You are on page 1of 1

Machinery Division (Kobe) CHECK SHEET REXAS-42525-3 (3/3)

[ Confirmation of Follow up operation ]

Ship Name AL NISR Checking Date

Item CPP Follow up Operation Type KST-200ZC/B1

1. Confirm pressure at Rexpeller room when the pitch is operated by FOLLOW UP mode with CLUTCH OFF
and M/E idle speed.

※If the pressure value is hunting, please write the range of value in the below table. (Ex. 5~7 MPa)

Result of inspection
Checking items PORT STBD

01) Check oil temperature. ℃ ℃


Check pump delivery pressure during NO PITCH
02) MPa MPa
OPERATION.
AH to AS AH to AS
AH press : MPa AH press : MPa
Check each pressure and pitch changing time
03) AS press : MPa AS press : MPa
during CPP movement. (AH max to AS max).
Pump Del : MPa Pump Del : MPa
Time : sec Time : sec
AS to AH AS to AH
AH press : MPa AH press : MPa
Check each pressure and pitch changing time
04) AS press : MPa AS press : MPa
during CPP movement. (AS max to AH max).
Pump Del : MPa Pump Del : MPa
Time : sec Time : sec