENTIAL as defined under the Olkiluoto 3 Plant Contract

3 Connect the URSULA box

Setup of the URSULA box (Default setting)


In the URSULA box, choose the menu “Default setting” and for each features (Control variant,
4 Actuator protection and EPT type) choose the correct parameter (found in DSV)
Control Variant: Choose the type of valve, CIRVAR 03x
5 Note: With this information, URSULA stops the valve properly according to the command
termination and avoid to destroy the valve
Actuator Protection: Choose “Yes”
6
URSULA box can detect whether an actuator protection is present
EPT type: Choose the type of EPT (“Poti” or “4-20 mA”)
7 Be careful, it’s possible to destroy the “Poti” if you choose “4-20 mA”. “Poti” works with 1V
and “4-20 mA” works with 24 V
Basic test (Switch test)

8 Turn handwheel until valve is in intermediate position


In the switch compartment, check the setup of the torque switch, note on RRS (criteria) and
9 compare it with the data in the DSV. If the values do not match, report but don’t setup the
torque by yourself!
In the switch compartment, activate manually limit switch and torque switch :
- Limit switch open
- Limit switch close
10 - Torque switch open
N

- Torque switch close


ECCN:

and check the signal on the URSULA box


Setup end position CLOSED in “Tip mode” (inching mode)
N

With the URSULA box, perform CLOSE command in inching mode.


11 Check correct direction of control action (criteria) and activate torque close contact during
AL:

closing but before travel limit is reached


12 Check that valve stopped due to activation of the torque switch

13 In manual, turn handwheel clockwise until valve is closed


Upon reaching the final position, turn back the handwheel by approximately ½ of turn.
14 Take into account the clearance of the handwheel
Check the limit switch close (change of state) and fill out the RRS (criteria). If it doesn’t match
15 continue in step 16, else continue in step 19

16 Adjust the limit switch close according to [1] § 9 or [2] § 9) and add a note in RRS

17 In manual, open the valve in the intermediate position


Project OL3 N° ° FSS DC 0427
Confidentiality:
RESTRICTED REV. D 25 / 29

Step # Step Description

18 In manual, close the valve and check on the URSULA box the change of state of the LS

Setup end position OPEN in “Tip mode” (inching mode)


With the URSULA box, perform OPEN command in inching mode.
Check correct direction of control action (criteria) and activate torque open contact during
19 opening but before travel limit is reached (travel limit can be check with the graduate on the
valve)
CONFIDENTIAL as defined under the Olkiluoto 3 Plant Contract

20 Check that drive stops and measure the overrun

21 In manual, turn handwheel counterclockwise until valve is open


Upon reaching the final position, turn back the handwheel by the amount equal to the overrun
22 + approximately ½ of turn.
Take into account of the clearance of the handwheel
Check the limit switch open (change of state) and fill out the RRS (criteria). If it doesn’t match
23
continue in step 24, else continue in step 27

24 Adjust the limit switch open according to [1] § 9 or [2] § 9) and add a note in RRS

25 In manual, close the valve in the intermediate position

26 In manual, open the valve and check on the URSULA box the change of state of the LS

Checking of setting in automatic mode


With the URSULA box, perform CLOSE command and check correct command termination
27 by the corresponding switch (LS first and TS second). If the TS is activated, correct the
setting of the LS according to step 16 to 18
With the URSULA box, perform OPEN command and check correct command termination by
28 the corresponding switch (by the LS). If the TS is activated, correct the setting of the LS
according to step 24 to 26
Setup the remote indication
N

29 This is an option, if used see 8.3.4 (remote position indication)


ECCN:

Verification of running time in automatic mode


N

The valve is fully open


30
AL:

With the URSULA box, perform CLOSE command

31 Compare the measuring result of URSULA box with the required running time (referenced in
the “data sheet valve”)
The valve is fully closed
32
With the URSULA box, perform OPEN command

33 Compare the measuring result of URSULA box with the required running time (referenced in
the “data sheet valve”)
34 Fill out the RRS (criteria) and sign

35 Restoration of the state of the valve according to 8.4


Project OL3 N° ° FSS DC 0427
Confidentiality:
RESTRICTED REV. D 26 / 29

8.3.4. Set up the remote position


The remote indication can be used to know the position of the valve. There are existing two
technologies to realize this function.
According to these technologies use the appropriate set up.
8.3.4.1. Setting the potentiometer (Poti)

Step # Step Description


CONFIDENTIAL as defined under the Olkiluoto 3 Plant Contract

1 Move the valve to the end position CLOSED


Turn potentiometer “0” (the big one) clockwise to the stop
2 End position CLOSED correspond to 0%, end position OPEN to 100%

3 Turn potentiometer back a little.

4 Perform fine-tuning of the 0 point at external setting potentiometer (for remote indication)

5 Fill out the RRS (criteria) and sign

8.3.4.2. Setting the electronic position transmitter RWG (4-20 mA)

Step # Step Description

1 Move the valve to the end position CLOSED


Turn potentiometer “0” (the big one) for SAN actuator or the spindle for SAI actuator*
2 clockwise to the stop

3 Turn potentiometer back a little (not for SAI actuator).


N
ECCN:

4 Turn potentiometer “0” clockwise until output current starts to increase


Turn potentiometer “0” back until the value 1.6 % is reached on the URSULA panel.
5 This ensured that the signal remains above the dead and live zero point
N

6
AL:

Move the valve to end position OPEN

7 Set potentiometer “MAX” to end value 100%


Approach end position CLOSED anew and check minimum value (1.6%). If necessary,
8 correct the setting

9 Fill out the RRS (criteria) and sign

* For more details see documents [1] or [2] § 13 and 14


Project OL3 N° ° FSS DC 0427
Confidentiality:
RESTRICTED REV. D 27 / 29

8.4. Restoration of test of valve

Step # Step Description

1 Remove the URSULA box plugs from the electrical connection


CONFIDENTIAL as defined under the Olkiluoto 3 Plant Contract

In manual, place the valve in position measured in 8.3.1 or 8.3.2


2
or 8.3.3 step 2

3 Close the switch compartment (according [1] or [2])

4 Close the electrical compartment (according [1] or [2])


N
ECCN:
N
AL:
Project OL3 N° ° FSS DC 0427
Confidentiality:
RESTRICTED REV. D 28 / 29

9. APPENDICES

Appendix A: RESULT RECORD SHEETS A1


Appendix B: summary of needs to prepare the test B1
Appendix C: Example of SCI52’s RSS to be used C1
CONFIDENTIAL as defined under the Olkiluoto 3 Plant Contract
N
ECCN:
N
AL:
Project OL3 N° ° FSS DC 0427
Confidentiality:
RESTRICTED REV. D Page A1 of A5
CONFIDENTIAL as defined under the Olkiluoto 3 Plant Contrac

APPENDIX A: RESULT RECORD SHEETS


Pretest on the valve with URSULA box
N
ECCN:
N
AL:
Project OL3 N° ° FSS DC 0427
Confidentiality:
RESTRICTED REV. D Page A2 of A5

RESULT RECORD SHEET

SIEMENS Project : Olkiluoto 3 NPP


TI Pretest on the
Appendix A Valve: Pretest with URSULA
valve
TI App. System/SCP KKS Task
CONFIDENTIAL as defined under the Olkiluoto 3 Plant Contrac

IDENTIFICATION OF TEST EQUIPMENT USED

Test equipment
Type/Model Identification reference Calibration certificate Comment

SPECIAL PRECAUTIONS

Verify that the Test Personnel has fulfilled the Safety Requirements according section 4.
Completed by
Name (Print) Signature Date
Test Performer

TEST PREPARATION

Test preparation to be performed according section 8.2.

KKS of actuator: Type of actuator and speed:


KKS of valve: Type of gearbox:
N
ECCN:

Completed by
Name (Print) Signature Date
Test Performer
N
AL:

COMMENTS PERFORMED BY CHECKED BY


Date : Date :
Name : Name :
Signature : Signature :
Project OL3 N° ° FSS DC 0427
Confidentiality:
RESTRICTED REV. D Page A3 of A5

RESULT RECORD SHEET

SIEMENS Project : Olkiluoto 3 NPP


TI Pretest on the
Appendix A Valve: Pretest with URSULA
valve
TI App. System/SCP KKS Task
CONFIDENTIAL as defined under the Olkiluoto 3 Plant Contrac

TEST PROCEDURE

Test
Scope of test: see section 8.3.1 or 8.3.2 or 8.3.3 and/or 8.3.4.
For each valve the RRS is composed of this appendix and the RRS of the SCI52 NI.
In the SCI52’s RRS, only the part “Adjustment / Measurements drive” is used for this pretest. It must
be labeled with “PRE-TESTING” (stamp). See an example in Appendix C Figure 1

To be filled:

KKS valve: Movement with or without fluid:

CIRVAR: EPT type (analog position):

# Instructions according to § 8 Done

1 Measure the position of the valve before to start the test (step2)

2 Setup of the URSULA box


N

3 Basic test (to fill out SCI52’s RSS)


ECCN:

4 Setup end position CLOSED and OPEN (to fill out SCI52’s RSS)

5 Checking of setting in automatic mode


N

6 Setup the remote indication, if used (to fill out SCI52’s RSS)
AL:

7 Checking of running time (to fill out SCI52’s RSS)


Restoration, place the valve in position measured at the beginning of
8
the test
Project OL3 N° ° FSS DC 0427
Confidentiality:
RESTRICTED REV. D Page A4 of A5

RESULT RECORD SHEET

SIEMENS Project : Olkiluoto 3 NPP


TI Pretest on the
Appendix A Valve: Pretest with URSULA
valve
TI App. System/SCP KKS Task

Acceptance Criteria
CONFIDENTIAL as defined under the Olkiluoto 3 Plant Contrac

Check that criteria listed in section 2 have been met with section CHECK LIST of this RRS
The detail of test criteria could be added here.
 with comments (see section COMMENTS)

 conform (see section COMMENTS)

Measured parameter / Acceptance criteria

Characteristic Checked

In accordance with the Data


Direction of rotation
Sheet Valve
In accordance with the Data
Adjustment of limit switch
Sheet Valve
In accordance with the Data
Torque setting
Sheet Valve
Running time In accordance with the Data
Sheet Valve
Remote indication (if used) In accordance with the Data
Sheet Valve
N
ECCN:

Performed by / /
Name (Print) Signature Date
Test Performer
N
AL:

Verified by / /
Name (Print) Signature Date
Test Supervisor

TEST RESTORATION

Test restoration performed according to section 8.4.

Completed by / /
Name (Print) Signature Date
Test Performer
Project OL3 N° FSS DC 0427
Confidentiality:
RESTRICTED REV. D PAGE Page A5 of A5

RESULT RECORD SHEET

SIEMENS Project : Olkiluoto 3 NPP


TI Pretest on the
Appendix A Valve Pretest with URSULA
valve
CI App. System/SCP KKS Task

COMMENTS
CONFIDENTIAL as defined under the Olkiluoto 3 Plant Contract
N
ECCN:
N
AL:

COMMENTS PERFORMED BY CHECKED BY


Date : Date :
Name : Name :
Signature : Signature :
Project OL3 N° FSS DC 0427
Confidentiality:
RESTRICTED Page B1 of
REV. D B2
CONFIDENTIAL as defined under the Olkiluoto 3 Plant Contract

APPENDIX B: SUMMARY OF NEEDS TO PREPARE THE TEST


N
ECCN:
N
AL:
Project OL3 N° FSS DC 0427
Confidentiality:
RESTRICTED Page B2 of
REV. D B2

Information useful for the test

KKS-catalogue of valves – List of valves with technical specification


Document Number: FSF DC 0512
Information available in this document
• KKS
• Valve type
• DN
• Kind of actuator
• ValveSpec
• Document number – valve data sheet
• Batch
CONFIDENTIAL as defined under the Olkiluoto 3 Plant Contract

• Supplier
• Drawing
Note: Valves operated via black box are not listed in this document. In this case some
information can be found in the black box documentation.

Documents useful for Pre-testing with URSULA:


• Actuation Control Concept – DR 2.4.07 - [4]
• Installation Instruction for AUMA SAI actuator type – 5298 INS 012 - [5]
• Operation and Maintenance Manuals AUMA SAI – AUMA-TVO3-DOK20-SAI - [1]
• Operation and Maintenance Manuals AUMA SAN – AUMA-TVO3-DOK20-SAN - [2]
• Description of Actuator Series – General Technical Data – AUMA-TVO3-DOK1-SAN
- [2]
• Description of Actuator Series – General Technical Data – AUMA-TVO3-DOK1-SAI -
[2]
• Definition of the Valve Specification – PEEO-G/2010/en/1003 - [6]

Documents required for Pre-testing with URSULA:


• Data sheet for valves - DSV (find in FSF DC 0512)
• Actuator Technical Sheet ATS: Example SARN 07.1-32 (find in Work Package e.g.
NI-1-4915)
• Drawing of valve (find in FSF DC 0512)
• RRS with Pre-testing stamp
• Technical Instruction (URSULA manual, AUMA manuals)
N

Data required for Pre-testing with URSULA (find in DSV):


• Power supply: Example 400V VAC / 3 phases
ECCN:

• Running time
• Gear ratio
• Hand Gear ratio
• Torque switch OPEN/CLOSE
N

• CoMmanD TERMinal VARiant (see [4])


AL:

Contact :

Bastian Ruebenach Daniel Levecque


Valve Engineer Valve Team – Preparation – Person to ask at the
Office U102 / Phone : 7226 – (0)447467226 Warehouse
Office T207 / Phone : (0)44 324 1496

Thorsten Ackmann Sébastien Casset


Can help for calculation ( example : ratio…) I&C team
Office M214 / Phone : 7549 – (0)44 324 4549 Office M3-105 / Phone: 7234 - (0)44 746 7234
Project OL3 N° FSS DC 0427
Confidentiality:
RESTRICTED Page C1 of
REV. D C2

APPENDIX C: EXAMPLE OF SCI52’S RSS TO BE USED


Project OL3 N° FSS DC 0427
Confidentiality:
RESTRICTED Page C2 of
REV. D C2

Note: for this pretest, use the SCI52’s RSS of each valve and fill out only the part indicate in
the Figure 1

FIGURE 1: EXAMPLE OF SCI52’S RSS TO BE USED